power distribution of a steel plant

Upload: kashif-hussain-razwi

Post on 04-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Power Distribution of a Steel Plant

    1/72

    Presented by

    Alok GKeerthana A.N.

    Md.Kashif hussain

    Shruthi S.M.

  • 8/13/2019 Power Distribution of a Steel Plant

    2/72

    Project overview

    Maximum demand calculation

    Load flow studies Short circuit studies

    Protection

    Relay coordination

  • 8/13/2019 Power Distribution of a Steel Plant

    3/72

    This Project is actually the brown field expansionof a 0.6 MTPA Pellet plant to 1.8 MTPA integratedsteel plant.

    Existing Facilities include the following:

    25 MW power plant

    70 MW power plant

    2 x 1.2 MTPA beneficiation plant

    2x1.2 MTPA pellet plant

    4 x 500 TPD DRI Plant

    A small capacity bar mill.

  • 8/13/2019 Power Distribution of a Steel Plant

    4/72

    Expansion to 1.8 MTPA Integrated Steel Plant isplanned in two stages of 0.9 MTPA each.

    The major units envisaged in Stage-I and Stage-IIare as follows:

    100T EAF/LF

    Oxygen Plant

    Sinter Plant

    Blast Furnace

    Coke Oven

    Bar Mill And Billet Caster

  • 8/13/2019 Power Distribution of a Steel Plant

    5/72

  • 8/13/2019 Power Distribution of a Steel Plant

    6/72

  • 8/13/2019 Power Distribution of a Steel Plant

    7/72

    The existing plant receives power at 220 kV fromnearby switching station, located approximately 17kms away from the plant.

    In addition to the grid supply, in-house generationfrom 25 MW and 70 MW CPPs also caters to the loaddemand.

    Excess power generated after meeting the demand ofthe plant is exported to the Grid.

  • 8/13/2019 Power Distribution of a Steel Plant

    8/72

  • 8/13/2019 Power Distribution of a Steel Plant

    9/72

    To cater to the increased demand of the power dueto expansion of the plant , an additional capacity of140 MW (2x70 MW CPPs) generation is also planned tobe set up.

    For feeding the new plant units at 33 kV, a new220/33 kV Main Receiving Substation (MRSS) isplanned.

    The interconnection of the existing power system,CPPs and new MRSS and CPPS is planned through anumber of interconnections considering variousfactors to ensure maximum availability andreliability.

  • 8/13/2019 Power Distribution of a Steel Plant

    10/72

  • 8/13/2019 Power Distribution of a Steel Plant

    11/72

  • 8/13/2019 Power Distribution of a Steel Plant

    12/72

    Maximum demand calculations Transformer selection

    Load flow analysis Short circuit analysis

    Selection of Protective equipments Relay co-ordination

  • 8/13/2019 Power Distribution of a Steel Plant

    13/72

  • 8/13/2019 Power Distribution of a Steel Plant

    14/72

    Shop/UnitProduction(Tonnes/yr)

    Workingdays/year

    Workinghours/year

    Sp. EnergyConsumption(kW h/Tonnes)

    Annu al EnergyConsumption (kWh)

    Average Lo ad(MW)

    Load FactorMaximum Demand (MD)

    in 15 Min. (MW)

