pmp/capm prep workshop intro and scope pmp/capm prep workshop1
TRANSCRIPT
PMP/CAPM Prep Workshop 1
PMP/CAPM Prep WorkshopIntro and Scope
2
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Course Objectives• The Class Will
– Prepare You to Take the PMP Exam– Cover Most of the Required Classroom Training Hours
• The Class Will Not – Make You an Expert on Project Management – Make You a Expert Project Manager – Serve as Your Only Reference for the Exam
3
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tonight’s Topic:Introduction, Project Lifecycle, Project Management Processes
• Reference Material– Chapters 1-3 PMBOK 5th Edition
4
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Management Professional (PMP) Certification
• Professional Credential by the Project Management Institute (PMI)
• PMI Certification Means– Professional Experience and/or Education– Passed Exam– Agree to Follow the Code of Conduct– Committed to Ongoing Education via Professional
Development Units (PDUs)
5
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Management Professional (PMP) Certification
• PMP Credential Handbookhttp://www.pmi.org/info/PDC_PMPHandbook.pdf
PMP Code of Ethicshttp://www.pmi.org/PDF/ap_pmicodeofethics.pdf
Go to www.pmi.org and search for these two PDF documents.
6
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Exam
7
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Exam Details
• Time Limit of 4 Hours• 200 Multiple Choice Questions
– 4 Choices Available - Choose the Best Answer – Presented in Random Order– Selected Randomly from the Test Database– 25 Questions are not Scored (Pre-release Questions)– Many Questions will be Situational– Some Questions Require Calculations– Application of PM Principles as Described in PMBOK
• Passing Score – no longer published– 106 / 175 Correct – about 61%
8
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
PMP Certification Exam OverviewPM Process # KA
Processes% of Questions
# of Questions
Initiating 10 11 20Planning 25 23 40Executing 22 27 48Monitor/Controlling 19 21 37Closing 9 9 15Professional Responsibility
0 9 15
9
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Exam Hints
• Answer All Questions with the “PMBOK” Perspective– Your Experiences may not be in sync with
Generally Accepted Practices or PMBOK Perspective
• The Exam is not just on PMBOK– PMBOK Gives an Overview– Details Need to be Gathered from Other Sources– Questions are Often Situational
10
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Exam Hints
• Mulcahy Lists a number of Tricks for Taking the Exam – Read Them– Determine Which Will Work Best for You– Heed Them
• PMI-isms– Project Management Fundamentals– Know Them!
11
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Ch 1: IntroductionProject
Management
12
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
What is a Project?
“A project is a temporary endeavor undertaken to create a unique product, service, or result.”
“Projects and operations differ primarily in that operations are ongoing and repetitive, while projects are temporary and unique.”
13
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Characteristics
• A Project is Temporary– It has a Definite Beginning and Definite End– It has Limited or Designated Funding
• A Project is Progressively Elaborated– Progressive: Proceeding in Steps or Increments– Elaborated: Worked out with Care and in Detail
14
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Projects vs. OperationsProjects vs. Operations Project
Start DateEnd DateUnique Designated FundingAttain Objective & Terminate
Operation
Start DateNo End DateRepetitiveGeneral FundingSustain the Business
Projects and Operations Are:
Performed by PeopleConstrained by Limited Resources
15
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Management
“Project Management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.”
Through the application and integration of42 project management processes comprising the 5 Process Groups.
16
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Major Project Documents
• Project Charter– Formally Authorizes the Project– Provides Project Manager with Authority to Apply
Resources• Project Scope Statement
– States What Work is to be Accomplished and What Deliverables Need to be Produced
• Project Management Plan– States How the Work Will be Performed– Composed of Subsidiary Plans – Documents the Project Management System
17
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Subsidiary Plans and Components of the PM Plan
• Scope– Project Scope Management
Plan
• Time– Schedule Management Plan – Milestone List – Resource Calendar– Schedule Baseline
• Cost– Cost Management Plan– Cost Baseline
• Quality– Quality Management Plan– Process Improvement Plan– Quality Baseline
• Human Resource• Staffing Management Plan
• Communication• Communication
Management Plan
• Risk• Risk Management Plan• Risk Register
• Procurement• Procurement Management
plan
• Stakeholder• Stakeholder
Management Plan
18
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational, Portfolio, Program,
andProject Management
19
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organization Project Management (OPM)
• Framework for keeping the organization while focused on the overall strategy.
