power distribution of a steel plant
TRANSCRIPT
-
8/13/2019 Power Distribution of a Steel Plant
1/72
Presented by
Alok GKeerthana A.N.
Md.Kashif hussain
Shruthi S.M.
-
8/13/2019 Power Distribution of a Steel Plant
2/72
Project overview
Maximum demand calculation
Load flow studies Short circuit studies
Protection
Relay coordination
-
8/13/2019 Power Distribution of a Steel Plant
3/72
This Project is actually the brown field expansionof a 0.6 MTPA Pellet plant to 1.8 MTPA integratedsteel plant.
Existing Facilities include the following:
25 MW power plant
70 MW power plant
2 x 1.2 MTPA beneficiation plant
2x1.2 MTPA pellet plant
4 x 500 TPD DRI Plant
A small capacity bar mill.
-
8/13/2019 Power Distribution of a Steel Plant
4/72
Expansion to 1.8 MTPA Integrated Steel Plant isplanned in two stages of 0.9 MTPA each.
The major units envisaged in Stage-I and Stage-IIare as follows:
100T EAF/LF
Oxygen Plant
Sinter Plant
Blast Furnace
Coke Oven
Bar Mill And Billet Caster
-
8/13/2019 Power Distribution of a Steel Plant
5/72
-
8/13/2019 Power Distribution of a Steel Plant
6/72
-
8/13/2019 Power Distribution of a Steel Plant
7/72
The existing plant receives power at 220 kV fromnearby switching station, located approximately 17kms away from the plant.
In addition to the grid supply, in-house generationfrom 25 MW and 70 MW CPPs also caters to the loaddemand.
Excess power generated after meeting the demand ofthe plant is exported to the Grid.
-
8/13/2019 Power Distribution of a Steel Plant
8/72
-
8/13/2019 Power Distribution of a Steel Plant
9/72
To cater to the increased demand of the power dueto expansion of the plant , an additional capacity of140 MW (2x70 MW CPPs) generation is also planned tobe set up.
For feeding the new plant units at 33 kV, a new220/33 kV Main Receiving Substation (MRSS) isplanned.
The interconnection of the existing power system,CPPs and new MRSS and CPPS is planned through anumber of interconnections considering variousfactors to ensure maximum availability andreliability.
-
8/13/2019 Power Distribution of a Steel Plant
10/72
-
8/13/2019 Power Distribution of a Steel Plant
11/72
-
8/13/2019 Power Distribution of a Steel Plant
12/72
Maximum demand calculations Transformer selection
Load flow analysis Short circuit analysis
Selection of Protective equipments Relay co-ordination
-
8/13/2019 Power Distribution of a Steel Plant
13/72
-
8/13/2019 Power Distribution of a Steel Plant
14/72
Shop/UnitProduction(Tonnes/yr)
Workingdays/year
Workinghours/year
Sp. EnergyConsumption(kW h/Tonnes)
Annu al EnergyConsumption (kWh)
Average Lo ad(MW)
Load FactorMaximum Demand (MD)
in 15 Min. (MW)
PHASE-1
RAW MATERIAL YARD To Unit
Raw Coal Coke Oven 802569 365 8760 8 6420552 0.73 0.85 0.86
Sinter Sinter Plant 1478798 350 8400 8 11830384 1.41 0.85 1.66
Lime stone Lime Plant 187186 320 7680 8 1497488 0.19 0.85 0.23
RMHS Total Load 59636718 8.56
BLAST FURNACE
GHM B.F Output 910000 350 8400 175 159250000 18.96 0.8 23.70
COKE OVEN
COKE CO Output 450000 350 8400 60 27000000 3.21 0.8 4.02
SGP
SLAG SGP 318500 365 8760 25 7962500 0.91 0.8 1.14
EAF/LF
EAF/LF Auxil laries EAF/LF 1100000 320 7680 50 550000 00 7.16 0.9 7.96
PIG CASTING MACHINE
-
8/13/2019 Power Distribution of a Steel Plant
15/72
Step-1Calculation of Annual Energy Consumption
Step-2Calculation of Average Load of each unit
Step-3 Calculation of individual maximum demand of each unit
Step-4calculation of total maximum demand
Step-5calculation of simultaneous maximum demand considering 3% losses
Step-6calculation of total maximum demand considering 5% contingency
Step-7 calculation of total energy requirements per annum
-
8/13/2019 Power Distribution of a Steel Plant
16/72
Sum of Individual Maximum Demand (considering 3% losses) =83.45MW
Max. Demand (MD) (considering diversity factor of 1.25) = 66.76MW
Max. Demand (MD) (considering 5% contingency requirement) =3.34 MW
Total load demand =70.10MW
Total EAF demand=106.0MW
Total Energy consumption per annum (considering 3% losses) = 18089046.94kWh
Total Energy requirement per annum = 621.06MkWh
-
8/13/2019 Power Distribution of a Steel Plant
17/72
Transformer selected will have the rating twicethe calculated MVA for each load.
