post damage assessment

116
Postdisaster damage assessment Binay Shrestha [email protected] Download damage assessment guideline published by DUDBC from Facebook page “building code implementation program”

Upload: binay-shrestha

Post on 04-Aug-2015

436 views

Category:

Engineering


11 download

TRANSCRIPT

Page 1: Post damage assessment

Post‐disaster damage assessment

Binay [email protected]

Download damage assessment guideline published by DUDBC from Facebook page “building code implementation program”

Page 2: Post damage assessment

1. Important short‐term aims for inspections include:safe use of streets adjacent to damaged buildingssafe occupation of buildings for:

continued use, especially emergency facilitiesminimization of impact on commercial activityminimization of displacement of people

assessment of the need for temporary works such as shoring, temporary securing and making safesaving property from unnecessary demolition

conserving heritage fabricminimizing economic impact for the owners and community

Page 3: Post damage assessment

2. Inspections also contribute to longer‐term recovery measures, by assisting with:

cost of damage estimatesdetermining the aid and resources required for permanent recoveryobtaining engineering, scientific and insurance data to improve disaster mitigation measures.

Page 4: Post damage assessment

I. Windshield:  Overall scope of damageII. Rapid : Assessment sufficient for most 

buildingsIII. Detailed:  Closer assessment of difficult or 

complex buildings IV. Engineering : Consultant engaged by owner

Page 5: Post damage assessment
Page 6: Post damage assessment
Page 7: Post damage assessment

The objective of the Rapid Evaluation is to quicklyinspect and evaluate buildings in the damaged areawith a minimum manpower available at the time ofemergency.The rapid evaluation can be done by civil,structural, geotechnical engineers and architectswith experience on building construction andtrained on rapid evaluation methodology.Rapid evaluation is done just after the earthquaketo assess the safety of buildings to judge whetherpeople can enter the building or not. It can be doneby visual inspection.

Page 8: Post damage assessment

Right to inspect??Observe expected and unexpected damageAssume that significant aftershocks will occurJudgment in assessing risk from damage

Page 9: Post damage assessment

Safety of assessment team comes first:CollapseFalling hazardsOther hazards

Page 10: Post damage assessment

All possible safety precautions should beexercised as building under study could be indilapidated condition and could loss its stabilityin whole or in parts causing casualty.

The team must comprise at least two personnel,both trained in assessment works.

Page 11: Post damage assessment

The team personnel must wear safety hatswhen assessing the buildings.

Before entering a house, its condition should bewell assessed as the house could be indangerous state.

Wherever the uncertainty exists and team is indoubt, it is better to be conservative.

Page 12: Post damage assessment

Before going into steps:

Behavior of buildings during earthquake

Page 13: Post damage assessment

Corner SeparationOut of plane failure, delamination, gable wall failureIn plane failure, diagonal crackingFloor/roof connection failure

Page 14: Post damage assessment
Page 15: Post damage assessment
Page 16: Post damage assessment
Page 17: Post damage assessment
Page 18: Post damage assessment

Soft Story DamageShort Column DamageBeam Column Joint FailureStrong Column Weak BeamLap Splice DamageInfill panel Damage

Page 19: Post damage assessment
Page 20: Post damage assessment
Page 21: Post damage assessment
Page 22: Post damage assessment
Page 23: Post damage assessment
Page 24: Post damage assessment
Page 25: Post damage assessment

Step‐ I: Study the house from outside, take a walk around the house and do visual inspection

Visual inspection from outside and inside of thebuilding is the only method applicable for rapidevaluation of buildings.Generally, earthquake damage to concrete andmasonry walls (common building types in Nepal) isvisible on the exposed surface.Observable types of damage include cracks, spallsand delaminations, permanent lateral displacement,and buckling or fracture of reinforcements.

Page 26: Post damage assessment

Step‐II: Enter the house to do assessment inside if it is safe to do so.Enter the building if entering the house is safe.Inspect the house from inside as done from outside. Identify cracks, spalls and delaminations, joints opening, permanent lateral displacement, and buckling or fracture of reinforcements. Come out of the houses as soon as possible.