• Provides direction to portfolios, programs, and projects alike.
• The key thing to remember for this section is that it’s all driven by the business strategy.
• Also, this is different from OPM3 – which is PMI’s project management maturity model. Be sure not to confuse the two on the test.
20
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Portfolio Management
• “Collection of projects or programs and other work that are grouped together to facilitate effective management of that work to…”
• Centralized management of one or more portfolios which includes prioritizing, authorizing, managing, and controlling projects, programs and other related work to…”
meet strategic business objectives
21
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Portfolio Management Focus
• Prioritizing resource allocation across programs and projects
• Portfolio is consistent with and aligned to organizational strategies.
22
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Program Management
• “Related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.”
• Centralized coordinated management of a program to achieve the program’s strategic objectives and benefits.
23
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Program Management Focus
• Project Interdependencies and optimal approach to managing them– Resource constraints or conflicts– Aligning strategic direction affecting project and
program goals– Resolving issues and change management
24
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Projects
• Utilized as a means of achieving an organization’s strategic plan
• Projects are authorized because…– Legal / Legislative– Market Demand– Strategic Opportunity or Business Need– Customer Request– Technological Advance
25
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
26
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
27
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Management Office (PMO)• An organizational body or entity assigned
various responsibilities related to the centralized and coordinated management of those projects under its domain.
• Responsibilities…– Project management support functions– Direct management of a project.
28
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
PMO Primary Functions• Managed share resources• Identifying and developing PM
Methodologies, best practices, and standards• Coaching, mentoring, oversight• Monitoring compliance through project audits• Developing project policies, procedures,
templates (Organizational Process Assets)• Coordinate communication across projects.
29
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Business Value
• This is unique to each organization. It essentially is the value of the entire organization: – Tangible values: Monetary assets, fixtures, stockholder
equity,
– Intangible Elements: Brand recognition, good will, public benefit, and trademarks.
• Organization will seek to enhance business value through portfolio, program, and project management practices.
30
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Role of the Project Manager
• Achieve the Project Objectives• Understand and apply good practices (knowledge, tools,
techniques)• Possess the following characteristics
– Knowledge – what is known about project management– Performance – what is accomplished while applying this knowledge– Personal - behavior while managing the project
• To be successful in the real world, you need to be able to understand the business value, and understand how your effort adds to the organization’s value.
31
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Additional Information
• Project Management (PMBoK) standards do not address everything…single projects and good practices.
• Additional Standards– Standard for Program Management– Standard for Portfolio Management– Organizational Project Management Maturity
Model (OPM3)
32
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Additional Information
• Project Management (PMBoK) standards do not address everything…single projects and good practices.
• Constraints:– Time – Cost– Scope– Quality– Risk– Resources– Customer Satisfaction
33
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Ch2: Organizational Influences and
Project Lifecycle
34
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational Influence
• An organizations culture and process have a large impact on how you will navigate through the various project management processes. For example:
– Outlook towards Risk– Motivation and rewards systems– View of leadership
35
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational Influences
• Type of Organization– Government– Corporations– Healthcare
• Maturity of Organization– Culture– Style– Structure
36
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational Systems
• Project Based– Accomplished through vendor relationships– Adopted Project Management best practices
• Non-project Based– Lack existing management systems for supporting
project management best practices.– Decentralized management of projects
37
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational Influences
• Organizational Structure– Functional – Organized by Function – Projectized – Organized by Project– Matrix – Mix of Above
• Weak• Balanced• Strong
– Composite – an organization that involves all of these structure in some way or form.