For 70 MW plant loads, transformer selected is,63/80 MVA
For 106 MW EAF load, transformer selected is,
130/160 MVA
-
8/13/2019 Power Distribution of a Steel Plant
18/72
Load flow studies are carried out to determine thepower flow in the system.
Load flow studies helps in planning the operation of
power system under existing conditions, itsimprovements and future expansion.
The study also helps to identify
Overloading of transmission lines Voltage limit violations at the buses
-
8/13/2019 Power Distribution of a Steel Plant
19/72
Case-1: Grid and 25MW CPP feeding existing loads
Case-2: Grid and 95MW (1x25 & 1x70) CPPs feeding existingloads
Case-3:Grid and 95MW (1x25 & 1x70) CPPs feeding existingloads and phase-1 loads.
Case-4:Grid and 165MW (1x25 & 2x70) CPPs feeding existingloads, phase-1 and phase-2 loads.
Case-5: Grid and 235MW (1x25 & 3x70) CPPs feeding existingloads, phase-1 and phase-2 loads.
-
8/13/2019 Power Distribution of a Steel Plant
20/72
-
8/13/2019 Power Distribution of a Steel Plant
21/72
DESCRIPTION GENERATION GRID 25MWCPP
70 MWCPP-1
70 MWCPP-2
70 MWCPP-3
LOAD
CASE-1 MW 35.41 25 0 0 0 60.05
MVAR 14.09 20.30 0 0 0 37.22
-
8/13/2019 Power Distribution of a Steel Plant
22/72
! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 0^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 1& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 6
* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 1
FROM
NODE FROMNAME TONODE TONAMEFORWARD LOSS %
LOADIN
GMW MVAR MW MVAR1 Bus1 2 Bus2 27.866 21.65 0.1313 0.0912 27.6 ^4 Bus4 3 Bus3 -21.915 -12.477 0.0283 -0.0417 3.2 &2 Bus2 5 Bus5 12.845 7.952 0.0243 -0.006 11.9 &2 Bus2 6 Bus6 14.008 8.676 0.0289 -0.0018 12.9 &7 Bus7 8 Bus8 35.443 15.98 0.0482 -2.5716 17.8 &12 Bus12 8 Bus8 LINE IS OPEN8 Bus8 14 Bus14 0 -0.028 0 -0.0282 0.0 *12 Bus12 14 Bus14 LINE IS OPEN1 Bus1 19 Bus19 -4.661 -1.371 0.0025 -0.0262 3.8 &20 Bus20 2 Bus2 2.32 1.194 0.0007 -0.0275 2.1 &
-
8/13/2019 Power Distribution of a Steel Plant
23/72
-
8/13/2019 Power Distribution of a Steel Plant
24/72
DESCRIPTION GENERATION GRID 25MWCPP 70 MWCPP-1 70 MWCPP-2 70 MWCPP-3 LOAD
CASE-2 MW (-) 34.42 25 70 0 0 60.05
MVAR 3.99 6.47 25.85 0 0 37.22
-
8/13/2019 Power Distribution of a Steel Plant
25/72
! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 0^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 1& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 6* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 1
FROM
NODEFROM
NAMETO
NODETO
NAME
FORWARD LOSS%
LOADINGMW MVAR MW MVAR
1 Bus1 2 Bus2 34.476 13.555 0.1446 0.1034 28.9 ^4 Bus4 3 Bus3 34.75 -1.559 0.051 -0.0247 4.3 &2 Bus2 5 Bus5 12.85 7.952 0.0243 -0.006 11.9 &2 Bus2 6 Bus6 14.012 8.675 0.0289 -0.0018 12.9 &7 Bus7 8 Bus8 -34.39 6.838 0.0387 -2.6328 15.9 &12 Bus12 8 Bus8 LINE IS OPEN8 Bus8 14 Bus14 0 -0.028 0 -0.0284 0.0 *12 Bus12 14 Bus14 LINE IS OPEN1 Bus1 19 Bus19 -11.245 -8.123 0.0203 -0.0101 10.8 &20 Bus20 2 Bus2 8.924 7.5 0.0144 -0.0151 9.1 &
-
8/13/2019 Power Distribution of a Steel Plant
26/72
LOAD FLOW ANALYSIS-CASE 3
-
8/13/2019 Power Distribution of a Steel Plant
27/72
DESCRIPTION GENERATION GRID 25MWCPP
70 MWCPP-1
70 MWCPP-2
70 MWCPP-3
LOAD
CASE-3 MW (-)163.54 25 70 70 70 69.85
MVAR 19.90 6.31 25.35 2.50 2.5 43.3
-
8/13/2019 Power Distribution of a Steel Plant
28/72
! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 2^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 1& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 5* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 0
FROMNODE
FROMNAME
TONODE
TONAME
FORWARD LOSS %LOADING
MW MVAR MW MVAR
1 Bus1 2 Bus2 34.47 13.339 0.144 0.1028 28.9^
4 Bus4 3 Bus3 34.754 -2.266 0.0511 -0.0246 4.4&
2 Bus2 5 Bus5 12.85 7.952 0.0243 -0.006 11.9&
2 Bus2 6 Bus6 14.013 8.675 0.0289 -0.0018 12.9&
7 Bus7 8 Bus8 -163.08 26.426 0.8468 1.6732 73.7$
12 Bus12 8 Bus8 129.549 -14.312 0.0524 -0.0049 57.9$
8 Bus8 14 Bus14 LINE IS OPEN
12 Bus12 14 Bus14 LINE IS OPEN
1 Bus1 19 Bus19 -11.24 -8.124 0.0202 -0.0101 10.8&
20 Bus20 2 Bus2 8.924 7.494 0.0144 -0.0151 9.1&
-
8/13/2019 Power Distribution of a Steel Plant
29/72
-
8/13/2019 Power Distribution of a Steel Plant
30/72
DESCRIPTION GENERATION GRID 25MWCPP
70 MWCPP-1
70 MWCPP-2
70 MWCPP-3
LOAD
CASE-5 MW 77.91 25 70 70 0 240.95MVAR 74.38 9.45 35.60 13.60 0 107.185
-
8/13/2019 Power Distribution of a Steel Plant
31/72
! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 1^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 2& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 7
* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 0
