pointview presentation for gridweek asia 2012 by n.s. · pdf filehsil/re-conductoring with...
TRANSCRIPT
EHV Transmission
Issues, Technology & Growth
Presentation by N. S. Sodha
Executive DirectorLoad Despatch & Communication Department GridWeek Asia 2012
Indian Power System – An overview
Future Transmission Plan
Cross-Country Interconnection
Issues and Challenges
Outline
GridWeek Asia 2012
NER
ER
NR
WR
SR AN
DA
MA
N &
NIC
OB
AR
LAK
SH
AD
WE
EP
All figs. in MW
Indian Power System - Present
Installed Capacity –174,000 MW
Peak Demand –120,000 MW
Growth rate – 8-9% per annum
Per capita consumption– 750 kwh
Indian Power Sector- Overview
GridWeek Asia 2012
4
NEW Grid
SouthGrid
South
West
North
East
Northeast
Five Regional GridsFive Frequencies
October 1991East and Northeast
synchronized
March 2003West synchronized
With East & Northeast
August 2006North synchronized
With Central Grid
Central Grid
Five Regional GridsTwo Frequencies
Installed Capacity 174 GW
MERGINGOF
MARKETS
GridWeek Asia 2012
• 765kV/400kV lines: about1,03,000 ckms
• 220kV lines: about 132,000ckms
• HVDC Bipole(±500kV): 7,500ckms – 3 nos.
• HVDC Back-to-back: 7 nos.(3000MW)
• FSC – 22 nos.; TCSC – 6nos.
Transmission Network - Present
POWER MAP OF INDIA
GridWeek Asia 2012
National Grid – A Continuing Process
National Grid – Present
Inter-regional Capacity –22,400MW
GridWeek Asia 2012
NLDCEnsure integrated operation of National Grid
RLDCEnsure integrated operation of Regional Grid
SLDC Ensure integrated operation of State Grid
31
5
Grid Management Hierarchy
GridWeek Asia 2012
Future Growth Plan
GridWeek Asia 2012
Need of new initiatives in Transmission
Transmission growth driven by
Strong GDP growth – requiring
massive expansion of Power Sector
Uneven distribution of energy
resources
Change in generation profile
Growth Drivers
GridWeek Asia 2012
Power Supply Scenario
100
152
218
437
323
2007 2012 2017 2022 2027Year
GW
Peak Demand
132220
306
575
425
2007 2012 2017 2022 2027Year
GW
Installed Capacity Requirement
End of X plan
During 12th
planDuring 13th
planDuring 11th
plan
Future Power Scenario
205
GridWeek Asia 2012
Coal – In Central India ‾ Chhattisgarh : 58000 MW‾ Orissa : 30000 MW‾ Jharkhand : 15000 MW‾ Madhya Pradesh:16000 MW
Hydro – In North Eastern & Northern Himalayan region
Coastal based‾ Andhra Pradesh: 24000 MW‾ Tamil Nadu : 10000 MW‾ Gujarat : 11000 MW
Expected Installed Capacity (2025) : 6,00,000MW
Lara
Partabpur
Talcher/Ib Valley
Krishnapatnam
NEPAL
KorbaBhopalIndore
Tadri
Girye
Kaiga
Thiruvananthapuram
Pipavav
Kudankulam
SR
Bangalore
Kayamkulam
WR
Tarapur
Mumbai
Cuddalore
Ennore
Akaltara
Raipur
Hyderabad
RAPP
Gandhinagar
Mudra
Delhi
Ludhiana
NR
Jaipur
Jammu
Sasan
Vindhyachal
Lucknow
Load Centre Based GenerationUltra-Mega Generation
Hydro Based Generation
Coastal Generation
Coal Based generation
Nuclear generation
BhubaneswarDarlipali
Vizag
Simhadri
LEGEND
Load-Centre
NERGuwahati
Koderma
SIKKIM
Kolkata
ERPatna
NECKCHICKEN
BHUTAN
DESHBANGLA
MY
AN
MM
AR
Mangalore
KozhikodeSouth MadrasChennai
Energy resources (coal, water etc.) unevenly distributed
Energy Resources Map
GridWeek Asia 2012
36874
26783
15043
28600
14400
57000
0
10000
20000
30000
40000
50000
60000
Central Sector State Sector Private Sector
XI Plan
XII Plan
Change in Generation Profile
Central Sector State Sector Private Sector Total
36874 (47%) 26783(34%) 15043(19%) 78700
28600 (28%) 14400(15%) 57000 (57%) 100000
XI
XII GridWeek Asia 2012
Need of new initiatives in Transmission
Increased role of ISTS power transfer
Need of long distance Transmission system
Minimum use of land and Right-of-Way
Optimal cost per MW transmission
Optimal Transmission Losses
Adequate margin – to cater trading, contingencies
Implementation – Equipment availability,
manpower
Future Transmission Planning- Consideration
GridWeek Asia 2012
High Voltage line
Increase the capacity of trans. corridor through
HSIL/re-conductoring with HTLS /Upgradation
Utilisation of transmission lines upto full thermal
capacity – Series capacitors, SVC, FACTS
Optimization of Tower design – tall tower, multi-ckt. tower
GIS substation
EHVAC : 400kV 765kV 1200kV
HVDC : 500kV 800kV
Technology being Adopted
GridWeek Asia 2012
Road Map for Indian Power SystemHigh Power Intensity Corridor
200 ft. 750 ft.
