portfolio

12
2010 David Coombes Design Portfolio BEng (Hons) - Manufacturing Engineering and Management Diploma in Industrial Studies (DIS) MSc - Advanced Manufacturing Engineering and Management

Upload: david-coombes

Post on 27-Mar-2016

212 views

Category:

Documents


0 download

DESCRIPTION

Design Portfolio

TRANSCRIPT

2010

David Coombes

Design Portfolio

BEng (Hons) - Manufacturing Engineering and Management

Diploma in Industrial Studies (DIS)

MSc - Advanced Manufacturing Engineering and Management

I believe a top engineer should not only

possess great theoretical and analytical skills

gained through training and experience but

also the ability to inspire innovation, drive

improvement and sustain success.

With the use of a combination of skills sets

(such as: Creativity, Analytical and

Constructive) the individual, and team, can

be propelled to a greater level of

achievement.

My diverse background and skills make me a

valuable member of any team. I bring fresh

ideas grounded in solid engineering

fundamentals, making me an asset in all

problem solving situations.

Take a look…

Feeder-pan Motor Housing Jig

Summary; problems arose in the field with

inaccurate mounting of the motor housing to

the feeder-pan. The housing was mounted

incorrectly and not concentric to the hole.

This lack of concentricity caused the seals to

be misaligned and oil leakages occurred.

Project Description; the need for a jig to aid

the mounting of the housing was essential.

Initial step was to view the parts in question.

A plug was needed which sat in each end of

the housing, and a mock shaft through the

middle. With correct tolerances, this should

ensure concentricity. By using nominal

dimensions for the model, tolerances could

be added to the drawing later.

Treadmill Design

Summary; the task was to design a treadmill

interface, as part of a final year module. The

task included; design and analysis,

manufacture analysis, ergonomic analysis

and structural analysis.

Project Description; during a series of

lectures, and in any spare time, a design was

formulated and analysed from numerous

different perspectives. The images show the

analysis from these viewpoints. These

perspectives were: aesthetics, manufacturing,

ergonomics, stress and strain and marketing.

Phone

Summary; as a purely design focused project; the task was

to design a mobile phone to be used by the less able and

elderly.

Project Description; the initial stage of this project was

information gathering. This came in the form a

questionnaire, answered by the target market. From this

feedback, it was found that; a flip phone, with larger

buttons, simple menu, large display, tactile buttons and

sounds accessibility. With this project solely a design

related one; most of the considerations went into the

design rather than production. Functionality was

considered more than form, due to the nature of the user.

Steel Hydraulic Pipes

Summary; new hydraulic system, lead to the need for new

hydraulic pipes. These pipes connected the manifold to

certain pumps, valves and back to the reservoir.

Project Description; by using the information from

within the office, and from information from the line. It

was relatively simple to understand the ports in which the

pipes should connect. The distance between the two

locations was found, in all three dimensions. This was

double checked using the CAD model, and all avoidances

were found using the model. This distance and the areas to

avoid, dictated the profile of the pipes.

Problems; a major problem occurred due to not being

able to test the pipes until the machine was built. By

organising a one-off batch from the supplier, when the

first machine was ready, all design changes could be

captured. This saved a significant amount of money, due

to not having stock which was not useable, and also

ensured quality was maintained.

Wiring Diagrams

Summary; keeping all diagrams up to date is essential

within any manufacturing organisation. The project

consisted of ensuring all wiring diagrams were up to date

and correct any changes.

Project Description; by contacting the suppliers of the

electric equipment, it was possible to get all drawings for

the systems that they provided. These were then put onto

the system using a 2D CAD system.

Problems; a major hindrance within this project came

with the revision of drawings received from the suppliers.

The suppliers did not want to supply current revisions,

due to the possibility of losing a customer. With this in

mind, all drawings supplied were checked against a

current machine, to ensure they were up-to-date and all

changes were completed if necessary.

Power-Pack Trolley

Summary; there was a need for moving a complete power-

pack (engine) from the bay in which it is built to the bay in

which it is fitted to the machine.

Project Description; the request was made by

production. The first step was to understand the needs of

production; once this was completed a rough drawing was

agreed with them regarding the overall design of the

trolley. Research regarding details was needed after the

general design was finalised. The maximum and minimum

size of the power-packs indicated the degree of

adjustability needed. The maximum weight would dictate

the strength of the wheels needed. A safety factor of 3 was

considered. The maximum weight of any individual

power-pack was 2,500kg. Each caster would be loaded with

a maximum of 625kg. The safety factor of 3 ensured that

all casters could hold weights up to 1,875kg (2,000kg).

Reinforcing Plates

Summary; an extremely old machine had been returned

for service, due to the excessive forces on the chassis from

where the jaw crusher sat, the chassis had cracked.

Reinforcing plates were needed to be welding on to

prevent the crack from spreading.

Project Description; initially, photographs of the cracked

chassis were taken to determine the extent of the damage

and to indicate the areas the plates need to cover. Once

completed, the drawings were drawn up; one-off set was

made in fabrication and fitted to the machine. Within this

project, form was not considered. It was purely a

functional item and was designed to complete the job.

Problems; there was one severe problem encountered.

The plates welded to the chassis would cause the jaw box

to sit a higher height than before. This could potentially

result in a clash with the feeder, which sat only a few

millimetres above the jaw box. After investigating the

clearance, it was found that the jaw box would be too

high. Smaller plates were made for the feeder to sit on, to

maintain the clearance. This new height was checked to

ensure it was still inside transport regulations.

New Main Conveyor

Summary; an alteration in cones used on the cone

crushers required the development of a complete new

machine. The re-design of the main conveyor was my role.

Project Description; to save a significant amount of time,

the design was completed by altering an existing conveyor.

Where possible, to reduce waste and as part as an

initiative to implement lean manufacturing, current parts

were used. This could not be achieved in numerous

situations, in these situations entirely new parts were

created. Alongside the generation of the 3D model,

engineering drawings for all components were also

needed. Problems; one problem encountered, was during the

design of the “nip guard”. This guard is used to ensure no

debris attaches to the head drum and damages the belt.

The new conveyor was wider than previous conveyors, so

previous nip guards could be altered, and the change

accounted for, resulting in less time re-designing. It was

found that due to the bigger new head drum, to power the

wider belt, the old nip guard design would collide. A

prototype was created, incorporating a new length which

should clear the new head drum. This then could be

tested on an existing conveyor, using the new guard and

bigger drum. The prototype work perfectly, and the new

guard was sent to production.

CV

Thank you…

David Coombes

E-mail; [email protected]

Tel; +44 (0) 7891 814 590