38
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational Structures
39
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Functional Organization - Pros
• One Boss - Supervisor• Easier Management of Specialists
– Specialists are Together in One Organization– Defined Career Path for Specialty
• Experts Available for Multiple Projects– Flexible Staff Use
40
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Functional Organization - Cons
• Emphasis on Functional Specialty Not Project– Fragmented Approach to Project & Project Management – Lower Client Focus
• No One Fully Responsible for Project– Utilize Project Coordinator Not Project Manager– Utilize Project Expeditor Not Project Manager– Project Manager has No Authority
• No Project Manager Advancement Path
41
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Projectized Organization - Pros
• One Boss – Project Manager• Project Manager has Independence and Authority• Efficient Project Organization • Team Loyalty to Project – No Divided Interests• More Effective Communication
– Team Members often Co-located – Team Members Treated as Insiders– Most Resources are Involved in Project Work
42
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Projectized Organization - Cons
• Team Members have No Post Project Home– May Contribute to Inflated Costs – May Contribute to Team Anxiety at Project End
• Requires Increased – Bureaucracy– Standards– Procedures
• Less Expertise in Some Disciplines• Duplication of Facilities and Job Functions• Less Efficient Resource Utilization
43
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Matrix Organization - Pros
• Project is Point of Emphasis• Maximize Utilization of Scarce Resources• Team Members Maintain a Home• Improved Project Manager Control of
Resources• Minimizes Staff Fluctuations• Better Firm-wide Balance of Resources
44
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Matrix Organization - Cons
• Two-boss Syndrome (PM and Functional)– Authority Conflicts– Priority Conflicts– Reluctance to Share Staff– Political In-fighting
• Increased Effort to Create Team• More Complex to Monitor and Control• Requires Extensive Policies and Procedures
45
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Composite Organizations
• Many organizations have combination of all of the different structures in some form. – A fundamentally functional organization may
create a special project team for a critical effort that is more projectized.
• This team may include full time staff, create their own processes outside of the organizational standard.
– An organization may manage most of its projects in a strong-matrix format but allow smaller efforts to be run by the functional departments
46
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Organizational Process Assets
• Processes and Procedures for conducting work:– Processes and Procedures
• Standards, Policies• Life cycles, Templates• Closure Guidelines
– Corporate Knowledge• Process measurement databases• Historical Information, Lessons Learned• Issue / Defect Management databases
47
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Enterprise Environmental Factors
• Internal / External factors influencing a project’s success.– Organizational Culture and Structure– Standards – regulatory, quality, codes of conduct– Existing human resources – skills, disciplines– Politics– Stakeholders and Stakeholder risk tolerances
• Considered to be input to most planning processes
48
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Work Performance Data, Information, and Reports
• Throughout the lifecycle of a project, a great deal of information is generated, considered, and communicated. – Work Performance Data are the initial measurements and
details about activities gathered during project work.
– Work Performance information is the result of analysis of work data to determine what it means to the project.
– Work Performance Reports are the results that are shared with project stakeholders.
49
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Lifecycle
50
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Product Life Cycle
• Stages that Make Up the Life of the Product• Example:
– Introduction– Growth– Maturity– Decline
51
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Life Cycle• Sequential, sometimes overlapping, phases that
make up a project.
• Every project has a start and finish, but what happens between varies widely from one project to the next.
• The lifecycle is the framework for managing the project, regardless of the specific work involved.
52
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Life Cycle Characteristics
• Projects vary in size and complexity• All projects can be mapped to the following
structure– Starting the project– Organizing and preparing– Carrying out the project work– Closing the project
53
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Cost vs. Staffing Levels
54
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Variables over Project Time
55
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Phases• Divisions within a project where extra control is
needed.• Usually completed sequentially, but can overlap.• Regardless of the number of phases, all have
similar characteristics– At the close, there is some form of transfer or
handoff– The work has a different focus– The primary deliverable requires an extra degree of
control for success.
56
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Phase to Phase Relationships
• Sequential
57
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Phase to Phase Relationships• Overlapping
58
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Predictive Lifecycles• AKA – Fully Plan Driven – project scope, time,
and budget are determined as early as possible.
59
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Iterative and Adaptive
• Iterative/Incremental: when a team intentionally repeats certain activities– Preferred when an organization is managing changing scope– Also allows for the incorporation of lessons learned at each
iteration
• Adaptive: iterative approach that is rapid and involves heavy engagement from stakeholders– Agile methods– Sprints– Backlogs etc.
60
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
CH 3:Project Management Process Groups and
Knowledge Areas
61
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Management Processes
• Project Management is accomplished through – Processes– Application of Project Management Knowledge– Skills– Tools and Techniques
• Apply Above to Inputs to Produce Desired Output
62
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5 Process Groups
• Initiating • Planning• Executing• Controlling and Monitoring• Closing
63
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5 Process Groups
64
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Boundaries
SponsorProject Inputs
Project Boundaries
Planning
Executing
Monitor &
Controlling
Initiating Closing
Project Deliverables
End UserEnd User
Project Records
Process Assets
65
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
10 Knowledge Areas• Project Integration Management• Project Scope Management • Project Time Management • Project Cost Management • Project Quality Management• Project Human Resource Management• Project Communication Management• Project Risk Management• Project Procurement Management• Project Stakeholder Management
66
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Rita’s book p. 50
• Map to Knowledge Areas – 10-n-5– Project Management Process Groups– Knowledge Areas
67
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Question
• What process group has the most processes across all Knowledge areas?