    PHASE-1

    RAW MATERIAL YARD To Unit

    Raw Coal Coke Oven 802569 365 8760 8 6420552 0.73 0.85 0.86

    Sinter Sinter Plant 1478798 350 8400 8 11830384 1.41 0.85 1.66

    Lime stone Lime Plant 187186 320 7680 8 1497488 0.19 0.85 0.23

    RMHS Total Load 59636718 8.56

    BLAST FURNACE

    GHM B.F Output 910000 350 8400 175 159250000 18.96 0.8 23.70

    COKE OVEN

    COKE CO Output 450000 350 8400 60 27000000 3.21 0.8 4.02

    SGP

    SLAG SGP 318500 365 8760 25 7962500 0.91 0.8 1.14

    EAF/LF

    EAF/LF Auxil laries EAF/LF 1100000 320 7680 50 550000 00 7.16 0.9 7.96

    PIG CASTING MACHINE

  • 8/13/2019 Power Distribution of a Steel Plant

    15/72

    Step-1Calculation of Annual Energy Consumption

    Step-2Calculation of Average Load of each unit

    Step-3 Calculation of individual maximum demand of each unit

    Step-4calculation of total maximum demand

    Step-5calculation of simultaneous maximum demand considering 3% losses

    Step-6calculation of total maximum demand considering 5% contingency

    Step-7 calculation of total energy requirements per annum

  • 8/13/2019 Power Distribution of a Steel Plant

    16/72

    Sum of Individual Maximum Demand (considering 3% losses) =83.45MW

    Max. Demand (MD) (considering diversity factor of 1.25) = 66.76MW

    Max. Demand (MD) (considering 5% contingency requirement) =3.34 MW

    Total load demand =70.10MW

    Total EAF demand=106.0MW

    Total Energy consumption per annum (considering 3% losses) = 18089046.94kWh

    Total Energy requirement per annum = 621.06MkWh

  • 8/13/2019 Power Distribution of a Steel Plant

    17/72

    Transformer selected will have the rating twicethe calculated MVA for each load.

    For 70 MW plant loads, transformer selected is,63/80 MVA

    For 106 MW EAF load, transformer selected is,

    130/160 MVA

  • 8/13/2019 Power Distribution of a Steel Plant

    18/72

    Load flow studies are carried out to determine thepower flow in the system.

    Load flow studies helps in planning the operation of

    power system under existing conditions, itsimprovements and future expansion.

    The study also helps to identify

    Overloading of transmission lines Voltage limit violations at the buses

  • 8/13/2019 Power Distribution of a Steel Plant

    19/72

    Case-1: Grid and 25MW CPP feeding existing loads

    Case-2: Grid and 95MW (1x25 & 1x70) CPPs feeding existingloads

    Case-3:Grid and 95MW (1x25 & 1x70) CPPs feeding existingloads and phase-1 loads.

    Case-4:Grid and 165MW (1x25 & 2x70) CPPs feeding existingloads, phase-1 and phase-2 loads.

    Case-5: Grid and 235MW (1x25 & 3x70) CPPs feeding existingloads, phase-1 and phase-2 loads.

  • 8/13/2019 Power Distribution of a Steel Plant

    20/72

  • 8/13/2019 Power Distribution of a Steel Plant

    21/72

    DESCRIPTION GENERATION GRID 25MWCPP

    70 MWCPP-1

    70 MWCPP-2

    70 MWCPP-3

    LOAD

    CASE-1 MW 35.41 25 0 0 0 60.05

    MVAR 14.09 20.30 0 0 0 37.22

  • 8/13/2019 Power Distribution of a Steel Plant

    22/72

    ! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 0^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 1& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 6

    * NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 1

    FROM

    NODE FROMNAME TONODE TONAMEFORWARD LOSS %

    LOADIN

    GMW MVAR MW MVAR1 Bus1 2 Bus2 27.866 21.65 0.1313 0.0912 27.6 ^4 Bus4 3 Bus3 -21.915 -12.477 0.0283 -0.0417 3.2 &2 Bus2 5 Bus5 12.845 7.952 0.0243 -0.006 11.9 &2 Bus2 6 Bus6 14.008 8.676 0.0289 -0.0018 12.9 &7 Bus7 8 Bus8 35.443 15.98 0.0482 -2.5716 17.8 &12 Bus12 8 Bus8 LINE IS OPEN8 Bus8 14 Bus14 0 -0.028 0 -0.0282 0.0 *12 Bus12 14 Bus14 LINE IS OPEN1 Bus1 19 Bus19 -4.661 -1.371 0.0025 -0.0262 3.8 &20 Bus20 2 Bus2 2.32 1.194 0.0007 -0.0275 2.1 &

  • 8/13/2019 Power Distribution of a Steel Plant

    23/72

  • 8/13/2019 Power Distribution of a Steel Plant

    24/72

    DESCRIPTION GENERATION GRID 25MWCPP 70 MWCPP-1 70 MWCPP-2 70 MWCPP-3 LOAD

    CASE-2 MW (-) 34.42 25 70 0 0 60.05

    MVAR 3.99 6.47 25.85 0 0 37.22

  • 8/13/2019 Power Distribution of a Steel Plant

    25/72

    ! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 0^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 1& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 6* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 1

