pony pines residential€¦ · during the p.m. peak hour it is expected to generate 811 new two-way...
TRANSCRIPT
GHD | Pony Pines Development Inc. | 8811691 | Page i
Pony Pines Residential Traffic Impact Study Milton, Ontario April 12, 2020 Pony Pines Development Inc.
GHD | Pony Pines Development Inc. | 8811691 | Page ii
April 5, 2020
Executive Summary
GHD Limited (GHD) was retained to prepare a Traffic Impact Study (TIS) for the proposed Pony Pines Development located on the north side of Britannia Road between Tremaine Road and the CN Railway in the Town of Milton. This report establishes the existing road network and the subsequent traffic-related impacts on the adjacent future road network during the weekday a.m. and p.m. peak hours. These impacts are based on projected future background traffic for the 2024 and 2029 planning horizons.
The overall draft plan consists of 498 detached homes and 438 townhouses. The minor sub-node located in the southwest corner proposes an estimated 166 medium density residential units.
Access to the development from the surrounding existing and future road network is proposed as follows:
• Proposed full moves signalized intersections at the Street ‘A’ and Street ‘C’ intersections at Britannia Road; and
• Proposed interim right in/right-out unsignalized intersection at the Collector Road ‘A’ and Street ‘B’ at Tremaine Road intersection for horizon year 2024.
• Proposed full-moves signalized intersection at the Collector Road ‘A’ and Street ‘B’ at Tremaine Road intersection for horizon year 2029.
The proposed development is expected to generate a total of 630 two-way vehicle trips during the a.m. peak hour consisting of 154 inbound and 476 outbound trips. During the p.m. peak hour it is expected to generate 811 new two-way vehicle trips consisting of 510 inbound and 301 outbound trips.
The study area intersections are expected to operate acceptably during the weekday peak hours for 2024 and 2029 future conditions, under the planned traffic control and intersection configurations.
Respectfully submitted,
GHD William Maria, P. Eng. Senior Project Manager
GHD | Pony Pines Development Inc. | 8811691 | Page iii
Table of Contents
1. Introduction ........................................................................................................ 1
1.1 Retainer and Objective .............................................................................. 1
1.2 Study Team ............................................................................................... 1
1.3 Response to Comments ............................................................................ 1
1.4 Study Area Intersections ........................................................................... 1
2. Site Characteristics ............................................................................................ 2
2.1 Site Location .............................................................................................. 2
2.2 Draft Plan .................................................................................................. 4
3. Existing Road Network ....................................................................................... 5
3.1 Existing Road Network .............................................................................. 5
3.2 Pedestrian and Cycling Routes ................................................................. 5
3.3 Transit Services ......................................................................................... 5
3.4 Existing Traffic Data .................................................................................. 5
4. Future Background Traffic ................................................................................. 8
4.1 Planned Road Improvements .................................................................... 8
4.2 Study Horizon Years ................................................................................. 8
4.3 Future Background Developments ............................................................ 8
4.4 Future Background Volumes ................................................................... 15
5. Site Generated Traffic ...................................................................................... 20
5.1 Transit Modal Split ................................................................................... 20
5.2 Site Trip Generation ................................................................................ 20
5.3 Site Trip Distribution and Assignment ..................................................... 24
6. Future Total Traffic ........................................................................................... 24
7. Intersection Capacity Analysis ......................................................................... 27
7.1 Britannia Road at Street A ....................................................................... 27
7.2 Britannia Road at Street C ....................................................................... 28
7.3 Tremaine Road at Street B ...................................................................... 29
7.4 Street A at Street B ................................................................................. 29
7.5 Street C at Street B ................................................................................. 30
7.6 Tremaine Road at Collector A ................................................................. 31
GHD | Pony Pines Development Inc. | 8811691 | Page iv
7.7 Street A at Collector A ............................................................................. 31
7.8 Street C at Collector A ............................................................................. 32
7.9 Tremaine Road at Louis Saint Laurent Avenue ....................................... 33
7.10 Tremaine Road at Britannia Road ........................................................... 34
8. All-Way Stop Control Warrants ........................................................................ 35
9. Draft Plan Review ............................................................................................ 36
10. Conclusion ....................................................................................................... 37
Figure Index
Figure 1 Site Location ................................................................................................ 3 Figure 2 Overall Draft Plan ......................................................................................... 4 Figure 3 Existing Traffic Volumes ............................................................................... 6 Figure 4 Existing Balanced Traffic Volumes ............................................................... 7 Figure 5 Full Boyne RNA Site Traffic Volumes ......................................................... 11 Figure 6 Reduced Boyne RNA Site Traffic Volumes (2024) ..................................... 12 Figure 7 Reduced Boyne RNA Site Traffic Volumes (2029) ..................................... 13 Figure 8 Existing & Reduced Boyne RNA Traffic Volumes ...................................... 14 Figure 9 2024 Corridor Growth Volumes .................................................................. 16 Figure 10 2029 Corridor Growth Volumes ................................................................ 17 Figure 11 2024 Future Background Volumes ........................................................... 18 Figure 12 2029 Future Background Volumes ........................................................... 19 Figure 13 Estimated Site Trips – 2024 ..................................................................... 22 Figure 14 Estimated Site Trips – 2029 ..................................................................... 23 Figure 15 2024 Future Total Volumes ...................................................................... 25 Figure 16 2029 Future Total Volumes ...................................................................... 26
GHD | Pony Pines Development Inc. | 8811691 | Page v
Table Index
Table 1 Site Trip Generation – Overall Draft Plan ................................................ 20 Table 4 Site Trip Distribution ................................................................................ 24 Table 5 Capacity Analysis for Britannia Road at Street A .................................... 27 Table 6 Capacity Analysis for Britannia Road at Street C .................................... 28 Table 7 Capacity Analysis for Tremaine Road at Street B ................................... 29 Table 8 Capacity Analysis for Street A at Street B ............................................... 29 Table 9 Capacity Analysis for Street C at Street B ............................................... 30 Table 10 Capacity Analysis for Tremaine Road at Collector A ............................... 31 Table 11 Capacity Analysis for Street A at Collector A .......................................... 31 Table 12 Capacity Analysis for Street C at Collector A .......................................... 32 Table 13 Capacity Analysis for Tremaine Road at Louis Saint Laurent Avenue .... 33 Table 14 Capacity Analysis for Tremaine Road at Britannia Road ........................ 34
Appendix Index
Appendix A Traffic Data
Appendix B Background Developments Traffic Data
Appendix C Transportation Tomorrow Survey (TTS) Data and Internal Site Trips
Appendix D Capacity Analysis
Appendix E Site Plan
GHD | Pony Pines Development Inc. | 8811691 | Page 1
1. Introduction
1.1 Retainer and Objective
GHD Limited (GHD) is pleased to provide this Traffic Impact Study for the proposed Pony Pines Development located on the north side of Britannia Road between Tremaine Road and the CN Railway in the Town of Milton. The objective of the study is to:
• Establish baseline traffic conditions for the study area and update the existing traffic conditions to derive the future background operating conditions at a future 2024 and 2029 horizon;
• Apply the estimated traffic generation and distribution of the development to the adjacent road network, and determine the future impacts in the context of all local transportation modes; and
• Review the site plan in the context of operational/geometric issues, and provide recommendations on how to address any deficiencies (if any are revealed).
1.2 Study Team
• William Maria, P. Eng., Senior Project Manager
• Adam Mildenberger, B.A., C.E.T., Transportation Planner
• Ivan Drewnitski, Dipl.T., Junior Transportation Planner
• Dominic Cho, Transportation Planner
1.3 Response to Comments
An initial Traffic Impact Study report was submitted to the Town and Region, dated May, 2019. Town and Regional comments have been provided, dated January 13, 2020 and January 17, 2020, respectively. This submission of the report is based on revisions made in response to the received comments.
1.4 Study Area Intersections
The study area includes the following intersections, with their expected traffic signals for horizon year 2024:
• Louis Saint Laurent Avenue at Tremaine Road (existing roundabout);
• Collector Road A at Tremaine Road (future unsignalized right-in-right-out only – Varga site);
• Street B at Tremaine Road (future unsignalized & right-in-right-out only – Pony Pines site);
GHD | Pony Pines Development Inc. | 8811691 | Page 2
• Britannia Road at Tremaine Road (existing roundabout);
• Collector Road A at Street C (future unsignalized – Varga site);
• Collector Road A at Street A (future unsignalized – Varga site);
• Street B at Street C (future unsignalized – Pony Pines site);
• Street B at Street A (future unsignalized – Pony Pines site);
• Street C at Britannia Road (future unsignalized – Pony Pines site); and
• Street A at Britannia Road (future unsignalized – Pony Pines site). It has been requested by the Town that following intersections at Tremaine Road to be analyzed as full-moves signalized intersections under horizon year 2029:
• Collector Road A at Tremaine Road (future full-moves signalized intersection, 2029); and
• Street B at Tremaine Road (future full-moves signalized intersection, 2029).
2. Site Characteristics
2.1 Site Location
The location of the site within the local transportation network is shown in Figure 1. The site is situated north of Britannia Road between Tremaine Road to the west and the CN Railway to the east. The site is situated within the Boyne West Secondary Plan Area.
GHD | Pony Pines Development Inc. | 8811691 | Page 3
Figure 1 Site Location
GHD | Pony Pines Development Inc. | 8811691 | Page 4
2.2 Draft Plan
The April 2020 Draft Plan prepared by Glen Schnarr & Associates is a redline update to the approved Pony Pines Draft Plan of Subdivision in June 2019 (24T-14003M).The 2019 approval was based on Pony Pines’ available servicing allocation purchased through the 2012 Halton Region Allocation Program of 200 units of allocation, permitting approval of 500 SDE in residential units based on the Regions requirement of having a minimum of 40% of the required allocation for a Development proposal. In November 2019, Pony Pines Development Inc. submitted an Expression of Interest in the 2020 Halton Region Allocation Program, and has since executed an Allocation Agreement with Halton Region securing a total of 593 additional SDEs. Accordingly, a Redline revision application is being made to incorporate additional lands east of Savoline Boulevard, a holdout property municipally known as 6081 Tremaine Road, as well as various minor revisions to the draft approved lands.
The purpose of this report and analysis is to update our analysis based on the redline Draft Plan dated April 1, 2020 (see Figure 2 or Appendix E). The Draft Plan consists of 498 detached homes and 438 townhouses. The minor sub-node located in the south west corner proposes an estimated 166 medium density residential units.
Figure 2 Overall Draft Plan
GHD | Pony Pines Development Inc. | 8811691 | Page 5
3. Existing Road Network
3.1 Existing Road Network
Tremaine Road (Regional Road #22) is a north-south Regional major arterial road under the jurisdiction of Halton Region. The road has an existing six-lane urban cross-section and a posted speed limit of 70 km/h. Tremaine Road intersects with Britannia Road and Louis St. Laurent Avenue with a four lane cross-section roundabout.
Britannia Road (Regional Road #6) is an east-west major arterial road under jurisdiction of Halton Region. The road has an existing two-lane urban cross-section with a posted speed limit of 80 km/h, and is expected to be widened to a six-lane cross-section prior to the 2026 horizon year.
Louis Saint Laurent Ave is an east-west minor arterial road under the jurisdiction of the Town of Milton with an existing four-lane cross-section and a posted speed limit of 60 km/h.
3.2 Pedestrian and Cycling Routes
There is sidewalks and designated cycling routes on both sides of Louis St. Laurent Avenue and Tremaine Road within the study area. Britannia Road currently provides no sidewalks or bicycle facilities, although is expected to include sidewalks and cycling routes after the widening.
3.3 Transit Services
There are currently no transit services provided within the study area.
3.4 Existing Traffic Data
The Region has provided GHD with turning movement counts at the Town intersection of Tremaine Road at Louis Saint Laurent Avenue, dated May 2018, and GHD has historical turning movement count data at the Regional intersection of Tremaine Road at Britannia Road, dated February 2016. The intersection turning movement counts are provided in Appendix B.
The adopted existing traffic volumes for the weekday a.m. and p.m. peak hours are shown in Figure 3.
GHD | Pony Pines Development Inc. | 8811691 | Page 6
Figure 3 Existing Traffic Volumes
(12)
(243
)
(38) 75 (85)
11 544
97 4 (8)
170 (81)
(13) 5
(10) 7 0 279
178
(7) 3
(0)
(444
)
(136
)
(231
)71
7
457
(441
)
(231
)71
7
457
(441
)
(44)
(175
)
(12) 12 (48)
47 404
33 75 (169)
37 (43) 124 (260) 124 (260)
(47) 48 (120) 256 (120) 256
(81) 170 4 238
53
(8) 15
(11)
(346
)
(27)
Britannia Road
Tremaine Road
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 7
The existing volumes were balanced based on the highest volumes along the Tremaine Road. The balanced existing traffic volumes are shown in Figure 4.
Figure 4 Existing Balanced Traffic Volumes
(12)
(243
)
(38) 75 (85)
11 544
97 4 (8)
170 (81)
(13) 5
(10) 7 0 279
178
(7) 3
(0)
(444
)
(136
)
(331
)71
7
457
(580
)
(331
)71
7
457
(580
)
(63)
(251
)
(17) 18 (63)
70 598
49 75 (75)
37 (37) 130 (175) 130 ####
(62) 74 (240) 272 (240) 272
(170) 170 4 365
53
(15) 15
(4)
(455
)
(53)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Britannia Road
Tremaine Road
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 8
4. Future Background Traffic
4.1 Planned Road Improvements
The planned Town of Milton and the Region of Halton road network improvements were reviewed and included the following studies:
• Halton Region Transportation Master Plan (2012-2021);
• Halton Region Capital Projects (2021-2031);
• Town of Milton Construction Projects Forecast (2012-2017);
• Tremaine Road Transportation Corridor Improvements Class EA Study (2009); and
• Britannia Road West Transportation Corridor Improvements Class EA Study (2012).
The site’s planned Street A and Street C intersections at Britannia Road are planned for signalization under both Interim (two lane cross-section on Britannia Road) and Ultimate (six lane cross-section on Britannia Road) conditions. As a conservative measure, the intersections have been modelled without auxiliary turning lanes.
The site’s planned Street B intersection at Tremaine Road is planned for unsignalized right-in/right-out configuration, with stop control for the Street B approach.
4.2 Study Horizon Years
As per consultation with Town and Regional staff, the following future horizon years and/or analysis scenarios have been included for analysis:
• Existing Conditions;
• “Existing plus Boyne West” (existing traffic volumes plus 100% Boyne West traffic);
• 2024 horizon year (five years post current year); and
• 2029 horizon year (ten years post current year).
4.3 Future Background Developments
The future background conditions represent future road network conditions prior to build-out of the subject development, with the assumption that the remaining Boyne area (development and road network) has been fully developed. To avoid double counting, estimated trips generated from the subject site and Varga site adopted in the Boyne RNA study were removed from the Boyne site trips. The trip
GHD | Pony Pines Development Inc. | 8811691 | Page 9
generation assumptions adopted in the Boyne RNA for the subject site, and the Varga site, are described as follows:
The Boyne RNA assumed the following for the subject site:
• Zone 7A: 248 single-family detached residential units for the subject site, resulting in 143 two-way vehicle trips during the a.m. peak hour consisting of 43 inbound and 100 outbound trips. During the p.m. peak hour it was expected to generate 190 new two-way vehicle trips consisting of 112 inbound and 78 outbound trips.
• Zone 7B: 125 residential condominium/townhouse units for the subject site, resulting in 52 two-way vehicle trips during the a.m. peak hour consisting of 8 inbound and 44 outbound trips. During the p.m. peak hour it was expected to generate 63 new two-way vehicle trips consisting of 43 inbound and 20 outbound trips.
• Zone 7C: 16.824 GLA (1,000 sq ft) shopping centre for the subject site, resulting in 49 two-way vehicle trips during the a.m. peak hour consisting of 30 inbound and 19 outbound trips. During the p.m. peak hour it was expected to generate 90 new two-way vehicle trips consisting of 44 inbound and 46 outbound trips.
• Zone 8: 154 single-family detached residential units for the subject site, resulting in 89 two-way vehicle trips during the a.m. peak hour consisting of 26 inbound and 63 outbound trips. During the p.m. peak hour it was expected to generate 118 new two-way vehicle trips consisting of 70 inbound and 48 outbound trips.
• Zone 9: 84 single-family detached residential units for the subject site, resulting in 48 two-way vehicle trips during the a.m. peak hour consisting of 14 inbound and 34 outbound trips. During the p.m. peak hour it was expected to generate 65 new two-way vehicle trips consisting of 39 inbound and 26 outbound trips.
• Zone 10: 532 single-family detached residential units for the subject site, resulting in 307 two-way vehicle trips during the a.m. peak hour consisting of 92 inbound and 215 outbound trips. During the p.m. peak hour it was expected to generate 407 new two-way vehicle trips consisting of 240 inbound and 167 outbound trips.
With respect to the commercial component of the Varga site (Zone 4, 5 and 6 in the Boyne RNA), the Boyne RNA assumed the following for the subject site:
• Zone 4: 361 single-family detached residential units for the subject site, resulting in 208 two-way vehicle trips during the a.m. peak hour consisting of 62 inbound and 146 outbound trips. During the p.m. peak hour it was expected to generate 276 new two-way vehicle trips consisting of 163 inbound and 113 outbound trips.
GHD | Pony Pines Development Inc. | 8811691 | Page 10
• Zone 5A: 630 student’s elementary school the subject site, resulting in 70 two-way vehicle trips during the a.m. peak hour consisting of 49 inbound and 21 outbound trips. During the p.m. peak hour it was expected to generate 23 new two-way vehicle trips consisting of 11 inbound and 12 outbound trips.
• Zone 5B: 630 student’s elementary school the subject site, resulting in 70 two-way vehicle trips during the a.m. peak hour consisting of 49 inbound and 21 outbound trips. During the p.m. peak hour it was expected to generate 23 new two-way vehicle trips consisting of 11 inbound and 12 outbound trips.
• Zone 5C: 26 single-family detached residential units for the subject site, resulting in 15 two-way vehicle trips during the a.m. peak hour consisting of 5 inbound and 10 outbound trips. During the p.m. peak hour it was expected to generate 20 new two-way vehicle trips consisting of 11 inbound and 9 outbound trips.
• Zone 6: 335 single-family detached residential units for the subject site, resulting in 193 two-way vehicle trips during the a.m. peak hour consisting of 58 inbound and 135 outbound trips. During the p.m. peak hour it was expected to generate 257 new two-way vehicle trips consisting of 152 inbound and 105 outbound trips.
Supporting pages and calculation sheets extracted from the Boyne RNA that justify this approach are provided in Appendix C. The Boyne RNA traffic as outline in the Boyne RNA in Appendix C are shown in Figure 5. The reduced Boyne volumes with the development zones volumes removed are shown in Figure 6 and Figure 7. Please note that the Figure 7 is the full Boyne volumes used for horizon year 2029, while Figure 6 outlines the volumes with some traffic at Tremaine Road intersections diverted with respect to right-in-right-out only lane configurations, prepared for horizon year 2024.
The Town and the Region requested that the existing volumes and the reduced Boyne volumes to be added together and analyzed as interim condition. Figure 8 shows the balanced existing traffic volumes and the horizon year 2024 (Figure 6) reduced Boyne volumes, added together.
GHD | Pony Pines Development Inc. | 8811691 | Page 11
Figure 5 Full Boyne RNA Site Traffic Volumes
(0)
(614
)
(875
)
730 (556)
0 230
316
0 (0)
87 (76)
(0) 0
(0) 0 0 573
50
(0) 0
(0)
(462
)
(80)
(493
)
(25)
(45)
(29) 10 (17) (86)
(212
)
(21) 17 (19)
244
32 30 18 121 (103) 42 109 8 21 (20)
208 (188) 28 (43) 16 (13)
(24) 16 (69) 42
403 9 (123) 47 83 62 34 (26) 10 90 168 8
(386
)
(25) (82) 35
(75)
(50)
(18) (89) 48
(70)
(177
)
(18)
(365
)
(8)
(78)
(11) 13 (8)
(154
)
(0)
205
13 80 17 62 (45) 135 0
129 (111) 11 (24)
(13) 8 (50) 36
283
16 (61) 27 78 64 20 (47) 30 47 96
(300
)
(22) (92) 41
(73)
(100
)
(14)
(37)
(201
)
(47)
(41)
(276
)
230 (204) (23)
(94)
(29)
(148
)
55 50 134
298 (219) 27 123
51 (131) 38 181
77 (205)
157 (120) 659 (520) 672 (623)
(62) 23 (33) 11 (41) 19
(333) 127 0 27 56 (753) 306 (806) 410
(0) 0
(0)
(59)
(176
)
Britannia Road Britannia Road
Tremaine Road
Street B
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C Street A
Collector A
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 12
Figure 6 Reduced Boyne RNA Site Traffic Volumes (2024)
(0)
(0)
(787
)
677 (512)
0 0 282
0 (0)
76 (56)
(0) 0
(0) 0 0 291
40
(0) 0
(0)
(228
)
(71)
(166
)
(25)
(14)
(26) 7 (15) (49)
(56)
(14) 10 (14)
125
32 13 11 46 (47) 21 41 5 1 (12)
68 (76) 1 (0) 7 (10)
(24) 16 (58) 25
251
85 (43) 16 10 19 0 (14) 0 13 33 4
(254
)
(218
)
(18) 23 (1
7)
(28)
(3) (12) 13
(15)
(70)
(15)
(319
)
(0)
(31) (4)
3 (4) (10)
(65) (0)
0 (0)
178 0 44 2 0 (0) 5 61 0 0 (0)
4 (3) 3 (2) 0 (0)
(3) 0 (10) 7
332
59 (0) 0 1 15 1 (0) 0 3 39 0
(469
)
(149
)
(2) 33
(3)
(41)
(2) (7) 11
(9)
(88)
(0)
(38)
(36)
(247
)
212 (170) (0)
(27) (5)
(63)
32 34 84 283 (200) 23 61 13 (34) 6 75 32 (84)
153 (109) 624 (479) 631 (508)
(49) 19 (2) 0 (7) 3
(303) 116 0 160
50 (707) 250 (727) 308
(0) 0
(0)
(399
)
(159
)
Britannia Road Britannia Road
Tremaine Road
Street B
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C Street A
Collector A
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 13
Figure 7 Reduced Boyne RNA Site Traffic Volumes (2029)
(0)
(314
)
(787
)
677 (512)
0 126
282
0 (0)
76 (56)
(0) 0
(0) 0 0 291
40
(0) 0
(0)
(228
)
(71)
(312
)
(25)
(14)
(26) 7 (15) (49)
(56)
(14) 10 (14)
183
32 13 11 46 (47) 21 41 5 1 (12)
68 (76) 1 (0) 7 (10)
(24) 16 (58) 25
251 7 (43) 16 10 19 0 (14) 0 13 33 4
(254
)
(17) (18) 4
(17)
(28)
(3) (12) 13
(15)
(70)
(15)
(319
)
(0)
(31) (4)
3 (4) (65) (0)
197 0 25 2 0 (0) 61 0
4 (3) 3 (2)
(3) 0 (10) 7
254 1 (0) 0 1 15 1 (7) 11 3 39
(268
)
(3) (2) 5
(3)
(41)
(2)
(9)
(88)
(38)
(36)
(247
)
212 (170) (0)
(27) (5)
(63)
43 44 110
272 (200) 2 35 13 (34) 6 75 32 (84)
143 (109) 624 (479) 631 (508)
(49) 19 (2) 0 (7) 3
(303) 116 0 24 50 (707) 276 (727) 308
(0) 0
(0)
(52)
(159
)
Britannia Road Britannia Road
Tremaine Road
Street B
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C Street A
Collector A
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 14
Figure 8 Existing & Reduced Boyne RNA Traffic Volumes
(12)
(510
)
(913
)
805 (641)
11 638
413
4 (8)
257 (157)
(13) 5
(10) 7 0 852
228
(7) 3
(0)
(906
)
(216
)
(678
)
(25)
(45)
(29) 10 (17) (86)
(212
)
(21) 17 (19)
903
32 30 18 121 (103) 42 109 8 21 (20)
208 (188) 28 (43) 16 (13)
(24) 16 (69) 42
860
87 (123) 47 83 62 34 (26) 10 90 168 8
(966
)
(226
)
(82) 54 (7
5)
(50)
(18) (89) 48
(70)
(177
)
(18)
(696
)
(8)
(78)
(11) 13 (8)
(154
)
(0)
903
13 99 17 62 (45) 135 0
129 (111) 11 (24)
(13) 8 (50) 36
818
74 (61) 27 78 64 20 (47) 30 47 96
(108
1)
(168
)
(92) 69
(73)
(100
)
(14)
(37)
(201
)
(110
)
(292
)
(293
)
248 (267) (23)
(94)
(29)
(148
)
114
638
157
384 (294) 48 149
51 (131) 38 181
77 (205)
204 (157) 789 (695) 802 (798)
(124) 97 (33) 11 (41) 19
(503) 297 4 528
109 (993) 552 (1046) 682
(15) 15
(4)
(861
)
(229
)
Britannia Road
Tremaine Road
Britannia Road
Street B
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C Street A
Collector A
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 15
4.4 Future Background Volumes
Corridor growth on the arterial corridors adopted the Region’s 3% compound annual growth rate to 5-year (2024) and 10-year (2029) planning horizon years.
The projected future corridor volumes with just the growth (no background developments) during each of the horizon years are shown in Figure 9 and Figure 10, respectively.
Future background volumes were calculated by adding the Boyne site trips from the Boyne RNA, and the adjacent Varga development site trips, to the forecasted 2024 and 2029 corridor growth volumes. As previously noted, to avoid double counting, estimated trips generated from the subject site and Varga site adopted in the Boyne RNA study were removed from the Boyne site trips. The detailed site trips figures for Boyne RNA and Varga development are shown in Appendix C.
Please note that the town has requested that two intersections along Tremaine Road to be analyzed and right-in-right-out (RIRO), unsignalized for 2024 horizon year and full-moves, signalized for 2029 horizon year. As such, the background development trips were reassigned to reflect traffic controls and lane configurations at Tremaine Road intersections at Collector A (Varga) and Street B (Pony Pines) during each horizon years, respectively.
The projected future background traffic conditions during each of the horizon years are shown in Figure 11 and Figure 12, respectively.
GHD | Pony Pines Development Inc. | 8811691 | Page 16
Figure 9 2024 Corridor Growth Volumes
(12)
(290
)
(38) 75 (85)
11 650
97 5 (10)
170 (81)
(13) 5
(12) 8 0 333
178
(7) 3
(0)
(530
)
(136
)
(378
)82
3
511
(666
)
(378
)82
3
511
(666
)
(63)
(298
)
(17) 18 (63)
70 704
49 90 (90)
37 (37) 145 (190) 145 (190)
(62) 74 (273) 305 (273) 305
(203) 203 4 419
53
(15) 15
(4)
(541
)
(53)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Britannia Road
Tremaine Road
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 17
Figure 10 2029 Corridor Growth Volumes
(12)
(336
)
(38) 75 (85)
11 753
97 6 (11)
170 (81)
(13) 5
(14) 10 0 386
178
(7) 3
(0)
(615
)
(136
)
(424
)92
6
564
(751
)
(424
)92
6
564
(751
)
(63)
(344
)
(17) 18 (63)
70 807
49 104 (104)
37 (37) 159 (204) 159 (204)
(62) 74 (305) 337 (305) 337
(235) 235 4 472
53
(15) 15
(4)
(626
)
(53)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Britannia Road
Tremaine Road
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 18
Figure 11 2024 Future Background Volumes
(12)
(426
)
(825
)
752 (597)
11 802
379
5 (10)
358 (236)
(13) 5
(12) 8 0 804
352
(7) 3
(0)
(861
)
(284
)
(779
)
(51)
(37)
(26) 7 (15)
(216
)
(74)
(14) 10 (14)
1212 47 43 11 243 (224) 232
46 5 1 (12)
268 (171) 127 (75) 7 (10)
(49) 41 (104) 113
875
390 (199) 231 71 50 35 (14) 0 146
82 4
(100
6)
(477
)
(138) 185 (5
8)
(42)
(30) (143) 208
(124
)
(90)
(15)
(932
)
(13)
(163
)
(13) 3 (4)
(185
)
(0)
1265 43 239
34 0 (1) 264 0
47 (16) 3 (2)
(3) 0 (19) 39
1163 59 (0) 0 1 63 1 (7) 11 3 158
(118
4)
(149
)
(2) 33
(3)
(87)
(2)
(9)
(198
)
(101
)
(569
)
(264
)
230 (233) (72)
(88) (5)
(182
)
102
1002
133
464 (342) 113
166
43 (61) 7 277
151 (193)
190 (146) 770 (669) 806 (725)
(160) 149 (21) 18 (8) 3
(526) 337 4 843
103 (981) 555 (1061) 718
(15) 15
(4)
(117
5)
(212
)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C
Tremaine Road
Street A
Collector A
Britannia Road
Street B
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 19
Figure 12 2029 Future Background Volumes
(12)
(786
)
(825
)
752 (597)
11 1031
379
6 (11)
358 (236)
(13) 5
(14) 10 0 857
352
(7) 3
(0)
(946
)
(284
)
(736
)
(297
)
(51)
(37)
(26) 7 (15)
(216
)
(74)
(14) 10 (14)
1109
288
268 (171) 47 43 11 268 (235) 232
46 5 1 (12)
74 (51) 102 (64) 7 (10)
(49) 41 (104) 113
928
48 (199) 231 79 50 35 (14) 0 146
82 4
(109
1)
(41) (114) 141
(61)
(42)
(30) (143) 208
(124
)
(90)
(15)
(782
)
(4)
(13)
(105
)
(13) 3 (4)
(185
)
(0)
1181 2 47 (16) 43 162
34 0 (0) 264 0
1 (1) 3 (2)
(3) 0 (19) 39
874 1 (0) 0 1 63 1 (7) 11 3 158
(106
8)
(3) (2) 5
(3)
(87)
(2)
(9)
(198
)
(140
)
(380
)
(264
)
230 (233) (14)
(88) (5)
(182
)
171
851
159
409 (318) 34 140
43 (61) 7 277
151 (193)
180 (146) 784 (683) 820 (739)
(160) 149 (21) 18 (8) 3
(558) 369 4 496
103 (1013) 613 (1093) 750
(15) 15
(4)
(678
)
(212
)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C
Tremaine Road
Street A
Collector A
Britannia Road
Street B
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 20
5. Site Generated Traffic
5.1 Transit Modal Split
As a conservative measure, no transit modal split reduction was applied to the trip generation calculations, based on the assumption that transit modal split reductions are already captured in the trip generation rates provided by the Institute of Transportation Engineers (ITE).
5.2 Site Trip Generation
Trip generation during the weekday peak hours for the proposed Pony Pines development was estimated using ITE 10th Edition LUC #210 for single family dwellings, LUC #220 for multifamily housing (low-rise), and LUC #221 for multifamily housing (mid-rise).
The Overall Draft Plan proposes 497 detached homes and 438 townhouses. The minor sub-node located in the southwest corner proposes an estimated 166 medium density residential.
Table 1 Site Trip Generation – Overall Draft Plan
Land Use Code
Units/ GFA (ft2)
Parameters
Peak Hour Trip Generation
Weekday AM Weekday PM
In Out Total In Out Total
Single-Family
Detached (LUC 210)
498 Units
Trip Rate 0.186 0.555 0.741 0.624 0.366 0.990
Trip Ratio 25% 75% - 63% 37% - Total New
Trips 92 277 369 311 182 493
Multifamily Housing
(Low-Rise) (LUC 220)
438 Units
Trip Rate 0.105 0.354 0.459 0.352 0.207 0.559
Trip Ratio 23% 77% - 63% 37% - Total New
Trips 46 155 201 154 91 245
Multifamily Housing
(Mid-Rise) (LUC 221)
166 Units
Trip Rate 0.096 0.265 0.361 0.269 0.171 0.440
Trip Ratio 26% 74% - 61% 39% - Total New
Trips 16 44 60 45 28 73
Overall Total Site Trips 154 476 630 510 301 811
GHD | Pony Pines Development Inc. | 8811691 | Page 21
The proposed development is expected to generate a total of 630 two-way vehicle trips during the a.m. peak hour consisting of 154 inbound and 476 outbound trips. During the p.m. peak hour it is expected to generate 811 new two-way vehicle trips consisting of 510 inbound and 301 outbound trips. The weekday AM and PM trip generation is summarized in Table 1.
Figure 13 and Figure 14 shows the total estimated site trips for horizon year 2024 and 2029, respectively.
The Town has requested that two intersections along Tremaine Road be analyzed as right-in-right-out (RIRO) for the interim condition in the 2024 horizon year and signalized full-moves intersection for the 2029 horizon year. As such, the estimated site trips were reassigned to reflect traffic controls and lane configurations at Tremaine Road intersections at Collector A and Street B during each horizon years, respectively.
GHD | Pony Pines Development Inc. | 8811691 | Page 22
Figure 13 Estimated Site Trips – 2024
(0)
(153
)
(0)
0 (0)
0 46 0 0 (0)
0 (0)
(0) 0
(0) 0 0 143 0
(0) 0
(0)
(90)
(0)
(153
)
(0)
(0)
(0)
0 (0) (0)
(0)
(0)
0 (0)
46 0 0 0 0 (0) 0 0 0 0 (0)
0 (0) 0 (0) 0 (0)
(0) 0 (0) 0
143 0 (0) 0 0 0 0 (0) 0 0 0 0
(90)
(0) (0) 0
(0)
(0)
(0) (0) 0
(0)
(0)
(0)
(77) (0)
(18) (0)
0 (0) (55)
(55) 0 (0)
23 0 28 0 96 (52) 87 87 14 (9)
143 (90) 0 (0) 19 (12)
(0) 0 (0) 0
0 9 (6) 10 75 0 0 (0) 0 49 31 5
(0)
(31) (18) 28
(111
)
(0)
(0) (6) 10
(26)
(111
)
(12)
(18) (0)
(77) 0 (0) (18)
(52)
(18)
(104
)
9 0 23 57 (36) 29 83 27 (88) 29 165
53 (177)
0 (0) 29 (18) 27 (88)
(31) 9 (69) 21 (69) 21
(61) 18 0 0 0 (69) 21 (52) 83
(0) 0
(0)
(0)
(0)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C
Tremaine Road
Street A
Collector A
Britannia Road
Street B
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 23
Figure 14 Estimated Site Trips – 2029
(0)
(153
)
(0)
0 (0)
0 46 0 0 (0)
0 (0)
(0) 0
(0) 0 0 143 0
(0) 0 (0)
(90)
(0)
(153
)
(0)
(0)
(0)
(0)
0 (0) (0)
(0)
(0)
0 (0)
46 0 0 (0) 0 0 0 0 (0) 0 0 0 0 (0)
0 (0) 0 (0) 0 (0)
(0) 0 (0) 0
143 0 (0) 0 0 0 0 (0) 0 0 0 0
(90)
(0) (0) 0 (0)
(0)
(0) (0) 0 (0)
(0)
(0)
(77)
(77) (0)
(18) (0)
0 (0) (26)
(55) (0)
0 (0)
23 23 143 (90) 0 28 0 96 (52) 41 87 0 14 (9)
9 (18) 0 (0) 19 (12)
(0) 0 (0) 0
0 9 (6) 10 75 0 0 (0) 0 49 31 5
(0)
(31) (18) 28
(111
)
(0)
(0) (6) 10
(26)
(111
)
(12)
(18) (0)
(77) 0 (0) (18)
(52)
(18)
(104
)
9 0 23 57 (36) 29 83 27 (88) 29 165
53 (177)
0 (0) 29 (18) 27 (88)
(31) 9 (69) 21 (69) 21
(61) 18 0 0 0 (69) 21 (52) 83
(0) 0 (0)
(0)
(0)
Tremaine Road
Britannia Road Britannia Road
Street B
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C Street A
Collector A
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 24
5.3 Site Trip Distribution and Assignment
The site trips were assigned at the site access roads (expected to be initially stop controlled) at Street B and Tremaine Road and at Streets C and A on Britannia Road. The adopted directional distributions was extracted from the 2016 Transportation Tomorrow Survey (TTS) which contains origin-destination statistics for the Greater Toronto Area. The distribution extracted from the survey is representative of a.m. and p.m. peak hour conditions in the study area and is consistent with the distributions from the RNA study.
Table 2 summarizes the proportion of residential site trips distributed to the study area limits under the 2024 and 2029 road network. The raw TTS data outputs are provided in Appendix D.
It has been noted by the region that the proposed development is a green field development, where caution must be taken using TTS data due to lack of data. Therefore, as shown in Appendix D, the 2016 TTS data was taken under planning district settings to capture trips distributions for larger Milton area.
Table 2 Site Trip Distribution
Trip Orientation AM Peak Hour PM Peak Hour In Out In Out
North – Tremaine Road 30% 30% 30% 30% East – Britannia Road 52% 52% 52% 52% West – Britannia Road 18% 18% 18% 18%
It was noted by the region and the town that development as large as the subject site requires trips to be distributed in separate sections, grouped by their location. Therefore, the estimated site trips in Figure 11 were divided into four sections, then distributed using the TTS results shown in Table 4. The detailed sectional internal trips within the subject site are shown in Appendix D.
6. Future Total Traffic
The future total traffic conditions for the 2024 and 2029 planning horizons were derived by combining the projected future background traffic with the corresponding estimate of the total site generated traffic. Peak hour future total traffic volumes for the 2024 and 2029 horizon years are presented in Figure 15 and Figure 16, respectively.
