potassium topping cycles for stationary power · pdf filepotassium topping cycles for...

132
NASA CONTRACTOR REPORT LO CM NASA CR-2518 POTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for Lewis Research Center NATIONAL AERONAUTICS AND SPACE ADMINISTRATION WASHINGTON, 0. C. MARCH 1975 https://ntrs.nasa.gov/search.jsp?R=19750014834 2018-05-24T05:14:15+00:00Z

Upload: lehanh

Post on 26-Mar-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

N A S A C O N T R A C T O R

R E P O R T

LOCM

N A S A C R - 2 5 1 8

POTASSIUM TOPPING CYCLESFOR STATIONARY POWER

R. J. Rossbach

Prepared by

GENERAL ELECTRIC COMPANY

Cincinnati, Ohio 45215

for Lewis Research Center

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION • WASHINGTON, 0. C. • MARCH 1975

https://ntrs.nasa.gov/search.jsp?R=19750014834 2018-05-24T05:14:15+00:00Z

Page 2: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

1. Report No.

NASA CR-2518 ... .2. Government Accession No.

4 . Title a n d Subtitle - • < - . . • • . , : ; - • • } . > ' . •

POTASSIUM TOPPING CYCLES FOR STATIONARY POWER

7. Author(s)

R. J. Rossbach

9. Performing Organization Name and Address

General Electric CompanyP.O. Box 15132

Cincinnati, Ohio 45215

12. Sponsoring Agency Name and AddressNational Aeronautics arid

Space Administration aiWashington, D.C. 20546

Office of Coal Researchid 2100 M Street, N. W.

Washington, D.C. 20240

3. Recipient's Catalog No.

5. Report DateMarch 1975

6. Performing Organization Code

8. Performing Organization Report No.

GESP-741

10. Work Unit No.

11. Contract or Grant No.

NAS3-1735413. Type of Report and Period Covered

Contractor Report14. Sponsoring Agency Code

15. Supplementary Notes

Final Report. Project Manager, Martin U. Gutstein, Power Systems Division, NASA Lewis Re-search Center, Cleveland, Ohio

16. Abstract

In this program, a design study was made of the potassium topping cycle powerplant for centralstation use. Initially powerplant performance and economics were studied parametrically byusing an existing steam plant as the bottom part of the cycle. Two distinct powerplants wereidentified which had good thermodynamic and economic performance. Conceptual designs weremade of these two powerplants in the 1200 MWe size, and capital and operating costs were es-timated for these powerplants. A technical evaluation of these plants was made including con-servation of fuel resources, environmental impact, technology status, and degree of developmentrisk. It was concluded that the potassium topping cycle could have a significant impact on nationalgoals such as air and water pollution control and conservation of natural resources because ofits higher energy conversion efficiency.

17. Key Words (Suggested by Author(s))

Potassium topping cycle; Advanced cycle;Pressurized furnace; Fluidized bed furnace;Coal; Stationary power

18. Distribution Statement

Unclassified - unlimitedSTAR category 31 (rev.)

19. Security Classif. (of this report)

Unclassified20. Security Classif. (of this page)

Unclassified21. No. of Pages

129

22. Price"

$5.75

* For sale by the National Technical Information Service, Springfield, Virginia 22151

Page 3: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Page Intentionally Left BlariK

Page 4: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE OF CONTENTS

Page

SUMMARY 1

INTRODUCTION... ....'...- 3

PRELIMINARY ANALYSES OF POTASSIUM-STEAM TOPPING CYCLES 5

Selection of Reference Steam Powerplant 5Analyses of Potassium-Steam Topping Cycle 5

Basic Potassium-Steam Topping Cycle 5

Recommended Powerplants for Conceptual Design 5

CONCEPTUAL DESIGN OF PROMISING POTASSIUM-STEAM TOPPING CYCLES. . 14

Selected Powerplants for Conceptual Design 14Pressurized Furnace Powerplant Conceptual Design 14

Potassium Boiler 14High Pressure Turbine . 21Low Pressure Turbine 24Potassium Condenser/Steam Generator 29Potassium Dump Tanks 29Plant Conceptual Layout - Cycle #1 - Pressurized BoilerSystem 35

Pressurized Fluidized Bed Boiler Powerplant ConceptualDesign - . 45

Potassium Boiler 45Potassium Turbine 49Potassium Condenser/Steam Generator 49Plant Conceptual Layout - Cycle //2 (Pressurized Fluid BedBoiler) . 49

ECONOMIC AND TECHNICAL EVALUATION 61

Potassium Component Costs 61

Methods Used 62Condenser-Steam Generator. ... 62Potassium Boilers 62Potassium Feed Pumps 65Potassium Turbines 65Summary of Potassium Component Costs 72

Powerplant Costs 74

iii

Page 5: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Page

Methods Used - . . - . . . . . - 74Summary of .Capital Costs 76Summary of Cost of Electricity 78

Technical Evaluation 80

Conservation of Fuel Resources 80Environmental Impact 81Status of Technology 92Degree of Development Risk and Associated Costs 94

CONCLUSIONS AND RECOMMENDATIONS .' 97

APPENDICES 99

Appendix A. - Potassium-Steam Topping Cycle Code. 99Appendix B. - Topping Cycle Performance Calculation Code -

Base Case 104Appendix C. - Variation of Performance and Cost with Cycle

Conditions IllAppendix D. - Performance Calculations for Selected Cycles. . .116

REFERENCES 124

iv

Page 6: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

SUMMARY

General Electric has performed A Study of Potassium Topping Cyclesfor Stationary Power under NASA Contract NAS3-17354 for NASA and theOffice of Coal Research. The following objectives were established forthis program:

1. To conduct preliminary assessments of the capital cost of avariety of potassium-steam topping cycles.

2. To prepare conceptual designs of selected topping cycle power-plants.

3. To perform technical and economic evaluations of topping cyclepowerplants based upon the conceptual designs.

Task I included preliminary analyses of several variations of abasic topping cycle powerplant, and the selection of promising configura-tions for which conceptual designs were done in Task II. A computer codewas written to calculate topping cycle performance and capital and operat-ing costs. This code was used to analyze a large variety of topping cycleplants to identify on an approximate basis those cycles that appear tooffer high plant efficiency and low capital costs.

Based on the results of Task I, four topping cycles were consideredas most promising. These included cycles with a conventional coal firedfurnace, a supercharged furnace and two fluidized bed furnaces, onepressurized and one at atmospheric pressure. The pressurized furnacesystem is compatible with clean fuel derived from coal gasificationplants. This was the first choice for conceptual design. The secondchoice was the pressurized fluidized bed system because it had the lowestcost of electricity.

In Task II, conceptual designs were made for the two selected toppingcycle systems. The potassium components, boiler, turbine, and condenser/steam generator, received the most attention since the cost estimateswere to be based on the conceptual designs. Selection of conventionalsteam powerplant components and the layout of the overall powerplantswere done by the Installation, Service and Engineering group of GeneralElectric who are familiar with conventional powerplant practices.

Task III was the economic and technical evaluation of these two con-ceptually designed plants. The fluidized bed plant had about 18% higher(coal pile to bus bar) efficiency than the pressurized boiler plant, dueto the conversion efficiency of the coal gasification plant required for

Page 7: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

the pressurized boiler system. The pressurized fluidized bed boiler wasjudged to be the major development risk and cost.

The pressurized fluidized bed topping cycle system would use 21%less fuel and have 35% less heat rejection than a conventional steamplant of the same power output due to its higher coal-to-busbar con-version efficiency. Assuming an adequate development program, it wasestimated that a demonstration topping cycle powerplant could be opera-tional in ten years.

Page 8: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

INTRODUCTION

By 1990 the installed capacity of United States powerplants will befour times the capacity of 1970, based on the historic growth rate ofdoubling every ten years. Because oil and natural gas are in short supply,the principal sources of energy for future electric power production arecoal and uranium. Although there has been a trend away from coal to oiland natural gas for central-station powerplants because these fuels werecheap, this trend will probably reverse because forecasters predict onlya few decades supply of domestic oil or natural gas at present consump-tion rates while they forecast hundreds of years of coal reserves. Thetrend away from coal was caused by several factors, including: airquality regulations issued in accordance with the Clean Air Act of 1970which limit the amount of S02 and NO^ emissions in stack gases; the CoalMine Health and Safety Act of 1969, which has resulted in a slowdown ofproduction in underground mines; and public sentiment against surfacemining which imposes limitations on the amount of coal that can be pro-duced by that method. Since coal is our most plentiful fossil fuel itwill have to be used for central station powerplants. Unfortunatelyonly a small fraction of this country's coal has a low enough sulfurcontent (less than about 0.9% sulfur) to meet the standards for S02 emis-sions but there are several options for attacking this problem. Potentialsolutions include the production of clean fuel by liquifaction or gasi-fication of coal, the use of a fluidized bed of coal and limestone inthe furnace, and S02 stack gas scrubbers with a conventional pulverizedcoal furnace.

Because of the impending fuel shortage there is considerable in-terest in utilizing fossil fuel resources more effectively by improvingthe efficiency of central-station powerplants and minimizing environ-mental impact by controlling stack gas emissions and reducing heat dis-charges. The potassium topping cycle can accomplish both of these ob-jectives because this cycle permits the use of heat from combustion gasesat a higher temperature than is possible with a conventional steam power-plant. The higher cycle temperature increases powerplant efficiency andtherefore the topping cycle rejects less heat to the atmosphere than aconventional steam powerplant with the same power output.

The potassium technology was developed on the Advanced Rankine CycleProgram for Space Power. Potassium boiling and condensing data have beenobtained by the General Electric Company over the past ten years in threeseparate test facilities designed for heat transfer experimentation. Aconcurrent potassium turbine program included the design, fabricationand testing of two and three stage potassium turbines. Although potassiumboilers, turbines, pumps, valves and condensers were tested for thousandsof hours on the space program, it will be necessary to scale those com-ponents up to commercial powerplant size and extend the design life tovalues required for commercial power stations.

Page 9: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

For central station application, the heat of condensation of thepotassium cycle would be rejected to a steam generator, which would pro-duce steam at conditions comparable with those of modern steam powerplants.Fraas (ref. 1,2) has described the potassium topping cycle studies doneat ORNL and concludes that the concept is feasible and attractive.

The main advantage of the potassium topping cycle is a higher thermalefficiency, over 50%, compared with 40% for a conventional steam plant.For a given power output, the topping cycle uses 20% less fuel and re-jects only two thirds as much heat as a conventional steam plant. Thetopping cycle can be integrated with a coal gasification plant or canuse coal directly. The liquid metal technology developed for the toppingcycle concept will be applicable to fusion powerplants when that technologybecomes feasible.

In this program, a design study was made of potassium topping cyclesfor central station use. Initially powerplant performance and economicswere studied parametrically using an existing steam plant as the bottompart of the cycle. Two distinct powerplants were identified which hadgood thermodynamic and economic performance. Conceptual designs weremade of these two powerplants in the 1200 MWe size, and capital andoperating costs were estimated for these powerplants. A technical evalua-tion of these plants was made including conservation of fuel resources,environmental impact, technology status and degree of development risk.

Page 10: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

PRELIMINARY ANALYSES OF POTASSIUM-STEAM TOPPING CYCLES

Selection of Reference Steam Powerplant

The Bull Run Steam Plant is a TVA coal-fired steam powerplant havinga capacity of 950 MWe and was constructed near Knoxville, Tennessee inthe 1961-1966 time period. The steam cycle has 2413 N/on2 (3500 psig)and 811 K (1000°F) turbine inlet conditions with one reheat to 811 K(1000°F) and "once through" condenser cooling. Reference 3 contains acomplete description of this powerplant, including component designs,operating conditions, performance and capital costs. The thermal effi-ciency of the plant is 40.7 percent with river cooling water. It wasrecommended and approved that the Bull Run Steam Plant be selected as thereference steam plant for the topping cycle study.

Analyses of Potassium-Steam Topping Cycle

BASIC POTASSIUM-STEAM TOPPING CYCLE

A computer code was written to calculate on a parametric basis theperformance of potassium-steam topping cycles and estimated componentcosts. A schematic diagram of the cycle is shown in Figure 1, and thecode is described in Appendix A.

The performance of a topping cycle with 1033 K (1400°F) potassiumturbine inlet temperature and a conventional furnace is shown in Table 1,and a detailed computer print out for this case is presented in AppendixB. This cycle was called the "base case" because it was the initialtopping cycle to be investigated. Parametric variations were made sub-sequently to determine the effects on performance and costs. The cycleefficiency of 44.4 percent is about 14 percent higher than the steamplant alone which was calculated to have an efficiency of 38.8 percentwith a wet cooling tower.

A cost summary for the base case topping cycle is shown in Table 2,for a system with a conventional furnace.

Recommended Powerplants for Conceptual Design•

The topping cycle code was used to determine the sensitivity oftopping cycle performance and costs to cycle variations; this work isdescribed in Appendix C. Based on the results of the parametric study,six cycles were identified as candidates for conceptual design. Threeof these had conventional furnaces, the base case and two with higherpotassium turbine inlet temperature, as this was the most significantparameter in the sensitivity study. The other three were topping cycle

Page 11: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

o•H

o

O 00H O

CU

U 0)

O 3P.

•H O

O OH «H

oo•rlfa

-j c«q M

Page 12: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 1. - PERFORMANCE SUMMARY-CONVENTIONAL BOILER

(Base Case)

Steam Turbine Inlet Pressure, N/cm (psia)

Steam Turbine Inlet Temperature, K (°F)2

Steam Reheat Pressure, N/cm (psia)

Steam Reheat Temperature, K (°F)

Steam Condensing Temperature, K (°F)

Steam Flow Rate, kg/s (Ib/hr)2

Potassium Turbine Inlet Pressure, N/cm (psia)

Potassium Turbine Inlet Temperature, K (°F)2

Potassium Condensing Pressure, N/cm (psia)

Potassium Condensing Temperature, K (°F)

Potassium Flow Rate, kg/s (Ib/hr)

Steam System Output, MWe

Potassium System Output, MWe

Total Output, MWe

Cvcle Efficiency, percent

2424 (3515)

811 (1000)

372 (540)

811 (1000)

330 (135)

820.7 (6.5 x 106)

10.46 (15.17)

1033 (1400)

1.6/0.76 (2.4/1.1)

866/811 (1100/1000)

902.8 (7.15 x 106)

914

289

1203

44.4

Page 13: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 2. - COST SUMMARY - CONVENTIONAL BOILER

(Base Case)

FPCClass Description Cost (MM$)

310 Land and Land Rights 0.479

311 Structures and Improvements 50.132

312 Boiler Plant Equipment 119.009

Boiler 54.032

313 Potassium Plant Equipment (Excl. Furnace) 39.455

314 Turbogenerator Units 42.341

315 Accessory Electric Equipment 11.154

316 Miscellaneous Powerplant Equipment 4.729

35X Transmission Plant 8.234

397. Communications 0.400

Total Direct Cost 275.934

Indirect Construction 7.726

Total Construction Cost 283.660

Engineering and Design 25.529

G & A 17.587

Interest 23.260

Total Project Cost

Wages

Supplies

Maintenance

Capital

Depreciation

Insurance

Taxes

Operating Cost Per Year 42.316

Fuel Cost 25.852

Limestone Cost 1.470

Total Annual Operation Cost 69.637

Cost of Electricity Mills/MJ (Mills/KWH) 2.299 (8,278)

Page 14: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

systems with a pressurized fluidized bed furnace, a pressurized furnaceand an atmospheric pressure fluidized bed furnace. These cycles areshown in Table 3.

Case 1 is the base case described earlier. Cases 2 and 3 are fora conventional furnace with potassium turbine inlet temperatures of 1116and 1200 K (1550 and 1700°F), with condensing temperature of 839 K (1050°F).Case 4 is for a pressurized boiler using a clean fuel from a coal gasifi-cation plant. The potassium turbine inlet temperature is 1033 K (1400°F),and the gas turbine inlet temperature is 1255 K (1800°F), which is attain-able today. The pressure in the furnace was assumed to be 241 N/cm^(350 psia). Case 5 is for a pressurized fluidized bed furnace at 91 N/cm(132 psia). The gas turbine inlet temperature was limited to 1144 K(1600°F) to permit sulfur removal in the fluidized bed. The last caseis for a fluidized bed furnace at atmospheric pressure, the cycle condi-tions being the same as the base case. Shown in successive columns arecycle efficiency, capital and yearly fuel costs, and the cost of electricityfor two fuel costs, $0.38 and $0.76 per GJ ($0.40 and $0.80 per millionBtu) .

Of these six cycles, four systems were considered as candidates forconceptual design based on the results in Table 3 that the type of furnacehas the largest effect on the cost of electricity; cycles 1 and 3 weredropped from further consideration. A summary of the four candidatesystems is given in Table 4. The capital costs are shown in Table 5 andthe operating costs are summarized in Table 6 for the four powerplants.

Although the conventional, furnace system has a lower cost of electricity(including a nominal amount for an 862 stack gas scrubber) than the pres-surized boiler system using gasified coal (see Table 6), it is felt thatthe two powerplants are not comparable on that basis because of the un-certainties of the cost and effectiveness of stack gas S02 scrubbers.However, on the basis of using gasified coal in both plants, the pres-surized boiler plant has the lower cost of electricity. The plants withfluidized bed boilers are attractive because they have the lowest costof electricity (see Table 6), but they are not yet as well developed asthe combined coal gasification-pressurized boiler technology, especiallythe pressurized fluidized bed. In addition it must be verified that thenon-vitrified ash in the pressurized fluidized bed is soft enough not tocause erosion of the gas turbine.

The pressurized boiler system was most attractive because the tech-nology has been developed in naval boilers (ref. 4), the capital costwas lowest of all the systems investigated and the system is compatiblewith fuel derived from coal gasification. Therefore, the first choicefor conceptual design was the topping cycle system with a pressurizedfurnace. The second choice was the supercharged fluidized bed systemwith the atmospheric fluidized bed system as an alternate if fly asherosion of the gas turbines is considered to be a problem.

Page 15: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

3U

ca

34J

r, MCJ VO rH~^0 COO rH OCO -s. CJCO O

O-a-

SOor-l

B-S

O

co

oo

O

CMO

voi-H

O

CM00

voo

o

co

oo

CM

00

OO

in

oinco

CTv

inCM

CM-a-

CO

oCON*X

oo

CM•

CM

inn

oin

COi-l

O

00s^

co

CM

CM

nCM

VOmro

oo*o

00CM

00•

CO

oo\0m

oomso

\ooomsi-

ooCOooCM

ooVOco

oCM

m

roCM

om

in^a-CM

ino\

oo

r-ooCTi

CM

CM

inoo

inCM

•a-coco

covoCM

CMsr

(0

g

Co4Ja•H^1CJCOcuQ

fa

11

rta0•H

C0)>Co^101COrt

CJ

01COrtM

01CJrte£

rH<0

g

•H4J

C0)

rjO

CJ

sroommrH

*stVOrHrH

II

C•H

Vj

H

'•

0

Om0rH

K^

OVco00

II

.

fc

01 o o0 o m

rHcfl

g

01

oo

O CT>O COCM 00

•H

4-13O

mmCM

00H

rl01HiHOm-a01N•rl ^

3 oCO OCO O01 00M rH

•O PnQ> ON O•H OT3 vD

CJ)N

3 IICOCO 0}Ol coM 00

PH EH

m

rlEH01

rH •>•H tOO CO

"3Z »3 mco cdco PQ01M to

PH S

CJ o)•H rHM U0) >*

CO <U^ 60 Cg4-1 W

•o01

TD

i-HOC

voo

oo•a-

o00co

4JCOOCJ

§•H

•a01

coCJ

encdfi

cdOCJ

M<4H

eoCOO

10

Page 16: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

CO(XW,-Jt-HOCQ

g

MCOCO<HOfa

faO

COW

HS

@WfafarHO

P:HM&

COHJ3^2

&

Ofa

HH

*

MO§"faoaoCO%%oU(

-a-[dij

3

TJ•o v(U CQNiH TJM <U3 NCO -Hco -a<U -HP 3fa rH

fa

•aU CU•rl CQM<1) TJ

J3 <Ua. NCO -rlO TJe IH4-> 3<! rH

fa

TJ0)N•Hh3cocacuM

fa

rHcd

•o dfl> 0N -rl

•H 4J

J S4J >a co o

o

o"O

T-H

enenOrH

o1

oi-H

enenO

x-\oo•a-rH\^s

en

orH

X-%

0inmrH

rHrHrH

^fae

4-1H

^

t4

oT^43

rd

HIO,

H

rHed

cSTJcuN•Hrlfl>>rH3

fa

-J^1

ed

8•oOJN•HMCU>

rH

fa

rHCU3

fa

TJCU>•Hrl

0>nirHrdOO

rHcdO

CJ

TJCUNiHhCU

iH

fa

rHCU

£

cf ooto -H Chi rH -HU) TJ rHN C TJ

•H <d Crl 33 COU SB> rH

rH Cd £3 O COfa cj <j

00C t>0

CO iH CM rH iH0> TJ rHN C TJ•H ffl Cri 35 ed0) 23> rHrH cd .e3 0 COfa 0 <

co•HUao.iHUH•rlCOCOO *

4J .rH tSCd Cd0 rH

CJ fa

§t>0 4JC 60 CO

M iH C >.H H TH CO<0 TJ i-HN C TJ rHiH CO C iHn a co oQ> 33> rH H

rH CO JC 4)

fa CJ <j fa

CXiH3o-

rH0)

fa

TJCUtoTJ•rl

rHfa

eM

TJCU«

TJiH3rHfa

CH

4JCCOrHfa

Co•H4Js•HMH•HCOedoCM

rlV

5

SU

CO

4J0)3

rHeo

o

CN4

S

TJcu«TJiH3rHfa

CM

TJ.01PQ

TJ•H3

rHfa

M

rH0)

fa

34-1«

s3

TJ0)00cfl4-1CO

A

Co•H4-1cdrH

3 t fU iH•H 'ftu C0) 3« PQ

rHO^44JPiOU

X

4J

rH

|

§otf

CMOCO

0)^J

rH(fj

O

CsJ

S

cu4-1COp^

rj

g

4-1

pfj

xg

**\x

4-1•H

•cx53H

COCOO

rHm

CM\0

00«n

oom

jrH

A

4-1COO

rlCUrH•rlO«

CMooCM

00OOCM

0000CM

in

**

%A

M0)

1

I•HCOCOcd4JO

fa

rHen

CMrHCTl

00o

10^

^fc

cuofa

0)4Jco

^^00H

O

•a-oCM

-

o

S

vT0)

Q

faCO<0o

rHrHen

sf

en

^«ooCM

Omen

014-1

O

4-1CcdrHO.rloO

favO0

rH rHCO -CO-4JOH

•K«4J•rlU•H

4-1U

rHW

MHO

4JCO

cS

en

m0

CMCM

m•ON^s

tOVO

CM

§•

oo

CM

cn•o

vDoo

fH

O x-sU 3

CU *~)N OVO•rl -s.0rl OrHCO 00 —.> en oi-l O3 *J -a-

\o4J Ofl rH

CO Ocd oO oo3

m o

cos

uen

crea

sed

>>jo cu

4->4J CO

§ 58 SCJ rvl

« *"H fa

11

Page 17: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

enHenOu

CO

a•I o

£j;j j f"j• j in— • i i r/jU. — iu-j fj J'_/•) «— • *— »

to D OLU _l CDrX uQ.

U~ QC£. LULU M QCr — LU0. Q _

O D C

I- U_

QUJNl

o: u~— N i_•* — Jcn ~

LU cfy

0.

^LU OM •-•— H-r z•-i LU1 ^^

Q. ZO O

O

zo1— <

t

DE

SC

RI

coO <ln iU. O

C O C M L A J- CT> LA rA fAO- T ^ H O cn cn ^H) r** C M J -

T J O O CM L O i - t J " OO OT» CO lA rA t— f

J- U* LACM UD CM• • •

r— ( vD LDLA rA t-H

OO CM rA LO . l/ hA I*A f~ j - i - H L D J - r A r - » r > - C M J -

O C 2 L D CT» C M t — t J - OO OLA O rA j- i-l

r- 1

OO LD OLA J- O

* • •-i cn o

OO CM i-H OO LD LA rA tA Oj - r - i c n LO - o i-i r*. C M J -

o o r ^ j - L D i - n J - o o oLA LA LA rA •-<

C5 LA rA^D CT* r*^

oo LD r*>»rA rA f-H

O O C M C M L A L A L A r A I A O

o o 'J- cn 'r»> i-i j- oooLA CM rA rA t-t

1-t

LO LA OJ- LA 0• • •

OO CT> Oin rA

CO r- Zt Z co LU

21 Q. CO Of Z •— ' $UJ ^— I-H 1™ III " ""> 1

C O t D U B ' E « C O Q i U j ' Q "H QiS LU Z O r— O Oi Zn i o , o . p c5 »-« j— o LU to

« S 3 ^ s LU § ^ 5 o < PC* O' OOO LU (— CL _J<

Q L U U L U Z O Q . OQ Z Q Z Z l u L U C O H Hz <! t z go « o _j r> z z•3, Z ^ 15 •— < CQ O LU O O2

ZO -J »- i < O r - o 2 E « - i Ot ^~ O^ " , ^ ^^ ^^ ^Q ^Q ^J T»>^ ^>^

C-) LU ^5 (/) ^3 UJ ^^ -C ^^ ii i Q_ yj • fr—O Z5 — J 00 *C . *- C5 ^1 ^J ^J *™^ Ib 2

_ ) c o § £ c o < 2 T L U I - a -

C3 i— < CM rA J - l A L O Xr^r-( 1— 1 1— 1 •— 1 1— 1 1— ( 1— 1 1 A C T >r A t A r A r A r A r A f A r A r A

cr» LD0 00

IA LDJ-CM

J- ooLA rArA r^LDCM

vD LDr CM

rA LOCMCM

CM "t

LD r>xf*^CM

CO

COoo

r- gCO HH

0 1-0 0

H a:0 1-LU COOL Z

Q 8

^ br- LUO 0£I- •—

Z

LA OO CM LD

-< CM IA C3LA CM i-H CMCM

CM OO O CMcn rA oo CM

O J- LD CMf1^ CM i-H CMCM

CM O LO LDO 1^ CM OO

O O J- OOrA CM i-H t-tCM

r* LO I-H CT>cr> LA LD CM

tA LA r^ rAOO CM r-H CMCM

o1— LU «CO . > r-O —• O0 -, H ^Z 6 S r-Q _ l_ ini-i CO CO Zr- LU 1-1 OU Q Z 0

Q£ Q 51 CBh- Z 5 ZCO ^ < >— i§ C £

O Q OU Z Z Q

_J S r-< LU _J COI- LU < LUO Z o2 ofL_ _, LU LU

O Z I—

LU L5 "-i

.^^cn,_,•—IN^

CMrA

j-

rA

J-00

rAooCM

J-0LArA

r-co

8r-

PR

OJE

C

*i-oi-

12

Page 18: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

10cu

cuCu,

CO

COrHrH

&

UHO

coCo•H

XC

•a -Hcu oN

3CO NCOco -a

PH S

CJ iH•H O

CU

cxCO NO iH

22< S

•ocuN•HJJ CU3 rHCOco c;Q)

co•a Ccu ~N

•H 4J

•H CU

ft C

°8

CO O1* vO vO P*» r** rH vDc M C M r H v o r ^ c o c o r * *

r H O C M O O I ^ O r - Oi-H

O O " i C M v O v O O v D - 3 "C M C M C O O C O > 3 - C O O O

i - H O C M O O O O I ^ OCM

e~) o^ r^ co co *sf r^* coC N C M O N O r H C O v D O

r H O r H ^ - r - s O v D O•H

i

O C T N C O C M v O C M ^ O OC M C M - 3 - O P ^ - v T C M C O

r H O C M r H O O O O O HCM

CM m

00 COCO CM

co mCO OO

rH m«3- CM

O voVO 00

sr mCO -3"

m mp*s CO

CO -3--3- CM

^

rHVO

00rH

VO

vO•3-

O00

orH

00VO

CO

O

CN

CTi

CNCM

CM

CTiO

00

mCM

CM

P-,inON

voVO

CM

r7CO

O

voooCM

COo

CJCOrH

CO

oco0)o

coCU00(0

COcu•HrH(XO.D

cuo§g

COucoocj

C -H•H O.CO COS CJ

g

CUCJ

§t-t

rl 3a. to xco a coQ M H

oCO CO

CU

CO

COo

CJ

co•H4JCO

coao

tfl

303

oH

COoCJ

rHCU3In

mo

CJ

1CO 4J CO

OH

COrH

0•H

O0)

4JCOo

CJ

3

OooCO

iH 4JX to

CO

8?u

U w

NvO•H O

CO *^> OrH O3 -3-p I \^

•OvO

CO s**i

CO 4J

3*vD

3 O

fflOO00

15

Page 19: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

CONCEPTUAL DESIGN OF PROMISING POTASSIUM-STEAM TOPPING CYCLES

Selected Powerplants for Conceptual Design

The two systems selected for conceptual design are summarized inTable 7, and detailed performance calculations are presented in AppendixD. These cycles are slightly different than those discussed in the pre-ceeding section. The potassium condensing temperature was raised to866 K (1100°F) to reduce costs, the steam temperature was raised to 839 K(1050°F) because the fireside corrosion problem is removed from the steamgenerator and a second reheat station was added to improve performance.The gas turbine pressure ratio was reduced to 15 to be more consistentwith projected designs and the potassium turbine inlet temperature wasincreased to 1116 K (1550°F) for the topping cycle with the pressurizedfurnace. For the system with a pressurized fluidized bed the gas turbineinlet temperature was increased to 1200 K (1700°F) as the maximum bedtemperature at which sulfur removal was adequate, but the potassium tur-bine inlet temperature was kept at 1033 K (1400°F) to have adequate heattransfer temperature difference in the bed.