    FROM

    NODEFROM

    NAMETO

    NODETO

    NAME

    FORWARD LOSS%

    LOADINGMW MVAR MW MVAR

    1 Bus1 2 Bus2 34.476 13.555 0.1446 0.1034 28.9 ^4 Bus4 3 Bus3 34.75 -1.559 0.051 -0.0247 4.3 &2 Bus2 5 Bus5 12.85 7.952 0.0243 -0.006 11.9 &2 Bus2 6 Bus6 14.012 8.675 0.0289 -0.0018 12.9 &7 Bus7 8 Bus8 -34.39 6.838 0.0387 -2.6328 15.9 &12 Bus12 8 Bus8 LINE IS OPEN8 Bus8 14 Bus14 0 -0.028 0 -0.0284 0.0 *12 Bus12 14 Bus14 LINE IS OPEN1 Bus1 19 Bus19 -11.245 -8.123 0.0203 -0.0101 10.8 &20 Bus20 2 Bus2 8.924 7.5 0.0144 -0.0151 9.1 &

  • 8/13/2019 Power Distribution of a Steel Plant

    26/72

    LOAD FLOW ANALYSIS-CASE 3

  • 8/13/2019 Power Distribution of a Steel Plant

    27/72

    DESCRIPTION GENERATION GRID 25MWCPP

    70 MWCPP-1

    70 MWCPP-2

    70 MWCPP-3

    LOAD

    CASE-3 MW (-)163.54 25 70 70 70 69.85

    MVAR 19.90 6.31 25.35 2.50 2.5 43.3

  • 8/13/2019 Power Distribution of a Steel Plant

    28/72

    ! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 2^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 1& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 5* NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 0

    FROMNODE

    FROMNAME

    TONODE

    TONAME

    FORWARD LOSS %LOADING

    MW MVAR MW MVAR

    1 Bus1 2 Bus2 34.47 13.339 0.144 0.1028 28.9^

    4 Bus4 3 Bus3 34.754 -2.266 0.0511 -0.0246 4.4&

    2 Bus2 5 Bus5 12.85 7.952 0.0243 -0.006 11.9&

    2 Bus2 6 Bus6 14.013 8.675 0.0289 -0.0018 12.9&

    7 Bus7 8 Bus8 -163.08 26.426 0.8468 1.6732 73.7$

    12 Bus12 8 Bus8 129.549 -14.312 0.0524 -0.0049 57.9$

    8 Bus8 14 Bus14 LINE IS OPEN

    12 Bus12 14 Bus14 LINE IS OPEN

    1 Bus1 19 Bus19 -11.24 -8.124 0.0202 -0.0101 10.8&

    20 Bus20 2 Bus2 8.924 7.494 0.0144 -0.0151 9.1&

  • 8/13/2019 Power Distribution of a Steel Plant

    29/72

  • 8/13/2019 Power Distribution of a Steel Plant

    30/72

    DESCRIPTION GENERATION GRID 25MWCPP

    70 MWCPP-1

    70 MWCPP-2

    70 MWCPP-3

    LOAD

    CASE-5 MW 77.91 25 70 70 0 240.95MVAR 74.38 9.45 35.60 13.60 0 107.185

  • 8/13/2019 Power Distribution of a Steel Plant

    31/72

    ! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 1^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 2& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 7

    * NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 0

    FROMNODE FROMNAME TONODE TONAME FORWARD LOSS %LOADING

    MW MVAR MW MVAR1 Bus1 2 Bus2 34.545 16.371 0.154 0.112 29.9^4 Bus4 3 Bus3 34.67 7.673 0.0532 -0.0227 4.4&2 Bus2 5 Bus5 12.848 7.952 0.0243 -0.006 11.9&2 Bus2 6 Bus6 14.011 8.675 0.0289 -0.0018 12.9&7 Bus7 8 Bus8 77.909 74.381 0.3656 -0.8488 48.8^12