Page 27: Post damage assessment

Step‐III: Fill‐up the form, note the observationsRapid evaluation form is given in Annex III of the guideline. The key information to be collected is:

Information about evaluatorBuilding Description: Owners’ name, Address, contact no, total plinth area, type of construction, Type of floor, type of roof, primary occupancy etc.Damage conditionsEstimated building damage ratioSafety status (Posting)Further Actions

Page 28: Post damage assessment
Page 29: Post damage assessment
Page 30: Post damage assessment
Page 31: Post damage assessment

When filling the form, the evaluators must use:General knowledge of construction –

Professional experience –

Good judgment ‐

Page 32: Post damage assessment

Six main parameters are evaluated during rapid evaluation process. Safety of the building is judged primarily based on these six parameters. If the building has any of condition 1, 2, 3 or 5 as per the Table, the building is categorized as unsafe. If the building has condition 4 or 6, it can be termed as unsafe or area unsafe.  

Page 33: Post damage assessment

S.N. Conditions Posting

1 Building has collapsed, partially collapsed, or moved off its foundation Unsafe

2 Building or any story is significantly out of plumb Unsafe

3

Obvious severe damage to primary structural members, severe cracking of walls, severe cracking of columns, beam‐column joints, buckling of reinforcement bars,  or other signs of severe distress present

Unsafe

4 Obvious parapet, chimney, or other falling hazard present Area Unsafe

5 Large fissures in ground, massive ground movement, or slope displacement present Unsafe

6 Other hazard present (e.g. fallen power line, fallen tree)Unsafe or Area Unsafe

Page 34: Post damage assessment

If these entire six factors give positive result the building is obviously safe. The remaining buildings with damage that do not fall under these six factors are questionable buildings and based on conditions limited entry or restricted use. As the purpose of the rapid assessment is to identify the buildings’ safety rapidly, all the buildings that are done rapid assessment should undergo detail assessment.

Page 35: Post damage assessment

Photo 1: Building Partially Collapsed

Page 36: Post damage assessment

Photo 2: Building with a story out ‐of ‐plumb

Page 37: Post damage assessment

Photo‐3: Building with Severe Damage to Primary Structural System

Page 38: Post damage assessment

Photo 4: Building with Severe Damage to Primary Structural System

Page 39: Post damage assessment

Three kinds of posting similar to ATC‐20 are recommended in this guideline also. Posting classifications, colour and description of the posting

• INSPECTED (Green): Appears safe forlawful occupancy

• LIMITED ENTRY/RESTRICTED USE(Yellow): Some restriction on use, controlledby building owner/manager

• UNSAFE (Red): Entry controlled byjurisdiction

Page 40: Post damage assessment

Posting Classification Color Description

INSPECTED Green No apparent hazard found, although repairsmay be required. Original lateral loadcapacity not significantly decreased. Norestriction on use or occupancy

LIMITEDENTRY/Restricted Use

Yellow Dangerous condition believed to bepresent. Entry by owner permitted only foremergency purposes and only at own risk.No usage on continuous basis. Entry bypublic not permitted. Possible majoraftershock hazard

UNSAFE Red Extreme hazard may collapse. Imminentdanger of collapse from an aftershock.Unsafe for occupancy or entry, except byauthorities.

Page 41: Post damage assessment

Inspected posting means habitable, minor or no damage.Green placard is used to identify buildings that have been inspected but in which no serious damage has been found. These structures are in a condition that allows them to be lawfully reoccupied; however, repairs may be necessary

Page 42: Post damage assessment
Page 43: Post damage assessment

Following are the main this classification:Observed damage, if any, does not appear to pose a safety risk Vertical or lateral capacity not significantly decreased Repairs may be required Lawful entry, occupancy and use permitted

Page 44: Post damage assessment

Limited entry or restricted use means damagewhich represents some degree of threat tooccupants.

Restricted Use is intended for buildings that havebeen damaged; yet the damage does not totallypreclude occupying the structure.

It can mean that parts of a structure could beoccupied, or it could be used to denote thosebuildings that can be entered for a brief periodof time only to remove possessions.

Page 45: Post damage assessment

The use of a Restricted Use placard will minimizethe number of buildings which will requireadditional safety assessments becauserestrictions can be placed on the use andoccupancy of the structure until such a time asthe owner can retain an architect or engineer todevelop the necessary repair program.

Page 46: Post damage assessment
Page 47: Post damage assessment

Some risk from damage in all or part of buildingRestricted on

duration of occupancyareas of occupancyUsage

Restrictions enforced by owner / manager

Page 48: Post damage assessment

UNSAFE posting means not habitable, significant threat to life safety. 

The red ATC‐20 Unsafe placard is used on those structures with the most serious damage. 

Typically, these are structures that represent a threat to life‐safety should they be occupied.