Pressurized Furnace Powerplant Conceptual Design

POTASSIUM BOILER

The conceptual design of the pressurized furnace potassium boileris illustrated in Figure 2. The boiler shown is one of eight modulesrequired for the entire 1200 MW plant. The module is contained withina 4.34 m (14.25 ft) diameter cylindrical shell, enlarged at the gas dis-charge section to 6.25 m (20.5 ft) diameter. Overall height of the pres-sure vessel is 11.3 meters (37 feet). The size and proportions of thisvessel were determined as a reasonable mutual accommodation of a numberof requirements including the following:

1; Cycle air flow rate and heat input for eight boiler modules.

2. Axial velocity limits for a high efficiency swirl type gasburner.

3. Pressure drop through the combustion chamber and heat transferpasses.

4. Limitation of tube length in order to accommodate tube andpressure vessel differential expansion.

14

Page 20: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TD0)N•H73

CO-O r-l<U -HN O

•H PQl-l

COCOCUM

PL,

OMCO

8§uoig

CO

CO

CJ

I

•r>»

oPQ

•acoN

OO

OoCN

Oo

roo

o<•co

oo

•CN

o\

om

coCM

oo

SOvO00

ooinco

Ha-<N

OOao

mu-ics

Om10

CN

vO

ooooCNm

tne

Pno

Q.

§H

CUC

COcOO

M-l

a.

cuco•H CNOH E

a)•HcoP.

CN

cut-t3COCOcu(-1

CU0

4->CU

£l-l

CUa•H^oMS3H

I•HCOCOCO4-1O

P-

CUH

O

C

*^4CU

•HO

PQ

HCUCOCCU•0Cou

a3H

00ct, i•PI

COacu•ac0o

g•HCQCOCO4-JO

FM

3H

CU•w

CU93

•Ocucu

§•H

COCO(04-1o

PL,

CU

ycococu)-iP-,

On

cu4-1CO

M

I

34-1m

COCO<ut-io•HCO

cue

CO4-1COcucuPiI4_| Q}

0)^3

COcuffi

uccu

M-lM

15

Page 21: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

16

Page 22: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

5. Tube surface requirements.

6. Tube spacing requirements for meeting header ligament stresslimits.

7. Vapor velocity level limits inside the tubes, discharge headerand discharge ducts.

8. Insulation thickness requirements inside of vessel.

9. Maintenance of vessel components within size limits for shopfabrication and shipment to installation site.

The tubes occupy the annular region between the central combustionchamber and the refractory lining of the pressure vessel. These tubesare welded into toroidal headers for liquid feed (lower) and vapor dis-charge (upper). The gas burner structure is at the top of the unit.Combustion gases flow downward through the combustion chamber, then turnupward and pass over the tubes in a direction parallel to the tube axesbefore leaving through four ducts joined into the enlarged upper sectionof the boiler shell. The inner ring of tubes is fabricated into a membranewall which contains the combustion chamber and which receives radiantheat from the hot pressurized gases. At their lower ends the boilertubes are of reduced diameter (0.95 cm) (3/8 in.). This section of thetubes carries only liquid, and the small diameter tube ends are bent beforeentering the inlet header in order to accommodate differential expansionbetween tubes. Since the tube bundle is suspended from the vapor exitducts attached to the upper header and the only connection between theshell structure and the lower header is through the few flexible liquidfeed tubes, there is no important differential thermal expansion problembetween the tubes and the shell. Equalization of gas flow distributionthrough the main portion of the tube bundle is promoted by the incorpora-tion of an enlarged diameter section of tube (or a suitable bushingattached to the tube) at the transition between the 0.95 cm (3/8 in.)diameter tubes and the 3.81 cm (1.5 in.) diameter tubes. These shortenlarged sections create an orificing effect as the gas enters the mainheat transfer region of the tube bundle. The enlargement of the upperpart of the boiler pressure vessel is for the purpose of creating adischarge plenum for the combustion gases as they pass from the tubebundle space. This also helps to maintain a uniform flow distributionover the tube bundle annulus.

The material selected for the potassium tubes, headers and outletducts is Haynes 188, (nominal composition: 22Cr-22Ni-14.5W-0.lC-0.lLa-0.35Si-Bal. Co). This cobalt base, high chromium alloy has exceptionallygood resistance to sulphidation corrosion which might be expected on thefire-side of the boiler tubing. It also has excellent strength andoxidation resistance for a ductile, fabricable and weldable tubing alloy;and similar cobalt base alloys (i.e., HS-25) have demonstrated very satis-factory alkali metal compatability at temperatures above 1550°F. Thus,HA-188 is probably the best available alloy with the widest margin ofproperty capabilities beyond those considered necessary for boiler appli-cation.

17

Page 23: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

At the reference cycle condition of 1255 K (1800°F) gas outlet tem-perature, and 1116 K (1550°F) potassium vapor temperature, it is possibleto design the boiler for once through operation without exceeding 1186 K(1675°F) metal temperature at the high quality end of the tubing. Theboiler heat transfer surface, as determined by the data shown in Table 8,has been sized for this condition. An alternate possibility is to de-sign the boiler as a recirculating type, with a liquid drain providedfrom the upper header, a phase separator in the vapor discharge flow anda recirculating pump. This would provide a greatly increased internalheat transfer coefficient at the upper ends of the tubes and would permithigher levels of combustion gas outlet temperature without overtempera-turing the tubes.

Other advantages of a recirculating type boiler are that it is easierto start up and control, it provides a higher average tube heat flux,thusreducing the tube surface, and it has a lower peak metal temperature.

Further, significant corrosion and mass transfer benefits are de-rived from the use of a recirculating boiler:

1. The carryover of dust-like solid solute particles is avoidedby boiling only a small portion of the recirculating liquid.When all the liquid is evaporated, as in a once-through boiler,solute contained in the liquid either must be conducted by thevapor as it leaves the boiler tubes or must be deposited on thetube surfaces.

2. The recirculation of a large portion of the boiler liquid,saturated with solute, minimizes the potential for corrosion inthe boiler by minimizing the solubility potential; such corrosionis more likely to occur in a once-through boiler in which allincoming liquid metal is a potentially corrosion aggresive con-densate liquid with very little dissolved solids to fill theliquid's solubility capability.

3. Mixing of a small portion of boiler feed liquid with a largevolume of recirculating boiler liquid results both in dilutionand in fast heating of the boiler feed. This is accomplishedout of direct contact with the boiler tube walls where corrosionand thermal fatigue effects would otherwise occur.

It has been demonstrated by ORNL that recirculating potassiumboilers have operated for very extended periods without boiler corrosionbut that once-through boilers are troubled with the above solution cor-rosion and dust carry over problems.

The problem of NOX limitation is a critical one in the design ofthis boiler. Standard successful design features for NO control includestaged combustion and exhaust gas recirculation. Staged combustion canbe provided for by the incorporation of the inlet air flow bypass annulus(SiC sleeve) around the primary combustion zone. Thus, the burning ofthe gas fuel in the immediate wake of the burner injection head, down-

18

Page 24: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

BSW^JMOCQ

UR

IZE

D

C/5C/3HB5

srHC/5V)

HOPL,

1

.

00

S5H

s-f rH

'J

— 34->rq

4-1C

CU COfa 9 PM4J* §

a o1 SH rH

rl rl0 0i& M^CO

cu

S" -Ho 30 0-in cum B^rH»-/ CO

cu3

rH O-H grH

00

Oo' X

'a

ON

-*rH

0)CO

CJ

cu3

cfl

60

iH4JCO0)

JJQ

j_5

|

P^cu3

|(-irH

•*OrH

^f

ooCOrH

CO

^ «f^rH

CU4-1CO

PS

rHCU3

)_itr*^v^^

. 34JM

\OOrH

^in

oooCM

rHOi3

B0

^w

3CX

M

4-1CO0)

PC

•CO•HCOCX

oCMSwS

CM

|

cnf*^rH

CDrl3COCQ01rl

CQ

0

4-1Q)HCM

J2~*XIrH

roOrH

X

\oCNoo

60

•tfOH

CU4-1

(3jjorH1*4

rl

3

y— N

«•HCOcx

rHCN f~*CN fci^ 0 <U

m aCM rH -H

B oo xi

£5 W HCM 00 COm o corH I-. O

cu3

CU 4-1rl CO3 V4 CJCO CD OCO CX rlcu s 3rl 53 O|X| H CO

rl rl H•H 1H -H

, ^CO x~s•H •ca XcO cdO Q

4-1 f±4x; o00 C^•H c^a> oS oo

\~saO $4

CMrH CN•• o^

vO rH

CUrH

cj3

pqcuQ

g

5rl

O 01•H 4J•P C

(3 w•

rH CU§ 1fu H

M CO•H CO

rq**^rtH

enorH

x™\ Xp-4o CNco ooCO CT\oo ^rH

mm si-CN CNrH H

01i-l34-1CO(-101px, ^§ o

rHEH fe

cO (0o o4-> 4-1CO CQ3 3cO coxi x:

j3*^

X~N XI

CO rH•Hco m(X O

x-» rH•H OCO IO Xo* <^^

fe ^ OirH CO rv_x O CM ^-^

rH gN rH 0 CQ

§ ^ S5 "oo^^^ t^ \£

J5 ^d"\O C^ ^5

O \O OrH 00 ? rH

0)M34J CU

p t £ J3< a> co

a, co§ 0) CU

}•! 4-1

co p44-1 4-1

CO 0) CD SCO H rH OO C C rH

M M ft.•

4-* S S *

c3 ^ r* r4

MX!^"X^

3x-v 4J x-x

cO pq CM•H 4JCO VO 4-1(X 0

x-v rH O(n C7\ Oo • X *OCO CO **in co ^^ vo

^^ CM N-XB «N

vO 3 CN

rH rH O inrH CM CM rH

CU 0)M O3 CO

4J Q) 14-1

CO rl S rl

CU CO S CO(X CO

§ 0) O ^4rl 4-* 0)

EH p i 14-14-1 CO

. 3 C

CO CO C rl•H iH M HQ Q

4-1 4-1r = cO cfl

CM ooi -H rH

19

Page 25: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

^-s•

o•»

H2;0ux_x

&anJMOOQ

QMNMBJDCOCOrvl§PMjgsMCOCO

tSs

1

00

wH-]

5H

o"••

CN4-1

>4-l• ^

34-1«

^N0 fa\O o

4-1CU C)-i CO3 rH4J PL,cflM 50) SP. _a o3 oH CN

t-Hno na oCO »*H

> -ax-x CUrT. LJ0 -H0 3m crin QJrH PJ

**^CO

^ (U

\0 3rH T3rH OrH g

oo

•—' Oo

rH 001& ?

Vw/

CN1 W

s -*-cfo -*sren ,?

4JCcu

•Ha•H>4-l

(4HCUOoMcumcaCcoH

4-1COcu

SC

tHtH

COrl Q(U H^ Ao 3

4-1rH COtHCO5 m

C6 -Hu cu

MvO-* T)

CU0 C

•H» rH•

0 f*0 i-i

0& 1 *

0 oCO

rH M00 <4-l

• 0)ro rt

iHtO•HMcu4-1Cfls00 rH00 rHH CU

i, -12«JJ COW

CU1 M

3co cacu ca

42 cu3 rlH PL,

tH CN n srCN CN CN CN

20

Page 26: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

stream of the primary air swirl vanes, will be rich, and combustion willbe completed in the lean region downstream of the injection ports forthe bypass air.

Forced recirculation of 1255 K (1800°F), or higher, furnace combustiondischarge gases is a difficult problem, involving expensive high tempera-ture fans. To avoid this it is proposed to operate the boiler modulesin pairs, which receive flow from the gas turbines in series. Thus, thefirst boiler will operate with slightly more than 100% excess air, whichcan be used to dilute and reduce the temperature of the primary combustiongases. For the reference cycle using low Btu gas fuel, which includesa large percentage of inert gas, the first boiler burned-gas-temperatureafter dilution of primary zone gases will be approximately 1700 K (2600°F).The second boiler will operate with very little excess air, but dilutionand burned gas temperature reduction is accomplished by the cooled burnedgas from the first boiler. The post-mixing burned-gas-temperature inthis boiler will be approximately 1866 K (2900°F). Preliminary calcula-tions indicate that with this approach NC^ emissions can be held withinEPA regulations for gaseous fuel (86 ng/J) (.2 Ib N02/106 Btu). A ma-terials list for this boiler is presented in Table 9.

HIGH PRESSURE TURBINE

The conceptual design of the high pressure potassium turbine is shownin Figure 3. This is a double-flow, single-stage machine operating be-tween an inlet condition of 1116 K (1550°F), 21 N/cm2 (30 psi) and adischarge condition of 1005 K (1350°F), 7.6 N/cm2 (11 psi). The aero-dynamic design is that of a high efficiency, free vortex turbine with asmall degree of reaction at the bucket root. Ten nozzle groups are pro-vided at the inlet, for each of which a control valve (not shown) willbe provided. The turbine angular velocity is 188 rad/s (1800 rpm), andthe bucket speed at the root of the bucket is 290 m/s (950 ft/sec). Discdiameter is 305 centimeters (120 inches)* The rotor construction isthat of discs and spacer rings joined by curvic couplings held togetherby tie bolts. Material for the buckets, discs, spacer rings and tiebolts is TZM molybdenum alloy. The bucket root centrifugal stress levelis approximately 27,580 N/cm2 (40,000 psi), and the wheel and fir treedove tail stresses have been determined to be of approximately the samemagnitude, which is estimated to be safely within the 1-2% creep stresslimit of TZM alloy for a thirty year life at 1005 K (1350°F) temperature.The connection between the end spacer rings and the A-286 shaft is bymeans of a "half barrel" type of curvic coupling, which maintains con-centricity while permitting radial differential thermal expansion be-tween the coupled parts. This construction was thoroughly proof testedin the three stage potassium turbine program^"'.

TZM molybdenum alloy was successfully used in small scaleturbines to demonstrate the potassium cycle. Scaling to 36 inchdiameter appears feasible using present technology. To attainlarger diameters would probably require the use of powder metal-lurgy and hot isostatic pressing followed by upset forging, cross

*Can be reduced to 36 inches by modularization.

21

Page 27: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 9. - MATERIALS SELECTION FOR THEPRESSURIZED FURNACE

Component

Pressure Shell

Stack

Mr Inlet

Flame Liner

Burner and Supports

Flame Liner Supports

Upper Center Head and Ports

Upper Dome

Exhaust Duct

Lower Dome

Boiler Tubes

Boiler Drum

Vapor Outlet

Lower Inner Flame

Inner Combustion Baffle

Material

Low Carbon Steel (Refractory Insulated)

, AISI Type 304

AISI Type 304

Silicon Carbide

AISI Type 304

AISI Type 304

AISI Type 304

Low Carbon Steel (Refractory Insulated)

Low Carbon Steel (Refractory Insulated)

Low Carbon Steel (Refractory Insulated)

HA-188

HA-188

HA-188

Silicon Carbide

HA-188

22

Page 28: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

23

Page 29: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

rolling and sector forging. Particular attention must be paid to thesefactors; control of MoO, smoke which issues from the surface of the partwhen forged in air, the low ductility of this alloy at temperatures be-low 500-700°F, the dissimilarity in thermal expansion between this alloyand the superalloys used for mating parts. The accommodation of thesecharacteristics along with the high strength margin advantages of TZMmolybdenum alloy will require considerable integrated development effortbetween designers, materials engineers and metal processing sources.The oil lubricated bearings are supported from cylindrical extensions ofthe horizontally split shell structure. These extensions are of suffi-cient length to accept the temperature difference between the oil cooledbearing support stations and the exhaust casing. Bearing pedestal struc-tures will support the turbine at the horizontal centerline at the bearingstations. One of these supports will permit longitudinal thermal ex-pansion. The one adjacent to the generator will be axially fixed.

To seal the rotating shaft against leakage of air or other non-condensable gas into the potassium vapor flow stream, a dynamic seal ofthe type successfully used in previous General Electric mercury andpotassium turbine designs is employed. In this seal, potassium liquidis introduced into a rotating annulus. Liquid discharging from the sealis mixed with a flow of argon buffer gas. Separation of the gas andliquid is accomplished externally and the components recycled. Practicallyno gas leaks through the rotating seal.

Design data relating to the turbine is presented in Table 10. Table11 presents a materials list. It will be noted that Haynes 188 alloy isemployed for the high temperature static parts and 304 stainless steeland low alloy chrome molybdenum steel are used where temperatures arelower.

LOW PRESSURE TURBINE

The low pressure turbine conceptual design is illustrated in Figure 4.It is a three stage double flow turbine. The rotor is constructed fromsuperalloy discs, spacer rings and shafts which are joined by boltingwith rabbets for maintaining concentricity. Superalloy buckets areassembled to the wheels by fir tree dovetails. The disc diameter isapproximately 305 centimeters (120 inches)? The turbine angular velocityis 126 rad/s (1200 rpm). Bucket root and wheel temperatures range from955 K (1260°F) to 866 K (1100°F) in the three stages. Stress levels(wheel, bucket root, and dovetail) range from approximately 12,400 N/cm(18,000 psi) in the first stage to about 24,100 N/cm2 (35,000 psi) bucketroot and dovetail stress in the last stage. These stress levels arecompatible with the estimated .2% creep limits of the wheel and bucketmaterials specified (see Table 12) for thirty years life at the tempera-tures involved.

The bearing, shaft seal, and mounting arrangement of this turbineare similar to those discussed above for the high pressure turbine.Flexible connections to the two condensers attached to the exhaust casingswill be required.

*Can be reduced to 40 inches by modularization. Superalloy discs of thissize have been forged.

24

Page 30: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

CO

CO4-1•H

V) G2; PoM CUCO MW 3 'Q CO

CO CMw a>Z v<i j Q .

032 !2*3 o

ww^COV3

aPSfXi i— 1

1;2o,J

iiA <i>CJ »-lM JS S 4Ja; oo a 'H

•H CO G i-Hs X cu pI—I (XiCOCO

o(X

1•

orH

d3T

QQ

<j

0)00(04JCO

VOCOrHi-H

rHCT\

••VOvOCMrHv»x

ONmON

^*^OmCOrH

inoorH

^ommrH

vOrHrHrH

^^fv,OSM^

«l

•cx5JH

4-1CUrH

O\CO

«

<r

COoCO

s~^

10CM

»fx.x^»*

0om

vOvO

rHrH

^~^

srooo

vOoooCO

00CM

rHCM

^^•HCOO.

CM

|

£5

»

rl3COCO0)rl

(X,

4J

CUHGM

^— (Osr

moorH

^^r**O>^^«-• *

m00rH

s~^fs^

O

m00rH

/^^OOco00

^fo

s-O0)CO

1JJrHN^X

CO

00

*0)4JCOP^

OrH

.

«

inCO

ro•

f*goo

/«N

s^

•mmN—^

co•CM00

/-•vj-tinCO

CO•

egoo

^^vO

»CMI-N

oo•oo

rH

^rH

34-)PQ

00

-^^H )fcfi

exoMQ

^»(XrH«

C

•xor-*.oo

CM•m

vO

^-^oegooS^ '

CTi•

ONsrCM

s~^or^

r-.9

srCOCM

^_^

OoHrH

CO•

mCOCO

s~\ocuCO

^x^4J

v '

CO

°n

X)0)0)ex

CO

rHCUcu

srinoCM

CMeg

« •in*

^-^srmoorHN— »*

iHf^s

•<a-

s^00

»!«>,vOrH

\OCN.

^

/^v

OvmrH

srosr

*G•HN*-

B,rlCU4-1CU

cB•HQ

ex•HH

00•

vOCM•H

CMCM

•CO

^^00

r-^CM•-H,N^

mCM•CO

CO•

vOCMrH

rHCM•

CO

^-^rHCMi-H

f«X

O

CO

-^iHN^

3

rl0)4-1CU

CD•HG

1

CO•

ONCO

00ON

ON•

o

Jf*^oo•

00CMx«/

COI*N»

•o '

mr^%

oCM

COmo

/— sO>rH

^

oosro

'G•H^«/

B

^•U*c00•Hd)

cuTJCO

rHPQ

in0*oo•

o

p*»CMCT*•

0

vO0\

•o

vOrHCT>

O

0*r~fTJ

4-1•Hi-HCfl3o-4J•H

OOCMrH

•inCMrH

y— OOCMrH•

r*^•

»nCMH

s~^ooCMrH

f*s

•mCMH

^_^oo00rH

m•

oooorH

9&SH/

0}"***x

*o(0rl

«t

4J^{uorH0)

^

rlCOiH3

I

25

Page 31: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 11. - MATERIALS SELECTION FOR THE HIGHPRESSURE POTASSIUM VAPOR TURBINE

Componen t

Inlet Casing

Nozzle Vanes

Inner Nozzle Support

Turbine Casing, Exhaust Nozzle & Scroll

Exhaust Nozzle Extension

Turbine Exhaust Scroll

Center Torque Tube

Turbine Disc

Disc Tie Bolt

Turbine Blades

Cup Shaft

Main Shaft

Shaft Tie Bolt

Cup Seal Stator

Cup Seal Rotor

Bearing & Seal Housing & Supports

Material

HA-188

HA-188 or X-40

HA-188

HA-188

AISI TP 304

AISI TP 304

TZM

TZM

TZM

TZM

TZM

A-286

M-252

AISI TP 304

A-286

2-1/4 Cr-Mo

Composition

Material

HA-188X-40AISI TP 304TZMA-286M-2522-1/4 Cr-Mo

C

.10

.50

.08

.015

.08

.15

Fe

—2.0Bal-Bal5.0

Ni

2210.510-25.5Bal

Co

BalBal---10.0

Cr

222519-15.319.0

W

14.57.5----

Mo

—--Bal1.39.8

Ti

— .--0.52.12.5

Al

—---0.31.0

Zr

—--0.08-

Other

0.35Si,0.1La

26

Page 32: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

4>

3

•e

4JO

20)0>

2Pu

OU

•sCO

I•

st

27

Page 33: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 12. - MATERIALS SELECTIONS FOR THE LOWPRESSURE POTASSIUM VAPOR TURBINE

Component

1st Stage Nozzle Inlet & Casing

Nozzle Vanes

Turbine Blades

Turbine Casings

Turbine Tip Seals

Interstage Seals

Inner & Outer Nozzle Bands

Center Spool

Stage 1 Disc

Stage 1-2 Spacer

Stage 2 Disc

Stage 2-3 Spacer

Stage 3 Disc

Stage 1 Bolts

Stage 2 Bolts

Stage 3 Bolts

Turbine Man Shaft

Turbine Exhaust Scroll

Bearing & Seal Casing & Supports

Cup Seal Stator

Cup Seal Rotor

Material

AISI TP 304

HA-188 or X-40

Rene' 77

AISI TP 304

HA-188

HA-188

AISI TP 304

Astroloy

Astroloy

Rene1 41

Rene1 41

INCO 706

INCO 706

Astroloy

Rene* 41

INCO 706

INCO 706

AISI TP 304

2-1/4 Cr-Mo

AISI TP 304

A-286

28

Page 34: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

POTASSIUM CONDENSER/STEAM GENERATOR

The potassium condenser/steam generator in the topping cycle is theinterface between the potassium system and the steam system. The ex-haust vapor from the potassium turbines gives up it's heat of condensa-tion to the water in three heat exchangers which make up the potassiumcondenser/steam generator. These heat exchangers are (1) a high pres-sure boiler, (2) an intermediate pressure reheater, and (3) a low-pres-sure reheater.

A conceptual design for the potassium condenser/steam generator isshown in Figure 5. Four units of this type are required for a 1200 MWeplant. Each module is small enough in width to be shipped to the plantsite by rail. The overall design approach was to contain the high-pres-sure water inside tubes with condensing potassium outside the tubes.The tube bundles for the three heat exchangers are located within asingle shell, and flow partitions separate the tube bundles on the shellside. The potassium condenser shell is made up of two ten-foot-highsections which would be welded together at the plant site. As indicatedin Figure 5, the flow of potassium vapor to each tube bundle assemblyis controlled with three sets of louvers located above the heat ex-changers .

A preliminary thermal-hydraulic analysis was performed for each ofthe three heat exchangers in order to estimate the required heat transferarea, total number of tubes, tube inside and outside diameters, and tubelengths. The results of the analysis, along with additional pertinentdata, are presented in Table 13. This heat exchanger is made of 304stainless steel, or Incoloy 800.

As shown in Figure 5, high pressure feed water to the boiler entersthe potassium condenser in a single pipe which penetrates the shell. Thefeedwater then flows into three headers where the water is distributed to990 tubes in parallel. The water in the boiler tubes makes two passesthrough the potassium where it is heated to the steam turbine inlet tem-perature of 839 K (1050°F). In each of the two reheaters, steam entersthe tube bundle from manifolds and makes a single pass through the potas-sium vapor where it is heated to 839 K (1050°F);. The inside diametersand number of tubes are determined by heat transfer and pressure dropconstraints.

POTASSIUM DUMP TANKS

The potassium storage or dump tank is shown on Figure 6. Four (4)separate tanks have been employed in the plant conceptual design. Thisnot only reduces the quantity of potassium in a single container, thusdecreasing the risk from a major spill, but allows purification of potas-sium (r.e., gettering of oxygen'from the potassium by hot trapping) inone container while others are in.the normal operating mode. It furtherprovides flexibility in plant operation if maintenance on a particularunit is-necessary.