    Bus12

    8

    Bus8

    25.511

    -2.3

    0.0021

    -0.2645

    11.6&

    8 Bus8 14 Bus14 137.478 75.849 0.0079 0.0144 70.9$12 Bus12 14 Bus14 39.256 5.293 0.005 -0.2489 17.9&1 Bus1 19 Bus19 -11.32 -8.113 0.0204 -0.0099 10.9&20 Bus20 2 Bus2 8.917 7.565 0.0145 -0.015 9.2&

  • 8/13/2019 Power Distribution of a Steel Plant

    32/72

  • 8/13/2019 Power Distribution of a Steel Plant

    33/72

    DESCRIPTION GENERATION GRID 25MWCPP

    70 MWCPP-1

    70 MWCPP-2

    70 MWCPP-3

    LOAD

    CASE-4 MW 12.97 25 70 70 70 245.85MVAR 74.59 8.97 34.02 34.02 34.02 110.22

  • 8/13/2019 Power Distribution of a Steel Plant

    34/72

    ! NUMBER OF LINES LOADED BEYOND 125%: 0@ NUMBER OF LINES LOADED BETWEEN 100% AND 125%: 0# NUMBER OF LINES LOADED BETWEEN 75% AND 100%: 0$ NUMBER OF LINES LOADED BETWEEN 50% AND 75%: 1^ NUMBER OF LINES LOADED BETWEEN 25% AND 50%: 4& NUMBER OF LINES LOADED BETWEEN 1% AND 25%: 5

    * NUMBER OF LINES LOADED BETWEEN 0% AND 1%: 0

    FROMNODE

    FROMNAME

    TONODE

    TONAME

    FORWARD LOSS %LOADING

    MW MVAR MW MVAR

    1 Bus1 2 Bus2 34.536 16 0.1527 0.1107 29.7^

    4 Bus4 3 Bus3 34.679 6.458 0.0525 -0.0233 4.4&

    2 Bus2 5 Bus5 12.848 7.952 0.0243 -0.006 11.9&

    2 Bus2 6 Bus6 14.011 8.675 0.0289 -0.0018 12.9&

    7 Bus7 8 Bus8 12.967 74.59 0.184 -1.8226 34.9^

    12 Bus12 8 Bus8 59.441 -2.078 0.0112 -0.2169 26.8^

    8 Bus8 14 Bus14 106.64 75.626 0.0054 0.0013 58.9$

    12 Bus12 14 Bus14 70.099 5.498 0.0157 -0.193 31.7^

    1 Bus1 19 Bus19 -11.31 -8.115 0.0204 -0.01 10.9&

    20 Bus20 2 Bus2 8.918 7.557 0.0145 -0.015 9.2&

  • 8/13/2019 Power Distribution of a Steel Plant

    35/72

    Losses in the system are calculated.

    No buses or Lines are getting overloaded.

    No need for additional generation andinductive VAR support or placement ofcapacitors to maintain system voltages

    within specified limits is found.

  • 8/13/2019 Power Distribution of a Steel Plant

    36/72

    Short circuit calculations provide currents andvoltages on a power system during faultconditions.

    Short circuit study calculates the maximumavailable short circuit current at various pointsthroughout the system and the calculatedvalues are then used to evaluate the

    application of protective devices, and todevelop circuit breaker trip settings.

  • 8/13/2019 Power Distribution of a Steel Plant

    37/72

    Case-1: Grid and 25MW CPP & 70 MW CPP

    Case-2: with grid and all CPP sources (1x25 & 3x70MW)

  • 8/13/2019 Power Distribution of a Steel Plant

    38/72

  • 8/13/2019 Power Distribution of a Steel Plant

    39/72

    BUS NUMBER BUS VOLTAGE MVA LEVEL

    FAULT CURRENT

    (kA)

    Bus1 11 587.1 30.815

    Bus2 11 591.4 31.04

    Bus3 11 1013.5 53.197

    Bus4 11 1011.7 53.1Bus5 11 556.7 29.219

    Bus6 11 556.7 29.219

    Bus7 220 7267.9 19.074

    Bus8 220 3510.1 9.212Bus19 11 572.2 30.032

    Bus20 11 575.1 30.188

  • 8/13/2019 Power Distribution of a Steel Plant

    40/72

  • 8/13/2019 Power Distribution of a Steel Plant

    41/72

    41

  • 8/13/2019 Power Distribution of a Steel Plant

    42/72

    BUS NUMBER BUS VOLTAGE MVA LEVEL FAULT CURRENT(kA)