GHD | Pony Pines Development Inc. | 8811691 | Page 25
Figure 15 2024 Future Total Volumes
(12)
(579
)
(825
)
752 (597)
11 848
379
5 (10)
358 (236)
(13) 5
(12) 8 0 947
352
(7) 3 (0
)
(951
)
(284
)
(932
)
(51)
(37)
(26) 7 (15)
(216
)
(74)
(14) 10 (14)
1258 47 43 11 243 (224) 232
46 5 1 (12)
268 (171) 127 (75) 7 (10)
(49) 41 (104) 113
1018
390 (199) 231 71 50 35 (14) 0 146
82 4
(109
6)
(477
)
(157) 185
(58)
(42)
(30) (143) 208
(124
)
(90)
(15)
(108
5)
(13)
(202
)
(13) 3 (4) (32)
(244
)
(0)
0 (0)
1311 43 270
34 80 (44) 39 358 0 11 (7)
190 (106) 3 (2) 21 (13)
(3) 0 (19) 39
1163 68 (7) 10 73 63 1 (0) 0 46 195 7
(118
4)
(180
)
(40) 64
(128
)
(87)
(2) (14) 21
(31)
(326
)
(14)
(99)
(567
)
(404
)
230 (233)
(110
)
(165
)
(32)
(286
)
102
1002
179
549 (396) 156
249
70 (149) 50 442
204 (370)
190 (157) 812 (696) 832 (813)
(191) 158 (128) 50 (115) 35
(587) 355 4 843
103 (1075) 587 (1113) 800
(15) 15
(4)
(117
5)
(212
)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C
Tremaine Road
Street A
Collector A
Britannia Road
Street B
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 26
Figure 16 2029 Future Total Volumes
(12)
(939
)
(825
)
752 (597)
11 1077
379
6 (11)
358 (236)
(13) 5
(14) 10 0
1000
352
(7) 3 (0
)
(103
6)
(284
)
(889
)
(297
)
(51)
(37)
(26) 7 (15)
(216
)
(74)
(14) 10 (14)
1155
288
268 (171) 47 43 11 268 (235) 232
46 5 1 (12)
74 (51) 102 (64) 7 (10)
(49) 41 (104) 113
1071 48 (199) 231 79 50 35 (14) 0 146
82 4
(118
1)
(41) (114) 141
(61)
(42)
(30) (143) 208
(124
)
(90)
(15)
(859
)
(81)
(13)
(123
)
(13) 3 (4) (36)
(240
)
(0)
0 (0)
1204 25 190 (106) 43 190
34 96 (52) 46 351 0 14 (9)
10 (19) 3 (2) 19 (12)
(3) 0 (19) 39
874
10 (6) 10 76 63 1 (0) 0 52 189 5
(106
8)
(34) (20) 33
(114
)
(87)
(2) (13) 21
(35)
(309
)
(12)
(158
)
(380
)
(341
)
230 (233) (32)
(140
)
(23)
(286
)
180
851
182
466 (354) 63 223
70 (149) 36 442
204 (370)
180 (146) 812 (701) 847 (827)
(191) 158 (90) 39 (77) 24
(620) 388 4 496
103 (1082) 634 (1145) 833
(15) 15
(4)
(678
)
(212
)
Britannia Road
Tremaine Road
Louis Saint Laurent Ave
Louis Saint Laurent Ave
Street C
Tremaine Road
Street A
Collector A
Britannia Road
Street B
AM Peak Hour VolumesPM Peak Hour Volumes
LEGENDXX
(XX)
NOT TO SCALE
GHD | Pony Pines Development Inc. | 8811691 | Page 27
7. Intersection Capacity Analysis
The capacity analysis identifies how well the intersections and driveways are operating. The analysis contained within this report utilized the Highway Capacity Manual (HCM) 2000 techniques within the Synchro Version 10 Software package. The reported intersection volume-to-capacity ratios (v/c) are a measure of the saturation volume for each turning movement, while the levels-of-service (LOS) are a measure of the average delay for each turning movement. Queuing characteristics are reported as the predicted 95th percentile queue for each turning movement.
In accordance with the Town of Milton’s and Halton Region Transportation Impact Study Guidelines, the analysis includes identification for all v/c ratios, LOS indicators and 95th percentile queue lengths for all movements at all study intersections. Critical intersections and movements shall be highlighted (in bold). ‘Critical’ intersections and movements include:
• v/c ratios for overall intersections, through movements, or shared through/turning movements increases to 0.85 or above.
• v/c ratios for exclusive turning movements increases to 0.95 or above.
• Queues for an individual movement are projected to exceed available turning lane storage.
The detailed Synchro reports are provided in Appendix E.
The following tables summarize the Synchro/HCM capacity results for the study intersections during the weekday peak hours under existing and future conditions.
7.1 Britannia Road at Street A Signalized capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 3 from the appended detailed Synchro reports.
Table 3 Capacity Analysis for Britannia Road at Street A
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
Overall: v/c 0.75 (B) EBTL = 0.66 (A) 70 m WBTR = 0.80 (B) 170 m SBLR = 0.59 (C) 35 m
Overall: v/c 1.22 (F) EBTL = 1.42 (F) 235 m WBTR = 0.81 (B) 195 m SBLR = 0.78 (C) 35 m
Future Background 2024
Overall: v/c 0.43 (B) EBTL = 0.37 (A) 20 m WBTR = 0.45 (B) 35 m SBLR = 0.42 (B) 40 m
Overall: v/c 0.42 (A) EBTL = 0.37 (A) 20 m WBTR = 0.29 (A) 25 m SBLR = 0.56 (C) 35 m
Future Total 2024 Overall: v/c 0.60 (B) Overall: v/c 0.65 (A)
GHD | Pony Pines Development Inc. | 8811691 | Page 28
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour EBTL = 0.42 (A) 25 m WBTR = 0.43 (B) 40 m SBLR = 0.83 (C) 80 m
EBTL = 0.62 (A) 40 m WBTR = 0.41 (A) 30 m SBLR = 0.72 (C) 55 m
Future Total 2029 Overall: v/c 0.59 (B) EBTL = 0.41 (A) 25 m WBTR = 0.41 (B) 40 m SBLR = 0.82 (C) 75 m
Overall: v/c 0.61 (A) EBTL = 0.56 (A) 30 m WBTR = 0.41 (A) 35 m SBLR = 0.71 (C) 55 m
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing. Any current capacity constraints on Britannia Road are expected to be mitigated by the future planned widening.
7.2 Britannia Road at Street C
Signalized capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 4 from the appended detailed Synchro reports.
Table 4 Capacity Analysis for Britannia Road at Street C
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
Overall: v/c 0.70 (B) EBTL = 0.50 (A) 65 m WBTR = 0.74 (A) 135 m SBLR = 0.55 (C) 35 m
Overall: v/c 0.80 (B) EBTL = 0.88 (B) 195 m WBTR = 0.69 (A) 65 m SBLR = 0.41 (C) 25 m
Future Background 2024
Overall: v/c 0.37 (A) EBTL = 0.22 (A) 20 m WBTR = 0.28 (A) 25 m SBLR = 0.63 (C) 35 m
Overall: v/c 0.35 (A) EBTL = 0.33 (A) 25 m WBTR = 0.22 (A) 15 m SBLR = 0.43 (C) 25 m
Future Total 2024 Overall: v/c 0.49 (B) EBTL = 0.30 (A) 25 m WBTR = 0.34 (A) 25 m SBLR = 0.74 (C) 50 m
Overall: v/c 0.48 (A) EBTL = 0.55 (A) 50 m WBTR = 0.28 (A) 15 m SBLR = 0.64 (C) 40 m
Future Total 2029 Overall: v/c 0.41 (B) EBTL = 0.28 (A) 25 m WBTR = 0.31 (A) 25 m SBLR = 0.65 (C) 40 m
Overall: v/c 0.48 (A) EBTL = 0.47 (A) 35 m WBTR = 0.27 (A) 15 m SBLR = 0.53 (C) 30 m
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing.
GHD | Pony Pines Development Inc. | 8811691 | Page 29
7.3 Tremaine Road at Street B
Capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 5 from the appended detailed Synchro reports. As requested by the town, this intersection was analyzed as a RIRO unsignalized intersection for existing + Boyne, future background 2024 and future total 2024, but as a full-moves signalized intersection for future total 2029.
Note this intersection was analyzed with an exclusive right-turn lane for the northbound (south leg) approach for this revision of the report, at the request from the Region of Halton (January 17, 2020).
Table 5 Capacity Analysis for Tremaine Road at Street B
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan WBR = 0.20 (B) <1 veh WBR = 0.20 (B) <1 veh
Future Background 2024 WBR = 0.09 (B) <1 veh WBR = 0.03 (B) <1 veh
Future Total 2024 WBR = 0.35 (B) 15 m WBR = 0.20 (B) <1 veh
Future Total 2029
Overall: 0.44 (A) WBLR = 0.28 (B) 25 m NBT = 0.35 (A) 30 m
NBR = 0.01 (A) <1 veh SBTL = 0.55 (A) 15 m
Overall: 0.37 (A) WBLR = 0.18 (B) 20 m NBT = 0.43 (A) 35 m
NBR = 0.02 (A) <1 veh SBTL = 0.49 (A) 15 m
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing. As shown in Table 10, the northbound right-turn lane will experience maximum 95th percentile queue of less than a car length (7 m).
7.4 Street A at Street B
Unsignalized capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 6 from the appended detailed Synchro reports.
Table 6 Capacity Analysis for Street A at Street B
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
EBTLR = 0.11 (B) <1 veh WBTLR = 0.00 (A) <1 veh NBTLR = 0.04 (A) <1 veh
EBTLR = 0.17 (B) <1 veh WBTLR = 0.00 (A) <1 veh NBTLR = 0.03 (A) <1 veh
GHD | Pony Pines Development Inc. | 8811691 | Page 30
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Future Background 2024
EBTLR = 0.10 (A) <1 veh WBTLR = 0.00 (A) <1 veh NBTLR = 0.00 (A) <1 veh
EBTLR = 0.01 (A) <1 veh WBTLR = 0.01 (A) <1 veh NBTLR = 0.01 (A) <1 veh
Future Total 2024 EBTLR = 0.17 (C) <1 veh WBTLR = 0.11 (C) <1 veh NBTLR = 0.04 (A) <1 veh
EBTLR = 0.08 (B) <1 veh WBTLR = 0.07 (C) <1 veh NBTLR = 0.04 (A) <1 veh
Future Total 2029 EBTLR = 0.17 (C) <1 veh WBTLR = 0.11 (C) <1 veh NBTLR = 0.05 (A) <1 veh
EBTLR = 0.08 (B) <1 veh WBTLR = 0.07 (C) <1 veh NBTLR = 0.04 (A) <1 veh
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing.
7.5 Street C at Street B
Unsignalized capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 7 from the appended detailed Synchro reports.
Table 7 Capacity Analysis for Street C at Street B
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
EBTLR = 0.16 (B) <1 veh WBTLR = 0.18 (B) <1 veh NBTLR = 0.06 (A) <1 veh SBTLR = 0.01 (A) <1 veh
EBTLR = 0.26 (B) 8 m WBTLR = 0.18 (B) <1 veh NBTLR = 0.05 (A) <1 veh SBTLR = 0.01 (A) <1 veh
Future Background 2024
EBTLR = 0.05 (B) <1 veh WBTLR = 0.01 (B) <1 veh NBTLR = 0.00 (A) <1 veh SBTLR = 0.02 (A) <1 veh
EBTLR = 0.01 (B) <1 veh WBTLR = 0.01 (B) <1 veh NBTLR = 0.00 (A) <1 veh SBTLR = 0.01 (A) <1 veh
Future Total 2024 EBTLR = 0.13 (B) <1 veh WBTLR = 0.25 (C) 10 m NBTLR = 0.06 (A) <1 veh SBTLR = 0.02 (A) <1 veh
EBTLR = 0.08 (B) <1 veh WBTLR = 0.15 (C) <1 veh NBTLR = 0.10 (A) <1 veh SBTLR = 0.01 (A) <1 veh
Future Total 2029 EBTLR = 0.07 (B) <1 veh WBTLR = 0.27 (C) 10 m NBTLR = 0.06 (A) <1 veh SBTLR = 0.02 (A) <1 veh
EBTLR = 0.05 (B) <1 veh WBTLR = 0.15 (C) <1 veh NBTLR = 0.09 (A) <1 veh SBTLR = 0.01 (A) <1 veh
GHD | Pony Pines Development Inc. | 8811691 | Page 31
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing.
7.6 Tremaine Road at Collector A
Capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 8 from the appended detailed Synchro reports. As requested by the town, this intersection was analyzed as a RIRO unsignalized intersection for existing + Boyne, future background 2024 and future total 2024, but as a full-moves signalized intersection for future total 2029.
Table 8 Capacity Analysis for Tremaine Road at Collector A
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
WBR = 0.35 (B) 15 m WBR = 0.38 (B) 15 m
Future Background 2024
WBR = 0.59 (C) 30 m WBR = 0.43 (C) 20 m
Future Total 2024
WBR = 0.64 (D) 35 m WBR = 0.46 (C) 20 m
Future Total 2029 Overall: v/c 0.64 (C) WBLR = 0.33 (C) 30 m NBTR = 0.77 (C) 65 m SBL = 0.77 (C) 50 m SBT = 0.45 (A) 40 m
Overall: v/c 0.64 (C) WBLR = 0.22 (B) 20 m NBTR = 0.84 (D) 75 m SBL = 0.79 (C) 55 m SBT = 0.35 (A) 30 m
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing.
7.7 Street A at Collector A
Unsignalized capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 9 from the appended detailed Synchro reports.
Table 9 Capacity Analysis for Street A at Collector A
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
EBTLR = 0.21 (B) <1 veh WBTLR = 0.13 (B) <1 veh NBTLR = 0.07 (A) <1 veh SBTLR = 0.01 (A) 1 veh
EBTLR = 0.46 (C) 20 m WBTLR = 0.03 (C) <1 veh NBTLR = 0.06 (A) <1 veh SBTLR = 0.02 (A) <1 veh
Future Background 2024
EBTLR = 0.60 (C) <1 veh WBTLR = 0.06 (C) <1 veh
EBTLR = 0.55 (C) 25 m WBTLR = 0.11 (C) <1 veh
GHD | Pony Pines Development Inc. | 8811691 | Page 32
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour NBTLR = 0.13 (A) <1 veh SBTLR = 0.00 (A) <1 veh
NBTLR = 0.11 (A) <1 veh SBTLR = 0.01 (A) <1 veh
Future Total 2024 EBTLR = 0.60 (C) 30 m WBTLR = 0.06 (C) <1 veh NBTLR = 0.13 (A) <1 veh SBTLR = 0.00 (A) <1 veh
EBTLR = 0.55 (C) 25 m WBTLR = 0.11 (C) <1 veh NBTLR = 0.11 (A) <1 veh SBTLR = 0.01 (A) <1 veh
Future Total 2029 EBTLR = 0.60 (C) 30 m WBTLR = 0.06 (C) <1 veh NBTLR = 0.13 (A) <1 veh SBTLR = 0.00 (A) <1 veh
EBTLR = 0.55 (C) 25 m WBTLR = 0.11 (C) <1 veh NBTLR = 0.11 (A) <1 veh SBTLR = 0.01 (A) <1 veh
Under all scenarios the intersection is expected to be operating acceptably, with reserve capacity, acceptable levels of delay, and no critical queueing.
7.8 Street C at Collector A
Unsignalized capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 10 from the appended detailed Synchro reports.
Table 10 Capacity Analysis for Street C at Collector A
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing + Boyne Secondary Plan
EBTLR = 0.01 (A) <1 veh WBTLR = 0.02 (A) <1 veh NBTLR = 0.32 (B) 10 m SBTLR = 0.14 (B) <1 veh
EBTLR = 0.02 (A) <1 veh WBTLR = 0.03 (A) <1 veh NBTLR = 0.33 (C) 11 m SBTLR = 0.21 (B) <1 veh
Future Background 2024
EBTLR = 0.03 (A) <1 veh WBTLR = 0.12 (A) <1 veh NBTLR = 0.89 (F) 55 m SBTLR = 0.41 (D) 15m
EBTLR = 0.04 (A) <1 veh WBTLR = 0.07 (A) <1 veh NBTLR = 0.53 (D) 25 m SBTLR = 0.36 (C) 15 m
Future Total 2024 EBTLR = 0.03 (A) <1 veh WBTLR = 0.12 (A) <1 veh NBTLR = 0.89 (F) 55 m SBTLR = 0.41 (D) 15 m
EBTLR = 0.04 (A) <1 veh WBTLR = 0.07 (A) <1 veh NBTLR = 0.54 (D) 25 m SBTLR = 0.36 (C) 15 m
Future Total 2029 EBTLR = 0.04 (A) <1 veh WBTLR = 0.10 (A) <1 veh NBTLR = 0.85 (F) 50 m SBTLR = 0.37 (C) 15 m
EBTLR = 0.04 (A) <1 veh WBTLR = 0.06 (A) <1 veh NBTLR = 0.52 (D) 20 m SBTLR = 0.35 (C) 15 m
GHD | Pony Pines Development Inc. | 8811691 | Page 33
The northbound shared through movement during the a.m. peak hour has unacceptable LOS and v/c for through movements under future background 2024, future total 2024 and future total 2029 scenarios. However, the movement has reserve capacity with maximum v/c ratio of 0.89 in horizon year 2024. Therefore it is expected that the intersection overall will not have significant traffic issues, especially since all other movements are operating well below capacity.
7.9 Tremaine Road at Louis Saint Laurent Avenue
Roundabout capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 11 from the appended detailed Synchro reports.
Table 11 Capacity Analysis for Tremaine Road at Louis Saint Laurent Avenue
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing SB = 0.33 (A) <25m EB = 0.01 (A) <25m NB = 0.22 (A) <25m WB = 0.13 (A) <25m
SB = 0.14 (A) <25m EB = 0.02 (A) <25m NB = 0.28 (A) <25m WB = 0.10 (A) <25m
Existing + Boyne Secondary Plan
SB = 0.56 (A) <25m EB = 0.01 (A) <25m NB = 0.61 (A) <25m WB = 0.74 (A) <25m
SB = 0.72 (C) 68m EB = 0.03 (A) <25m NB = 0.80 (B) <25m WB = 0.57 (A) <25m
Future Background 2024
SB = 0.65 (A) <25m EB = 0.02 (A) <25m NB = 0.64 (A) <25m WB = 0.74 (A) <25m
SB = 0.65 (A) <25m EB = 0.03 (A) <25m NB = 0.78 (B) <25m WB = 0.58 (A) <25m
Future Total 2024 SB = 0.67 (A) <25m EB = 0.02 (A) <25m NB = 0.71 (A) <25m WB = 0.80 (B) <25m
SB = 0.73 (A) <25m EB = 0.04 (A) <25m NB = 0.84 (A) <25m WB = 0.61 (A) <25m
Future Total 2029 SB = 0.80 (A) <25m EB = 0.02 (A) <25m NB = 0.74 (A) <25m WB = 0.83 (C) <25m
SB = 0.92 (C) <25m EB = 0.06 (A) <25m NB = 0.90 (C) 51m WB = 0.64 (A) <25m
Under all scenarios this roundabout intersection is expected to operate acceptably with ample reserve capacity, acceptable levels of delay, and no critical queueing. This includes a conservatively applied 15% y-intercept adjustment, as requested by the Town, which is meant to simulate inefficient roundabout operations. Results
GHD | Pony Pines Development Inc. | 8811691 | Page 34
from the analysis without the applied y-intercept adjustment are appended, which illustrate very acceptable conditions.
7.10 Tremaine Road at Britannia Road
Roundabout capacity analyses during the weekday a.m. and p.m. peak hours are summarized in Table 12 from the appended detailed Synchro reports.
Table 12 Capacity Analysis for Tremaine Road at Britannia Road
Traffic Condition Movement v/c (LOS) 95th Percentile Queue AM Peak Hour PM Peak Hour
Existing SB = 0.35 (A) <25m EB = 0.16 (A) <25m NB = 0.22 (A) <25m WB = 0.07 (A) <25m
SB = 0.16 (A) <25m EB = 0.13 (A) <25m NB = 0.27 (A) <25m WB = 0.10 (A) <25m
Existing + Boyne Secondary Plan
SB = 0.55 (A) <25m EB = 0.31 (A) <25m NB = 0.38 (A) <25m WB = 0.52 (A) <25m
SB = 0.40 (A) <25m EB = 0.42 (A) <25m NB = 0.79 (A) <25m WB = 0.54 (A) <25m
Future Background 2024
SB = 0.78 (B) <25m EB = 0.47 (A) <25m NB = 0.59 (A) <25m WB = 0.67 (A) <25m
SB = 0.54 (A) <25m EB = 0.52 (A) <25m NB = 1.02 (F) 317m WB = 0.54 (A) <25m
Future Total 2024 SB = 0.84 (B) <25m EB = 0.52 (A) <25m NB = 0.61 (A) <25m WB = 0.73 (B) <25m
SB = 0.64 (A) <25m EB = 0.65 (A) <25m NB = 1.18 (F) 583m WB = 0.66 (A) <25m
Future Total 2029 SB = 0.76 (A) <25m EB = 0.49 (A) <25m NB = 0.39 (A) <25m WB = 0.55 (A) <25m
SB = 0.51 (A) <25m EB = 0.58 (A) <25m NB = 0.75 (A) <25m WB = 0.52 (A) <25m
Under all scenarios this roundabout intersection is expected to operate acceptably with ample reserve capacity, acceptable levels of delay, and no critical queueing. This includes a conservatively applied 15% y-intercept adjustment, as requested by the Town, which is meant to simulate inefficient roundabout operations. Results from the analysis without the applied y-intercept adjustment are appended, which illustrate very acceptable conditions.
GHD | Pony Pines Development Inc. | 8811691 | Page 35
8. All-Way Stop Control Warrants
The Town has requested all-way stop control warrants, per the Ministry of Transportation Ontario’s (MTO) Ontario Traffic Manual (OTM) methodology, be undertaken for the future internal intersections in the development.
According to the OTM Book 5 (2012), the first criteria of the warrant includes volume conditions where total vehicle volume on all intersection approaches must exceed 350 for the highest hour recorded (minor roads warrant) to satisfy the condition.
The second criteria requires volumes do not exceed a directional split of 75/25 (i.e., 75 percent of traffic travelling east-west, 25 percent of traffic travelling north-south) for t-intersections, and 65/35 for four-legged intersections. This is because it is strongly recommended that the overall intersection volume be relatively evenly dispersed among the approaches, rather than overly concentrated to one or two approaches, for an all-way stop control to operate efficiently.
Both criteria must be met. The results of the volume warrants based on the forecasted 2029 future total volumes are as follows:
• Street ‘B’ at Street ‘C’ (four-legged intersection)
− Highest hour recorded – a.m. peak hour: 549 vph (satisfied) − North/South-East/West Directional Split: 74% north-south, 26% east-west (not
satisfied)
• Street ‘B’ at Street ‘A’ (four-legged intersection)
− Highest hour recorded – p.m. peak hour: 736 vph (satisfied)
− North/South-East/West Directional Split: 87% north-south, 13% east-west (not satisfied)
As shown above, both intersections do not satisfy both directional split criteria.
The Town has also requested a 5% handicap be applied to the directional-split criteria of the volume warrants, resulting in a direction split threshold of 80/20 for t-intersections, and 70/30 for four-legged intersections. Even with this handicapped directional split criteria applied, both intersections have too much high of a directional split to satisfy the warrant.
Given the Town has requested roundabouts be proposed at intersections warranting all-way stop control, roundabouts at Street ‘B’ at Street ‘C’ and Street ‘B’ at Street ‘A’ are not warranted.
GHD | Pony Pines Development Inc. | 8811691 | Page 36
9. Draft Plan Review
GHD undertook a review of the proposed layout of the Draft Plan from a traffic operational and safety perspective, with the following key findings:
• The north-south Street ‘C’ and east-west Street ‘B’ local roads are proposed to have a right-of-way width of 20 metres, which adheres to the preferred width as per the Boyne RNA;
• The north-south Street ‘A’ collector road is proposed to have a right-of-way width of 24 metres, which adheres to the preferred width as per the Boyne RNA;
• The internal site local roads are proposed to have a right-of-way width of 16 metres, which is considered acceptable from a transportation perspective;
• Several 90 degree bends are proposed within the internal local road network, which is considered acceptable for local roads based on common subdivision planning practice;
• Intersection spacing meets the 40 metre minimum t-intersection recommended spacing (measured centreline-to-centreline) as per the Transportation Association of Canada (TAC) Geometric Design Guide for Canadian Roads;
• Intersection spacing meets the 60 metre minimum four-legged intersection recommended spacing (measured centreline-to-centreline) as per the Transportation Association of Canada (TAC) Geometric Design Guide for Canadian Roads;
• Any horizontal curves in the collector road alignments are considered minor, with the recommended 85 metre stopping sight distance along all segments and 130 metre intersection sight distance at all intersections (for 60 km/h design speeds) as per TAC expected to be achievable;
• Given the proposed curve in right-of-way alignment of Street ‘B’ just west of Street ‘C’, a detailed sightline assessment can be undertaken for this approach to the intersection upon development of a detailed roadway design. The objective will be to align the road within the curved right-of-way so as to ensure the minimum recommended sightlines are maintained as per TAC.
• All internal intersections are proposed as two-way stop controlled (roundabout control is not recommended as per the Boyne RNA report);
• Per the Town’s Transportation Master Plan, Street ‘B’ and Street ‘A’ north of Street ‘B’ are expected to include on-street bike lanes;
• Sidewalks are expected on both sides of all local and collector roads; • On-street parking is generally expected on both sides of collector roads, and
on one side of local roads.
GHD | Pony Pines Development Inc. | 8811691 | Page 37
10. Conclusion
The proposed development is expected to generate a total of 630 two-way vehicle trips during the a.m. peak hour consisting of 154 inbound and 476 outbound trips. During the p.m. peak hour it is expected to generate 811 new two-way vehicle trips consisting of 510 inbound and 301 outbound trips.
The study area intersections are expected to operate generally well during the peak hours under 2024 and 2029 future conditions, under each intersections respective planned future traffic control and configuration.
Based on a review of the proposed Draft Plan road network layout, the layout is considered acceptable, meeting the Town’s, Region’s, and TAC’s applicable guidelines. There is not expected to be any significant operational, safety or sightline concerns with the Draft Plan.
Appendices
Appendix B
Proxy Parking Survey Results
Appendix A
Traffic Data
Ontario Traffic Inc.
Morning Peak Diagram Specified Period
From:
To:
7:00:00
9:00:00
One Hour Peak
From:
To:
7:30:00
8:30:00
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Milton
1605100001
Tremaine Rd & Britannia Rd
1
11-Feb-16
Weather conditions:
Person(s) who counted:
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
782
484
0
Cyclists
Trucks
Cars
Totals
0
0
47
47
0
5
399
404
0
2
31
33
0
7
477
Cyclists
Trucks
Cars
Totals
0
6
292
298
CyclistsTrucks Cars Totals
0 2 124 126
CyclistsTrucks Cars Totals
0 1 47 48
0 2 168 170
0 1 14 15
0 4 229
Peds Cross:
West Peds:
West Entering:
West Leg Total:
0
233
359
Tremaine Rd
Britannia Rd
W
N
E
S
Britannia Rd
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
380
124
0
Cars Trucks CyclistsTotals
10 2 0 12
73 2 0 75
37 0 0 37
120 4 0
Cars Trucks CyclistsTotals
252 4 0 256
Cars
Trucks
Cyclists
Totals
450
6
0
456
Cars
Trucks
Cyclists
Totals
4
0
0
4
235
3
0
238
53
0
0
53
292
3
0
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
295
751
Comments
Ontario Traffic Inc.
Afternoon Peak Diagram Specified Period
From:
To:
16:00:00
18:00:00
One Hour Peak
From:
To:
17:00:00
18:00:00
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Milton
1605100001
Tremaine Rd & Britannia Rd
1
11-Feb-16
Weather conditions:
Person(s) who counted:
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
672
231
0
Cyclists
Trucks
Cars
Totals
0
0
44
44
0
3
172
175
0
1
11
12
0
4
227
Cyclists
Trucks
Cars
Totals
0
3
438
441
CyclistsTrucks Cars Totals
0 2 222 224
CyclistsTrucks Cars Totals
0 0 47 47
0 0 81 81
0 0 8 8
0 0 136
Peds Cross:
West Peds:
West Entering:
West Leg Total:
0
136
360
Tremaine Rd
Britannia Rd
W
N
E
S
Britannia Rd
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
380
260
0
Cars Trucks CyclistsTotals
48 0 0 48
167 2 0 169
43 0 0 43
258 2 0
Cars Trucks CyclistsTotals
119 1 0 120
Cars
Trucks
Cyclists
Totals
223
3
0
226
Cars
Trucks
Cyclists
Totals
11
0
0
11
343
3
0
346
27
0
0
27
381
3
0
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
384
610
Comments
Ontario Traffic Inc.
Total Count Diagram
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Milton
1605100001
Tremaine Rd & Britannia Rd
1
11-Feb-16
Weather conditions:
Person(s) who counted:
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
2545
1309
0
Cyclists
Trucks
Cars
Totals
0
1
180
181
0
21
1027
1048
0
5
75
80
0
27
1282
Cyclists
Trucks
Cars
Totals
0
15
1221
1236
CyclistsTrucks Cars Totals
0 13 688 701
CyclistsTrucks Cars Totals
0 1 146 147
0 3 392 395
0 1 40 41
0 5 578
Peds Cross:
West Peds:
West Entering:
West Leg Total:
0
583
1284
Tremaine Rd
Britannia Rd
W
N
E
S
Britannia Rd
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
1361
734
0
Cars Trucks CyclistsTotals
110 3 0 113
478 10 0 488
133 0 0 133
721 13 0
Cars Trucks CyclistsTotals
619 8 0 627
Cars
Trucks
Cyclists
Totals
1200
22
0
1222
Cars
Trucks
Cyclists
Totals
30
2
0
32
965
11
0
976
152
0
0
152
1147
13
0
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
1160
2382
Comments
Ontario Traffic Inc.
Traffic Count SummaryIntersection: Tremaine Rd & Britannia Rd Count Date: 11-Feb-16 Municipality: Milton
North Approach Totals South Approach Totals
East Approach Totals West Approach Totals
Includes Cars, Trucks, & Cyclists Includes Cars, Trucks, & Cyclists
Includes Cars, Trucks, & Cyclists Includes Cars, Trucks, & Cyclists
Hour Hour
Hour Hour
Ending Ending
Ending Ending
Left Left
Left Left
Thru Thru
Thru Thru
Right Right
Right Right
Grand Grand
Grand Grand
Total Total
Total Total
Total Total
Total Total
Peds Peds
Peds Peds
North/South
East/West
Total
Total
Approaches
Approaches
Calculated Values for Traffic Crossing Major Street
Hours Ending:Crossing Values:
Totals:
Totals:
7:00:00 0 0 0 0 0 0 7:00:00 0 0 0 0 08:00:00 28 355 36 419 0 657 8:00:00 5 190 43 238 09:00:00 35 318 45 398 0 643 9:00:00 5 186 54 245 0
16:00:00 0 0 0 0 0 0 16:00:00 0 0 0 0 017:00:00 5 200 56 261 0 554 17:00:00 11 254 28 293 018:00:00 12 175 44 231 0 615 18:00:00 11 346 27 384 0
7:00:00 0 0 0 0 0 0 7:00:00 0 0 0 0 08:00:00 23 45 5 73 0 263 8:00:00 35 140 15 190 09:00:00 26 65 13 104 0 275 9:00:00 36 123 12 171 0
16:00:00 0 0 0 0 0 0 16:00:00 0 0 0 0 017:00:00 41 209 47 297 0 383 17:00:00 29 51 6 86 018:00:00 43 169 48 260 0 396 18:00:00 47 81 8 136 0
0:00 0:00 7:00 8:00 9:00 16:00 17:00 18:000 0 0 198 185 0 279 259
80 1048 181 1309 0 2469 32 976 152 1160 0
133 488 113 734 0 1317 147 395 41 583 0
On
tario
Traff
ic In
c.
Co
un
t D
ate
: 1
1-F
eb
-16
Sit
e #
: 1
605100001
Inte
rval
Tim
e
Passen
ger
Cars
- N
ort
h A
pp
roach
Tru
cks -
No
rth
Ap
pro
ach
Cycli
sts
- N
ort
h A
pp
roach
Ped
estr
ian
s
Left
Left
Left
Th
ruT
hru
Th
ruR
igh
tR
igh
tR
igh
tN
ort
h C
ross
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
7:0
0:0
00
00
00
00
00
00
00
00
00
00
0
7:1
5:0
05
545
45
11
00
44
00
00
00
00
00
7:3
0:0
015
10
125
80
12
11
00
40
00
00
00
00
00
7:4
5:0
021
6249
124
26
14
11
51
00
00
00
00
00
8:0
0:0
027
6350
101
36
10
10
50
00
00
00
00
00
8:1
5:0
037
10
426
76
47
11
10
61
00
00
00
00
00
8:3
0:0
046
9524
98
59
12
21
93
00
00
00
00
00
8:4
5:0
051
5601
77
74
15
31
10
10
00
00
00
00
0
9:0
0:0
060
9662
61
81
73
011
10
00
00
00
00
0
9:0
3:3
360
0662
081
03
011
00
00
00
00
00
0
16:0
0:0
060
0662
081
03
011
00
00
00
00
00
0
16:1
5:0
061
1713
51
93
12
30
14
30
00
00
00
00
0
16:3
0:0
062
1768
55
107
14
30
14
01
10
00
00
00
0
16:4
5:0
063
1812
44
118
11
41
17
31
00
00
00
00
0
17:0
0:0
064
1855
43
136
18
40
18
11
00
00
00
00
0
17:1
5:0
068
4902
47
151
15
40
20
21
00
00
00
00
0
17:3
0:0
069
1951
49
163
12
40
20
01
00
00
00
00
0
17:4
5:0
073
4985
34
176
13
40
20
01
00
00
00
00
0
18:0
0:0
075
21027
42
180
45
121
11
00
00
00
00
0
18:1
5:0
075
01027
0180
05
021
01
00
00
00
00
0
18:1
7:3
775
01027
0180
05
021
01
00
00
00
00
0
On
tario
Traff
ic In
c.
Co
un
t D
ate
: 1
1-F
eb
-16
Sit
e #
: 1
605100001
Inte
rval
Tim
e
Passen
ger
Cars
- E
ast
Ap
pro
ach
Tru
cks -
East
Ap
pro
ach
Cycli
sts
- E
ast
Ap
pro
ach
Ped
estr
ian
s
Left
Left
Left
Th
ruT
hru
Th
ruR
igh
tR
igh
tR
igh
tE
ast
Cro
ss
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
7:0
0:0
00
00
00
00
00
00
00
00
00
00
0
7:1
5:0
01
11
10
00
00
00
00
00
00
00
0
7:3
0:0
05
47
61
10
00
00
00
00
00
00
0
7:4
5:0
016
11
22
15
21
00
11
00
00
00
00
00
8:0
0:0
023
743
21
53
00
21
00
00
00
00
00
8:1
5:0
033
10
57
14
72
00
20
11
00
00
00
00
8:3
0:0
042
980
23
11
40
02
02
10
00
00
00
0
8:4
5:0
046
491
11
14
30
03
13
10
00
00
00
0
9:0
0:0
049
3105
14
15
10
05
23
00
00
00
00
0
9:0
3:3
349
0105
015
00
05
03
00
00
00
00
0
16:0
0:0
049
0105
015
00
05
03
00
00
00
00
0
16:1
5:0
059
10
149
44
23
80
06
13
00
00
00
00
0
16:3
0:0
069
10
197
48
34
11
00
71
30
00
00
00
00
16:4
5:0
076
7242
45
47
13
00
70
30
00
00
00
00
17:0
0:0
090
14
311
69
62
15
00
81
30
00
00
00
00
17:1
5:0
0101
11
350
39
75
13
00
10
23
00
00
00
00
0
17:3
0:0
0112
11
404
54
84
90
010
03
00
00
00
00
0
17:4
5:0
0124
12
447
43
98
14
00
10
03
00
00
00
00
0
18:0
0:0
0133
9478
31
110
12
00
10
03
00
00
00
00
0
18:1
5:0
0133
0478
0110
00
010
03
00
00
00
00
0
18:1
7:3
7133
0478
0110
00
010
03
00
00
00
00
0
On
tario
Traff
ic In
c.
Co
un
t D
ate
: 1
1-F
eb
-16
Sit
e #
: 1
605100001
Inte
rval
Tim
e
Passen
ger
Cars
- S
ou
th A
pp
roach
Tru
cks -
So
uth
Ap
pro
ach
Cycli
sts
- S
ou
th A
pp
roach
Ped
estr
ian
s
Left
Left
Left
Th
ruT
hru
Th
ruR
igh
tR
igh
tR
igh
tS
ou
th C
ross
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
7:0
0:0
00
00
00
00
00
00
00
00
00
00
0
7:1
5:0
00
027
27
77
00
00
00
00
00
00
00
7:3
0:0
04
465
38
19
12
00
11
00
00
00
00
00
7:4
5:0
05
1124
59
30
11
00
10
00
00
00
00
00
8:0
0:0
05
0188
64
43
13
00
21
00
00
00
00
00
8:1
5:0
08
3244
56
58
15
00
31
00
00
00
00
00
8:3
0:0
08
0300
56
72
14
00
41
00
00
00
00
00
8:4
5:0
09
1343
43
82
10
00
51
00
00
00
00
00
9:0
0:0
010
1371
28
97
15
00
50
00
00
00
00
00
9:0
3:3
310
0371
097
00
05
00
00
00
00
00
0
16:0
0:0
010
0371
097
00
05
00
00
00
00
00
0
16:1
5:0
010
0425
54
105
82
27
20
00
00
00
00
0
16:3
0:0
011
1485
60
111
62
08
10
00
00
00
00
0
16:4
5:0
015
4549
64
117
62
08
00
00
00
00
00
0
17:0
0:0
019
4622
73
125
82
08
00
00
00
00
00
0
17:1
5:0
024
5705
83
135
10
20
80
00
00
00
00
00
17:3
0:0
025
1780
75
143
82
08
00
00
00
00
00
0
17:4
5:0
025
0869
89
148
52
010
20
00
00
00
00
0
18:0
0:0
030
5965
96
152
42
011
10
00
00
00
00
0
18:1
5:0
030
0965
0152
02
011
00
00
00
00
00
0
18:1
7:3
730
0965
0152
02
011
00
00
00
00
00
0
On
tario
Traff
ic In
c.