29

Page 35: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

aU i_LU! .jui u -^lnllW;

ooOS

01Ctt)O

M11in

m•oocj

§•HCOCO(0AJO

CU

in

Q)

00

30

Page 36: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

I•

CO

•o

M0)C0)O

CO

0)COCcu•oo

CJ

•rlcococfl4Jo

PH

Q)

OOCM

toO

•O01

3cr01

cocu

CM

rH

3

Boile

r I

o0rHr-H

vOVOOO

/-•N

O0rHrH

VOVOOO

«--x

OorHrH

VOVOoo

s~~\

o*^s

•t•

exacuH

a5•HCOCOCO4-10

PH

CM

VO

rH

CM

mvO

i-H

CM

m

s- \

TiCO

\^r

CM

~S5

•COCOcuto

PH

F3y•HCOCOCO4-1O

(10,0

00)

in

vOm

oo0

o\rH

mP-.vOm

CDoocTrH

m

vO

rH

•M1

«\

<4J.MH

CUO

• FTiH o

33 CN4-1

£ *4H3 1•H toCO 42CO ~-s.« 34-1 4->O pq

coorH

X '

r--rH

rH

CO

ao~*orH

XCOCM

CM

mvO

/— NOsorH

X

O

rH•>—s

VO0CO

s-*.

34-1

N^

M

a)

Ma)

*-Mco(3o5j^H

4->

O

OO

i-H

vO

0000in

CMooin

/— x

ovO

COOsin

/-X.

PHox_x

<U

34-1COMCUP,

§H

4-JCU

•-HCM

°CM33

0morH

OSCOoo

oinoi-H

OSCOoo

CDmorH

COCO

s—\

O^~s

a?to4JCOrlCU

§ta-

rn

4-1cu

rH4-130

OCM

33

mrH

VOco

OS

rH

rHrHi-H

OSrH

00OrH

C

^**

ON»X

•I

H•

£5

<00)S•

60OrJ

CM

r-H

i-HrH

OovO

rH

O0VDCO

CM00sj-CM

s~\cO•HCOp.\^

CN12;

A

0)rl

COco0)to

PH

4-1CUHtiM

OCM

33

ininrH

orH

CD

in

CM

CO

mrHmco

CM

CM

s~\CO•HCOCir

VI

IsA

cuto

coco0)to

PH

4J0)

rH4-13O

OCM

CM

inmmrH

COrH

vO

o

m

mCMmCM

H1

M

'Ift

<4H

CUO <~v

CJ pL|

O

• 1HCM

• 4-Jffi <4H

rH to

Cfl "*"*to 3CU 4J

CD ^— '

m

i-H

m

o"

rH

m

CM

ino

CM

H

^\•

C•H

§

•CO•HQ

CUT3•HCO

M

0)

•§

H

o"O

CM

00C

om

inCM

rH

00rH

CO

00

O

COoCM

/— V

•C•H>— '

•i•

cfl•H

CU

•r{CO4-13O

0)

•§H

inCMrH

mCMrH

0

Os

CO0)

"3H

morlQ)

jQ

1

oo

vO

rH

00

VO

rH

COOS

CO

00CM

<

4J

<wx

J24-160CO>i-q

01

H

0in

mmCM

rH

in

vo

i-H

o"orH

CMrH

CMrHi-H

/-N.

N4-1

14-4

N6

nT0)

<

•£— I

•33

HITJ•HCO

PCOCU4-1C/3

0O

mrH

mooOsvO

oCOCMOs

oorH

COooco*OS

COin

*^^J3rH^~s

60

^4-1JS60•HCU

CU

3H

.OOrH

00COCO

vOOi-H

•OOrH

X

OSoo\^

COrHrH

>£>0rH

XvO

o\

rHrH

x"^to

^\-S

CO

•k0)

COPi

»j

orHLX4

OCM

X

CM CO in vo oo os O CM co m vo

31

Page 37: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

vD

0)

3Ml

32

Page 38: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Storage tanks are sized to hold sufficient liquid to adequately fillthe system. Since potassium has a high affinity for oxygen, it will re-move this gas from the internal walls of the piping system and components.In this sense, it is very desirable to hot flush a liquid metal loop withpotassium. In a large two phase system containing a recirculating typeboiler, the boiler tube bundle is normally hot flushed at 533 K (500°F)and a gettering cycle then runs in the dump tank after the boiler isdrained.

The gettering or hot trapping cycle in the dump tank consists ofelevating the potassium to 1033 K (1400°F). This is accomplished byheating the dump tank and holding the above temperature for about 24hours. Potassium samples are extracted periodically from the tank andanalyzed for oxygen content. When the oxide level is acceptable, thegettering cycle is complete.

Since the dump tank is not normally designed to contain enough potas-sium to flood both the boiler and condenser tubes at the same time, aseparate hot flush cycle is conducted on the condenser in a similarmanner to the cycle conducted or the boiler. Condenser tubes are heatedto 533 K (500°F) with auxiliary heaters during the flushing operation.

The vapor piping between boiler and turbine and turbine and condenseris not hot flushed due to its large volume and complications which wouldresult from flooding the turbine with liquid. As a result oxygen pickedup from these components during -initial operation of the system must beremoved by the hot traps installed in the boiler and condenser. Thesetraps provide a continuous gettering function during system operation.System purity is continuously monitored by in-line oxygen sensors. Asudden increase in oxygen level after the system has been in operationnormally indicates a leak in the condenser region where the pressure isbelow atmospheric. In this event, the complete system is dumped to thestorage tank and leak tests conducted to determine the location and ex-tent of damage.

In the case of small tanks electric heaters are normally employedto elevate the tank and its potassium inventory to gettering temperature.With large tanks this does not appear to be an economical method andaccessory air heaters, utilizing clean fuel are contemplated. These maybe either direct or indirect fired units. The storage tank then requiresan insulated jacket through which the hot air can be conducted and inturn transfer heat to the tank walls by convection.

The solubility of oxygen in potassium increases with increasing tem-perature. Its presence in solution has an adverse effect on the wallsof material conducting the fluid. The higher the concentration thegreater will be the corrosive effects. The storage tank provides anexcellent point to remove oxygen from the potassium, and thus, it isequipped with a gettering material such as zirconium which has a higheraffinity for the oxygen than the potassium at elevated temperatures.The zirconium is normally installed in the tank in the form of multiplesheets in a closely spaced array, or chips installed in a wire mesh basket

33

Page 39: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

may be utilized. In either case the design must allow for a maximum ofzirconium surface area exposed to the potassium. From experimental datait has been concluded that one part of zirconium to 25 parts of potassiumby weight will provide a capability to getter oxygen from 800 ppm to< 50 ppm. Such a capability in a sealed system should meet normal 30year getter life requirements. Of course, care of and monitoring of thegetter are important to assure effective getter capability under ex-tenuating circumstances. Oxygen concentration in the system is usuallymaintained below 20 ppm. After a hot flushing procedure, concentrationof 50 ppm or higher can be obtained. The storage tank contains a samplingsystem whereby potassium can be removed for laboratory analysis. Thisis done prior to and after a hot trapping operation. Approximately 8to 16 hours is normally required to decrease the oxygen concentration toacceptable levels.

In addition to being a storage tank from which the system is filled,and part of the potassium purity control system, the tank also acts asnormal and emergency dump container. Valving separates the dump tankfrom the two phase system during normal operation. In the event of aleak in the potassium system it is sometimes necessary to remove thepotassium from the entire system as fast as possible. The system isdesigned for gravity drainage of all components and piping to the dumptank. Separate drain lines from major high temperature components suchas the boiler are provided and sized to handle the dump via gravity ina short time. The tank is equipped with special thermal shock resistingvalves on these lines, and thermal sleeves at the tank nozzles are de-signed to eliminate failure under such conditions. An equalizing covergas system insures that cover gas pressure will not interfere with gravitydrainage. Sump tank temperature is held at some intermediate temperatureduring operation so that thermal shock during an emergency dump will notbe excessive.

For additional safety, the storage tank may require individual sec-ondary containment. In any event, an isolated area, which can be sealedoff to prevent the entrance of air and ventilated to the air scrubbingsystems, appears desirable. Since the tank must be at the lowest pointin the system, a concrete lined pit for each tank appears practical andfeasible.

34

Page 40: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

PLANT CONCEPTUAL LAYOUT - CYCLE //I - PRESSURIZED BOILER SYSTEM

The conceptual plant layout of a 1200 MW electric generating plantis shown on Figures 7, 8, and 9. This layout is predicated on the useof pressurized gas fired boiler modules and is a ternary cycle utilizingpotassium vapor turbines, steam turbines and gas turbines to generateuseful electrical power. Cycle #1 utilizes a single potassium highpressure (21 N/cm^) double ended turbine and two low pressure (10.5 N/cm^)double ended potassium turbines each driving generators. Two gas tur-bines driving compressors for boiler combustion air supply and electricalgenerators are employed. A single multi-stage steam turbine generatorprovides the remainder of the electrical power.

Potassium System. - Prior to attempts to prepare a plant layout somebasic rules governing arrangement of potassium components were establishedas follows:

1. The potassium system with all of its components would be housedin an area separated as much as possible from the steam portionof the plant by fire resistant walls. This area would be keptas small as practically possible since it must be ventilatedthrough a scrubbing system to remove potassium oxide smoke inthe event of a leak.

2. Gravity drainage of potassium from components and piping to thestorage tanks is required.

3. Potassium vapor piping runs from the boilers to the high pressureturbine should be as short as possible. This will keep heatloss to a minimum, keep pressure drop low, reduce thermal ex-pansion problems, and keep high temperature piping and insula-tion costs to a minimum.

4. The high-pressure, high-temperature gas piping from the boilersto the gas turbines should be as short as possible. The reason-ing in Item 3 above applies here also.

5. The low-pressure potassium ducting from the high-pressure turbineexhausts to the low pressure turbine inlets should be as shortas possible. The same reasons as Item 3 above pertain.

6. The potassium condensers should be placed as close to the lowpressure turbine discharge as possible.

7. With short, large-diameter vapor piping runs, expansion loopsbecome impossible. Therefore, adequate and reliable expansionjoints (bellows type) must be developed. Bellows joints mustbe installed in a manner to result in minimum forces on theturbine frames.

8. Turbine manifold inlet nozzles are assumed to be fixed points.

35

Page 41: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

oocooooo-"JOltMt TQWtfiS >

OOOOOOOO

I I

rOO

1°fo q00

_JL

O-— cu,i;

(~

Figure 7. Potassium Pressurized Boiler Combined Powerplant (SK 707E811)

36

Page 42: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

sxss

Figure 8. Potassium Pressurized Boiler Combined Powerplant (SK 707E813)

37

Page 43: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

oow

4J

§

a)g

PH

0)C

M0)

•a0)N

wCOa)

0}COa)

CTi

CU)-i

00•H

38

Page 44: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

9. Boiler discharge vapor nozzles are assumed to be fixed points.The size and weight of these units makes floating type supportsimpractical.

With the above guidelines, initial layouts of the potassium systemand gas turbines were made, shown on Figure 10. This layout assumed theuse of four (4) gas turbine/compressors with the eight boiler modulesplaced in pairs between the turbines. Subsequent changes (increases) inthe boiler pressure made possible the use of a conceptual design gasturbine with a 15:1 compression ratio. Since two of these machines wouldprovide the necessary air flow for all boilers, nesting of the eightboiler modules together with gas turbines outboard of this nest was pos-sible. This considerably reduced the length of boiler to turbine vaporpiping.

Low-pressure potassium turbines were placed directly above theirrespective condensers (i.e., one condenser for each low pressure turbineexhaust hood, total of four). High-pressure turbine exhausts dischargingdownward were taken under the turbine floor and brought up into the bottomof the low pressure turbine inlet manifold. By off-setting the turbines,adequate space for this large ducting was available, and interferencewith the below floor condenser/steam generators eliminated.

Vapor piping from the boilers to the high pressure turbine was es-tablished at an elevation for adequate overhead clearance on the turbinefloor, and boilers were elevated to match their discharge vapor nozzleswith two main vapor headers which enter the turbine manifold at the threeand nine o'clock positions.

Although not shown on the layouts, consideration will have to begiven to bypass ducting .and valves which would allow operation of the twolow-pressure turbines in the event a high-pressure turbine outage isencountered during plant operation. Under these conditions boiler firingrate would be reduced to provide the lower pressure vapor.

A by-pass system for shunting potassium vapor directly to the con-denser/steam generator should be considered, at least for initial orpilot plant designs. This will allow considerably more flexibility instartup, system check-out and general plant operation. It does, however,impose additional requirements on the condenser design (i.e., condensermust be designed for maximum boiler temperature) and requires additionalvalves, piping and control.

Potassium piping (liquid) from condenser wells to pumps via flow-meters back to the boiler inlets is not shown. Boiler drain lines, dumptank system fill lines, and dump tank charging and interconnecting headersare not shown. These systems present no major problems, however, largevalves and expansion loops or joints will be required. Large liquidsodium valves are presently under development as a part of the BreederReactor sodium systems and knowledge gained there will be utilized inthe selection of potassium valves. The same is true of flowmeters.Electromagnetic types are most commonly used.

39

Page 45: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

oCO00Pi

4J

§rH

Ba

M01

•O0)

COD)0)M

(Xi

60•H

40

Page 46: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Potassium pumps are indicated on the layouts. These are of thecentrifugal type as manufactured by companies for the LMFBR program.Four (4) pumps are indicated on the layout. Each would have a capacityof ^ 0.28 m-Vs (4500 gpm) at adequate head to feed the boilers. Muchlarger pumps have been built for sodium service and the selection offour units rather than two was primarily based on ability to provideadequate power turn-down and redundancy for reliability.

The extent of the heating of potassium piping will depend on operat-ing procedures. Electric heating has normally been employed utilizingcalrod type heaters beneath insulation. Since potassium freezes at 337 K(147°F), any stagnant potassium not capable of receiving heat input fromthe main stream would require .continuous heating and temperature monitor-ing. Assuming the piping systems (main liquid runs) are filled from thestorage tank at 533 K (500°F) and circulation is started shortly there-after, heating of main runs may not be necessary. Preheating all potas-sium containing lines does assist in the baking out of surface absorbedgases from the containing materials during initial evacuation of thesystem (i.e., removal of air). In GE's small 3 MW experimental plant allpiping was preheated. This included a hot gas system for preheating thepotassium condenser. If necessary, auxiliary heaters might be used toheat the water in the condenser tube bundle prior to startup. After start-up this system could be shutdown. Preheating of the condenser will alsoreduce the possibility of failure due to thermal shock at startup.

Other systems not shown in the plant layout but included in costestimates are as follows:

1. Vacuum system for initial evacuation of the potassium systemand removal of noncondensibles from the potassium system (con-denser) .

2. Separation systems for removal of potassium vapor, liquid anddust from the noncondensible gas removed from the condenser.

3. Argon reclamation system. The potassium turbine requires a gasbuffer seal between the potassium system and the bearing lubesystem. The argon gas entering this buffer flows across labyrinthseals to the bearing oil sump and the potassium slinger sealsystem. The argon gas must be removed from both of these sys-tems to prevent a pressure buildup in either system which wouldresult in potassium being forced into the oil or vice-versa.Due to the large quantity of gas required, systems for recoveringthe gas from the potassium system and the oil system are required.Removing the gas from the potassium system requires a complexseries of heaters, coolers and filters to prevent plugging ofcomponents and piping with frozen potassium. Removal of oilvapor from the gas require coolers, separators, filters, andsieves. After the gas has passed through these systems, itenters a compressor inlet receiver tank. A hermetically sealed(diaphram type) compressor recompresses the gas so that it canagain be fed to the turbine buffer seal. The recovery of gas

41

Page 47: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

from the oil system has never proven to be economically success-ful due to the inability to remove all oil vapor. The use of aface type seal on .the oil side of the potassium/oil gas. bufferwould eliminate gas leakage into the turbine oil sump and eliminatethis problem.

Each potassium turbine will be equipped with a lube system and potas-sium system to provide potassium specifically for the slinger type potas-sium seal. Slinger seal potassium systems are indicated on the layoutdrawing, located on the first floor beneath each potassium turbine.

The safety and environment problems associated with the operationof a potassium vapor system require special attention. During the initialdesign of General Electric's 3 MW Potassium Turbine Test Facility theinsuring agency along with G.E. established design criteria for safestorage, handling and general operation of the facility. These criteriawere briefly as follows:

1. No sprinkler systems were to be installed in potassium contain-ing areas.

2. All potassium containing components or piping should have sec-ondary containment. In the case of the boiler, the furnace-boxwas construed to be the secondary containment. In the case ofcomponents and piping located inside of the building structurethe building was construed to be the secondary containment.

3. Secondary containment areas should be vented to the atmospherethrough a scrubbing system to prevent an excess of potassiumoxide smoke from being emitted to the atmosphere. Scrubbingsystems should be 98% effective.

4. Instrumentation for the detection of airborne potassium oxidealong with interlock control systems so that automatic failsafe shutdown results were required.

Safe procedures for handling and storage of alkali metals have beenestablished for years. Experience gained with EBR-2 fast breeder re-actor experiments in the United States and Dounreay fast breeder reactorexperiment in Great Britain are good indications of the feasibility ofhandling large quantities of alkali metal in a safe fashion. The worldwide commitment to the development of liquid metal fast breeder reactorsfurther exemplifies the confidence level in the handling and storage ofthese materials.

Although GE experience with the operation of a 3 MW plant for approxi-mately seven years resulted in no. serious injury to operating personnel,major damage to equipment or pollution of the atmosphere, to infer thatrisks are not involved in the operation of such a system would be mis-leading. Many small system leaks did occur during the operating lifeof this research and development facility, however, the safety equipment(i.e., oxide smoke detectors and water wash type scrubber) performed theirjob in a satisfactory manner.

42

Page 48: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

The safety problems involved in a LMFBR are far greater than thoseinvolved with a potassium topping cycle since radioactive material ispresent. The general philosophy of safety employed in the design of apotassium topping cycle would, however,be very similar to that used ina LMFBR Power Generating Plant. The use of Nuclear codes and RDT standardsare not necessary, however the design of high temperature componentswith emphasis on cyclic thermal stress analysis, exacting quality controlin the area of raw materials, fabrication, joining, testing and cleaningare required. GE has established computer programs covering thermalstress analysis and specifications for establishing quality control inall of the above areas.

Potassium Oxide Scrubbers. - A potassium oxide scrubber installationis indicated on the proposed 1200 MW Plant Layouts. Duct work to thevarious secondary containment areas is not indicated, however, these wouldbe included. The scrubber capacity will depend largely on the volume ofsecondary containment areas which it services. The type of potassiumboiler used and operating procedures for emergency shutdown will alsoaffect the scrubber system.

For instance, a pressurized boiler experiencing a tube leak willallow the furnace gases to enter the potassium system, since the gaspressure is much higher than the potassium pressure. This inward leakageof gas, including some air, must be indicated and stopped as soon aspossible or potassium system pressure will drive toward the boiler gaspressure, resulting in the eventual rupture of the potassium containmentsystem at the weakest point. Due to the large volume of the boiler tubebundle vapor piping and condenser such a pressure buildup would be veryslow (i.e., in the case of a small tube leak). Automatic pressure con-trols would have plenty of time to actuate pressure dump systems to avoida pressure buildup above boiler and loop design pressure. The oxygenadmitted during this process will rapidly combine with the potassium and,if substantial, may result in an oxide plug at some point in the system.It is, however, expected that this oxide will remain in the boiler andthat a gettering cycle on the dumped boiler potassium alone would be re-quired. Stoppage of the fuel supply to the boiler and venting the gaspressure to the atmosphere, plus closing off the compressed air supply,would bring the boiler to atmospheric pressure. Assuming that the potas-sium vapor pressure at this time is still above atmospheric pressure,potassium vapor or liquid (depending on the location of the leak andpressure) would start to leak into the combustion chamber and, assumingoxygen remained in the chamber, a fire and the resulting oxide smokewould be emitted from the open vent valve. If this valve were closedat this time, along with the inlet air valve, the fire would stop assoon as the oxygen was used up. A buildup of pressure'in the combustionchamber might occur, however, it is doubtful if it would come near thedesign pressure of the combustor casing. After a suitable cool downperiod, the vent valve would again be opened and the combustion chambervented to the scrubber. In the scheme outlined a large scrubber capacitydoes not appear necessary for the boiler. In the case of a combustorboiler designed for operation at atmospheric pressure, the same systemcould be utilized as long as the combustor (furnace box) is designed

43

Page 49: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

airtight and capable of withstanding maximum potassium pressure obtainableduring normal operation (15 psig).

The size of the scrubber required is, therefore, determined largelyby the secondary containment volume of the building. Along these linesmanufacturers were contacted to determine the size and cost of oxidescrubbers. The cost estimates in the section ECONOMIC AND TECHNICAL EVAL-UATION (p. 61) include 2 - 550,000 CFM venturi type scrubbers. This typeof unit was selected for its high scrubbing efficiency. These units wouldprovide ventilation for the building area containing potassium componentsand piping. In the event of a potassium leak, water pumps would be auto-matically started as directed by sensing instrumentation located at appro-priate points throughout the building. A closed loop water system wouldbe utilized and a storage tank or pond, where the water could be neutral-ized, would be provided.

A leak in the potassium condenser/steam generator may appear to bea formidable problem at first glance. However, proper design, utilizingknowledge gained from years of experimenting with water/alkali metalreactions, plus adequate control systems and operating procedures greatlyreduce the operating risk. Fraas discusses these problems in reference8 and concludes that the risks are manageable.

Turbo-Compressors. - The turbine compressors shown on the plantlayout drawing are advanced gas turbine units which are presently in theconceptual design stage. As a packaged unit, these turbines contain in-let air silencer, starter, compressor (15:1), corabustor, turbine, generator,exhaust ducting with provisions for a waste heat exchanger and exhaustsilencer. Modification to these units would be necessary so that com-pressor discharge air can be ducted to the boiler combustor, and hot gasleaving the boiler ducted to the turbine inlet. Due to the high tempera-ture and pressure of the gases leaving the boilers, piping design mustbe done carefully.

The water economizer and feedwater heater are located in the turbineexhaust gas stream. Water piping to and from these heat exchangers isnot shown. Routing, however, will be based on keeping as much of thispiping out of the potassium areas as possible. Final entrance to thepotassium condenser/steam generator must, however, be made in the potas-sium area.

Additonal thought will have to be given to the number of gas turbines/compressors to be used from the standpoint of plant turndown and outagefor maintenance.

Steam System. - The steam system, with the exception of potassiumcondenser/steam generator, presents no major design problems. The turbo-generator layouts, along with condenser, condensate pumps, heaters, boilerfeed pumps, water treatment equipment, etc., were taken from a proposalrecently prepared by GE Steam Turbine and Generator Division for a 750 MWsteam plant.

44

Page 50: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

The steam condenser cooling water system utilizes mechanical drafttype wet cooling towers. Vendors studies of the requirements in thisarea resulted in the mechanical draft type units; although the initialcost of these units is less than a hyperbolic tower, operating and main-tenance costs would be higher. Further study in this area appears neces-sary prior to a final selection.

Fuel System. - The layouts are predicated on the use of a clean fuel.(low Btu gas) and indicate a main underground supply. The location ofthe coal gasification plant on or off the plant property was not con-sidered.

Service Areas. - The plant layouts indicate the type and locationof various services. These include office, maintenance shops, parkingareas, railroad spurs, etc. The land area required for the completeplant (not including a coal gasification facility) was estimated at1.4 km2 (350 acres).

Pressurized Fluidized Bed Boiler PowerplantConceptual Design

POTASSIUM BOILER

In Figure 11 the design concept for the pressurized fluidized bedpotassium boiler for cycle number 2 is illustrated. The boiler unitshown in the drawing, which is one of eight boiler modules required forthe 1200 MW system, consists of four vertically stacked beds. Thesebeds operate in parallel with respect to the air, coal, limestone, andpotassium flows. A tabulation of values for the major design parametersis presented in Table 14.

The potassium flow circuit of the boiler consists of 120 layers ofinvolute tubes in each bed, each layer composed of 75 curved tubes,approximately seven feet long joined at their outside ends to verticalliquid feed header pipes and joined at their inside ends to a commoncentral vapor discharge drum. The tubes are one inch O.D. located bothhorizontally and vertically on two inch centers. An effect of tubestagger can be achieved by vertically offsetting alternate tubes in eachlayer. Because of the high sensitivity of the potassium vaporizationtemperature to pressure level at the 1033 K (1400°F) inlet vapor tem-perature level, it is important to minimize boiler tube pressure drop.A pressure drop of 3.4 N/cm2 (5 psi) will result in 55.6 K (100°F) dif-ference in vaporization temperature. Thus a high pressure drop in theembedded tubes will result in local overtemperaturing of the tubes. Theproposed concept avoids this problem through the use of short horizontaltubes, low tube mass flow rates, pumped recirculation boiling (as opposedto once through boiler which requires increased tube pressure drop), andindividual orificing of the tubes at the inlet end. By proper orificingthe effect of the gravitational head differences between tube layers canbe cancelled. Insulation will be provided on the vertical feed tubes toprevent overtemperaturing of these tubes in the lower portion of the bed.

45

Page 51: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

•o<ato

oPU

46

Page 52: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 14. - POTASSIUM PRESSURIZED FLUIDIZED BED BOILER

1033 K (1400°F) Potassium Turbine Inlet Temp.

1200 MW (8 Modules)

1. Total Heat Transferred toPotassium

2. Total Potassium Flow Rate

3. Total Combustion Air Flow Rate

4. Bed Pressure

5. Bed Temperature

6. Bed Discharge Gas Temperature

7. No. of Beds per Module

8« Bed Outside Diameter

9. Outside Diameter of Central .Vapor Disch. Header

10. Bed Depth

11. Embedded Tube Configuration

12. Total Heat Transfer Surfaceper Bed

13. Tube Heat Flux (Avg)

14. Heat Transfer Surface/BedVolume

15. Superficial Velocity thru Bed

16. Fluidized Bed Heat TransferCoefficient, U

17. Coal Feed Rate per Bed

18. Limestone Feed Rate per Bed

19. Carbon Burn Up

1.74 GW (5.95 x 10 Btu/hr)

846 kg/s (6.7 x 106 Ibs/hr)

884 kg/s (7.0 x 106 Ibs/hr)

91 N/cm2 (132 psia)

1200 K (1700°F)

1200 K (1700°F)

4

3.66 m (12 ft)

1.22 m (4 ft)

6.71 m (22 ft)

Involute, 1" tubes on 2"centers, 120 layers

1533 m2 (16,500 ft2)

35623 W/m2 (11,300 Btu/hr-ft2)

27.1 m2/m3 (8.25 ft2/ft3)

1.07 m/s (3.5 ft/sec)

284 WnfV"1 (50 Btu/hr-f t2-°F)

2.6 kg/s (5.8 Ibs/sec)

0.4 kg/s (.9 Ibs/sec)

Intra Bed

47

Page 53: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

The pressure difference between the bed and the potassium vapor issufficiently great to cause a compressive stress level in the centraldrum above the thirty year life stress rupture limit of 304 stainlesssteel. It is proposed to reinforce this drum internally with superalloyrings. The upper spherical end of the drum will be Havnes 188 material.

The selected level of superficial velocity of the combustion gasesthrough the bed (1.1 m/s) corresponds to a value found by BCURA to becompatible with high uniform bed heat transfer, good combustion effi-ciency, and low NOx and 862 emissions. It has also been determined thatthe 1200 K (1700°F) bed temperature is compatible with the 91 N/cm2(9 atm) pressure level from the standpoint of limestone calcination.