    Bus1 11 591.8 31.064

    Bus2 11 596.3 31.297

    Bus3 11 1028.1 53.961

    Bus4 11 1025.8 53.844

    Bus5 11 561 29.447

    Bus6 11 561 29.447

    Bus7 220 7641 20.053

    Bus8 220 3946.1 10.356

    Bus9 11 882.2 46.307

    Bus10 11 882.2 46.307

    Bus12 220 3842.9 10.085

    Bus14 220 3924.2 10.299

    Bus15 33 537.4 9.402Bus16 33 537.4 9.402

    Bus17 33 965.4 16.89

    Bus19 11 576.7 30.269

    Bus20 11 579.8 30.432

  • 8/13/2019 Power Distribution of a Steel Plant

    43/72

  • 8/13/2019 Power Distribution of a Steel Plant

    44/72

    Short circuit studies provide post fault busvoltages at different buses in the network fora fault at any location in the network.

    These results are typically given as faultMVA.

    Short circuit studies for minimum fault levelcondition is of interest in relay coordination

    to check whether relays can distinguishbetween the Maximum Load Currents andMinimum Fault Currents.

  • 8/13/2019 Power Distribution of a Steel Plant

    45/72

    The purpose of an electrical power system is togenerate and supply electrical energy to consumers.The system should be designed and managed to deliverenergy to the utilisation points with both reliability and

    economy.Protection should be done to prevent the following:

    Prevent any disruption of supply

    Electrical equipment used is very expensive and weshould prevent any damage to the equipment

    Power system should operate in a safe manner atall times

    Fault may represent a risk to life and property

  • 8/13/2019 Power Distribution of a Steel Plant

    46/72

    Maximum protection

    Minimum equipment cost

    Reliable protection

    High-speed operation Simple designs

    High sensitivity to faults

    Insensitivity to normal load currents

    Selectivity in isolating a minimum portion ofthe system

  • 8/13/2019 Power Distribution of a Steel Plant

    47/72

  • 8/13/2019 Power Distribution of a Steel Plant

    48/72

  • 8/13/2019 Power Distribution of a Steel Plant

    49/72

    For attaining higher reliability, quick action and

    improvements in operating flexibility of the protection

    schemes, separate elements of a power system , in addition

    to main or primary protection , are provided with a back-up

    and auxiliary protection.

    ProtectionZone B

    ProtectionZone A

    To Zone BRelays

    To Zone ARelays

  • 8/13/2019 Power Distribution of a Steel Plant

    50/72

    Short-circuit protection includes two protection systems: primaryand backup protection. Primary protection is the first line ofdefense.

    Back up protection gives back up to the main protection, whenthe main protection fails to operate or is cut out for repairs etc.

  • 8/13/2019 Power Distribution of a Steel Plant

    51/72

  • 8/13/2019 Power Distribution of a Steel Plant

    52/72

  • 8/13/2019 Power Distribution of a Steel Plant

    53/72

  • 8/13/2019 Power Distribution of a Steel Plant

    54/72

  • 8/13/2019 Power Distribution of a Steel Plant

    55/72

    PROTECTION EQUIPMENT AND DEVICES

    Relays

    Current Transformers CTs

    Voltage Transformers VTs or PTs

    Circuit Breakers CBs etc.

  • 8/13/2019 Power Distribution of a Steel Plant

    56/72

    Protection function can be classified asfollows:

    Back up protection

    (Over current and Earth Fault) Power transformer protection

    (Unit or Differential Protection)

    Distance protection

    Differential protection Busbar protection, etc.

  • 8/13/2019 Power Distribution of a Steel Plant

    57/72

    Application

    The most commonly used protective relays arethe instantaneous overcurrent relays. They areused as both primary and backup protective

    devices and are applied in every protective zonein the system.

