Poinciana-Area CFX Projects
— June 16, 2021 —
Dana Chester, PE, CFX Manager of EngineeringRalph Bove, Volkert, Inc.
PRFSC
1
![Page 2: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/2.jpg)
About CFX
• 125 miles of expressway
•
• Orange, Osceola, Seminole, Lake,
Brevard
• All CFX operations are funded by
tolls – no taxes
• $3.2 Billion 5-Year Work Plan
2
![Page 3: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/3.jpg)
Planned Projects In The Poinciana Area
• Southport Connector PD&E Study
• SR 538 Poinciana Parkway Widening
• SR 538 Poinciana Parkway Extension
• CR 532/Osceola Polk Line Road Widening
3
![Page 4: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/4.jpg)
Southport Connector PD&E Study
444
![Page 5: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/5.jpg)
Southport Connector PD&E Study:
Goals and Objectives
• Improve connections to existing corridors
• Enhance mobility of growing population and economy
• Relieve capacity constraints along Cypress Parkway
• Accommodate future transit options
o Local, state and regional plans
o Close coordination with future land use development
• Promote regional connectivity
• Enhance evacuation and emergency service
5
![Page 6: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/6.jpg)
Southport PD&E Study: Decision Points
Connection to Poinciana Parkway/ Pleasant Hill Road
Connection to Canoe Creek Road
Crossing Reedy CreekConnection to
Florida’s Turnpike
6
![Page 7: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/7.jpg)
Southport PD&E Study Process
• Programming Final Design phase
• Identify opportunities for continued involvement
• Public Involvement
• Engineering Analysis
• Environmental Analysis
• Study Documents
PUBLIC INVOLVEMENT
• Local Governments• Non-governmental
Organizations• Community Leaders• Business Leaders• Advisory Groups
ENVIRONMENTALANALYSIS
• Social• Cultural• Natural• Physical• Agency Coordination
STUDYDOCUMENTS
• Environmental Documents
• Support Documents• Concept Plans• Pass the Torch
PRELIMINARY ENGINEERING
•Data Collection• Interchange Concepts•Roadway•Structures•Drainage•Lighting/Utilities
7
![Page 8: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/8.jpg)
Environmental Constraints
DWP
Conservation Easements
Public Lands
Floodplains
Surface Waters
Wetlands
Study Area
Mitigation Banks8
![Page 9: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/9.jpg)
South Lake Toho Master Plan
Green Island Development Plan
East Lake Toho Development Plan
9
Social Constraints
![Page 10: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/10.jpg)
10
Preliminary Alternatives
![Page 11: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/11.jpg)
11
Social Constraints: Cypress Parkway
![Page 12: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/12.jpg)
Conceptual Rendering
Design speed = 70 mph
12
*Results from Southport Connector CF&M Study
Poinciana Parkway to Pleasant Hill Road
![Page 13: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/13.jpg)
Cypress Parkway Segment
Legend
Cypress Parkway
Expressway
Preliminary: Subject to Change
13
*Results from Southport Connector CF&M Study
![Page 14: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/14.jpg)
East of Pleasant Hill Road
Key Issues: Environmental/Cultural
Preliminary: Subject to Change14
*Results from Southport Connector CF&M Study
![Page 15: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/15.jpg)
Typical Section - Reduced
East of Pleasant Hill Road to end of Reedy Creek Bridge
Design speed = 70 mph15
*Results from Southport Connector CF&M Study
![Page 16: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/16.jpg)
Typical SectionEast of Reedy Creek Bridge to Canoe Creek Road
Design speed = 70 mph
16
*Results from Southport Connector CF&M Study
![Page 17: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/17.jpg)
Southport Connector PD&E Study: Next Steps
17
Click to add textClick to add text• Study beganto add text
• Study began: Aug. 2020
• Study Area Revised: Feb. 2021
• Kickoff mailing: May 2021
• Alternatives Workshop: Oct. 2021
• Public Hearing: Mar. 2022
• Board Presentation: June 2022
![Page 18: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/18.jpg)
SR 538/Poinciana Parkway Widening Project
18
![Page 19: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/19.jpg)
Ronald Reagan Parkway to CR 580/Cypress Parkway
• Construction began in spring 2021
• Completion expected in fall 2023
• Widening 7.2 miles
• Four proposed sound walls
19
![Page 20: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/20.jpg)
EXISTINGEXISTING
Marigold Avenue Interchange
20
![Page 21: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/21.jpg)
SR 538/Poinciana Parkway Extension
21
![Page 22: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/22.jpg)
SR 538/Poinciana Parkway Extension
22
• Design began June 2020
• Two project segments
• Nearly half a mile of bridging over
Reedy Creek Mitigation Bank
• Interchanges at US 17/92 and CR 532
![Page 23: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/23.jpg)
Segment 1 Segment 2
23
![Page 24: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/24.jpg)
CR 532/Osceola Polk Line Road Widening
24
![Page 25: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/25.jpg)
End Project
Begin Project
Polk County
Osceola County
• CR 532 (Osceola Polk Line Road)
• In Osceola County
• From S. Old Lake Wilson Road / Lake Wilson Road to US 17/92
• Approximately three miles
CR 532/Osceola Polk Line Road Widening
25
![Page 26: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/26.jpg)
CR 532
Existing Typical Section
26
![Page 27: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/27.jpg)
CR 532
Alternative 1
Typical Section
27
![Page 28: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/28.jpg)
CR 532
Alternative 2
Typical Section
28
![Page 29: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/29.jpg)
CR 532
Alternative 3 Typical Section
29
![Page 30: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/30.jpg)
Access Management
Full Access Directional Median Opening
30
![Page 31: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/31.jpg)
CR 532: DRAFT Access Management Plan
• S. Old Lake Wilson Rd./Lake Wilson Rd.
• Old Lake Wilson Road (Polk)
• Sullivan Road
• Sandy Ridge Road
• Poinciana Parkway Extension
• Duke Energy Intercession City Plant Access
Drive
• US 17/92
• Tanglewood Drive
• 21 Palms RV Resort Access Drive
• Sabal Trail Access Drive
• Sandy Oak Drive
*Access points (median openings and driveways) are under evaluation and subject to change
Full Median Opening Directional Median Opening
31
![Page 32: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/32.jpg)
CR 532 Widening: Next Steps
Click to add textClick to add text• Study beganto add text
Click to add text
• Study began: June 2020
• Public Alternatives Meeting:
May 25, 2021
• Board presentation: Aug. 2021
• Design public meeting: Jan. 2022
• Design complete: June 2022
• Construction: Early 2023
32
![Page 33: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/33.jpg)
CR 532: Other Area Projects
Polk County
Osceola County
Poinciana Parkway Extension PD&E Study
S. Old Lake Wilson Road PD&E Study
Lake Wilson Road Widening
I-4 Improvements & 17/92 Widening PD&E Study
Poinciana Parkway Extension & CR 532 Widening
33
![Page 34: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/34.jpg)
For more information contact:
Kathy PutnamPublic Involvement Coordinator
CFX web address:www.CFXway.com
Project Contacts
Kevin CamaraPublic Information Officer
• Southport Connector PD&E Study• CR 532 Widening
• Poinciana Parkway Widening• Poinciana Parkway Extension
34
![Page 35: Poinciana-Area CFX Projects](https://reader031.vdocuments.us/reader031/viewer/2022022301/621531388aaad3281a626709/html5/thumbnails/35.jpg)
THANK YOU!