Although higher values of superficial velocity were considered, withcorresponding reductions in bed diameter, it was found that no costsaving resulted because of the following:

1. The bed volume is controlled by the boiler tubing surface re-quirements. Thus, a reduction in bed diameter is offset by anincrease in bed height.

2. The required transport disengaging height above the bed increasesas superficial velocity increases.

3. Increased bed height results in cost increases resulting frommore tube to header joints and greater length of vapor dischargeheader.

Design details relating to coal and limestone feeding, CaSO^ removal,air injection, and combustion gas discharge have been discussed withvarious contractors subsequent to completion of the drawine of Figure 11.Their critical comments are considered very valuable and are summarizedas follows:

1. Several feet of bed "free board height" should be provided be-tween the top layer of embedded tubes and the gas dischargeports, in order to avoid overflow of bed material into the gasdischarge. It was stated that since the assumed level of bedheat transfer coefficient is lower than test values they haveexperienced, the bed depth may be reduced somewhat to achievethis free board height without significant change in the over-all boiler module height.

2. Mr should be injected at the bottom of the bed through "mush-room" type injection nozzles. Coal feed should be introducedfrom the side of the bed into the bed space immediately abovethe air injection nozzles. One coal feed port for every tensquare feet of bed cross sectional area is a good "rule ofthumb".

3. Limestone should be introduced near the top of the bed and re-moved from the bed through openings in the air injector nozzleplate.

48

Page 54: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

The arrangement of the f ] uidizc.d bed boiler is shown in Figure 12,indicating external piping for the conceptual design. A materials listfor this boiler is presented in Table 15.

POTASSIUM TURBINE

A conceptual design for the potassium turbine for cycle number 2 isshown in Figure 13. The construction features, bucket and wheel stresslevels, disc diameters, etc., are very similar to those of the low pres-sure turbine for cycle number 1. This turbine has four stages as opposedto three for the latter design. Table 16 summarizes some of the designparameters. The first stage metal temperature is somewhat higher (about33 K) than for the cycle number 1 low pressure turbine. However, themechanical design appears to be comfortably within the capabilities ofsuperalloy materials. In a final design it may be found desirable to.incorporate condensate extraction features (grooved buckets, casing ex-traction ports) in order to maximize efficiency. The materials for thisturbine are the same as for the low pressure turbine of the pressurizedboiler cycle, with the additional fourth stage having,the same materialas the third stage shown in Table 12.

POTASSIUM CONDENSER/STEAM GENERATOR

A conceptual design of the potassium condenser/steam generator isshown in Figure 14. The overall design, including tube sizes and totalnumber of tubes, is the same as that described in the section PressurizedFurnace Powerplant Conceptual Design (p. 14). The tube lengths, and hencethe total heat transfer area, are larger in order to accommodate the higherpotassium condenser heat transfer rate for this cycle. Design data forthis component are presented in Table 17, and like the other condenser/steam generator, this component is made of 304 stainless steel or Incoloy800 if stress corrosion cracking is considered to be a problem.

PLANT CONCEPTUAL LAYOUT - CYCLE #2 (PRESSURIZED FLUID BED BOILER)

The conceptual plant layout of a 1200 MW electric generating plantis shown in Figures 15, 16, and 17. A pressurized fluidized bed boiler(8 modules) is utilized along with potassium vapor turbines, steam turbinesand gas turbines, all driving electric generators to form a ternary cycle.Cycle //2 utilizes two potassium low pressure (10.5 N/cm^) double endedturbines each driving generators. Four gas turbines driving compressors(9:1 pressure ratio), to supply boiler combustion air and also driveelectrical generators, are also employed. A single multiple stage steamturbine generator provides the remainder of the electrical power.

Potassium System. - The basic rules for the potassium system arethe same as those outlined for the pressurized boiler cycle. Since fourboiler modules are required for each potassium turbine, these units havebeen nested together so that potassium vapor piping can be kept as shortas possible. The gas turbines have been located outboard of each boilernest to keep hot gas piping as short as possible. A layout of thefluidized bed boilers with separators for collecting unburned fuel and

49

Page 55: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Figure 12.' Potassium Pressurized Fluidized BedBoiler Piping (SK 707E799)

50

Page 56: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 15. - MATERIALS SELECTION FOR THE PRESSURIZEDFLUIDIZED BED BOILER

Component

Pressure Shell

Bed Support Plate

Boiler Tubes

Upper Vapor Drum Support

Center Vapor Drum Support

Vapor Exhaust

Upper Pressure Head

Center Vapor Drum

Bed Discharge Tube

Fuel Supply Tubes

Material

Low Carbon Steel (Refractory Insulated)

AISI Type 304 or TP 310

AISI Type 304

HA-138

HA-188

AISI Type 304

AISI Type 304

AISI Type 304

Low Carbon Steel (Refractory Insulated)

AISI Type 304

51

Page 57: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

52

Page 58: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

2OM</>

§

CN

O

I•

i-H

H

0)

SP4JCO

0

•-HrHx^

If)

0ON

s***CO*CNi-Hs_x

5ON

/^vON

COrH

00ooON

/— x0O•o-rH*~s

COCOO

/— \

o>*

«

a?^434Jnj^40)aQ)

H

4J0)rHBM

vOON•

CO^^

mP^•

CN

s~^i-HCO•

vO\^

inCO•

O-

s-f**

CO•

ON

i-Hco•

vO

x™\00rH•

ini-H^^

-a-•

orH

x-»cfl

CO

V.X

CN

|

25

»0)^43COCOcu}4

p-4-1<U

rHCM

x*%p^»in^^x

P**oCN

|inv-/

oCN

/— \

m•vt

f>^O<N

/— Vpx

ms-/

OCN

x-\0Oco.

JO_J^^\~S

CO•CO

^•k

0)4J

.pi^

i-Hfa

/-N

CN

v^X

CN00CO

2

^\CNCOv»^

CN00COst

/— \CNCO

CN00CO

^^CNCO\*^

CN00CO

x-s43^^

•uPQN»X

00

•>-)•t

a.onQ

>.aCQ*c4-»

x-^ocooo^^

00vOCN

/— s0CN00>»x

OmCN

X-\

O

!"•»

inCOCN

/^\OCN

v^

ON

CN

s~**O0)ca

• .•U

^^/

CO

aM

•oCU0)(Xto

rH010)

x-%0\0CNs^ /

rHCO•m

X"N

^^OOI-*N»X

s•

**

x1^CO

9

0

rH

^

«^CO•«*

*--\

•mmrH<^inON

CO

/-N

•(3, 1*M

*^

aA

rl0)4-1d)ic3•HQ

O.•HH

X-N

f^CNl_^v-/

COCNCO

x-\»^CNrH>^

rH

ro

/~\eg•

COCNi-H

^COH

CO

^— \vO•

ON'rHrH

•—X

O•

CO

^"\•

B*M

S-

s•t

Mo>4-1cuIi•HQ

1

y-^rHSt^ /

"*

O•

i-H

X"Nm•

CNCO^x

CO00•

0

/-N

00•

coCN^^

ovO•

0

/-NON•

r^rH*M*

m"» *

•0

x-^•

5•n\_x

S•k

4JX00•H0)

*H)•ocstHpa

vO

oo•

0

0

•0

COCOON•

0

vOON•

O

>,"4J•Hf—t

cd£4J•Ha

53

Page 59: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

HP! iK-5±Umh. — I , ,.- "LJ_.J_ =r-e—I

•H

tr

n)Ma)Ca)O

(U(0

a)•oao

•H CO(n aoto OS

O tMPL. ^

00

54

Page 60: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

wH-3i™

nWcq

Qw(SjIN)1 1

u^ 1

"—v

§r *n

tS3M

SCO

r--i

Sc^

.

sr"S

/«v

CM O=*te O

iH

§ 2vOvO00

/»-<^

rH O=S= O

rH35 rH

<u & ^•H

*O C \OO ctf OOa rH

PUMO CO4-1 SCO g

0) OC 0CU CNO rH

H o r C X - N0) U-l Q) O4J rH OCO T3 -H rH

<U O rHM f-i PQ v-^(U -HCO 3 vOC CT VO(U CU 00

Co to

CJ Q)

§ 3•0

•H Oto atocO -*

oPi

£"0N^x

KXJ

•I

•a§HQ

— j•H

COCOcO

oPi

^ .

~&•

CN

invO

•iH

/ N>Hf

•CN

x-'

mvO•

rH

s- .+3-•

CM

mvO•

rH

-

CO•HCO

N^

CM

U

-x^

^M

•COCO0)

pi

g3•HCOCOcO•MoPi

X-N,

oOO

OrHN«

«?r^vOm

o0oorHNv*/

inP«N-vOm

s— N

OOO

cTrH•wx

m*r^vOin

rH1

CMI

2j

„«

14HU-l<uoU

• p4H «

• 133 CM

4J

§ IM1•H Mco x:co --N.co 34J 4->O PQPi ^

00 VOO OrH iH

X Xr*N> -3"O <T»CO •. O

S^X

O^OO rHCO rH

" VO^O

oo"O XrH

COX O

Om •• rH

ps,CO CMf^ rH

X^> X-N

CTi vOO OrH rH

M id

m <rvO vOrH O

H ^ tt—1^^^* ^^^

rH -3-*1T COCO iH

rl

•^x^

3 X-NIJ *J

PQ fXi!N r* «*s

S rHpTl S^^

* CO0) ""*••».4J. 00

prj

A

M IDCD 4J

M-l (0CO p£<cCO 5(I OH r-l

4-1CO O<1) CM

33 33

x— \X-N O

oo m«3- Or- rH

rH C7>r- rovO 00

X-N

X-v 0oo moo om IH

CM CTioo com oo

X-N

S^ O

CM mCO O

S Cx

vO OiO COvO OO

X-NX-N fHF*. 0

0 ^-^N«r*

^^ A

A •• PJ

P. B§ HH

4-14J C]Jeu rHrH 4Ja 3M O

o oCM CM

33 33

X-N.

x^ CMm •>•m rHN X

CT*\O iH00 iH

X-N X-N

o\ ocr* orH vO

iH -3-H rHrH -3-

/^OX-N O

I-N. vooo co

CN-3- 00O -3"rH CM

X-N

CO•HtoP.

cCMe

0X"N *-

ta ^ZoN*-X ««

•W co

CO• cu

H H< PH

C 4JCO 0)CO rHa G

M•

00 OO CM

r-3 33

x .X-N 0

m om corH V^

>^^

CMr- oO r--H rH

/<— \

X-N 0>

O SO*3" 1 *m " -x*~^ fCM vOPN» CO

CO Sf

^m X-NrH inin -3-CO -3-

-31 mCM CM-3- inCM CM

^CO•H

CO rHa. i

CMM 1

S 1— N^5? A

•> <4H

• MHto cuCO O X-Na) cj PHrl 0Pi • 1

HCM•U •4-1

0) 33 «wrH 1*J H rl3 rH X!

c^ ^0 ^*vrl 3

O CU 4->CM > pq

33 0 ^

x-smp"*.•

rHN_X

mf•

-3-

-N

O

i-H^^

j.m•CM

y«-

in*o

r>»CM•

H

s**^

G•H

««

to•HQ

0)

•HcoCM

CUO

3H

x^0O

*CMs_x

00o ^n

• CMm H

^^inCM•rHN_X

OOrH in

• CMco rH

-N00•

0

COO 0• en

CM O\

X*N

•(3

""'

«k

•CQ

•H COQ (U

o, •§•0 H•HCO >4H

*J O30 M

CU<U XIXi g3 3r 25

^*-\ON

iCT\

9

•&rH

r™\

Om'*-'CM•in

H

X-N

00orH

a\•CMCO

/***.

<uM-lS— X

s•k

XJ4J00ccu^J

4)Q3H

X-N

OO

X^N r^*m -o m00 rH

CMrH CMNO rHCM r

•N

X-N O

<r oCO vOvO CTirH N^

mCM inm corH N3-

s-*^ox^ Oo m0O CO

•> rH

^J ^^ .

"" j.

•H 00O -3"CO rHrH in

x— \CM

4JVMN X

CMaA

Ctf s~\a) ,a* d• oo

EH rv^

33 • •>4-1

cu x:T3 00•H -HU) CU

1 3:CO CUCD xi4J 3CO H

CM CO in vo oo cy> CM co m \o

55

Page 61: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

56

Page 62: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

:-: o ,/,/,/• o i i i : i •

Figure 16. Potassium Pressurized Fluidized Bed BoilerCombined Powerplant (707E815)

57

Page 63: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

-IS

oCO

T301ta•a<uN ^•H VO•O ft-H 00s wiH r-Pu o

t^•a *-»<uN 4J

•H Ch CO3 ft0) O.<n M01 01u 3a. o

P-.

•H 0)O Cm T-Ica ^*J eo oa. u

1-101

3cxi

58

Page 64: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

fly ash is shown in Figure 12. Pipe sizes indicated on this drawing werecalculated for the particular flow (i.e., air, gas and potassium) so thatsizes shown are realistic. Because of lack of information on particlesizes, quantities of fuel carry over and fly ash, cyclone separator sizeindicated is approximate.

The system for removing the CaSO is not indicated on the layouts.Whether this should be a continuous process or batch process was notdetermined. An ash and CaSO^ pit along with storage areas are indicatedon the plot plan. Since no process for regenerating the CaSO^ was con-sidered in this study, further considerations must be given to the handl-ing (storage) and regeneration or ultimate disposal of the CaSO..

The remainder of the potassium system is basically the same as thatcovered in Cycle //I and remarks in that section apply equally to Cycle#2. The lower boiler potassium vapor discharge pressure and temperaturethan Cycle //I allow the use of stainless steel materials in the vaporpiping region, however, the increase in vapor piping diameter and re-sulting stresses may not justify its use from a cost standpoint. Itwill be necessary to consider alternate design methods for supportingthese highly stressed parts in stainless steel before reverting to theuse of the higher strength alloys such as HA-188.

Potassium Oxide Scrubbers. - The scrubbing system for Cycle #2 isbasically the same as that proposed for Cycle #1; scrubber capacity isbased primarily on building volume.

Turbo Compressors. - The turbine-compressors shown on the layoutsare General Electric Company's MS-7000 packaged generating units. Aswith Cycle //I, modifications to the unit would be required in the areaof compressor discharge scroll, combustor and turbine inlet scroll.These modifications are considered to be feasible by the G.E. Gas TurbineProduct Department. Four units as indicated would provide adequateplant turndown capability. Economizer and feed water heater exchangersare located in the turbine exhaust gas stream.

Steam System. - Layouts of the steam system are identical to Cycle#1.

Fuel System. - The fluidized bed boiler, of course, requires a com-plete coal storage handling, processing and injection system. Coupledwith this are the same requirements for limestone. The plant layoutsindicate the coal and limestone storage areas plus rail facilities forunloading from cars. From the respective breaker houses, coal and lime-stone are conveyed to the live piles. From these piles both are trans-ferred to the bunker house. Here coal and limestone are metered frombunkers into a grinder. The grinder supplies a feed control unit withthe proper size and mixture of fuel and limestone. The system for in-troducing fuel into each boiler bed utilizes compressed air. The com-pressors adjacent to the bunker house provide the air. Individual linesto each boiler module are indicated. Further fuel flow control is thendone at each module. Compressors must be capable of producing a pressure

59

Page 65: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

higher than that in the boiler bed. This type of system requires con-siderable power for driving the compressors. A screw type metering pumpfed by conveyors and located close to the boiler module may be a moreeconomical method.

Service Areas. - The various plant services (offices, maintenance,shops, parking areas, etc.) are identical to the layouts for Cycle //I.Ash storage areas do require space not required with a clean fuel plant.These, along with the coal and limestone storage areas, greatly increasethe amount of land required. Approximately 3.8 km^ (950 acres) are re-quired for the Cycle #2 plant.

60

Page 66: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

ECONOMIC AND TECHNICAL EVALUATION

Potassium Component Costs

This section presents the estimated capital costs of those systemcomponents which are in the potassium portions of the plant. The groundrules for this program required that these capital cost estimates bemade in 1972 dollars, for a developed technology, that is, after enoughunits have been built so as to remove any learning effect, and assuminglarge volume production of the special, high-temperature alloys required.This requirement can be met for steam and gas turbine components bysoliciting budgetary estimates from present suppliers. The accuracy ofthese estimates is subject only to the variations in specification be-tween a budgetary request and an actual purchase, and competitive marketforces. The accuracy of these estimates is not usually affected bytechnological uncertainties.

In contrast, the cost estimates for the potassium components mustbe based on conceptual designs of components which have never been built.The basic cost estimation problem involves the scale-up of the componentsfrom present experience to the sizes required by these conceptual designs.The technical confidence ranges from very high for the pumps, a nearlyoff-the-shelf item,to somewhat less for the pressurized fluidized bedboiler, which is not even state-of-the-art for steam.

The components for which budgetary quotes were not available are:

1. Potassium boiler2. Potassium turbogenerators3. Condenser-steam generator4. Dump tank5. Potassium pumps

The boiler, condenser-steam generator, and dump tank are much alikein that they all contain large, complex welded structures. The dump tankstructure is similar to the shell of the condenser-steam generator, whilethe condenser-steam generator and the potassium boiler both have complex,welded tubular heat exchanger internals. The condenser-steam generatorhas operating conditions similar to the Liquid Metal Fast Breeder Reactor(LMFBR) steam generators. The turbine and pump are, however, uniquecomponents. The turbine resembles a large steam turbine in size, al-though not in materials. The pump is similar to those designed for theLMFBR program.

61

Page 67: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

METHODS USED

In general, the approach used to cost each component for which abudgetary quote was not available was as follows. First, calculate theweight of each material. Then, using estimated material prices and scrapfactors, calculate the material cost. Second, identify either a similarsteam component for which labor and material costs were available, or asimilar liquid metal component for which labor and material costs werealso available. Third, using subjective judgment, estimate from the"similar" component a labor cost to build the potassium component.Lastly, add a percentage profit and add up the cost of materials, labor,and profit.

It is difficult to estimate the accuracy of these methods. Earlierunpublished work, as well as information from General Electricfs NuclearEnergy Division (NED), indicates that the cost of heat transfer componentssuch as the boiler tube bundles and the condenser/steam generator shouldbe fairly accurate, say + 30%. The costs of the potassium turbines areprobably not as well estimated, with perhaps + 50% being reaslistic. Itshould be noted that cost estimates for the scale-up of components tofull commercial size from development hardware is notoriously inaccurate.It was assumed for this study that, by maintaining internal consistency,valid comparisons of competing potassium topping cycle systems can bemade. -.

CONDENSER-STEAM GENERATOR

This component, to be made of 304 stainless steel, is shown inFigures 5 and 14 for cycles 1 (pressurized boiler) and 2 (pressurizedfluidized bed), respectively. Table 18 shows the cost estimates forthese potassium condenser-steam generators. The cost of similar units(from an earlier, unpublished study) had been estimated by General Electric1!Nuclear Energy Division (NED) based on their experience in the LMFBRapplication. A new material cost quote was obtained for the 304 stain-less steel tubing in large quantities. The labor cost, including qualityassurance, was estimated using a ratio of the labor/material costs takenfrom the earlier study. An NED learning curve showed that the fullydeveloped unit would cost 80% of the first unit, and this percentage de-crease was used.

POTASSIUM BOILERS

Supercharged Boiler (Fig. 2). - The supercharged boiler for Cycle 1consists of 8 modular units, each containing 2114 3.81 cm (1.50 in.)diameter boiler tubes made out of HA-188. The rest of the structureconsists primarily of a welded pressure vessel of 304 stainless steel andcarbon steel which is insulated by a 15.24 cm (6.0 in.) thick lining ofrefractory. The estimate is shown in Table 19. The high material costis due to the $18.74 per kilogram ($8.50 per pound) cost of HA-188 inhigh quality boiler tube. The labor estimate was made by assuming an allstainless heat exchanger and using the NED condenser-boiler cost splitbetween labor and materials. The labor cost so found was increased by

62

Page 68: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 18. - CONDENSER-STEAM GMERATORS

Cycle 1 Cycle 2

304 SST Wt-kg (Ibs) 117709 (259500) 128913 (284200)

Material Cost <? 3.73 $/kg (1.69 $/lb) $ 438,600 $ 480,300

Labor (Including 0/H, G&A, Engr'g) 937,700 1,026,800NED Labor/Material Ratio

Profit @ 9% 136.100 149.100

Total FOB Cost First Unit $1,512,400 $ 1,656,200

Unit Cost @ 80% $1,210,000 $ 1,325,000

Insulation Area 286 m2 (3082 ft2) 323 m2 (3480 f t2)

Cost @ 430 $/m2 (40 $/ft2) $ 123,000 $ 139,000

For 4 Units

FOB $4.84 x 106 $5.30 x 106

Insulation 0.49 x 106 0.56 x 1Q6

Total $5.33 x 106 $5.86 x 106

Fully developed unit.

63

Page 69: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

. TABLE 19. - PRESSURIZED BOILER COSTS

(8 Units Required)

A. MATERIAL COSTS

Material Gross Weight Cost/Weight Cost

kg (Ib) $/kg ($/lb)

HA-188 78,473 (173,000) 18.74 (8.50) $1,470,000

304 SS 8.868 ( 18,550) 2.76 (1.25) 24,000

Carbon Steel 63,958 (141,000) 0.55 (0.25) 35,000

Silicon Carbide 5,988 ( 13,200) 1.10 (0.50) 7,000

Refractory Lining 110,769 (244,200) 0.33 (0.15) 37,000

$1,573,000

[If this were all stainless steel, cost would be about $ 319,000]

B. LABOR COSTS

Using NED percentages for stainless steel assembly:

319,000 is 29% of $1,100,000

so 62% (Labor) is 682,000

C. COMBINE AND ACCOUNT FOR LEARNING CURVE

8 UnitsClass 1st

Materials

Labor

Profit

FOB Price

Install Liningat Site(A. P. Green Co.]

Total

$

^

)

$

1

1

2

2

Unit

,573

,023

257

,853

8

,861

>

»

f

>

>

>

Cost

000

000 (1)

000

000

400

400

Unit

$ 1,

2,

$ 2,

Cost

573

818

236

627

8

635

>

»

P

>

>

»

000

000

000

000

400

400

$ 12,584,000

6,544,000

1.888,000

21,016,000

67,000

$ 21,083,000

is 1.5 times $682,000 to account for HA-188 component fabrication,

Fully developed unit.

64

Page 70: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

50% to account for the lesser workability of HA-188 compared with 304stainless steel. The labor cost was then decreased by 20% to accountfor a learning curve effect, although the material cost was left unchanged(the $18.64/kg HA-188 price already includes a learning curve effect).The cost of insulation (refractory) was determined from information fromA.P. Green Co. for their "Mizzou" brand of gunning refractory.

Pressurized Fluidized Bed Boiler (Fig. 11). - The pressurized fluidizedbed boiler for Cycle 2 is a tall, modular structure originally with theheat transfer bundle made out of HA-188. However, later in the study,it was decided that at the potassium temperature of 1033 K (1400°F) 304stainless steel could be used for the heat transfer bundle, especiallyif local reinforcing members of Astroloy were used. This use of 304stainless steel rather than HA-188 allowed a significant cost reduction(nearly 50 million dollars).

Table 20 shows the cost estimate used for this component. The laborcost assumes that the complexity is similar to the NED costed condenser-boiler, and no allowance was made for the small amounts of high tempera-ture alloy since so much carbon stfal was also used. Insulation wasassumed to be the same "Mizzou" brand gunning mixture specified for thepressurized boiler.

Dump Tanks and Potassium Inventory (Fig. 6). - The dump tank is acylindrical vessel with an insulated jacket surrounding it. Hot gas canbe circulated between the vessel and the jacket in order to control thetemperature between the melting point of the potassium and the hot-trapping temperature (^ 1033 K (1400°F)). Zirconium material for getteringis placed in the tank, however there are no other internals except in-let and exit pipes and control equipment. Table 21 shows the cost break-down. The factory labor estimate was based on the labor for the stain-less steel shells of the condenser-boiler as estimated by NED (45% of thematerial cost before adding engineering, 0/H, G&A, etc.). The zirconiumwas not included in the material total used to compute the labor. Nolearning curve was applied to this component, since it is as close toa conventionally constructed unit as any of the potassium components.The insulation used is the same as that for the condenser boiler.

POTASSIUM FEED PUMPS

The potassium feed pumps are very similar to the sodium pumps usedin the LMFBR program and for many liquid metal test loops. A quotationof $250,000 for a 9000 GPM pump was received from Byron-Jackson PumpDivision of the Borg-Warner Co., based on the non-nuclear section of theboiler code. Four are required.

POTASSIUM TURBINES

Cycle 1 (Pressurized Furnace) Turbines. - For this cycle, one highpressure turbine, operating between 1116 K (1550°F) and 1005 K (1350°F)was combined with two low-pressure turbines, operating between 1005 K(1350°F and 866 K (1100°F).

65

Page 71: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

COHCOoCJ

MOPQ

0W

sCOCO

P-i

I

OCM

I

•oCUM

00

p

Mo

Pb

COHCOo

Q

||

CO

5JMPJwH

3

<

x~\.CO

4JC-5*^ %-CO rHO

CJ X

•CO-N /

1 1

COoCJ

4-1•rl£3

*~^

4-1szOD•HCU

COCOoo

toO

• 4JCJCOf*ftCO

OCO

4-1

iHcu

12

CO•HGiH

rHtO•H

4J

a

rH

m-3-CO

/^^ oJQ m

— 00</>v^ >"'

-3-00 P-.*^ *^ 00

•CO- ,-H

O^ o

CO \Oo ««

rH 0<S— * <J"

v^

OCM

00 «.M oo

rH

mrH

rH

"-s o"CO O

,O CO

«-x mCO

v^

ooo

j? vorH

0000rH

1

. &

ooo>vOm

•rH

^vONVO

i-H

^

COr^•

CO

C?oON

OOCMON

Oin

A

HCM

inrH

H

CDO

!Ooo

oCO

vovoCO

HCOCO

* -oCO

CM

rHmCO

^^0oorH^^

mo•CMCM

OOrH

«tinCO

v_,

OCM

°i>inrH

inCM

H

OOrH

ooCM

^_,

0mf**CMH

orHO

4J

48

>*

ONoo

mCM

O

V^

mm•o

CDOin

Mr^inCO

ovO

A

CMvOrH

inCM

rH

OOovo00CM

OCO•ONCMrH

_Jr"l

CUCU4-1coGo^too

vo

COVO

/-v

rH

ON~'

COCO•

o

ooin

A

COCM

sOOjrn

CMONH

O0

rH

"SO

COCM

cS

OO

CMONrH

GO•H4->CO

-3coCM

O

O\rHsrCM

OO

O*00mrH

O

ON

vo"rH

VOO

X

vO

CO

CM

GO

mG

coH

8

co4Jcooo

CO4-J•HGP00

voOiH

X

CMmCO•

ONrH•CO-

VOO

>i

CMCOCMo

CMCO

VOOrH

^OvOrHam

voo

,3->3*p**o

vOin•CO-

COco XCU VDH sr O• CM iH

COoo4-1•rl.§

VO0..Iim

X

CT\rH

CM•CO-

VDO_J^1

XCJNCMO

-*

vOO__J

^^

X

m•vO

CD

VOO__J

r^

XCOCJNO

r^•CO-

OO

tO 8^•H CTito CMCU•u ca

voo

X

COom•c/>

10

o

CO4JCO

vO vo vO VDO O O O

COCU00

X XON VOi-H CO<t O

CM m<n-

X XvO rH

OCM•

oo•CO-

m CM

GCU CMo <n-to(U

0)CO

tD

OCO

COcocO

i-HCJ M

ater

ia:

toO

(0

rHCO4-1

5

VO

o•co-

co00CO

vOm

Go

ooG

to4JcoGi-tOH

OH

*n

§•oCUCUo

CU

>,rHrH

pq

66

Page 72: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 21. - POTASSIUM DUMP TANK AND INVENTORY COSTS

(1 Unit Cost; 4 Units Required)

A. MATERIALS AND' COSTS

1. Factory Materials

304 SST; 62140 kg @ 2.76 (137,000 Ibs @ 1.25) -' $ 171,200

Inconel 600; 5220 kg @ 5.51 (11,500 Ibs @ 2.50) = 28,800

Zirconium; 2670 kg @ 30.86 (5880 Ibs @ 14.00) = 82.300$ 282,300

2. Site Material

Insulation; 200 m2 @ 430.57 (2140 ft2 @ 40.00) = $ 85,600

Potassium; 66680 kg @ 2.76 (147,000 Ibs @ 1.25) = 183,800$ 269,400

-X

B. COST ESTIMATE

Material (not including Zirconium) $ 200,000

Labor (NED labor without burden/material ratio) 90,000@ 45% of Material above

Zirconium 83,300

Overhead (@ 150% of Labor) 135,000

Total Direct Cost $ 507,300

Engineering (15) 76.100

Total $ 583,400

E&A (15%) 87.500

Total $ 670,900

Profit (10%) 67.100

Total Factory Price . $ 738,000

Site Material 269.000

Total Cost $1,007,000

67

Page 73: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

A. Low-Pressure Turbine (Figure 4) . - The cost technqiue used wasquite different for the turbines than for the other components. Thiscomponent is quite similar in size to the low pressure unit of a cross-compound steam turbine. The GE price book values for large steam turbo-generators were correlated by GE-ESP with the number of low-pressure tur-bine last stage bucket rows (NLSB) which is always an even number (2-8)and the length of the last stage blades (LLsg) . This correlation, in-cluding a factor for 1972 prices is:

Cost ($ x 106) = 2.337 NQ x 0.02214 Ptro (MWe)o WK.