• Let’s see….
68
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Initiating Process Group
“Those processes performed to authorize and define the scope of a new phase or project or that can result in the continuation of a halted project work.
A large number of the initiating processes are typically done outside the project’s scope of control by the organization, program, or portfolio processes…”
69
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Planning Process Group
“Those processes performed to define and mature the project scope, develop the project management plan, and identify and schedule the project activities that occur within the project.”
Includes processes in ALL Knowledge Areas
70
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Executing Process Group
“Those processes performed to complete the work defined in the project management plan to accomplish the project’s objectives defined in the project scope statement.”
71
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Monitoring and Controlling Process Group
“Those processes performed to measure and monitor project execution so that corrective action can be taken when necessary to control the execution of the phase or the project.”
72
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Closing Process Group
“Those processes performed to formally terminate all activities of a project or phase, and transfer the completed product to others or close a cancelled project.”
Includes 2 Processes in 2 Knowledge Areas
73
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
End of introduction
74
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
CH 5 Scope Management
75
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project Scope Management
• Reference Material– Chapter 5 PMBOK 5th Edition
76
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Learning Objectives
• Learning Goal– Participants will be able to correctly answer the Scope
Management questions required to pass the PMP certification exam -- following focused study on the topics presented.
• Each participant will be able to:– Define Scope Management– Name Scope Management Processes and Map to PMBOK
Process Groups– Identify Inputs and Outputs to Each Process– Define Each Scope Deliverable and Its Contents– Build a Work Breakdown Structure
77
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Scope Management Definition
• Processes required to ensure that the project includes all the work required and only the work required to complete the project successfully
• Encompasses Both Product Scope and Project Scope
78
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Scope Management Processes • Project Scope Management:
– Plan Scope Management:• Process of creating a scope management plan that articulates how
project scope will be defined, validated, and controlled.– Collect Requirements
• Defining and documenting stakeholders’ needs to meet the project objectives.
– Define Scope • Developing a detailed description of the project and product.
– Create Work Breakdown Structure (WBS)• Subdividing project deliverables into smaller, more manageable
components.– Verify Scope
• Formalizing acceptance of the completed project deliverables.– Control Scope
• Monitoring the status of the project and product scope and managing changes to the scope baseline.
79
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Project vs. Product Scope
• Project Scope is different from Product Scope.– Project Scope
• The Work that Must be Performed to Deliver a Product, Service, or Result with the Specified Features and Functions
– Product Scope • The Features and Functions that Characterize a
Product, Service, or Result – i.e., the Attributes and Characteristics of the Product Created by a Project
80
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Scope Management Processes
• Planning– Collect Requirements– Define Scope– Create WBS (Work
Breakdown Structure)
• Monitor and Controlling– Verify Scope– Control Scope
81
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.1: Plan Scope Management
82
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Plan Scope Management
• Creating and documenting a plan for how scope will be identified, validated, and controlled throughout the project lifecycle.
• Helps reduce risk of “scope creep” by setting an approach.
• Takes place in which process group?
83
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Plan Scope Management
• Inputs: – Project management plan– Project Charter– Enterprise Environmental Factors
• Organization’s Culture• Infrastructure• Marketplace Conditions
– Organization Process Assets• Policies and Procedures• Historical information• Lessons Learned findings
84
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Plan Scope Management
• Tools and Techniques:– Expert Judgment:
• Use your resources (both human and other)
– Meetings:• Project Kickoff sessions
85
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Plan Scope Management
• Outputs: – Scope Management Plan
• Process that enables completion of WBS• Process that establishes how the WBS will be maintained
and approved• Process that defines how deliverables will be accepted• Process to control requests for changes to the scope
statement of the project.
– Requirements Management Plan• Describes how requirements will be identified,
documented, and managed.
86
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Plan Scope Management
• Requirements Management Plan– Documents how the requirements will be
• Analyzed• Documented• Managed
– Documents how requirements will be prioritized– Documents how requirements will be traced
87
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.2: Collect Requirements
88
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.2Collect Requirements
• Things to keep in mind– It’s all about stakeholder needs and engagement
• If you missed requirements, chances are you didn’t engage a stakeholder well enough
– You can’t define scope without requirements
89
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Definition of Collect Requirements
• Defining and documenting stakeholder’s needs to meet the project objectives.
