Project Management Core Problems
Khalid Ahmad Khan, PE, PMPPresident – PMI Lahore Chapter
22 December 2009
![Page 2: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/2.jpg)
About PMIIntroduction
![Page 3: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/3.jpg)
Founded in 1969 by working project managers ◦ 420,000 members and credential
holders◦ 250 chapters in over 70 countries◦ 450 members in Lahore
Goal: Organizations everywhere will embrace, value and utilize project management and then attribute their successes to it.
Project Management Institute
![Page 4: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/4.jpg)
A Guide to the Project Management Body of Knowledge
The purpose of the Guide is “to identify and describe that subset of the PMBOK® which is generally recognized as good practice”
PMBOK Guide®
![Page 5: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/5.jpg)
Standards ensure a basic project management framework is applied consistently worldwide
Project Management Institute
![Page 6: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/6.jpg)
Public Sector Performance
Analysis / Lessons
SolutionsBenefits
PM Core Problems
![Page 7: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/7.jpg)
Public Sector PerformanceChallenges
![Page 8: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/8.jpg)
Public Sector Project Performance 2003
Unsatisfactory outcomes• Cost over runs• Long delays• Poor quality• Unsatisfied users
Planning Commission
![Page 9: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/9.jpg)
Public Sector Project Performance – Nov 2007
World Bank – Pakistan Infrastructure Implementation Capacity Assessment Nov 07
![Page 10: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/10.jpg)
Public Sector Project Performance – Nov 2007
Programming Wrongly selected Planning Poorly executed
World Bank – Pakistan Infrastructure Implementation Capacity Assessment Nov 07
![Page 11: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/11.jpg)
• Wrong Project Design, Location or Basis
• Typical examples• Schools at wrong locations• Infrastructure inconsistent with
needs• Gross over or under design
• Untested development hypothesis
Selection of projects
Programming failure
![Page 12: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/12.jpg)
Example – Addressing urban traffic congestion
C&W Increase capacity
Road widening
Transport Reduce load
Improve Public transport
Other possibilities
Shift trafficRestrict access
(Congestion Charge)
Programming Challenge
![Page 13: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/13.jpg)
Example – Gastro problem in city
WASA Reduce leaks
Revamp sewage lines
Health Enhance capacity
Additional emergency
beds
Environment Improve
water supply
Install Filtration
plants
Other possibilities
Hygiene Education
Water treatment
Programming Challenge
![Page 14: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/14.jpg)
Programming Failure◦ Wrong Project Design, Location, Basis 0-100%
loss Project Delay - Loss of benefits
◦ Electricity production from Ghazi Brotha Rs. 145 million/day – Rs 52 billon/year Total delay in project – 4+ Years
Project Delay - Inflation◦ Impact of inflation on RBOD
Rs. 6.1 million/day – Rs. 2.3 billion/year Total delay in project – Uncertain (current 5+
Years)
Cost of failure
![Page 15: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/15.jpg)
RBOD Project – Nov 05
Project Approved May 2001 Original Budget Rs. 13.95 billion Target Completion June 2005 (48
months) Progress Rs. 2.7 billion (20%)
Apr-01 Apr-09
Jan-02 Jan-03 Jan-04 Jan-05 Jan-06 Jan-07 Jan-08 Jan-09
Jan-03Construction
Aug-04Consultant M&E
Feb-06PC-1 Revision
Jul-01 - Jul-05Project Span
May-01PC-1 Approval
Jul-05 - Dec-08Extension
Jan-02Consultants
![Page 16: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/16.jpg)
RBOD Revision 2005
Original PC-1May 2001
Revised PC-1Dec 2005
Revised PC-1May 2001 Value
Discounting to May 2001
Rs. 13.95 billion Rs. 30.74 billion
Rs. 21.74 billion
InflationRs. 9 billion
53.6 %
ScopeRs. 7.8 billion
46.4%
OverallRs. 16.8 billion
Progress Rs. 2.7 billion (8.7%)
![Page 17: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/17.jpg)
Analysis/LessonsReasons for failure
![Page 18: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/18.jpg)
PM and Programming
Input Transform Outcome Model
Input Build Output UtilizeOutcom
esIdentify Select
Project Management Processes
![Page 19: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/19.jpg)
Major Causes for Project FailureSecretaries workshop - 2003
Rank P&D and Finance1 Original assumptions & estimates invalid2 Change in government priorities3 Unclear Objectives4 Lack of senior management support5 Ineffective team
Rank Others1 Ineffective team2 Lack of senior management support3 Inadequate funding4 Change in government priorities5 Original assumptions & estimates invalid
![Page 20: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/20.jpg)
Major Gaps in Delivery of Projects – Nov 2007
World Bank – Pakistan Infrastructure Implementation Capacity Assessment Nov 22-07
![Page 21: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/21.jpg)
Public Sector DevelopmentEstimation at PC-1 Stage
Payments[10%]
Project Identified
PC-2Feasibility
PC-1Project Approval
Technical Sanction[4%]
Tendering[Premium]
Award
Execution Measurement of Work
Estimate Type Design Complete AccuracyOrder of Magnitude 0-5% +50% to -30%Budget 10-15% +30% to -15%Definitive 45-100% +15% to -5%
Estimation Standards – American Association of Cost Engineers © 2002
![Page 22: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/22.jpg)