RoW (m)
Capacity
(MW)
MW/m RoW
400kV S/c 52 500 9.6
400kV D/c 46 1000 21.8
765kV S/c 64 2500 39
765kV D/c 69 4000 58
800kV DC 70 6000 85
64 m230 m
GridWeek Asia 2012
1977 1990 2000 2012 2017-18
Voltage (kV)
Year
220kV400kV
500kVHVDC
765kV800kVHVDC
Increase in Transmission voltage
Complexities with high voltage AC system
• Reactive Power Management
• Availability of switchgear
• Corona Loss
• Sustainability of grid during contingencies
Voltage Upgradation1200kV
GridWeek Asia 2012
Road Map for Indian Power System
• Creation of 11 High Capacity Trans. Corridors for 55IPPs (55,000 MW) – about Rs. 65,000 Cr (USD 14 Bn)
• Ultra Trans. System for 6 UMPPs (24000MW) – Rs.29,000 Cr (USD 6 Bn)
• Transmission system for DVC generation projects(5000MW) – Rs. 11,000 Cr. (USD 2.5 Bn)
• Transmission system for Evacuation of power fromNER & Bhutan – Rs. 11,000 Cr. (USD 2.5 Bn)
Few Major Transmission Projects
GridWeek Asia 2012
Proposed 11 nos. High Capacity Transmission Corridors for IPP Projects
GridWeek Asia 2012
National Grid – A Continuing Process
2240028000
70000
0
20000
40000
60000
80000
Present By 2011-12 By 2016-17
Emerging National Grid
Expected Cumulative Growth of Inter-regional capacity in MW
GridWeek Asia 2012
Long-term Open Access Applications received: 187 nos.(incl. UMPP)
– Capacity : about 1,77,000 MW – Generation commissioning schedule indicated as 2011-12 to 2016-17
• All the applications processed. Based on the progress of projects,LTOA granted as under:
– LTOA granted : 1,16,257 MW (135 nos.)
System already in place : about 43,435 MW
System finalised : about 72,822 MW
(11 High Capacity Corridors , UMPP/other strength.)
– Balance: abt. 61000 MW, 52 Nos LTA applications processed.Progress of Generation projects not upto the mark. It was decided toclose/review the application based on subsequent progress.
Long-term Open Access Applications from IPPs for generation projects
GridWeek Asia 2012
Road Map for Indian Power System
• Lot of uncertainty in actual materialization ofgeneration capacity compared to the projected one
• Non firming up of end customers of the power
• Penalty clause as per BPTA in case of Transmissionnot coming up by the committed date
• Commercial disputes in case Tr. system materializesbut generation gets delayed/deferred
• Technical problems in operation of the system inabsence of planned generation
Issues with Tr. system for IPPs
GridWeek Asia 2012
Expansion Programme for next 5-6 years(POWERGRID)
Transmission Line : 50,000 ckm
• 765kV – 17120 ckm
• 400kV – 22000 ckm
• 220kV/132kV – 1230 ckm
• HVDC - 9630 ckm
Substations : about 109,400 MVA (60 nos.)