• Defining and managing customer expectations
• Foundation for the WBS• Cost, Schedule, Quality Planning built
upon these requirements
90
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Collect Requirements - Details
• Process of defining and documenting stakeholders’ needs to meet the project objectives.
• Requirements need to be elicited, analyzed, and recorded in enough detail to be measured.
• Development of requirements start with:– Project Charter– Stakeholder Register
91
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Collect RequirementsInputs
Scope Management PlanRequirements Management PlanStakeholder Management PlanProject Charter
Stakeholder Register
Tools & Techniques
Interviews
Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making Techniques
Questionnaires and Surveys
Observations
Prototypes
Outputs
Requirements Documentation
Requirements Management Plan
Requirements Traceability Matrix
92
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Inputs 5.2.1
• Scope Management Plan• Requirement Management Plan• Stakeholder Management Plan• Project Charter
– Formally authorizes and initiates a project or phase– Documents initial requirements satisfying stakeholder
needs and expectations
• Stakeholder’s Register– Contains details related to the project stakeholders.
93
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques 5.2.2• Interviews
– Talking to Stakeholders directly• Focus Groups
– Prequalified group of stakeholders and Subject Matter Experts
– Learn about their expectations and attitudes about the proposed product, project, service, or result.
• Facilitated Workshops– Focused sessions bring key cross-functional stakeholders
together to define product requirements.
94
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques 5.2.2• Group Creativity Techniques
– Brainstorming, Nominal Group Techniques, Idea / Mind mapping.
• Group Decision Making Techniques– Assessment process of multiple alternatives with an
expected outcome.– Unanimity, Majority, Plurality, Dictatorship
• Questionnaires and Surveys– Written sets of questions designed to quickly gather
information from a wide number of respondents.
95
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques 5.2.2• Observations
– Direct viewing of individuals in their work environment and how they perform their jobs.
– Good technique if there are detailed processes or they are unable to articulate their requirements.
• Prototypes– Assessment process of multiple alternatives with an
expected outcome.
96
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs• Requirements Documentation
– Describes how individual requirements meet the business need for the project.
– Requirements may be Progressively Elaborated• Requirements Traceability Matrix:
– Links product requirements from their origin to the deliverables that satisfy them
97
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs 5.2.3
• Requirements Traceability Matrix (RTM)– Links requirements to their origin and traces them
throughout the project life cycle. – Allows tracking of requirements from
identification / documenting through implementation.
– Ensures approved requirements are delivered at the end of the project.
98
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.2 Collect Requirements - SummaryInputs
Project Charter
Stakeholder Register
Tools & Techniques
Interviews
Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making Techniques
Questionnaires and Surveys
Observations
Prototypes
Outputs
Requirements Documentation
Requirements Management Plan
Requirements Traceability Matrix
99
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.3 Define Scope
100
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
What is Define Scope?
• Process of developing a detailed description of the project and product.– Build upon major deliverables, constraints, and
assumptions documented during Initiation.– Refines Project Scope with Greater Specificity
• Progressive Elaboration
– Confirms / Completes List of Assumptions and Constraints
101
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Define Scope
Inputs Tools & Techniques
Outputs
Scope Management Plan Expert Judgment Project Scope Statement
Project Charter Product Analysis Project Document Updates
Requirements Documentation
Alternatives Identification
Organizational Process Assets
Facilitated Workshops
102
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Inputs (5.3.1)
• Scope Management Plan• Project Charter • Requirements Documentation• Organizational Process Assets
– Policies, procedures, templates for a project scope statement
– Project files from previous projects– Lessons Learned
103
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques (5.3.2)
• Expert Judgment– Those with specialized knowledge or training
• Product Analysis– Used when the project deliverable is a “product” rather than a service or
result.
• Alternatives Identification– Technique to Generate Different Approaches to Execute Work of Project
• Facilitated Workshops– Focused sessions bring key cross-functional stakeholders together to
define product requirements.