FROMNODE FROMNAME TONODE TONAME FORWARD LOSS %LOADING
MW MVAR MW MVAR1 Bus1 2 Bus2 34.545 16.371 0.154 0.112 29.9^4 Bus4 3 Bus3 34.67 7.673 0.0532 -0.0227 4.4&2 Bus2 5 Bus5 12.848 7.952 0.0243 -0.006 11.9&2 Bus2 6 Bus6 14.011 8.675 0.0289 -0.0018 12.9&7 Bus7 8 Bus8 77.909 74.381 0.3656 -0.8488 48.8^12
Bus12
8
Bus8
25.511
-2.3
0.0021
-0.2645
11.6&
8 Bus8 14 Bus14 137.478 75.849 0.0079 0.0144 70.9$12 Bus12 14 Bus14 39.256 5.293 0.005 -0.2489 17.9&1 Bus1 19 Bus19 -11.32 -8.113 0.0204 -0.0099 10.9&20 Bus20 2 Bus2 8.917 7.565 0.0145 -0.015 9.2&
-
8/13/2019 Power Distribution of a Steel Plant
32/72
-
8/13/2019 Power Distribution of a Steel Plant
33/72
DESCRIPTION GENERATION GRID 25MWCPP
70 MWCPP-1
70 MWCPP-2
70 MWCPP-3
LOAD
CASE-4 MW 12.97 25 70 70 70 245.85MVAR 74.59 8.97 34.02 34.02 34.02 110.22
-
8/13/2019 Power Distribution of a Steel Plant
34/72
! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 1^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 4& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 5
* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 0
FROMNODE
FROMNAME
TONODE
TONAME
FORWARD LOSS %LOADING
MW MVAR MW MVAR
1 Bus1 2 Bus2 34.536 16 0.1527 0.1107 29.7^
4 Bus4 3 Bus3 34.679 6.458 0.0525 -0.0233 4.4&
2 Bus2 5 Bus5 12.848 7.952 0.0243 -0.006 11.9&
2 Bus2 6 Bus6 14.011 8.675 0.0289 -0.0018 12.9&
7 Bus7 8 Bus8 12.967 74.59 0.184 -1.8226 34.9^
12 Bus12 8 Bus8 59.441 -2.078 0.0112 -0.2169 26.8^
8 Bus8 14 Bus14 106.64 75.626 0.0054 0.0013 58.9$
12 Bus12 14 Bus14 70.099 5.498 0.0157 -0.193 31.7^
1 Bus1 19 Bus19 -11.31 -8.115 0.0204 -0.01 10.9&
20 Bus20 2 Bus2 8.918 7.557 0.0145 -0.015 9.2&
-
8/13/2019 Power Distribution of a Steel Plant
35/72
Losses in the system are calculated.
No buses or Lines are getting overloaded.
No need for additional generation andinductive VAR support or placement ofcapacitors to maintain system voltages
within specified limits is found.
-
8/13/2019 Power Distribution of a Steel Plant
36/72
Short circuit calculations provide currents andvoltages on a power system during faultconditions.
Short circuit study calculates the maximumavailable short circuit current at various pointsthroughout the system and the calculatedvalues are then used to evaluate the
application of protective devices, and todevelop circuit breaker trip settings.
