POWER STATION POWER STATION MANAGEMENT MANAGEMENT
MBPM-401MBPM-401
![Page 2: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/2.jpg)
RAKESH PANDEYRAKESH PANDEY
MANAGERMANAGERNTPC LTDNTPC LTD
CONTACT NO. : 9868391300CONTACT NO. : 9868391300
E-MAIL ID : E-MAIL ID : [email protected] [email protected]
![Page 3: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/3.jpg)
• Different aspects of power plant constructions
• Performance management of boiler, turbine , cycle efficiency and other performance parameters.
• Management of fuel and water resources
• Operation and maintenance of different power projects
• Performance enhancement & efficiency improvement
SYLLABUS
![Page 4: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/4.jpg)
• Statutory Requirements, Safety Act, Environmental Regulation
• Cost Management Strategies - Inventory Control in fuel
• Managing O & M interfaces
• RLA and R&M
• Factory act
SYLLABUS ….Contd….Contd
![Page 5: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/5.jpg)
• Statutory requirements to set power project
• Different Steps of Construction
• Electricity Demand and fuel supply
• Management of Fuel
– Storage and handling of coal/oil/gas
– Coal /gas linkages
– Inventory control
– Pricing & contracts
• Water Resources Management
![Page 6: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/6.jpg)
• Performance Management
–Boiler Efficiency
–Turbine Efficiency
–Cycle Efficiency
–Monitoring and control of heat rate
• Energy conservation & Efficiency measures
• Maintenance planning
![Page 7: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/7.jpg)
• Regulatory aspects related to Power station management
–Indian Electricity Act
–Safety Act
–Environmental Act
• Financial Aspect
–Working capital Management
–Cost Management Strategies
![Page 8: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/8.jpg)
• Human Resources Management of Power Station
• Management Information system
![Page 9: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/9.jpg)
BOOKS BOOKS
1.Power Plant Performance Management, Butter Worth, A.B. Gill
2.Modern Power Station Practice, Publisher British Electricity Authority.
3.Power Station Engg. & Economy – B.G.A. Skrotzki & W.A. Vopat , Tata McGraw Hill.
4.Standard Plant Operators Manual – Stephen Michael Elanka, McGraw Hill Book Company
![Page 10: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/10.jpg)
INDIAN POWER SECTOR&
YOUR ROLE
![Page 11: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/11.jpg)
• Power for all by 2012• Present Per capita Consumption – 606 kwh• Per capita Consumption by 2012 – 1,000 kwh• Peak demand Estimation by 2012 – 157 GW• Inter Regional Transmission capacity to reach
37,000 MW by 2012 from 17,000 MW in 2007• Investment requirement by 2012 – USD 100 Billion• Generation – USD 50 Billion• Transmission & Distribution – USD 50 Billion
•
Indian Power Scenario – Projected Growth
![Page 12: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/12.jpg)
• To Make available the Power at “Affordable Rate” i.e. to Common People
• 10% Rate of Growth in Power Sector supports roughly 6-7% Growth in GDP
• To be competitive in Global Market “Cheap Electricity” is essential
• Quality and uninterrupted Power Supply • The aim should be 8-10% increase in KWH
power given to consumer• Rural Electrification• Government Agenda “Power on Demand by
2012
•
EXPECTATIONSEXPECTATIONS
![Page 13: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/13.jpg)
• Electricity Being Used to attract Votes
• Regulator in Power Sector but no Regulator in Fuel
• Balance of Thermal, Hydro, and Nuclear Power to minimise cost of Electricity
• T&D Losses•
CONSTRAINTSCONSTRAINTS
![Page 14: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/14.jpg)
Power Sector is Back Bone of Economy
![Page 15: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/15.jpg)
• Cost Reduction by way of Higher Performance in Construction Schedule, Operation of Plant, and Technological Up gradation
• To Promote those Policies whereby the overall Indian Power Sector turns into an efficient system whereby total consumer needs are met with quality and an affordable cost
YOUR ROLE YOUR ROLE
![Page 16: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/16.jpg)
YOUR ROLE YOUR ROLE ….….ContdContd
• Resource Optimisation
• Financial Management
• HR Management
• Inventory Managements
• Safety Aspects
![Page 17: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/17.jpg)