• 765kV – 88,000 MVA
• 400kV – 7560 MVA
• 220kV/132kV – 840 MVA
• HVDC - 13,000 MVA
Estimated Investment – Rs. 120,000 Cr (USD 26 Bn) GridWeek Asia 2012
Equipment Requirement (POWERGRID)
765 kV 400 kV 220/132 KV
ICT 500 MVA , 1 , -175 nos
500 MVA , 3 , - 15 nos
100 MVA , 3 , - 9 nos
Circuit Breaker
500 nos 460 nos 70 nos
Isolator 1100 nos 1140 nos 210 nos
Current Transformer
1470 nos 1572 nos 140 nos
CVT 720 nos 684 nos 288 nos
Surge Arrestor 1200 nos 900 nos 200 nos
GridWeek Asia 2012
Line Material Requirement(POWERGRID)
Conductor : 5 to 6 lakh kms
Tower Parts : 25 lakh to 30 lakh MT
Insulators : 350 to 400 lakhs disc units
Hardware fittings : 3.5 to 4 lakhs sets
Spacer Dampers : 20-25 lakh nos
GridWeek Asia 2012
Cross-Country Interconnection
GridWeek Asia 2012
• Geographically widely
spread Indian Grid can
facilitate interconnections
with Neighboring countries
• India can provide a good
demand market to harness
energy resources of other
countries
• Optimal utilisation of
energy resources
India
Nepal
Bangladesh
Bhutan
Interconnection with neighbouring Countries
GridWeek Asia 2012
• 220kV Interconnection from Chukha HEP (4x84 MW)
• 132kV Interconnection from Kurichu HEP (4x15 MW)
• 400kV Interconnection from Tala HEP (6x170 MW = 1020 MW)
• Future Interconnection planned with Punatsanchu HEP I & II
India – Bhutan: Interconnection
GridWeek Asia 2012
EVACUATION FROM POWER PROJECTS IN BHUTAN
LEGEND
400 KV LINE220 KV LINE132 KV LINE
Future Transmission System
SIKKIM
ASSAM
ARUNACHALPRADESH
BHUTAN
BANGLADESH
BTPS
Siliguri
Balipara
BornagarSalakati
Dhaligaon
Agia
Rangia
Guwahati
Birpara
Dalkhola
Purnea
GeylegphugNganglam
Tintibi
Siliguri
Tala(1020MW)
(132 KV)
(220
KV
)
Kurichhu(60MW)
Pemaghatshel
Deothang
KanglungKilikhar
Tangmachu
Amingaon
Gohpur
Teesta-V
Malbase
Punatsangchu-I(1200MW)
Kishan
HVDCTO
AGRA(NR)
Bongaigaon
Ganj
Teesta-III / Rangpo
Punatsangchu-II(990MW)
(208MW)Nikhachu
(336MW)Chukha
(4000MW)Sankosh
Alipurduar
+ 800kV 6000MW HVDC Bipole line
BishwanathChariyali
Mangdechu(720MW)
Chamkharchu-I(670MW)
Quad Moose
Qua
d
Tali-buli
JigmelingLhamoizingkha
+ 800kV 6000MW HVDC Bipole line
(900MW)Wangchu
GridWeek Asia 2012
BOGRASOUTH
BHERAMARA
NAOGAON
NIAMATPUR
FARRAKA
SUBHASGRAM
KATWA
GOKARNA
JEERATKHULNA(SOUTH)
BOTTAIL
BAHARAMPUR
CH. NAWABGANJ
RAGHUNATHGANJ
KA
HA
LGA
ON
SAGARDIGHI
RAJSHAHI
BAHARAMPURISHURDI
NATORE
KHEJURIA
FARIDPUR
BAGHABARI
GHORASAL
MA
DH
OP
UR
SHAHJAD
PABNA PUR
SIRAJGANJ
BOGRA
INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS
400 kV230 kV132 kV
THE PROJECTLEGEND
BAKRESHWAR
KOLAGHAT
BANGLADESH
INDIA
400kV D/c
(400 KV)
MALDA
DHULIAN
DURGAPUR
ExistingUnder Constr. / Future
JAYPURHAT BARAPUKURIA
GridWeek Asia 2012
• Scope
– Establishment of 400kV Sw. Stn. at
Baharampur(India) by LILO of Farakka-Jeerat
400kV S/c line
– Baharampur(India) – Bheramara(Bangladesh)
400kV D/c line – 85 kms + 40 kms.
– Installation of 500MW HVDC back-to-back station
at Bheramara(Bangladesh).
• The target date of commissioning : 2012
India – Bangladesh Interconnection
GridWeek Asia 2012
185 Kms
50 Kms
150 Kms
Proposed Route for Interconnection
Madurai
Rameshwaram
Anuradhapura
Talaimannar
India – Sri Lanka Interconnection
GridWeek Asia 2012
Road Map for Indian Power System
• Creation of reliable repairing facilities & developmentof indigenous manufacturing capacity
• Need to establish reliable testing facilities for EHV andUHV
• Development of Smart Grid for real-time monitoring ofdynamic state and optimal utilisation of facilities
Issues & Challenges
GridWeek Asia 2012
Road Map for Indian Power System
• Issues concerning availability of RoW and
same are becoming critical –– Resistance of people, terrains in areas of mountains and
forest
• Sector to grow from 174 GW to 600 GW in next 20years – Even 765kV system may not be good enough.New methods have to be found out
• Cable manufacturers need to Research & developcables which could be more cost effective
• Increasing magnitude of power transmission & createnew challenges of proper O&M
Issues & Challenges
GridWeek Asia 2012