Page 49: Post damage assessment

It is important to note that this category does not mean the building must be demolished. This placard carries the statement, "THIS IS NOT A DEMOLITION ORDER" to clarify that the building simply is not safe enough to occupy. 

In the vast majority of cases, structures posted unsafe can be repaired to a safe and usable condition.

Page 50: Post damage assessment
Page 51: Post damage assessment

Following are the main criteria for this classification:Falling, collapse, or other hazard.Does not necessarily indicate that demolition is required.Owner must mitigate hazards to satisfaction of jurisdiction to gain entry.

Page 52: Post damage assessment

The rapid evaluation is carried out just after an earthquake for the purpose of safety evaluation of the buildings so that people can decide to occupy or not enter the building following an earthquake. The result whatever comes from the rapid evaluation MUST NOT BE USED FOR DEMOLITION as many buildings that are assigned as UNSAFE might be possible to restore and retrofit.

Page 53: Post damage assessment
Page 54: Post damage assessment

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa

Red

Page 55: Post damage assessment

Red

Page 56: Post damage assessment

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaYellow

Page 57: Post damage assessment

Aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa

yellow

Page 58: Post damage assessment

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa

Green

Page 59: Post damage assessment
Page 60: Post damage assessment

In detailed Evaluation, buildings are inspected morethoroughly, with more investigation into thevertical and lateral load resisting systems.

The purpose of detailed evaluations is not only toidentify the level of safety but also to identify thebuildings that can be restored and retrofitted orneed to demolish.

Only limited buildings that are difficult torecommend for retrofit or demolition will berecommended for detailed quantitativeassessment.

Page 61: Post damage assessment

However, after detail retrofit design and cost estimation, if the retrofitting cost is higher, it might be suggested for reconstruction. 

General recommendation for feasibility of retrofitting is up to 30% of the reconstruction cost of the same size building. 

Page 62: Post damage assessment

Detailed assessment is conducted after some time of an earthquake to assess level of damage in detail. Main purpose of this assessment is to assess compensation to household, planning for reconstruction activity or to assess level of intervention required for repair and retrofitting.

Page 63: Post damage assessment

Understanding the Characteristics of Damaging Earthquake 

Review of Existing Building Data

it is helpful to assemble the following documents if possible:

Site seismicity/geotechnical reportsStructural calculationsConstruction specificationsAs Built Drawings Foundation reportsPrior building assessmentsNon destructive testing

Page 64: Post damage assessment

Detail evaluation form should be filled in reference with section mentioned above. The detail evaluation should also recommend different grade of damage. The damage grade goes from damage grade 1 to damage grade 5. Different level of damage grades with photographs for masonry and reinforced concrete buildings are given in this guideline.

Page 65: Post damage assessment
Page 66: Post damage assessment
Page 67: Post damage assessment
Page 68: Post damage assessment
Page 69: Post damage assessment

Identification of Damage Levels Masonry Buildings

Page 70: Post damage assessment

70

Damage Grades: RC Frame Buildings

Damage Grades Extent of Damage Suggested post-earthquake actions

G1 Negligible-slight damage (no structural, slight non-structural)

Fine cracks in plaster over frame members or in walls at the base,Fine cracks in partitions and infill

Building need not be vacated, only architectural repairs needed, Seismic strengthening advised.

G2 Moderate damage(slight structural, moderate non-structural damage)

Cracks in columns and beams of frame and in structural walls,Cracks in partition and infill walls, fall of brittle plaster and cladding, falling mortar from joints of wall panel

Architecture repairs needed, Seismic strengthening advised.

G3 Substantial to heavy Damage (moderate Structural, heavy non-structural damage)

Cracks in column and beam at the base, spalling of concrete covers, buckling of steel bars, Large cracks in partitions and infill walls, failure of individual infill panels

Cracks in wall need grouting, architectural repairs required, Seismic strengthening advised

G4 Very heavy damage (Heavy structural , very heavy non- structural damage)

Large cracks in structural elements with compression failure of concrete and fracture of rebars, bond failure of beam bars, tilting of columns, collapse of few columns or single upper floor

Vacate the building, demolish and construct or extensive restoration and strengthening

G5 Destruction (Very heavy structural damage)

Collapse of ground floor or parts of the building Clear the site and reconstruction

Page 71: Post damage assessment

Earthquake damage grades of Masonry buildings with flexible floor and roof

Thin cracks in plaster, falling of plasterbits in limited parts, fall of loose stonefrom upper part of building in rare cases

Building need not be vacated, onlyarchitectural repairs needed, Seismicstrengthening advised

Damage Grade 1

Damage Grade 1

Page 72: Post damage assessment

Thin cracks in many walls, falling ofplaster in last bits over large area,damage to non‐structural parts likechimney, projecting cornices; The loadcarrying capacity is not reducedappreciably.