Different aspects of power plant constructions
![Page 18: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/18.jpg)
• FEASIBILITY STUDY• DETAILED PROJECT REPORT• STATUATORY CLEARANCES• NON STATUATORY CLEARANCES• FINANCIAL CLOSURE• ALLOCATION OF FUEL LINKAGES• ALLOCATION OF WATER• LAND AQUISTION•
DIFFERENT STEPSDIFFERENT STEPS
![Page 19: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/19.jpg)
• SITE LEVELING • PRELIMINARY CONSTRUCTION
ACTIVITY• VENDOR SELECTION FOR
MAIN PACKAGE• AWARD OF MAIN PACKAGE• DETAILED ENGINEERING• ERRECTION•
DIFFERENT STEPS DIFFERENT STEPS ….….ContdContd
![Page 20: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/20.jpg)
• COMMISSIONING• COMMERCIAL DECLRATION• PERFORMANCE GUARANTEE
TEST• CNTRACT CLOSURE
•
DIFFERENT STEPS DIFFERENT STEPS ….….ContdContd
![Page 21: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/21.jpg)
FEASIBILITY STUDYFEASIBILITY STUDY
• Different Surveys to access Impact
• Availability of land
• Water Availability
• Transportation
• Availability of Fuel Linkage
![Page 22: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/22.jpg)
FEASIBILITY STUDY FEASIBILITY STUDY ….….ContdContd
• Topographical Survey• Geo Technical Study• Area drainage Study• EIA Study • Socio Economic survey • Hydrographic Study (for coastal projects)
![Page 23: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/23.jpg)
CASE STUDYCASE STUDY
SETTING UP OF SETTING UP OF
ULTRA MEGA PROJECTULTRA MEGA PROJECT
![Page 24: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/24.jpg)
THE CONCEPTTHE CONCEPT
• Setting up of large projects of 4000 MW at a single location: ensuring economies of scale
• Utilisation of super critical technology: ensuring higher efficiency and lower CO2 emissions
• Award of projects to developer through tariff based competitive bidding : ensuring cheaper power
![Page 25: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/25.jpg)
THE APPROACHTHE APPROACH
• Guidelines for determination of tariff through bidding process were issued on 19th January, 2005 under Section 63 of the Electricity Act, 2003. These provide for procurement of power by Distribution Licensees through competitive bidding
• Separate SPVs for each project to undertake project development activities including bid process management on behalf of procurers
![Page 26: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/26.jpg)
TECHNICAL FEATURESTECHNICAL FEATURES
• Utilisation of higher efficiency super critical technology with unit size of 800 MW
• Station capacity of about 4000 MW (5x800 MW)
• Flexibility re: unit size to be permitted, subject to meeting thermal efficiency requirements
![Page 27: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/27.jpg)
SITE SELECTIONSITE SELECTION
• Site selection by CEA taking into consideration availability of fuel, land and water etc.
• 5 suitable locations identified based on preliminary scrutiny by CEA of a number of potential sites available in the country :– Two pithead locations based on domestic coal.
• Sasan in MP• Akaltara in Chhattisgarh
– Three coastal locations based on imported coal.• Mundra in Gujarat• Girye in Maharashtra• Tadri in Karnataka
– One additional pithead site in Orissa and one coastal site in Andhra Pradesh are also under consideration
![Page 28: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/28.jpg)
ROLE OF MINISTRY OF POWERROLE OF MINISTRY OF POWER
• Ministry of Power to be facilitator• Co-ordination with concerned Ministries/
Agencies and State Govts. for ensuring:– Coal block allotment/ coal linkage– Environment/ forest clearances– Facilitate acquisition of land– Required support from State Govt. & its agencies on
various issues– Financial closure by Financial Institutions– To facilitate PPA and proper payment security mechanism
with State Govt./ State utilities – Monitoring the progress of shell companies w.r.t
predetermined timelines
![Page 29: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/29.jpg)
ROLE OF SHELL COMPANIESROLE OF SHELL COMPANIES
• Shell Companies to take action for:– Appointment of Consultants to undertake preparation of
Project Report– Initiate land acquisition proceedings– Obtain coal linkages/ allocation of captive coal blocks for
pit-head projects.– Allocation of water by the State Govt. for pit-head locations– Approval for use of seawater from Maritime Board/ other
Govt. Agencies for coastal locations– Appointment of Consultants for International Competitive
Bidding (ICB), document preparation & evaluation.
