potential network benefits of concentrating solar thermal ... · cst provides energy storage for...
TRANSCRIPT
Potential network benefits of concentrating solar thermal generationJay Rutovitz, 24th June 2013
Project Consortium Consortium
• Australian Solar Thermal Energy Association (AUSTELA) • Institute for Sustainable Futures (UTS)• Centre for Energy and Environmental Markets (UNSW)
Ergon Energy major project partner; other network operators provided data and collaborating on case studies (Essential, Transgrid, Electranet, SP Ausnet, Powercor, SA Power Networks)
ARENA Emerging Renewables Program – 66% of funding
Project objectivesQuantify potential economic network benefit from installing CST in grid constrained areas
Identify and map locations where CST could provide cost‐effective network support services before 2020
Four case studies (one each state) of CST in promising locations
Engage TNSPs and DNSPs about CST as an alternative to network augmentation
Project overview
TASK 3 Map cost effective
distributed CST
TASK 1Quantify and Map network constraint
zones (ISF)
TASK 2Map of potential
firm capacityUNSW
TASK 4 1 CASE STUDY PER
STATE
Project overview
TASK 3 Map cost effective
distributed CST
TASK 1Quantify and Map network constraint
zones (ISF)
TASK 2Map of potential
firm capacityUNSW
TASK 4 1 CASE STUDY PER
STATE
Interactive on web
Why?
CST provides energy storage for dispatchable output
CST has reliability to provide network services
Network spending significant driver of rising electricity prices, CST has potential to reduce network spending
Potential to accelerate Australian CST deployment
Allows greater adoption of renewable generation by complementing intermittent resources
To answer these questions, we created
DANCEThe Dynamic Avoidable Network Cost
Evaluation Model
Where within the electricity network do the most
cost‐effective DE opportunities exist?
How much could DE be worth at these locations?
When are the key years and times of constraint?
TASK 1 – MAPPING NETWORK CONSTRAINTS
The mapping…
• SEE GOOGLE EARTH FILE
Task 1 – Quantifying potentially avoidable investment
** draft results for Vic * Most of SA investment for one site
QLD NSW VIC** SA Total Total investment 2013 to 2024 $477 m $128 m $485 m $242 m $1,332 m Number of constraints 24 10 44 3 81 Proposed nvestment 2013 – 2024(locations with DNI>20) $473 m $73 m $76 m $231 m* $852 m
Number of constraints 22 6 10 2 40
Task 2 – Indicative Firm Capacity from CST (1)
Model uses hourly DNI as key input (2009 –2011) to calculates energy flows
For each location takes the 21 highest peak events for winter afternoon, winter evening, summer afternoon, summer evening periods
For each event determines whether CST would have been generating
Indicative Firm Capacity is taken as average value of output over the 21 events
Modelling indicative firm capacity from CST (2)
Dispatch strategy: start at 12 noon and keep going flat out until storage empty (ienot optimum for meeting peak)
6 different storage configurations• 0 hr 1 hr 3 hr
5 hr 10 hr 15 hr
INDICATIVE FIRM CAPACITY – SUMMER AFTERNOON, 1 HR STORAGE
INDICATIVE FIRM CAPACITY – SUMMER AFTERNOON, 5 HR STORAGE
INDICATIVE FIRM CAPACITY – WINTER EVENING, 1 HR STORAGE
INDICATIVE FIRM CAPACITY – WINTER EVENING, 5 HR STORAGE
INDICATIVE FIRM CAPACITY – WINTER EVENING, 10 HR STORAGE
INDICATIVE FIRM CAPACITY – WINTER EVENING, 15 HR STORAGE
Indicative firm capacity
Most locations can reach 90% IFC and above by increasing storage hours
These results for crude dispatch strategy; could certainly improve to get better availability at peak times
Task 3 - Cost effectiveness
Integrate solar mapping with network constraint mapping,
1st question: where can CSP avoid the need for network augmentation?
2nd question: what is the cost benefit LCOE – pool price – LRET – network support payment
Can CSP avoid the need for network augmentation?
QLD NSW VIC SA All states All locations 21 6 21 3 51
% of all locations 90% 75% 54% 100% 70%
% of locations with DNI > 21 90%
100% 100% 100% 94%
DRAFT RESULTS
What is the cost effect?
DRAFT RESULTS
QLD NSW VIC SA All states
Positive cost benefit 29% 0% 13% 100% 25%
Proportion where cost benefit > ‐$20 43% 20% 13% 100% 39%
Cost benefit DRAFT results – best sites
Charleville ZS Emerald ZS Monash TS (new line)Proposed network investment $70.0 m $24.0 m $226.0 mCommissioning year 2022 2020 2022DNI (MJ/m2/yr) 25.1 24.1 23.4 Optimal plant Plant size (MW) 18 70 47 storage (hours) 3 5 1 Indicative Firm Capacity 91% 84% 85%Total plant cost ($m) $113 m $405 m $224 mAnnual Network Support Payment ($/yr) $5.2 m $1.8 m $16.6 m
COST BENEFIT CALCULATION LCOE $160 $135 $164 Electricity sales $74 $65 $108Carbon price effect $62 $52 $83LGC $16 $28 $16NSP contribution ($/MWh) $79 $6 $143BENEFIT ($/MWh) $70 $17 $185
Cost benefit DRAFT results – best sites
Charleville ZS Emerald ZS Monash TS (incremental) Proposed network investment $70.0 m $24.0 m $10 m Commissioning year 2022 2020 2022DNI (MJ/m2/yr) 25.1 24.1 23.4 Optimal plant Plant size (MW) 18 70 47storage (hours) 3 5 1 Indicative Firm Capacity 91% 84% 85%Total plant cost ($m) $113 m $405 m $224 m Annual Network Support Payment ($/yr) $5.2 m $1.8 m $0.7 m COST BENEFIT CALCULATION LCOE $160 $135 $164 Electricity sales $74 $65 $108Carbon price effect $62 $52 $83 LGC $16 $28 $16NSP contribution ($/MWh) $79 $6 $6 BENEFIT ($/MWh) $70 $17 $48
Cost effectiveness by year (DRAFT results)
0%10%20%30%40%50%60%70%80%90%
100%
2014 2016 2018 2020 2022 2024
(excluding sites <20 MJ/m2/day)
Proportion of sites where cost benefit > ‐$20
QLD
NSW
VIC
SA
Task 4 - Case studies - approach
1 per state, in collaboration with DNSPExamine whether CST can meet the
constraintExamine business caseWorkshop with network provider
… some interesting outcomes so far re HOW to meet constraint
Type of contraints by state
0
2
4
6
8
10
12
14
16
18
Growth Voltage Reliability N‐1 SOS
Num
ber o
f con
straints
South Australia
NSW
Queensland
THANK YOU