PMP ® Preparation Course 5005/104-0032 uen Rev PC 103 Copyright © 2009 Greenlight Project Management S.L. 50 sample questions 1. A project scope statement is important because it: A) Breaks a project down into successively greater detail by level B) Provides the basis for making future project decisions C) Provides criteria for follow up of project cost D) Initiates the project 2. You have formed a new project team. Which of the following topics is the responsibility of this team? A) Issue the project charter B) Identify and manage stakeholders C) Approving the final schedule during schedule development D) Set priorities between projects 3. You have resolved a two-party conflict by using compromise. What is the likely result? A) Win-win B) Lose-win C) Lose-lose D) Win-lose 4. The following are steps of Stakeholder Analysis except: A) Identify all potential project stakeholders B) Asses how key stakeholders are likely to react in various situations C) Analyze the potential impact each stakeholder could generate D) Identify the desire engagement level of the key stakeholders 5. Which of the following tools are frequently used in Human resource planning A) Organization charts, Networking, Organizational theory B) Organization charts, Networking, training C) Organizational theory, stakeholder analysis, team-building activities D) Stakeholder analysis, training, team-building activities

Upload: frank-instine

Post on 30-Sep-2015

5 views

Category:

Documents


3 download

DESCRIPTION

PMP 50 Questions

TRANSCRIPT

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 103

    Copyright 2009 Greenlight Project Management S.L.

    50 sample questions

    1. A project scope statement is important because it:

    A) Breaks a project down into successively greater detail by level B) Provides the basis for making future project decisions C) Provides criteria for follow up of project cost D) Initiates the project

    2. You have formed a new project team. Which of the following topics is the responsibility of this team?

    A) Issue the project charter B) Identify and manage stakeholders C) Approving the final schedule during schedule development D) Set priorities between projects

    3. You have resolved a two-party conflict by using compromise. What is the likely result?

    A) Win-win B) Lose-win C) Lose-lose D) Win-lose

    4. The following are steps of Stakeholder Analysis except:

    A) Identify all potential project stakeholders B) Asses how key stakeholders are likely to react in various situations C) Analyze the potential impact each stakeholder could generate D) Identify the desire engagement level of the key stakeholders

    5. Which of the following tools are frequently used in Human resource planning

    A) Organization charts, Networking, Organizational theory B) Organization charts, Networking, training C) Organizational theory, stakeholder analysis, team-building activities D) Stakeholder analysis, training, team-building activities

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 104

    Copyright 2009 Greenlight Project Management S.L.

    6. The following items are important for professional responsibility except:

    A) Do the right thing B) Avoid to report violations C) Act ethically D) Follow the right process

    7. Your new assignment is as project manager of an international project. You and your family will move abroad to a country with a very different culture. The disorientation that may occur when you find yourself with other cultures in a different environment is called:

    A) Culture difference B) Culture diversity C) Culture surprise D) Culture shock

    8. Which are the outputs of Close project?

    A) Lessons learned, Final product B) Administrative closure procedure, corrective action C) Corrective action, product verification D) Lessons learned, product verification

    9. The following are outputs from Control scope except:

    A) Changes Request B) Work performance information C) Lessons learned D) Deliverables

    10. As a project manager you can choose between different conflict management approaches. Which of the following approaches is believed to lead to the least enduring positive results?

    A) Forcing B) Compromising C) Withdrawal D) Problem solving

    11. The BAC is $22,000. The present CPI is 0.8. Assuming that the variances in the past are typical also for the future variances, what is the EAC?

    A) $22,000 B) $27,500 C) $17,600 D) $15,000

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 105

    Copyright 2009 Greenlight Project Management S.L.

    12. An appropriate sequence for risk management activities is:

    A) Risk analysis, risk mitigation, plan risk responses B) Identify risks, risk elimination, risk mitigation C) Identify risks, risk analysis, plan risk responses D) Risk assessment, risk analysis, plan risk responses

    13. To transfer most of the risk to the seller, the buyer may use a _______ contract:

    A) Purchase order B) Cost reimbursable C) Fixed price D) Cost plus fixed fee

    14. In quality work a diagram which shows how many results were generated by type or category of identified cause is called:

    A) Ishikawa diagram B) Pareto diagram C) Responsibility diagram D) Fishbone diagram

    15. The critical path is found by calculating the following dates:

    A) Predecessor-to-successor, predecessor-to-predecessor, successor-to-successor B) Start-to-start, start-to-finish, finish-to-start, finish-to-finish C) Early start, early finish, late start, late finish D) Total float start, total float finish

    16. The following are tools for Acquire Project Team except:

    A) Virtual teams B) Multi-criteria decision analysis C) Acquisition D) Colocation

    17. Your most recent project status report contains the following information: EV=$3,000, AC=$3,500 and PV=$4,000. The project is then:

    A) Behind schedule and under budget B) Behind schedule and over budget C) Ahead schedule and over budget D) Ahead schedule and under budget

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 106

    Copyright 2009 Greenlight Project Management S.L.

    18. The following are tools for estimate activity durations except:

    A) Analogous estimating B) Expert judgment C) Leveling D) Quantitatively based durations

    19. One of the most important roles of the project manager is as:

    A) Sponsor B) Integrator C) Resource owner D) Receiver

    20. The project management plan is used to all of the following except:

    A) Guide execution B) Document project planning assumptions C) Develop project charter D) Facilitate communication among stakeholders

    21. A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables is called:

    A) Work package B) Product description C) Work breakdown structure D) Product scope

    22. Project management processes and product-oriented processes:

    A) overlap and interact throughout the project B) do not interact C) are used to manage the project work D) are measured against the product requirements

    23. A project document including the identification, assessment, and classification of project stakeholders is called:

    A) Stakeholder plan B) Stakeholder management list C) Stakeholder register D) Stakeholder information

    24. The project life cycle is only one stage of the:

    A) product life cycle B) project management life cycle C) process groups

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 107

    Copyright 2009 Greenlight Project Management S.L.

