Port of Seattle IAF Overview
March 27, 2018
Item No. 9a_supp Meeting Date: March 27, 2018
![Page 2: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/2.jpg)
Project Briefing
• Benefits of the IAF • Construction Progress Photos • Project Delivery Strategy • Key IAF Project Initiatives • Progressive Design-Build Contract Overview
2
Major program meeting a critical airport need
![Page 3: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/3.jpg)
Benefits of IAF • Increases passenger processing capacity from 1,200 to
2,600 pax/hour • Reduces passenger transit time through the facility • Provides a modern and welcoming facility for international
travelers coming to the world class cities in our region • Supports our international airlines
– Six new international carriers since 2016 – Annually, each provides $89M regional economic benefit
• Provides 20 dual-capable flexible gates for both large international aircraft and smaller domestic aircraft
Enhance the experience of arriving international passengers 3
![Page 4: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/4.jpg)
IAF Aerial View 4
![Page 5: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/5.jpg)
IAF Night View IAF Night View 5
![Page 6: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/6.jpg)
Airside Construction Progress
6
![Page 7: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/7.jpg)
Airside Construction Progress
7
![Page 8: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/8.jpg)
Landside Construction Progress
8
![Page 9: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/9.jpg)
Project Delivery Strategy • Progressive Design-Build Offered an 18-Month Schedule Advantage in
Completing the Time-critical new IAF • Although the IAF is Delayed, the Current Schedule Benefit is Estimated
to be 12 Months Compared to Other Project Delivery Methods • Schedule-impacting Issues Encountered as the IAF Progressed:
– Dec 2016 – Local Market Conditions (Delayed GMP Negotiations) • Fewer interested bidders • Shortage of skilled labor
– Aug 2017 – PCB Contamination (3,200+ tons removed) – Sep 2017 – Baggage Handling System Scope Additions – Nov 2017 – Emergency Generator Re-design – Nov 2017 – CBP’s Transition to Facial Recognition
Halfway Through Delivery Period 9
![Page 10: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/10.jpg)
???
IAF Project Initiative Report Card
X
X
10
Overall assessment
![Page 11: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/11.jpg)
The Contract Contemplated Three Distinct Time Periods
Progressive Design-Build Contract Overview
GMP Development
Period
Commence Design, Early Work Construction, and Long Lead Time
Item Procurement
Post-GMP
Period Validation
Period
Test, Validate, Confirm Project Definition
Document Full Build
Set Target Budget & Target Schedule
1/04/16 March 27, 2018
7/20/15
11
![Page 12: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/12.jpg)
GMP Overview (Three Contract Periods)
Project challenges have delayed contract negotiations
Mar 2018
Mini-GMPs
12
![Page 13: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/13.jpg)
Budget Overview
Target budget has not been met – outcome of negotiations is uncertain.
Original Target Budget
Phase 2 Scope Added (Pod D & 2600 Pax/Hour)
Related Projects Added
Adjusted Target Budget
BUDGET OVERRUN (Reported in the November 2017 Commission Meeting)
Revised Project Cost
Potential Additional Costs
Design Exceeding Budget
Current GMP Forecast
$608.4M
$105.6M
$790M
$830M
$684.4M
$52M
$24M
$40M
$146M
13
![Page 14: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/14.jpg)
Budget Overrun Breakdown
Description of Forecasted Costs Overruns:
Seattle Market Conditions $14M
Original Target Budget Understated $29M
Misjudged Code Requirements (ex. Smoke Control) $22M
Failure to Design to the Adjusted Target Budget $35M
Baggage Handling System Enhancements and Changes to the
Equipment Specifications $13M
Emergency Generator Change $4M
Remediation of PCBs on IAF Building Site $4M
CBP Facial Recognition (Addition of a 3rd Escalator) $1M
Occupancy Classification Change in Bagwell $2M
Schedule Phasing/Complexity $5M
Increased Costs Driven by Above Cost Overruns (WA B&O
Tax, Sales Tax rate, Builder’s Risk, etc.) $17M
Total $146M
Assessment of causes for cost growth
14
![Page 15: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/15.jpg)
Schedule Overview
Recovery from schedule delays will cost additional money
JUL '17 SEP '19 FEB '20
IAF BUILDING
PASSENGER BRIDGE
JUL '20
STERILE CORRIDOR (Pods A, B & C)
STERILE CORRIDOR (Pod D)
26 months
11 months
166 Days26 months
26 months
15
![Page 16: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/16.jpg)
Backup Slides
16
![Page 17: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/17.jpg)
Landside Construction Progress
17
![Page 18: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/18.jpg)
Landside Construction Progress
18
![Page 19: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/19.jpg)
Key IAF Project Initiatives
• Establish the Right Project Scope • Capture Northwest Sense of Place in
Design • Community Participation (Small Business) • Environmental (Sustainability) • Achieve Budget and Schedule Objectives
Initiatives Largely on Track 19
![Page 20: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/20.jpg)
The Right IAF Project Scope PPD
2013-2014
PDD 2014-2015
BoD 2016
Planning & Programming Document (PPD)
Program Definition Document (PDD)
Basis of Design (BoD)
Scope and Design Coordinated with Port, Airline and Federal Stakeholders
20
![Page 21: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/21.jpg)
Community Participation
Contracted to Date
SBE – 17.5%
SCS – 12%
SBE – 20.0%
SCS – 4.2%
Planned
Small Business Participation 21
![Page 22: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/22.jpg)
Apprenticeship Utilization
Overall to Date – 16.81%
Women – 10%
Minority – 15% Minority – 13.87%
Women – 2.56%
Overall Goal – 15% (of which 10% are to be Women)
22
Exceeding overall goal; minorities nearly on target, women below target.
![Page 23: Port of Seattle IAF Overview · 2018-03-21 · Port of Seattle IAF Overview March 27, 2018 Item No. 9a_supp Meeting Date: March 27, 2018 . ... 1/04/16 March 27, 2018 7/20/15 11](https://reader036.vdocuments.us/reader036/viewer/2022081607/5eceda650e2bd5210370c728/html5/thumbnails/23.jpg)
Environmental Features of the IAF Project Water Efficiency: • Rainwater Management - Installing double pipe for future rainwater system.
Energy Use Reduction:
• LED lighting and high efficiency motors in baggage system. • Harnessing daylighting with the use of daylight sensors to reduce energy. • Efficient central airport plant for heating and cooling.
Environmentally Friendly Materials:
• Locally based and low impact to the extent possible.
Enhanced Commissioning:
• Independent Commissioning Agent.
Targeting LEED Silver
IAF is First Port Facility to Pursue LEED v4
Silver
23