Architecture repairs needed, Seismicstrengthening advised.

Earthquake damage grades of Masonry buildings with rigid floor and roof

Page 73: Post damage assessment

Large and extensive cracks in mostwalls, roof tiles detach, tilting or fallingof chimneys, failure of individual non-structural elements such as partition/gable walls. Load carrying capacity ofstructure is partially reduced.

Cracks in wall need grouting,architectural repairs required, Seismicstrengthening advised

Earthquake damage grades of Masonry buildings with flexible floor and roof

Page 74: Post damage assessment

Gaps occur in walls, walls collapse,partial structural failure of floor/ roof,Building takes a dangers state.

Vacate the building, demolish andconstruct or extensive restoration andstrengthening

Earthquake damage grades of Masonry buildings with rigid floor and roof

Page 75: Post damage assessment

Total or near total collapse Clear the site and reconstruction

Earthquake damage grades of Masonry buildings with flexible floor and roof

Page 76: Post damage assessment

Identification of Damage Levels in RC Buildings

Page 77: Post damage assessment

Earthquake damage grades of Reinforced Concrete Buildings

Fine cracks in plaster over framemembers or in walls at the base, Finecracks in partitions and infill

Building need not be vacated, onlyarchitectural repairs needed, Seismicstrengthening advised.

Damage Grade 1

Page 78: Post damage assessment

Cracks in columns and beams of frameand in structural walls, Cracks inpartition and infill walls, fall of brittleplaster and cladding, falling mortarfrom joints of wall panel

Architecture repairs needed, Seismicstrengthening advised.

Earthquake damage grades of Reinforced Concrete Buildings

Page 79: Post damage assessment

Cracks in column and beam at the base,spalling of concrete covers, buckling ofsteel bars, Large cracks in partitions andinfill walls, failure of individual infillpanels

Cracks in wall need grouting,architectural repairs required, Seismicstrengthening advised

Earthquake damage grades of Reinforced Concrete Buildings

Page 80: Post damage assessment

Large cracks in structural elements withcompression failure of concrete andfracture of rebars, bond failure of beambars, tilting of columns, collapse of fewcolumns or single upper floor

Vacate the building, demolish andconstruct or extensive restoration andstrengthening

Earthquake damage grades of Reinforced Concrete Buildings

Page 81: Post damage assessment

Collapse of ground floor or parts of thebuilding

Clear the site and reconstruction

Earthquake damage grades of Reinforced Concrete Buildings

Page 82: Post damage assessment

Exercise

Page 83: Post damage assessment

DG1

Page 84: Post damage assessment

DG1

Page 85: Post damage assessment

DG4

Page 86: Post damage assessment

DG1

Page 87: Post damage assessment

DG2

Page 88: Post damage assessment

DG2

Page 89: Post damage assessment

DG4

Page 90: Post damage assessment

DG2

Page 91: Post damage assessment

DG3

Page 92: Post damage assessment

DG3

Page 93: Post damage assessment

DG3

Page 94: Post damage assessment

DG3

Page 95: Post damage assessment

DG3

Page 96: Post damage assessment

DG4

Page 97: Post damage assessment

DG4

Page 98: Post damage assessment

DG4

Page 99: Post damage assessment

DG2

Page 100: Post damage assessment

DG4

Page 101: Post damage assessment

DG5

Page 102: Post damage assessment

DG5

Page 103: Post damage assessment

DG4

Page 104: Post damage assessment

DG4

Page 105: Post damage assessment

DG4

Page 106: Post damage assessment

DG5

Page 107: Post damage assessment

DG4

Page 108: Post damage assessment

DG5

Page 109: Post damage assessment
Page 110: Post damage assessment

DAMAGED SUSPENDED CEILING

Page 111: Post damage assessment

TOPPLED SHELVING (FURNISHINGS)

Page 112: Post damage assessment

GROUND DISPLACEMENT

Page 113: Post damage assessment

BUILDING FOUNDATION SETTLEMENT DUE TO SOIL LIQUEFACTION

Page 114: Post damage assessment

BUILDING DAMAGE DUE TO LATERAL SPREADING

Page 115: Post damage assessment
Page 116: Post damage assessment