104
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.3.3)• Project Scope Statement
– Describes in detail the Project’s Deliverables– Documents Work Required to Complete the Deliverables– Provides a common understanding of Project Scope to all
Project Shareholders– Enables Project Team to Perform more Detailed Planning– Provides Baseline Against which Request for Changes are
Evaluated to Determine if within Project Boundaries
105
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.2.3)• Project scope statement contains the
following:
– Product Scope Description– Product Acceptance Criteria– Project Deliverables– Project Exclusions– Project Constraints– Project Assumptions
106
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.2.3)
• Project Document Updates– Stakeholder register– Requirements Documentation– Requirements Traceability Matrix
107
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Define Scope - Summary
Inputs Tools & Techniques
Outputs
Scope management Plan Expert Judgment Project Scope Statement
Project Charter Product Analysis Project Document Updates
Requirements Documentation
Alternatives Identification
Organizational Process Assets
Facilitated Workshops
108
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.4 Create WBS(Work Breakdown
Structure)
109
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Definition of WBS
• The process of subdividing the Project Deliverables and Project Work into smaller, more manageable components.
• Deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables.
• Defines what is “in” and “out” of scope.
110
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
WBS Details• Process of subdividing the deliverables into smaller,
more manageable components.• Organizes and defines the total scope of the project.• Represents the work in the current approved project
scope statement.• Work Packages: The lowest level of planned work
that can be…• Scheduled• Cost estimated• Monitored and controlled
111
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Create WBS 5.4
Inputs Tools & Techniques
Outputs
Scope Management Plan Decomposition Scope Baseline
Project Scope Statement Expert Judgment Project Document Updates
Requirements DocumentationEnterprise Environmental FactorsOrganizational Process Assets
112
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Inputs (5.4.1)
• Scope Management Plan• Project Scope Statement• Requirements Documentation• Enterprise Environmental Factors• Organizational Process Assets
113
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques (5.4.2)• Decomposition
– Subdivision of Scope and Deliverables into smaller, more manageable components
• Work Packages
– Sufficient detail to support executing, monitoring, and controlling the work
– May not be possible for distant future deliverables– Different levels of decomposition– Avoid excessive decomposition
114
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques (5.4.2)• Decomposition (continued)
– Steps in Decomposition• Identify Major Deliverables and Related Work• Structure and Organize WBS• Decompose Upper Level WBS into Lower Levels• Develop and Assign Identification Codes to WBS Components (Code
of Accounts)• Verify the Level of Decomposition
• Expert Judgment:– Often used to analyze the information needed in order to
complete the decomposition process– May be technical
115
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.4.3)• Scope Baseline:
– Scope Statement– WBS
• Key output of this process, generally structured like Organizational Chart.
• Organizing WBS – Major Deliverables and Sub-Deliverables– Subprojects (Different Teams are handling these subprojects.)– Project Phases– Combination Approach
– WBS Dictionary– Project Document Updates
116
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs cont’d (5.4.3)
• WBS – Understanding WBS leveling
• Project Manager should identify the levels in the WBS.• Highest level is project itself.• PMBOK – level one is the first level of decomposition.• First level can be deliverables, phases, or subproject.• Each lower level shows more details.• Lowest level of WBS is called Work Package.
117
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs cont’d (5.4.3)
• WBS – What is a Work Package?
• A Deliverable or Project Component at the Lowest Level of Each Branch of the WBS
• Assigned to a Small Team, with Clear Accountability and Responsibility
• Level at which Cost / Time can be Reliably Estimated• Should Present “Schedule Activity” and “Milestones”
Related to the Work Package
118
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
WBS Example
119
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Schedule based upon WBS
120
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs cont’d (5.4.3)• WBS Dictionary
– A Companion document for WBS, providing additional information for respective WBS components
– For each WBS component, dictionary can have one or all of the following:
Code of Account Identifier Description of Work Responsible Organization Schedule Milestones Cost Estimates
Quality Requirements Resources Contract Information Acceptance Criteria
121
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Recap: Outputs (5.4.3)
• Scope Baseline – Component of the Project Management Plan and includes:
• Scope Statement• WBS• WBS Dictionary
• Project Document (Updates)– Any project documents that require updates.
122
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Create WBS - SummaryInputs Tools &
TechniquesOutputs
Scope Management Plan Decomposition Scope Baseline
Project Scope Statement Expert Judgment Project Document Updates
Requirements Documentation
Enterprise Environmental Factors
Organizational Process Assets
123
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.5 Validate Scope
124
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Definition - Validate Scope
• Process of formalizing acceptance of the completed project deliverables.– Increases the chance that the final product,
service, or result will be accepted.