(Ng is Number of shafts, 2 for cross compound)

Generators correlate as (approximate GE prices)

Cost •($ x 106) - 0.066 N0 + 0.00872 .Prro (MWe)o WK.

Therefore turbines alone cost:

Cost ($ x 106) = 2.271 N_ + 0.01342 Prro (MWe)o WJ\

The split between high pressure and low pressure sections was based onthe weight split of the Bull Run turbines, where 70% of the weight wasin the low pressure unit. Each unit has 1 shaft, so:

Cjj, ($ x 106) = 2.271 + 0.01032 P (KWe)

The power of these units is proportional to the number of last stagebucket rows and blade size:

Therefore:

PWR (MWe) =0.133

($ x 106) = 2.271 + (0.001373) (NLS]J)

The split between factory material and labor was taken from ORNL-CON-CEPT-I (ref. 9) cost code models as 47% material and 53% labor (includingprofit). These figures, along with the estimated material costs, areshown in Table 22 for the low pressure, cycle 1 turbine. The labor,compiled as above, is multiplied by 1.5 to account for the harder-to-work materials (an arbitrary assumption).

B. High-Pressure Turbine (Figure 3). - Although the material costswere estimated as detailed above, the labor was arbitrarily set as equalto the material cost (about 73% of the low pressure unit labor cost)even though this unit weighs only 56% of the low pressure unit. Table23 shows these results.

Cycle 2 (Fluidized Bed) Turbine (Figure 13). - This cycle used twodouble flow units, handling potassium from 1033 K (1400°F) to 866 K(1100°F). Table 24 shows the cost estimate, prepared in essentially thesame way as the low-pressure cycle 1 turbines.

68

Page 74: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 22. - LOW PRESSURE POTASSIUM TURBINE COSTS

A. MATERIAL COST (per Unit)

Material Weight Cost/Weight Cost

304 SS

Astroloy

HA-188

Rene1 77

Cr-Mo Steel

Inco 706

Rene1 41

kg (lb)

309,360 (682,000)

39,200 ( 86,400)

13,060 ( 28,800) -

17,780 ( 39,200)

25,580 ( 56,400)

69,130 (152,400)

35,930 ( 79,200)

$/kg

2.76

22.05

13.23

17.64

0.66

14.33

16.53

($/lb)

(1.25)

(10.00)

( 6.00)

( 8.00)

( 0.30)

( 6.50)

< 7.50)

$ 852,000

864,000

173,000

313,000

17,000

991, 000

594,000

$3,804,000

B. LABOR COST (Includes Profit)

Low Pressure Steam Turbine Section with same size last stage bucket'.

C = 2.271 + (0.001373) (2) (38.4)2

= $6.320 x 106

Factory Material (47%) ref. 9 $2,972 x 106

Factory Labor (53%) ref. 9 $3.348 x 106

C. TOTAL COST

Material $3.804 x 106 + profit = $4.146 x 106

Labor $3.348 x 106 x 1.50(1)= $5.022 x 1Q6

Total $9.168 x 106

Two Turbines: $18,336,000

'Materials harder to work than for steam turbines. ,

69

Page 75: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 23. - HIGH PRESSURE POTASSIUM TURBINE COSTS

A. MATERIAL COST

Material Weight Cost/Weight Cost

kg (Ib) $/kg ($/lb)

304 SS 69,670 (153,600) 2.76 ( 1.25) $ 192,000

M252 2,720 ( 6,000) 15.43 ( 7.00) 42,000

A286 16,870 ( 37,200) 5.51 ( 2.50) 93,000

Astroloy 13,060 ( 28,800) 22.05 (10.00) 288;000

TZM 45,720 (100,800) 26.46 (12.00) 1,210,000

HA-188 108,860 (240,000) 13.23 ( 6.00) 1,440,000

Rene' 77 3,810 ( 8,400) 17.64 ( 8.00) 67,000

Cr-Mo Steel 23,950 (52,800) 0.66 ( 0.30) 16.000

Total • $3,348,000

B. ESTIMATED COST '

Material (same method as L.P. turbine) $3,348,000

Labor (larger than if scaled by weight) 3,348,000

Profit 662.000

$7,358,000

70

Page 76: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Ma

CO

ocuCM

i•

CN

4, COCO <o

CJ X

<Tr

S0)

&4

0!uH

g

•co-

00

00•H0)

COcoso

oa)

MOcn

&•H

co

(8•H

(V4J

CO

00

r^

o0iH

vOCM

vO

CN

oOvO

vOmoo

0

m0000CO

CM

rH

0O00

COrH

O00

CO

co

en-a-oco

CO

inCN

OO

fO

COrH

OO

CM

O

CO

CTsH

H

OOvO

vn

0m

sOrH

8rH1

CM

CO

oo

ooorH

oCNCM

OOCO

OO

0

vO

ooCO

CN

rH

O0rH

rH

OmCM

CMco

OrHOH4J

CM

ooCOmH

OmvO

COCO

rH

OOvO

vOCOCM

OtNCO

r>0rH

CM

O0CM

r-vTv

Om

00

vO0

8

CTi

o\m

0m

comvOiH

o0CO

£

0

a\

CO

CM

rH

O0rH

vOVO

1

CM

rH

"i

CO

•H

OO

OO

vO

S

O0CN

COrH

0

rH

CMCO

rH

OO

OiCMrH

OO

ooin

"i

C3 * 3

m r-»

0CO

0

vOSO

0

0oCM

oin

or-.

CMCM

CM

rH

O O0 0oo o

960 (

41,

27

0(1

.25

5,

00 ONrH VD

m

rH<U0)4JCO

vO vO vO00 0rH rH rH

X X X

vO 00 vovo r 10CM vO CO

• * . 'c*) co \o

o

0)

CC?4J

CO

c«rH

0)N•HCO

CU

(

&4->•H CM

inC CMo ••H rH4J -*fj <t s ^^ ~~ ^i

4J CO CM . U-l•H ^ iw m o

r< -H ^s•PH J3 CO -s /-x H-

M H B>e »«M 3 O I"* CO vO \C 4J o vo <t in o•H . O "^ ^ rH'O B O rH•3 S r * -3 i

- C M c o - H r ^rH rH <J- V-i Vl r>-v^ 0) r» o W O •

M CM . 4j ja mtH 3 • vo *0 50 E-* </>c/5 co CM </y s; i_5 wO CO O rHU C D I I n > , x o c o

M W V4 -Hrt cu cj o o H-) nO 4J 4J < 0)pa S o o H 4-1« ' O CO' QJ o coiJ i-J ti4 t*i H S

PQ O

VO vO0 0rH i-H

r^ co•H rin oo

• •

in I-HrH

*-NH

0""" 0• rH o

0 ^O

x St

vo co• 4J

CO . «H

O

O^3 >-i

CO O

CO01a

I

<k>CO

<4H

I4J

t

±4

«ja

71

Page 77: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

SUMMARY OF POTASSIUM COMPONENT COSTS

The direct costs of the potassium components are summarized inTable 25. It is obvious that much of the preceeding data depends onjudgment rather than solid fact.. Nevertheless, these results certainlyare of the right magnitude, and are probably accurate to +_ 50%. If theyare, the contribution of this error to the total powerplant cost will bemuch less (15 to 20%), still a large variation, but within the limits ofaccuracy often quoted for this type of estimate.

For the purposes of ranking potassium plants, the systematic methodsused should provide a valid comparison even if the absolute values ares'ightly in error. That is,any large difference between the cycle 1 andcycle 2 plant costs would be meaningful.

The aid of more equipment vendors would be needed to improve thepotassium component cost estimates. . More work is especially needed inthe area of turbine manufacturing methods and costs.

72

Page 78: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 25. - SUMMARY OF DIRECT COSTS OF POTASSIUM COMPONENTS

Millions of Dollars

Pressurized BoilerCycle

56.6

Pressurized FluidizedBed Boiler Cycle

Boilers

Turbines

Condensers

Pumps

Dump Tank

(8)

(3)

(4)

(4)

(4)

21.1

25.7

4.8

1.0

4.0

(8)

(2)

(4)

(4)

(4)

56.9

23.7

5.3

1.0

.4.0

90.9

73

Page 79: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Powerplant Costs

This section reports the estimated capital cost of the two selectedpowerplant configurations and an estimate of the cost of electricitygenerated by each. These costs are all based on 1972-1973 dollars (noinflation to the next decade) and assume a developed technology (noallowance for development).

METHODS USED

This section contains a summary of the methods used to estimate thecapital, operating, and fuel costs for the two selected powerplants.

Direct Cost Estimates. - The direct cost for the two powerplantswas estimated by the Project Engineering Operation, Installation andService Engineering Department of the General Electric Company (IS&E).The costs of potassium components were estimated as discussed in theabove section. All other costs were compiled by IS&E from suppliers ofthe individual component, or by their recent experience on similar equip-ment. In addition IS&E estimated the site labor and material requiredto erect the powerplant. Site-related items were estimated for theNortheastern U.S., to simulate the USAEC Middletown Site.

Indirect Cost Estimates. - In Task I, the indirect cost estimateswere based on the data given in ref. 10. These estimates were based onaverage values, and applied as a percent to the direct cost and totalconstruction cost. Table 26 shows these percentages as well as the IS&Eresults expressed as equivalent percentages. Note that the IS&E values,which were used in Task III, are not much larger than those assumed forTask I.

Operating Cost Estimates. - In Task I the operating cost estimateswere based on the correlations reported in ref. 10. The following itemswere included:

r

Wages $1000/MWeSupplies $ 240/MWeMaintenance 0.88% of direct costCapital Costs 6% of project costDepreciation 2.5% of project costInsurance 0.12% of project costTaxes 2.35% of project cost

Fuel costs were calculated from the cycle data using an 80% loadfactor (7008 hours/year). Sulfur removal costs were computed from litera-ture supplied by various system vendors.

For Task III, each of the above items was reevaluated. Wages,supplies, and maintenance were grouped into two classes, operating ex-penses and maintenance expenses. The 1971 operating data for seven large(800-1600 MWe) coal-fired plants were compared (ref. 11). The averageoperating expenses were 0.487 mills/kwh and the average maintenance ex-penses were 0.436 mills/kwh for a total of 0.923 mills/kwh. (The overall

74

Page 80: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

COUH

HMW

HM

86S

W,-3-

3

• Q U O )cu pa I-HN O

Vi <U CJ3 Nco 1-1 uiCO *O CU0) -rl iHM 3 -H

CU-O iH<U CJN >,•H CJl-l3 Vtco a)CO iHCU -HM 0

OL, (O

M

CO

H

OH

CU•H•-IP.Pi

a0•H4Jcx•H^40coQ

i-i•PO

gsg

CO

•ro

co«CM

COOo4-1OCU

•HP

mCOoCJ

Co•H4-10

}44-1COCa4JO.<u^J•H•OCM

S•

^j•-I

gsg

IO

»

I— {

iH

O»<y>

4-1oCUn•oC

T3

§

4J0CU

•HP

co4-1010CJ

COC

•H

CU<uc1-1j3H

t*«.•

vO

B-9CO

«VC

6-SCMt

VO

4-1O

n'OCM

T)

§

4JOcu•HO

J^Q)

5o•o§CU

•H4J COCO CUt-i m4-1 am 0)•H p.C X•H {3

*9^

?H•o\

6s?o

•<T^

^ •00

4JOCUH

•0e

•o§4JUCU

•H

°

C.04JU3M4-1CO0

800C•HM

4-1COCU

' 1

0)4-1£3M

75

Page 81: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

average of all reported plants was 0.94 mills/kwh).

These values were used for the pressurized fluidized bed powerplant.This implies that the potassium topping cycle plants will be no more ex-pensive to operate and maintain than present large coal-fired plants.An additional 2.2 mills/kg ($2.00 per ton) of limestone was added tooperating expense to account for the disposal of this material (ref. 12).It was also noted that gas fired plants require only about 65 to 75% asmany personnel as coal-fired plants, so, for the pressurized boiler power-plant, a reduction of 25% was used on the combined operating and main-tenance expenses, giving a value of 0.692 mills/kwh. This reduction wastaken primarily in operating expenses, to account for the smaller coalhandling crew required.

The capital cost, or investment cost, was computed using formulaefrom ref. 13. Using several different sets of bond interest, tax rate,return to stockholders, and bond/stock split for a utility company, itwas decided to use the recommended value from ref. 13 of 7.2%. Thisfigure is arrived at by assuming that the utility is profitable, has alarge fraction of its capital from bonds (whose interest is not taxableas profit), and pays a reasonable dividend on its stock (from its taxableearnings). It is specifically not the interest rate on utility bonds(currently about 8%) nor the return to the investor in utility stocks.Several different calculations were made for a range of postulated companystructures. The investment cost ranged from 9% to 5%, so that the 7.2%actually used appears reasonable.

Depreciation was computed using the recommended value from ref. 13,1.02%. This is a sinking-fund method calculation for a 30 year periodwith a 7.2% rate of return on money (that which the utility pays for itscapital). Note that the sum of capital cost and depreciation is 8.02%,slightly less than the similar value used in Task I.

Insurance and taxes were calculated with the same factors used inTask I.

9Fuel costs were based on 8.4096 x 10 kwh per year (7008 hours at

1200 MWe) and either 38C/GJ (40C/106 Btu) for coal or 76C/GJ (SOc/106 Btu)for gas from coal. These values were those selected by OCR for thisstudy.

Limestone for the pressurized fluidized bed boiler powerplant wasconsumed at a rate of 15% of the coal by weight and priced at 5.5 mills/kg ($5.00/ton) (ref. 12).

SUMMARY OF CAPITAL COSTS

Table 27 shows the capital cost of both cycles. The following dif-ferences are noteworthy. First, the pressurized fluidized bed boilercycle requires more land for coal yards and limestone facilities. Second,the combined potassium components and boiler plant equipment are almosttwice as large for the pressurized fluidized bed boiler cycle as for the

76

Page 82: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

(C

o

CM

1

C-1U]

M UQ rJM CJ

,-J UC*d

a:Q W

N M*-* oas «co oco uM gg

0,

asW1-3

O

Q MW i 1N U

COco

»

DE

SC

RIP

TIO

N

CO0 CO&4 «C(Z< ^J

t-3

j

r-. co m vo c s i m i n ^-orH O O <• VO C*^ O COOvo co co r^ oo 00 in m -*

in vo r-I r^ r - I o o ^ in oCM f * CM CO

rH

^

r-» a\

00 00

co POG\ f)

en c* rn <* oo m o, coof*^ C^ CM CM vO CO ^^ CO ^Oo c M i n « * - * o o o o m - ^c M v o i n c o o o o c o i n o

C N r H < T > ' C O

.

^-\ /-^00 rH

rH CM

4-1CO 4J (U4J C 0)c o> s« e 5. 4JB a to -H c« W -H 4J 3 Cd> C 9 C CO CT rH

c o o a ) c r a i c o * J W f x*J rl E W C *J -H VI C

J = O . C u O - H C U O I 4 J O

• H > M < 3 S | ' 5 : 3 ' r « c 5 § 4 Jp*l n" ^^ Q ^4 4J Qu rH CO

" O W U O I O U p L i O•a c -o c u cu co -HC c d * J C g - H « r H 3 C CC O C < 5 r O r < U O O 3

^3 CO CO - H M O ) 01 "H 1

TD ^4 pu 9 00 E^ fti W fl) C« CD OC 3 -rt CO O O r H O I < H C JC d 4 J V i C 0 4 J C O CO rH g g

O O ) O Q O C d C C Q O ) C U v O 4 J

C V i i H 4 J 0) 0 03 3 CO COto *j o o 4-> o in cr >j r-iJ CO PQ PLI CO •< S U H Oi

O f H o i c o - < r i n v o X f ^i— 1 iH rH rH rH rH rH m < 7 »CO CO CO CO CO CO CO CO CO

r^ voo orH Pv

•* a\cy^CM

o m>3- i-H

^D ^DooiH

tJcoO

CJ

Direct

Co

st

Constr

uction

rH 4-»CO U4J 0)O r<

H -H•0

M

co o co mrH m vo m00 00 CTi CM

co m o ooO CO CM CMCO

00 CM vO 00m CM oo om r** CM o\

CM CM co rOS CM i-H rHrH

Co

4-< O) -rlCD > 4JO - H OU 4J 3

C Cd MC 00 M *JO -H 4J CO

•H CO CD C*J V -rH OU Q C U3 -Hn -a g oo4J C TJ Cco cd <I «HC Mo oo -a 3° 5 § °rH |H 4JCd 01 i-H CO4J 01 «J 0*O C rl rl

H -H 4) 0100 C 4JC 01 CM U M

rHOO00

00ooCO

SJ-f**

•*

vo

CM

4Ja

4-1uV

"t?rl

p-_J

cd4JoH

77

Page 83: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

pressurized boiler cycle. This is due to the more expensive boiler aswell as the coal handling facilities required by the fluidized bed boilercycle but not by the pressurized boiler cycle. All other costs are eithersimilar or identical. The total cost of the pressurized fluidized bedboiler cycle is 58% higher than the pressurized boiler cycle.

SUMMARY OF COST OF ELECTRICITY .

Table 28 shows the estimated cost of electricity based on the capitalcosts and the methods discussed above.

The cost of electricity for the pressurized fluidized bed boilercycle is slightly lower than that for the pressurized boiler cycle,despite the much higher capital cost. This difference is due to themuch lower cost for coal versus gas from coal. In essence, the pressurizedfluidized bed boiler cycle economically combines the functions of'boththe gasification plant and the electric powerplant.

78

Page 84: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

1-1toCU

rlCUa.co

aCOCo

CO4-1COOU

•o<uN

•H <a•0 r-l•rl 0

rH O

•a cu« ^jr-lN iH•H 0rl «3CO T3CO 0)0) PQheu

CU

u

M0)rH•rlo

CQ

a)N•HM3COcoCDM

CU

C0•H4JP<•rl

0COCUO

vO ^D ^^ ^^ ^^ O^ON 00 O» vO vO COON ""> ON ON <" rH

CO CO f CO O ONCM

«* ui SO •* vO CMCO 00 - rH O> ONo in i*« m CM r~CM CO F*. CM O "">

ffj

0)souC•H

CO 00<u a

CO CO -Heu C -aCO 0) 3C O . r H<u x oo. u to aX 4J C -H

W CD CO OO O -H 4J

00 C U 4J 0) OC tO to CJ Z•H C H -rl C ^W 0) CO 0 tOtO 4J U CU M Wr< C iH M 3 0)CU -H O. O. CO XC^ (Q Q) ^ C ^0O S 0 Q M H

•* \O Om •*• "0rH Vt St

ON CM CM-* CM

r~. O ^nl-H O rHo o •*CM O CMco sr

4-1COo0

<2 Q) 4JH C COo o oH 4J 0

COCU r-le cu•H 3rJ b

§O

<tf^

CMCO

vj-p^»

EH

O

,

^*~^

g

l_3

HOH

/"^V

0 rH

V— ' ooo oCMO Tj

ON 00 3CO o

rlO

z g00 o

CO

O CU

ON VO i[ |f^ -H

COCOO

|

"w 'si— | 4JrH ^Q•H2 soO O

H^» *^^

W ^U•H *-)l-i O4J *~^0 0CU

rH •>W W B

co C«4H O O0 U fc,

4J rH rHCO CU 0)O 3 3

C_> fH fn

79

Page 85: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Technical Evaluation

Major technical considerations relating to a comparative evaluationof the clean fuel pressurized boiler system and the coal burning pres-surized fluidized bed system include the following:

1. Conservation of fuel resources2. Environmental impact3. Status of technology4. Degree of development risk and associated costs

CONSERVATION OF FUEL RESOURCES

The basic fuel resource involved with both of the alternative sys-tems is coal. Therefore, a logical basis of comparison is that of over-all system efficiency, defined as useful output power divided by theheating value represented in the raw coal supply required to support thesystem operation. In the case of the gaseous fuel system this efficiencywill be the thermal efficiency of the power system times the energy con-version efficiency of the coal gasification plant. Since the pressurizedfluidized bed system uses coal directly, the overall efficiency of coalutilization is simply the thermal efficiency of the powerplant.

The most economical coal derived gaseous fuel for the pressurizedboiler topping cycle system is low Btu gas produced from the water gasreaction and other associated reactions. In the most economical processair is used to oxidize some of the coal to furnish heat required to main-tain the endothermic water gas reaction. The gasification plant for pro-cessing the coal fuel is located at the site of the powerplant. Thus,little gas transportation penalty results from the low heating value ofthe fuel gas. The inherent advantages of this type of fuel for the pres-surized boiler topping cycle include the following:

1. The gasification process can be carried out at a pressure levelwhich is close to optimum for the power cycle. This facilitatesan efficient integration of the powerplant and the gasificationplant. The fact that the volume flow of air required for thegasification process is of the order of half the volume flow ofdelivered fuel gas is very favorable from the standpoint ofefficiency and specific output, of the gas turbine portion of thepower system, after allowance for the air compression powersupplied for gasification.

2. Capital costs for the low Btu gasification processes are lowerthan for medium and high Btu processes.

3. The fuel energy conversion efficiency achievable in a low Btugasification process is higher than for medium and high Btuprocesses. At the current state of the art (Lurgi fixed bedprocess) a value of 77% fuel energy conversion efficiency fromcoal to product gas is attainable. For advanced processes,such as partial oxidation, 86% energy conversion efficiency is

80

Page 86: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

(14)projected . These efficiency values account for the heatequivalent of the process air compression work, assuming com-pression is accomplished by electrically driven compressors fedfrom the power system output, and also account for all processsteam requirements.

4. The presence of a substantial quantity of nitrogen, carbon di-oxide, and water vapor inert gases in the fuel is favorablefrom the standpoint of NOX generation in the boiler, since itresults in reduced adiabatic combustion temperature.

In Figure 18 the overall thermal efficiency of the pressurized boilerpotassium-steam-gas power system combined with a low Btu coal gasificationplant having a fuel energy conversion efficiency of .80 is plotted againstgas turbine inlet temperature and gas turbine pressure ratio. Values forthe potassium and steam cycle parameters are indicated. These curves arebased on the assumption of a minimal gas turbine cooling penalty whichis estimated to be characteristic of advanced developmental cooled turbinedesigns. If the gasification plant energy conversion efficiency is raisedto the projected level of .86, the overall efficiency curves will beraised 7% (3-1/2 points).

The system thermal efficiency of a pressurized fluidized bed boilerpotassium-steam-gas power system is plotted in Figure 19 for a range ofvalues of gas turbine inlet temperature and potassium inlet temperature(steam conditions are indicated). The boiler pressurization level is9.0 x 10^ N/m^ (nine atmospheres), which is a reasonably conservativeprojection of the potential capability of the technology, and is closeto an optimum value from a cycle standpoint at the 1200 K (1700°F) gasturbine inlet temperature. This temperature is limited to the boilerbed temperature, which must remain safely below the coal ash fusion tem-perature, and which must remain in a range which is compatible with highsulfur dioxide removal in the bed. A peak development value for thistemperature is estimated to be 1255 K (1800°F).

The comparative levels of overall system thermal efficiency of thegaseous fuel and coal fuel potassium-steam-gas topping cycle systems,which are indicated by Figures 18 and 19, lead to the following conclusion.

From the standpoint of conservation of coal resources, the pressurizedfluidized bed coal burning technology appears to offer the highest potential.The margin of overall efficiency advantage of the coal burning toppingcycle system is, for the two reference cycles of the section CONCEPTUALDESIGN OF PROMISING POTASSIUM-STEAM TOPPING CYCLES (p. 14), in the rangeof 10 to 15 percent.

ENVIRONMENTAL IMPACT

Key factors in the evaluation of the environmental impact of thealternate potassium topping cycle power systems include (1) emissionrates of NOX and S025 (2) thermal pollution; and (3) any environmentalhazards peculiar to the specific plants.

81

Page 87: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

0.50

0.48

o 0.46<o•HO•rl<4-414-1w 0.44

0.42

i0.38

1116 K (1550°F) Potassium2413 N/cm2/839 K/839 K/839 K Steam(3500 psi/10500F/1050°F/1050°F)

Coal to Gas Conversion Efficiency 0.8

Pressure Ratio

2520

15

I I I1200 1300 1400 1500 1600 1700 1800 1900

Gas Turbine Inlet Temperature, K

l 1 i j i j i_

1600 1800 2000 2200 2400 2600 2800

Gas Turbine Inlet Temperature, °F

3000

Figure 18. - Performance of Pressurized Boiler Topping Cycle

82

Page 88: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

0.54

0.32

0.50

CJ

a<u•g 0.48U-l4-4

CO>»en

I

0.46

0.44

0.42

0.40

Potassium Temp., K (°F)

1089 (1500)

1033 (1400)

2413 N/cm /839 K/839 K/839 K(3500/1050/1050/1050 Steam)

Pressure Ratio 9

I1050 1100 1150 1200 1250

Gas Turbine Inlet Temperature, K

I I I L i

1300

1400 1500 1600 1700 1800

Gas Turbine Inlet Temperature, °F

Figure 19. - Performance of Pressurized Fluidized Bed Topping Cycle

83

Page 89: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

NOX Emissions Gaseous Fuel Cycle. - For the gaseous fuel plant care-ful design and considerable experimental development work will be re-quired to bring the NC^ emissions from the pressurized boiler within EPAregulation limits. The problem is in general similar to that currentlybeing experienced with gas turbine combustors. Certain important dif-ferences exist, however, between the ordinary gas turbine combustor andthe pressurized boiler combustor:

1. Low Btu coal gas contains a large percentage of inert gas(nitrogen, water vapor, and carbon dioxide), which is unaffectedby the combustion reactions and which receives a substantialportion of the heat of combustion thus lowering the adiabaticflame temperature well below the level attained in the primaryreaction zone with conventional gas turbine fuels , (at a givenlevel of combustor air inlet temperature).

