poseidon med activity 5

22
POSEIDON MED Activity 5- Risk Assessment OntheMosWay project University of Piraeus Monday 23 rd of November 2015

Upload: vunhan

Post on 12-Feb-2017

217 views

Category:

Documents


0 download

TRANSCRIPT

POSEIDON MEDActivity 5- Risk Assessment

OntheMosWay

project

University of Piraeus

Monday 23rd of November 2015

Poseidon Med anatomy

POSEIDON MED is the first Cross European Border project which aims to introduce LNG

as the main fuel for the shipping industry and develop a sufficient infrastructure network

of bunkering value chain.

It focuses in the eastern Mediterranean region with five Member States (Cyprus, Greece,

Italy, Croatia and Slovenia) involved.

It is a partnership between gas suppliers , shipping companies, Port Authorities, Technical

organisations etc.

It is officially included in ‘Juncker package’ Candidate projects.

Objectives of Activity 5

• The objective of this activity is to complete a risk assessment and establish risk

acceptance criteria which will address hazards and operability issues related with

LNG as a marine fuel.

• Risk qualification will be presented as a product of the likelihood (frequency) of any

adverse occurrence, and the impact of such an adverse effect (consequence).

So, what is risk?

Hazard

something with the potential to cause an adverse consequence

e.g. a flammable material

Consequence

harm as a result of a hazard being realised

e.g. fatality from ignition of a flammable material

Likelihood

the chance that the consequence occurs

e.g. a frequency of 1 in 100 years or a probability of 0.01

Risk:The chance that something bad happens - a combination of hazard likelihood and

consequence

4

Vessels Retrofit

Risk Assessment on vessels retrofit and installations: 6 vessels under investigation

The overall scope of work for the risk assessment of the vessels involved in the study should cover the

following as a minimum:

LNG fuel system and bunker station on-board the receiving ship

Bunkering system and offloading station on-board the bunker tanker

The 6 pilot vessels under examination are:

• Cruise ferry: “FESTOS PALACE”, of Minoan Lines

• Cruise Ferry: “SUPERFAST I”, of Superfast

• High Speed Passenger ferry: “HIGHSPEED 6” of Hellenic Seaways Maritime SA

• Modern Pure Car Carrier : “NEPTUNE GALENE”, of Neptune Lines

• Converted Car Ferry: “ARIADNE” of Hellenic Seaways Maritime SA

• Typical Cargo Vessel: “MARINE LEGEND I

Assessment of Risk Based Designs (ARBD) Process

Stage 1

Design & Safety

Statement

Stage 2

Risk

Assessment

Stage 3

Revision (supporting studies)

Stage 4

Final Design

Review

ENDSTAR

TCriteria

Satisfied

No

Yes

6

ARBD Questionnaire sub sections

• The questionnaire that was used during the Vessels workshop focused on the following

issues:

A. Fuel Tank – Protective Distance

B. Fuel Tank – Below Deck – Fuel tank within a Fuel Storage Hold Space (FSHS)

C. Tank Connection Space (TCS) – Below Deck

D. Fuel Preparation Room (FPR) – Below Deck

E. Fuel Tank – On-Deck

F. Tank Connection Space (TCS) – On-Deck

G. Fuel Preparation Room (FPR) – On-Deck

H. Pressure Relief Valves (PRVs)

I. Gas Valve Unit (GVU) / Gas Regulation Unit (GRU) – valves regulating supply to consumers

J. Master Gas Fuel Valve (MGFV)

K. Bunkering Station (BS)

Methodology used

• Screening reports workshops facilitated by

LR experts:

The workshop uses a pre-prepared question

set developed by LR as part of its process to

screen the suitability of designs and

arrangements for “gas as fuel”

Rule criteria follow the LR rules for the

classification of Natural Gas Fuelled ships

and the IGF code

Based on the outcome and comments of the

screening reports an Approval in Principle will

be issued for the vessels.

Vessels Installations

• Key Technical issues

Tank Connection Space arrangements ( Categorisation of spaces)

Vent location

Bunkering rates and operations

Tank arrangements in relation with IGF provisions

Standardising connections and manifolds

Shiptype influences decisions (double hull or high speed , small size)

Vessels Installations

MINOAN LINES – FESTOS PALACE ARBD

Workshop

• Completion of the 69 point questionnaire of the

ARBD process

• Despite an ambitious enclosed space tank location,

no major showstopper identified

• Points for further consideration were among other

the vent location and the tank connection space

access arrangement

Vessels Installations

• SUPERFAST FERRIES – SUPERFAST I ARBD

Workshop

• Completion of the 69 point questionnaire of the ARBD

process

• An opendeck arrangement of LNG tanks, no major

showstopper identified

• Points for further consideration were the vent position as

well as SIMOPS and exclusion zones

• Improved alternative tank arrangements could result

from this consultation

• Major showstopper identified in relation with the exact

port layout and operations, this alarmed us , triggered a

preliminary review

Vessels Installations

• NEPTUNE LINES – NEPTUNE GALENE

• Completion of the 69 point questionnaire of the ARBD

process

• Arrangement of LNG tanks, in car decks 1-2, no major

showstopper identified, favourable conditions for retrofit

• Points for further consideration were the vent position as

well as SIMOPS and exclusion zones, point identified for the

bunker station

• Improved alternative tank arrangements resulted from this

consultation

• First Gas Retrofit Concept Survey onboard a Greek vessel

• Conclusion, A good design to proceed with!