Co
un
t D
ate
: 1
1-F
eb
-16
Sit
e #
: 1
605100001
Inte
rval
Tim
e
Passen
ger
Cars
- W
est
Ap
pro
ach
Tru
cks -
West
Ap
pro
ach
Cycli
sts
- W
est
Ap
pro
ach
Ped
estr
ian
s
Left
Left
Left
Th
ruT
hru
Th
ruR
igh
tR
igh
tR
igh
tW
est
Cro
ss
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Cu
mC
um
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
Incr
7:0
0:0
00
00
00
00
00
00
00
00
00
00
0
7:1
5:0
04
426
26
33
00
00
00
00
00
00
00
7:3
0:0
08
451
25
63
00
11
00
00
00
00
00
7:4
5:0
021
13
94
43
10
41
12
11
10
00
00
00
0
8:0
0:0
034
13
138
44
14
41
02
01
00
00
00
00
0
8:1
5:0
048
14
173
35
18
41
03
11
00
00
00
00
0
8:3
0:0
055
7219
46
20
21
03
01
00
00
00
00
0
8:4
5:0
065
10
247
28
26
61
03
01
00
00
00
00
0
9:0
0:0
070
5260
13
26
01
03
01
00
00
00
00
0
9:0
3:3
370
0260
026
01
03
01
00
00
00
00
0
16:0
0:0
070
0260
026
01
03
01
00
00
00
00
0
16:1
5:0
075
5274
14
29
31
03
01
00
00
00
00
0
16:3
0:0
084
9284
10
30
11
03
01
00
00
00
00
0
16:4
5:0
091
7300
16
32
21
03
01
00
00
00
00
0
17:0
0:0
099
8311
11
32
01
03
01
00
00
00
00
0
17:1
5:0
0106
7323
12
34
21
03
01
00
00
00
00
0
17:3
0:0
0117
11
337
14
34
01
03
01
00
00
00
00
0
17:4
5:0
0131
14
350
13
37
31
03
01
00
00
00
00
0
18:0
0:0
0146
15
392
42
40
31
03
01
00
00
00
00
0
18:1
5:0
0146
0392
040
01
03
01
00
00
00
00
0
18:1
7:3
7146
0392
040
01
03
01
00
00
00
00
0
Tremaine Rd @ Louis St Laurent
Morning Peak Diagram Specified Period
From:
To:
7:00:00
9:00:00
One Hour Peak
From:
To:
7:30:00
8:30:00
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Halton Region
0000003186
Tremaine Rd & Louis St Laurent
3
24-May-2018
Weather conditions:Clear/Dry
Person(s) who counted:Cam
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
1011
652
0
Heavys
Trucks
Cars
Totals
0
1
10
11
8
12
524
544
6
3
88
97
14
16
622
Heavys
Trucks
Cars
Totals
14
7
338
359
Heavys Trucks Cars Totals
0 1 14 15
Heavys Trucks Cars Totals
0 0 5 5
0 1 6 7
0 0 3 3
0 1 14
Peds Cross:
West Peds:
West Entering:
West Leg Total:
0
15
30
Tremaine Rd
Louis St Laurent
W
N
E
S
Louis St Laurent
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
531
249
1
Cars Trucks Heavys Totals
66 1 8 75
4 0 0 4
158 2 10 170
228 3 18
Cars Trucks Heavys Totals
257 4 21 282
Cars
Trucks
Heavys
Totals
685
14
18
717
Cars
Trucks
Heavys
Totals
0
0
0
0
267
6
6
279
163
0
15
178
430
6
21
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
457
1174
Comments
Tremaine Rd @ Louis St Laurent
Mid-day Peak Diagram Specified Period
From:
To:
11:00:00
14:00:00
One Hour Peak
From:
To:
12:00:00
13:00:00
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Halton Region
0000003186
Tremaine Rd & Louis St Laurent
3
24-May-2018
Weather conditions:Clear/Dry
Person(s) who counted:Cam
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
367
169
0
Heavys
Trucks
Cars
Totals
0
0
16
16
5
8
110
123
8
2
20
30
13
10
146
Heavys
Trucks
Cars
Totals
9
5
184
198
Heavys Trucks Cars Totals
0 3 30 33
Heavys Trucks Cars Totals
0 0 7 7
0 0 6 6
0 2 8 10
0 2 21
Peds Cross:
West Peds:
West Entering:
West Leg Total:
1
23
56
Tremaine Rd
Louis St Laurent
W
N
E
S
Louis St Laurent
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
181
97
2
Cars Trucks Heavys Totals
28 2 9 39
8 0 0 8
48 0 2 50
84 2 11
Cars Trucks Heavys Totals
59 2 23 84
Cars
Trucks
Heavys
Totals
166
10
7
183
Cars
Trucks
Heavys
Totals
6
3
0
9
149
3
0
152
33
0
15
48
188
6
15
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
209
392
Comments
Tremaine Rd @ Louis St Laurent
Afternoon Peak Diagram Specified Period
From:
To:
15:00:00
18:00:00
One Hour Peak
From:
To:
16:45:00
17:45:00
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Halton Region
0000003186
Tremaine Rd & Louis St Laurent
3
24-May-2018
Weather conditions:Clear/Dry
Person(s) who counted:Cam
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
835
293
0
Heavys
Trucks
Cars
Totals
0
0
12
12
1
1
241
243
0
0
38
38
1
1
291
Heavys
Trucks
Cars
Totals
7
4
531
542
Heavys Trucks Cars Totals
0 0 20 20
Heavys Trucks Cars Totals
0 0 13 13
0 0 10 10
0 0 7 7
0 0 30
Peds Cross:
West Peds:
West Entering:
West Leg Total:
1
30
50
Tremaine Rd
Louis St Laurent
W
N
E
S
Louis St Laurent
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
358
174
3
Cars Trucks Heavys Totals
83 1 1 85
8 0 0 8
80 0 1 81
171 1 2
Cars Trucks Heavys Totals
181 0 3 184
Cars
Trucks
Heavys
Totals
328
1
2
331
Cars
Trucks
Heavys
Totals
0
0
0
0
435
3
6
444
133
0
3
136
568
3
9
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
580
911
Comments
Tremaine Rd @ Louis St Laurent
Total Count Diagram
Municipality:
Site #:
Intersection:
TFR File #:
Count date:
Halton Region
0000003186
Tremaine Rd & Louis St Laurent
3
24-May-2018
Weather conditions:Clear/Dry
Person(s) who counted:Cam
** Non-Signalized Intersection ** Major Road: Tremaine Rd runs N/S
North Leg Total:
North Entering:
North Peds:
Peds Cross:
5033
2514
1
Heavys
Trucks
Cars
Totals
0
2
75
77
43
46
1976
2065
61
9
302
372
104
57
2353
Heavys
Trucks
Cars
Totals
100
39
2380
2519
Heavys Trucks Cars Totals
0 9 137 146
Heavys Trucks Cars Totals
0 1 56 57
0 2 47 49
0 3 40 43
0 6 143
Peds Cross:
West Peds:
West Entering:
West Leg Total:
5
149
295
Tremaine Rd
Louis St Laurent
W
N
E
S
Louis St Laurent
Tremaine Rd
East Leg Total:
East Entering:
East Peds:
Peds Cross:
2394
1273
10
Cars Trucks Heavys Totals
409 9 61 479
54 2 0 56
709 5 24 738
1172 16 85
Cars Trucks Heavys Totals
949 16 156 1121
Cars
Trucks
Heavys
Totals
2725
54
67
2846
Cars
Trucks
Heavys
Totals
8
5
0
13
1915
29
39
1983
600
5
95
700
2523
39
134
Peds Cross:
South Peds:
South Entering:
South Leg Total:
0
2696
5542
Comments
Appendix B
Background Developments Traffic Data
COLL
ECTO
R RO
AD 'A
'
COLL
ECTO
R RO
AD 'B
'
COLL
ECTO
R RO
AD 'C
'
COLL
ECTO
R RO
AD 'D
'
COLL
ECTO
R RO
AD 'E
'CO
LLEC
TOR
ROAD
'E'
COLL
ECTO
R RO
AD 'D
'
LOUI
S ST
. LAU
RENT
AVE
NUE
LOUI
S ST
. LAU
RENT
AVE
NUE
BRIT
ANNI
A RO
AD W
EST
SIXTEEN MILE CREEK
DIEFENBAKER STREET
FARMSTEAD DRIVE
LEGER WAY
CN RAIL
SAVOLINE BOULEVARD
UREL WAY
TREMAINE ROAD
COLLECTOR ROAD 'H'
COLLECTOR ROAD 'I'
COLLECTOR ROAD 'I'
COLLECTOR ROAD 'J'
COLLECTOR ROAD 'U'
COLLECTOR ROAD 'J'
COLLECTOR ROAD 'V'
COLLEC
TOR ROAD 'K
' COLLECTOR ROAD 'K'
COLLECTOR ROAD 'L'
COLLECTOR ROAD 'L'
12
314
1516
1718
19
20
2625
2423
22
21
12
11
6
10
98
745
2713
2829
3031
32
COLLECTOR ROAD 'K'
COLL
ECTO
R RO
AD 'E
'
Job
Num
ber
Rev
isio
n
Fig
ure
Dat
e
6705
Mill
cree
k D
rive,
Uni
t 1, M
issi
ssau
ga O
ntar
io L
5N 5
M4
T 1
416
213
7121
F 1
416
890
8499
E in
fo@
ghdc
anad
a.co
mW
ww
w.g
hd.c
omG
:\Leg
acy\
Ser
nasT
rans
Tec
h\P
roje
cts\
2013
\132
21 B
OY
NE
RD
NE
ED
S A
SS
ES
SM
EN
T\O
CT
OB
ER
201
5 U
PD
AT
E -
US
E!!!
!!!!!!
!!\13
221
Boy
ne F
igur
es (
July
201
6).d
wg
Cad
File
No:
23 N
ovem
ber
2016
- 2
:34
PM
Plo
t Dat
e:A
dam
Mild
enbe
rger
Plo
tted
by:
01
Milt
on P
hase
3 L
ando
wne
rs G
roup
Boy
ne S
urve
yR
oad
Net
wor
k A
sses
smen
t
Wes
t Blo
ckB
oyne
Sur
vey
Roa
d N
etw
ork
28-2
1522
C July
201
6
Lege
nd
Exi
stin
g T
raffi
c S
igna
l
Pro
pose
d T
raffi
c S
igna
l
2015
Rou
ndab
out
Pro
pose
d R
ound
abou
t
Fut
ure
draf
t pla
ns w
ill c
onfir
m a
fina
l rec
omm
ende
d de
sign
crit
eria
.F
utur
e dr
aft p
lans
will
con
firm
a fi
nal r
ecom
men
ded
desi
gn c
riter
ia.
Job
Num
ber
Rev
isio
n
Fig
ure
Dat
e
6705
Mill
cree
k D
rive,
Uni
t 1, M
issi
ssau
ga O
ntar
io L
5N 5
M4
T 1
416
213
7121
F 1
416
890
8499
E in
fo@
ghdc
anad
a.co
mW
ww
w.g
hd.c
omG
:\Leg
acy\
Ser
nasT
rans
Tec
h\P
roje
cts\
2013
\132
21 B
OY
NE
RD
NE
ED
S A
SS
ES
SM
EN
T\O
CT
OB
ER
201
5 U
PD
AT
E -
US
E!!!
!!!!!!
!!\13
221
Boy
ne F
igur
es (
July
201
6).d
wg
Cad
File
No:
23 N
ovem
ber
2016
- 3
:57
PM
Plo
t Dat
e:A
dam
Mild
enbe
rger
Plo
tted
by:
11A
Milt
on P
hase
3 L
ando
wne
rs G
roup
Boy
ne S
urve
yR
oad
Net
wor
k A
sses
smen
t
AM
Pea
k H
our
Tot
al 2
026
Wes
t Blo
ck T
raffi
c
28-2
1522
CLe
gend
Exi
stin
g T
raffi
c S
igna
l
Pro
pose
d T
raffi
c S
igna
l
2015
Rou
ndab
out
Pro
pose
d R
ound
abou
t
Fut
ure
draf
t pla
ns w
ill c
onfir
m a
fina
l rec
omm
ende
d de
sign
crit
eria
.F
utur
e dr
aft p
lans
will
con
firm
a fi
nal r
ecom
men
ded
desi
gn c
riter
ia.
Sep
t 201
7
Job
Num
ber
Rev
isio
n
Fig
ure
Dat
e
6705
Mill
cree
k D
rive,
Uni
t 1, M
issi
ssau
ga O
ntar
io L
5N 5
M4
T 1
416
213
7121
F 1
416
890
8499
E in
fo@
ghdc
anad
a.co
mW
ww
w.g
hd.c
om
G:\L
egac
y\S
erna
sTra
nsT
ech\
Pro
ject
s\20
13\1
3221
BO
YN
E R
D N
EE
DS
AS
SE
SS
ME
NT
\OC
TO
BE
R 2
015
UP
DA
TE
- U
SE
!!!!!!
!!!!!\
1322
1 B
oyne
Fig
ures
(Ju
ly 2
016)
.dw
gC
ad F
ile N
o:23
Nov
embe
r 20
16 -
4:2
8 P
MP
lot D
ate:
Ada
m M
ilden
berg
erP
lotte
d by
:
12A
Milt
on P
hase
3 L
ando
wne
rs G
roup
Boy
ne S
urve
yR
oad
Net
wor
k A
sses
smen
t
PM
Pea
k H
our
Tot
al 2
026
Wes
t Blo
ck T
raffi
c
28-2
1522
CLe
gend
Exi
stin
g T
raffi
c S
igna
l
Pro
pose
d T
raffi
c S
igna
l
2015
Rou
ndab
out
Pro
pose
d R
ound
abou
t
Fut
ure
draf
t pla
ns w
ill c
onfir
m a
fina
l rec
omm
ende
d de
sign
crit
eria
.F
utur
e dr
aft p
lans
will
con
firm
a fi
nal r
ecom
men
ded
desi
gn c
riter
ia.
Sep
t 201
7
Zone 4 – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 361.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 66 154 220 220 452
Gross Rate 0.183 0.426 0.609
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 4 8 12
New 62 146 208
Rate 0.172 0.404 0.576
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
62 OK
OUT Check
146 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
29 80% 67 0 100% 0 3 100% 7
0% R T L 20% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 23 6 0 0 0 0 3 0 100% 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 9 Wbd
0% T 0 0 T T 0 0 T T 17 0 T
0 Ebd 0 R 0 0 L 6 Ebd 6 R 6 0 L 17 Ebd 17 R 0 9 L 21 Ebd
OK 0% 0 67 0 0 0 17 0 7 4
L T R L T R L T R
23 67 6 17 12 11
Sbd Nbd Sbd Nbd Sbd Nbd
23 67 6 17 12 11
R T L 37 R T L 50 R T L 51OK 0 0 23 0 6 0 12 0 0
0 Wbd 0 L 0 67 R 68 Wbd 68 L 0 0 R 12 Wbd 12 L 11 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 1 L 24 Ebd 24 R 24 12 L 11 Ebd 11 R 0 0 L 0 Ebd
OK 0 0 1 68 17 11 0 0 0
L T R L T R L T R
1 1 42 96 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
1 1 50 20 0 0
R T L 38 R T L 52 R T 53OK 0 1 0 6 44 0 0 0
0 Wbd 0 L 0 0 R 6 Wbd 6 L 3 0 R 0 Wbd 0 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 6 L 3 Ebd 3 R 0 0 L 0 Ebd 0 R 0 0 Ebd
OK 0 1 3 0 17 0 0 0
L T R L T R L T
7 4 20% T 44 17 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
7 4
R T L 70OK 0 7 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 4 0
L T R
7 4
Sbd Nbd Sbd Nbd Sbd Nbd
7 4 44 17 0 0
R T L 1 R T L 25 R T L 26OK 60% 4 3 0 4 0 40 0 0 0
7 Wbd 7 L 2 0 R 4 Wbd 4 L 1 16 R 16 Wbd 16 L 0 0 R 16 Wbd 16
40% T 1 3 T T 0 0 T T 40 16 T
3 Ebd 3 R 0 1 L 1 Ebd 1 R 0 0 L 40 Ebd 40 R 0 0 L 40 Ebd 40
OK 0 2 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
4 80% 2 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Savoline Blvd
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H'
29 67 0 0 3 7
SITE OK OK OK OK OK OK
LSL
BLOCK 4
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
OK OK OK OK OK OK
Zone 5A – AM
AM Land Use Elementary School
Students (ITE Avg) 630.000
Land Use Code 520 AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn ln(T) = 1.14Ln(X) - 1.86 ITE pg 935
IN 55% Avg.Rate 0.45
Out 45%
Pass by 0%
Internal 75%
Transit Reduction 0%
Source ITE IN OUT Total Avg Eqn
Gross 156 128 284 284 242
Gross Rate 0.248 0.203 0.451 100%
Pass By 0 0 0 284 242
Internal 107 107 214
Transit Reduction 0 0 0
New 49 21 70
Rate 0.078 0.033 0.111
Elementary School
IN Check
22 ERROR
OUT Check
24 ERROR
Sbd Nbd Sbd Nbd Sbd Nbd
0 40% 0 0 100% 0 0 100% 0
0% R T L 60% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 0 0 0 0 0 0 0 0 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
0% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0% 0 0 0 0 0 0 0 0 0
L T R L T R L T R
0 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 6 3 25% L 6 3
R T L 37 R T L 50 25% R 25% T R T L 51OK 0 0 0 0 0 6 75% L 50% R 6 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 3 R 11 Wbd 25 L 3 0 R 6 Wbd
T 0 0 T T 0 0 T T 3 6 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 8 L 25 Ebd 11 R 5 0 L 3 Ebd
OK 0 0 0 0 0 18 50% 50% 12 0 0
L T R L T R L T R
0 0 STAY 25% 2 8 18 5 12 50% STAY 2.6
Sbd Nbd 4.6 50% T Sbd Nbd Sbd Nbd 50% T 6.1
0 0 25% L 6 14 in 49 out 21 3 6
R T L 38 R T L 52 R T 53OK 0 0 0 0 4 2 0 3
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 5 R 5 Wbd 5 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 2 Ebd 2 R 2 0 Ebd
OK 0 0 0 0 9 0 5 6
L T R L T R L T
0 0 20% T 4 9 CHECK 5 11
Sbd Nbd 80% R Sbd Nbd in 49 out 21 Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 0 0 0 0
R T L 1 R T L 25 R T L 26OK 50% 0 0 0 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0
50% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0
OK 0 0 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
0 80% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Savoline Blvd
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H'
0 0 0 0 0 0
SITE OK OK OK OK OK OK
LSL
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 5A NORTHSIDE
SCHOOL
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
OK OK OK OK OK OK
Zone 5B – AM
AM Land Use Elementary School
Students (ITE Avg) 630.000
Land Use Code 520 AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn ln(T) = 1.14Ln(X) - 1.86 ITE pg 935
IN 55% Avg.Rate 0.45
Out 45%
Pass by 0%
Internal 75%
Transit Reduction 0%
Source ITE IN OUT Total Avg Eqn
Gross 156 128 284 284 242
Gross Rate 0.248 0.203 0.451 100%
Pass By 0 0 0 284 242
Internal 107 107 214
Transit Reduction 0 0 0
New 49 21 70
Rate 0.078 0.033 0.111
Elementary School
IN Check
11 ERROR
OUT Check
15 ERROR
Sbd Nbd Sbd Nbd Sbd Nbd
0 40% 0 0 100% 0 0 100% 0
0% R T L 60% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 0 0 0 0 0 0 0 0 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
0% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0% 0 0 0 0 0 0 0 0 0
L T R L T R L T R
0 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 3 1 50% L 6 3
R T L 37 R T L 50 50% T R T L 51 50% T
OK 0 0 0 0 3 0 0% R 2 5 0 50% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 3 Wbd 3 L 1 0 R 6 Wbd
T 0 0 T T 0 0 T T 1 2 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 3 L 1 Ebd 1 R 0 5 L 3 Ebd
OK 0 0 0 0 1 1 0 2 2
L T R IN OUT L T R L T R OUT IN
0 0 6.1 STAY 2.6 50% 6 3 9 4 50% STAY 3.9 9
Sbd Nbd 25% T Sbd Nbd Sbd Nbd 50% T
0 0 25% R 12 5 in 49 out 21 18 8
R T L 38 R T L 52 R T 53OK 0 0 0 0 0 12 50% 50% 18 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 5 R 11 Wbd 25 L 8 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 5 L 25 Ebd 11 R 3 0 Ebd
OK 0 0 0 0 0 12 50% L 75% L 6 0
L T R L T R 50% R 25% R L T
0 0 20% T 5 12 CHECK 3 6
Sbd Nbd 80% R Sbd Nbd in 49 out 21 Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 0 0 0 0
R T L 1 R T L 25 R T L 26OK 50% 0 0 0 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0
50% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0
OK 0 0 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
0 80% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
0 0 0 0 0 0
SITE OK OK OK OK OK OK
LSL
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 5B SOUTHSIDE
SCHOOL
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
OK OK OK OK OK OK
Zone 5C – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 26.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 5 11 16 16 60
Gross Rate 0.192 0.423 0.615
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 0 1 1
New 5 10 15
Rate 0.192 0.385 0.577
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
5 OK
OUT Check
10 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
3 80% 3 0 100% 0 0 100% 1
0% R T L 20% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 2 1 0 0 0 0 0 0 100% 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 1 Wbd
0% T 0 0 T T 0 0 T T 2 0 T
0 Ebd 0 R 0 0 L 1 Ebd 1 R 1 0 L 2 Ebd 2 R 0 1 L 3 Ebd
OK 0% 0 3 0 0 0 2 0 1 1
L T R L T R L T R
2 3 1 2 1 2
Sbd Nbd Sbd Nbd Sbd Nbd
2 3 1 2 1 2
R T L 37 R T L 50 R T L 51OK 0 0 2 0 1 0 1 0 0
0 Wbd 0 L 0 3 R 3 Wbd 3 L 0 0 R 1 Wbd 1 L 2 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 2 Ebd 2 R 2 1 L 2 Ebd 2 R 0 0 L 0 Ebd
OK 0 0 0 3 2 2 0 0 0
L T R L T R L T R
0 0 4 7 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 3 1 0 0
R T L 38 R T L 52 R T 53OK 0 0 0 0 3 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 Ebd
OK 0 0 0 0 1 0 0 0
L T R L T R L T
0 0 20% T 3 1 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 3 1 0 0
R T L 1 R T L 25 R T L 26OK 0% 0 0 0 1 0 2 0 0 0
1 Wbd 1 L 0 0 R 1 Wbd 1 L 0 1 R 1 Wbd 1 L 0 0 R 1 Wbd 1
100% T 0 1 T T 0 0 T T 2 1 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 2 Ebd 2 R 0 0 L 2 Ebd 2
OK 0 0 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
0 80% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
3 3 0 0 0 1
O1 D1 O28 D28 O27 D27
SITE OK OK OK OK OK OK
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 4
LSL
CN
R
Col
lect
or 'B
'
Col
lect
or 'B
'
Brit
anni
aM
EV
Str
eet '
D'
OK OK OK OK OK OK
Zone 6 – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 335.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 61 143 204 204 427
Gross Rate 0.182 0.427 0.609
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 3 8 11
New 58 135 193
Rate 0.173 0.403 0.576
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
58 OK
OUT Check
135 OK
Sbd Nbd Sbd Nbd Sbd Nbd
25 60% 60 0 100% 0 3 100% 7
0% R T L 40% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 15 10 0 0 0 0 3 0 20% R
0 Wbd 0 L 0 24 R 24 Wbd 24 L 0 0 R 24 Wbd 24 L 0 0 R 9 Wbd
0% T 0 0 T T 10 24 T T 0 0 T
0 Ebd 0 R 0 0 L 10 Ebd 10 R 0 0 L 10 Ebd 10 R 10 9 L 21 Ebd
OK 0% 0 36 0 0 0 0 24 7 21
L T R L T R L T R
15 36 0 0 22 52
Sbd Nbd Sbd Nbd Sbd Nbd
15 36 0 0 22 52
R T L 37 R T L 50 R T L 51OK 0 0 15 0 0 0 0 22 0
0 Wbd 0 L 0 36 R 37 Wbd 37 L 0 0 R 37 Wbd 37 L 0 0 R 0 Wbd
T 0 0 T T 15 37 T T 0 0 T
0 Ebd 0 R 0 1 L 15 Ebd 15 R 0 0 L 15 Ebd 15 R 15 0 L 0 Ebd
OK 0 0 0 0 0 0 37 52 0
L T R L T R L T R
1 0 0 0 37 89
Sbd Nbd Sbd Nbd Sbd Nbd
1 0 0 0 46 21
R T L 38 R T L 52 R T 53OK 0 1 0 0 0 0 2 44
0 Wbd 0 L 0 0 R 2 Wbd 2 L 0 0 R 2 Wbd 2 L 1 0 Wbd
T 0 0 T T 1 2 T
0 Ebd 0 R 0 2 L 1 Ebd 1 R 0 0 L 1 Ebd 1 R 0 0 Ebd
OK 0 0 1 0 0 0 0 20
L T R L T R L T
3 1 20% T 0 0 44 20
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
3 1
R T L 70OK 0 3 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 1 0
L T R
3 1
Sbd Nbd Sbd Nbd Sbd Nbd
3 1 0 0 44 20
R T L 1 R T L 25 R T L 26OK 25% 2 1 0 0 0 0 8 0 36
7 Wbd 7 L 1 0 R 8 Wbd 8 L 0 0 R 8 Wbd 8 L 4 16 R 16 Wbd 16
75% T 2 5 T T 4 8 T T 0 0 T
3 Ebd 3 R 0 3 L 4 Ebd 4 R 0 0 L 4 Ebd 4 R 0 0 L 36 Ebd 36
OK 0 0 2 0 0 0 0 0 0
0% L T R 80% L T R L T R
4 20% 2 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
25 60 0 0 3 7
SITE OK OK OK OK OK OK
LSL
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 6 RESIDENTIAL
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
OK OK OK OK OK OK
Zone 7A – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 248.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 45 106 151 151 339
Gross Rate 0.181 0.428 0.609
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 2 6 8
New 43 100 143
Rate 0.173 0.404 0.577
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
43 OK
OUT Check
100 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
20 90% 45 0 100% 0 2 100% 5
0% R T L 10% 7 0% R T L 0% 13 100% 10% T 0% R T L 0% 14OK 0% 0 18 2 0 0 0 90% R 0 2 0
0 Wbd 0 L 0 0 R 6 Wbd 6 L 0 0 R 6 Wbd 6 L 0 0 R 6 Wbd
0% T 0 0 T T 2 6 T T 15 6 T
0 Ebd 0 R 0 6 L 4 Ebd 4 R 2 0 L 15 Ebd 15 R 0 0 L 15 Ebd
OK 0% 0 45 2 0 0 14 0 5 0
L T R L T R L T R
24 47 2 14 2 5
Sbd Nbd Sbd Nbd Sbd Nbd
24 47 2 14 2 5
R T L 37 R T L 50 R T L 51OK 0 24 0 0 2 0 0 2 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 47 0 0 14 0 0 5 0
L T R L T R L T R
24 47 2 14 2 5
Sbd Nbd Sbd Nbd Sbd Nbd
24 47 2 14 2 5
R T L 38 R T L 52 R T 53OK 0 0 24 0 2 0 2 0
0 Wbd 0 L 0 47 R 47 Wbd 47 L 0 0 R 2 Wbd 2 L 5 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 24 Ebd 24 R 24 2 L 5 Ebd 5 R 0 0 Ebd
OK 0 0 0 47 14 5 0 0
L T R L T R L T
0 0 20% T 28 65 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0
T 0
0 Ebd 0 R 0
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 35 15 0 0
R T L 1 R T L 25 R T L 26OK 0% 0 0 0 8 0 27 0 0 0
5 Wbd 5 L 0 0 R 8 Wbd 8 L 3 12 R 12 Wbd 12 L 0 0 R 12 Wbd 12
100% T 2 5 T T 0 0 T T 27 12 T
2 Ebd 2 R 0 3 L 3 Ebd 3 R 0 0 L 27 Ebd 27 R 0 0 L 27 Ebd 27
OK 0 0 1 0 0 0 0 0 0
0% L T R 100% L T R L T R
3 0% 1 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
20 45 0 0 2 5
SITE OK OK OK OK OK OK
LSL
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 7A RESIDENTIAL
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
OK OK OK OK OK OK
Zone 7B – AM
Condominium/Townhouse
AM Land Use Residential Condominium/Townhouse
Dwelling Units 125.000
Land Use Code 230 AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn ln(T) = 0.80Ln(X) + 0.26 ITE pg 389
IN 17% Avg.Rate 0.44
Out 83%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 9 46 55 55 62
Gross Rate 0.072 0.368 0.440
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 1 2 3
New 8 44 52
Rate 0.064 0.352 0.416
IN Check
8 OK
OUT Check
44 OK
Sbd Nbd Sbd Nbd Sbd Nbd
3 100% 20 0 100% 0 0 100% 0
0% R T L 0% 7 0% R T L 0% 13 100% T 0% R T L 0% 14OK 0% 0 3 0 0 0 0 0% R 0 0 0
0 Wbd 0 L 0 0 R 2 Wbd 2 L 0 0 R 2 Wbd 2 L 0 0 R 2 Wbd
0% T 0 0 T T 7 2 T T 7 2 T
0 Ebd 0 R 0 2 L 7 Ebd 7 R 0 0 L 7 Ebd 7 R 0 0 L 7 Ebd
OK 0% 0 20 7 0 0 0 0 0 0
L T R L T R L T R
5 27 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
5 27 0 0 0 0
R T L 37 R T L 50 R T L 51OK 0 5 0 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 27 0 0 0 0 0 0 0
L T R L T R L T R
5 27 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
100% T 5 27 0 0 0 0
0% L R T L 38 R T L 52 R T 53OK 0 5 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 Ebd
OK 0 27 0 0 0 0 0 0
L T R L T R L T
5 27 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
5 27
R T L 70OK 0 5 0
0 Wbd 0 L 0 0
T 0 0
0 Ebd 0 R 0 0
OK 0 27 0
L T R
5 27
Sbd Nbd Sbd Nbd Sbd Nbd
17 3 0 0 0 0
R T L 1 R T L 25 100% T R T L 26OK 100% 2 1 14 0 0 0 0% R 0 0 0
2 Wbd 2 L 0 3 R 3 Wbd 3 L 0 0 R 3 Wbd 3 L 0 0 R 3 Wbd 3
0% T 0 0 T T 14 3 T T 14 3 T
0 Ebd 0 R 0 0 L 14 Ebd 14 R 0 0 L 14 Ebd 14 R 0 0 L 14 Ebd 14
OK 0 0 0 0 0 0 0 0 0
0% L T R 0% L T R L T R
1 100% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
3 20 0 0 0 0
SITE OK OK OK OK OK
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK
CN
R
Col
lect
or 'B
'
Col
lect
or 'B
'
Brit
anni
a
BLOCK 7B RESIDENTIAL
HD
ME
V S
tree
t 'D
'
OK OK OK OK OK OK
Zone 7C – AM
Shopping Centre
AM Land Use Shopping Centre
1,000 sq.ft. GLA 16.824
Land Use Code 820 AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn ln(T) = 0.59Ln(X) + 2.32 ITE pg 1501
IN 61% Avg.Rate 1
Out 39%
Pass by 0%
Internal 0%
Transit Reduction 10.0%
Source ITE IN OUT Total Avg Eqn
Gross 33 21 54 17 54
Gross Rate 1.961 1.249 3.210
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 3 2 5
New 30 19 49
Rate 1.783 1.130 2.913
IN Check
30 OK
OUT Check
19 OK
Sbd Nbd Sbd Nbd Sbd Nbd
0 80% 0 0 100% 0 8 0% 5
0% R T L 20% 7 0% R T L 0% 13 100% R T L 0% 14OK 0% 0 0 0 0 0 0 0 8 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
0% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0% 0 0 0 0 0 0 0 5 0
L T R L T R 0% L L T R 0% L
0 0 0 0 0% T 8 5 100% T
Sbd Nbd Sbd Nbd 0% R Sbd Nbd 0% R
0 0 2 1 8 5
R T L 37 R T L 50 R T L 51OK 0 0 0 0 2 0 0 8 0
0 Wbd 0 L 0 0 R 0 Wbd 2 L 0 0 R 3 Wbd 2 L 0 0 R 4 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 3 R 3 3 L 2 Ebd 4 R 4 4 L 2 Ebd
OK 0 0 0 2 1 2 2 5 2
L T R L T R 40% L L T R 25% L
0 0 8 5 20% T 15 10 50% T
Sbd Nbd Sbd Nbd 40% R Sbd Nbd 25% R
0 0 8 5 15 10
R T L 38 R T L 52 R T 53OK 0 0 0 8 0 0 8 8
0 Wbd 0 L 0 0 R 15 Wbd 15 L 5 0 R 8 Wbd 8 L 5 0 Wbd
T 0 0 T T 5 8 T
0 Ebd 0 R 0 15 L 10 Ebd 10 R 0 0 L 5 Ebd 5 R 0 0 Ebd
OK 0 0 10 0 0 0 0 5
L T R L T R L T
15 10 0 0 8 5
Sbd Nbd Sbd Nbd Sbd Nbd
15 10
R T 70OK 0 15
0 Wbd 0 L 0
0 Ebd 0 R 0
OK 0 10 IN OUT
L T 30 19
15 10
Sbd Nbd even dist. 25% Sbd Nbd Sbd Nbd
10 15 8 5 8 5
R T L 1 R T L 25 R T L 26OK 100% 0 0 10 8 0 0 8 0 0
0 Wbd 0 L 0 15 R 15 Wbd 15 L 5 0 R 8 Wbd 8 L 5 0 R 0 Wbd 0
0% T 0 0 T T 5 8 T T 0 0 T
0 Ebd 0 R 0 0 L 10 Ebd 10 R 0 0 L 5 Ebd 5 R 0 0 L 0 Ebd 0
OK 0 0 0 0 0 0 0 0 0
0% L T R 0% L T R L T R
0 100% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
0 0 0 0 0 0
SITE OK OK OK OK ERROR ERROR
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
BLOCK 7C COMMERCIA
L
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
Brit
anni
aM
EV
Str
eet '
D'
OK OK OK OK OK OK
Zone 8 – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 154.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 28 66 94 94 235
Gross Rate 0.182 0.428 0.610
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 2 3 5
New 26 63 89
Rate 0.169 0.409 0.578
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
26 OK
OUT Check
63 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
11 85% 28 0 100% 0 1 100% 2
0% R T L 15% 7 0% R T L 0% 13 100% 10% T 0% R T L 0% 14OK 0% 0 9 2 0 0 0 90% R 0 1 0
0 Wbd 0 L 0 0 R 3 Wbd 3 L 0 0 R 3 Wbd 3 L 0 0 R 3 Wbd
0% T 0 0 T T 1 3 T T 9 3 T
0 Ebd 0 R 0 3 L 3 Ebd 3 R 2 0 L 9 Ebd 9 R 0 0 L 9 Ebd
OK 0% 0 28 1 0 0 8 0 2 0
L T R L T R L T R
12 29 2 8 1 2
Sbd Nbd Sbd Nbd Sbd Nbd
12 29 2 8 1 2
R T L 37 R T L 50 R T L 51OK 0 12 0 0 2 0 0 1 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 29 0 0 8 0 0 2 0
L T R L T R L T R
12 29 2 8 1 2
Sbd Nbd Sbd Nbd Sbd Nbd
12 29 2 8 1 2
R T L 38 R T L 52 R T 53OK 0 0 12 0 2 0 1 0
0 Wbd 0 L 0 29 R 30 Wbd 30 L 0 0 R 1 Wbd 1 L 2 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 1 L 12 Ebd 12 R 12 1 L 2 Ebd 2 R 0 0 Ebd
OK 0 0 0 30 8 2 0 0
L T R L T R L T
1 0 20% T 15 40 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
1 0
R T L 70OK 0 1 0
0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd
OK 0 0 0
L T R
1 0
Sbd Nbd Sbd Nbd Sbd Nbd
1 0 23 11 0 0
R T L 1 R T L 25 R T L 26OK 25% 1 0 0 4 0 19 0 0 0
3 Wbd 3 L 0 0 R 4 Wbd 4 L 2 9 R 9 Wbd 9 L 0 0 R 9 Wbd
75% T 1 2 T T 0 0 T T 19 9 T
1 Ebd 1 R 0 2 L 2 Ebd 2 R 0 0 L 19 Ebd 19 R 0 0 L 19 Ebd
OK 0 0 1 0 0 0 0 0 0
0% L T R 80% L T R L T R
2 20% 1 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
11 28 0 0 1 2
SITE OK OK OK OK OK
Col
lect
or 'A
'LS
L
OK
CN
R
Col
lect
or 'B
'B
ritan
nia
BLOCK 8 RESIDENTIAL
ME
V S
tree
t 'D
'
OK OK OK OK OK OK
Zone 9 – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 84.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 15 36 51 51 147
Gross Rate 0.179 0.428 0.607
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 1 2 3
New 14 34 48
Rate 0.167 0.404 0.571
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
14 OK
OUT Check
34 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
7 85% 15 0 100% 0 1 100% 2
0% R T L 15% 7 0% R T L 0% 13 0% R T L 0% 14 0% T
OK 0% 0 6 1 0 0 0 0 1 0 ### L
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 2 Wbd
0% T 0 0 T T 1 0 T T 0 0 T
0 Ebd 0 R 0 0 L 1 Ebd 1 R 0 0 0 1 Ebd 1 R 1 2 L 5 Ebd
OK 0% 0 15 0 70% T 0 0 0 0 2 5
L T R 30% R L T R L T R
6 15 0 0 4 7
Sbd Nbd Sbd Nbd Sbd Nbd
6 15 0 0 4 7
