potf status update. paths reviewed tot-2a path 31 path 49 path 66 north bpa

9
POTF Status update

Upload: amelia-hart

Post on 27-Mar-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

POTF Status update

Page 2: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

Paths Reviewed

• TOT-2a Path 31• Path 49• Path 66 North BPA

Page 3: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

• The Path Operations issues we are experiencing are due in part to the fact that path limits are considered SOLs. The current paradigm marries operating limits and Transfer Capability into a single parameter for WECC paths – the historical OTC.

• This approach reveals inconsistencies and conflicts with real-time information and tools.

• What does it mean to “operate” a path in the operations horizon?• Why do we require WECC Paths to have SOLs? Are there better

ways to determine that we have acceptable system performance?

History of Path Operations

Page 4: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

• Current paradigm reveals conflicts between Path SOLs and real-time information and tools:

• Path XYZ – thermally limited to 650 MW in the E>W direction. 650 MW is the Path SOL. Loss of line A results in line B reaching its emergency Facility Rating at path transfer levels of 650 MW E>W.

• When path flows exceed 650 MW TOPs mitigate – up to and including shedding load (for TOP-007-WECC-1 paths)

• When the Path SOL is being exceeded, what if real-time information or RTCA isn’t showing that the loss of line A results in line B exceeding its emergency Facility Rating?

• Is an SOL really being exceeded? NO• Inverse is also true – what if the Path SOL is not being exceeded, but the

underlying condition driving the establishment of the Path SOL is being violated? YES

Issues With Current Paradigm

Page 5: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

• WECC and the POTF are considering the following:• What if a thermally limited Path SOL were not an SOL at all, rather the

facility ratings of the impacted facilities were the SOL?• What if the Path had a Transfer Capability instead of an SOL?• What if the Path Transfer Capability was observed for scheduling

purposes but not treated as an operational parameter?• Should we be using real-time information and tools such as real-time

contingency analysis to determine acceptable pre- and post-Contingency system performance?

• If a Path does not have an SOL, does a Path really need to be “operated”?

Challenging Questions Brett

Page 6: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

Findings

• Path Operator is in practice responsible for outage reporting to assure correct topology and Path SOL’s to the WECC RC per the IRO-10 RC Data Request.

Page 7: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

Findings

• Capital “D” Directives issued to Path Operator(s) for Path SOL exceedences.• Coordinated procedures that have been agreed

upon may result in other TOP’s receiving Directives.

Page 8: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

Issues Identified For Some Paths

• Path Operator does not have specific authority to direct the TOP’s unless contracts provide that authority.

• Path Operators, have indicated that the counterparties have no incentive to enter into contracts assigning responsibility for path Exceedance.

• There is no single entity under the NERC Functional Model identified for path management.

• Path Operators have little Authority for the Path but in some cases have been held responsible for the Path SOL violation.

Page 9: POTF Status update. Paths Reviewed TOT-2a Path 31 Path 49 Path 66 North BPA

NERC Functional Model

• No true definition of Path Operator in Reliability requirements, responsible entities listed are RC, TOP, TO, BA, GO, GOP, LSE………….. No mention of Path Operator