    D) product development process

    25. An advantage of a matrix organization is:

    A) Administration is easier B) Communication is easier C) Improved project manager control of resources D) Only one boss for project team members

    26. PDM uses four different logical relationships, but it does not use:

    A) Start to finish B) Finish to start C) Begin to end D) Finish to finish

    27. You have the following activities in a network diagram:

    Activity Predecessors Duration (days)

    A None 3 B A 5 C A 6 D B 3 E C, D 3 F D 4

    What is the critical path?

    A) ABDE B) ACE C) ABDF D) ACEF

    28. In the network diagram above, which activities have float?

    A) C, F B) C, E C) D, E D) None

    29. In the network diagram above, what happens if the duration of activity C is 9 days?

    A) The length of the critical path has increased by one day B) The critical path is ACE C) The float of E is one day D) The network has two critical paths

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 108

    Copyright 2009 Greenlight Project Management S.L.

    30. The following items are inputs to Develop project charter:

    A) Agreements, statement of work, lessons learned B) Contract, statement of work, scope statement C) Contract, expert judgment, scope statement D) Product description, scope statement, project selection criteria

    31. Quality audits are used in Perform quality assurance to:

    A) help analyze how problems occur B) identify lessons learned that can improve performance of this project C) identify lessons learned that can improve performance of this project or of other projects D) forecast future outcomes based on historical results

    32. The CPI, which is used to forecast final cost of the project, is calculated by using which formula?

    A) EV/AC B) AC/EV C) EV/PV D) PV/EV

    33. A project team consisting of 4 persons work with a work package. To increase speed two more persons are added to the team. How many communication channels are added?

    A) 8 B) 9 C) 10 D) 11

    34. Suppose a project of $2 million has a risk with probability 0.12 of occurrence and a potential loss of $30,000. This represents an expected negative value of:

    A) $24,000 B) $240,000 C) $36,000 D) $3,600

    35. In a buyer/seller relationship a Cost-plus-incentive fee contract is signed. The target cost is $100, the fee to the seller is $10 and the sharing formula is 85/15%. If the sellers cost is 80, what is the final price?

    A) $85 B) $90 C) $93 D) $100

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 109

    Copyright 2009 Greenlight Project Management S.L.

    36. What is the main difference between an internal agreement within the performing organization and a contract with an external company?

    A) Internal agreements are easier to change B) Internal agreements do not need to be signed C) A contract is legally binding D) Contract language is difficult to understand

    37. Risks will be identified during which phase of the project life cycle?

    A) Concept phase B) Development phase C) Implementation phase D) All phases

    38. Decomposition is a technique used to construct a:

    A) Risk plan B) Project plan C) Work breakdown structure D) Network diagram

    39. You are the project manager for a $2 million project. The customer is not satisfied with the high risk of the project which is due to a new advanced technology which the project team has proposed. Therefore, you and the project team propose that an old well known technology will be used. What is this risk response technique called?

    A) Avoidance B) Transference C) Mitigation D) Acceptance

    40. Customer satisfaction requires a combination of:

    A) Gold plating and fitness for use B) Conformance to requirements and fulfillment of budget requirements C) Fitness for use and fulfillment of budget requirements D) Conformance to requirements and fitness for use

    41. Manage Stakeholder Engagement belongs to which of the following process group?

    A) Controlling processes B) Planning processes C) Executing processes D) Closing processes

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 110

    Copyright 2009 Greenlight Project Management S.L.

    42. A cost baseline has all of the following characteristics EXCEPT

    A) It is a time phased cost plan B) It is a component of the project management plan C) It is approved by the senior management D) It shows the actual costs by period

    43. A Benefit cost ratio of 1.6 means?

    A) Costs are 1.6 times the profit B) Profit is 1.6 times the costs C) Payback is 1.6 times the costs D) Costs are 1.6 times the payback

    44. Conduct procurements belongs to the following process group:

    A) Controlling processes B) Planning processes C) Executing processes D) Closing processes

    45. The fundamental tenets of modern quality management is that quality is:

    A) designed and built in B) planned, designed and built in C) built and inspected in D) designed, built and inspected in

    46. Because the product of the project is unique, the characteristics that distinguish the product must be:

    A) progressively planned B) elaborated in advance C) meticulously planned D) progressively elaborated

    47. Which are the outputs of Control Stakeholder Engagement?

    A) Change Requests, Project Documents Updates and Stakeholder Engagement Plan B) Change Requests, Project Management Plan Updates and Work Performance Information C) Change Requests Project Management Plan Updates and Work Performance Data D) Project Management Plan Updates, Work Performance Information and Information management System

    48. All the following are interpersonal skills of a Project Manager, except:

    A) Team building B) Competence

  • PMP Preparation Course

    5005/104-0032 uen Rev PC 111

    Copyright 2009 Greenlight Project Management S.L.

    C) Motivation D) Decision making

    49. A distinct, scheduled portion of work performed during the course of a project is called?

    A) Activity B) Project task C) Activity code D) Work package

    50. Maslows hierarchy of needs theory has five levels. What is the highest level called?

    A) Physiological needs B) Esteem needs C) Social/affiliation needs D) Self-actualization needs