R T L 37 R T L 50 R T L 51OK 0 6 0 0 0 0 0 4 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 15 0 0 0 0 0 7 0
L T R L T R L T R
6 15 0 0 4 7
Sbd Nbd Sbd Nbd Sbd Nbd
6 15 0 0 4 7
R T L 38 R T L 52 R T 53OK 0 0 6 0 0 0 0 4
0 Wbd 0 L 0 15 R 15 Wbd 15 L 0 0 R 15 Wbd 15 L 0 0 Wbd
T 0 0 T T 6 15 T
0 Ebd 0 R 0 0 L 6 Ebd 6 R 0 0 L 6 Ebd 6 R 6 0 Ebd
OK 0 0 0 0 0 0 15 7
L T R L T R L T
0 0 20% T 0 0 10 22
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 0 0 12 4
R T L 1 R T L 25 R T L 26OK 0% 0 0 0 0 0 0 3 0 9
2 Wbd 2 L 0 0 R 3 Wbd 3 L 0 0 R 3 Wbd 3 L 1 3 R 3 Wbd 3
100% T 1 2 T T 1 3 T T 0 0 T
1 Ebd 1 R 0 1 L 1 Ebd 1 R 0 0 L 1 Ebd 1 R 0 0 L 9 Ebd 9
OK 0 0 0 0 0 0 0 0 0
0% L T R 80% L T R L T R
1 20% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
7 15 0 0 1 2
SITE OK OK OK OK OK
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK
CN
R
Col
lect
or 'B
'
Col
lect
or 'B
'
Brit
anni
a
BLOCK 9 RESIDENTIAL
ME
V S
tree
t 'D
'
OK OK OK OK OK OK
Zone 10 – AM
AM Land Use Single-Family Detached Housing
Dwelling Units 532.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code AM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 30% Avg.Rate 0.609
Out 70%
Pass by 0%
Internal 0%
Transit Reduction 5.3%
Source ITE IN OUT Total Avg Eqn
Gross 97 227 324 324 610
Gross Rate 0.182 0.427 0.609
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 5 12 17
New 92 215 307
Rate 0.173 0.404 0.577
Single-Family Detached Housing - BRISTOL TRIP GEN
IN Check
92 OK
OUT Check
215 OK
Sbd Nbd Sbd Nbd Sbd Nbd
40 70% 97 0 100% 0 5 100% 11
0% R T L 30% 7 0% R T L 0% 13 0% R T L 0% 14OK 0% 0 28 12 0 0 0 0 5 0
0 Wbd 0 L 0 29 R 29 Wbd 29 L 0 0 R 29 Wbd 29 L 0 0 R
0% T 0 0 T T 11 29 T T 0 0 T
0 Ebd 0 R 0 0 L 12 Ebd 12 R 1 0 0 11 Ebd 11 R 11 13 L
OK 0% 0 68 0 100% 90% T 0 0 0 29 11 29
L T R 10% R L T R L T R
28 68 1 0 29 69
50% L Sbd Nbd 50% L Sbd Nbd Sbd Nbd
50% T 28 68 50% T 1 0 90% T 29 69
R T L 37 R T L 50 10% L R T L 51OK 0 14 14 0 1 1 0 26 3
0 Wbd 0 L 0 34 R 35 Wbd 35 L 0 0 R 35 Wbd 35 L 0 7 R
T 0 0 T T 15 35 T T 4 9 T
0 Ebd 0 R 0 1 L 15 Ebd 15 R 0 0 L 15 Ebd 15 R 11 0 L
OK 0 34 1 0 0 0 25% T 26 62 0
L T R L T R 75% R L T R
15 35 1 0 37 89
Sbd Nbd Sbd Nbd Sbd Nbd
15 35 1 0 STAY 60% 33 27
R T L 38 R T L 52 40% T R T 53OK 0 1 14 0 0 1 18 15
0 Wbd 0 L 0 34 R 37 Wbd 37 L 0 0 R 37 Wbd 37 L 8
T 0 0 T T 15 37 T
0 Ebd 0 R 0 3 L 15 Ebd 15 R 0 0 L 16 Ebd 16 R 8
OK 0 1 1 0 0 0 50% L 18 19
L T R L T R 50% R L T
4 2 30% T 0 0 23 38
Sbd Nbd 70% R Sbd Nbd Sbd Nbd
4 2
R T L 70OK 0 4 0
0 Wbd 0 L 0 0 R 0 Wbd 60% T
T 0 0 T R
0 Ebd 0 R 0 0 L 0 Ebd 40% STAY
OK 0 2 0
L T R
4 2
Sbd Nbd Sbd Nbd Sbd Nbd
4 2 0 0 74 32
R T L 1 R T L 25 R T L 26OK 25% 3 1 0 0 0 0 13 0 61
11 Wbd 11 L 1 0 R 13 Wbd 13 L 0 0 R 13 Wbd 13 L 6 26 R
75% T 4 8 T T 6 13 T T 0 0 T
5 Ebd 5 R 0 5 L 6 Ebd 6 R 0 0 L 6 Ebd 6 R 0 0 L
OK 0 1 2 0 0 0 0 0 0
0% L T R 80% L T R L T R
6 20% 3 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
UPDATE LINK TO EACH BLOCK 1 2 3
Tremaine Road Collector Road 'H' Savoline Blvd
O1 D1 O28 D28 O27 D27
40 97 0 0 5 11
SITE OK OK OK OK OK
Col
lect
or 'A
'LS
L
OK
ME
V S
tree
t 'D
'C
olle
ctor
'B'
Brit
anni
a
OK OK OK OK OK OK
Zone 4 – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 361.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 169 117 286 286 452
Gross Rate 0.468 0.324 0.792
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 6 4 10
New 163 113 276
Rate 0.452 0.313 0.765
IN Check
163 OK
OUT Check
113 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
74 80% 51 0 100% 0 8 100% 6
0% R T L 20% 7 0% R T L 0% 13 0% R T L 0% 14 100% 80% T
OK 0% 0 59 15 0 0 0 0 8 0 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 24 Wbd
0% T 0 0 T T 0 0 T T 14 0 T
0 Ebd 0 R 0 0 L 15 Ebd 15 R 15 0 L 14 Ebd 14 R 0 24 L 17 Ebd
OK 0% 0 51 0 0 0 14 0 6 3
L T R L T R L T R
59 51 15 14 32 9
Sbd Nbd Sbd Nbd Sbd Nbd
59 51 15 14 32 9
R T L 37 R T L 50 R T L 51OK 0 0 59 0 15 0 32 0 0
0 Wbd 0 L 0 51 R 52 Wbd 52 L 0 0 R 32 Wbd 32 L 9 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 1 L 61 Ebd 61 R 61 32 L 9 Ebd 9 R 0 0 L 0 Ebd
OK 0 0 2 52 14 9 0 0 0
L T R L T R L T R
1 2 108 75 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
1 2 38 55 0 0
R T L 38 R T L 52 R T 53OK 0 1 0 5 33 0 0 0
0 Wbd 0 L 0 0 R 5 Wbd 5 L 7 0 R 0 Wbd 0 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 5 L 7 Ebd 7 R 0 0 L 0 Ebd 0 R 0 0 Ebd
OK 0 2 7 0 48 0 0 0
L T R L T R L T
6 9 20% T 33 48 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
6 9
R T L 70OK 0 6 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 9 0
L T R
6 9
Sbd Nbd Sbd Nbd Sbd Nbd
6 9 33 48 0 0
R T L 1 R T L 25 R T L 26OK 60% 4 2 0 3 0 30 0 0 0
6 Wbd 6 L 5 0 R 3 Wbd 3 L 4 44 R 44 Wbd 44 L 0 0 R 44 Wbd 44
40% T 3 2 T T 0 0 T T 30 44 T
8 Ebd 8 R 0 1 L 4 Ebd 4 R 0 0 L 30 Ebd 30 R 0 0 L 30 Ebd 30
OK 0 4 1 0 0 0 0 0 0
0% L T R 20% L T R L T R
3 80% 5 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 4
LSL
OK OKSITE OK OK OK OK
74 51 0 0 8 6
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 5A – PM
PM Land Use Elementary School
Students (ITE Avg) 630.000
Land Use Code 520 PM Peak of Adjacent Street Traffic, 1Hr 4-6
Eqn NOT GIVEN ITE pg 936
IN 49% Avg.Rate 0.15
Out 51%
Pass by 0%
Internal 75%
Transit Reduction 0.0%
Source ITE IN OUT Total Avg Eqn
Gross 47 48 95 95 242
Gross Rate 0.075 0.076 0.151 100%
Pass By 0 0 0 95 242
Internal 36 36 72
Transit Reduction 0 0 0
New 11 12 23
Rate 0.017 0.020 0.037
Elementary School
IN Check
8 ERROR
OUT Check
8 ERROR
Sbd Nbd Sbd Nbd Sbd Nbd
0 40% 0 0 100% 0 0 100% 0
0% R T L 60% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 0 0 0 0 0 0 0 0 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
0% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0% 0 0 0 0 0 0 0 0 0
L T R L T R L T R
0 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 1 2 25% L 1 2
R T L 37 R T L 50 25% R 25% T R T L 51OK 0 0 0 0 0 1 75% L 50% R 1 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 2 R 6 Wbd 6 L 2 0 R 1 Wbd
T 0 0 T T 0 0 T T 2 1 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 5 L 6 Ebd 6 R 3 0 L 2 Ebd
OK 0 0 0 0 0 4 50% 50% 3 0 0
L T R L T R L T R
0 0 STAY 25% 1.1 5 4 3 3 50% STAY 1.5
Sbd Nbd 1 50% T Sbd Nbd Sbd Nbd 50% T 1.4
0 0 25% L 3 3 in 11 out 12 2 1
R T L 38 R T L 52 R T 53OK 0 0 0 0 2 1 0 2
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 1 R 1 Wbd 1 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 1 Ebd 1 R 1 0 Ebd
OK 0 0 0 0 2 0 1 1
L T R L T R L T
0 0 20% T 2 2 CHECK 3 2
Sbd Nbd 80% R Sbd Nbd in 11 out 12 Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 0 0 0 0
R T L 1 R T L 25 R T L 26OK 50% 0 0 0 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0
50% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0
OK 0 0 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
0 80% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 5A NORTHSIDE
SCHOOL
LSL
OKSITE OK OK OK OK OK
0 0 0 0 0 0
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 5B – PM
PM Land Use Elementary School
Students (ITE Avg) 630.000
Land Use Code 520 PM Peak of Adjacent Street Traffic, 1Hr 4-6
Eqn NOT GIVEN ITE pg 936
IN 49% Avg.Rate 0.15
Out 51%
Pass by 0%
Internal 75%
Transit Reduction 0.0%
Source ITE IN OUT Total Avg Eqn
Gross 47 48 95 95 242
Gross Rate 0.075 0.076 0.151 100%
Pass By 0 0 0 95 242
Internal 36 36 72
Transit Reduction 0 0 0
New 11 12 23
Rate 0.017 0.020 0.037
Elementary School
IN Check
4 ERROR
OUT Check
4 ERROR
Sbd Nbd Sbd Nbd Sbd Nbd
0 40% 0 0 100% 0 0 100% 0
0% R T L 60% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 0 0 0 0 0 0 0 0 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
0% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0% 0 0 0 0 0 0 0 0 0
L T R L T R L T R
0 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 1 1 50% L 1 2
R T L 37 R T L 50 50% T R T L 51 50% T
OK 0 0 0 0 1 0 0% R 0 1 0 50% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 1 Wbd 1 L 0 0 R 1 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 1 L 1 Ebd 1 R 0 1 L 2 Ebd
OK 0 0 0 0 1 1 0 1 1
L T R IN OUT L T R L T R OUT IN
0 0 1.4 STAY 1.5 50% 1 2 2 2 50% STAY 2.3 2
Sbd Nbd 25% T Sbd Nbd Sbd Nbd 50% T
0 0 25% R 3 3 in 11 out 12 4 5
R T L 38 R T L 52 R T 53OK 0 0 0 0 0 3 50% 50% 4 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 3 R 6 Wbd 6 L 5 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 3 L 6 Ebd 6 R 2 0 Ebd
OK 0 0 0 0 0 3 50% L 75% L 1 0
L T R L T R 50% R 25% R L T
0 0 20% T 3 3 CHECK 2 1
Sbd Nbd 80% R Sbd Nbd in 11 out 12 Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 0 0 0 0
R T L 1 R T L 25 R T L 26OK 50% 0 0 0 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0
50% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0
OK 0 0 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
0 80% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 5B SOUTHSIDE
SCHOOL
LSL
OKSITE OK OK OK OK OK
0 0 0 0 0 0
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 5C – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 26.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 12 9 21 21 60
Gross Rate 0.462 0.346 0.808
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 1 0 1
New 11 9 20
Rate 0.423 0.346 0.769
IN Check
11 OK
OUT Check
8 ERROR
Sbd 100% Nbd Sbd Nbd Sbd Nbd
3 80% 5 0 100% 0 1 100% 0
0% R T L 20% 7 0% R T L 0% 13 0% R T L 0% 14 100% 80% T
OK 0% 0 2 1 0 0 0 0 1 0 20% R
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 3 Wbd
0% T 0 0 T T 0 0 T T 1 0 T
0 Ebd 0 R 0 0 L 1 Ebd 1 R 1 0 L 1 Ebd 1 R 0 3 L 1 Ebd
OK 0% 0 5 0 0 0 1 0 0 0
L T R L T R L T R
2 5 1 1 4 0
Sbd Nbd Sbd Nbd Sbd Nbd
2 5 1 1 4 0
R T L 37 R T L 50 R T L 51OK 0 0 2 0 1 0 4 0 0
0 Wbd 0 L 0 5 R 5 Wbd 5 L 0 0 R 4 Wbd 4 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 2 Ebd 2 R 2 4 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 0 0 5 1 0 0 0 0
L T R L T R L T R
0 0 7 6 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 2 4 0 0
R T L 38 R T L 52 R T 53OK 0 0 0 0 2 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 Ebd
OK 0 0 0 0 4 0 0 0
L T R L T R L T
0 0 20% T 2 4 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 2 4 0 0
R T L 1 R T L 25 R T L 26OK 0% 0 0 0 0 0 2 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 1 3 R 3 Wbd 3 L 0 0 R 3 Wbd 3
100% T 1 0 T T 0 0 T T 2 3 T
1 Ebd 1 R 0 0 L 1 Ebd 1 R 0 0 L 2 Ebd 2 R 0 0 L 2 Ebd 2
OK 0 0 0 0 0 0 0 0 0
0% L T R 20% L T R L T R
0 80% 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 4
LSL
OK OKSITE OK OK OK OK
3 5 0 0 1 0
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 6 – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 335.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 157 109 266 266 427
Gross Rate 0.469 0.325 0.794
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 5 4 9
New 152 105 257
Rate 0.454 0.313 0.767
IN Check
152 OK
OUT Check
105 OK
Sbd Nbd Sbd Nbd Sbd Nbd
66 60% 48 0 100% 0 8 100% 5
0% R T L 40% 7 0% R T L 0% 13 0% R T L 0% 14 80% T
OK 0% 0 40 26 0 0 0 0 8 0 20% R
0 Wbd 0 L 0 19 R 19 Wbd 19 L 0 0 R 19 Wbd 19 L 0 0 R 24 Wbd
0% T 0 0 T T 26 19 T T 0 0 T
0 Ebd 0 R 0 0 L 26 Ebd 26 R 0 0 L 26 Ebd 26 R 26 24 L 16 Ebd
OK 0% 0 29 0 0 0 0 19 5 16
L T R L T R L T R
40 29 0 0 58 40
Sbd Nbd Sbd Nbd Sbd Nbd
40 29 0 0 58 40
R T L 37 R T L 50 R T L 51OK 0 0 40 0 0 0 0 58 0
0 Wbd 0 L 0 29 R 29 Wbd 29 L 0 0 R 29 Wbd 29 L 0 0 R 0 Wbd
T 0 0 T T 41 29 T T 0 0 T
0 Ebd 0 R 0 0 L 41 Ebd 41 R 0 0 L 41 Ebd 41 R 41 0 L 0 Ebd
OK 0 0 1 0 0 0 29 40 0
L T R L T R L T R
0 1 0 0 99 69
Sbd Nbd Sbd Nbd Sbd Nbd
0 1 0 0 36 53
R T L 38 R T L 52 R T 53OK 0 0 0 0 0 0 2 34
0 Wbd 0 L 0 0 R 2 Wbd 2 L 0 0 R 2 Wbd 2 L 2 0 Wbd
T 0 0 T T 2 2 T
0 Ebd 0 R 0 2 L 2 Ebd 2 R 0 0 L 2 Ebd 2 R 0 0 Ebd
OK 0 1 2 0 0 0 0 51
L T R L T R L T
2 3 20% T 0 0 34 51
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
2 3
R T L 70OK 0 2 0
0 Wbd 0 L 0 0 R
T 0 0 T
0 Ebd 0 R 0 0 L
OK 0 3 0
L T R
2 3
Sbd Nbd Sbd Nbd Sbd Nbd
2 3 0 0 34 51
R T L 1 R T L 25 R T L 26OK 25% 1 1 0 0 0 0 6 0 28
5 Wbd 5 L 2 0 R 6 Wbd 6 L 0 0 R 6 Wbd 6 L 10 41 R 41 Wbd 41
75% T 6 4 T T 10 6 T T 0 0 T
8 Ebd 8 R 0 2 L 10 Ebd 10 R 0 0 L 10 Ebd 10 R 0 0 L 28 Ebd 28
OK 0 1 4 0 0 0 0 0 0
0% L T R 80% L T R L T R
3 20% 5 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
BLOCK 6 RESIDENTIAL
LSL
OK OKSITE OK OK OK OK
66 48 0 0 8 5
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 7A – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 248.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 116 81 197 197 339
Gross Rate 0.468 0.326 0.794
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 4 3 7
New 112 78 190
Rate 0.452 0.314 0.766
IN Check
112 OK
OUT Check
78 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
53 90% 37 0 100% 0 3 100% 2
0% R T L 10% 7 0% R T L 0% 13 100% T 0% R T L 0% 14 50% T
OK 0% 0 48 5 0 0 0 0% R 0 3 0 50% L
0 Wbd 0 L 0 0 R 9 Wbd 9 L 0 0 R 9 Wbd 9 L 0 0 R 18 Wbd
0% T 0 0 T T 6 9 T T 6 9 T
0 Ebd 0 R 0 9 L 11 Ebd 11 R 5 0 L 6 Ebd 6 R 0 9 L 12 Ebd
OK 0% 0 37 6 0 0 0 0 2 6
L T R L T R L T R
57 43 5 0 12 8
Sbd Nbd Sbd Nbd Sbd Nbd
57 43 5 0 12 8
R T L 37 R T L 50 R T L 51OK 0 57 0 0 5 0 0 12 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 43 0 0 0 0 0 8 0
L T R L T R L T R
57 43 5 0 12 8
Sbd Nbd Sbd Nbd Sbd Nbd
57 43 5 0 12 8
R T L 38 R T L 52 R T 53OK 0 0 57 0 5 0 12 0
0 Wbd 0 L 0 43 R 43 Wbd 43 L 0 0 R 12 Wbd 12 L 8 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 57 Ebd 57 R 57 12 L 8 Ebd 8 R 0 0 Ebd
OK 0 0 0 43 0 8 0 0
L T R L T R L T
0 0 20% T 74 51 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0
T 0
0 Ebd 0 R 0
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 27 38 0 0
R T L 1 R T L 25 R T L 26OK 0% 0 0 0 6 0 21 0 0 0
4 Wbd 4 L 0 0 R 6 Wbd 6 L 9 29 R 29 Wbd 29 L 0 0 R 29 Wbd 29
100% T 6 4 T T 0 0 T T 21 29 T
6 Ebd 6 R 0 2 L 9 Ebd 9 R 0 0 L 21 Ebd 21 R 0 0 L 21 Ebd 21
OK 0 0 3 0 0 0 0 0 0
0% L T R 100% L T R L T R
2 0% 3 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
a
BLOCK 7A RESIDENTIAL
ME
V S
tree
t 'D
'C
olle
ctor
'B'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK OKSITE OK OK OK OK
53 37 0 0 3 2
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 7B – PM
Condominium/Townhouse
PM Land Use Residential Condominium/Townhouse
Dwelling Units 125.000
Land Use Code 230 PM Peak of Adjacent Street Traffic, 1Hr 4-6
Eqn ln(T) = 0.82Ln(X) + 0.32 ITE pg 389
IN 67% Avg.Rate 0.52
Out 33%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 44 21 65 65 72
Gross Rate 0.352 0.168 0.520
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 1 1 2
New 43 20 63
Rate 0.344 0.160 0.504
IN Check
42 ERROR
OUT Check
19 ERROR
Sbd Nbd Sbd Nbd Sbd Nbd
21 100% 9 0 100% 0 1 100% 1
0% R T L 0% 7 0% R T L 0% 13 100% T 0% R T L 0% 14OK 0% 0 21 0 0 0 0 0% R 0 1 0
0 Wbd 0 L 0 0 R 6 Wbd 6 L 0 0 R 6 Wbd 6 L 0 0 R 6 Wbd
0% T 0 0 T T 2 6 T T 2 6 T
0 Ebd 0 R 0 6 L 2 Ebd 2 R 0 0 L 2 Ebd 2 R 0 0 L 2 Ebd
OK 0% 0 9 2 0 0 0 0 1 0
L T R L T R L T R
27 11 0 0 1 1
Sbd Nbd Sbd Nbd Sbd Nbd
27 11 0 0 0 0
R T L 37 R T L 50 R T L 51OK 0 27 0 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 11 0 0 0 0 0 0 0
L T R L T R L T R
27 11 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
100% T 27 11 0 0 0 0
0% L R T L 38 R T L 52 R T 53OK 0 27 0 0 0 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 Ebd
OK 0 11 0 0 0 0 0 0
L T R L T R L T
27 11 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd
27 11
R T L 70OK 0 27 0
0 Wbd 0 L 0 0
T 0 0
0 Ebd 0 R 0 0
OK 0 11 0
L T R
27 11
Sbd Nbd Sbd Nbd Sbd Nbd
8 15 0 0 0 0
R T L 1 R T L 25 100% T R T L 26OK 100% 1 1 6 0 0 0 0% R 0 0 0
1 Wbd 1 L 2 12 R 12 Wbd 12 L 0 0 R 12 Wbd 12 L 0 0 R 12 Wbd 12
0% T 0 0 T T 6 12 T T 6 12 T
2 Ebd 2 R 0 0 L 6 Ebd 6 R 0 0 L 6 Ebd 6 R 0 0 L 6 Ebd 6
OK 0 1 0 0 0 0 0 0 0
0% L T R 0% L T R L T R
1 100% 1 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
a
BLOCK 7B RESIDENTIAL
HD
ME
V S
tree
t 'D
'C
olle
ctor
'B'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK OKSITE OK OK OK OK
21 9 0 0 1 1
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 7C – PM
Shopping Centre
PM Land Use Shopping Centre
1,000 sq.ft. GLA 16.824
Land Use Code 820 PM Peak of Adjacent Street Traffic, 1Hr 4-6
Eqn ln(T) = 0.67Ln(X) + 3.37 ITE pg 1502
IN 49% Avg.Rate 3.73
Out 51%
Pass by 43%
Internal 0%
Transit Reduction 10.0%
Source ITE IN OUT Total Avg Eqn
Gross 95 98 193 63 193
Gross Rate 5.647 5.825 11.472
Pass By 42 42 84
Internal 0 0 0
Transit Reduction 9 10 19
New 44 46 90
Rate 2.615 2.735 5.350
IN Check
44 OK
OUT Check
46 OK
Sbd Nbd Sbd Nbd Sbd Nbd
12 80% 13 0 100% 0 2 0% 2
0% R T L 20% 7 0% R T L 0% 13 100% R T L 0% 14OK 0% 0 12 0 0 0 0 0 2 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 2 Wbd
0% T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 2 L 2 Ebd
OK 0% 0 13 0 0 0 0 0 2 2
L T R L T R 0% L L T R 0% L
12 13 0 0 0% T 4 4 50% T
Sbd Nbd Sbd Nbd 0% R Sbd Nbd 50% R
12 13 1 1 4 4
R T L 37 R T L 50 R T L 51OK 0 12 0 0 1 0 0 4 0
0 Wbd 0 L 0 0 R 4 Wbd 1 L 0 0 R 1 Wbd 2 L 0 0 R 2 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 4 L 4 Ebd 1 R 1 1 L 1 Ebd 2 R 2 2 L 2 Ebd
OK 0 13 4 1 1 1 2 4 2
L T R 0% L L T R 25% L L T R 25% L
17 17 75% T 3 3 50% T 8 9 50% T
Sbd Nbd 25% R Sbd Nbd 25% R Sbd Nbd 25% R
17 17 3 3 8 9
R T L 38 R T L 52 R T 53OK 0 17 0 3 0 0 3 6
0 Wbd 0 L 0 0 R 6 Wbd 6 L 3 0 R 3 Wbd 3 L 3 0 Wbd
T 0 0 T T 3 3 T
0 Ebd 0 R 0 6 L 6 Ebd 6 R 0 0 L 3 Ebd 3 R 0 0 Ebd
OK 0 17 6 0 0 0 0 6
L T R 0% L L T R L T
22 23 75% T 0 0 6 6
Sbd Nbd 25% R Sbd Nbd Sbd Nbd
22 23
R T 70OK 0 22
0 Wbd 0 L 0
0 Ebd 0 R 0
OK 0 23 IN OUT
L T 44 46
22 23
Sbd Nbd even dist. 25% Sbd Nbd Sbd Nbd
23 22 11 12 6 6
R T L 1 R T L 25 R T L 26OK 100% 0 0 23 11 0 0 6 0 0
0 Wbd 0 L 0 22 R 22 Wbd 22 L 12 0 R 11 Wbd 11 L 6 0 R 6 Wbd 6
0% T 0 0 T T 12 11 T T 6 6 T
0 Ebd 0 R 0 0 L 23 Ebd 23 R 0 0 L 12 Ebd 12 R 0 0 L 6 Ebd 6
OK 0 0 0 0 0 0 50% L 0 0 0 50% L
0% L T R 0% L T R 50% T L T R 50% T
0 100% 0 0 0 0% R 0 0 0% R
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
a
BLOCK 7C COMMERCIA
L
ME
V S
tree
t 'D
'C
olle
ctor
'B'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
ERRORSITE ERROR ERROR OK OK ERROR
O1 D1 O28 D28 O27 D27
0 0 0 0 0 0
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 8 – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 154.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 72 50 122 122 235
Gross Rate 0.468 0.324 0.792
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 2 2 4
New 70 48 118
Rate 0.455 0.311 0.766
IN Check
70 OK
OUT Check
49 ERROR
Sbd 100% Nbd Sbd Nbd Sbd Nbd
32 85% 25 0 100% 0 2 100% 1
0% R T L 15% 7 0% R T L 0% 13 100% 10% T 0% R T L 0% 14 50% T
OK 0% 0 27 5 0 0 0 90% R 0 2 0 50% L
0 Wbd 0 L 0 0 R 5 Wbd 5 L 0 0 R 5 Wbd 5 L 0 0 R 9 Wbd
0% T 0 0 T T 1 5 T T 5 5 T
0 Ebd 0 R 0 5 L 6 Ebd 6 R 5 0 L 5 Ebd 5 R 0 5 L 5 Ebd
OK 0% 0 25 1 0 0 5 0 1 0
L T R L T R L T R
32 26 5 5 7 1
Sbd Nbd Sbd Nbd Sbd Nbd
32 26 5 5 7 1
R T L 37 R T L 50 R T L 51OK 0 32 0 0 5 0 0 7 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 26 0 0 5 0 0 1 0
L T R L T R L T R
32 26 5 5 7 1
Sbd Nbd Sbd Nbd Sbd Nbd
32 26 5 5 7 1
R T L 38 R T L 52 R T 53OK 0 0 32 0 5 0 7 0
0 Wbd 0 L 0 26 R 27 Wbd 27 L 0 0 R 7 Wbd 7 L 1 0 Wbd
T 0 0 T T 0 0 T
0 Ebd 0 R 0 1 L 33 Ebd 33 R 33 7 L 1 Ebd 1 R 0 0 Ebd
OK 0 0 1 27 5 1 0 0
L T R L T R L T
1 1 20% T 44 32 0 0
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
1 1
R T L 70OK 0 1 0
0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd
OK 0 1 0
L T R
1 1
Sbd Nbd Sbd Nbd Sbd Nbd
1 1 17 26 0 0
R T L 1 R T L 25 R T L 26ERROR 25% 1 0 0 3 0 14 0 0 0
2 Wbd 3 L 1 0 R 3 Wbd 3 L 5 21 R 21 Wbd 21 L 0 0 R 21 Wbd 21
75% T 3 2 T T 0 0 T T 14 21 T
4 Ebd 4 R 0 1 L 5 Ebd 5 R 0 0 L 14 Ebd 14 R 0 0 L 14 Ebd 14
OK 0 0 2 0 0 0 0 0 0
0% L T R 80% L T R L T R
1 20% 2 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
a
BLOCK 8 RESIDENTIAL
ME
V S
tree
t 'D
'C
olle
ctor
'B'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK OKSITE OK OK OK OK
32 25 0 0 2 1
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 9 – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 84.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 40 27 67 67 147
Gross Rate 0.476 0.322 0.798
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 1 1 2
New 39 26 65
Rate 0.464 0.310 0.774
IN Check
39 OK
OUT Check
28 ERROR
Sbd 100% Nbd Sbd Nbd Sbd Nbd
18 85% 14 0 100% 0 2 100% 1
0% R T L 15% 7 0% R T L 0% 13 0% R T L 0% 14 0% T
OK 0% 0 15 3 0 0 0 0 2 0 ### L
0 Wbd 0 L 0 2 R 2 Wbd 2 L 0 0 R 2 Wbd 2 L 0 0 R 5 Wbd
0% T 0 0 T T 2 2 T T 0 0 T
0 Ebd 0 R 0 0 L 3 Ebd 3 R 1 0 0 2 Ebd 2 R 2 5 L 2 Ebd
OK 0% 0 12 0 100% 70% T 0 0 0 2 1 2
L T R 30% R L T R L T R
15 12 1 0 9 5
Sbd Nbd Sbd Nbd Sbd Nbd
15 12 1 0 9 5
R T L 37 R T L 50 R T L 51OK 0 15 0 0 1 0 0 9 0
0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T T 0 0 T T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd 0 R 0 0 L 0 Ebd
OK 0 12 0 0 0 0 0 5 0
L T R L T R L T R
15 12 1 0 9 5
Sbd Nbd Sbd Nbd Sbd Nbd
15 12 1 0 9 5
R T L 38 R T L 52 R T 53OK 0 0 15 0 0 1 0 9
0 Wbd 0 L 0 12 R 12 Wbd 12 L 0 0 R 12 Wbd 12 L 0 0 Wbd
T 0 0 T T 15 12 T
0 Ebd 0 R 0 0 L 15 Ebd 15 R 0 0 L 16 Ebd 16 R 16 0 Ebd
OK 0 0 0 0 0 0 12 5
L T R L T R L T
0 0 20% T 0 0 25 17
Sbd Nbd 80% R Sbd Nbd Sbd Nbd
0 0
R T L 70OK 0 0 0
0 Wbd 0 L 0 0 R 0 Wbd
T 0 0 T
0 Ebd 0 R 0 0 L 0 Ebd
OK 0 0 0
L T R
0 0
Sbd Nbd Sbd Nbd Sbd Nbd
0 0 0 0 11 14
R T L 1 R T L 25 R T L 26OK 0% 0 0 0 0 0 0 2 0 9
1 Wbd 1 L 0 0 R 2 Wbd 2 L 0 0 R 2 Wbd 2 L 3 11 R 11 Wbd 11
100% T 2 1 T T 3 2 T T 0 0 T
2 Ebd 2 R 0 1 L 3 Ebd 3 R 0 0 L 3 Ebd 3 R 0 0 L 9 Ebd 9
OK 0 0 1 0 0 0 0 0 0
0% L T R 80% L T R L T R
1 20% 1 0 0 0 0
Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK
Brit
anni
a
BLOCK 9 RESIDENTIAL
ME
V S
tree
t 'D
'C
olle
ctor
'B'
Col
lect
or 'B
'
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK OKSITE OK ERROR OK OK
18 12 0 0 2 1
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3
Zone 10 – PM
Single-Family Detached Housing - BRISTOL TRIP GEN
PM Land Use Single-Family Detached Housing
Dwelling Units 532.000
BRISTOL SURVEY TRIP GENERATION
Land Use Code PM Peak of Adjacent Street Traffic, 1Hr 7-9
Eqn
IN 59% Avg.Rate 0.793
Out 41%
Pass by 0%
Internal 0%
Transit Reduction 3.5%
Source ITE IN OUT Total Avg Eqn
Gross 249 173 422 422 610
Gross Rate 0.468 0.325 0.793
Pass By 0 0 0
Internal 0 0 0
Transit Reduction 9 6 15
New 240 167 407
Rate 0.451 0.314 0.765
IN Check
240 OK
OUT Check
167 OK
Sbd 100% Nbd Sbd Nbd Sbd Nbd
109 70% 76 0 100% 0 12 100% 8
0% R T L 30% 7 0% R T L 0% 13 0% R T L 0% 14 0% T
OK 0% 0 76 33 0 0 0 0 12 0 100% L
0 Wbd 0 L 0 23 R 23 Wbd 23 L 0 0 R 23 Wbd 23 L 0 0 R 31 Wbd
0% T 0 0 T T 30 23 T T 0 0 T
0 Ebd 0 R 0 0 L 33 Ebd 33 R 3 0 0 30 Ebd 30 R 30 31 L 22 Ebd
OK 0% 0 53 0 100% 90% T 0 0 0 23 8 22
L T R 10% R L T R L T R
76 53 3 0 73 53
50% L Sbd Nbd 50% L Sbd Nbd Sbd Nbd
50% T 76 53 50% T 3 0 90% T 73 53
R T L 37 R T L 50 10% L R T L 51OK 0 38 38 0 2 2 0 65 7
0 Wbd 0 L 0 27 R 27 Wbd 27 L 0 0 R 27 Wbd 27 L 0 5 R 12 Wbd
T 0 0 T T 39 27 T T 10 7 T
0 Ebd 0 R 0 1 L 39 Ebd 39 R 0 0 L 41 Ebd 41 R 31 0 L 17 Ebd
OK 0 27 1 0 0 0 25% T 21 48 0
L T R L T R 75% R L T R
39 28 2 0 96 68
Sbd Nbd Sbd Nbd Sbd Nbd
39 28 2 0 STAY 60% 53 72
R T L 38 R T L 52 40% T R T 53OK 0 1 38 0 0 2 14 38
0 Wbd 0 L 0 27 R 29 Wbd 29 L 0 0 R 29 Wbd 29 L 21 0 Wbd
T 0 0 T T 41 29 T
0 Ebd 0 R 0 2 L 41 Ebd 41 R 0 0 L 42 Ebd 42 R 21 0 Ebd
OK 0 1 3 0 0 0 50% L 14 50
L T R L T R 50% R L T
3 4 30% T 0 0 60 65
Sbd Nbd 70% R Sbd Nbd Sbd Nbd
3 4
R T L 70OK 0 3 0
0 Wbd 0 L 0 0 R 0 Wbd 60% T
T 0 0 T R
0 Ebd 0 R 0 0 L 0 Ebd 40% STAY
OK 0 4 0
L T R
3 4
Sbd Nbd Sbd Nbd Sbd Nbd Sbd Nbd
3 4 0 0 58 84 0 0
R T L 1 R T L 25 R T L 26 R T L 27OK 25% 2 1 0 0 0 0 10 0 48 0 0 0
8 Wbd 8 L 3 0 R 10 Wbd 10 L 0 0 R 10 Wbd 10 L 15 69 R 69 Wbd 69 L 0 0 R
75% T 9 6 T T 15 10 T T 0 0 T T 48 69 T
12 Ebd 12 R 0 4 L 15 Ebd 15 R 0 0 L 15 Ebd 15 R 0 0 L 48 Ebd 48 R 0 0 L
OK 0 1 6 0 0 0 0 0 0 0 0 0
0% L T R 80% L T R L T R L T R
5 20% 7 0 0 0 0 0 0
Sbd Nbd Sbd Nbd Sbd Nbd Sbd NbdOK OK OK OK OK OK OK OK
Brit
anni
aM
EV
Str
eet '
D'
Col
lect
or 'B
'
Col
lect
or 'B
'
CN
R
BLOCK 10 RESIDENTIAL
CN
R
Col
lect
or 'A
'
Col
lect
or 'A
'
LSL
OK OKSITE OK OK OK OK
109 76 0 0 12 8
CN
R
O1 D1 O28 D28 O27 D27
Tremaine Road Collector Road 'H' Savoline Blvd
UPDATE LINK TO EACH BLOCK 1 2 3 4
Varg
a Si
te T
rips – A
M
INO
UT
TOT
INO
UT
TOT
748
905
1653
674
518
1192
INO
UT
TOT
INO
UT
TOT
Sbd
Nbd
748
905
1653
15
21
80
00
0
RT
L74
890
516
53
015
20
Wbd
0L
00
R1
12
Wbd
T0
0T
Ebd
0R
011
2L
13
4E
bd
018
013
4
LT
R
26
43
14
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
26
43
14
45
56
13
52
16
13
7
RT
LR
T L
RT
LR
T L
00
264
1530
06
07
211
50
Wbd
0L
020
1R
25
9W
bd3
06
L25
0R
32
3W
bd3
61
L2
3R
35
3W
bd3
44
L88
0R
0W
bd
T0
0T
T21
522
2T
T25
734
7T
T0
0T
Ebd
0R
058
L3
05
Ebd
37
7R
137
101
L2
50
Ebd
26
2R
33
L2
72
Ebd
28
3R
195
0L
0E
bd
011
341
6931
358
08
133
490
LT
RL
T R
LT
RL
T R
58
15
425
26
81
35
61
62
00
18
2
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
58
99
21
24
82
03
15
1
RT
LR
T L
RT
L
058
043
137
320
203
0
Wbd
0L
043
R4
3W
bd4
3L
00
R0
Wbd
0L
R0
Wbd
0L
320
R0
Wbd
T0
0T
T0
0T
T32
TT
00
T
Ebd
0R
00
L0
Ebd
0R
00
L3
2E
bd3
2R
L3
2E
bd3
2R
00
L0
Ebd
056
00
480
011
90
LT
RL
T R
LT
R
58
56
13
74
82
03
11
9
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
58
56
13
74
82
03
11
9
RT
LR
T L
RT
L
580
032
010
51
020
2
Wbd
91
L56
0R
33
Wbd
33
L18
30R
31
Wbd
31
L0
0R
31
Wbd
31
L0
119
R1
49
Wbd
T18
33T
T0
1T
T10
531
TT
105
30T
Ebd
74
R0
0L
18
Ebd
18
R0
0L
10
5E
bd1
05
R0
0L
10
5E
bd1
05
R0
0L
30
7E
bd
00
0
LT
R
00
Sbd
Nbd
AM
PM
Gen
Tot
[Str
eet
A]
AM
Trem
aine
Louis St Laurent
Louis St Laurent
Street A [Street B] Britannia
Str
eet
JS
tree
t B
[C
]
Str
eet
K
AM
PM
Trem
aine
Street A [Street B] Britannia
Varg
a Si
te T
rips – P
M
INO
UT
TOT
INO
UT
TOT
748
905
1653
674
518
1192
INO
UT
TOT
INO
UT
TOT
Sbd
Nbd
674
518
1192
13
61
03
00
0
RT
L67
451
811
92
013
60
Wbd
0L
00
R9
9W
bd
T0
0T
Ebd
0R
099
L7
7E
bd
010
377
LT
R
23
51
80
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
23
51
81
49
39
91
61
85
66
RT
LR
T L
RT
LR
T L
00
235
2623
04
05
167
180
Wbd
0L
095
R1
33
Wbd
25
8L
250
R2
52
Wbd
26
0L
79
R2
69
Wbd
27
6L
460
R0
Wbd
T0
0T
T15
618
8T
T17
225
0T
T0
0T
Ebd
0R
038
L2
59
Ebd
27
7R
9664
L1
83
Ebd
18
8R
910
L1
82
Ebd
17
7R
131
0L
0E
bd
086
2444
1427
60
510
920
0
LT
RL
T R
LT
RL
T R
38
11
024
18
38
51
91
11
49
12
9
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
39
62
96
46
12
01
19
RT
LR
T L
RT
L
039
013
749
012
00
Wbd
0L
013
R1
3W
bd1
3L
00
R0
Wbd
0L
R0
Wbd
0L
90
R0
Wbd
T0
0T
T0
0T
TT
T0
0T
Ebd
0R
00
L0
Ebd
0R
00
L9
Ebd
0R
L0
Ebd
9R
00
L0
Ebd
049
00
460
011
00
LT
RL
T R
LT
R
39
49
74
46
12
01
10
Sbd
Nbd
Sbd
Nbd
Sbd
Nbd
39
49
75
46
11
91
10
RT
LR
T L
RT
L
390
014
061
00
119
Wbd
53
L49
0R
14
Wbd
14
L19
27R
27
Wbd
27
L0
0R
27
Wbd
27
L1
109
R1
36
Wbd
T20
14T
T1
0T
T62
27T
T61
27T
Ebd
69
R0
0L
20
Ebd
20
R0
0L
62
Ebd
62
R0
0L
62
Ebd
62
R0
0L
18
0E
bd
00
0
LT
R
00
Sbd
Nbd
AM
Gen
PM
PM
Louis St Laurent
Louis St Laurent
Trem
aine
Britannia
[Str
eet
A]
BritanniaStreet A [Street B]
Str
eet
J
Str
eet
K
Str
eet
B [
C]
AM
PM
Trem
aine
Street A [Street B]
Tot
Appendix C
Transportation Tomorrow Survey (TTS) Data and
Internal Site Trips
Wed
Oct
31
2018
07:
58:3
6 GM
T-04
00 (E
aste
rn D
aylig
ht T
ime)
- Ru
n Ti
me:
220
3ms
Cros
s Tab
ulat
ion
Que
ry F
orm
- Tr
ip -
2016
v1.