125
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Validate Scope - Details• Reviewing deliverables with customer or
Sponsor to ensure they are completed satisfactorily
• Obtain formal acceptance of deliverables by the customer or Sponsor
• SCOPE VALIDATION DIFFERS FROM QUALITY CONTROL
126
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Scope Validation VS. Quality Control
Scope Verification• Acceptance of
Deliverables
Quality Control• Correctness of Deliverables• Meet Quality
Requirements for the specified deliverables
• Generally performed before Scope Verification, but can be done in parallel.
127
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Validate ScopeInputs Tools &
TechniquesOutputs
Project Management Plan
Inspection Accepted Deliverables
Requirements Documentation
Group Decision Making Techniques
Change Requests
Requirements Traceability Matrix
Work Performance Information
Validated Deliverables Project Document UpdatesWork Performance Data
128
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Inputs (5.5.1)• Project Management Plan
– Project Scope Statement– Scope Baseline
• WBS• WBS Dictionary
• Requirements Documentation • Requirements Traceability Matrix• Validated Deliverables
129
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques (5.4.2)
• Inspection – Activities to determine whether work and deliverables
meet requirements and product acceptance criteria.• Also known as:
– Reviews– Product Reviews– Audits– Walkthroughs
• Group Decision Making– Used to reach a conclusion when the validation is
completed by team members and stakeholders.
130
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.5.3)• Accepted Deliverables
– Deliverables that meet the acceptance criteria and are approved by the sponsor or customer.
• Change Requests– Deliverables that have not been accepted, along with the reason for the
non-acceptance– These may require a change request to correct a defect.– Processed through the Integrated Change Control process.
• Project Document Updates– Corrective actions are documented recommendations to bring future
performance into conformance with the project management plan.
131
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Verify Scope - Summary
Inputs Tools & Techniques
Outputs
Project Management Plan
Inspection Accepted Deliverables
Requirements Documentation
Group Decision Making Techniques
Change Requests
Requirements Traceability Matrix
Project Document Updates
Validated DeliverablesWork Performance Data
132
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
5.6 Control Scope
133
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Definition - Control Scope
• The process of monitoring the status of the project and product scope
• And managing changes to the scope baseline
134
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Control Scope - Details
• Ensures all requested changes and recommended corrective or preventative actions go through Integrated Change Control.
• Used to manage the actual changes when they occur.• Scope changes always happen. Project team should
be prepared to handle this.• Scope Creep – Uncontrolled changes
135
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Control ScopeInputs Tools &
TechniquesOutputs
Project Management Plan Variance Analysis
Work Performance InformationRequirements Documentation
Change Requests
Requirements Traceability Matrix
Project Management Plan (Updates)
Work Performance Data Project Document (Updates)
Organizational Process Assets
Organizational Process Assets (Updates)
136
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Inputs (5.6.1)
• Project Management Plan– Scope Baseline– Scope Management Plan– Change Management Plan– Configuration Management Plan– Requirements Management Plan
137
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Inputs cont’d (5.6.1)• Work Performance Information
– Project progress– Deliverables Status
• When they started• Current progress• When did they finish
• Requirements Documentation• Requirements Traceability Matrix• Organizational Process Assets
138
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Tools & Techniques (5.6.2)
• Variance Analysis
– Performance measurements are used to assess the magnitude of variation from the original scope baseline.
– Determine the cause of the variance and decide if a Corrective or Preventative Action is required.
139
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.6.3)
• Work Performance Measurements• Organizational Process Assets (Updates)
– Causes of Variances– Reasons behind the corrective actions chosen– Other Lessons Learned from Project Scope Control
• Change Requests– Changes Requested to Scope – Must be Considered
According to Change Control Process
140
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Outputs (5.6.3)
• Project Management Plan (Updates)– Scope Baseline
• If project scope statement changes, so does the scope baseline.
– Other Baseline Updates• Cost, Schedule
141
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
Control Scope - SummaryInputs Tools &
TechniquesOutputs
Project Management Plan
Variance Analysis
Work Performance Information
Requirements Documentation
Change Requests
Requirements Traceability Matrix
Project Management Plan (Updates)
Work Performance Data Project Document (Updates)
Organizational Process Assets
Organizational Process Assets (Updates)
142
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
References
• A Guide to the Project Management Body of Knowledge, 5th ed. Project Management Institute, Inc.
• Rita Mulcahy’s PMP Exam Prep 8th edition
143
PMP/CAPM Prep WorkshopContains Confidential information which may not be disclosed
with out express written authorization from PMI-CIC.
End of Scope