-
8/13/2019 Power Distribution of a Steel Plant
37/72
Case-1: Grid and 25MW CPP & 70 MW CPP
Case-2: with grid and all CPP sources (1x25 & 3x70MW)
-
8/13/2019 Power Distribution of a Steel Plant
38/72
-
8/13/2019 Power Distribution of a Steel Plant
39/72
BUS NUMBER BUS VOLTAGE MVA LEVEL
FAULT CURRENT
(kA)
Bus1 11 587.1 30.815
Bus2 11 591.4 31.04
Bus3 11 1013.5 53.197
Bus4 11 1011.7 53.1Bus5 11 556.7 29.219
Bus6 11 556.7 29.219
Bus7 220 7267.9 19.074
Bus8 220 3510.1 9.212Bus19 11 572.2 30.032
Bus20 11 575.1 30.188
-
8/13/2019 Power Distribution of a Steel Plant
40/72
-
8/13/2019 Power Distribution of a Steel Plant
41/72
41
-
8/13/2019 Power Distribution of a Steel Plant
42/72
BUS NUMBER BUS VOLTAGE MVA LEVEL FAULT CURRENT(kA)
Bus1 11 591.8 31.064
Bus2 11 596.3 31.297
Bus3 11 1028.1 53.961
Bus4 11 1025.8 53.844
Bus5 11 561 29.447
Bus6 11 561 29.447
Bus7 220 7641 20.053
Bus8 220 3946.1 10.356
Bus9 11 882.2 46.307
Bus10 11 882.2 46.307
Bus12 220 3842.9 10.085
Bus14 220 3924.2 10.299
Bus15 33 537.4 9.402Bus16 33 537.4 9.402
Bus17 33 965.4 16.89
Bus19 11 576.7 30.269
Bus20 11 579.8 30.432
-
8/13/2019 Power Distribution of a Steel Plant
43/72
-
8/13/2019 Power Distribution of a Steel Plant
44/72
Short circuit studies provide post fault busvoltages at different buses in the network fora fault at any location in the network.
These results are typically given as faultMVA.
Short circuit studies for minimum fault levelcondition is of interest in relay coordination
to check whether relays can distinguishbetween the Maximum Load Currents andMinimum Fault Currents.
-
8/13/2019 Power Distribution of a Steel Plant
45/72
The purpose of an electrical power system is togenerate and supply electrical energy to consumers.The system should be designed and managed to deliverenergy to the utilisation points with both reliability and
economy.Protection should be done to prevent the following:
Prevent any disruption of supply
Electrical equipment used is very expensive and weshould prevent any damage to the equipment
Power system should operate in a safe manner atall times
Fault may represent a risk to life and property
-
8/13/2019 Power Distribution of a Steel Plant
46/72
Maximum protection
Minimum equipment cost
Reliable protection
High-speed operation Simple designs
High sensitivity to faults
Insensitivity to normal load currents
Selectivity in isolating a minimum portion ofthe system
-
8/13/2019 Power Distribution of a Steel Plant
47/72
-
8/13/2019 Power Distribution of a Steel Plant
48/72
-
8/13/2019 Power Distribution of a Steel Plant
49/72
For attaining higher reliability, quick action and
improvements in operating flexibility of the protection
schemes, separate elements of a power system , in addition
to main or primary protection , are provided with a back-up
and auxiliary protection.
ProtectionZone B
ProtectionZone A
To Zone BRelays
To Zone ARelays
-
8/13/2019 Power Distribution of a Steel Plant
50/72
Short-circuit protection includes two protection systems: primaryand backup protection. Primary protection is the first line ofdefense.
Back up protection gives back up to the main protection, whenthe main protection fails to operate or is cut out for repairs etc.
-
8/13/2019 Power Distribution of a Steel Plant
51/72
-
8/13/2019 Power Distribution of a Steel Plant
52/72
-
8/13/2019 Power Distribution of a Steel Plant
53/72
-
8/13/2019 Power Distribution of a Steel Plant
54/72
-
8/13/2019 Power Distribution of a Steel Plant
55/72
PROTECTION EQUIPMENT AND DEVICES
Relays
Current Transformers CTs
Voltage Transformers VTs or PTs
Circuit Breakers CBs etc.
-
8/13/2019 Power Distribution of a Steel Plant
56/72
Protection function can be classified asfollows:
Back up protection
(Over current and Earth Fault) Power transformer protection
(Unit or Differential Protection)
Distance protection
Differential protection Busbar protection, etc.
-
8/13/2019 Power Distribution of a Steel Plant
57/72
Application
The most commonly used protective relays arethe instantaneous overcurrent relays. They areused as both primary and backup protective
devices and are applied in every protective zonein the system.