1
Row
: Pla
nnin
g di
stric
t of h
ouse
hold
- pd
_hhl
dCo
lum
n: P
lann
ing
dist
rict o
f em
ploy
men
t - p
d_em
p
Filte
rs:
No
Filte
rs
Trip
201
6Ta
ble:
Not
em
ploy
edPD 1
of T
oron
toPD
2 o
f Tor
onto
PD 3
of T
oron
toPD
4 o
f Tor
onto
PD 5
of T
oron
toPD
6 o
f Tor
onto
PD 7
of T
oron
toPD
8 o
f Tor
onto
PD 9
of T
oron
toPD
10
of T
oron
toPD
11
of T
oron
toPD
12
of T
oron
toPD
13
of T
oron
toPD
14
of T
oron
toPD
15
of T
oron
toM
ilton
6109
260
0563
356
559
527
515
163
619
1524
5212
4710
3825
141
00
04.
5716
%0.
4819
%0.
4301
%0.
4530
%0.
2094
%0.
1150
%0.
4842
%1.
4579
%1.
8667
%0.
9493
%0.
7902
%0.
1911
%0.
3121
%0.
0000
%0.
0000
%TO
TAL
1313
54
PD 1
6 of
Tor
onto
Broc
kU
xbrid
geSc
ugog
Pick
erin
gAj
axW
hitb
yO
shaw
aCl
arin
gton
Geor
gina
East
Gw
illim
bury
New
mar
ket
Auro
raRi
chm
ond
Hill
Whi
tchu
rch-
Stou
ffvill
eM
arkh
amKi
ngVa
ugha
nCa
ledo
nBr
ampt
onM
ississ
auga
Halto
n Hi
lls20
20
00
5331
00
360
081
5835
60
910
030
2829
210
019
3711
427
370.
1538
%0.
0000
%0.
0000
%0.
0000
%0.
0403
%0.
0236
%0.
0000
%0.
0000
%0.
0274
%0.
0000
%0.
0000
%0.
0617
%0.
0442
%0.
2710
%0.
0000
%0.
6928
%0.
0000
%2.
3052
%0.
2223
%7.
6275
%28
.254
9%2.
0837
%
Milt
onO
akvi
lleBu
rling
ton
Flam
boro
ugh
Dund
asAn
cast
erGl
anbr
ook
Ston
ey C
reek
Ham
ilton
Grim
sby
Linc
oln
Pelh
amN
iaga
ra-o
n-th
e-La
keSt
. Cat
harin
esTh
orol
dN
iaga
ra F
alls
Wel
land
Port
Col
born
eFo
rt E
rieW
est L
inco
lnW
ainf
leet
Wat
erlo
o36
837
9643
5401
258
00
122
373
1730
00
00
143
014
10
00
00
967
28.0
441%
7.34
12%
4.11
18%
0.19
64%
0.00
00%
0.00
00%
0.09
29%
0.28
40%
1.31
71%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.10
89%
0.00
00%
0.10
73%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.73
62%
Kitc
hene
rCa
mbr
idge
Nor
th D
umfr
ies
Wilm
otW
elle
sley
Woo
lwic
hCi
ty o
f Gue
lph
Pusli
nch
Guel
ph/E
ram
osa
Cent
re W
ellin
gton
Erin
Ora
ngev
ille
Barr
ieIn
nisf
ilBr
adfo
rd-W
est G
will
imbu
ryN
ew T
ecum
seth
Adja
la-T
osor
ontio
Essa
Clea
rvie
w98
710
610
00
018
6749
360
1620
00
00
280
00
0.75
14%
0.80
77%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
1.42
13%
0.37
53%
0.04
57%
0.01
22%
0.01
52%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.02
13%
0.00
00%
0.00
00%
0.00
00%
Sprin
gwat
erKa
war
tha
Lake
sPe
terb
orou
ghCa
van
Mon
agha
nO
tona
bee-
Sout
h M
onag
han
Asph
odel
-Nor
woo
dDu
mm
er-D
ouro
Selw
ynN
orth
umbe
rland
Rest
of P
eter
boro
ugh
Hast
ings
Halib
urto
nM
usko
kaGr
eyRe
st o
f Wel
lingt
onPe
rth
Oxf
ord
00
00
00
00
00
00
00
013
530.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0099
%0.
0403
%
Kitc
hene
rCa
mbr
idge
Nor
th D
umfr
ies
Wilm
otW
elle
sley
Woo
lwic
hCi
ty o
f Gue
lph
Pusli
nch
Guel
ph/E
ram
osa
Cent
re W
ellin
gton
Erin
Ora
ngev
ille
Barr
ieIn
nisf
ilBr
adfo
rd-W
est G
will
imbu
ryN
ew T
ecum
seth
Adja
la-T
osor
ontio
Essa
Clea
rvie
w98
710
610
00
018
6749
360
1620
00
00
280
00
0.75
14%
0.80
77%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
1.42
13%
0.37
53%
0.04
57%
0.01
22%
0.01
52%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.02
13%
0.00
00%
0.00
00%
0.00
00%
Sprin
gwat
erKa
war
tha
Lake
sPe
terb
orou
ghCa
van
Mon
agha
nO
tona
bee-
Sout
h M
onag
han
Asph
odel
-Nor
woo
dDu
mm
er-D
ouro
Selw
ynN
orth
umbe
rland
Rest
of P
eter
boro
ugh
Hast
ings
Halib
urto
nM
usko
kaGr
eyRe
st o
f Wel
lingt
onPe
rth
Oxf
ord
00
00
00
00
00
00
00
013
530.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0000
%0.
0099
%0.
0403
%
Bran
tHa
ldim
and-
Nor
folk
Colli
ngw
ood
Was
aga
Beac
hTi
nyPe
neta
ngui
shen
eM
idla
ndTa
yO
ro-M
edon
teSe
vern
Ram
ara
Oril
liaM
ulm
urSh
elbu
rne
Amar
anth
Mel
anct
hon
Mon
oGr
and
Valle
yEa
st G
araf
raxa
Bran
tfor
dN
o U
sual
Pla
ceExte
rnal
00
00
00
00
00
030
00
00
00
021
1372
650
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.02
28%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.00
00%
0.01
60%
15%
30%
27.5%
27.5%
Green
Zon
e 20
24
AMS
bdN
bdS
bdN
bd
310
00
RT
LR
T L
031
00
00
Wbd
30L
00
R0
Wbd
10L
00
R0
Wbd
21.4
T10
0T
T0
0T
Ebd
42R
310
L10
Ebd
10R
100
L0
Ebd
300
010
00
LT
RL
TR
6330
1010
Sbd
63N
bdS
bd0
Nbd
Street B
Str
eet C
Str
eet A
PMS
bdN
bdS
bdN
bd
200
00
RT
LR
T L
020
00
00
Wbd
98L
00
R0
Wbd
0L
00
R0
Wbd
13.5
T7
0T
T0
0T
Ebd
26R
200
L7
Ebd
7R
70
L0
Ebd
980
00
00
LT
RL
TR
4098
70
Sbd
39.6
Nbd
Sbd
0N
bdStreet B
Str
eet C
Str
eet A
Red Zo
ne 202
4
AMS
bdN
bdS
bdN
bd
00
128
39
RT
LR
T L
00
034
940
Wbd
40L
00
R40
Wbd
40L
00
R16
Wbd
40T
040
TT
06
T
Ebd
0R
00
L0
Ebd
0R
010
L4
Ebd
00
00
394
LT
RL
TR
00
104
43
Sbd
0N
bdS
bd10
4N
bd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
00
8112
8
RT
LR
T L
00
022
590
Wbd
22L
00
R22
Wbd
25L
00
R10
Wbd
22T
022
TT
04
T
Ebd
0R
00
L0
Ebd
0R
07
L14
Ebd
00
00
128
14
LT
RL
TR
00
6614
2
Sbd
0N
bdS
bd66
Nbd
Str
eet C
Str
eet A
Street B
Yello
w Zon
e 20
24
AMS
bdN
bdS
bdN
bd
00
00
RT
LR
T
00
00
0
Wbd
43L
00
R0
Wbd
0L
00
Wbd
43T
00
T
Ebd
0R
00
L0
Ebd
0R
00
Ebd
430
00
0
LT
RL
T
043
00
Sbd
63N
bdS
bd0
Nbd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
00
00
RT
LR
T
00
00
0
Wbd
27L
00
R0
Wbd
0L
00
Wbd
27T
00
T
Ebd
0R
00
L0
Ebd
0R
00
Ebd
270
00
0
LT
RL
T
027
00
Sbd
40N
bdS
bd0
Nbd
Str
eet C
Str
eet A
Street B
Blue
Zon
e 20
24
AMS
bdN
bdS
bdN
bd
00
00
RT
LR
T L
00
00
00
Wbd
40L
00
R40
Wbd
40L
00
R16
Wbd
40T
040
TT
06
T
Ebd
0R
00
L0
Ebd
0R
010
L4
Ebd
00
034
04
LT
RL
TR
00
1039
Sbd
0N
bdS
bd10
4N
bd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
00
00
RT
LR
T L
00
00
00
Wbd
22L
00
R22
Wbd
25L
00
R10
Wbd
22T
022
TT
04
T
Ebd
0R
00
L0
Ebd
0R
07
L0
Ebd
00
022
00
LT
RL
TR
00
722
Sbd
0N
bdS
bd65
.7N
bd
Str
eet C
Str
eet A
Street B
Green
Zon
e 20
24
AM
Sbd
Nbd
Sbd
Nbd
280
00
RT
LR
T L
028
00
00
Wbd
24L
00
R0
Wbd
10L
00
R0
Wbd
25.7
T10
0T
T0
0T
Ebd
37R
280
L10
Ebd
10R
100
L0
Ebd
240
010
00
LT
RL
TR
5624
1010
Sbd
56N
bdS
bd0
Nbd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
180
00
RT
LR
T L
018
00
00
Wbd
79L
00
R0
Wbd
0L
00
R0
Wbd
16.3
T6
0T
T0
0T
Ebd
24R
180
L6
Ebd
6R
60
L0
Ebd
790
00
00
LT
RL
TR
3579
60
Sbd
35.1
Nbd
Sbd
0N
bd
Str
eet C
Str
eet A
Street B
Red Zo
ne 202
4
AM
Sbd
Nbd
Sbd
Nbd
00
128
33
RT
LR
T L
00
041
870
Wbd
48L
00
R48
Wbd
48L
00
R17
Wbd
48T
048
TT
07
T
Ebd
0R
00
L0
Ebd
0R
010
L4
Ebd
00
00
334
LT
RL
TR
00
9737
Sbd
0N
bdS
bd97
Nbd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
00
8111
1
RT
LR
T L
00
026
550
Wbd
26L
00
R26
Wbd
30L
00
R10
Wbd
26T
026
TT
04
T
Ebd
0R
00
L0
Ebd
0R
06
L12
Ebd
00
00
111
12
LT
RL
TR
00
6112
3
Sbd
0N
bdS
bd61
Nbd
Str
eet C
Str
eet A
Street B
Yello
w Zon
e 20
24
AM
Sbd
Nbd
Sbd
Nbd
00
00
RT
LR
T
00
00
0
Wbd
51L
00
R0
Wbd
0L
00
Wbd
51T
00
T
Ebd
0R
00
L0
Ebd
0R
00
Ebd
510
00
0
LT
RL
T
051
00
Sbd
56N
bdS
bd0
Nbd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
00
00
RT
LR
T
00
00
0
Wbd
33L
00
R0
Wbd
0L
00
Wbd
33T
00
T
Ebd
0R
00
L0
Ebd
0R
00
Ebd
330
00
0
LT
RL
T
033
00
Sbd
35N
bdS
bd0
Nbd
Str
eet C
Str
eet A
Street B
Blue
Zon
e 20
24
AM
Sbd
Nbd
Sbd
Nbd
00
00
RT
LR
T L
00
00
00
Wbd
48L
00
R48
Wbd
48L
00
R17
Wbd
48T
048
TT
07
T
Ebd
0R
00
L0
Ebd
0R
010
L4
Ebd
00
041
04
LT
RL
TR
00
1045
Sbd
0N
bdS
bd96
.8N
bd
Str
eet C
Str
eet A
Street B
PMS
bdN
bdS
bdN
bd
00
00
RT
LR
T L
00
00
00
Wbd
26L
00
R26
Wbd
30L
00
R10
Wbd
26T
026
TT
04
T
Ebd
0R
00
L0
Ebd
0R
06
L0
Ebd
00
026
00
LT
RL
TR
00
626
Sbd
0N
bdS
bd61
.2N
bd
Str
eet C
Str
eet A
Street B
Appendix D
Capacity Analysis Results
HCM Unsignalized Intersection Capacity Analysis1: Tremaine Rd & Collector "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 1AM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 208 860 87 0 903Future Volume (Veh/h) 0 208 860 87 0 903Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 226 935 95 0 982PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1310 359 1030vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1310 359 1030tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 65 100cM capacity (veh/h) 151 637 670
Direction, Lane # WB 1 NB 1 NB 2 NB 3 SB 1 SB 2 SB 3Volume Total 226 374 374 282 327 327 327Volume Left 0 0 0 0 0 0 0Volume Right 226 0 0 95 0 0 0cSH 637 1700 1700 1700 1700 1700 1700Volume to Capacity 0.35 0.22 0.22 0.17 0.19 0.19 0.19Queue Length 95th (m) 12.1 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 13.7 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 13.7 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 1.4Intersection Capacity Utilization 38.1% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 2AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 16 47 54 28 121 10 83 62 34 18 30 32Future Volume (Veh/h) 16 47 54 28 121 10 83 62 34 18 30 32Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 17 51 59 30 132 11 90 67 37 20 33 35PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 143 110 364 318 80 382 342 138vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 143 110 364 318 80 382 342 138tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 99 98 83 88 96 96 94 96cM capacity (veh/h) 1440 1480 531 580 980 493 562 911
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 127 173 194 88Volume Left 17 30 90 20Volume Right 59 11 37 35cSH 1440 1480 601 639Volume to Capacity 0.01 0.02 0.32 0.14Queue Length 95th (m) 0.3 0.5 10.6 3.6Control Delay (s) 1.1 1.4 13.8 11.5Lane LOS A A B BApproach Delay (s) 1.1 1.4 13.8 11.5Approach LOS B B
Intersection SummaryAverage Delay 7.0Intersection Capacity Utilization 35.7% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 3AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 42 10 48 16 21 17 90 168 8 8 109 42Future Volume (Veh/h) 42 10 48 16 21 17 90 168 8 8 109 42Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 46 11 52 17 23 18 98 183 9 9 118 46PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 572 547 141 600 566 188 164 192vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 572 547 141 600 566 188 164 192tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 88 97 94 95 94 98 93 99cM capacity (veh/h) 380 411 907 359 401 855 1414 1381
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 109 58 290 173Volume Left 46 17 98 9Volume Right 52 18 9 46cSH 532 461 1414 1381Volume to Capacity 0.21 0.13 0.07 0.01Queue Length 95th (m) 5.8 3.3 1.7 0.1Control Delay (s) 13.5 13.9 3.0 0.4Lane LOS B B A AApproach Delay (s) 13.5 13.9 3.0 0.4Approach LOS B B
Intersection SummaryAverage Delay 5.1Intersection Capacity Utilization 41.9% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis4: Tremaine Rd & Street "B" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 4AM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 129 818 74 0 903Future Volume (Veh/h) 0 129 818 74 0 903Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 140 889 80 0 982PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1216 296 969vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1216 296 969tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 80 100cM capacity (veh/h) 173 700 707
Direction, Lane # WB 1 NB 1 NB 2 NB 3 NB 4 SB 1 SB 2 SB 3Volume Total 140 296 296 296 80 327 327 327Volume Left 0 0 0 0 0 0 0 0Volume Right 140 0 0 0 80 0 0 0cSH 700 1700 1700 1700 1700 1700 1700 1700Volume to Capacity 0.20 0.17 0.17 0.17 0.05 0.19 0.19 0.19Queue Length 95th (m) 5.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 11.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 11.4 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 0.8Intersection Capacity Utilization 30.5% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 5AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 8 27 69 11 62 13 78 64 20 17 99 13Future Volume (Veh/h) 8 27 69 11 62 13 78 64 20 17 99 13Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 9 29 75 12 67 14 85 70 22 18 108 14PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 450 413 115 492 409 81 122 92vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 450 413 115 492 409 81 122 92tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 98 94 92 97 86 99 94 99cM capacity (veh/h) 435 493 937 406 495 979 1465 1503
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 113 93 177 140Volume Left 9 12 85 18Volume Right 75 14 22 14cSH 708 519 1465 1503Volume to Capacity 0.16 0.18 0.06 0.01Queue Length 95th (m) 4.3 4.9 1.4 0.3Control Delay (s) 11.0 13.4 3.9 1.0Lane LOS B B A AApproach Delay (s) 11.0 13.4 3.9 1.0Approach LOS B B
Intersection SummaryAverage Delay 6.4Intersection Capacity Utilization 29.5% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 6AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 36 0 30 0 0 0 47 96 0 0 135 54Future Volume (Veh/h) 36 0 30 0 0 0 47 96 0 0 135 54Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 39 0 33 0 0 0 51 104 0 0 147 59PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 382 382 176 416 412 104 206 104vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 382 382 176 416 412 104 206 104tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 93 100 96 100 100 100 96 100cM capacity (veh/h) 559 530 867 512 510 951 1365 1488
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 72 0 155 206Volume Left 39 0 51 0Volume Right 33 0 0 59cSH 668 1700 1365 1488Volume to Capacity 0.11 0.00 0.04 0.00Queue Length 95th (m) 2.7 0.0 0.9 0.0Control Delay (s) 11.0 0.0 2.8 0.0Lane LOS B A AApproach Delay (s) 11.0 0.0 2.8 0.0Approach LOS B A
Intersection SummaryAverage Delay 2.8Intersection Capacity Utilization 31.9% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 7AM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 11 552 789 149Future Volume (vph) 11 552 789 149Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 39.4 39.4 11.6Actuated g/C Ratio 0.66 0.66 0.19v/c Ratio 0.50 0.74 0.58Control Delay 8.0 12.0 24.3Queue Delay 0.0 0.0 0.0Total Delay 8.0 12.0 24.3LOS A B CApproach Delay 8.0 12.0 24.3Approach LOS A B C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 60Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.74Intersection Signal Delay: 12.1 Intersection LOS: BIntersection Capacity Utilization 63.3% ICU Level of Service BAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 8AM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 612 913 214v/c Ratio 0.50 0.74 0.58Control Delay 8.0 12.0 24.3Queue Delay 0.0 0.0 0.0Total Delay 8.0 12.0 24.3Queue Length 50th (m) 28.2 37.5 18.0Queue Length 95th (m) 63.1 m#135.6 m31.7Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 1214 1227 736Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.50 0.74 0.29
Intersection Summary# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.m Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 9AM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 11 552 789 51 149 48Future Volume (vph) 11 552 789 51 149 48Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 1.00 1.00 1.00Frt 1.00 0.99 0.97Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 1882 1868 1755Flt Permitted 0.98 1.00 0.96Satd. Flow (perm) 1851 1868 1755Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 12 600 858 55 162 52RTOR Reduction (vph) 0 0 2 0 27 0Lane Group Flow (vph) 0 612 911 0 187 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 39.4 39.4 11.6Effective Green, g (s) 39.4 39.4 11.6Actuated g/C Ratio 0.66 0.66 0.19Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 1215 1226 339v/s Ratio Prot c0.49 c0.11v/s Ratio Perm 0.33v/c Ratio 0.50 0.74 0.55Uniform Delay, d1 5.3 6.9 21.9Progression Factor 1.00 0.99 1.00Incremental Delay, d2 1.5 2.5 1.9Delay (s) 6.8 9.3 23.9Level of Service A A CApproach Delay (s) 6.8 9.3 23.9Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 10.2 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.70Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 63.3% ICU Level of Service BAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 10AM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 19 682 802 181Future Volume (vph) 19 682 802 181Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 38.2 38.2 12.8Actuated g/C Ratio 0.64 0.64 0.21v/c Ratio 0.66 0.80 0.61Control Delay 9.4 17.3 25.3Queue Delay 0.0 0.0 0.0Total Delay 9.4 17.3 25.3LOS A B CApproach Delay 9.4 17.3 25.3Approach LOS A B C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 65Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.80Intersection Signal Delay: 15.2 Intersection LOS: BIntersection Capacity Utilization 71.0% ICU Level of Service CAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 11AM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 762 956 238v/c Ratio 0.66 0.80 0.61Control Delay 9.4 17.3 25.3Queue Delay 0.0 0.0 0.0Total Delay 9.4 17.3 25.3Queue Length 50th (m) 23.5 64.8 21.5Queue Length 95th (m) #66.8 #166.9 35.9Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 1156 1188 733Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.66 0.80 0.32
Intersection Summary# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 12AM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 19 682 802 77 181 38Future Volume (vph) 19 682 802 77 181 38Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 1.00 1.00 1.00Frt 1.00 0.99 0.98Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 1881 1861 1767Flt Permitted 0.96 1.00 0.96Satd. Flow (perm) 1815 1861 1767Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 21 741 872 84 197 41RTOR Reduction (vph) 0 0 4 0 17 0Lane Group Flow (vph) 0 762 952 0 221 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 38.2 38.2 12.8Effective Green, g (s) 38.2 38.2 12.8Actuated g/C Ratio 0.64 0.64 0.21Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 1155 1184 376v/s Ratio Prot c0.51 c0.13v/s Ratio Perm 0.42v/c Ratio 0.66 0.80 0.59Uniform Delay, d1 6.8 8.1 21.2Progression Factor 0.74 1.00 1.00Incremental Delay, d2 2.7 5.9 2.4Delay (s) 7.7 14.0 23.6Level of Service A B CApproach Delay (s) 7.7 14.0 23.6Approach LOS A B C
Intersection SummaryHCM 2000 Control Delay 12.7 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.75Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 71.0% ICU Level of Service CAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis1: Tremaine Rd & Collector "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 1PM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 188 966 226 0 678Future Volume (Veh/h) 0 188 966 226 0 678Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 204 1050 246 0 737PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1419 473 1296vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1419 473 1296tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 62 100cM capacity (veh/h) 128 538 531
Direction, Lane # WB 1 NB 1 NB 2 NB 3 SB 1 SB 2 SB 3Volume Total 204 420 420 456 246 246 246Volume Left 0 0 0 0 0 0 0Volume Right 204 0 0 246 0 0 0cSH 538 1700 1700 1700 1700 1700 1700Volume to Capacity 0.38 0.25 0.25 0.27 0.14 0.14 0.14Queue Length 95th (m) 13.4 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 15.7 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS CApproach Delay (s) 15.7 0.0 0.0Approach LOS C
Intersection SummaryAverage Delay 1.4Intersection Capacity Utilization 42.0% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 2PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 24 123 82 43 103 17 75 50 18 29 45 25Future Volume (Veh/h) 24 123 82 43 103 17 75 50 18 29 45 25Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 26 134 89 47 112 18 82 54 20 32 49 27PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 130 223 497 454 178 492 490 121vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 130 223 497 454 178 492 490 121tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 98 97 80 89 98 92 89 97cM capacity (veh/h) 1455 1346 414 475 864 417 454 930
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 249 177 156 108Volume Left 26 47 82 32Volume Right 89 18 20 27cSH 1455 1346 466 505Volume to Capacity 0.02 0.03 0.33 0.21Queue Length 95th (m) 0.4 0.8 11.1 6.1Control Delay (s) 0.9 2.3 16.6 14.0Lane LOS A A C BApproach Delay (s) 0.9 2.3 16.6 14.0Approach LOS C B
Intersection SummaryAverage Delay 6.9Intersection Capacity Utilization 37.9% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 3PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 69 26 89 13 20 19 70 177 18 21 212 86Future Volume (Veh/h) 69 26 89 13 20 19 70 177 18 21 212 86Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 75 28 97 14 22 21 76 192 20 23 230 93PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 708 686 276 788 723 202 323 212vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 708 686 276 788 723 202 323 212tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 75 92 87 94 93 97 94 98cM capacity (veh/h) 304 341 762 238 325 839 1237 1358
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 200 57 288 346Volume Left 75 14 76 23Volume Right 97 21 20 93cSH 439 376 1237 1358Volume to Capacity 0.46 0.15 0.06 0.02Queue Length 95th (m) 17.7 4.0 1.5 0.4Control Delay (s) 19.9 16.3 2.6 0.7Lane LOS C C A AApproach Delay (s) 19.9 16.3 2.6 0.7Approach LOS C C
Intersection SummaryAverage Delay 6.6Intersection Capacity Utilization 58.2% ICU Level of Service BAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis4: Tremaine Rd & Street "B" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 4PM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 111 1081 168 0 696Future Volume (Veh/h) 0 111 1081 168 0 696Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 121 1175 183 0 757PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1427 392 1358vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1427 392 1358tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 80 100cM capacity (veh/h) 126 607 502
Direction, Lane # WB 1 NB 1 NB 2 NB 3 NB 4 SB 1 SB 2 SB 3Volume Total 121 392 392 392 183 252 252 252Volume Left 0 0 0 0 0 0 0 0Volume Right 121 0 0 0 183 0 0 0cSH 607 1700 1700 1700 1700 1700 1700 1700Volume to Capacity 0.20 0.23 0.23 0.23 0.11 0.15 0.15 0.15Queue Length 95th (m) 5.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 12.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 12.4 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 0.7Intersection Capacity Utilization 34.4% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 5PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 13 61 92 24 45 8 73 100 14 11 78 8Future Volume (Veh/h) 13 61 92 24 45 8 73 100 14 11 78 8Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 14 66 100 26 49 9 79 109 15 12 85 9PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 422 396 90 521 392 116 94 124vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 422 396 90 521 392 116 94 124tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 97 87 90 93 90 99 95 99cM capacity (veh/h) 475 509 968 359 511 936 1500 1463
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 180 84 203 106Volume Left 14 26 79 12Volume Right 100 9 15 9cSH 686 472 1500 1463Volume to Capacity 0.26 0.18 0.05 0.01Queue Length 95th (m) 8.0 4.9 1.3 0.2Control Delay (s) 12.1 14.3 3.2 0.9Lane LOS B B A AApproach Delay (s) 12.1 14.3 3.2 0.9Approach LOS B B
Intersection SummaryAverage Delay 7.2Intersection Capacity Utilization 34.1% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 6PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 50 0 47 0 0 0 37 201 0 0 154 52Future Volume (Veh/h) 50 0 47 0 0 0 37 201 0 0 154 52Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 54 0 51 0 0 0 40 218 0 0 167 57PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 494 494 196 544 522 218 224 218vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 494 494 196 544 522 218 224 218tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 89 100 94 100 100 100 97 100cM capacity (veh/h) 475 463 846 413 446 822 1345 1352
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 105 0 258 224Volume Left 54 0 40 0Volume Right 51 0 0 57cSH 603 1700 1345 1352Volume to Capacity 0.17 0.00 0.03 0.00Queue Length 95th (m) 4.8 0.0 0.7 0.0Control Delay (s) 12.2 0.0 1.4 0.0Lane LOS B A AApproach Delay (s) 12.2 0.0 1.4 0.0Approach LOS B A
Intersection SummaryAverage Delay 2.8Intersection Capacity Utilization 39.5% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 7PM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 33 993 695 94Future Volume (vph) 33 993 695 94Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 42.0 42.0 9.0Actuated g/C Ratio 0.70 0.70 0.15v/c Ratio 0.88 0.69 0.45Control Delay 19.7 8.5 23.9Queue Delay 0.0 0.0 0.0Total Delay 19.7 8.5 23.9LOS B A CApproach Delay 19.7 8.5 23.9Approach LOS B A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 90Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.88Intersection Signal Delay: 15.2 Intersection LOS: BIntersection Capacity Utilization 93.0% ICU Level of Service FAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 8PM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1115 897 127v/c Ratio 0.88 0.69 0.45Control Delay 19.7 8.5 23.9Queue Delay 0.0 0.0 0.0Total Delay 19.7 8.5 23.9Queue Length 50th (m) 73.6 40.2 10.6Queue Length 95th (m) #191.6 m64.9 m21.8Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 1264 1298 587Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.88 0.69 0.22
Intersection Summary# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.m Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 9PM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 33 993 695 131 94 23Future Volume (vph) 33 993 695 131 94 23Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 1.00 1.00 1.00Frt 1.00 0.98 0.97Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 1880 1843 1763Flt Permitted 0.96 1.00 0.96Satd. Flow (perm) 1807 1843 1763Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 36 1079 755 142 102 25RTOR Reduction (vph) 0 0 7 0 19 0Lane Group Flow (vph) 0 1115 890 0 108 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 42.0 42.0 9.0Effective Green, g (s) 42.0 42.0 9.0Actuated g/C Ratio 0.70 0.70 0.15Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 1264 1290 264v/s Ratio Prot 0.48 c0.06v/s Ratio Perm c0.62v/c Ratio 0.88 0.69 0.41Uniform Delay, d1 7.1 5.2 23.1Progression Factor 1.00 1.10 1.01Incremental Delay, d2 9.1 1.4 1.0Delay (s) 16.2 7.2 24.3Level of Service B A CApproach Delay (s) 16.2 7.2 24.3Approach LOS B A C
Intersection SummaryHCM 2000 Control Delay 12.9 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.80Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 93.0% ICU Level of Service FAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 10PM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 41 1046 798 148Future Volume (vph) 41 1046 798 148Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 39.7 39.7 11.3Actuated g/C Ratio 0.66 0.66 0.19v/c Ratio 1.42 0.89 0.56Control Delay 208.7 22.0 25.6Queue Delay 0.0 0.0 0.0Total Delay 208.7 22.0 25.6LOS F C CApproach Delay 208.7 22.0 25.6Approach LOS F C C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 110Control Type: Actuated-CoordinatedMaximum v/c Ratio: 1.42Intersection Signal Delay: 111.8 Intersection LOS: FIntersection Capacity Utilization 105.7% ICU Level of Service GAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 11PM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1182 1090 193v/c Ratio 1.42 0.89 0.56Control Delay 208.7 22.0 25.6Queue Delay 0.0 0.0 0.0Total Delay 208.7 22.0 25.6Queue Length 50th (m) ~179.2 78.1 17.5Queue Length 95th (m) m#232.6 #193.8 31.1Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 834 1223 586Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 1.42 0.89 0.33
Intersection Summary~ Volume exceeds capacity, queue is theoretically infinite. Queue shown is maximum after two cycles.# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.m Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 03-04-2020
Existing + Boyne West Synchro 9 Report, Page 12PM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 41 1046 798 205 148 29Future Volume (vph) 41 1046 798 205 148 29Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 1.00 1.00 1.00Frt 1.00 0.97 0.98Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 1880 1831 1768Flt Permitted 0.67 1.00 0.96Satd. Flow (perm) 1259 1831 1768Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 45 1137 867 223 161 32RTOR Reduction (vph) 0 0 11 0 15 0Lane Group Flow (vph) 0 1182 1079 0 178 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 39.7 39.7 11.3Effective Green, g (s) 39.7 39.7 11.3Actuated g/C Ratio 0.66 0.66 0.19Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 833 1211 332v/s Ratio Prot 0.59 c0.10v/s Ratio Perm c0.94v/c Ratio 1.42 0.89 0.54Uniform Delay, d1 10.1 8.4 22.0Progression Factor 0.84 1.00 1.00Incremental Delay, d2 192.4 10.1 1.7Delay (s) 200.9 18.5 23.7Level of Service F B CApproach Delay (s) 200.9 18.5 23.7Approach LOS F B C
Intersection SummaryHCM 2000 Control Delay 106.4 HCM 2000 Level of Service FHCM 2000 Volume to Capacity ratio 1.22Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 105.7% ICU Level of Service GAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis1: Tremaine Rd & Collector "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 1AM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 268 875 390 0 1211Future Volume (Veh/h) 0 268 875 390 0 1211Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 291 951 424 0 1316PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1602 529 1375vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1602 529 1375tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 41 100cM capacity (veh/h) 97 494 495
Direction, Lane # WB 1 NB 1 NB 2 NB 3 SB 1 SB 2 SB 3Volume Total 291 380 380 614 439 439 439Volume Left 0 0 0 0 0 0 0Volume Right 291 0 0 424 0 0 0cSH 494 1700 1700 1700 1700 1700 1700Volume to Capacity 0.59 0.22 0.22 0.36 0.26 0.26 0.26Queue Length 95th (m) 28.5 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 22.2 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS CApproach Delay (s) 22.2 0.0 0.0Approach LOS C
Intersection SummaryAverage Delay 2.2Intersection Capacity Utilization 48.9% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 2AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 41 231 185 127 243 7 71 50 35 11 43 47Future Volume (Veh/h) 41 231 185 127 243 7 71 50 35 11 43 47Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 45 251 201 138 264 8 77 54 38 12 47 51PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 272 452 1060 990 352 1050 1086 268vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 272 452 1060 990 352 1050 1086 268tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 97 88 43 74 95 91 74 93cM capacity (veh/h) 1291 1109 134 208 692 137 183 771
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 497 410 169 110Volume Left 45 138 77 12Volume Right 201 8 38 51cSH 1291 1109 190 268Volume to Capacity 0.03 0.12 0.89 0.41Queue Length 95th (m) 0.8 3.2 51.3 14.5Control Delay (s) 1.1 3.8 89.5 27.5Lane LOS A A F DApproach Delay (s) 1.1 3.8 89.5 27.5Approach LOS F D
Intersection SummaryAverage Delay 17.1Intersection Capacity Utilization 71.3% ICU Level of Service CAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 3AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 113 0 208 7 1 10 146 82 4 5 46 232Future Volume (Veh/h) 113 0 208 7 1 10 146 82 4 5 46 232Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 123 0 226 8 1 11 159 89 4 5 50 252PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 606 597 176 821 721 91 302 93vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 606 597 176 821 721 91 302 93tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 66 100 74 96 100 99 87 100cM capacity (veh/h) 363 363 867 195 308 967 1259 1501
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 349 20 252 307Volume Left 123 8 159 5Volume Right 226 11 4 252cSH 582 360 1259 1501Volume to Capacity 0.60 0.06 0.13 0.00Queue Length 95th (m) 30.0 1.3 3.3 0.1Control Delay (s) 20.0 15.6 5.6 0.2Lane LOS C C A AApproach Delay (s) 20.0 15.6 5.6 0.2Approach LOS C C
Intersection SummaryAverage Delay 9.4Intersection Capacity Utilization 63.5% ICU Level of Service BAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis4: Tremaine Rd & Street "B" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 4AM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 47 1163 59 0 1264Future Volume (Veh/h) 0 47 1163 59 0 1264Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 51 1264 64 0 1374PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1722 421 1328vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1722 421 1328tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 91 100cM capacity (veh/h) 80 581 516
Direction, Lane # WB 1 NB 1 NB 2 NB 3 NB 4 SB 1 SB 2 SB 3Volume Total 51 421 421 421 64 458 458 458Volume Left 0 0 0 0 0 0 0 0Volume Right 51 0 0 0 64 0 0 0cSH 581 1700 1700 1700 1700 1700 1700 1700Volume to Capacity 0.09 0.25 0.25 0.25 0.04 0.27 0.27 0.27Queue Length 95th (m) 2.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 11.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 11.8 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 0.2Intersection Capacity Utilization 32.5% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 5AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 0 0 33 3 0 3 1 63 1 34 239 43Future Volume (Veh/h) 0 0 33 3 0 3 1 63 1 34 239 43Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 0 36 3 0 3 1 68 1 37 260 47PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 431 428 284 464 452 68 307 69vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 431 428 284 464 452 68 307 69tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 100 100 95 99 100 100 100 98cM capacity (veh/h) 523 506 755 475 491 995 1254 1532
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 36 6 70 344Volume Left 0 3 1 37Volume Right 36 3 1 47cSH 755 643 1254 1532Volume to Capacity 0.05 0.01 0.00 0.02Queue Length 95th (m) 1.1 0.2 0.0 0.6Control Delay (s) 10.0 10.7 0.1 1.0Lane LOS B B A AApproach Delay (s) 10.0 10.7 0.1 1.0Approach LOS B B
Intersection SummaryAverage Delay 1.7Intersection Capacity Utilization 33.7% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 6AM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 39 0 11 0 0 0 3 158 0 0 264 5Future Volume (Veh/h) 39 0 11 0 0 0 3 158 0 0 264 5Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 42 0 12 0 0 0 3 172 0 0 287 5PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 468 468 290 480 470 172 292 172vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 468 468 290 480 470 172 292 172tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 92 100 98 100 100 100 100 100cM capacity (veh/h) 505 492 750 488 490 872 1270 1405
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 54 0 175 292Volume Left 42 0 3 0Volume Right 12 0 0 5cSH 544 1700 1270 1405Volume to Capacity 0.10 0.00 0.00 0.00Queue Length 95th (m) 2.5 0.0 0.1 0.0Control Delay (s) 12.3 0.0 0.2 0.0Lane LOS B A AApproach Delay (s) 12.3 0.0 0.2 0.0Approach LOS B A
Intersection SummaryAverage Delay 1.3Intersection Capacity Utilization 24.2% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 7AM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 18 554 769 166Future Volume (vph) 18 554 769 166Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 37.2 37.2 13.8Actuated g/C Ratio 0.62 0.62 0.23v/c Ratio 0.22 0.28 0.67Control Delay 6.0 6.3 22.9Queue Delay 0.0 0.0 0.0Total Delay 6.0 6.3 22.9LOS A A CApproach Delay 6.0 6.3 22.9Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.67Intersection Signal Delay: 9.0 Intersection LOS: AIntersection Capacity Utilization 47.4% ICU Level of Service AAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 8AM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 622 883 303v/c Ratio 0.22 0.28 0.67Control Delay 6.0 6.3 22.9Queue Delay 0.0 0.0 0.0Total Delay 6.0 6.3 22.9Queue Length 50th (m) 9.3 11.9 22.3Queue Length 95th (m) 18.4 22.3 35.9Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 2884 3169 746Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.22 0.28 0.41