Bias in Project Roles
ClientEngineer
Contractor
Role of Client1. Sponsor
Role of Engineer2. Design3. Control Quality4. Supervise contractor5. Project Planning
Percent based consulting fee
![Page 23: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/23.jpg)
Limitations of Financial Monitoring
Assumes all money spent is used with 100% efficiency◦ Works fine only if the project is on-track◦ Ignores Scope & Time
Physical Progress vs. Financial Progress
80.00
70.00
50.00
70.00
100.00
- 20.00 40.00 60.00 80.00 100.00 120.00
Physical-3
Physical-2
Physical-1
Utilized
Budget
BudgetUtilizedPhysical-1Physical-2Physical-3
![Page 24: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/24.jpg)
Project Splitting/Organization
Project Director
ProjectManageme
nt
Operations
ContractManageme
nt
Technical
Finance
Project Director
Package 1
Package 2
Package 3
Package 4
Package 5
Traditional Functional
![Page 25: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/25.jpg)
SolutionsImproving outputs/outcomes
![Page 26: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/26.jpg)
PMP Prep Primavera PM Soft Skills Leadership Incentives for
government officials 100% subsidy on
training course + exam fees
Bonus of USD 2,000 for passing certification
Skill Enhancement
![Page 27: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/27.jpg)
Programming (Portfolio, Program)• Focus: Selecting the Right Projects
Project Management• Focus: Do the Project Right
Integrated Programming/PM
• Budget• Resources
Inputs
• Methodology• Activities
Process • Deliverables
Outputs
• Proper use of Deliverables
Utilization • Improved indicators
Outcomes
![Page 28: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/28.jpg)
Analysis of Project Context - PPM
Stakeholder Analysis – PM 2.3
Problem/Situation Analysis - PPM
Objectives Analysis – PM 4.1
Plan of Activities – PM 4.2
Resource Planning – PM 6.1
Measurement of Objectives - PPM
Risk Analysis & Mgt – PM 11.1
Analysis of Assumptions -
PPM
Design: LFA and PMI Standards
![Page 29: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/29.jpg)
Project Management Standard – PMI PMBoK 4th Ed
Initiating
Controlling
Executing
Planning
Closing
![Page 30: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/30.jpg)
Earned Value Project Management
• Plan all Work prior to beginning it• Measure performance based on an objective
set of Criteria• Analyze schedule using a Time Phased CPM• Analyze the expenditure of funds in light of the
work Accomplished
Core Concept
![Page 31: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/31.jpg)
Earned Value Analysis
Conclusion: •Accurate picture of project status•cost, schedule, and technical•Early and accurate identification of trends and problems•Basis for course correction•Bring project in on schedule and cost
![Page 32: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/32.jpg)
Project Roles
ClientPM Firm
Engineer Contractor
Role of Client1. Sponsor
Role of PM Consultant2. Manage Schedule
Role of Engineer3. Design4. Control Quality5. Supervise contractor
Fixed/Incentive price consultant fee
![Page 33: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/33.jpg)
BenefitsResults of good project management
![Page 34: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/34.jpg)
Construction Work in Progress on Taunsa Barrage Rehabilitation and Modernization Project
Taunsa Barrage Rehabilitation
Taunsa Barrage
•Duration: 1092 days, 10th May 2005 – 31st May 2008
•Cost: Rs 4,527.6 Million
•Major Works: Strengthening of Existing Barrage, Construction of Subsidiary Weir, Construction of Silt Excluder, Remodeling of DG Khan Canal Head Regulator
Taunsa Barrage
•Duration: 1092 days, 10th May 2005 – 31st May 2008
•Cost: Rs 4,527.6 Million
•Major Works: Strengthening of Existing Barrage, Construction of Subsidiary Weir, Construction of Silt Excluder, Remodeling of DG Khan Canal Head Regulator
![Page 35: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/35.jpg)
Taunsa Project Baseline
May 10, 2005May 10, 2005
May 31, 2008May 31, 2008
15/6/06 - 15/9/06Flood Season
Non-Work
15/6/07 - 15/9/07Flood Season
Non-Work
15/6/05 - 15/9/05Flood Season
Non-Work
May 10, 2005May 10, 2005
May 31, 2008May 31, 2008
15/12/05 - 22/2/06Canal Closure
Work Time
15/12/06 - 22/2/07Canal Closure
Work Time
12/15/2007 - 2/22/2008Canal Closure
Work Time
EARLY
![Page 36: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/36.jpg)
ROI of Project Management
Construction Inflation◦ Long term (4 yr) trend: 9.1% per annum
Based on RBOD-II analysis◦ Short term (1 yr) trend: 13.3% per annum
Based on Market Rates data from Finance
Taunsa Project◦ Budget: Rs. 4.26 billion ◦ 3 Yr Inflation Impact: Rs. 883 million◦ 2 Yr Inflation Impact: Rs. 555 million
Saving: Rs 328 million (8.0% of Budget Cost) PM Cost:
PMO I&P: Rs 50 million (1% of Budget Cost) PMU P&D: Rs. 5 million (0.1% of Budget Cost)
![Page 37: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/37.jpg)
PM Implementations Lessons
LCCE Lahore RR RBOD-II Taunsa
PMO No No No Yes
Client Project Plan Yes Yes No Yes
Contract n x NCB n x NCB n x NCB 2 x ICB
Contractor Project Plan No No No Yes
Performance Delay 2 yrs Delay 2 yrs Delay 4 yrs Ahead 1 yr
![Page 38: Pmi Project Management Core Problems Uet Dec 22 09](https://reader035.vdocuments.us/reader035/viewer/2022081519/55839d73d8b42a1f098b4d68/html5/thumbnails/38.jpg)
Good Programming
• Insures selection of Right Projects
Good Project Management
• Based on: PMI PM Framework
• Insures that projects are executed successfully
• Project Plan• Procurement Plan• Responsibility Matrix
Conclusion