-
8/13/2019 Power Distribution of a Steel Plant
58/72
Restricted earth faultprotection is provided inelectrical powertransformer for sensinginternal earth fault of thetransformer
-
8/13/2019 Power Distribution of a Steel Plant
59/72
FaultLoad
Radial Line
The current decreases as the distance increases,This indicates that the operation time of the relaywill be larger as the current is farther from thesource. This is one of theadvantages of inverse-type overcurrent relays.
RELAYOPERATIONTIME
Current (A)
Time (s)
-
8/13/2019 Power Distribution of a Steel Plant
60/72
Distance protection uses current and voltageinformation to make a direct, or indirect,estimate of the distance to the fault.
Application
Distance relays are widely used for primary andbackup protection on transmission lines wherehigh-speed relaying is desired.
Other applications include generator backup
protection for faults on the system and startup oflarge motors with high inertia.
-
8/13/2019 Power Distribution of a Steel Plant
61/72
Application
Synchronism check relays are applied when twoor more sources of power are to be connected toa common bus.
-
8/13/2019 Power Distribution of a Steel Plant
62/72
K
L
The arrows shown in the figure areused to represent the protection
tripping direction. Note that therelays are oriented towards theprotected lines. This orientationdivides the system protection intotwo independent groups: the relayslooking to the right and those
looking to the left. Thedirectionality divides thecoordination process into twoindependent processes. A relay onlyneeds to be coordinated with theother relays in its group.
-
8/13/2019 Power Distribution of a Steel Plant
63/72
Application
Directional overcurrent relays are used toprovide sensitive tripping for fault currents inone(tripping) direction and not trip for load or
fault currents in the reverse (normal) direction.
-
8/13/2019 Power Distribution of a Steel Plant
64/72
ExternalFault
IDIF = 0
CT CT
50
Balanced CT Ratio
ProtectedEquipment
If the primary andsecondary currentsat both sides of the
protected
equipment areequal. There willbe no difference,and the relay will
not operate.
-
8/13/2019 Power Distribution of a Steel Plant
65/72
InternalFault
IDIF
> ISETTING
CTR CTR
50
Relay Operates
Protected
Equipment
For an internalfault, the
secondary currents
are 180 out ofphase and produce
a differentialcurrent through theovercurrent relay.If this differentialcurrent is larger
than the pickup forthe relay, the relay
will trip bothcircuit breakersinstantaneously.
-
8/13/2019 Power Distribution of a Steel Plant
66/72
Bus protection
Transformer protection
Generator protection
Line protection Large motor protection
Reactor protection
Capacitor bank protection
Compound equipment protection
-
8/13/2019 Power Distribution of a Steel Plant
67/72
The basic idea of coordination is that thebackup relay should be slower than theprimary relay, with a minimum separation ofTbetween curves calculated as follows:
tbackup= tprimary+ T
-
8/13/2019 Power Distribution of a Steel Plant
68/72
Distance
Distance
t
I
} } }T T T
-
8/13/2019 Power Distribution of a Steel Plant
69/72
For relay R1,CT chosen =1600/1AMaximum fault current(I) = 10.297kACurrent setting(IS)=130% of 1600A =2080A
For t=0.15s, TMS=0.035
-
8/13/2019 Power Distribution of a Steel Plant
70/72
-
8/13/2019 Power Distribution of a Steel Plant
71/72
By performing various system studies using MiPower, the following thingswere concluded:
From the results of Load flow analysis it is verified that:
No bus or transmission line is getting overloaded.
Real and Reactive power requirement or excess under variousoperating conditions is found.
Loading of transformers is verified.
From the results of Short circuit analysis following observations aremade:
Required rating of equipments and Interrupting capacities ofbreakers is found.
No requirement for change in the existing system on account ofexpansion and capacity addition was found.
Short circuit levels obtained at various buses is used as input forrelay coordination.
From the results of Relay Coordination following observations aremade:
Settings for over current relays at various feeders were given andcoordination between them was verified.
-
8/13/2019 Power Distribution of a Steel Plant
72/72
THANK YOU