Intersection Summary
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 9AM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 18 554 769 43 166 113Future Volume (vph) 18 554 769 43 166 113Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.99 0.95Flt Protected 1.00 1.00 0.97Satd. Flow (prot) 5134 5101 1729Flt Permitted 0.91 1.00 0.97Satd. Flow (perm) 4655 5101 1729Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 20 602 836 47 180 123RTOR Reduction (vph) 0 0 7 0 53 0Lane Group Flow (vph) 0 622 876 0 250 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 37.2 37.2 13.8Effective Green, g (s) 37.2 37.2 13.8Actuated g/C Ratio 0.62 0.62 0.23Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2886 3162 397v/s Ratio Prot c0.17 c0.14v/s Ratio Perm 0.13v/c Ratio 0.22 0.28 0.63Uniform Delay, d1 5.0 5.2 20.8Progression Factor 1.00 1.03 1.00Incremental Delay, d2 0.2 0.2 3.1Delay (s) 5.2 5.6 23.8Level of Service A A CApproach Delay (s) 5.2 5.6 23.8Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 8.5 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.37Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 47.4% ICU Level of Service AAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 10AM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 3 717 805 277Future Volume (vph) 3 717 805 277Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MaxAct Effct Green (s) 26.5 26.5 24.5Actuated g/C Ratio 0.44 0.44 0.41v/c Ratio 0.37 0.46 0.42Control Delay 8.7 11.5 14.8Queue Delay 0.0 0.0 0.0Total Delay 8.7 11.5 14.8LOS A B BApproach Delay 8.7 11.5 14.8Approach LOS A B B
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.46Intersection Signal Delay: 11.0 Intersection LOS: BIntersection Capacity Utilization 42.2% ICU Level of Service AAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 11AM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 782 1039 309v/c Ratio 0.37 0.46 0.42Control Delay 8.7 11.5 14.8Queue Delay 0.0 0.0 0.0Total Delay 8.7 11.5 14.8Queue Length 50th (m) 15.0 25.2 23.0Queue Length 95th (m) 18.2 34.6 40.6Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 2127 2261 733Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.37 0.46 0.42
Intersection Summary
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 12AM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 3 717 805 151 277 7Future Volume (vph) 3 717 805 151 277 7Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.98 1.00Flt Protected 1.00 1.00 0.95Satd. Flow (prot) 5141 5020 1790Flt Permitted 0.94 1.00 0.95Satd. Flow (perm) 4816 5020 1790Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 3 779 875 164 301 8RTOR Reduction (vph) 0 0 45 0 2 0Lane Group Flow (vph) 0 782 994 0 307 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 26.5 26.5 24.5Effective Green, g (s) 26.5 26.5 24.5Actuated g/C Ratio 0.44 0.44 0.41Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2127 2217 730v/s Ratio Prot c0.20 c0.17v/s Ratio Perm 0.16v/c Ratio 0.37 0.45 0.42Uniform Delay, d1 11.2 11.7 12.7Progression Factor 0.73 1.00 1.00Incremental Delay, d2 0.5 0.7 1.8Delay (s) 8.6 12.3 14.5Level of Service A B BApproach Delay (s) 8.6 12.3 14.5Approach LOS A B B
Intersection SummaryHCM 2000 Control Delay 11.3 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.43Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 42.2% ICU Level of Service AAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis1: Tremaine Road & Collector "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 1PM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 171 1006 477 0 779Future Volume (Veh/h) 0 171 1006 477 0 779Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 186 1093 518 0 847PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1634 623 1611vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1634 623 1611tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 57 100cM capacity (veh/h) 92 429 401
Direction, Lane # WB 1 NB 1 NB 2 NB 3 SB 1 SB 2 SB 3Volume Total 186 437 437 737 282 282 282Volume Left 0 0 0 0 0 0 0Volume Right 186 0 0 518 0 0 0cSH 429 1700 1700 1700 1700 1700 1700Volume to Capacity 0.43 0.26 0.26 0.43 0.17 0.17 0.17Queue Length 95th (m) 16.3 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 19.7 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS CApproach Delay (s) 19.7 0.0 0.0Approach LOS C
Intersection SummaryAverage Delay 1.4Intersection Capacity Utilization 47.4% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 2PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 49 199 138 75 224 15 58 42 30 26 37 51Future Volume (Veh/h) 49 199 138 75 224 15 58 42 30 26 37 51Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 53 216 150 82 243 16 63 46 33 28 40 55PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 259 366 887 820 291 868 887 251vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 259 366 887 820 291 868 887 251tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 96 93 68 83 96 87 84 93cM capacity (veh/h) 1306 1193 199 277 748 209 253 788
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 419 341 142 123Volume Left 53 82 63 28Volume Right 150 16 33 55cSH 1306 1193 270 340Volume to Capacity 0.04 0.07 0.53 0.36Queue Length 95th (m) 1.0 1.7 21.5 12.2Control Delay (s) 1.4 2.5 32.3 21.5Lane LOS A A D CApproach Delay (s) 1.4 2.5 32.3 21.5Approach LOS D C
Intersection SummaryAverage Delay 8.4Intersection Capacity Utilization 49.0% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 3PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 104 14 143 10 12 14 124 90 15 14 74 216Future Volume (Veh/h) 104 14 143 10 12 14 124 90 15 14 74 216Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 113 15 155 11 13 15 135 98 16 15 80 235PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 625 612 198 766 721 106 315 114vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 625 612 198 766 721 106 315 114tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 67 96 82 95 96 98 89 99cM capacity (veh/h) 345 360 844 230 312 948 1245 1475
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 283 39 249 330Volume Left 113 11 135 15Volume Right 155 15 16 235cSH 512 370 1245 1475Volume to Capacity 0.55 0.11 0.11 0.01Queue Length 95th (m) 25.3 2.7 2.8 0.2Control Delay (s) 20.4 15.9 4.9 0.4Lane LOS C C A AApproach Delay (s) 20.4 15.9 4.9 0.4Approach LOS C C
Intersection SummaryAverage Delay 8.6Intersection Capacity Utilization 62.4% ICU Level of Service BAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis4: Tremaine Road & Street "B" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 4PM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 16 1184 149 0 932Future Volume (Veh/h) 0 16 1184 149 0 932Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 17 1287 162 0 1013PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1625 429 1449vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1625 429 1449tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 97 100cM capacity (veh/h) 93 574 463
Direction, Lane # WB 1 NB 1 NB 2 NB 3 NB 4 SB 1 SB 2 SB 3Volume Total 17 429 429 429 162 338 338 338Volume Left 0 0 0 0 0 0 0 0Volume Right 17 0 0 0 162 0 0 0cSH 574 1700 1700 1700 1700 1700 1700 1700Volume to Capacity 0.03 0.25 0.25 0.25 0.10 0.20 0.20 0.20Queue Length 95th (m) 0.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 11.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 11.5 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 0.1Intersection Capacity Utilization 32.9% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 5PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 3 0 2 2 1 4 3 87 2 13 163 13Future Volume (Veh/h) 3 0 2 2 1 4 3 87 2 13 163 13Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 3 0 2 2 1 4 3 95 2 14 177 14PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 318 315 184 316 321 96 191 97vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 318 315 184 316 321 96 191 97tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 100 100 100 100 100 100 100 99cM capacity (veh/h) 625 594 858 630 589 960 1383 1496
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 5 7 100 205Volume Left 3 2 3 14Volume Right 2 4 2 14cSH 701 774 1383 1496Volume to Capacity 0.01 0.01 0.00 0.01Queue Length 95th (m) 0.2 0.2 0.0 0.2Control Delay (s) 10.2 9.7 0.2 0.6Lane LOS B A A AApproach Delay (s) 10.2 9.7 0.2 0.6Approach LOS B A
Intersection SummaryAverage Delay 0.8Intersection Capacity Utilization 25.0% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 6PM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 19 0 7 0 0 0 9 198 0 0 185 10Future Volume (Veh/h) 19 0 7 0 0 0 9 198 0 0 185 10Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 21 0 8 0 0 0 10 215 0 0 201 11PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 442 442 206 450 447 215 212 215vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 442 442 206 450 447 215 212 215tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 96 100 99 100 100 100 99 100cM capacity (veh/h) 523 506 834 512 503 825 1358 1355
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 29 0 225 212Volume Left 21 0 10 0Volume Right 8 0 0 11cSH 583 1700 1358 1355Volume to Capacity 0.05 0.00 0.01 0.00Queue Length 95th (m) 1.2 0.0 0.2 0.0Control Delay (s) 11.5 0.0 0.4 0.0Lane LOS B A AApproach Delay (s) 11.5 0.0 0.4 0.0Approach LOS B A
Intersection SummaryAverage Delay 0.9Intersection Capacity Utilization 27.7% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 7PM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 21 980 668 88Future Volume (vph) 21 980 668 88Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 41.8 41.8 9.2Actuated g/C Ratio 0.70 0.70 0.15v/c Ratio 0.33 0.22 0.53Control Delay 4.3 3.4 19.4Queue Delay 0.0 0.0 0.0Total Delay 4.3 3.4 19.4LOS A A BApproach Delay 4.3 3.4 19.4Approach LOS A A B
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.53Intersection Signal Delay: 5.3 Intersection LOS: AIntersection Capacity Utilization 50.7% ICU Level of Service AAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 8PM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1088 792 174v/c Ratio 0.33 0.22 0.53Control Delay 4.3 3.4 19.4Queue Delay 0.0 0.0 0.0Total Delay 4.3 3.4 19.4Queue Length 50th (m) 13.0 8.3 9.8Queue Length 95th (m) 24.6 13.8 21.9Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 3281 3543 607Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.33 0.22 0.29
Intersection Summary
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 9PM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 21 980 668 61 88 72Future Volume (vph) 21 980 668 61 88 72Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.99 0.94Flt Protected 1.00 1.00 0.97Satd. Flow (prot) 5136 5078 1722Flt Permitted 0.92 1.00 0.97Satd. Flow (perm) 4715 5078 1722Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 23 1065 726 66 96 78RTOR Reduction (vph) 0 0 11 0 61 0Lane Group Flow (vph) 0 1088 781 0 113 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 41.8 41.8 9.2Effective Green, g (s) 41.8 41.8 9.2Actuated g/C Ratio 0.70 0.70 0.15Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 3284 3537 264v/s Ratio Prot 0.15 c0.07v/s Ratio Perm c0.23v/c Ratio 0.33 0.22 0.43Uniform Delay, d1 3.6 3.3 23.0Progression Factor 1.00 0.93 0.97Incremental Delay, d2 0.3 0.1 1.1Delay (s) 3.9 3.2 23.5Level of Service A A CApproach Delay (s) 3.9 3.2 23.5Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 5.3 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.35Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 50.7% ICU Level of Service AAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 10PM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 8 1060 724 182Future Volume (vph) 8 1060 724 182Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 39.0 39.0 12.0Actuated g/C Ratio 0.65 0.65 0.20v/c Ratio 0.37 0.30 0.57Control Delay 4.7 4.4 27.1Queue Delay 0.0 0.0 0.0Total Delay 4.7 4.4 27.1LOS A A CApproach Delay 4.7 4.4 27.1Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.57Intersection Signal Delay: 6.5 Intersection LOS: AIntersection Capacity Utilization 43.9% ICU Level of Service AAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 11PM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1161 997 203v/c Ratio 0.37 0.30 0.57Control Delay 4.7 4.4 27.1Queue Delay 0.0 0.0 0.0Total Delay 4.7 4.4 27.1Queue Length 50th (m) 15.1 11.5 20.1Queue Length 95th (m) 19.8 21.0 33.8Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 3116 3295 583Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.37 0.30 0.35
Intersection Summary
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 03-04-2020
Future Background 2024 Synchro 9 Report, Page 12PM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 8 1060 724 193 182 5Future Volume (vph) 8 1060 724 193 182 5Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.97 1.00Flt Protected 1.00 1.00 0.95Satd. Flow (prot) 5140 4979 1790Flt Permitted 0.93 1.00 0.95Satd. Flow (perm) 4793 4979 1790Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 9 1152 787 210 198 5RTOR Reduction (vph) 0 0 59 0 2 0Lane Group Flow (vph) 0 1161 938 0 201 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 39.0 39.0 12.0Effective Green, g (s) 39.0 39.0 12.0Actuated g/C Ratio 0.65 0.65 0.20Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 3115 3236 358v/s Ratio Prot 0.19 c0.11v/s Ratio Perm c0.24v/c Ratio 0.37 0.29 0.56Uniform Delay, d1 4.8 4.5 21.6Progression Factor 0.80 1.00 1.00Incremental Delay, d2 0.3 0.2 2.0Delay (s) 4.2 4.8 23.7Level of Service A A CApproach Delay (s) 4.2 4.8 23.7Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 6.1 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.42Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 43.9% ICU Level of Service AAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis1: Tremaine Rd & Collector "A" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 268 1017 390 0 1257Future Volume (Veh/h) 0 268 1017 390 0 1257Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 291 1105 424 0 1366PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1772 580 1529vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1772 580 1529tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 36 100cM capacity (veh/h) 74 457 432
Direction, Lane # WB 1 NB 1 NB 2 NB 3 SB 1 SB 2 SB 3Volume Total 291 442 442 645 455 455 455Volume Left 0 0 0 0 0 0 0Volume Right 291 0 0 424 0 0 0cSH 457 1700 1700 1700 1700 1700 1700Volume to Capacity 0.64 0.26 0.26 0.38 0.27 0.27 0.27Queue Length 95th (m) 33.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 25.6 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS DApproach Delay (s) 25.6 0.0 0.0Approach LOS D
Intersection SummaryAverage Delay 2.3Intersection Capacity Utilization 51.6% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 41 231 185 127 243 7 71 50 35 11 43 47Future Volume (Veh/h) 41 231 185 127 243 7 71 50 35 11 43 47Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 45 251 201 138 264 8 77 54 38 12 47 51PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 272 452 1060 990 352 1050 1086 268vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 272 452 1060 990 352 1050 1086 268tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 97 88 43 74 95 91 74 93cM capacity (veh/h) 1291 1109 134 208 692 137 183 771
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 497 410 169 110Volume Left 45 138 77 12Volume Right 201 8 38 51cSH 1291 1109 190 268Volume to Capacity 0.03 0.12 0.89 0.41Queue Length 95th (m) 0.8 3.2 51.3 14.5Control Delay (s) 1.1 3.8 89.5 27.5Lane LOS A A F DApproach Delay (s) 1.1 3.8 89.5 27.5Approach LOS F D
Intersection SummaryAverage Delay 17.1Intersection Capacity Utilization 71.3% ICU Level of Service CAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 113 0 208 7 1 10 146 82 4 5 46 232Future Volume (Veh/h) 113 0 208 7 1 10 146 82 4 5 46 232Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 123 0 226 8 1 11 159 89 4 5 50 252PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 606 597 176 821 721 91 302 93vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 606 597 176 821 721 91 302 93tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 66 100 74 96 100 99 87 100cM capacity (veh/h) 363 363 867 195 308 967 1259 1501
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 349 20 252 307Volume Left 123 8 159 5Volume Right 226 11 4 252cSH 582 360 1259 1501Volume to Capacity 0.60 0.06 0.13 0.00Queue Length 95th (m) 30.0 1.3 3.3 0.1Control Delay (s) 20.0 15.6 5.6 0.2Lane LOS C C A AApproach Delay (s) 20.0 15.6 5.6 0.2Approach LOS C C
Intersection SummaryAverage Delay 9.4Intersection Capacity Utilization 63.5% ICU Level of Service BAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis4: Tremaine Rd & Street "B" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 189 1163 68 0 1310Future Volume (Veh/h) 0 189 1163 68 0 1310Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 205 1264 74 0 1424PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1739 421 1338vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1739 421 1338tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 65 100cM capacity (veh/h) 78 581 511
Direction, Lane # WB 1 NB 1 NB 2 NB 3 NB 4 SB 1 SB 2 SB 3Volume Total 205 421 421 421 74 475 475 475Volume Left 0 0 0 0 0 0 0 0Volume Right 205 0 0 0 74 0 0 0cSH 581 1700 1700 1700 1700 1700 1700 1700Volume to Capacity 0.35 0.25 0.25 0.25 0.04 0.28 0.28 0.28Queue Length 95th (m) 12.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 14.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 14.5 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 1.0Intersection Capacity Utilization 40.8% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 0 10 64 3 79 3 73 63 1 34 270 43Future Volume (Veh/h) 0 10 64 3 79 3 73 63 1 34 270 43Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 11 70 3 86 3 79 68 1 37 293 47PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 663 618 316 692 640 68 340 69vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 663 618 316 692 640 68 340 69tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 100 97 90 99 76 100 94 98cM capacity (veh/h) 285 370 724 295 359 995 1219 1532
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 81 92 148 377Volume Left 0 3 79 37Volume Right 70 3 1 47cSH 641 364 1219 1532Volume to Capacity 0.13 0.25 0.06 0.02Queue Length 95th (m) 3.3 7.5 1.6 0.6Control Delay (s) 11.4 18.2 4.6 0.9Lane LOS B C A AApproach Delay (s) 11.4 18.2 4.6 0.9Approach LOS B C
Intersection SummaryAverage Delay 5.2Intersection Capacity Utilization 39.2% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 39 0 21 20 11 0 45 194 6 0 357 39Future Volume (Veh/h) 39 0 21 20 11 0 45 194 6 0 357 39Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 42 0 23 22 12 0 49 211 7 0 388 42PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 728 725 409 744 742 214 430 218vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 728 725 409 744 742 214 430 218tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 87 100 96 93 96 100 96 100cM capacity (veh/h) 319 336 642 308 329 825 1129 1352
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 65 34 267 430Volume Left 42 22 49 0Volume Right 23 0 7 42cSH 388 315 1129 1352Volume to Capacity 0.17 0.11 0.04 0.00Queue Length 95th (m) 4.5 2.7 1.0 0.0Control Delay (s) 16.1 17.8 1.9 0.0Lane LOS C C AApproach Delay (s) 16.1 17.8 1.9 0.0Approach LOS C C
Intersection SummaryAverage Delay 2.7Intersection Capacity Utilization 48.3% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 50 587 812 248Future Volume (vph) 50 587 812 248Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 32.6 32.6 18.4Actuated g/C Ratio 0.54 0.54 0.31v/c Ratio 0.30 0.35 0.76Control Delay 8.9 8.2 23.9Queue Delay 0.0 0.0 0.0Total Delay 8.9 8.2 23.9LOS A A CApproach Delay 8.9 8.2 23.9Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.76Intersection Signal Delay: 11.7 Intersection LOS: BIntersection Capacity Utilization 64.1% ICU Level of Service CAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 692 958 438v/c Ratio 0.30 0.35 0.76Control Delay 8.9 8.2 23.9Queue Delay 0.0 0.0 0.0Total Delay 8.9 8.2 23.9Queue Length 50th (m) 13.9 12.8 34.1Queue Length 95th (m) 25.2 25.6 50.6Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 2303 2771 744Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.30 0.35 0.59
Intersection Summary
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 50 587 812 69 248 155Future Volume (vph) 50 587 812 69 248 155Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.99 0.95Flt Protected 1.00 1.00 0.97Satd. Flow (prot) 5122 5081 1733Flt Permitted 0.83 1.00 0.97Satd. Flow (perm) 4244 5081 1733Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 54 638 883 75 270 168RTOR Reduction (vph) 0 0 13 0 44 0Lane Group Flow (vph) 0 692 945 0 394 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 32.6 32.6 18.4Effective Green, g (s) 32.6 32.6 18.4Actuated g/C Ratio 0.54 0.54 0.31Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2305 2760 531v/s Ratio Prot c0.19 c0.23v/s Ratio Perm 0.16v/c Ratio 0.30 0.34 0.74Uniform Delay, d1 7.5 7.7 18.7Progression Factor 1.00 0.94 0.96Incremental Delay, d2 0.3 0.3 5.6Delay (s) 7.8 7.5 23.6Level of Service A A CApproach Delay (s) 7.8 7.5 23.6Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 11.0 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.49Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 64.1% ICU Level of Service CAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 35 800 832 442Future Volume (vph) 35 800 832 442Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 29.5 29.5 21.5Actuated g/C Ratio 0.49 0.49 0.36v/c Ratio 0.42 0.45 0.83Control Delay 7.8 10.0 29.1Queue Delay 0.0 0.0 0.0Total Delay 7.8 10.0 29.1LOS A A CApproach Delay 7.8 10.0 29.1Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.83Intersection Signal Delay: 13.2 Intersection LOS: BIntersection Capacity Utilization 75.5% ICU Level of Service DAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 908 1126 533v/c Ratio 0.42 0.45 0.83Control Delay 7.8 10.0 29.1Queue Delay 0.0 0.0 0.0Total Delay 7.8 10.0 29.1Queue Length 50th (m) 16.5 25.1 48.7Queue Length 95th (m) 21.9 36.8 #80.8Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 2175 2518 732Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.42 0.45 0.73
Intersection Summary# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 04/06/2020
Future Total - 2024 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 35 800 832 204 442 49Future Volume (vph) 35 800 832 204 442 49Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.97 0.99Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 5131 4990 1778Flt Permitted 0.86 1.00 0.96Satd. Flow (perm) 4423 4990 1778Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 38 870 904 222 480 53RTOR Reduction (vph) 0 0 64 0 7 0Lane Group Flow (vph) 0 908 1062 0 526 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 29.5 29.5 21.5Effective Green, g (s) 29.5 29.5 21.5Actuated g/C Ratio 0.49 0.49 0.36Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2174 2453 637v/s Ratio Prot c0.21 c0.30v/s Ratio Perm 0.21v/c Ratio 0.42 0.43 0.83Uniform Delay, d1 9.8 9.8 17.5Progression Factor 0.69 1.00 1.00Incremental Delay, d2 0.6 0.6 8.6Delay (s) 7.3 10.4 26.1Level of Service A B CApproach Delay (s) 7.3 10.4 26.1Approach LOS A B C
Intersection SummaryHCM 2000 Control Delay 12.6 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.60Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 75.5% ICU Level of Service DAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis1: Tremaine Road & Collector "A" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 171 1096 477 0 932Future Volume (Veh/h) 0 171 1096 477 0 932Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 186 1191 518 0 1013PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1788 656 1709vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1788 656 1709tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 54 100cM capacity (veh/h) 72 408 368
Direction, Lane # WB 1 NB 1 NB 2 NB 3 SB 1 SB 2 SB 3Volume Total 186 476 476 756 338 338 338Volume Left 0 0 0 0 0 0 0Volume Right 186 0 0 518 0 0 0cSH 408 1700 1700 1700 1700 1700 1700Volume to Capacity 0.46 0.28 0.28 0.44 0.20 0.20 0.20Queue Length 95th (m) 17.6 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 21.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS CApproach Delay (s) 21.0 0.0 0.0Approach LOS C
Intersection SummaryAverage Delay 1.3Intersection Capacity Utilization 49.1% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 49 199 157 75 224 15 58 42 30 26 37 51Future Volume (Veh/h) 49 199 157 75 224 15 58 42 30 26 37 51Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 53 216 171 82 243 16 63 46 33 28 40 55PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 259 387 898 830 302 878 908 251vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 259 387 898 830 302 878 908 251tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 96 93 68 83 96 86 84 93cM capacity (veh/h) 1306 1171 195 273 738 205 246 788
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 440 341 142 123Volume Left 53 82 63 28Volume Right 171 16 33 55cSH 1306 1171 265 333Volume to Capacity 0.04 0.07 0.54 0.37Queue Length 95th (m) 1.0 1.7 22.2 12.6Control Delay (s) 1.3 2.5 33.3 22.0Lane LOS A A D CApproach Delay (s) 1.3 2.5 33.3 22.0Approach LOS D C
Intersection SummaryAverage Delay 8.5Intersection Capacity Utilization 49.5% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 104 14 143 10 12 14 124 90 15 14 74 216Future Volume (Veh/h) 104 14 143 10 12 14 124 90 15 14 74 216Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 113 15 155 11 13 15 135 98 16 15 80 235PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 625 612 198 766 721 106 315 114vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 625 612 198 766 721 106 315 114tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 67 96 82 95 96 98 89 99cM capacity (veh/h) 345 360 844 230 312 948 1245 1475
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 283 39 249 330Volume Left 113 11 135 15Volume Right 155 15 16 235cSH 512 370 1245 1475Volume to Capacity 0.55 0.11 0.11 0.01Queue Length 95th (m) 25.3 2.7 2.8 0.2Control Delay (s) 20.4 15.9 4.9 0.4Lane LOS C C A AApproach Delay (s) 20.4 15.9 4.9 0.4Approach LOS C C
Intersection SummaryAverage Delay 8.6Intersection Capacity Utilization 62.4% ICU Level of Service BAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis4: Tremaine Road & Street "B" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (veh/h) 0 106 1184 179 0 1085Future Volume (Veh/h) 0 106 1184 179 0 1085Sign Control Stop Free FreeGrade 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 115 1287 195 0 1179PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 1680 429 1482vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 1680 429 1482tC, single (s) 6.8 6.9 4.1tC, 2 stage (s)tF (s) 3.5 3.3 2.2p0 queue free % 100 80 100cM capacity (veh/h) 86 574 450
Direction, Lane # WB 1 NB 1 NB 2 NB 3 NB 4 SB 1 SB 2 SB 3Volume Total 115 429 429 429 195 393 393 393Volume Left 0 0 0 0 0 0 0 0Volume Right 115 0 0 0 195 0 0 0cSH 574 1700 1700 1700 1700 1700 1700 1700Volume to Capacity 0.20 0.25 0.25 0.25 0.11 0.23 0.23 0.23Queue Length 95th (m) 5.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0Control Delay (s) 12.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0Lane LOS BApproach Delay (s) 12.8 0.0 0.0Approach LOS B
Intersection SummaryAverage Delay 0.5Intersection Capacity Utilization 36.1% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 3 6 39 2 44 4 127 87 2 13 201 13Future Volume (Veh/h) 3 6 39 2 44 4 127 87 2 13 201 13Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 3 7 42 2 48 4 138 95 2 14 218 14PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 653 626 225 670 632 96 232 97vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 653 626 225 670 632 96 232 97tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 99 98 95 99 86 100 90 99cM capacity (veh/h) 311 356 814 316 353 960 1336 1496
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 52 54 235 246Volume Left 3 2 138 14Volume Right 42 4 2 14cSH 643 369 1336 1496Volume to Capacity 0.08 0.15 0.10 0.01Queue Length 95th (m) 2.0 3.9 2.6 0.2Control Delay (s) 11.1 16.4 5.1 0.5Lane LOS B C A AApproach Delay (s) 11.1 16.4 5.1 0.5Approach LOS B C
Intersection SummaryAverage Delay 4.7Intersection Capacity Utilization 37.8% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 19 0 13 13 7 0 30 325 14 0 244 31Future Volume (Veh/h) 19 0 13 13 7 0 30 325 14 0 244 31Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 21 0 14 14 8 0 33 353 15 0 265 34PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 712 716 282 722 726 360 299 368vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 712 716 282 722 726 360 299 368tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 94 100 98 96 98 100 97 100cM capacity (veh/h) 334 346 757 329 342 684 1262 1191
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 35 22 401 299Volume Left 21 14 33 0Volume Right 14 0 15 34cSH 430 334 1262 1191Volume to Capacity 0.08 0.07 0.03 0.00Queue Length 95th (m) 2.0 1.6 0.6 0.0Control Delay (s) 14.1 16.6 0.9 0.0Lane LOS B C AApproach Delay (s) 14.1 16.6 0.9 0.0Approach LOS B C
Intersection SummaryAverage Delay 1.6Intersection Capacity Utilization 47.7% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 128 1075 695 165Future Volume (vph) 128 1075 695 165Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 37.3 37.3 13.7Actuated g/C Ratio 0.62 0.62 0.23v/c Ratio 0.55 0.29 0.68Control Delay 8.4 4.4 23.8Queue Delay 0.0 0.0 0.0Total Delay 8.4 4.4 23.8LOS A A CApproach Delay 8.4 4.4 23.8Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 50Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.68Intersection Signal Delay: 8.8 Intersection LOS: AIntersection Capacity Utilization 67.2% ICU Level of Service CAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1307 917 299v/c Ratio 0.55 0.29 0.68Control Delay 8.4 4.4 23.8Queue Delay 0.0 0.0 0.0Total Delay 8.4 4.4 23.8Queue Length 50th (m) 25.7 10.5 22.8Queue Length 95th (m) 47.3 14.8 37.7Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 2395 3156 602Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.55 0.29 0.50
Intersection Summary
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 128 1075 695 149 165 110Future Volume (vph) 128 1075 695 149 165 110Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.97 0.95Flt Protected 0.99 1.00 0.97Satd. Flow (prot) 5115 5006 1730Flt Permitted 0.75 1.00 0.97Satd. Flow (perm) 3854 5006 1730Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 139 1168 755 162 179 120RTOR Reduction (vph) 0 0 45 0 46 0Lane Group Flow (vph) 0 1307 872 0 253 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 37.3 37.3 13.7Effective Green, g (s) 37.3 37.3 13.7Actuated g/C Ratio 0.62 0.62 0.23Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2395 3112 395v/s Ratio Prot 0.17 c0.15v/s Ratio Perm c0.34v/c Ratio 0.55 0.28 0.64Uniform Delay, d1 6.5 5.2 20.9Progression Factor 1.00 0.80 0.98Incremental Delay, d2 0.9 0.2 3.4Delay (s) 7.4 4.4 24.0Level of Service A A CApproach Delay (s) 7.4 4.4 24.0Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 8.3 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.57Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 67.2% ICU Level of Service CAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 115 1113 812 286Future Volume (vph) 115 1113 812 286Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 35.2 35.2 15.8Actuated g/C Ratio 0.59 0.59 0.26v/c Ratio 0.62 0.43 0.73Control Delay 8.3 6.1 28.4Queue Delay 0.0 0.0 0.0Total Delay 8.3 6.1 28.4LOS A A CApproach Delay 8.3 6.1 28.4Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 55Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.73Intersection Signal Delay: 9.7 Intersection LOS: AIntersection Capacity Utilization 76.8% ICU Level of Service DAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1335 1284 346v/c Ratio 0.62 0.43 0.73Control Delay 8.3 6.1 28.4Queue Delay 0.0 0.0 0.0Total Delay 8.3 6.1 28.4Queue Length 50th (m) 19.8 18.9 32.9Queue Length 95th (m) 38.8 30.8 53.1Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 2166 2990 584Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.62 0.43 0.59
Intersection Summary
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 04/06/2020
Future Total 2024 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 115 1113 812 369 286 32Future Volume (vph) 115 1113 812 369 286 32Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.95 0.99Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 5118 4901 1778Flt Permitted 0.72 1.00 0.96Satd. Flow (perm) 3696 4901 1778Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 125 1210 883 401 311 35RTOR Reduction (vph) 0 0 119 0 7 0Lane Group Flow (vph) 0 1335 1165 0 339 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 35.2 35.2 15.8Effective Green, g (s) 35.2 35.2 15.8Actuated g/C Ratio 0.59 0.59 0.26Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2168 2875 468v/s Ratio Prot 0.24 c0.19v/s Ratio Perm c0.36v/c Ratio 0.62 0.41 0.72Uniform Delay, d1 8.0 6.7 20.1Progression Factor 0.80 1.00 1.00Incremental Delay, d2 1.1 0.4 5.5Delay (s) 7.5 7.1 25.6Level of Service A A CApproach Delay (s) 7.5 7.1 25.6Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 9.5 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.65Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 76.8% ICU Level of Service DAnalysis Period (min) 15c Critical Lane Group
Timings1: Tremaine Rd & Collector "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group WBL NBT SBL SBTLane ConfigurationsTraffic Volume (vph) 74 1071 288 1155Future Volume (vph) 74 1071 288 1155Turn Type Prot NA pm+pt NAProtected Phases 8 2 1 6Permitted Phases 6Detector Phase 8 2 1 6Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 9.5 22.5Total Split (s) 23.0 23.0 14.0 37.0Total Split (%) 38.3% 38.3% 23.3% 61.7%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5 4.5Lead/Lag Lag LeadLead-Lag Optimize? Yes YesRecall Mode Max Max Max MaxAct Effct Green (s) 18.5 18.5 32.5 32.5Actuated g/C Ratio 0.31 0.31 0.54 0.54v/c Ratio 0.52 0.77 0.77 0.45Control Delay 8.2 32.2 25.0 9.0Queue Delay 0.0 0.0 0.0 0.0Total Delay 8.2 32.2 25.0 9.0LOS A C C AApproach Delay 8.2 32.2 12.2Approach LOS A C B
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 45 (75%), Referenced to phase 1:SBL and 6:SBTL, Start of GreenNatural Cycle: 60Control Type: PretimedMaximum v/c Ratio: 0.77Intersection Signal Delay: 19.4 Intersection LOS: BIntersection Capacity Utilization 69.6% ICU Level of Service CAnalysis Period (min) 15
Splits and Phases: 1: Tremaine Rd & Collector "A"
Queues1: Tremaine Rd & Collector "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group WBL NBT SBL SBTLane Group Flow (vph) 371 1216 313 1255v/c Ratio 0.52 0.77 0.77 0.45Control Delay 8.2 32.2 25.0 9.0Queue Delay 0.0 0.0 0.0 0.0Total Delay 8.2 32.2 25.0 9.0Queue Length 50th (m) 8.8 53.3 17.2 27.6Queue Length 95th (m) 29.3 66.2 #50.8 36.4Internal Link Dist (m) 276.2 424.4 874.9Turn Bay Length (m) 15.0Base Capacity (vph) 714 1583 408 2785Starvation Cap Reductn 0 0 0 0Spillback Cap Reductn 0 0 0 0Storage Cap Reductn 0 0 0 0Reduced v/c Ratio 0.52 0.77 0.77 0.45
Intersection Summary# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.