2. The total air supply rate from the gas turbine to the pres-surized boilers will be closer to the stoichiometric value re-quired for the combustion of the total fuel supplied. By con-trast conventional gas turbines normally pass a substantialflow of excess air through the combustion system which can beemployed for dilution and temperature reduction of primary zonegases.

From the standpoint of limiting NOX generation, (1) above is afavorable factor, and (2) is unfavorable. Preliminary calculationshave been made to evaluate the adiabatic flame temperature level of thecombustion chamber of the reference pressurized boiler system using lowBtu gas fuel. The composition of this fuel is shown in Table 29, for atypical system. These calculations show an adiabatic flame temperatureof approximately 2200 K (3500°F) under the reference cycle condition of15/1 pressure ratio, and with no excess air. The gas residence time inthe combustion chamber prior to cooling by heat transfer to the boilertubes is approximately 100 milliseconds. Under these conditions excessiveamounts of HO are generated - more than 1.3 pg NO /J (3 Ib NO /106 Btu).

X £. £*

One means to reduce the NOx generation rate without encounteringmajor performance penalties is the gas turbine - boiler air flow circuitshown in Figure 20. The boilers are arranged in pairs which receiveflow in series from the gas turbines. The first boiler in the pairoperates with excess air which can be used for dilution and reduction ofadiabatic flame temperature. The inlet flow to the second boiler in thepair has essentially no excess air but does have cooled combustion gaswhich serves asa diluent for flame temperature reduction. Since thestoichiometric fuel air ratio for the typical low Btu gas fuel of Table 29is 1 kg fuel for 1.3 kg air, a situation providing equal heat liberationrates in the two boilers would provide a ratio of 2.6 kg air to 1 kg fuelin the first boiler (100% excess air), and a ratio of 3.6 kg combustiongas to 1 kg fuel in the second boiler. The first boiler flame tempera-ture, after dilution, would be approximately 1700 K (2600°F) and thesecond boiler flame temperature 1866 K (2900°F). Closer equalization ofthese two temperatures could be achieved by burning more fuel in the

84

Page 90: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 29. - COMPOSITION OF LOW BTU GAS

Constituent

H2

CO

CH,

COS

Out of

kg/s

0.68

13.02

9.41

1.50

4.82

32.78

0.46

0.19

0.09

62.95

Second Stage

Ib/hr

5366

103158

74541

11866

38166

259639

3641

1470

751

498598

Out of

kg/s

Same

Same

Same

Same

Same

Same

0.008

0.027

0.063

62.31

Scrubber

Ib/hr

Same

Same

Same

Same

Same

Same

61

216

499

493512

From E. Damon, Foster Wheeler Corp.

85

Page 91: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Air FromGas TurbineCompressor

Low Btu Gas Fuel

Boiler#1

Low Btu Gas Fuel

Boiler#2

Combustion GasTo Turbine

Figure 20. - Paired Boiler Series Flow Arrangement for NO Control

86

Page 92: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

first boiler than in the second. However, equal NCL. generation rates2V

in the two boilers would require a somewhat lower flame temperature inthe first boiler than in the second because of the higher oxygen con-centration in the burned gas.

With this approach it appears possible to reduce combustion chamberpeak temperatures to levels at which NOX control within the gas fuellimit of 0.086 ug N02/J (.2 Ib N02/10

6 Btu) is possible. An advantageof the use of series flow in paired boilers is the avoidance of the de-sign problem of recirculating 1255 K (1800°F) gas. A possible disad-vantage is the reduction in the number of independently operable boilermodules .

With the gas fueled pressurized boiler cycle the problem ofemissions control will become increasingly difficult as the gas turbineinlet temperature is raised, and also as the gas turbine pressure ratiois raised. This factor, in conjunction with the status of turbinecooling technology, may well limit the extent to which the efficiencygains attainable by high gas turbine inlet temperature and high pressureratio (Figure 18) can be realized in practice.

Coal Burning Cycle. - One of the characteristics of the fluidizedbed boilers is that combustion occurs at a temperature level well belowthat at which thermal NC^ is generated (in any significant amount) bythe hot air mechanism. However, important amounts of NOX can be generatedin fluidized bed combustors as a result of reaction between the fuel-bound nitrogen and the combustion air(15).

In a fluidized bed coal combustor operating with a stoichiometricfuel-air ratio, a NC^ concentration of approximately 400 ppm in the ex-haust gases corresponds to the EPA limit of 0.3 Ug N02/J (.7 Ib N02/106 Btu)for coal fuel. Under some conditions NOx emissions from fluidized bedboilers have exceeded three times this value(15 ,16) . Most of the publisheddata, however, apply to atmospheric pressure type boilers. Pressurizedbed boilers have consistently demonstrated lower NOX emissions than at-mospheric fluidized bed boilers (17). This is believed to be a combinedresult of the influence of pressure on the NQ^ generation and NOj. re-duction reactions and of the influence of increased bed depth and intra-bed residence time. Low superficial velocity, which is generallycharacteristic of pressurized beds, also results in increased residencetime, and, probably, in reduced NOX genera tion (16 ). Unfortunately thereis an inverse relationship between NOjj emissions and S02 emissions, since862 promotes the reduction of NO (15) .

The following factors have been identified as being important de-terminants of the level of NO emissions from coal burning fluidized bedboilers:

1. Pressure Level - Increased pressure tends to reduce NO .

2. Amount of Excess Air - Reducing conditions are favorable forless NOX. Thus, it is desirable to minimize the amount ofexcess air supplied.

87

Page 93: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

3. Coal Particle Size - Increasing the coal particle size has beenfound to result in reduced NO generation.

X

4. Air and Coal Feed Distribution - Two stage combustion, whereinthe coal is initially introduced into a sub-stoichiometric re-gion of the bed, with secondary air injection to complete com-bustion, has been found to result in reduced NO emissions.

X

In summary it can be said that although control of NO emissionsfrom fluidized bed boilers will continue to be a matter for research anddevelopment, there have been reports of very encouraging results on NOemissions from pressurized fluidized bed boilers. Reference 18 reportslevels of 50 to 150 ppm in the effluent gases from a fluidized bed boileroperating at 6.0 x 10^ N/m^ (six atmospheres). This permits a predictionthat the NOX emission problem is a solvable one.

Insofar as the reference cycles of the section CONCEPTUAL DESIGN OFPROMISING POTASSIUM-STEAM TOPPING CYCLES (p. 14) for the gas fired and coalfired potassium-steam-gas topping cycle power systems are concerned, itmay be stated that there is a high level of probability that NOX emissionsfrom both systems can be controlled within regulation limits. Neithersystem can be said at this point in time to have any marked potentialcomparative advantage.

S02 Emissions-Gas Fueled System. - Sulfur dioxide emission controlin the gas fueled pressurized boiler system depends upon efficientscrubbing of the fuel gas obtained from the coal gasifier. Table 29indicates the degree of sulfur compound removal achieved at the gasscrubber exit of a typical low Btu coal gasification process. This tableindicates values of 1.2 x 10~4 kg H2S/kg fuel gas and 10~3 kg COS/kgfuel gas in the scrubbed gas. These amounts correspond to 0.043 yg S02/J(.1 Ib S02/10

6 Btu) from the H2S combustion and 0.215 ug S02/J (.5 IbS02/10

6 Btu) from COS combustion. The total S02/J (S02/106 Btu) is

one half the EPA limit of 0.516 yg S02/J (1.2 Ib S02/106 Btu) for coal

fuel. By refinements to the gas scrubbing system the S02 emissions canbe reduced substantially, probably at increased cost.

In general, it may be stated that adequate technology exists to re-duce S02 emissions from low Btu coal gas fuel to levels well below exist-ing regulations for coal fuel.

Fluidized Bed Coal Burning System. - For a fluidized bed coal bum-ing boiler the S02 emissions can be related to the percentage of sulfurin the coal and the percentage S02 removal in the bed in the manner in-dicated in Figure 21. From this figure it may be seen, for example, that60% removal effectiveness will bring the S02 emissions to the regulationlevel of 0.516 yg S02/J (1.2 Ib S02/10

6 Btu) in 1% sulfur coal. For 6%sulfur coal a removal effectiveness of 90% is required. Realizing adequatesulfur removal effectiveness, subject to other design requirements, suchas operating the bed at a high temperature level for good thermal effi-ciency, making use of available limestone supplies, and limitation ofexcess air for reasons of performance and NOjj emission control, is oneof the key problems to be solved in the development of fluidized bedboiler technology.

88

Page 94: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

10.0 -

9.0

8.0

7.0

6.0W

VDO

0).0

co•H

COCO

5.0

4.0

3.0

2.0

1.0

0 L

3.5

3.0

2.5

CMOCO

CO2.0

o•HCOCO-H

$

1.5

1.0

0.5

5%

EPA Limit forCoal Fuel

I20 40 60 80 100

Required Sulfur Removal Effectiveness

Figure 21. - SO2 Emission Rate versus Fluid Bed Sulfur Removal Effectivenessand Sulfur Content of Fuel

89

Page 95: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

The following factors have been found to influence the sulfur re-moval effectiveness of fluidized bed boilers.

1. Bed Temperature - Maximum sulfur removal in atmospheric fluidizedbed boilers has been obtained at bed temperatures between 1061 Kand 1144 K (1450°F and 1600°F). However, it has been reported(ref. 18) that a removal effectiveness as high as 97% has beenobtained in a pressurized bed 6.0 x 10^ N/m2 (6 atmospheres) at1255 K (1800°F) temperature. In this connection it is importantto note that as bed pressure increases the temperature requiredfor calcination of the limestone also increases. Since lime-stone calcination is essential for effective sulfur dioxide re-moval the bed temperature must be high enough to accomplishthis. This condition appears to be met by the reference cycleof the section CONCEPTUAL DESIGN OF PROMISING POTASSIUM-STEAMTOPPING CYCLES (p. 14) (9.0 x 105 N/m2 1200 K) (9 atmospheres1700° F).

2. Ca/S Ratio - Increasing the mole ratio of calcium to sulfur inthe feed to the combustor increases the degree of sulfur re-moval. At Ca/S ratios in the range of 2 to 3 a sulfur removalefficiency at 90% has been achieved (ref. 18).

3. Fluidizing Velocity - Low levels of fluidizing velocity, whichcorrespond to long intra-bed residence time, are favorable forhigh S02 removal effectiveness. Results reported in refer-ence 18 show a decrease in removal effectiveness from 90% to70% for an increase in fluidizing velocity from 0.6 m/s(2 ft/second) to 1.8 m/s (6 ft/second).

Stone Type and Source.. - Dolomite, which contains MgC03 as well asCaC03»has been found to be more effective in sulfur removal than line-stone, for the same Ca/S ratio (ref. 18). MgC03 is more readily reducedto the oxide than CaC03 and this property apparently increases the stoneporosity and promotes the reaction between the stone and S02. Limestonesfrom different sources have demonstrated markedly different S02 removaleffectiveness values in fluidized bed cotnbustors. Tymochtee dolomite isparticularly effective at temperatures above 1144 K (1600°F). When re-generated bed stone is employed, the effectiveness deteriorates on suc-cessive cycles of usage. Stone particle size has been shown to have aneffect on reactivity but the available data is contradictory. Relativelylarge stone (greater than 300 microns) is believed to be best for deepbeds, such as pressurized designs. The residence time of large stone islonger than for fine stone, and introduction of the stone near the topof the bed, where it can be most effective in S02 removal, and extractionof stone at the bottom of the bed is the presently recommended practice(ref. 18). Stone movement through the bed in a direction counter currentto the bed gas stream is feasible only for the coarser grades of stone.

Bed Depth. - Increasing bed depth, which, like reducing fluidizingvelocity, increases the intra-bed residence time, has been found to im-prove sulfur removal effectiveness. Another effect of increased beddepth is believed to be that of preventing the prevalence of reducingconditions, which usually occur in the vicinity of the coal admission

90

Page 96: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

ports near the bottom oE the bed, throughout the bed. It is importantthat excess oxygen be present near the top of the bed where the stone isintroduced. Such conditions are most favorable for SC>2 removal.

Excess Air. - Excess air is favorable for S02 removal, particularlyat elevated bed temperature (above 1255 K). However, excess air is un-favorable for NO removal.

X

In summary, it can be stated that the problem of achieving adequateSC>2 removal, consistent with meeting other design requirements, is acritical one for the pressurized fluidized bed designer. This problemis currently and will continue to be a subject for research and develop-ment. Demonstrated sulfur removal efficiencies above 90% have beenachieved under conditions approximately those of the pressurized fluidizedbed reference system cycle, (6.0 x 105 N/m2, 1255 K) (6 atmospheres, 1800°F).This justifies the prediction that design of such systems to meet EPAregulations can be accomplished.

With respect to the SO- emission problem, some preference must begiven to the gas fueled topping cycle system, because of the presentavailability of high efficiency gas scrubbing technology.

Thermal Pollution. - Both of the topping cycle systems which havebeen studied and defined in terms of the reference cycles of the sectionCONCEPTUAL DESIGN OF PROMISING POTASSIUM-STEAM TOPPING CYCLES (p. 14) arebased on the use of cooling towers for waste heat rejection. With thismanner of heat rejection there should be no serious thermal pollutionproblem for either cycle.

The topping cycle reduces thermal pollution by increasing the thermalefficiency of power generation. Cycle calculations indicate a thermalefficiency of 0.392 for a conventional, modern steam plant compared with0.528 for a potassium topping cycle plant with a supercharged furnace.Assuming that both powerplants have coal gasification to control sulfuremissions, the heat inputs from fuel are 2551 and 1894 MW respectivelyfor 1000 MW plant output. The heat rejection to the atmosphere, in-cluding condensate cooling, is 1551 and 894 MW, respectively. Therefore,only 74% as much fuel is required and only 58% as much heat is rejectedby the topping cycle powerplant.

The topping cycle powerplant with a fluidized bed combustor has acalculated thermal efficiency of 0.499, which means 2004 MW heat addi-tion and 1004 MW heat rejection for 1000 MW plant output. Assuming thatthe conventional steam plant could also have a fluidized bed combustor,the topping cycle uses 79% as much fuel and rejects only 65% as much heatas the conventional steam plant.

Special Environmental Hazards. - In general the hazards of thealternate topping cycle systems are similar to those of conventionalsteam and gas turbine powerplants. The presence of the potassium flowloop will introduce some degree of additional hazard. Potassium is

flammable, and care must be taken to avoid leaks, to quickly detect themand to minimize their effects should they occur. Modularization of the

91

Page 97: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

potassium components and flow loops will aid in this. Potassium oxideand hydroxide are caustic and toxic and evacuation systems to safelychannel and water scrub any such accidental plant emission must be pro-vided. Fraas^8) concludes that a well designed potassium topping cyclesystem would present unusual and difficult but manageable problems.

STATUS OF TECHNOLOGY

The technologies involved in the gas fueled pressurized boiler sys-tem and in the coal fueled pressurized fluidized bed boiler system canbe outlined as follows:

Gas Fueled Pressurized Boiler System

Steam TurbineGas TurbinePotassium TurbinePotassium Two Phase Loop Metallurgy and Fluid PurificationPotassium BoilerPotassium Condenser - Steam GeneratorPotassium Boiler Feed PumpLow NOx CombustionLow Btu Coal Gas Production and PurificationPotassium Valves, Expansion JointsControls

Coal Fueled 3'ressurized Fluidized Bed Boiler System

Steam Turbine'Gas TurbinePotassium TurbinePotassium Two Phase Loop Metallurgy and Fluid PurificationPotassium Condenser - Steam GeneratorPotassium Boiler Feed PumpPressurized Fluidized Boiler (Bed Side)Potassium Boiler (Potassium Side)Potassium Valves, Expansion JointsControls

For both systems the potassium technology is available for the selectedcycle conditions at the 3 MWt level. The basis for this statement isthe extensive development work on potassium Rankine cycle space powersystem components conducted by the General Electric Company under contractto NASA. Reports covering this work are listed in references 19 thru 33.Because of the size limitation on disc forging of super alloys andrefractory alloys the potassium turbines will be modularized, permittingthe use of 40 inch discs for the fluidized bed powerplant and 36 inchdiscs for the pressurized boiler powerplant. There may be a costpenalty associated with modularization. In this way the presently availabletechnology for superalloys can be used. Large molybdenum alloy turbine

92

Page 98: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

discs pose a particularly involved problem. It may be advisable to de-sign for use of only superalloy materials. In addition to the largedisc problem, other materials and process efforts required in connectionwith applying and extending the successful efforts of the past to largestationary powerplants include the following:

1. Determination of the compatibility of boiler and condenser ma-terials with operating environments including both firesidecorrosion and alkali metal effects. The possibility of fire-side corrosion of the boiler tubes in the fluidized bed packedwith limestone is an area of particular concern.

2. Acquisition of long term mechanical property design data oncritical materials such at- potassium containment materialsand potassium turbine: rotating parts materials.

3. Development oi: seamless tubing manufacturing and quality con-trol processes for new boiler materials.

4. Design and construction of module size full scale turbine seals,boilers (gas fired, pressurized), condenser-steam generators,and inlet control valves.

Steam turbine and gas turbine technology is available for both ref-erence systems. Advances in long life, high- temperature turbine coolingtechnology will be required for realization of the potential efficienciesindicated (Figure 18) for the gas fueled system at gas turbine inlet tem-peratures in the range of 1366 K to 1922 K (2000°F to 3000°F) . For thepressurized fluidized bed boiler system the projected condition of erosionand deposit free gas turbine operation has yet to be proven by actualgas turbine operation on the scrubbed gases from fluidized bed boiler.Present favorable estimates of this potential problem area are based onBritish turbine cascade

Gas fired pressurized boiler technology (fireside) is available.As indicated above, materials properties for long, high- temperature lifeoperating under the required stress and temperature conditions in therequired fireside and potassium side environments require detailed evalua-tion. However, the related experience is sufficient in both the firesidecorrosion and potassium areas- that no serious basic problems are anticipated.

Low NOX combustor technology for application to the gas fueled pres-surized boiler is generally available, but requires careful design, and,also probably development effort for the specific application.

Low Btu coal gasification and purification technology is currentlyavailable for a coal energy conversion efficiency of 77%, and advancesin this technology to permit efficiencies as high as 86% can be expected.

Pressurized fluidized bed boiler technology for application to thereference cycle is in a very early stage of development, at least in thiscountry. Many aspects of this technology require better definition in-cluding basic heat transfer, control, sulfur removal, NOx generation

93

Page 99: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

control, limestone regeneration, coal and limestone feeding. Boiler tubefireside corrosion in t.he bed containing large amounts of CaSO^ requirescareful evaluation, although preliminary Uritisli data for stainless steeland other alloys, such as high chromium and cobalt alloys, are very en-couraging(l7). However, basic feasibility has been established and re-ports of the British effort indicate that pressurized fluidized bedshave been operated at pressure levels as high as 6.0 x 10^ N/m2 (6atmospheres) at 1255 K (1800°F) bed temperature with NOx and SC>2 emissionswithin EPA regulations.

In general, it may be stated that insofar as present availabilityof required technology is concerned the gas fueled pressurized boilersystem is ahead of the pressurized fluidized bed system. However, asindicated above, the latter system is believed to possess a greaterfuture potential for efficient low cost coal energy conversion.

DEGREE OF DEVELOPMENT RISK AND ASSOCIATED COSTS

In the previous section the status of the various elements of thetechnology required for the gas fueled pressurized boiler potassium-steam-gas power system and for the coal fueled pressurized fluidized bedboiler system has been summarily evaluated, and the technological ele-ments requiring future development have been identified. The largestarea of undeveloped basic technology is that of the pressurized fluidizedbed potassium boiler and its closely associated feeding, limestone re-generating, particulate removal auxiliary components. This major com-ponent involves development risks in connection with a number of potentialproblems, including fireside tube corrosion, sulfur removal, limestoneregeneration, NOx emissions, combustion efficiency, stability, and uni-formity, transient and part load operation, and assured delivery of anonerosive and nondeposit-forming gas flow to the gas turbine. Becauseof this situation the gas fired pressurized boiler system offers, atthis point in time, a more readily available body of basically proventechnology than does the coal fired system. Both systems share risk inconnection with the scaling up of the potassium flow loop componentsfrom the size of the laboratory units which have been proven, to thatof a 1200 MW size powerplant. (The proposed modular approach to the de-sign of potassium components for this plant will, of course, ease thisproblem.) This scaling up will involve important manufacturing processchanges, and, also, for economic reasons, some changes in material selec-tions. The most critical potassium technology related problem areasare large potassium turbine disc manufacturing, and assurance of re-liability and steam leak incident damage control in the potassium con-denser/steam generator.

For each of the two systems the recommended development programsare listed in Tables 30 and 31. These programs have been divided intotwo categories, basic development problems and design verification pro-grams. The latter category covers many of the previously mentionedproblems associated with scaling up proven potassium component technology.The estimated costs include only the work necessary to bring the elementsof the technology to a state of readiness for design and construction ofa pilot plant. They do not include the costs of such a plant.

94

Page 100: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 30. - GAS FUELED PRESSURIZED BOILER SYSTEMDEVELOPMENT PROGRAMS

Basic Development Problem Programs Est. Dev. Time Est. Dev. Cost

1. Large Superalloy Turbine Disc

2. Large TZM Molybdenum TurbineDisc

3. Low NO Pressurized CombustorX

5 years

3 years

1.5 years

$ 3.0 x 10

$ 3.5 x 10(

$ 0.5 x 106

Design Verification Programs

1. Potassium Boiler

2. Potassium Condenser/SteamGenerator

3. Potassium Control Valves

4. 'Turbine Shaft Seal

5. Materials & Processes

6. Potassium Component Facility

2 years

2 years

2 years

2 years

5 years

$ 1.5 x 10

$ 1.7 x 10€

$ 0.8 x 106

$ 0.5 x 106

$ 5.0 x 106

$ 3.0 x 10e

Total Development Cost $19.5 x 10C

95

Page 101: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 31. - COM, FIRED PRESSURIZED FLUIDIZED BED BOILERSYSTEM DEVELOPMENT PROGRAMS

Basic Development Problem Programs Est. Dev. Time Est. Dev. Cost

1. Pressurized Fluidized Bed 5 yearsPotassium Boiler

This is a very large and complexprogram involving both firesideand potassium side phenomena.(The unknowns are almost entirelyon the fireside). Firesidecorrosion problems of boilertubing embedded in CaSO, requireinvestigation.

2. Large Superalloy Turbine Disc 5 years

3. Gas Turbine Erosion Test 2 years

$40.0 x 10C

$ 3.0 x 10

$ 1.0 x 10(

Design Verification Programs

1. Potassium Condenser/SteamGenerator

2. Potassium Control Valves

3. Turbine Shaft Seal

A. Materials & Processes

5. Potassium Component Facility

2 years $ 1.7 x 10

3 years

2 years

5 years

$ 0.8 x 10°

$ 0.5 x 106

$ 5.0 x 106

Total Development Costs $55.0 x 10

96

Page 102: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

CONCLUSIONS AND RECOMMENDATIONS

As discussed in the section Powerplant Costs (p. 74), the capitalcosts of the pressurized fluidized bed system are $143 million more thanthose of the pressurized boiler system for a 1200 MW powerplant; the costof the coal gasification plant is not included in this cost comparison.The annual operating costs are equal for the two topping cycle systems be-cause the higher capital costs of the fluidized bed powerplant tend tooffset the higher fuel costs for the pressurized boiler powerplant.

The potassium topping cycle powerplant can have a significant im-pact with regard to national goals such as air and water pollution, andconservation of natural resources. The major air pollution problem withburning coal is the formation of S02 and its subsequent release to theatmosphere in the stack gas. The potassium topping cycle powerplantwith a supercharged furnace would use clean gas from a coal gasificationplant and the problems of S02 and particulate emissions would be eliminated.The CO and NO emissions can be controlled by the design of the combustionsystem.

An alternate potassium topping cycle powerplant with a fluidizedbed combustor wou]d use coal directly, without gasification, and thesulfur would be removed by chemical reaction with limestone in thefluidized bed combustor. NOx would be controlled by removing heat inthe bed with potassium boiler tubes, thus limiting the combustion tem-perature rise.

Considering conservation of fuel resources and thermal pollution,the pressurized fluidized bed topping cycle system has a coal to busbarefficiency of 0.499 compared with 0.392 for a coal burning steam power-plant calculated for comparable conditions. This means the toppingcycle system would use 21% less fuel and reject 35% less heat than asteam plant of the same power output. The pressurized boiler toppingcycle system has a coal to busbar efficiency of 0.422 (0.8 x 0.528) dueto the coal to gas conversion efficiency of 80%. This means that thepressurized boiler system would use 18% more coal than the fluidizedbed system. Considering the large number of powerplants that will bebuild in the next thirty years, and the scarGity of fuel, the 18% betterfuel consumption of the pressurized fluidized bed system, compared withthe pressurized boiler system, make the development of the fluidizedbed boiler a consideration, in spite of its greater development cost.

Since most of the components are common to both systems and thepressurized boiler technology is developed, it is recommended that thepressurized boiler topping cycle be developed through the pilot plant

97

Page 103: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

stage. It is also recommended that the pressurized fluidized bed boilerbe developed in parallel. Then, if the fluidized bed program is success-ful, the pilot plant could be retrofitted with a fluidized bed boilerbefore proceeding to the demonstration powerplant. If technical progressis not limited by funding, the estimated starting date of a demonstrationplant is 1983 to 1985.

98

Page 104: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

APPENDICES

Appendix A. - Potassium-Steam Topping Cycle Code

A computer code was written to calculate the performance of potas-sium-steam topping cycles; a schematic diagram of the cycle is shown inFigure 1. The steam cycle includes high, intermediate and low pressureturbines with extraction from each for feedwater heating. The steamcycle can have up to two reheat stations. Although most of the heatadded to the steam comes from the condensing potassium, there is pro- ••vision for a water economizer where heat from the furnace can be addedto the water directly. Various steam condensate cooling schemes can beused including run-of-river, and wet or dry cooling towers.

The potassium cycle includes a turbine which has provision for con-densing at two temperature levels. The lower temperature potassiumvapor provides heat to the steam until the steam temperature reaches apinch-point temperature difference between the steam and condensingpotassium vapor, the value of which is specified by input. The highertemperature potassium vapor supplies the rest of the heat to the steamincluding reheat if specified. The output of the steam system is speci-fied by input to the code, and the potassium flow rates and power outputare determined by the heat requirements of the steam cycle. The potas-sium cycle has provision for extraction for feed, heating if desired.

The furnace calculations determine the air and fuel flow rates re-quired to provide the heat requirements of the cycle. A pinch-point tem-perature difference between the furnace gas and the potassium boilingtemperature can also be specified. An air preheater is inlcuded in thecycle, the effectiveness of which is usually calculated to maintain thedesired stack gas temperature.

The component efficiency assumptions used in the cycle performancecode are shown in Table 32. The efficiencies for the steam componentswere taken from reference 10. The efficiencies for the potassium turbinesare lower for larger pressure ratios due to the presence of condensedliquid and the associated loss. The efficiency levels are based on cal-culated results from a turbine design code which gives performance levelsin agreement with small size potassium turbine tests(2l).