![Page 30: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/30.jpg)
ROLE OF SHELL COMPANIESROLE OF SHELL COMPANIES ….….Contd.Contd.
– Obtain various approvals and statutory clearances.
– Tie up for off-take/ sale of power as per provisions of Section 63 of EA 2003.
– Initiate action for development of the power evacuation system and undertake system studies considering the addition of capacity from these projects
![Page 31: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/31.jpg)
POWER OFF-TAKEPOWER OFF-TAKES.No. State\ Project -> Sasan (MP) Mundra(Gujarat) Girye(Mah.) Tadri( Karn)
1 Delhi 500 - - -
2 Uttar Pradesh 500 300 - -
3 Uttaranchal 100 - - -
4 Punjab 600 500 - -
5 Rajasthan 400 400 500 300
6 Haryana 450 400 - -
7 Madhya Pradesh 1200 - 500 -
8 Chattisgarh 250 - 500 -
9 Guajarat - 1600 - -
10 Maharashtra - 800 2000 1000
11 Karnataka - - 500 1500
12 Tamil Nadu - - - 1000
13 Kerala - - - 200
14 Andhara Pradesh - - - -
TOTAL 4000 4000 4000 4000
![Page 32: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/32.jpg)
STATUTORY CLEARNCESSTATUTORY CLEARNCES
• COST ESTIMATES• TECHNO-ECONOMIC
CLEARANCE/ CONCURRENCE OF CEA:
• Publication• WATER
AVAILABILITY• SEB CLEARANCE
• By CEA• By CEA
• State Government• State Government/
CWC• State
Government/SEB
![Page 33: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/33.jpg)
STATUTORY CLEARNCES STATUTORY CLEARNCES ….….ContdContd
• Pollution clearance water and air
• Forest clearance
• Environment & forest clearance
• Civil aviation clearance for chimney height
• Registration of company
• SPCB
• State Govt Min. of E&F
• State Govt Min. of E&F
• National Airport Authority
• Registrar of Comp-anies
![Page 34: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/34.jpg)
STATUTORY CLEARNCES STATUTORY CLEARNCES ….….ContdContd
• REHABILITATION & RESETTLEMENT OF DISPLACED FAMILIES BY LAND ACQUISITION
• HYDRO PROJECTS (MINI-MICRO)
• EQUIPMENT PROCUREMENT
• MoEF/ State Govt.
• Ministry of Water Resources
• DGTD/ CCI&E*
![Page 35: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/35.jpg)
Non STATUTORY CLEARNCESNon STATUTORY CLEARNCES
• Land availability • Fuel linkage
• Financing
• Transportation of fuel
• State Govt. • Deptt of Coal, Deptt. of
Petroleum & Natural Gas
• CEA, Deptt. of Power, Deptt of Eco. Affairs,
• Deptt of Coal, Min. of Petroleum & Natural Gas, Ministry of Railways, Shipping & Surface Transport
![Page 36: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/36.jpg)
MANAGERIAL ACTIVITIESMANAGERIAL ACTIVITIES
• PROPER PLANING
• RESOURCE MANAGEMENT
• AVAILABILITTY OF EQUIPMENT AND MACHINARY IN TIME
• PROPER MONITORING
• PROPER NETWORKING
• EFFECTIVE COORDINATION BETWEEN DIFFERENT AGENCIES
![Page 37: popwer station mgmtl1](https://reader035.vdocuments.us/reader035/viewer/2022062623/552852ab49795917048b4781/html5/thumbnails/37.jpg)
MANAGERIAL ACTIVITIES MANAGERIAL ACTIVITIES ….….ContdContd
• R&R ACTIVITIES TO MAINTAIN HARMONY
• MAINTAINING HIGHER MORAL OF EMPLOYEES
• ENSURING SAFETY OF MAN AND MACHINE
• MAINTAINING GOOD INDUSTRIAL RELATION