HCM Signalized Intersection Capacity Analysis1: Tremaine Rd & Collector "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (vph) 74 268 1071 48 288 1155Future Volume (vph) 74 268 1071 48 288 1155Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5 4.5Lane Util. Factor 1.00 0.91 1.00 0.91Frt 0.89 0.99 1.00 1.00Flt Protected 0.99 1.00 0.95 1.00Satd. Flow (prot) 1666 5109 1789 5142Flt Permitted 0.99 1.00 0.17 1.00Satd. Flow (perm) 1666 5109 328 5142Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 80 291 1164 52 313 1255RTOR Reduction (vph) 201 0 8 0 0 0Lane Group Flow (vph) 170 0 1208 0 313 1255Turn Type Prot NA pm+pt NAProtected Phases 8 2 1 6Permitted Phases 6Actuated Green, G (s) 18.5 18.5 32.5 32.5Effective Green, g (s) 18.5 18.5 32.5 32.5Actuated g/C Ratio 0.31 0.31 0.54 0.54Clearance Time (s) 4.5 4.5 4.5 4.5Lane Grp Cap (vph) 513 1575 408 2785v/s Ratio Prot c0.10 0.24 c0.12 0.24v/s Ratio Perm c0.29v/c Ratio 0.33 0.77 0.77 0.45Uniform Delay, d1 16.0 18.8 10.2 8.3Progression Factor 1.18 1.52 1.00 1.00Incremental Delay, d2 1.7 3.5 12.9 0.5Delay (s) 20.7 32.1 23.1 8.9Level of Service C C C AApproach Delay (s) 20.7 32.1 11.7Approach LOS C C B
Intersection SummaryHCM 2000 Control Delay 20.6 HCM 2000 Level of Service CHCM 2000 Volume to Capacity ratio 0.64Actuated Cycle Length (s) 60.0 Sum of lost time (s) 13.5Intersection Capacity Utilization 69.6% ICU Level of Service CAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 41 231 141 102 268 7 79 50 35 11 43 47Future Volume (Veh/h) 41 231 141 102 268 7 79 50 35 11 43 47Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 45 251 153 111 291 8 86 54 38 12 47 51PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m) 300pX, platoon unblockedvC, conflicting volume 299 404 1009 938 328 1000 1011 295vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 299 404 1009 938 328 1000 1011 295tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 96 90 44 77 95 92 77 93cM capacity (veh/h) 1262 1155 153 230 714 156 209 744
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 449 410 178 110Volume Left 45 111 86 12Volume Right 153 8 38 51cSH 1262 1155 209 297Volume to Capacity 0.04 0.10 0.85 0.37Queue Length 95th (m) 0.8 2.4 49.1 12.5Control Delay (s) 1.1 3.0 76.7 24.1Lane LOS A A F CApproach Delay (s) 1.1 3.0 76.7 24.1Approach LOS F C
Intersection SummaryAverage Delay 15.7Intersection Capacity Utilization 63.9% ICU Level of Service BAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 113 0 208 7 1 10 146 82 4 5 46 232Future Volume (Veh/h) 113 0 208 7 1 10 146 82 4 5 46 232Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 123 0 226 8 1 11 159 89 4 5 50 252PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 606 597 176 821 721 91 302 93vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 606 597 176 821 721 91 302 93tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 66 100 74 96 100 99 87 100cM capacity (veh/h) 363 363 867 195 308 967 1259 1501
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 349 20 252 307Volume Left 123 8 159 5Volume Right 226 11 4 252cSH 582 360 1259 1501Volume to Capacity 0.60 0.06 0.13 0.00Queue Length 95th (m) 30.0 1.3 3.3 0.1Control Delay (s) 20.0 15.6 5.6 0.2Lane LOS C C A AApproach Delay (s) 20.0 15.6 5.6 0.2Approach LOS C C
Intersection SummaryAverage Delay 9.4Intersection Capacity Utilization 63.5% ICU Level of Service BAnalysis Period (min) 15
Timings4: Tremaine Rd & Street "B" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group WBL NBT NBR SBL SBTLane ConfigurationsTraffic Volume (vph) 10 874 10 25 1204Future Volume (vph) 10 874 10 25 1204Turn Type Prot NA Perm Perm NAProtected Phases 8 2 6Permitted Phases 2 6Detector Phase 8 2 2 6 6Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5 22.5Total Split (s) 24.0 36.0 36.0 36.0 36.0Total Split (%) 40.0% 60.0% 60.0% 60.0% 60.0%Yellow Time (s) 3.5 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode Max Max Max Max MaxAct Effct Green (s) 19.5 31.5 31.5 31.5Actuated g/C Ratio 0.32 0.52 0.52 0.52v/c Ratio 0.36 0.35 0.01 0.55Control Delay 11.1 8.8 4.0 5.3Queue Delay 0.0 0.0 0.0 0.0Total Delay 11.1 8.8 4.0 5.3LOS B A A AApproach Delay 11.1 8.7 5.3Approach LOS B A A
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:NBT and 6:SBTL, Start of GreenNatural Cycle: 45Control Type: PretimedMaximum v/c Ratio: 0.55Intersection Signal Delay: 7.1 Intersection LOS: AIntersection Capacity Utilization 60.8% ICU Level of Service BAnalysis Period (min) 15
Splits and Phases: 4: Tremaine Rd & Street "B"
Queues4: Tremaine Rd & Street "B" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group WBL NBT NBR SBTLane Group Flow (vph) 216 950 11 1336v/c Ratio 0.36 0.35 0.01 0.55Control Delay 11.1 8.8 4.0 5.3Queue Delay 0.0 0.0 0.0 0.0Total Delay 11.1 8.8 4.0 5.3Queue Length 50th (m) 9.6 20.3 0.0 10.9Queue Length 95th (m) m21.3 27.5 1.8 13.8Internal Link Dist (m) 263.3 194.1 424.4Turn Bay Length (m) 15.0Base Capacity (vph) 598 2699 845 2451Starvation Cap Reductn 0 0 0 0Spillback Cap Reductn 0 0 0 0Storage Cap Reductn 0 0 0 0Reduced v/c Ratio 0.36 0.35 0.01 0.55
Intersection Summarym Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis4: Tremaine Rd & Street "B" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (vph) 10 189 874 10 25 1204Future Volume (vph) 10 189 874 10 25 1204Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5 4.5Lane Util. Factor 1.00 0.91 1.00 0.91Frt 0.87 1.00 0.85 1.00Flt Protected 1.00 1.00 1.00 1.00Satd. Flow (prot) 1638 5142 1601 5137Flt Permitted 1.00 1.00 1.00 0.91Satd. Flow (perm) 1638 5142 1601 4670Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 11 205 950 11 27 1309RTOR Reduction (vph) 67 0 0 5 0 0Lane Group Flow (vph) 149 0 950 6 0 1336Turn Type Prot NA Perm Perm NAProtected Phases 8 2 6Permitted Phases 2 6Actuated Green, G (s) 19.5 31.5 31.5 31.5Effective Green, g (s) 19.5 31.5 31.5 31.5Actuated g/C Ratio 0.32 0.52 0.52 0.52Clearance Time (s) 4.5 4.5 4.5 4.5Lane Grp Cap (vph) 532 2699 840 2451v/s Ratio Prot c0.09 0.18v/s Ratio Perm 0.00 c0.29v/c Ratio 0.28 0.35 0.01 0.55Uniform Delay, d1 15.0 8.3 6.8 9.5Progression Factor 1.06 1.00 1.00 0.47Incremental Delay, d2 1.3 0.4 0.0 0.8Delay (s) 17.3 8.7 6.8 5.2Level of Service B A A AApproach Delay (s) 17.3 8.6 5.2Approach LOS B A A
Intersection SummaryHCM 2000 Control Delay 7.6 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.44Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 60.8% ICU Level of Service BAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 0 9 32 3 95 3 76 63 1 34 189 43Future Volume (Veh/h) 0 9 32 3 95 3 76 63 1 34 189 43Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 0 10 35 3 103 3 83 68 1 37 205 47PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 592 538 228 577 560 68 252 69vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 592 538 228 577 560 68 252 69tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 100 98 96 99 74 100 94 98cM capacity (veh/h) 313 411 811 375 399 995 1313 1532
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 45 109 152 289Volume Left 0 3 83 37Volume Right 35 3 1 47cSH 667 405 1313 1532Volume to Capacity 0.07 0.27 0.06 0.02Queue Length 95th (m) 1.6 8.2 1.5 0.6Control Delay (s) 10.8 17.1 4.6 1.1Lane LOS B C A AApproach Delay (s) 10.8 17.1 4.6 1.1Approach LOS B C
Intersection SummaryAverage Delay 5.7Intersection Capacity Utilization 37.2% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 39 0 20 19 13 0 51 189 5 0 351 46Future Volume (Veh/h) 39 0 20 19 13 0 51 189 5 0 351 46Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 42 0 22 21 14 0 55 205 5 0 382 50PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 732 727 407 746 750 208 432 210vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 732 727 407 746 750 208 432 210tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 87 100 97 93 96 100 95 100cM capacity (veh/h) 314 333 644 306 324 833 1128 1361
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 64 35 265 432Volume Left 42 21 55 0Volume Right 22 0 5 50cSH 381 313 1128 1361Volume to Capacity 0.17 0.11 0.05 0.00Queue Length 95th (m) 4.5 2.8 1.2 0.0Control Delay (s) 16.3 17.9 2.1 0.0Lane LOS C C AApproach Delay (s) 16.3 17.9 2.1 0.0Approach LOS C C
Intersection SummaryAverage Delay 2.8Intersection Capacity Utilization 48.6% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 38 634 812 222Future Volume (vph) 38 634 812 222Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 36.0 36.0 15.0Actuated g/C Ratio 0.60 0.60 0.25v/c Ratio 0.28 0.31 0.67Control Delay 6.8 7.0 23.3Queue Delay 0.0 0.0 0.0Total Delay 6.8 7.0 23.3LOS A A CApproach Delay 6.8 7.0 23.3Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.67Intersection Signal Delay: 9.5 Intersection LOS: AIntersection Capacity Utilization 57.6% ICU Level of Service BAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 730 958 308v/c Ratio 0.28 0.31 0.67Control Delay 6.8 7.0 23.3Queue Delay 0.0 0.0 0.0Total Delay 6.8 7.0 23.3Queue Length 50th (m) 12.1 12.3 26.6Queue Length 95th (m) 22.8 25.6 m40.9Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 2650 3059 734Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.28 0.31 0.42
Intersection Summarym Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 38 634 812 69 222 62Future Volume (vph) 38 634 812 69 222 62Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.99 0.97Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 5127 5081 1759Flt Permitted 0.86 1.00 0.96Satd. Flow (perm) 4414 5081 1759Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 41 689 883 75 241 67RTOR Reduction (vph) 0 0 12 0 21 0Lane Group Flow (vph) 0 730 946 0 287 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 36.0 36.0 15.0Effective Green, g (s) 36.0 36.0 15.0Actuated g/C Ratio 0.60 0.60 0.25Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2648 3048 439v/s Ratio Prot c0.19 c0.16v/s Ratio Perm 0.17v/c Ratio 0.28 0.31 0.65Uniform Delay, d1 5.8 5.9 20.2Progression Factor 1.00 1.05 0.90Incremental Delay, d2 0.3 0.2 3.4Delay (s) 6.0 6.4 21.7Level of Service A A CApproach Delay (s) 6.0 6.4 21.7Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 8.6 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.41Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 57.6% ICU Level of Service BAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 23 832 846 442Future Volume (vph) 23 832 846 442Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 31.0 31.0 31.0 29.0Total Split (%) 51.7% 51.7% 51.7% 48.3%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 29.8 29.8 21.2Actuated g/C Ratio 0.50 0.50 0.35v/c Ratio 0.41 0.45 0.82Control Delay 7.7 9.9 28.4Queue Delay 0.0 0.0 0.0Total Delay 7.7 9.9 28.4LOS A A CApproach Delay 7.7 9.9 28.4Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.82Intersection Signal Delay: 12.8 Intersection LOS: BIntersection Capacity Utilization 66.8% ICU Level of Service CAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 929 1142 518v/c Ratio 0.41 0.45 0.82Control Delay 7.7 9.9 28.4Queue Delay 0.0 0.0 0.0Total Delay 7.7 9.9 28.4Queue Length 50th (m) 18.9 25.2 47.9Queue Length 95th (m) 22.3 37.6 75.5Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 2279 2542 732Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.41 0.45 0.71
Intersection Summary
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 04/06/2020
Future Total - 2029 Synchro 10 ReportAM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 23 832 846 204 442 35Future Volume (vph) 23 832 846 204 442 35Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.97 0.99Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 5135 4992 1782Flt Permitted 0.89 1.00 0.96Satd. Flow (perm) 4585 4992 1782Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 25 904 920 222 480 38RTOR Reduction (vph) 0 0 61 0 5 0Lane Group Flow (vph) 0 929 1081 0 513 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 29.8 29.8 21.2Effective Green, g (s) 29.8 29.8 21.2Actuated g/C Ratio 0.50 0.50 0.35Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2277 2479 629v/s Ratio Prot c0.22 c0.29v/s Ratio Perm 0.20v/c Ratio 0.41 0.44 0.82Uniform Delay, d1 9.5 9.7 17.6Progression Factor 0.69 1.00 1.00Incremental Delay, d2 0.5 0.6 8.0Delay (s) 7.1 10.3 25.6Level of Service A B CApproach Delay (s) 7.1 10.3 25.6Approach LOS A B C
Intersection SummaryHCM 2000 Control Delay 12.2 HCM 2000 Level of Service BHCM 2000 Volume to Capacity ratio 0.59Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 66.8% ICU Level of Service CAnalysis Period (min) 15c Critical Lane Group
Timings1: Tremaine Rd & Collector "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group WBL NBT SBL SBTLane ConfigurationsTraffic Volume (vph) 51 1180 297 889Future Volume (vph) 51 1180 297 889Turn Type Prot NA pm+pt NAProtected Phases 8 2 1 6Permitted Phases 6Detector Phase 8 2 1 6Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 9.5 22.5Total Split (s) 23.0 23.0 14.0 37.0Total Split (%) 38.3% 38.3% 23.3% 61.7%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5 4.5Lead/Lag Lag LeadLead-Lag Optimize? Yes YesRecall Mode Max Max Max MaxAct Effct Green (s) 18.5 18.5 32.5 32.5Actuated g/C Ratio 0.31 0.31 0.54 0.54v/c Ratio 0.37 0.84 0.79 0.35Control Delay 7.3 37.3 27.0 8.2Queue Delay 0.0 0.0 0.0 0.0Total Delay 7.3 37.3 27.0 8.2LOS A D C AApproach Delay 7.3 37.3 12.9Approach LOS A D B
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 46 (77%), Referenced to phase 1:SBL and 6:SBTL, Start of GreenNatural Cycle: 60Control Type: PretimedMaximum v/c Ratio: 0.84Intersection Signal Delay: 23.8 Intersection LOS: CIntersection Capacity Utilization 64.8% ICU Level of Service CAnalysis Period (min) 15
Splits and Phases: 1: Tremaine Rd & Collector "A"
Queues1: Tremaine Rd & Collector "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group WBL NBT SBL SBTLane Group Flow (vph) 241 1328 323 966v/c Ratio 0.37 0.84 0.79 0.35Control Delay 7.3 37.3 27.0 8.2Queue Delay 0.0 0.0 0.0 0.0Total Delay 7.3 37.3 27.0 8.2Queue Length 50th (m) 5.6 59.9 17.9 19.7Queue Length 95th (m) 20.1 #75.1 #54.0 26.7Internal Link Dist (m) 276.2 424.4 874.9Turn Bay Length (m) 15.0Base Capacity (vph) 643 1583 408 2785Starvation Cap Reductn 0 0 0 0Spillback Cap Reductn 0 0 0 0Storage Cap Reductn 0 0 0 0Reduced v/c Ratio 0.37 0.84 0.79 0.35
Intersection Summary# 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles.
HCM Signalized Intersection Capacity Analysis1: Tremaine Rd & Collector "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (vph) 51 171 1180 41 297 889Future Volume (vph) 51 171 1180 41 297 889Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5 4.5Lane Util. Factor 1.00 0.91 1.00 0.91Frt 0.90 0.99 1.00 1.00Flt Protected 0.99 1.00 0.95 1.00Satd. Flow (prot) 1668 5116 1789 5142Flt Permitted 0.99 1.00 0.17 1.00Satd. Flow (perm) 1668 5116 328 5142Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 55 186 1283 45 323 966RTOR Reduction (vph) 129 0 6 0 0 0Lane Group Flow (vph) 112 0 1322 0 323 966Turn Type Prot NA pm+pt NAProtected Phases 8 2 1 6Permitted Phases 6Actuated Green, G (s) 18.5 18.5 32.5 32.5Effective Green, g (s) 18.5 18.5 32.5 32.5Actuated g/C Ratio 0.31 0.31 0.54 0.54Clearance Time (s) 4.5 4.5 4.5 4.5Lane Grp Cap (vph) 514 1577 408 2785v/s Ratio Prot c0.07 0.26 c0.13 0.19v/s Ratio Perm c0.30v/c Ratio 0.22 0.84 0.79 0.35Uniform Delay, d1 15.4 19.4 10.6 7.8Progression Factor 1.11 1.64 1.00 1.00Incremental Delay, d2 1.0 5.2 14.5 0.3Delay (s) 18.0 36.8 25.1 8.1Level of Service B D C AApproach Delay (s) 18.0 36.8 12.4Approach LOS B D B
Intersection SummaryHCM 2000 Control Delay 24.2 HCM 2000 Level of Service CHCM 2000 Volume to Capacity ratio 0.61Actuated Cycle Length (s) 60.0 Sum of lost time (s) 13.5Intersection Capacity Utilization 64.8% ICU Level of Service CAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis2: Street "C" & Collector "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 49 199 114 64 235 15 61 42 30 26 37 51Future Volume (Veh/h) 49 199 114 64 235 15 61 42 30 26 37 51Sign Control Free Free Stop StopGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 53 216 124 70 255 16 66 46 33 28 40 55PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m) 300pX, platoon unblockedvC, conflicting volume 271 340 862 795 278 843 849 263vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 271 340 862 795 278 843 849 263tC, single (s) 4.1 4.1 7.1 6.5 6.2 7.1 6.5 6.2tC, 2 stage (s)tF (s) 2.2 2.2 3.5 4.0 3.3 3.5 4.0 3.3p0 queue free % 96 94 69 84 96 87 85 93cM capacity (veh/h) 1292 1219 210 289 761 221 269 776
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 393 341 145 123Volume Left 53 70 66 28Volume Right 124 16 33 55cSH 1292 1219 281 355Volume to Capacity 0.04 0.06 0.52 0.35Queue Length 95th (m) 1.0 1.4 20.9 11.5Control Delay (s) 1.4 2.1 30.7 20.4Lane LOS A A D CApproach Delay (s) 1.4 2.1 30.7 20.4Approach LOS D C
Intersection SummaryAverage Delay 8.2Intersection Capacity Utilization 46.7% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis3: Street "A" & Collector "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 104 14 143 10 12 14 124 90 15 14 74 216Future Volume (Veh/h) 104 14 143 10 12 14 124 90 15 14 74 216Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 113 15 155 11 13 15 135 98 16 15 80 235PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 625 612 198 766 721 106 315 114vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 625 612 198 766 721 106 315 114tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 67 96 82 95 96 98 89 99cM capacity (veh/h) 345 360 844 230 312 948 1245 1475
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 283 39 249 330Volume Left 113 11 135 15Volume Right 155 15 16 235cSH 512 370 1245 1475Volume to Capacity 0.55 0.11 0.11 0.01Queue Length 95th (m) 25.3 2.7 2.8 0.2Control Delay (s) 20.4 15.9 4.9 0.4Lane LOS C C A AApproach Delay (s) 20.4 15.9 4.9 0.4Approach LOS C C
Intersection SummaryAverage Delay 8.6Intersection Capacity Utilization 62.4% ICU Level of Service BAnalysis Period (min) 15
Timings4: Tremaine Rd & Street "B" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group WBL NBT NBR SBL SBTLane ConfigurationsTraffic Volume (vph) 19 1067 33 80 858Future Volume (vph) 19 1067 33 80 858Turn Type Prot NA Perm Perm NAProtected Phases 8 2 6Permitted Phases 2 6Detector Phase 8 2 2 6 6Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5 22.5Total Split (s) 24.0 36.0 36.0 36.0 36.0Total Split (%) 40.0% 60.0% 60.0% 60.0% 60.0%Yellow Time (s) 3.5 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode Max Max Max Max MaxAct Effct Green (s) 19.5 31.5 31.5 31.5Actuated g/C Ratio 0.32 0.52 0.52 0.52v/c Ratio 0.24 0.43 0.04 0.49Control Delay 11.8 9.4 3.4 5.9Queue Delay 0.0 0.0 0.0 0.0Total Delay 11.8 9.4 3.4 5.9LOS B A A AApproach Delay 11.8 9.2 5.9Approach LOS B A A
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:NBT and 6:SBTL, Start of GreenNatural Cycle: 45Control Type: PretimedMaximum v/c Ratio: 0.49Intersection Signal Delay: 7.9 Intersection LOS: AIntersection Capacity Utilization 57.7% ICU Level of Service BAnalysis Period (min) 15
Splits and Phases: 4: Tremaine Rd & Street "B"
Queues4: Tremaine Rd & Street "B" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group WBL NBT NBR SBTLane Group Flow (vph) 136 1160 36 1020v/c Ratio 0.24 0.43 0.04 0.49Control Delay 11.8 9.4 3.4 5.9Queue Delay 0.0 0.0 0.0 0.0Total Delay 11.8 9.4 3.4 5.9Queue Length 50th (m) 5.3 26.1 0.2 8.9Queue Length 95th (m) m17.4 34.6 3.4 11.7Internal Link Dist (m) 263.3 194.1 424.4Turn Bay Length (m) 15.0Base Capacity (vph) 576 2699 855 2070Starvation Cap Reductn 0 0 0 0Spillback Cap Reductn 0 0 0 0Storage Cap Reductn 0 0 0 0Reduced v/c Ratio 0.24 0.43 0.04 0.49
Intersection Summarym Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis4: Tremaine Rd & Street "B" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement WBL WBR NBT NBR SBL SBTLane ConfigurationsTraffic Volume (vph) 19 106 1067 33 80 858Future Volume (vph) 19 106 1067 33 80 858Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5 4.5Lane Util. Factor 1.00 0.91 1.00 0.91Frt 0.89 1.00 0.85 1.00Flt Protected 0.99 1.00 1.00 1.00Satd. Flow (prot) 1656 5142 1601 5120Flt Permitted 0.99 1.00 1.00 0.77Satd. Flow (perm) 1656 5142 1601 3942Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 21 115 1160 36 87 933RTOR Reduction (vph) 38 0 0 15 0 0Lane Group Flow (vph) 98 0 1160 21 0 1020Turn Type Prot NA Perm Perm NAProtected Phases 8 2 6Permitted Phases 2 6Actuated Green, G (s) 19.5 31.5 31.5 31.5Effective Green, g (s) 19.5 31.5 31.5 31.5Actuated g/C Ratio 0.32 0.52 0.52 0.52Clearance Time (s) 4.5 4.5 4.5 4.5Lane Grp Cap (vph) 538 2699 840 2069v/s Ratio Prot c0.06 0.23v/s Ratio Perm 0.01 c0.26v/c Ratio 0.18 0.43 0.02 0.49Uniform Delay, d1 14.5 8.7 6.9 9.1Progression Factor 1.14 1.00 1.00 0.55Incremental Delay, d2 0.7 0.5 0.1 0.8Delay (s) 17.3 9.2 6.9 5.8Level of Service B A A AApproach Delay (s) 17.3 9.2 5.8Approach LOS B A A
Intersection SummaryHCM 2000 Control Delay 8.2 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.37Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 57.7% ICU Level of Service BAnalysis Period (min) 15c Critical Lane Group
HCM Unsignalized Intersection Capacity Analysis5: Street "C" & Street "B" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 3 6 19 2 52 4 114 87 2 13 122 13Future Volume (Veh/h) 3 6 19 2 52 4 114 87 2 13 122 13Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 3 7 21 2 57 4 124 95 2 14 133 14PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 544 513 140 536 519 96 147 97vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 544 513 140 536 519 96 147 97tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 99 98 98 100 86 100 91 99cM capacity (veh/h) 372 421 908 407 417 960 1435 1496
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 31 63 221 161Volume Left 3 2 124 14Volume Right 21 4 2 14cSH 648 432 1435 1496Volume to Capacity 0.05 0.15 0.09 0.01Queue Length 95th (m) 1.1 3.8 2.2 0.2Control Delay (s) 10.8 14.7 4.7 0.7Lane LOS B B A AApproach Delay (s) 10.8 14.7 4.7 0.7Approach LOS B B
Intersection SummaryAverage Delay 5.1Intersection Capacity Utilization 32.3% ICU Level of Service AAnalysis Period (min) 15
HCM Unsignalized Intersection Capacity Analysis6: Street "A" & Street "B" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBRLane ConfigurationsTraffic Volume (veh/h) 19 0 13 12 8 0 35 308 12 0 240 36Future Volume (Veh/h) 19 0 13 12 8 0 35 308 12 0 240 36Sign Control Stop Stop Free FreeGrade 0% 0% 0% 0%Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92Hourly flow rate (vph) 21 0 14 13 9 0 38 335 13 0 261 39PedestriansLane Width (m)Walking Speed (m/s)Percent BlockageRight turn flare (veh)Median type None NoneMedian storage veh)Upstream signal (m)pX, platoon unblockedvC, conflicting volume 702 704 280 712 718 342 300 348vC1, stage 1 conf volvC2, stage 2 conf volvCu, unblocked vol 702 704 280 712 718 342 300 348tC, single (s) 7.1 6.5 6.2 7.1 6.5 6.2 4.1 4.1tC, 2 stage (s)tF (s) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2p0 queue free % 94 100 98 96 97 100 97 100cM capacity (veh/h) 338 350 758 333 344 701 1261 1211
Direction, Lane # EB 1 WB 1 NB 1 SB 1Volume Total 35 22 386 300Volume Left 21 13 38 0Volume Right 14 0 13 39cSH 434 338 1261 1211Volume to Capacity 0.08 0.07 0.03 0.00Queue Length 95th (m) 2.0 1.6 0.7 0.0Control Delay (s) 14.0 16.4 1.1 0.0Lane LOS B C AApproach Delay (s) 14.0 16.4 1.1 0.0Approach LOS B C
Intersection SummaryAverage Delay 1.7Intersection Capacity Utilization 47.0% ICU Level of Service AAnalysis Period (min) 15
Timings7: Britannia Rd & Street "C" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 89 1082 700 140Future Volume (vph) 89 1082 700 140Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 40.0 40.0 11.0Actuated g/C Ratio 0.67 0.67 0.18v/c Ratio 0.46 0.27 0.55Control Delay 6.0 3.6 23.3Queue Delay 0.0 0.0 0.0Total Delay 6.0 3.6 23.3LOS A A CApproach Delay 6.0 3.6 23.3Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 45Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.55Intersection Signal Delay: 6.4 Intersection LOS: AIntersection Capacity Utilization 60.5% ICU Level of Service BAnalysis Period (min) 15
Splits and Phases: 7: Britannia Rd & Street "C"
Queues7: Britannia Rd & Street "C" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1273 923 187v/c Ratio 0.46 0.27 0.55Control Delay 6.0 3.6 23.3Queue Delay 0.0 0.0 0.0Total Delay 6.0 3.6 23.3Queue Length 50th (m) 19.9 10.1 16.4Queue Length 95th (m) 35.8 14.3 m27.1Internal Link Dist (m) 239.3 367.0 415.2Turn Bay Length (m)Base Capacity (vph) 2738 3377 587Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.46 0.27 0.32
Intersection Summarym Volume for 95th percentile queue is metered by upstream signal.
HCM Signalized Intersection Capacity Analysis7: Britannia Rd & Street "C" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 89 1082 700 149 140 32Future Volume (vph) 89 1082 700 149 140 32Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.97 0.97Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 5122 5006 1764Flt Permitted 0.80 1.00 0.96Satd. Flow (perm) 4106 5006 1764Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 97 1176 761 162 152 35RTOR Reduction (vph) 0 0 39 0 16 0Lane Group Flow (vph) 0 1273 884 0 171 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 40.0 40.0 11.0Effective Green, g (s) 40.0 40.0 11.0Actuated g/C Ratio 0.67 0.67 0.18Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2737 3337 323v/s Ratio Prot 0.18 c0.10v/s Ratio Perm c0.31v/c Ratio 0.47 0.27 0.53Uniform Delay, d1 4.8 4.0 22.2Progression Factor 1.00 0.86 0.90Incremental Delay, d2 0.6 0.2 1.5Delay (s) 5.4 3.7 21.5Level of Service A A CApproach Delay (s) 5.4 3.7 21.5Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 6.0 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.48Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 60.5% ICU Level of Service BAnalysis Period (min) 15c Critical Lane Group
Timings8: Britannia Rd & Street "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBL EBT WBT SBLLane ConfigurationsTraffic Volume (vph) 76 1145 827 286Future Volume (vph) 76 1145 827 286Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Detector Phase 2 2 6 8Switch PhaseMinimum Initial (s) 5.0 5.0 5.0 5.0Minimum Split (s) 22.5 22.5 22.5 22.5Total Split (s) 36.0 36.0 36.0 24.0Total Split (%) 60.0% 60.0% 60.0% 40.0%Yellow Time (s) 3.5 3.5 3.5 3.5All-Red Time (s) 1.0 1.0 1.0 1.0Lost Time Adjust (s) 0.0 0.0 0.0Total Lost Time (s) 4.5 4.5 4.5Lead/LagLead-Lag Optimize?Recall Mode C-Max C-Max C-Min MinAct Effct Green (s) 35.3 35.3 15.7Actuated g/C Ratio 0.59 0.59 0.26v/c Ratio 0.56 0.43 0.71Control Delay 6.6 6.1 28.2Queue Delay 0.0 0.0 0.0Total Delay 6.6 6.1 28.2LOS A A CApproach Delay 6.6 6.1 28.2Approach LOS A A C
Intersection SummaryCycle Length: 60Actuated Cycle Length: 60Offset: 0 (0%), Referenced to phase 2:EBTL and 6:WBT, Start of GreenNatural Cycle: 50Control Type: Actuated-CoordinatedMaximum v/c Ratio: 0.71Intersection Signal Delay: 8.9 Intersection LOS: AIntersection Capacity Utilization 76.4% ICU Level of Service DAnalysis Period (min) 15
Splits and Phases: 8: Britannia Rd & Street "A"
Queues8: Britannia Rd & Street "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Lane Group EBT WBT SBLLane Group Flow (vph) 1328 1300 336v/c Ratio 0.56 0.43 0.71Control Delay 6.6 6.1 28.2Queue Delay 0.0 0.0 0.0Total Delay 6.6 6.1 28.2Queue Length 50th (m) 20.5 19.0 32.2Queue Length 95th (m) 26.7 31.5 51.7Internal Link Dist (m) 367.0 772.7 419.1Turn Bay Length (m)Base Capacity (vph) 2358 3005 584Starvation Cap Reductn 0 0 0Spillback Cap Reductn 0 0 0Storage Cap Reductn 0 0 0Reduced v/c Ratio 0.56 0.43 0.58
Intersection Summary
HCM Signalized Intersection Capacity Analysis8: Britannia Rd & Street "A" 04/06/2020
Future Total 2029 Synchro 10 ReportPM Peak Hour GHD
Movement EBL EBT WBT WBR SBL SBRLane ConfigurationsTraffic Volume (vph) 76 1145 827 369 286 23Future Volume (vph) 76 1145 827 369 286 23Ideal Flow (vphpl) 1900 1900 1900 1900 1900 1900Total Lost time (s) 4.5 4.5 4.5Lane Util. Factor 0.91 0.91 1.00Frt 1.00 0.95 0.99Flt Protected 1.00 1.00 0.96Satd. Flow (prot) 5126 4904 1782Flt Permitted 0.78 1.00 0.96Satd. Flow (perm) 4006 4904 1782Peak-hour factor, PHF 0.92 0.92 0.92 0.92 0.92 0.92Adj. Flow (vph) 83 1245 899 401 311 25RTOR Reduction (vph) 0 0 117 0 5 0Lane Group Flow (vph) 0 1328 1183 0 331 0Turn Type Perm NA NA ProtProtected Phases 2 6 8Permitted Phases 2Actuated Green, G (s) 35.3 35.3 15.7Effective Green, g (s) 35.3 35.3 15.7Actuated g/C Ratio 0.59 0.59 0.26Clearance Time (s) 4.5 4.5 4.5Vehicle Extension (s) 3.0 3.0 3.0Lane Grp Cap (vph) 2356 2885 466v/s Ratio Prot 0.24 c0.19v/s Ratio Perm c0.33v/c Ratio 0.56 0.41 0.71Uniform Delay, d1 7.6 6.7 20.1Progression Factor 0.68 1.00 1.00Incremental Delay, d2 0.9 0.4 4.9Delay (s) 6.1 7.1 25.0Level of Service A A CApproach Delay (s) 6.1 7.1 25.0Approach LOS A A C
Intersection SummaryHCM 2000 Control Delay 8.7 HCM 2000 Level of Service AHCM 2000 Volume to Capacity ratio 0.61Actuated Cycle Length (s) 60.0 Sum of lost time (s) 9.0Intersection Capacity Utilization 76.4% ICU Level of Service DAnalysis Period (min) 15c Critical Lane Group
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Turning Movement Forecasts
Source:
70
59
8
49
74
170
15
4
36
5
53
37
75
18
25
11
7
62
170
15
4
45
5 53
37
75
63
247
51
2
175
71
7
259
42
2
130
BritanniaRd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
BritanniaRd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
Existing PM Peak Hour
63
Existing AM Peak Hour
Britannia Rd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Geometric Design Parameters
Conceptual Design Geometry
Road HalfWidth, V (m)
EntryWidth, E
(m)
Eff. FlareLength, l'
(m)
EntryRadius, R
(m)
InscribedCircle Dia,
D (m)
EntryAngle, Ø
(deg.)
Exit Only(T/F)
Right-TurnBypass
(T/F)7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE
Other Inputs
FlareStorage (m)
PedestrianCrossings % Trucks Flow Profile Scaling
Factor30 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
Existing AM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 2.8 0.35 A<25 2.8 0.16 A<25 2.5 0.22 A<25 2.3 0.07 A
<25 2.2 0.30 A<25 2.2 0.13 A<25 2.0 0.19 A<25 1.8 0.06 A
Existing PM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 2.2 0.16 A<25 2.3 0.13 A<25 2.6 0.27 A<25 2.4 0.10 A
<25 1.8 0.14 A<25 1.8 0.11 A<25 2.1 0.22 A<25 1.9 0.08 A
A240%EB Britannia Rd.
NB Tremaine Rd. [NB Tremaine Rd.]WB Britannia Rd.
[NB Tremaine Rd.]
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
<5 A186%EB Britannia Rd.
WB Britannia Rd.100% y-int. AdjustmentSB Tremaine Rd.
<5
NB Tremaine Rd.
100% y-int. Adjustment
NB Tremaine Rd. [SB Tremaine Rd.]WB Britannia Rd.
SB Tremaine Rd.
<5 A199%EB Britannia Rd.
NB Tremaine Rd.WB Britannia Rd.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
<5 A152%EB Britannia Rd.
NB Tremaine Rd. [SB Tremaine Rd.]WB Britannia Rd.
EB Britannia Rd.
SB Tremaine Rd.EB Britannia Rd.NB Tremaine Rd.WB Britannia Rd.
SB Tremaine Rd.
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Turning Movement Forecasts
Source:
11
4
63
8
15
7
97
297
15
4
52
8
10
9
204
384
248
29
22
93
124
503
15
4
86
1
22
9
157
294
267
642
10
94
718
90
9
409
64
1
836
BritanniaRd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
BritanniaRd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
Existing+Boyne PM Peak Hour
11
0
Existing+Boyne AM Peak Hour
Britannia Rd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Geometric Design Parameters
Conceptual Design Geometry
Road HalfWidth, V (m)
EntryWidth, E
(m)
Eff. FlareLength, l'
(m)
EntryRadius, R
(m)
InscribedCircle Dia,
D (m)
EntryAngle, Ø
(deg.)
Exit Only(T/F)
Right-TurnBypass
(T/F)7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE
Other Inputs
FlareStorage (m)
PedestrianCrossings % Trucks Flow Profile Scaling
Factor30 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
Existing+Boyne AM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 5.0 0.55 A<25 4.0 0.31 A<25 3.6 0.38 A<25 4.7 0.52 A
<25 3.3 0.45 A<25 2.9 0.24 A<25 2.6 0.31 A<25 3.2 0.42 A
Existing+Boyne PM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 3.5 0.40 A<25 4.2 0.42 A<25 12.7 0.79 B<25 6.0 0.54 A
<25 2.6 0.33 A<25 2.9 0.34 A<25 5.6 0.62 A<25 3.7 0.42 A
EB Britannia Rd.
SB Tremaine Rd.EB Britannia Rd.NB Tremaine Rd.WB Britannia Rd.
SB Tremaine Rd.
NB Tremaine Rd.WB Britannia Rd.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
<5 A47%EB Britannia Rd.
NB Tremaine Rd. [SB Tremaine Rd.]WB Britannia Rd.100% y-int. Adjustment
NB Tremaine Rd. [SB Tremaine Rd.]WB Britannia Rd.
SB Tremaine Rd.
<5 A75%EB Britannia Rd.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
7 A11%EB Britannia Rd.
WB Britannia Rd.100% y-int. AdjustmentSB Tremaine Rd.
<5
NB Tremaine Rd.
A31%EB Britannia Rd.
NB Tremaine Rd. [NB Tremaine Rd.]WB Britannia Rd.
[NB Tremaine Rd.]
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Turning Movement Forecasts
Source:
10
2
10
02
13
3
149
337
15
4
84
3
10
3
190
464
230
56
92
64
160
526
15
4
11
75
21
2
146
342
233
701
13
91
721
12
37
501
95
0
884
BritanniaRd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
BritanniaRd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
2024FB PM Peak Hour
10
1
2024FB AM Peak Hour
Britannia Rd.
Britannia Rd.
Trem
aine
Rd.
Trem
aine
Rd.
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Geometric Design Parameters
Conceptual Design Geometry
Road HalfWidth, V (m)
EntryWidth, E
(m)
Eff. FlareLength, l'
(m)
EntryRadius, R
(m)
InscribedCircle Dia,
D (m)
EntryAngle, Ø
(deg.)
Exit Only(T/F)
Right-TurnBypass
(T/F)7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE7.40 8.00 15 20 44 20 FALSE FALSE
Other Inputs
FlareStorage (m)
PedestrianCrossings % Trucks Flow Profile Scaling
Factor30 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
2024FB AM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 10.3 0.78 B<25 6.6 0.47 A<25 5.5 0.59 A<25 8.4 0.67 A
<25 5.1 0.63 A<25 3.9 0.35 A<25 3.5 0.48 A<25 4.5 0.52 A
2024FB PM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 4.7 0.54 A<25 5.8 0.52 A
316.5 87.2 1.02 F<25 10.1 0.67 B
<25 3.2 0.45 A<25 3.6 0.41 A<25 10.7 0.80 B<25 5.2 0.51 A
EB Britannia Rd.
SB Tremaine Rd.EB Britannia Rd.NB Tremaine Rd.WB Britannia Rd.
SB Tremaine Rd.