  • 8/13/2019 Power Distribution of a Steel Plant

    58/72

    Restricted earth faultprotection is provided inelectrical powertransformer for sensinginternal earth fault of thetransformer

  • 8/13/2019 Power Distribution of a Steel Plant

    59/72

    FaultLoad

    Radial Line

    The current decreases as the distance increases,This indicates that the operation time of the relaywill be larger as the current is farther from thesource. This is one of theadvantages of inverse-type overcurrent relays.

    RELAYOPERATIONTIME

    Current (A)

    Time (s)

  • 8/13/2019 Power Distribution of a Steel Plant

    60/72

    Distance protection uses current and voltageinformation to make a direct, or indirect,estimate of the distance to the fault.

    Application

    Distance relays are widely used for primary andbackup protection on transmission lines wherehigh-speed relaying is desired.

    Other applications include generator backup

    protection for faults on the system and startup oflarge motors with high inertia.

  • 8/13/2019 Power Distribution of a Steel Plant

    61/72

    Application

    Synchronism check relays are applied when twoor more sources of power are to be connected toa common bus.

  • 8/13/2019 Power Distribution of a Steel Plant

    62/72

    K

    L

    The arrows shown in the figure areused to represent the protection

    tripping direction. Note that therelays are oriented towards theprotected lines. This orientationdivides the system protection intotwo independent groups: the relayslooking to the right and those

    looking to the left. Thedirectionality divides thecoordination process into twoindependent processes. A relay onlyneeds to be coordinated with theother relays in its group.

  • 8/13/2019 Power Distribution of a Steel Plant

    63/72

    Application

    Directional overcurrent relays are used toprovide sensitive tripping for fault currents inone(tripping) direction and not trip for load or

    fault currents in the reverse (normal) direction.

  • 8/13/2019 Power Distribution of a Steel Plant

    64/72

    ExternalFault

    IDIF = 0

    CT CT

    50

    Balanced CT Ratio

    ProtectedEquipment

    If the primary andsecondary currentsat both sides of the

    protected

    equipment areequal. There willbe no difference,and the relay will

    not operate.

  • 8/13/2019 Power Distribution of a Steel Plant

    65/72

    InternalFault

    IDIF

    > ISETTING

    CTR CTR

    50

    Relay Operates

    Protected

    Equipment

    For an internalfault, the

    secondary currents

    are 180 out ofphase and produce

    a differentialcurrent through theovercurrent relay.If this differentialcurrent is larger

    than the pickup forthe relay, the relay

    will trip bothcircuit breakersinstantaneously.

  • 8/13/2019 Power Distribution of a Steel Plant

    66/72

    Bus protection

    Transformer protection

    Generator protection

    Line protection Large motor protection

    Reactor protection

    Capacitor bank protection

    Compound equipment protection

  • 8/13/2019 Power Distribution of a Steel Plant

    67/72

    The basic idea of coordination is that thebackup relay should be slower than theprimary relay, with a minimum separation ofTbetween curves calculated as follows:

    tbackup= tprimary+ T

  • 8/13/2019 Power Distribution of a Steel Plant

    68/72

    Distance

    Distance

    t

    I

    } } }T T T

  • 8/13/2019 Power Distribution of a Steel Plant

    69/72

    For relay R1,CT chosen =1600/1AMaximum fault current(I) = 10.297kACurrent setting(IS)=130% of 1600A =2080A

    For t=0.15s, TMS=0.035

  • 8/13/2019 Power Distribution of a Steel Plant

    70/72

  • 8/13/2019 Power Distribution of a Steel Plant

    71/72

    By performing various system studies using MiPower, the following thingswere concluded:

    From the results of Load flow analysis it is verified that:

    No bus or transmission line is getting overloaded.

    Real and Reactive power requirement or excess under variousoperating conditions is found.

    Loading of transformers is verified.

    From the results of Short circuit analysis following observations aremade:

    Required rating of equipments and Interrupting capacities ofbreakers is found.

    No requirement for change in the existing system on account ofexpansion and capacity addition was found.

    Short circuit levels obtained at various buses is used as input forrelay coordination.

    From the results of Relay Coordination following observations aremade:

    Settings for over current relays at various feeders were given andcoordination between them was verified.

  • 8/13/2019 Power Distribution of a Steel Plant

    72/72

    THANK YOU