The cost portion of the code makes use of cost correlations foreach component in the entire cycle. In order to do this, certain addi-tional assumptions and calculations are required. As an example, thefeedwater heaters are accounted for by using a heat balance in the per-formance portion of the code. In the cost section, assumptions are madeof the heat transfer coefficients (based on a wide range of operational

99

Page 105: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 32. - COMPONENT EFFICIENCIES

Component Efficiency Source

Steam Cycle Turbines

HP .854 (Ref. 10)

IP .88

.891 (Ref. 10)

LP .92 .

.927 (Ref. 10)

Generator .985 (Ref. 10)

Pumps .85 (Ref. 10)

Potassium Cycle Turbines

Sta. 30 to 35 .90 (Ref. 21)

Sta. 30 to 31 .85

Sta. 30 to 37 .80

Potassium Pumps .80 (Ref. 34)

See Figure 1 for locations of stations 30, 31, 35, and 37.

100

Page 106: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

data) and the heal: transfer area calculated. The costs are then computedby a correlation Involving the unit's heat transfer tmrface area.

All steam system components were modeled using the correlating equa-tions of reference 10. In numerous cases, however, modifications weremade to match the reference steam plant, Bull Run Unit 1. All costs forsteam components are calculated in dollars appropriate to the Bull Runsite (rural Tennessee) and time period (1962-1966). Since the costs forthis study were calculated for the second half of 1972 (1972.5) at theUSAEC Model site, Middletown USA (a fictitious site in the Northeast),cost transforms were made for each component to generate revised costs.The technique used was basically that of the CONCEPT code (ref. 9) inwhich the cost associated with each component is broken down into frac-tions for site labor, site material, factory labor, and factory material.From published sources, the rates of each class were retrieved both forthe Bull Run time and location, and for Middletown USA in 1972.5. Byapplying these rates, the cost of each component can be transformed intime and space. This calculation was incorporated into the code. Typicalescalation (for a modified Bull Run plant) was a factor of 2.05, thecost rising from $126 x 106 to $258.8 x 106. Other features of the codeinclude the calculation of operating costs, expressed as $/year as wellas mills/kwh.

In developing the cost models for .Task I, it was decided that con-ceptual designs for the potassium components were required before thecost models could be used with confidence. Preliminary studies of pulver-ized coal, pressurized gas and fluidized bed type of potassium vaporgenerators were made so that adequate cost models could be generated.

To improve the potassium turbine cost models, layout drawings wereprepared for the limiting conditions. Flow path designs were calculatedfor the potassium turbines for the 1033 K (UOO°F) and 1200 K (1700°F)topping cycles. The 1033 K (1400°F) cycle has four 126 rad/s (1200 rpm)turbines of six stages each, with vapor extraction after the fourth stage.The 1200 K (1700°F) cycle has two single-stage high pressure (HP) turbinesat 188 rad/s (1800 rpm) and four seven-stage low pressure (LP) turbinesat 1061 K (1450°F) turbine inlet temperature and 126 rad/s (1200 rpm),with vapor extraction after the fifth stage. Preliminary mechanical de-sign of these turbines was done to evaluate their feasibility and estimatetheir cost.

Costs were estimated from the weight and specific material cost,and from estimates of the labor required to build them. The similarity,in size, of the potassium turbines to the low pressure sections of thesteam turbines was used to estimate the labor costs.

For each potassium component an estimate of the cost for a specificdesign was made, and was scaled to other power levels using trends notedfor similar steam components.

101

Page 107: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

During the performance analysis study several modifications weremade to the topping cycle performance code. For the systems with pres-surized furnaces, a compressor ,and gas turbine were added to the system.The furnace acts as the gas turbine combustor; after providing heat forboiling potassium, the combustion gases enter the gas turbine which drivesthe compressor and also an electrical generator. The gas turbine ex-haust is used to heat the feed water in an economizer, resulting in onlya small waste of heat in the stack. The other modification is in thefeedwater heater calculations. The number of extractions from the steamturbines was increased and a parallel flow system was designed so thatsome of the feedwater heating could be done by the gas turbine exhaustgas. The revised topping cycle schematic diagram is shown in Figure 22.

102

Page 108: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

\

auTqani /SBf)

60

5P.

I

9

0)oaB,2•o<uN

^8)0)

MO

Oi-l

eg

•sCO

CMCM

800

103

Page 109: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Appendix B. - Topping Cycle Performance Calculation Code - Base Case

The topping cycle performance calculation code was described inAppendix A. A list of nomenclature is presented in Table 33. A print-out of the performance code for the base case is shown in Table 34 inthree pages. The first page lists all the input specified for this case.The second page shows the fluid state conditions at the various stationsin the cycle, which correspond to the schematic diagram, Figure 1. Thethird page lists the output values calculated by the program. Both con-ventional and S.I. units are shown.

104

Page 110: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 33. - NOMENCLATURE

TOPPING CYCLE PERFORMANCE CODE - INPUT VALUES

ETAT1 Steam turbine efficiency from sta. 1 to sta. 2ETAT2 Steam turbine efficiency from sta. 3 to sta. 4ETAT3 Steam turbine efficiency from sta. 3 to sta. 5ETAT4 Steam turbine efficiency from sta. 6 to sta. 7ETAT5 Steam turbine efficiency from sta. 6 to sta. 8ETAGEN Generator efficiencyMW Steam plant net output, MWeETAP Hater pump efficiencyETAP2 Potassium pump efficiencyETA6 Potassium turbine efficiency from sta. 30 to sta. 35ETA7 Potassium turbine efficiency from sta. 30 to sta. 31ETAS Potassium turbine efficiency from sta. 30 to sta. 37ETAF Efficiency term for furnace heat lossFAIR Fuel to air ratioFHV Fuel heating value, Btu/lbm (J/kg)E Preheater effectivenessWX Exhaust gas reclrculation ratioDTPP Pinch point temp, diff., T37-Tsteam, °F (K)PI Steam pressure at sta. 1, psia (N/cm2)P2 Steam pressure at sta. 2, psia (N/cm2)P3 Steam pressure at sta. 3, psia (N/cm2)PA Steam pressure at sta. 4, psia (N/cm2)P5 Steam pressure at sta. 5, psia (N/cm2)P6 Steam pressure at sta. 6, psia (N/cm2)P7 Steam pressure at sta. 7, psia (N/cm2)P10 Water pressure at sta. 10, psia (N/cm2)P15 Steam pressure at sta. 15, psia (N/cm2)P27 Hater pressure at sta. 27, psia (N/cm2)P30 Potassium pressure at sta. 30, psia (N/cm2)P31 Potassium pressure at sta. 31, psia (N/cm2)P33 Potassium pressure at staP3A Porassium pressure at staP35 Potassium pressure at staP37 Potassium pressure at staTl Steam temperature at sta. 1, °F (K)T3 Steam temperature at sta. 3, *F (K)T6 Steam temperature at sta. 6, °F (K)T12 Hater temperature at sta. 12, *F (K)T14 Water temperature at sta. 14, °F (K)T16 Hater temperature at sta. 16, °F (K)T17 Condenser water inlet temp., °F (K)T21 Gas temp, leaving furnace, °F (initial value) (K)T27 Hater temperature at sta. 27, *F (K)T30 Potassium temperature at sta. 30, °F (K)T32 Potassium temperature at sta. 32, °F (K)T3A Potassium temperature at sta. 34> *F (K)A3 Code for sulfur extractionA6 Code for condenser water coolingCASEND Program control

_•— F j- _ __ \»-/ »-*** j

33, psia (N/cm2)34, psia (N/cm2)35, psia (N/cm2)37, psia (N/cm2)

105

Page 111: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 33. - NOMENCLATURE (Cont'd.)

DTT Temp, diff. in condenser, T8-T18, *F (K)DTK Teap. change in cooling water, T18-T17, *F (K)DTA T17-dry bulb air temp., *F (K)DISC Subcooling, T8-T9, *F (K)TDB Dry bulb air temperature, *FTWB Wet bulb air temperature, *FRUNTYP Program controlDTGK Pinch point temp, diff., gas to potassium, *F (K)

106

Page 112: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 33. - NOMENCLATURE (Cont'd.)

TOPPING CYCLE PERFORMANCE CODE - CYCLE PARAMETERS

WB2 Bleed flow fraction at station 2WB4 Bleed flow fraction at station 4WB7 Bleed flow fraction at station 7Wl Steam flow rate at station 1, Ibs/hr (kg/s)QBOIL Enthalpy change across steam boiler, Btu/lb (J/kg)QRHT1 Enthalpy change across 1st reheater, Btu/lb (J/kg)QRHT2 Enthalpy change across 2nd reheater, Btu/lb (J/kg)QCOND Enthalpy change across condenser, Btu/lb (J/kg)PUMP1 Enthalpy change across main feedwater pump, Btu/lb (J/kg)PUMP2 Enthalpy change across secondary feedwater pump, Btu/lb (J/kg)WOUT Total gross work from steam system, Btu/lb (J/kg)WNET Net work from steam system, Btu/lb (J/kg)ETAS Steam system efficiencySTHR Steam heat rate, (Btu/hr)/kw (W/kw)HKSGI Enthalpy of steam at boiler pinch-point, Btu/lb (J/kg)WCOND Condensing water flow rate, Ib/hr (kg/s)QKVAP Enthalpy change across furnace in potassium, Btu/lb (J/kg)QREJ Heat injected to steam boiler, Btu/hr (W)WKOUT Total gross heat rate of K-turbine, Btu/hr (W)PUMPS Main K-pump power, Btu/hr (W)PUMP6 Secondary feed pump power, Btu/hr (W)WKNET Net potassium system power, Btu/hr (W)W30 Potassium flow rate at station 30, Ib/hr (kg/s)W31 Potassium flow rate at station 31, Ib/hr (kg/s)W35 Potassium bleed flow rate at station 35, Ib/hr (kg/s)W37 Potassium flow rate at station 37, Ib/hr (kg/s)PMW Net power of potassium system, MWETAK Potassium system efficiencyQADD Total power transferred from the furnace to the potassium and

steam (water) lines, Btu/hr (W)WAIR Combustion air flow rate, Ib/hr (kg/s)WFUEL Fuel flow rate, Ib/hr (kg/s)HAIRMX Enthalpy of gas at combustion, Btu/lb (J/kg)TAIRMX Temperature of gas at combustion, °F (K)TGAS2 Temperature of gas after vaporizing potassium 8F (K)TGAS3 Temperature of gas after heating liquid K, °F (K)TGAS4 Temperature of gas leaving the furnace, °F (K)ETAB Furnace efficiencyTMW Total cycle power, MWETA Total cycle efficiency

107

Page 113: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 34. - COMPUTER PRINT-OUT FOR BASE CASE

CASE i TUCKING CYCLE INPUT VALUES 06/12/73 21 SOP. EOT

.•iu. KAPAMETEi< sru •

UMTS

i .2 .3.A ,b .6./ .b.9.

10.1 1 .12.l'3.14.i b .i 0.

17.18.

19.20.21 .22.23.24 .25.26 .27.28.29.30.

fcTAl'iEi'AlV.EfAi'3ETAF4ETAi'-Jr.'l AO EN/.;,<t'TAfET.Ar2fci'AoE l'A7ETA8ETAFFAIrtFHVE•*XDTPP

PiH2PJS^•4

Hbr"T>

P/

MO

PlbP27r'JOr-3 1

0.0.0.0.0.0 .

9140.0.0.0.0.1 .

bb-48808919209279bb

85'...80090CHbO800000

sUN

.1.ITS

0.00601 1900.0

0.0.

700300

50.0

3b 1 5600b '1 02. 001 /21 7250

3600r'OO

3600152

.00

.00

.00

. 00

. 00

.00

.00

. 00

. 00

.Oo

.17

.41

2.76609E+07

27.8

2423413J/21371 18i 1834

2442•jbl

248210

1

.bl

.69

.32

.90

.59

.59

.47

.1 1

.58

.1 1

.46

.60

NO.

31 .32.33.34.35.36.37.38.39.40.41 .42.43.44.45.46.47.48.49.50.51 .52.53.54.bb.56 .57.

PARAMETER

P33P34P35P37TlT3T6TI2T14T16T17T2 1T27T30T32T34A3A6CASHNUOTTDTPDTAD'i'SCTDF<TWRWUNl'YPDTGK

STD .UiHTS

35.33.10.

1 .1 000 .1 000 .

/03 .275.377.513.60.

656.705.

1400.1 000 .1001 .

1 .2.1

20.22.20.

1 .78.72.

niJTH100.

00000010ou00

HO000000/ ( )0000000000

005000000050

00

sUN

242260

H10

81004 O'108464540289019647

103381081 1

1 1121 10

298294

bD

.1 .ITS

.13

.75

.89

.70

.93

.93

.37

.Ib

.82

.37

.09

.82

.04

.15

.93

.48

.1 1

.50

. 1 1

.56

.71

.65

.50

108

Page 114: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 34. - COMPUTER PRINT-OUT FOR BASE CASE (Cont'd.)

CLi£ CALCULATIONS - PART I « J-'LUIl.' 5TAT:: SUMMARY

STA'i loii HNU . ( P S I A ) ( OHG-F ) ( dTU/L

i234•j

O/

.»Q

10

i 1

\ 213U15lo17Id1 '•)20<? l^

242:>26

£j

303!323334

35363/

'S"j 1 :;600t>4J2001 721 725o

2

^3600

3600

3600800

36001414

800200

bO3600

.I'j21

3o3310iu

1

.0

.O

.O

. 09 ^ i

.0

.0

. 13

.5

.0

.0

.0

.0

.0

.7

.7

.0

.0

.0

.0

.4

. 1

.0

.0

.0

. 0

.1

1000

1 000

7'J3

1351341 44

27 D

377

51392

1 1578

750962290

281705

1 400

1000

1001

13221 000

• )

.0

.:*

.0

.0

.-3

. )

.0

.0* 3

.0.0 •. -J. -J.0

.0

•;J

.0

.0

.0

. 1• *o

14211255151913951377137712531052

102I 12161251261355

1278502

6083

294349179

509355250789

1 1 8H1071283283283

1 157345

1039

*

«

9

m

«

,8) (l;TU/Ld/DF>

7 1.470132I 1.72803967 1 . 743 i 501081263!4b0

b2.'•$

,3b2hi

r j 1.1 14372 0.882617ri

9

4 0.9667163 O.H5570

(FT3/LB)

0.01627

0.01 /27

0.02232

0.02378

3b 345. /

109

Page 115: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 34. - COMPUTER PRINT-OUT FOR BASE CASE (Cont'd.)

Uit:

i .2 .3.4.b .o .7 .F .9 .0.1 .2 .3.4.

Ib.16.

1 7.1 8 .19.20.21 .22.?'•!.

24.2b.26.27.2K.

?9 .

30.

•il .V.33 .34.3b.36.'•17.

3c .39.

STHA.;. bL!-;HL< FLGH RMCTI-JN # STA.STtAM bLRF.D FLUri F PACT I ON ti STA.bitAM DLEED FLOW FI/ACTIJN a STA.TuTAL STi-AM FI OH R/'TF W STA. 1 ..HEAT AOi>-'D TO PRIMARY STFAM ....HEAT AOut-t) H F IRST KFH'~ATHEAT Aljij^.i i -j St -CGf 'D REHEATHhAT ivEJPCTE-') IN CUNDFNSERF EED.'M f UK PUMi-1 t'JGKKA U X . FFcDHATER PUMP WORKSTEAM TUHBINU OUTPUT .NET STEAM TUKb INE LiUTPUTSTEAM SYSTEM EFFICIENCYSTEAM H''-~A'T R A T ESTEAM ENTHALPY is riiilLER PINCH-HOICOOLING MATER FLGrt RATE

THE POTASSIUM SYSTEM

h'EAi A OOh- '•) TO HUTA'iSI UMHEAT REJECTED TO STEAM BOILER ..GROSS PO.ibK OF HOTASSIU.'l TURBINEHOHE'K JF MAIN POTASSIUM PUMP ....POWER OF AUX. POTASSIUM FEED PUMPNhT PUHER FROM P O T A S S I U M ' SYSTEM .POTASS I UiV FLJiJ RATi-' •'«> STA. 30 ..POTASS I ij.v FLJii RATH «* SfA 31POTASSIUM" BLEED FLiM RATE & STA.POTASS I U,V, FLOi^ RATE & STA 37 ..NEI ELEClRIC POViER FROM K-SYSTEMPCJTASSIili/i SYSTEM EFFICIFNCY

THE CG.-^USTIfJN SYSTEM

HEAT TRANSFERRED i;; FURNACE ....CLJj.\LJuSTIiiN AIR FLQif RAT'-"FUEL F'LJn RAT*-' 'GAS EN'TlALP/ *• COMf USTIONGAS TEMP. ^ CuMtjUST'I'JIJGAS Tc-'.-iH. AF"Ti:R K-'v APCJhlZATION ..GAS Tt ••/..-. AFTi -K LIOUID <-HEATINGGAS il-Mr LEA -1 ING THE FURNACE ..COMSUSTIjiJ EF! :ICIFNCY

OVERALL VALUES

iuTAL Ci'CLE PiJkiFKTOTAL C/CLE E : :FICH:NCY

Jb, C/B24 ... HB41 ... W R /

HI. . . QHOIL... ORHT1. . . QRHT2... QCOND... PUMP1... PUMP2.... AGUT.... hNET.... FTAS.... STHRNT, HKSGI... WCOND

... O K V A P

.... ORE J

. . . WKGUT

... PUMP5, PUMP6... WK.NET..... rt 30

H 3 |35, W35

H37PMn

.... FTAK

.... OADD

. . . . KAI R

... WFUFL

.. HAIRMX

.. T A I R M X

... T( -AS2

. . . TGAS3

... TCMS4

.... FT AH

TMWETA

SID. ENG.

0./9J470.07 I 670.062136.4674F.+06919.3213.40.0

641 .18.59744... 5433502.6279489.68720.43238015.391381.991 .846IEK)B

STD. ENG.

5.1.

j. i y i -r/0.071670.06213

STD. EN3.

H.3276F>091 . 1 768E+077.766YE+05867.242800,1519,1395963

,98.26.46.63

= 0.9010

STD. ENG.

= 1202.97= 0.44423

8.1657E+022. 1370E+064.9608E+053.bbQ6E.+OI1.4902E+06

1.0006E+041.I6H3E+06I.I383E+060.43232347.513.212.3E+062.3309E+04

S.I.

9.0498E+025.4674F>091 .0025E+091 .2516E+065.1211 E+0 11 .0013E+097. 1482E+062.079IE+064.0467F+025.0687E+00288.96780. 154d

2. 1036E+061 .6()13E*092.9361E+083.66b5E+051 .49U8E+012.9325E+089. 02 5 3E +022.6250E+025. I004E-026.3997E+02288.90780.1548

S.I .

.4389E+09,46'.)8E+03,80o3E+01.01

181 1 .4/1099.41

6372

0.9010

S.I.

1202.970.44423

030,

110

Page 116: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Appendix C. - Variation of Performance and Cost with Cycle Conditions

The topping cycle code described previously was used to determinethe sensitivity of topping cycle performance and costs to cycle varia-tions. In Table 35 are shown the cycle variations that were made. Thevalues in the left hand column are those associated with the base case.The other values were used one at a time in the parametric study; a totalof 15 cases were therefore examined, in addition to the base case. Theprincipal performance results are shown in Figure 23, where the base casevalue of each parameter is indicated by a round symbol. As expected, themost significant parameter was potassium turbine inlet temperature; in-creasing it from 1033 to 1200 K (1400 to 1700°F) increased cycle effi-ciency from 0.444 to 0.473 or 6.5%.

The base case topping cycle assumed two potassium condensing tempera-tures, 811 K (1000°F) to supply heat to the pressurized water until itreaches the pinch point temperature difference, and 866 K (1100°F) tosupply the rest of the heat, including steam reheat. The upper rightplot shows the effect of varying the lower condensing temperature. Al-though the plot shows cycle efficiency gains by condensing at tempera-tures lower than 811 K (1000°F), the potassium vapor pressure is lessthan 0.7 N/cm^ (1 psia) and the large volume flow rates make the potas-sium turbine design more difficult.

The third parameter that had a significant effect was the watereconomizer temperature rise, shown in the lower plot of Figure 23. Thisresult indicates that the water economizer should not be used but ratherthe water should be heated by the condensing potassium. This variationincreased the cycle efficiency from 0.444 to 0.457, or 2.9%. All othercycle variations had a small effect on performance.

The cycle variations run in the performance sensitivity study des-cribed above were run with the cost model to determine the sensitivityof system costs with cycle variations. The results are shown in Table 36.The base case is a topping cycle with 1033 K (1400°F) potassium turbineinlet temperature and 811 K (1000°F) for the lower potassium condensingtemperature. The steam cycle is the Bull Run cycle selected previously.Each case has a single variation from the base case, which is describedin the first two columns. The cycle efficiencies are based on a wetcooling tower to cool the condenser. The capital and yearly fuel costsare given in millions of dollars, the fuel assumed to cost $0.38 per GJ($0.40 per million Btu). The last column shows the cost of electricityin mills per kw hr. The plant size is 1200 MW.

Ill

Page 117: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

oo

OOCM

Omo\

enoo

oo

oo

ON»X

O

oom

-TCOo

ooCM

oinmOO

moo

OOinCM

00

oosc CM

CM

Iw

oo

VO

bozMPL,PL,

8i

oo

roroO

OOO

oo

Om

ooCM

o>«x

O

CMON

mmCO

CM*s-CM

tnCO

a3

P*o

CUM

4JCOM0)

I

0)C

•H

|

H

COcotO4JoP-.

PL,

)M3

Cfl

0)H

0)T3CO

CJ

COco

oCu

CM

•acto

c0)CU

CUpq

IC

•Ha

4JCO(11M

•O01CU

•HCOCOCO

CUCO

s01M4-1COM0)p.

MCUN

•H

g

Coowo

CMS3

CM

3COCO<uMO,

cu4JW

CO4JCOCU

<U4-1C/»

<4-l

O

•o

112

Page 118: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

xoccu

w

U>»U

1050

1400

1100 1150

K Boiling Temp., K

1 I1500 1600K Boiling Temp., °F

.46,-

g•HO

<4-lW

<uU

6*

ic.45

.44

I

1200

1700

.47 •-

.46

I 1

750 800 850

K Condensing Temp., K

I I900 1000 1100

K Condensing Temp., 8F

I

0 Base Case

0 50 • 100HO Economizer Temp. Rise, K

1 | |0 100 200

H_0 Economizer Temp. Rise, °F

Figure 23-. - Variation of Cycle Efficiency With Cycle Parameters(Based on Constant Stack Gas Temperature)

113

Page 119: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

4J 31co 3:

O "*"*en

O j^^

4) rH

W jg

4JCO >-30 S

U cnO .^jf*H(U MrH "Hu s

HrtlW

x-v faW vO^* " ! O HrH -•C rH TO5 N-x 4Jw oS =3 H

g o ^1 ° ' «£ 2w Jj

^^

2 00M

S3 t>3 ^•5>8555wpS ijn «>W 4J OJPH Qj 3

§ !_j

CO

« >vO /a";CO ***

wH^

1

Co•H*J(X•HVJUCOOla

nimCOCfl

COr .CM

OO

C*Osr-j

CM

in00

mCM

0

omCO

OS

mCM

CM-a--a

0)COcflo0)COCO

PQ

rH

f*^inCM

CO

OSCM

CM

-a-OS

j.CM

VO

mmCO

cooCM

rHO

vO

x~\

fao0mmrH

X

vOrHrHrH

OJ

ij4-1cflt-t

a,aSHjs/j

0)cniH

rl

CM

r^voCM

CO

vOOSCM

CM

\0CM

-a-CM

-a-COvOCO

m

COCM

CMCO

r*

y-N

fa

0OO

rH

^OOCMrH

0)

-)4J(0

aa9H

J« J

0)entH3CO

oOsrH

OO

mr*^CM

CM

mmvOCM

CM

r^coco

CO

inCM

inCM

CO

x^fao00rHi-H^^

vOvO00

0)

3

CO

0)O.

3H

-0Cou&4

cn

C?flj

6

•*

mvO~*CO

rHmCO

CM

in

mCM

ovOVOCO

mCOCOCM

rHOS

X-N

faO0inOS

COoo

0)

3

«

0)(X

§H

TJCOo*NXj

0)

S5tQ

6

m

vOr**.CM

CO

OSOSCM

CM

CMOO

mCM

OS

OS-3-CO

comCM

vO•*

^-^faoinCM

«OS•

COH

E~*

^•

4JO.

•sC•H

vO

COCOCM

CO

rHOCO

CM

0OS

mCM

rH

OinCO

ovO

CM

mCO

••faooorH

*VO•

mm

g-4

^•

4-1Pn

•sC-rl

"

vOooCM

CO

CMOCO

CM

rHCO

mCM

r~

omco

-a-vo

CM

CO-a-

^^faeO0H

«

vO«

mm

g1

iH4-1

X

73

01

M

oo

rHOCO

CO

vOOCO

CM

CO00

inCM

vO

rHmco

CM

r^CM

-a-

^^faoOOCM

W

HrHrH

00C•H4JCO0)

TJCU0)

M

OS

COCMCO

CO

COrHCO

CM

O

mCM

O

COmco

coCO

CM

COCO

^~^fao00CO

14f^VOrH

JP4Jcfl0)

ffi

7301(U

M

OrH

CMmCM

00

CMOSCM

CM

CO

mCM

i-H

CMinCO

mr^CM

COCM

m

•fao

CO

S*5

co

H

•ao0url0)

srHrH

COCOCM

CO

r-.COCM

CM

rH

inCM

CO

COmCO

in

ooCM

OSvO

m* -

fa1

0O^

s^

0

H

•COo

rl0)4-1

CMrH

CMCOCO

CO

<rrHCO

CM

COOS

inCM

r-CMinCO

OOJ

CM

oCM

-a-""

'«•HCOP.

OOmCM

CM1^3-CM

rH

OJM3COCO0)Mp-l

§0)4JW

COrH

inrHin00

mvOCO

CM

CMmVOCM

r^OvOCO

CO

-a-CM

r-CM

CO*^

•HCOCL,

00inrH

CM1J.

COorH

HI

3COOJ0)

P-<

a.0)4-1U)

rH

vOinCM

OO

COOSCM

CM

OS

mCM

i-H

OS-3-co

CM

inCM

-3-in

-**^

CM

CO4JcflOJf0>P^

0)4JC/>

•O

mrH

COo-a-CO

-a-COCO

CM

CMCM

VO.•M

rmmco

CM

0ooCM

COf--

CO*^

0

CO4Jcflcu0)pj

0

w0)4_)CO

§.VOrH

114

Page 120: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

These results indicate that the optimum potassium turbine inlet tem-perature is about 1116 K (1550°F). Increasing the potassium lower con-densing temperature to 866 K (1100°F) gave the lowest cost of electricityaccording to the cost model, due to eliminating the low pressure end ofthe potassium turbine.

115

Page 121: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

Appendix D. - Performance Calculations for Selected Cycles

Computer print-outs for the cycles selected for conceptual designare presented as Tables 37 and 38. Table 37 is for the superchargedfurnace topping cycle and Table 38 is for the pressurized fluidized bedcycle. These calculations were made with the modified code shown inFigure 22, and additional nomenclature is presented in Table 39.

116

Page 122: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 37. - POTASSIUM PRESSURIZED-BOILERCOMBINED CYCLE DATA

CASE TQPHNG CYCLE I N P U T VALUES I?./. I 1/73 15: I3EST

NO.

1 .2.3.4.5.6.7.3.y.

10.1 1 .12.13.14.ID.16.17.18.19.

P.O.21 .22.23.24.25.26.?. /.2'i.29.30.