NB Tremaine Rd.WB Britannia Rd.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
8 A15%EB Britannia Rd.
NB Tremaine Rd. [SB Tremaine Rd.]WB Britannia Rd.100% y-int. Adjustment
NB Tremaine Rd. [SB Tremaine Rd.]WB Britannia Rd.
SB Tremaine Rd.
<5 A37%EB Britannia Rd.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
37 E-6%EB Britannia Rd.
WB Britannia Rd.100% y-int. AdjustmentSB Tremaine Rd.
6
NB Tremaine Rd.
A12%EB Britannia Rd.
NB Tremaine Rd. [NB Tremaine Rd.]WB Britannia Rd.
[NB Tremaine Rd.]
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Turning Movement Forecasts
10
2
10
02
17
9
158
355
15
4
84
3
10
3
190
549
230
56
7
40
4
191
587
15
4
11
75
21
2
157
396
233
793
13
91
786
12
83
528
95
0
969
Britannia Rd.
Britannia Rd.
Tre
ma
ine
R
d.
Tre
ma
ine
R
d.
Britannia Rd.
Britannia Rd.
Tre
ma
ine
R
d.
Tre
ma
ine
R
d.
2024FT PM Peak Hour
99
2024FT AM Peak Hour
Britannia Rd.
Britannia Rd.
Tre
ma
ine
Rd
.
Tre
ma
ine
Rd
.
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Geometric Design ParametersConceptual Design Geometry
Road Half Width, V (m)
Entry Width, E
(m)
Eff. Flare Length, l'
(m)
Entry Radius, R
(m)
Inscribed Circle Dia,
D (m)
Entry Angle, Ø
(deg.)
Exit Only (T/F)
Right-Turn Bypass
(T/F)
7.40 8.00 15 20 44 20 FALSE FALSE
7.40 8.00 15 20 44 20 FALSE FALSE
7.40 8.00 15 20 44 20 FALSE FALSE
7.40 8.00 15 20 44 20 FALSE FALSE
Other Inputs
Flare Storage (m)
Pedestrian Crossings
% Trucks Flow ProfileScaling Factor
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
2024FT AM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
29.5 15.0 0.84 C
<25 7.4 0.52 A
<25 6.0 0.61 A
<25 10.6 0.74 B
<25 6.0 0.68 A
<25 4.2 0.38 A
<25 3.7 0.49 A
<25 5.1 0.57 A
2024FT PM Peak Hour95% Queue
(m)Delay
(s/vehicle)V/C Ratio LOS
Int. Delay (s/vehicle)
Int. LOS
<25 6.1 0.64 A
<25 8.7 0.65 A
575.5 270.1 1.18 F
<25 9.5 0.67 A
<25 3.8 0.52 A
<25 4.6 0.50 A
<25 22.2 0.90 C
<25 6.0 0.56 A
EB Britannia Rd.
SB Tremaine Rd.
EB Britannia Rd.
NB Tremaine Rd.
WB Britannia Rd.
SB Tremaine Rd.
NB Tremaine Rd.
WB Britannia Rd.
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
10 B8%EB Britannia Rd.
NB Tremaine Rd. [SB Tremaine Rd.]
WB Britannia Rd.
100% y-int. Adjustment
NB Tremaine Rd. [SB Tremaine Rd.]
WB Britannia Rd.
SB Tremaine Rd.
<5 A28%EB Britannia Rd.
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
98 F-13%EB Britannia Rd.
WB Britannia Rd.
100% y-int. Adjustment
SB Tremaine Rd.
11
NB Tremaine Rd.
B3%EB Britannia Rd.
NB Tremaine Rd. [NB Tremaine Rd.]
WB Britannia Rd.
[NB Tremaine Rd.]
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Turning Movement Forecasts
18
0
85
1
18
2
158
388
15
4
49
6
10
3
180
466
230
38
0
34
1
191
620
15
4
67
8
21
2
146
354
233
826
89
4
733
12
13
561
60
3
876
Britannia Rd.
Britannia Rd.
Tre
ma
ine
R
d.
Tre
ma
ine
R
d.
Britannia Rd.
Britannia Rd.
Tre
ma
ine
R
d.
Tre
ma
ine
R
d.
2029FT PM Peak Hour
15
8
2029FT AM Peak Hour
Britannia Rd.
Britannia Rd.
Tre
ma
ine
Rd
.
Tre
ma
ine
Rd
.
ARCADY Roundabout Capacity AnalysisTremaine Road at Britannia Road
Geometric Design Parameters
Conceptual Design Geometry
Road Half Width, V (m)
Entry Width, E
(m)
Eff. Flare Length, l'
(m)
Entry Radius, R
(m)
Inscribed Circle Dia,
D (m)
Entry Angle, Ø
(deg.)
Exit Only (T/F)
Right-Turn Bypass
(T/F)
7.40 8.00 15 20 44 20 FALSE FALSE
7.40 8.00 15 20 44 20 FALSE FALSE
7.40 8.00 15 20 44 20 FALSE FALSE
7.40 8.00 15 20 44 20 FALSE FALSE
Other Inputs
Flare Storage (m)
Pedestrian Crossings
% Trucks Flow ProfileScaling Factor
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
2029FT AM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
<25 9.5 0.76 A
<25 6.2 0.49 A
<25 3.9 0.39 A
<25 5.1 0.55 A
<25 4.9 0.62 A
<25 3.8 0.37 A
<25 2.8 0.32 A
<25 3.4 0.45 A
2029FT PM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
<25 4.4 0.51 A
<25 6.1 0.58 A
<25 12.0 0.75 B
670 5.3 0.52 A
<25 3.0 0.42 A
<25 3.8 0.46 A
<25 5.4 0.57 A
<25 3.5 0.41 A
EB Britannia Rd.
SB Tremaine Rd.
EB Britannia Rd.
NB Tremaine Rd.
WB Britannia Rd.
SB Tremaine Rd.
NB Tremaine Rd.
WB Britannia Rd.
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
7 A17%EB Britannia Rd.
NB Tremaine Rd. [SB Tremaine Rd.]
WB Britannia Rd.
100% y-int. Adjustment
NB Tremaine Rd. [SB Tremaine Rd.]
WB Britannia Rd.
SB Tremaine Rd.
<5 A39%EB Britannia Rd.
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
7 A11%EB Britannia Rd.
WB Britannia Rd.
100% y-int. Adjustment
SB Tremaine Rd.
<5
NB Tremaine Rd.
A32%EB Britannia Rd.
NB Tremaine Rd. [NB Tremaine Rd.]
WB Britannia Rd.
[NB Tremaine Rd.]
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Turning Movement Forecasts
Source: GHD, May 2017
11
54
4
97
5
7
3
0
27
91
78
170
4
75
24
3
38
13
10
7 0
44
4
13
6
81
8
85
30
58
0
174
65
2
15
45
7
249
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
Existing PM Peak Hour
12
Existing AM Peak Hour
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
N
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Geometric Design Parameters
Conceptual Design Geometry
Road HalfWidth, V (m)
EntryWidth, E
(m)
Eff. FlareLength, l'
(m)
EntryRadius, R
(m)
InscribedCircle Dia,
D (m)
EntryAngle, Ø
(deg.)
Exit Only(T/F)
Right-TurnBypass
(T/F)7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE
Other Inputs
FlareStorage (m)
PedestrianCrossings % Trucks Flow Profile Scaling
Factor30 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
Existing AM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 2.8 0.33 A<25 2.5 0.01 A<25 2.3 0.22 A<25 2.2 0.13 A
<25 2.1 0.27 A<25 2.0 0.01 A<25 1.8 0.19 A<25 1.8 0.11 A
Existing PM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 2.1 0.14 A<25 2.0 0.02 A<25 2.5 0.28 A<25 2.3 0.10 A
<25 1.7 0.12 A<25 1.7 0.01 A<25 1.9 0.23 A<25 1.8 0.08 A
EB Louis St. Laurent Ave.
SB Tremaine Rd.EB Louis St. Laurent Ave.NB Tremaine Rd.WB Louis St. Laurent Ave.
SB Tremaine Rd.
NB Tremaine Rd.WB Louis St. Laurent Ave.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
<5 A160%EB Louis St. Laurent Ave.
NB Tremaine Rd. [SB Tremaine]WB Louis St. Laurent Ave.100% y-int. Adjustment
NB Tremaine Rd. [SB Tremaine]WB Louis St. Laurent Ave.
SB Tremaine Rd.
<5 A212%EB Louis St. Laurent Ave.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
<5 A226%EB Louis St. Laurent Ave.
WB Louis St. Laurent Ave.100% y-int. AdjustmentSB Tremaine Rd.
<5
NB Tremaine Rd.
A293%EB Louis St. Laurent Ave.
NB Tremaine Rd. [NB Tremaine]WB Louis St. Laurent Ave.
[NB Tremaine]
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Turning Movement Forecasts
Source: GHD, May 2017
11
63
8
41
3
5
7
3
0
85
22
28
257
4
805
51
0
91
3
13
10
7 0
90
6
21
6
157
8
641
30
11
22
806
10
62
15
10
80
1082
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
Existing+Boyne PM Peak Hour
12
Existing+Boyne AM Peak Hour
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
N
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Geometric Design Parameters
Conceptual Design Geometry
Road HalfWidth, V (m)
EntryWidth, E
(m)
Eff. FlareLength, l'
(m)
EntryRadius, R
(m)
InscribedCircle Dia,
D (m)
EntryAngle, Ø
(deg.)
Exit Only(T/F)
Right-TurnBypass
(T/F)7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE
Other Inputs
FlareStorage (m)
PedestrianCrossings % Trucks Flow Profile Scaling
Factor30 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
Existing+Boyne AM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 4.4 0.56 A<25 3.4 0.01 A<25 5.3 0.61 A<25 9.7 0.74 A
<25 2.9 0.46 A<25 2.5 0.01 A<25 3.3 0.49 A<25 4.7 0.58 A
Existing+Boyne PM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 6.6 0.72 A<25 4.2 0.03 A<25 13.1 0.80 B<25 6.1 0.57 A
<25 3.8 0.60 A<25 2.9 0.02 A<25 5.4 0.62 A<25 3.6 0.44 A
EB Louis St. Laurent Ave.NB Tremaine Rd. [NB Tremaine]WB Louis St. Laurent Ave.
[NB Tremaine]
A32%
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
9 A10%EB Louis St. Laurent Ave.
WB Louis St. Laurent Ave.100% y-int. AdjustmentSB Tremaine Rd.
<5
NB Tremaine Rd.
100% y-int. Adjustment
NB Tremaine Rd. [WB LSL]WB Louis St. Laurent Ave.
SB Tremaine Rd.
<5 A40%EB Louis St. Laurent Ave.
NB Tremaine Rd.WB Louis St. Laurent Ave.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
6 A17%EB Louis St. Laurent Ave.
NB Tremaine Rd. [WB LSL]WB Louis St. Laurent Ave.
EB Louis St. Laurent Ave.
SB Tremaine Rd.EB Louis St. Laurent Ave.NB Tremaine Rd.WB Louis St. Laurent Ave.
SB Tremaine Rd.
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Turning Movement Forecasts
Source: GHD, May 2017
11
80
2
37
9
5
8
3
0
80
43
52
358
5
752
42
6
82
5
13
12
7 0
86
1
28
4
236
10
597
32
11
45
843
11
92
16
11
56
1115
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
2024FB PM Peak Hour
12
2024FB AM Peak Hour
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Trem
aine
Rd.
Trem
aine
Rd.
N
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Geometric Design Parameters
Conceptual Design Geometry
Road HalfWidth, V (m)
EntryWidth, E
(m)
Eff. FlareLength, l'
(m)
EntryRadius, R
(m)
InscribedCircle Dia,
D (m)
EntryAngle, Ø
(deg.)
Exit Only(T/F)
Right-TurnBypass
(T/F)7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE7.40 8.00 20 30 50 20 FALSE FALSE
Other Inputs
FlareStorage (m)
PedestrianCrossings % Trucks Flow Profile Scaling
Factor30 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.8930 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
2024FB AM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 5.7 0.65 A#VALUE! 4.0 0.02 A
<25 5.6 0.64 A<25 9.6 0.74 A
<25 3.5 0.53 A#VALUE! 2.8 0.01 A
<25 3.4 0.52 A<25 4.7 0.59 A
2024FB PM Peak Hour
95% Queue(m)
Delay(s/vehicle) V/C Ratio LOS Int. Delay
(s/vehicle) Int. LOS
<25 5.5 0.65 A#VALUE! 3.9 0.03 A
<25 11.4 0.78 B<25 6.1 0.58 A
<25 3.4 0.54 A#VALUE! 2.7 0.02 A
<25 5.1 0.61 A<25 3.7 0.46 A
EB Louis St. Laurent Ave.NB Tremaine Rd. [NB Tremaine]WB Louis St. Laurent Ave.
[NB Tremaine]
A35%
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
8 A13%EB Louis St. Laurent Ave.
WB Louis St. Laurent Ave.100% y-int. AdjustmentSB Tremaine Rd.
<5
NB Tremaine Rd.
100% y-int. Adjustment
NB Tremaine Rd. [WB LSL]WB Louis St. Laurent Ave.
SB Tremaine Rd.
<5 A40%EB Louis St. Laurent Ave.
NB Tremaine Rd.WB Louis St. Laurent Ave.
Intersection ResidualCapacity
85% y-int. AdjustmentSB Tremaine Rd.
7 A17%EB Louis St. Laurent Ave.
NB Tremaine Rd. [WB LSL]WB Louis St. Laurent Ave.
EB Louis St. Laurent Ave.
SB Tremaine Rd.EB Louis St. Laurent Ave.NB Tremaine Rd.WB Louis St. Laurent Ave.
SB Tremaine Rd.
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Turning Movement Forecasts
Source: GHD, April 2020
11
84
8
37
9
5
8
3
0
94
7
35
23 58
5
752
57
9
82
5
1 3
12
7
0
95
1
28
4
2 36
10
597
32
12
35
843
12
38
16
12
99
1115
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Tre
mai
ne R
d.
Tre
mai
ne R
d.
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Tre
mai
ne R
d.
Tre
mai
ne R
d.
2024FT PM Peak Hour
12
2024FT AM Peak Hour
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Tre
mai
ne R
d.
Tre
mai
ne R
d.
N
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Geometric Design Parameters
Conceptual Design Geometry
Road Half Width, V (m)
Entry Width, E
(m)
Eff. Flare Length, l'
(m)
Entry Radius, R
(m)
Inscribed Circle Dia,
D (m)
Entry Angle, Ø
(deg.)
Exit Only (T/F)
Right-Turn Bypass (T/F)
7.40 8.00 20 20 50 20 FALSE FALSE
7.40 8.00 20 20 50 20 FALSE FALSE
7.40 8.00 20 20 50 20 FALSE FALSE
7.40 8.00 20 20 50 20 FALSE FALSE
Other Inputs
Flare Storage (m)
Pedestrian Crossings
% Trucks Flow ProfileScaling Factor
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
2024FT AM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
<25 6.1 0.67 A
<25 4.2 0.02 A
<25 7.1 0.71 A
<25 13.4 0.80 B
<25 3.6 0.55 A
<25 2.9 0.01 A
<25 4.0 0.58 A
<25 5.5 0.62 A
2024FT PM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
<25 7.1 0.73 A
<25 4.4 0.04 A
29.5 15.7 0.84 C
<25 6.9 0.61 A
<25 4.0 0.61 A
<25 3.0 0.03 A
<25 5.8 0.66 A
<25 3.9 0.47 A
EB Louis St. Laurent Ave
NB Tremaine Rd. [NB Tremaine]
WB Louis St. Laurent Av
[NB Tremaine]
A29%
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
10 B7%EB Louis St. Laurent Ave
WB Louis St. Laurent Av
100% y-int. Adjustment
SB Tremaine Rd.
<5
NB Tremaine Rd.
100% y-int. Adjustment
NB Tremaine Rd. [WB LSL]
WB Louis St. Laurent Av
SB Tremaine Rd.
<5 A32%EB Louis St. Laurent Ave
NB Tremaine Rd.
WB Louis St. Laurent Av
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
9 A10%EB Louis St. Laurent Ave
NB Tremaine Rd. [WB LSL]
WB Louis St. Laurent Av
EB Louis St. Laurent Ave
SB Tremaine Rd.
EB Louis St. Laurent Ave
NB Tremaine Rd.
WB Louis St. Laurent Av
SB Tremaine Rd.
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Turning Movement Forecasts
Source: GHD, April 2020
11
10
77
37
9
5
10
3
0
10
00
35
23 58
6
752
93
9
82
5
1 3
14
7
0
10
36
28
4
2 36
11
597
34
13
20
844
14
67
18
13
52
1116
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Tre
mai
ne R
d.
Tre
mai
ne R
d.
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Tre
mai
ne R
d.
Tre
mai
ne R
d.
2029FT PM Peak Hour
12
2029FT AM Peak Hour
Louis St. Laurent Ave.
Louis St. Laurent Ave.
Tre
mai
ne R
d.
Tre
mai
ne R
d.
N
ARCADY Roundabout Capacity AnalysisLouis St. Laurent Avenue at Tremaine Road
Geometric Design Parameters
Conceptual Design Geometry
Road Half Width, V (m)
Entry Width, E
(m)
Eff. Flare Length, l'
(m)
Entry Radius, R
(m)
Inscribed Circle Dia,
D (m)
Entry Angle, Ø
(deg.)
Exit Only (T/F)
Right-Turn Bypass (T/F)
7.40 8.00 20 20 50 20 FALSE FALSE
7.40 8.00 20 20 50 20 FALSE FALSE
7.40 8.00 20 20 50 20 FALSE FALSE
7.40 8.00 20 20 50 20 FALSE FALSE
Other Inputs
Flare Storage (m)
Pedestrian Crossings
% Trucks Flow ProfileScaling Factor
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
30 0 2.0 ONE HOUR 0.89
Capacity Analysis Results
2029FT AM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
<25 9.8 0.80 A
<25 5.2 0.02 A
<25 7.9 0.74 A
<25 15.7 0.83 C
<25 4.7 0.65 A
<25 3.3 0.02 A
<25 4.2 0.61 A
<25 5.8 0.64 A
2029FT PM Peak Hour
95% Queue (m)
Delay (s/vehicle)
V/C Ratio LOSInt. Delay (s/vehicle)
Int. LOS
103.0 22.2 0.92 C
<25 6.7 0.06 A
71.5 23.5 0.90 C
<25 7.8 0.64 A
<25 6.5 0.76 A
<25 3.9 0.04 A
<25 6.7 0.71 A
<25 4.2 0.49 A
EB Louis St. Laurent Ave
NB Tremaine Rd. [NB Tremaine]
WB Louis St. Laurent Av
[NB Tremaine]
A24%
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
19 C3%EB Louis St. Laurent Ave
WB Louis St. Laurent Av
100% y-int. Adjustment
SB Tremaine Rd.
6
NB Tremaine Rd.
100% y-int. Adjustment
NB Tremaine Rd. [WB LSL]
WB Louis St. Laurent Av
SB Tremaine Rd.
<5 A29%EB Louis St. Laurent Ave
NB Tremaine Rd.
WB Louis St. Laurent Av
Intersection Residual Capacity
85% y-int. Adjustment
SB Tremaine Rd.
11 B7%EB Louis St. Laurent Ave
NB Tremaine Rd. [WB LSL]
WB Louis St. Laurent Av
EB Louis St. Laurent Ave
SB Tremaine Rd.
EB Louis St. Laurent Ave
NB Tremaine Rd.
WB Louis St. Laurent Av
SB Tremaine Rd.
Appendix ESite Plan
Vaca
nt /A
gric
ultu
ral
Prop
osed
Res
iden
tial
BL
OC
K 4
74
MIN
OR
S
UB
-N
OD
E
1.4
8h
a (3
.6
6a
c)
Vacant /Agricultural
C
. N
. R
a
ilw
a
y
Prop
osed
SWM
P
Prop
osed
Elem
enta
ry S
choo
l
Prop
osed
Res
iden
tial
BL
OC
K 4
23
6.4
m S
.T
.H
.
5 U
nits
BL
OC
K 4
24
6.4
m S
.T
.H
.
6 U
nits
BL
OC
K 4
25
6.4
m S
.T
.H
.
6 U
nits
BL
OC
K 4
76
ST
OR
MW
AT
ER
MA
NA
GE
ME
NT
P
ON
D
2.5
4h
a (6
.2
8a
c)
BL
OC
K 4
75
EL
EM
EN
TA
RY
S
CH
OO
L; 0
.7
2h
a (1
.7
8a
c)
Total: 2.84ha (7.02ac)
BL
OC
K 4
84
WO
OD
LO
T
2.2
9h
a (5
.6
6a
c)
BL
OC
K 4
79
ST
OR
MW
AT
ER
MA
NA
GE
ME
NT
P
ON
D
1.5
2h
a (3
.7
6a
c)
B
L
O
C
K
4
8
6
C
R
E
E
K
B
L
O
C
K
0
.
8
6
h
a
(
2
.
1
3
a
c
)
B
L
O
C
K
4
8
7
C
R
E
E
K
B
L
O
C
K
1
.
6
7
h
a
(
4
.
1
3
a
c
)
BL
OC
K 5
03
RO
AD
WID
EN
IN
G
0.0
4h
a
(0
.1
0a
c)
KOVACHIK BOULEVARD (STR. 'C')
BE
RG
AM
OT
A
VE
NU
E (S
TR
. 'B
')
BO
YD
L
AN
E (S
TR
. 'D
')
W
A
T
E
R
C
R
E
S
S
W
A
Y
(
S
T
R
.
"
F
"
)
PE
R
IW
IN
KLE
P
LA
C
E
(S
TR
. "H
")
CE
LA
ND
IN
E T
ER
RA
CE
(S
TR
. "G
")
TH
OR
NB
OR
RO
W C
OU
RT
(ST
R. "I")
K
I
T
C
H
E
N
C
O
U
R
T
(
S
T
R
.
"
L
"
)
STRAWBERRY LANDING
(STR. "M")
B
U
R
D
O
C
K
C
O
U
R
T
(
S
T
R
.
"
N
"
)
C
H
A
M
O
M
IL
E
C
R
E
S
.
(S
T
R
. "O
")
B
U
T
T
E
R
C
U
P
C
O
U
R
T
(
S
T
R
.
"
P
"
)
BL
OC
K 4
80
7.5
m S
WM
P B
UF
FE
R
0.1
0h
a (0
.2
5a
c)
BL
OC
K 4
89
1
0M
E
NV
IR
ON
ME
NT
AL
BU
FF
ER
B
LO
CK
0.2
1h
a (0
.5
2a
c)
BL
OC
K 4
90
1
0M
E
NV
IR
ON
ME
NT
AL
BU
FF
ER
B
LO
CK
0.2
3h
a (0
.5
7a
c)
BL
OC
K 4
92
1
0M
E
NV
IR
ON
ME
NT
AL
BU
FF
ER
B
LO
CK
0.4
1h
a (1
.0
1a
c)
BL
OC
K 4
91
1
0M
E
NV
IR
ON
ME
NT
AL
BU
FF
ER
B
LO
CK
0.3
8h
a (0
.9
4a
c)
BL
OC
K 5
05
RE
SE
RV
E B
LO
CK
0.0
1h
a (0
.0
2a
c)
BL
OC
K 5
01
5
M T
RA
IL
B
LO
CK
0.1
2h
a (0
.3
0a
c)
BR
IT
AN
NIA
R
OA
D
TR
EM
AIN
E R
OA
D
BL
OC
K 5
00
5
M T
RA
IL
BL
OC
K
0.1
9h
a
(0
.4
7a
c)
BL
OC
K 4
85
W
OO
DLO
T &
P
SW
BU
FF
ER
0.60
ha
(1
.4
8a
c)
TH
IM
BLE
WE
ED
C
OU
RT
(S
TR
. "J")
BL
OC
K 4
30
6.4
m S
.T
.H
.
5 U
nits
BLO
CK
435
6.4m
S
.T
.H
.
7 U
nits
TW
IN
FLO
WE
R P
LA
CE
(S
TR
. "K
")
BLO
CK
436
6.4m
S
.T
.H
.
6 U
nits
B
L
O
C
K
4
3
3
6
.
4
m
S
.
T
.
H
.
4
U
n
i
t
s
BLO
CK
434
6.4m
S
.T
.H
.
8 U
nits
B
L
O
C
K
4
2
9
6
.
4
m
S
.
T
.
H
.
7
U
n
i
t
s
BL
OC
K 4
06
6.4
m S
.T
.H
.
6 U
nits
B
L
O
C
K
4
3
2
6
.
4
m
S
.
T
.
H
.
5
U
n
i
t
s
BL
OC
K 4
72
6.4
m B
.T
.B
.
12
U
nits
BL
OC
K 4
71
6.4
m B
.T
.B
.
8 U
nits
BL
OC
K 4
73
6.4
m B
.T
.B
.
8 U
nits
BL
OC
K 4
10
6.4
m S
.T
.H
.
4 U
nits
BLO
CK
431
6.4m
S
.T
.H
.
3 U
nits
BL
OC
K 4
08
6.4
m S
.T
.H
.
4 U
nits
BL
OC
K 4
07
6.4
m S
.T
.H
.
4 U
nits
BL
OC
K 4
09
6.4
m S
.T
.H
.
6 U
nits
BL
OC
K 4
05
6.4
m S
.T
.H
.
4 U
nits
KIT
CH
EN
C
OU
RT
(S
TR
. "L")
BL
OC
K 4
78
ST
OR
MW
AT
ER
MA
NA
GE
ME
NT
P
ON
D
0.6
6h
a (1
.6
3a
c)
BL
OC
K 4
77
ST
OR
MW
AT
ER
MA
NA
GE
ME
NT
P
ON
D
0.8
8h
a (2
.1
7a
c)
BL
OC
K 4
83
7.5
m S
WM
P B
UF
FE
R
0.1
6h
a (0
.4
0a
c)
BL
OC
K 4
82
7.5
m S
WM
P B
UF
FE
R
0.0
9h
a (0
.2
2a
c)
BLO
CK
508
0.3m
R
ES
ER
VE
BLO
CK
507
0.3m
R
ES
ER
VE
C
E
N
TR
E
LIN
E
O
F 47m
R
O
W
BL
OC
K 5
04
RO
AD
W
ID
EN
IN
G
0.0
5h
a (0
.1
2a
c)
BL
OC
K 4
98
GR
AD
IN
G
BU
FF
ER
B
LO
CK
0.0
5h
a (0
.1
2a
c)
BL
K. 5
02
3M
W
ALK
WA
Y
0.01ha (0.0
2ac)
S
A
V
O
L
I
N
E
B
O
U
L
E
V
A
R
D
(
S
T
R
E
E
T
'
A
'
)
S
T
R
E
E
T
"
Q
"
S
T
R
E
E
T
"
Q
"
S
T
R
E
E
T
"W
"
S
T
R
E
E
T
"
U
"
S
T
R
E
E
T
"V
"
BL
OC
K 4
88
VIL
LA
GE
SQ
UA
RE
0.3
0h
a
(0
.7
4a
c)
ST
RE
ET
"S
"
ST
RE
ET
"R
"
ST
RE
ET
"T
"
ST
RE
ET
"Q
"
B
L
O
C
K
4
5
36
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
5
76
.4
m
S
.T
.H
.
7
U
n
its
B
L
O
C
K
4
5
8
6
.4
m
S
.T
.H
.
7
U
n
its
BLO
CK
459
6.4m
S
.T
.H
.
6 U
nits
BLO
CK
460
6.4m
S
.T
.H
.
6 U
nits
BLO
CK
461
6.4m
S
.T
.H
.
5 U
nits
B
L
O
C
K
4
6
2
6
.
4
m
S
.
T
.
H
.
3
U
n
i
t
s
BLO
CK
463
6.4m
S
.T
.H
.
7 U
nits
BLO
CK
464
6.4m
S
.T
.H
.
6 U
nits
B
L
O
C
K
4
6
5
6
.4
m
S
.T
.H
.
7
U
n
its
BLO
CK
466
6.4m
S
.T
.H
.
6 U
nits
BLO
CK
467
6.4m
S
.T
.H
.
8 U
nits
BLO
CK
468
6.4m
B
.T
.B
.
10 U
nits
BLO
CK
469
6.4m
B
.T
.B
.
16 U
nits
BLO
CK
470
6.4m
B
.T
.B
.
14 U
nits
BL
OC
K 4
81
7.5
m S
WM
P B
UF
FE
R
0.1
4h
a (0
.3
5a
c)
BL
OC
K 4
93
AC
OU
ST
IC
BU
FF
ER
B
LO
CK
0.0
2h
a (0
.0
5a
c)
BL
OC
K 4
95
AC
OU
ST
IC
BU
FF
ER
B
LO
CK
0.0
2h
a (0
.0
5a
c)
BL
OC
K 4
94
AC
OU
ST
IC
BU
FF
ER
B
LO
CK
0.0
2h
a (0
.0
5a
c)
BL
OC
K 4
99
RA
IL
WA
Y
BU
FF
ER
B
LO
CK
0.8
6h
a (2
.1
3a
c)
BL
OC
K 5
06
RE
SE
RV
E B
LO
CK
0.1
4h
a (0
.3
5a
c)
BL
OC
K 4
96
AC
OU
ST
IC
BU
FF
ER
B
LO
CK
0.0
2h
a (0
.0
5a
c)
BL
OC
K 4
97
GR
AD
IN
G
BU
FF
ER
B
LO
CK
0.0
2h
a (0
.0
5a
c)
B
E
R
G
A
M
O
T
A
V
E
N
U
E
(
S
T
R
E
E
T
'B
')
W
A
T
E
R
C
R
E
S
S
W
A
Y
(
S
T
R
.
"
F
"
)
K
O
V
A
C
H
IK
B
O
U
L
E
V
A
R
D
(
S
T
R
.
'C
')
CE
LA
ND
IN
E T
ER
RA
CE
(S
TR
. "G
")
B
U
T
T
E
R
C
U
P
C
O
U
R
T
(
S
T
R
.
"
P
"
)
BU
RD
OC
K C
OU
RT
(S
TR
. "N
")
TH
IM
BLE
WE
ED
C
OU
RT
(S
TR
. "J")
32
2
321
87
36
83
86
1
14
5
3
2
6
10
4
89
7
11
13
16
12
15
39
38
37
40
41
57
61
65
60
62
66
68
69
70
72
71
76
74
73
78
75
77
79
80
81
94
89
11
8
91
93
90
88
95
10
6
10
3
10
2
10
4
105
107
11
7
14
2
11
9
15
6
14
4
14
1
163
14
3
14
5
14
7
14
6
148
14
9
15
3
15
5
15
1
15
4
15
8
159
16
0
16
1
16
4
16
5
19
2
19
8
19
9
19
1
20
4
197
196
19
3
195
19
4
21
0
20
9
21
1
20
3
226
20
5
20
1
20
6
20
7
202
21
7
21
6
218
21
5
21
3
21
4
22
1
21
2
23
4
23
7
222
22
5
22
4
22
7
24
5
23
1
236
23
5
23
2
23
8
26
0
24
1
23
9
257
24
2
24
3
25
2
24
6
240
24
4
250
25
1
25
6
25
4
261
25
8
265
268
263
266
26
9
281
27
0
27
1
28
3
28
4
27
8
28
0
28
2
29
6
286
29
3
285
28
8
28
7
294
291
29
0
29
7
29
9
29
8
30
2
30
1
30
4
30
5
30
7
31
0
319
30
9
316
31
3
31
5
31
4
318
32
0
32
3
32
4
325
63
58
59
67
15
0
64
10
1
15
2
92
16
2
11
6
220
15
7
16
6
22
8
20
0
21
9
230
20
8
22
3
249
248
22
9
255
26
2
247
23
3
25
9
25
3
26
7
27
9
30
0
303
26
4
29
5
31
1
29
2
32
6
30
6
30
8
31
7
31
2
10
9
11
0
10
8
17
23
18
20
19
22
21
26
25
32
82
24
33
34
35
85
84
112
11
31
14
12
2
11
5
11
1
120
12
11
23
126
125
12
81
31
12
4
12
7
12
9132
13
4
13
0
13
61
33
13
5
14
0
13
81
37
17
0
13
9
169
16
7
172
17
1
17
4
17
3
17
6
17
5
181
17
7
179
17
8
27
2
180
18
2
27
42
73
275
27
6
27
7
28
9
27
28
29
30
31
18
3
18
4
18
5
18
6
18
7
18
8
18
9190
35
5
35
4
35
3
352
36
3
36
4
36
5
36
6
36
7
36
8
36
9
37
0
37
1
372
37
33
74
37
5
37
6
37
7
37
8
37
9
38
0
38
1
38
2
383
38
4
38
5
38
6
38
7
38
8
38
9
39
0
39
1
392
39
3
39
4
39
5
39
6
39
7
39
8
39
9
40
0
40
1
40
2
40
3
40
4
16
8
97
98
99
100
96
327
32
8
32
9
33
0
33
1
33
2
33
3
33
4
33
5
33
6
33
7
33
8
339
34
0
341
34
2
34
3
34
4
345
34
6
34
7
34
8
34
9
35
0
35
1
356
357
358
359
360
36
1
36
2
B
L
O
C
K
4
3
76
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
3
8
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
3
9
6
.4
m
S
.T
.H
.
7
U
n
its
B
L
O
C
K
4
4
0
6
.4
m
S
.T
.H
.
8
U
n
its
B
L
O
C
K
4
4
1
6
.4
m
S
.T
.H
.
4
U
n
its
B
L
O
C
K
4
4
2
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
4
3
6
.4
m
S
.T
.H
.
7
U
n
its
B
L
O
C
K
4
4
4
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
4
56
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
4
6
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
4
7
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
4
8
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
4
9
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
5
0
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
5
1
6
.4
m
S
.T
.H
.
6
U
n
its
B
L
O
C
K
4
5
2
6
.4
m
S
.T
.H
.
7
U
n
its
B
L
O
C
K
4
5
56
.4
m
S
.T
.H
.
4
U
n
its
B
L
O
C
K
4
5
46
.4
m
S
.T
.H
.
4
U
n
its
B
L
O
C
K
4
5
66
.4
m
S
.T
.H
.
6
U
n
its
BLO
C
K 4
19
6.4
m
S.T
.H
.
8 U
nits
BLO
C
K 4
20
6.4
m
S.T
.H
.
8 U
nits
BLO
C
K 4
17
6.4
m
S.T
.H
.
6 U
nits
BLO
C
K 4
18
6.4
m
S.T
.H
.
6 U
nits
BLO
C
K 4
16
6.4
m
S.T
.H
.
6 U
nits
BLO
C
K 4
15
6.4
m
S.T
.H
.
4 U
nits
BL
OC
K 4
11
6.4
m S
.T
.H
.
8 U
nits
BL
OC
K 4
12
6.4
m S
.T
.H
.
8 U
nits
BL
OC
K 4
13
6.4
m S
.T
.H
.
6 U
nits
B
L
O
C
K
4
1
4
6
.
4
m
S
.
T
.
H
.
7
U
n
it
s
BL
OC
K 4
22
6.4
m S
.T
.H
.
4 U
nits
BL
OC
K 4
21
6.4
m S
.T
.H
.
3 U
nits
B
L
O
C
K
4
2
7
6
.4
m
S
.T
.H
. 6
U
n
its
B
L
O
C
K
4
2
6
6
.
4
m
S
.
T
.
H
.
7
U
n
it
s
BLO
C
K 4
28
6.4
m
S.T
.H
.
6 U
nits
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
BLO
CK
509
0.3m
R
ES
ER
VE
ON
E O
F TH
E G
RE
AT
GU
LF G
RO
UP
OF
CO
MP
AN
IES
(g) S
HO
WN
IS
A
VA
ILA
BLE
(i) S
OIL IS
C
LA
Y LO
AM
(j) S
HO
WN
A
RE
A
VA
ILA
BLE
(l) S
HO
WN
(b) S
HO
WN
(c) S
HO
WN
(a) S
HO
WN
SU
BJE
CT
LA
ND
S
(e) S
HO
WN
(f) S
HO
WN
KE
Y P
LAN
R
E
G
IO
N
A
L R
O
A
D
25
SE
CTI
ON
51
(17)
OF
THE
PLA
NN
ING
AC
T
(d) T
HE
LA
ND
IS
T
O B
E
TO
T
HE
S
CH
ED
ULE
US
ED
A
CC
OR
DIN
G
SC
HE
DU
LE O
F A
DD
ITIO
NA
L IN
FOR
MA
TIO
N
(h) M
UN
IC
IP
AL W
AT
ER
(k) A
LL M
UN
IC
IP
AL
DE
RR
Y R
OA
D
BR
IT
AN
NIA
R
OA
D
TR
EM
AIN
E R
O
AD
FIR
ST
LIN
E
DR
AFT
PLA
N O
F S
UB
DIV
ISIO
N
Pon
y P
ines
Dev
elop
men
t Inc
.
Part of Lot 6, C
oncession 1
(G
eo
gra
ph
ic T
ow
nsh
ip
o
f T
ra
fa
lg
ar)
Tow
n of M
ilton, R
egional M
unicipality of H
alton
OF
LA
ND
U
SE
S
ER
VIC
E
Scale 1:1500
(24x36)
APRIL 1, 2020
NOTES:
-C
orner radii:
-W
here Local R
OW
intersects w
ith C
ollector - 7.5m
-W
here Local R
OW
intersects w
ith Local R
OW
- 5m
-T
rem
aine R
oad and B
ritannia R
oad D
aylight T
riangles - 15.0m
x 15.0m
-S
DE
F
actors:
2012 P
rogram
: S
ingle/S
em
i D
etached Lots - 1.0, S
treet T
ow
ns - 0.73
Back-to-B
ack/H
igh D
ensity - 0.50
2020 P
rogram
: S
ingle/S
em
i D
etached Lots - 1.0, S
treet T
ow
ns - 0.76
Back-to-B
ack/H
igh D
ensity - 0.45
SU
RV
EY
OR
'S
C
ER
TIF
IC
AT
E
OW
NE
R'S
C
ER
TIF
IC
AT
E
24T-
1400
3/M
SC
HE
DU
LE O
F LA
ND
US
E
www.ghd.com