Vessels Installations

• HELLENIC SEAWAYS– HIGHSPEED 6

• Completion of the 69 point questionnaire of the ARBD

process

• Case revealing problems identified for smaller ships

• Bunkering station proximity to LNG tanks , Exclusion Zone

requirements constitute a potential showstopper

• Conclusion, more focus to be shed on small designs

Posts Infrastructure

The aim of the risk assessment will be to cover the

significant components that are addressed during the design

of a new LNG infrastructure. The main aspects that will be

covered are:

• Bunkering System and off-loading station for the

receiving ships

• Storage and bunkering procedures

• Examination of the bunkering system design

arrangement (position, lay-out,

• Structural integration, equipment)

• Exclusion zones

The result of this sub-activity will be a report (HAZID)

including risk assessment of bunkering and off-loading

station for the receiving vessels, risk assessment of the

exclusion zones and risk assessment on the storage and

bunkering procedures.

HAZID Methodology

Compliance with the following:

• ISO 31010 Risk Assessment Techniques

• open group discussion with all team specialists having a direct input into the proceedings under the

direction of the HAZID Chairman.

• Site Evaluation Review. Address specific site issues related to the proposed location for bunkering operations

• Ranking of identified Risks. Critically address potential risks, prioritize using risk ranking methodology and

establish best options available for bunkering operations at port

HAZID Methodology

The evaluation process included the following:

• Undertake a site investigation in order to asses existing/proposed candidate bunkering locations and assess general

area layout

• Identification of potential hazards associated with the LNG bunker barge port approach and berthing alongside for ship-

to-ship (STS) bunkering operations at proposed jetty(s). Address impact on existing ship traffic management at port.

• Identify potential hazards associated with LNG bunker truck operations and jetty-to-ship (JTS) bunkering operations at

proposed jetty (s). Address traffic impact of LNG trucks in the wider Limassol Port area.

• Identify potential hazards associated with the proposed options with regards to the shore location, installation and

operation of a future LNG storage facility which can provide replenishment to both bunker barge and/or bunker trucks

operating within Port Authority areas. Critically compare between the two operations.

• Assess the adequacy of the proposed marine facilities, jetty facilities and the proposed bunkering storage layout design

for ensuring the safety of the surrounding area; establish the Regulatory requirements for project compliance.

• Perform a round table discussion of potential failure mode scenarios and emergency response procedures and critically

assess potential societal impact.

Port Infrastructure

• Establishing Safety in Piraeus Port

• Based on the findings of the HAZID study, the supply

infrastructure and the proposed LNG bunkering operations

judged not to present any intolerable risks, not any risks

significantly greater than those found to be acceptable for

conventional fuel bunkering operations at ports.

• The major events of marine failure, truck transportation

failure, LNG bunker transfer failure, LNG/gas release, and

control/isolation failure have been considered in all aspects

of the proposed operations and appropriate mitigation

measures were identified to reduce the risks.

Port of Piraeus HAZID study

• The study identified a number of potential

operational and bunkering system drawbacks

which could cause a reduction in operational

safety.

• However, it is accepted that specific risk critical

issues will be further mitigated by Risk

Assessment activities during Poseidon Med

phase II and that Piraeus Port Authority, based

on the experience gained, will establish LNG

Bunkering Procedures in order to identify the

minimum system specifications, operating

requirements, safety checklists and competence

levels to be met.

Port of Limassol HAZID workshop

• The intended scope of the Site Evaluation HAZID study was to apply a rigorous format of

examination to the proposed area(s), facilities, ship types, equipment and operational

activities in order to identify the best bunkering operational solution

• and to demonstrate that all credible accidental events have been considered and appropriate

mitigation procedures are in place to ensure safe operations.

Port Infrastructure

• Establishing Safety in Limassol Port

Layout particularities of Port, envisaged offshore

support area

Difficulties in adapting current port operations to LNG

Defining responsibilities between port, coastguard and

other authorities , case of Emergency

Other barriers:

Cypriot legislation barriers identified during workshop,

customs procedures

In the next phase more detailed scope is anticipated:

• Building of a pilot vessel LNG fuelled vessel for Venice Port

(1st in the Mediterranean)

10+ vessels approval in principal and detailed review including both new buildings and

retrofits

Continuation and follow up of the regulatory framework from Poseidon Med regulatory

framework gap analysis results

Studies and risk assessment in 5 ports

Shipyard preparedness

Working towards sustainability – next steps ahead

Thank you!

Yvonni- Effrosyni DamianidouT: 0030 210 45 80 916

E: [email protected]