PARAMETER

ETAi 1ETAT2E1A13ETAT4ETAT5ETAGENMriETAPEl AH 2ETA6ETA/ETA8ETAFFAIRFHVEWXDTPPPIP2P3P4PbP6P7P10Plb1-27P30K31

STD.UMTS

0.8.540.8800.8910.9200.927w.985

5820.3500.8000.9000.8500.8001 .000

0.76602000.00.7000.300

50.03515.00600.00540.00420.00172.001 55.001 16.00

3600.00BOO. 00

3600.0030.86

2.41

S.I.UNITS

4.64889E+06

27.82423.51

413.69372.32289.58118.59

.1 06 . 8779.98

2482. 1 1'/A. 58

2482. 1 121 .28

1 .66

NO.

31 .32.33.34.35.36.37.38.39.40.

*41 .*42.*43.

44.45.46.47.48.49.50.51 .52.53.54.'55.56.57.58.59.60.

PARAMETER

P33P34P35P37TlT3T6T12T14TI6T17T21T23T30T32T34A3A6CAS ENDDTTDTRDTADTSCTDBTWBRUNTYPDTGKMNIREADCFFILECRAHRV

STD.UNITS

51 .0049.001 0 . 002.4!

1050.001050.001050.00406.00476.00508.00

60.701 300 . 00250.00

1550.0011 00 . 00

.1 101 .000.3.\5.00

20.001 7 . 40

1 .0078.0072.60

MOTH1OO. 00

0TCCb'FSPFCRAdFILE

S.I.UNITS

35. 1633.786. 89\ .66

838.71838.71838.71480.935 1 9 . 82537.59289.09

1255.37394.26

1 1 1 6 . 48866.48867.04

2.781 1 . 1 19.670.56

298.71295.71

55.50

VALUES AODED FUR EXTRA FEED-HEATERS AND SUPERCHARGER UNIT

61 .62.63.64.65.66.67.68.69.

ETACPRCETAGTKP41P71P72Tl 11Tl 12

0.85015.000.900

0.9000295.00

78.0039.00

266.00300.00

203.4053.7826.89

397. b9'122.04

70.71 .72,73.74,75.76,77.

T12IT122T I41T28A4CSFUELWCDATA F I L E

359.00329.00439.00560.00

20.80000.0300

JPPBDATA

454.82438.15499.26566.48

117

Page 123: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 37. - POTASSIUM PRESSURIZED-BOILERCOMBINED CYCLE DATA (Cont'd.)

CASE 1 CYCLE FLUID STATE SUMMARY 12/11/73 I5H3EST

118

STATIONNO.

123456789

101112131415161718192021222324252627282930313233

- 3435363738

417172

1 1 11 12121122141241251252261262

P(PSIA)

3515.0600.0540.0420.0172.0155.01 16.0

1 .51 .5

3600.0

3600.0

3600.0800.0

3600.014.714.7

800.0420.0

39.03600.0

30.92.42.4

51 .049.010. 010.02.4

295.078.039.0

3600.03600.03600.03600.03600.0600.0295.0172.0

78.01 16.0

T( DEG-F )

1 050.0587.5

1050.0

746.31050.0

115.01 14.0124.8137.0406.0

476.0

508.090.0

110.078.0

806.71800.0832.4250.0

265 . 7666 . 7560.0

1 550.0

t 100.0

1 IOJ .0

1 322 . 11 1 00 . 3

256.0300.0359.0329.0439.0

H S(BTU/LB) (BTU/LB/DF)

1459.3 1.495441282.01546.2 1.74628151 1 .21399.31556.6 1.889031513.81 1 13.8

82.092.8

113.9385.6245.9460.9

1306.4496.758.078.0

308.8577.1315.4170.0509.8429.6

- 234.6707.4246.3

1195.2 1.084831032.9302.5302.7302 . 7

1.1 10.6345.6

1042.5345.8

1464.51459.21374.3232. 1276.4336.6305.8420.7471 .7392.3342.2280.3 ,309.9

V(FT3/LB)

0.01618

0 .01714

0.83871

Q.9U04

0.84967

0.02275

0.02378

Page 124: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 37. - POTASSIUM PRESSURIZED-BOILERCOMBINED CYCLE DATA (Cont'd.)

THi- STEAM SYJTEM STP. EN(>.

AAAAAAAAAAAAAAAAAAAAA

01020304Ob06070809101 112131415161718192021

STEAM BLEED FLOW FRACTION &STEAM DLEED FLOW FRACTION &STEAM BLEED FLOW FRACTION &STEAM BLEED FLOW FRACTION (9STEAM BLEED FLOW FRACTION @STEAM BLEED FLOW FRACTION &STEAM BLEED FLOW FRACTION §STEAM BLEED FLOW FRACTION 8TOTAL STEAM FLOW RATE k STA.HEAT ADDED TO PRIMARY STEAMHEAT ADDED IN FIRST REHEAT .HEAT ADDED IN SECOND REHEATHEAT REJECTED IN CONDENSER .FEEDWATER PUMP WORKAUX. FEEDWATER PUM*> WORK ...STEAM TURBINE OUTPUTNET STEAM TURBINE OUTPUT ...STEAM SYSTEM EFFICIENCY ....STEAM HEAT RATE

STA.STA.STA.STA.STA.STA.STA.STA.

1 .

STEAM ENTHALPY & BOILER PINCH-POCOOLING WATER FLOW RATE:

152441577172

HB15.. WB2.. WB4

KB 41.. WB5. . WB7

HB71WB72

.. .. WlQBOILQRHT1QRHT2OCQNDPUMP1PUMP2

. . UfllJTWNETFTAS;,THR

INT, HKSGI.... WCOND

THE POTASSIUM SYSTEM

B 01 HEAT ADDED TO POTASSIUM QKVAPB 02 HEAT REJECTED TO STEAM BOILER QHEJB 03 GROSS POWER OF POTASSIUM TURBINE ... WKOUTB 04 POWER OF MAIN POTASSIUM PUMP PUMP5B 05 POWER OF AUX. POTASSIUM FEED PUMP, PUMP6B 06 NET POWER FROM .POTASSIUM SYSTEM WKNETB 07 POTASSIUM FLOW RATE @ STA. 30 W30B 08 POTASSIUM FLOW RATE § STA. 31 W3IB 09 POTASSIUM BLEED FLOW RATE @ STA. 35, W35B 10 POTASSIUM FLOW RATE @ STA. 37 W37B II NET ELECTRIC POWER FROM K-SYSTEM PMWB 12 POTASSIUM SYSTEM EFFICIENCY ETAK

THE COMBUSTION SYSTEM

C 01 HEAT TRANSFERRED I;l FURNACE '. OADDC 02 COMBUSTION AIR FLOW RATE -UIRC 03 FUEL FLOn RATE W!-'UELC 04 GAS ENTHALPY i=l COMBUSTION HAIRMXC 05 GAS TEMP. & COMBUSTION TAIRMXC 06 GAS TEMP. AFTER K-VAPOtdZATION TGAS2C 07 GAS TEMP. AFTER LIQUI'D K-HEATING ... TGAS3C 08 GAS TEMP. LEAVING THE FURNACE TGAS4C 09 COMBUSTION EFFICIENCY ETABC 10 NET SUPERCHARGER POWER GAIN AMWC 11 FEEDWATER HEATERS FLOW FRACTION FWHS

OVERALL VALUES

D 01 TOTAL CYCLE POWER TMWD 02 TOTAL CYCLE EFFICIENCY ETAD 03 SYSTEM HEAT RATE (BTU/KW-HR) HTRATED 04 PARASITIC POviER LOSS XMrtINT

00.0000.0

- 2

01758019110121301721010170087801387

0.039049070E+061195. 5254.5145.3889 . 5

10.9308I .8326706.4704693.70700.43487968.58 .1459.461 .2953E+08

STD. ENG.

— ~7

8.9246E+023.3487E+09

0933E+08I628F>06

0817E+085460E+065905E-+06

0,7,4,1 ,0.2.9554E+06204.380J0.1746

SO). ENG.

4.05710+094.9383F.+063.7827H+06974.793164.881934.781798.281584.860.5363413.160.39153

STD. ENG.

1 170.660.528126462.55

28..88740

0.000.0.0.0.0.

S.I .

01758019.1 1012130172101017008780138703904

3.6704E+022.7789E+06

91 64E+053777E*050677E-+065408E+042599E+036422E+066125E*064348

2333.803.3924E+061 .6355E+04

S.I .

0745E+068074E*080775E+084056E-K35

074IE.+087398E+020082E*02

292302520.3.7315E*02204.380J0.1746

S.I.

1.1882E+096.235IF.+024.7761E+022.2658E+0620J3.641330.251254.421135.850.5363

413.160.39153

S.I.

1.170.660.52812

28.88740.119

Page 125: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 38. - POTASSIUM PRESSURIZED FLUIDIZED BEDCOMBINED CYCLE DATA

CASE 2 T O P P I N G CVCLE INPUT VALUES 12/1 1/73 lb:13EST

NO .

1 .2.3.4.5.6.7.8.9.

10.i 1 .12.13.14.15.16.17.18.19.20.21 .22.23.24.25.26.2 7 .28.29.30.

61 .62.63.64.65.66.67.68.69.

PARAMETcH

EFAnETAf2ETAT3ETAT4ETAT5ETAGENMhETAPETAP2ETA6ETA7ETA8ETAFFAIRFHVEWXDTPPPIP2P3P4P5P6P7P10P15P27P30P31

VALUES

ETACPHCETAGTKP41P71P72T i l lTl 12

STD.UNITS

0.8540.8800.8910.9200.9270.985

7500.8500.8000.9000.8500.8001 . 000

0.066011900.0

0.7000.300

50.03515.00

600 . 00540.00420.00172.001 55.001 1 6 . 00

3600.00800.00

3600.0015 .17

2.41

ADDED FOR

0.8509.00

0.9000.8700295.0078.0039.00

256.00300.00

S.I.UNITS

2.76609E+07

27.82423.51

413.69372.32289.58118.59106.8779.98

2482. 11551 .58

2482. 1 110.46

1 .66

• NO.

31 .32.33.34.35.36.37.38.39.40.

*4I .*42.*43.

44.45.46.47.48.49.50.51 .52.53.54.55.56.57.58.59.60.

EXTRA FEED-HEATERS

203.4053.7826.89 .

397 . 59422.04

70.71 .72.73.74.75.76.77.

PARAMETER

P33P34P35P37TlT3T6T12T14T16T17T21T23T30T32T34A3A6CASENDDTTDTRDTADTSCTDBTWBRUNTY PDTGKMNIREADCFFILECRA8RV

STD.UNITS

35.0033 . 001 0. 002.41

1050.001050.001 050 . 00406 . 00476.00508. 0060.70

1700.00 1250.00

1400.00 11 1 00 . 001 101 .00

3.3.45.00

20.0017.40

1 .0078.0072.60

BOTH100.00

2TCCEFSPFCRABFILE

S.I.UNITS

24. 1322.756.891 .66

838.71838.71838 . 7 1480.935 1 9 . 82537.59289.091 99 . 82394.26033., 15866.48867.04

2.781 1 ..119.670.56

298.71295.71

55.56

AND SUPERCHARGER UNIT

T121T122T 1 4 1 •T28A4CSFUELweDATA FILE

359.00329.00439.00

, 560.001

0.40000.0200

JPPBDATA

454.82438.15499.26566.48

120

Page 126: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 38. - POTASSIUM PRESSURIZED FLUIDIZED BEDCOMBINED CYCLE DATA (Cont'd.)

b'iATIUiii-lCJ.

123456789

101 1121314

' 151617181920212223242526272829303132333435363738

417172

1 1 11 121211 22141241251252261262

t>

(HS IA)

3515.0600.0540.0420.0172.0155.01 16.0

1 .51 .5

3600.0

3600.0

3600.0800.0

3600.014.714.7

800.0420.0

39.03600.0

15.22.42.4

35.033.010.010.02.4

29^.073.039.0

3600.03600.03600.03600.03600.0600.0293. 0172.073.0

1 16.0

Tf DKG-F)

1050.0•587.51050.0

746.31050.0

115.01 14.0124.8138.0406.0

476.0

508.090.0

1 10.078.0

623.51700.0

917.5250.0

265.7695.9560.0

1400.0

1 JOO.O

. 1 1 0 1 .0

1322.1i 1 00 . 3

256 . 0300.0359.0329.0439.0

H S(bTU/LR) (l.VfU/LR/DF)

V(FT3/LB)

1459,1282.1546,151 1 .1399,1556.1 5 1 3 .1 1 1 3 .

82.92.

1 14,385,245,460,

1306,406,

58,

30223688088699470

78.0

262.2549.0337.4170.0509.8429.6234.6764.8246.3

I I 88.81071 .2302.5302.6302.7

I 157.4345.6

1078.1345.7

1464.51459.21374.3232. 1276.4336.6305.3420,471.392.3342.2280.3309.9

.7

.7

1.49544

1 .74628

1.88903

0.01618

0.01714

1.114370.88261

0.96671

0.89056

0.02275

0.02378

121

Page 127: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

iHE STEAM SYSTEM

TABLE 38. - POTASSIUM PKESSURI/.ED FLUIDIZED BEDCOMBINED CYCLE DATA (Cont'd.)

STD. ENG.

A 01A 02A 03A .04A 05A 06A 07A 03A 09A -10A IIA 12A 13A l A.\ *+

A 15A 16A 17A 1 8A 19A 20A ?.:

B 01B 02B 03B 04B 05B 06B 07B 03B .09b 10B 1 1B 12

C 01C 02C 03C 04C ObC 06C 07C 03C 09C 10C 1 1

STEAM BLEED FLOv'l FRACTION 9 STA. 15STEAM BLEED FLOU FRACTION & STA. 2STEAM BLEED FLUH FRACT'ION § STA. 4STEAM BLEED FLO. FRACTION @ STA. 41STEAM BLEED FLUn FRACTION § STA. 5STEAM BLEED FLOri FRACTION & STA. 7STEAM BLEED FLON FRACTION @ STA. 71STEAM BLEED PLOW FRACTION .§ STA. 72TOTAL STEAM FLOW KATE <•? STA. i ....HEAT ADDED TO PRIN.ARY STEAMHEAT A X'LTJ I N F I RST R EMEATHEAT ADDED IN SECOND REHEATHEAT REJECTED IN CONDEilSER:~ i 'IT Hi/; A 'i'.- If LJI If ' '-> './HI I.-'/

AU'X. FEEDHATFR HUMP WORKSTEAM TURBINE OUTPUT '.NET STEAM TURBINE OUTPUTSTEAM SYSTEM EFF I CT EMC YSTEAM MEAT RATESTEAM ENTHALPY a RUILER PINCH-POINTCOUL i NG HATER FLOW RATH „

THE POTASSIUM SYSTEM

HEAT ADDED TO POTASSIUMHEAT REJECTED TO STEAM BOILERGROSS POtVER OF POTASSIUM TURBINE ..POrtEH GF MAIN POTASSIUM PUMPPOWER OF AUX. POTASSIUM FEED PUMP,MET POi-iuR FROM POTASSIUM SYSTEM ...POTASSIUM FLiiW RATE <S STA. 30POTASSIUM FLuH RATE ® :JTA. 31POTASSIUM LiLhED FUM RATE «f STA. 35PUTAooIUiVi FLG*i RATE M STA. 37liET ELECTRIC POHER FROM K-SYSTEM . ,POTA So I UM SYSTEM E FF I C I ENCY

THE CUMbUSTIUN SYSTEM

HEAT TRANSFERRED IN FURNACECOMBUSTION ' A I R FLOrt RATEFUEL FLUH RATEGAS ENTHALPY 3 COMBUSTIONGAS TEMP. & COMBUSTIONGAS TEMP. AFTER K-VAPOL'IZATION . . . .GAS TEMP. AFTER LIQUID K-HEATING ..GAS TEMP. LEAVING THE FURNACECOMBUSTION EFFICIENCYNET SUPERCHARGER POWER GAINFEED/MTER HEATERS FLOW FRACTION ...

W R 1 5.. WB2.. WB4

/<B4I. . WB5.. WB7

rtB71, rtB72

. , , Wl. QROIL. ORIIT1. ORHT2. QCOND

L) [ iff n 1• r U I A r I

. PUMP2

. . /JOUT

. . /WET

.. -TAS

.. STHR, HKSGI. WCOND

. QKVAP

.. QREJ

. WKOUT

. PUMP5PUMP6

. MKNETW30

, , , W31, W35. . . W37. . . PMW.. ETAK

. . QADD

.. WAIR

. WFUELHAIRMXTAIRMX

. TGAS2

. TGAS3

. TGAS4

.. ETAB

. . . AMW

. . i-WHS

OVERALL VALLES

D 01 TOTAL CYCLE rU/JEK TMWj 02 TOTAL CYCLE EFFICIENCY ETAD 03 SYSTEM HEAT HATE (3TU/KW-HR) HTRATED 04 PARASITIC POnER LOSS XM^INT

0.0.0.0.0.

= 3

0.01R470.020060127201805010630091901453 -

0.040597616E+061187.32541 44,88.3,

10.85051 .9163703.6187690.85140.43567955.171459.461.6638E+08

STD. ENG.

.0

.7

.0

S.I.

0.018470.020060.012720.018050.010630.009190.014530.04059

4.7494E+022.7599E+005.9051E+053.3o4U'+052.0525E+062.5;!2I E+044.4!>54F>OJI .6J55E+001.6058E+O60.43562329.873.3924E+062.1007E*04

S.I.

8.8614E-1-024..1 131E+096.0286E+OH9.1284E+054.4190E+016.0195E+085.321 1 h>061 .95()5EH)03.4920E+023.3702E+06173.72470.1277

2.0596E+061 .2046E+091 .7056E-+082.6735E+051 .2942E+01I .7630F.+OR6.71H4E+022.4627E+024.4090F.-0?4.2553E+02173.72470.1277

STD. ENG.

4.7I53E+091 .0197E+076.730IE+05

887.502870.371777.041698.671438.660.5888

276.080.4113^

STD. ENG.

1 1 70 .9 10.498996839.83

28.89272

S.I.

1.38IOE+091.2875E+038.4974E-+012.0029E+061850.021242.621199.081054.630.5M88

276.080 .4113S

S. I .

I 1 7(.'.'' 1

122

Page 128: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

TABLE 39. - ADDITIONAL NOMENCLATURE FOR REVISED CODE

ETACP Compressor efficiencyRC Compressor pressure ratioETAGT Gas turbine efficiencyK Ratio of gas turbine to compressor pressure ratios

P41 Steam pressure at station 41, psia (N/cm )P71 Steam pressure at station 71, psia (N/cm )P72 Steam pressure at station 72, psia (N/cm2)Till Water temperature at station 111, °F (K)T112 Water temperature at station 112, °F (K)T121 Water temperature at station 121, *F (K)T122 Water temperature at station 122, °F (K)T141 Water temperature at station 141, °F (K)T28 Gas temperature at station 28, °F (K)IREAD Program keyCFFILE Cost factor fileCRABRV Cost output fileA4 Furnace type indicatorCSFUEL Cost of fuel $/106 BtuWC Cooling flow fractionDATA FILE Name of input data fileAMW Gas turbine output, MWeFWHS Fraction of feed heating by steamHTRATE Heat rate, Btu/Kw-hrXMWINT Parasitic power, MWe

123

Page 129: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

REFERENCES

1. Fraas, A.P., "A Potassium-Steam Binary Vapor Cycle for a Molten-Salt Reactor Power Plant", ASME 66-GT/CLC-5, 1966.

2. Fraas, A.P., "A Potassium-Steam Binary Vapor Cycle for Better FuelEconomy and Reduced Thermal Pollution", ASME 71-WA/Ener-9, 1971.

3. The Bull Run Steam Plant, Technical Report No. 38, TVA, Knoxville,Tennessee, 1967.

4. Gorzegno, W.P. and Zoschak, R.J., "The Supercharged Steam Generator:Some Aspects of Design and Pressure Level Selection", ASME 66-GT/CMC-68,1966.

5. De Van, J.H., Personal Communication, 1-8-74.

6. Moor, B.L. and Schnetzer, E., "Three-Stage Potassium Vapor Test",NASA CR-1815, May 1971.

7. Mausteller, J.W., Tepper, F., and Rogers, S.J., "Alkali Metal Handlingand System Operating Techniques", Gordon & Breach, Science Publishers,New York, 1967.

8. Fraas, A.P., "The Safety and Environmental Problems Posed by Opera-tion of a Potassium Vapor Topping Cycle", ASME 73-WA/Ener-6, Nov.1973.

9. DeLozier, R.C., Reynolds, L.D. and Barnes, H.I., "CONCEPT, Computer-ized Conceptual Cost Estimates for Steam-Electric Power Plants",ORNL-TM-3276, ORNL, October 1971.

10. "The U.S. Energy Problem", ITC Report C-645, Inter Technology Corpora-tion, November, 1971.

11. "Steam-Electric Plant Construction Cost and Annual Production Ex-penses, Twenty-fourth Annual Supplement - 1971", Federal PowerCommission, Washington, D.C., February 1973.

12. Ruber, I.A., "Status of Technology of Commercially Offered Lime andLimestone Flue Gas Desulfurization Systems", Presented at EPA FlueGas Desulfurization Symposium, New Orleans, La., May 14-17, 1973.

13. "Guide for Economic Evaluation of Nuclear Reactor Plant Designs",NUS-531, NUS Corp., Rockville, Md., January 1969.

124

Page 130: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

14. Robson, F.L., et al., "Technological and Economic Feasibility ofAdvanced Power Cycles and Methods of Producing Nonpolluting Fuelsfor Utility Power Stations", PB 198392, United Aircraft ResearchLaboratories, Dec. 1970.

15. "Studies of Fluidized Lime-Bed Coal Combustion DesulfurizationSystem", Esso Research & Engineering Co., G.R.U. 13GFGS.71.

16. Argonne National Laboratory Annual Report for National Air PollutionControl Administration, July 1969 - June 1970.

17. "Pressurized Fluidized Bed Combustion", Final Report to Office ofCoal Research, Nov. 1973, National Research Development Corporation,London.

18. Archer, D.H., et al., "Evaluation of the Fluidized Bed CombustionProcess", Vol. II Technical Evaluation, Westinghouse ResearchLaboratories, Pittsburgh, Pa., November 1971, PB 212-960, APTD-1166.

19. Rossbach, R.J. and Wesling, G.C., "Two-Stage Potassium Test Turbine",I - Fluid Dynamic Design and Performance, NASA CR-922, February1968.

20. Rossbach, R.J., Wesling, G.C., and Lemond, W.F., "Three-Stage Potas-sium Test Turbine, Final Design", Volume I - Fluid Design TopicalReport, NASA CR-72249, General Electric Company.

21. Wesling, G.C., "Three-Stage Potassium Turbine Performance TestSummary", NASA CR-1483, General Electric Company, December 1969.

22. Moor, B.L., and Schnetzer, E., "Three-Stage Potassium Vapor TurbineTest", Final Report, GESP-547, General Electric Company, August1970.

23. Rossbach, R.J., and Kaplan, G.M., "Potassium Testing of CondensateRemoval Devices for Rankine Space Power Turbines", 719059, Proc.1971 IECEC, Boston, Massachusetts, August 1971.

24. Zimmerman, W.F'. , Hand, R.B., Engleby, D.S., and Semmel, J.W., Jr.,"Two-Stage Potassium Turbine: IV-Materials Support of Performanceand Endurance Tests", NASA CR-925, February 1968.

25. Nichols, H.E. and Fink,.R.W., "Two-Stage Potassium Turbine: II-Mechanical Design and Development", NASA CR-923, February 1968.

26. Eckard, S.E., "Two-Stage Potassium Test Rubine: Ill-Test Facilities",NASA CR-924, February, 1968.

27. Schnetzer, E., "3000-Hour Test - Two-Stage Potassium Turbine", FinalReport, NASA CR-72273, General Electric Company, July 1967.

125

Page 131: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

28. Peterson, J.R., "High Performance 'Once-Through' Boiling of Potassiumin Single Tubes at Vapor Temperatures From 1500°F to 1750°F", NASACR-842, Contract NAS 3-2528, August 1967.

29. Bond, J.A. and Converse, G.L., "Vaporization of High-TemperaturePotassium in Forced Convection at Temperatures From 1800°F to2100°F", NASA CR-843, Contract NAS 3-2528, July 1967.

30. Sawochka, S.G., "Thermal and Hydraulic Performance of PotassiumDuring Condensation Inside Single Tubes", NASA CR-851, ContractNAS 3-2528, 1967.

31. Peterson, J.R., ."Computer Program for the Thermal Design of Two-Fluid 'Once-Through' Potassium Boiler", Nuclear Systems Programs,MSD, General Electric Company, prepared for NASA under ContractNAS 3-9426, December 1968.

32. Bond, J.A. , "The Design of Components for an Advanced Rankine CycleTest Facility", Fifth Intersociety Energy Conversion EngineeringConference, Las Vegas, Nevada, September 21-25, 1970.

33. Bond, J.A. and Gutstein, M.U., "Component and Overall Performanceof an Advanced Rankine Cycle Test Rig", Presented at the 1971 Inter-society Energy Conversion Engineering Conference, Boston, Massachusetts,August 3-5, 1971.

34. SAN-631-1, Byron Jackson Co., September 1969.

NASA-Langley, 1975 -

Page 132: POTASSIUM TOPPING CYCLES FOR STATIONARY POWER · PDF filePOTASSIUM TOPPING CYCLES FOR STATIONARY POWER R. J. Rossbach Prepared by GENERAL ELECTRIC COMPANY Cincinnati, Ohio 45215 for

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

WASHINGTON. D.C. 2O546

OFFICIAL BUSINESS

PENALTY FOR PRIVATE USE S3OO

POSTAGE AND FEES PAIDNATIONAL AERONAUTICS AND

SPACE ADMINISTRATION

SPECIAL FOURTH-CLASS RATEBOOK

POSTMASTKK: If Itmlollverublp (Section 15SPostal Manua l ) Do Ni> t Re tu rn

"The aeronautical and space activities of the United States shall beconducted so as to contribute . . . to the expansion of human knowl-edge of phenomena in the atmosphere and space. The Administrationshall provide for the widest practicable and appropriate disseminationof information concerning its activities and the results thereof."

—NATIONAL AERONAUTICS AND SPACE ACT OF 1958

NASA SCIENTIFIC AND TECHNICAL PUBLICATIONSTECHNICAL REPORTS: Scientific andtechnical information considered important,complete, and a lasting contribution to existingknowledge.

TECHNICAL NOTES: Information less broadin scope but nevertheless of importance as acontribution to existing knowledge.

TECHNICAL MEMORANDUMS:Information receiving limited distributionbecause of preliminary data, security classifica-tion, or other reasons. Also includes conferenceproceedings with either limited or unlimiteddistribution.

CONTRACTOR REPORTS: Scientific andtechnical information generated under a NASAcontract or grant and considered an importantcontribution to existing knowledge.

TECHNICAL TRANSLATIONS: Informationpublished in a foreign language consideredto merit NASA distribution in English.

SPECIAL PUBLICATIONS: Informationderived from or of value to NASA activities.Publications include final reports of majorprojects, monographs, data compilations,handbooks, sourcebooks, an'd specialbibliographies.

TECHNOLOGY UTILIZATIONPUBLICATIONS: Information on technologyused by NASA that may be of particularinterest in commercial and other non-aerospaceapplications. Publications include Tech Briefs,Technology Utilization Reports andTechnology Surveys.

Details on the availability of these publications may be obtained from:

SCIENTIFIC AND TECHNICAL INFORMATION OFFICE

N A T I O N A L A E R O N A U T I C S A N D S P A C E A D M I N I S T R A T I O N

Washington, D.C. 20546