pm pmp exam preparation study guideglossary
TRANSCRIPT
GLOSSARY
Factors that for planning purposes will be considered to be true, real, orcertain (PMBOK® 4.1.1.5).
Assumptions
The transfer of a right, a contractual obligation, or property from oneparty to another.
Assignment
All items of value owned by a company.Assets
Characteristics of an individual concerned with task accomplishment.Assertive-Directing
A strong desire or ambition, as for advancement or honor.Aspiration
The process of settlement of a dispute between two parties by animpartial third party.
Arbitration
Characteristics of an individual concerned with planning and is fair andprincipled.
Analytic-Autonomizing
The power to simplify what is either complex or complicated.Analytical Skills
Also called top-down estimating; using the actual duration of a previous,similar activity as the basis for estimating the duration of a future activity(PMBOK® 6.3.2.2 and 7.2.2.1).
Analogous Estimating
A change to a contract by authority. Note: Either party to a contract canamend or change the contract. Usually all changes must be signed byboth parties.
Amendment
Characteristic of an individual concerned with the protection, growth, andwelfare of others.
Altruistic-Nurturing
Synonymous with contract.Agreement
Law that allows one party, called the principal, to delegate authority toanother party, called an agent, to act in all matters relating to thebusiness of the principal.
Agency Law
Verifying and documenting project results to formalize acceptance of theproduct of the project by the sponsor, client, or customer (PMBOK® 10.4).
Administrative Closure
The real, measurable, out-of-pocket costs recoverable as compensationfor actual loss.
Actual Damages
This term has been replaced with the term actual cost.Actual Cost of WorkPerformed (ACWP)
Total costs incurred that must relate to whatever cost was budgetedwithin the planned value and earned value in accomplishing work duringa given time period. (PMBOK® p. 197).
Actual Cost (AC)
A task (work element) performed over a period of time; a specific pieceof defined work from the WBS.
Activity
Assets = Liabilities + Owners’ EquityAccounting Equation
Agreement to the terms offered in a proposal or contract; the taking orreceiving of a contract deliverable.
Acceptance
Recognition of the fact that it is just as difficult for people to manageagreement as it is to manage conflict.
Abilene Paradox
DefinitionTerm
Glossary GL-1 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
A combination of producers of any product joined together to control itsproduction, sale, and price so as to obtain a monopoly and restrictcompetition in any particular industry or commodity.
Cartel
A business entity with a special relationship to a principal, making it easierto jointly address a business opportunity.
Business Partner
See estimate.Budget Estimate
This term is replaced with the team planned value.Budgeted Cost of WorkScheduled (BCWS)
This term is replaced with the team earned value.Budgeted Cost of WorkPerformed (BCWP)
The estimated total cost of the project when done.Budget at Completion (BAC)
Failure to perform a contractual obligation without legal excuse.Breach
Estimating the cost of individual work items and then summarizing orrolling up the individual estimates to get a project total (PMBOK® 7.2.2.3).
Bottom-Up Estimating
A monetary guarantee to cover losses suffered for specified reasons, anobligation, or constraint. See also bid bond; performance bond.
Bond
A monetary guarantee that the bidder, if awarded a contract, will in factexecute (sign) it. Note: A bid bond expires automatically at the time thecontract is signed by the parties or if the contract is not awarded.
Bid Bond
The estimated cost of a project based on the currently known factsregarding scope, schedule, and expectations. See time-and-materials.
Best Estimate
A statement in a proposal or contract that implies that the buyer or sellerwill put forth its best skills and dedication with the intent of meeting anobligation.
Best Efforts
Usually used with a modifier (e.g.., cost baseline, schedule baseline,performance measurement baseline).
Benefit-Cost Analysis
Anything accepted as true; a creed, doctrine, or tenant; an opinion,expectation, or judgment.
Beliefs
A version of a plan, with its associated estimate, that has been acceptedas part of the contract, and is now subject to change
Baseline Plan
The original plan (for a project, a work package or an activity) plus orminus approved changes. Usually used with a modifier (e.g.., costbaseline, schedule baseline, performance measurement baseline).(PMBOK® p 198)
Baseline
A graphic display of schedule -related information. Shows activity startand end dates and expected durations but do not usually showdependencies (PMBOK® 6.4.3.1).
Bar Charts (Gantt Charts)
The state of being insolvent; failure or inability to pay just debts orobligations.
Bankruptcy
The act of granting or assigning a contract from a buyer to a seller.Phase 2 of the contract management process.
Award
The only people who can make, accept, reject, defer, or negotiatechange.
Authorized Representatives
One’s disposition or opinion; position or stand; point of view.Attitudes
DefinitionTerm
Glossary
Glossary GL-2 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
Component of a statement of risk; a single phrase or sentence that brieflydescribes the key possible outcomes of the current conditions.
Consequence
Is a difference in opinion between two or more persons or groups thatcauses each to attempt to influence a situation affecting all partiesconcerned.
Conflict
Component of a statement of risk; a single phrase or sentence that brieflydescribes the key circumstances or situations causing the doubt, concern,anxiety, or uncertainty.
Condition
A person who creates or develops.Composer
Any subpart of an intermediate, higher-level deliverable with the attributesof a deliverable.
Component Deliverable
Persons or legal entities possessing legal capacity and authority to enterinto a contract.
Competent Parties
Sum of the information requirements of the project stakeholders(PMBOK® 10.1.1.1).
CommunicationRequirements
Determining the information and communication needs of stakeholders: who need what information, when they need it, and how it will be given tothem (PMBOK® 10.1).
CommunicationPlanning
Document that provides a collection and filing structure of methods usedto gather and store information; a distribution structure to detail to whominformation will flow and methods used to distribute information; adescription of information to be distributed; production schedules for eachtype of communication; methods to access information betweenscheduled communication; and a method to update and refine theCommunications Management Plan as the project progresses anddevelops (PMBOK® 10.1.3.1).
CommunicationManagement Plan
Communication refers to the transfer of symbols to create sharedmeaning in the mind of the sender and receiver.
Communication
Exchange of information (PMBOK® 2.4.2).Communicating
Sound and prudent judgment.Common Sense
The body of those principles and rules of action that derive their authorityfrom tradition, usage, custom, and previous judicial decisions.
Common Law
The act or condition of sticking together; blending or merging.Cohesion
Making or becoming easier to understand.Clarifying
The body of law created by acts of legislatures and concerned with civilor private rights and remedies.
Civil Law
A formal, written request by a buyer directing the seller to make changesaccording to the provisions of the contract documents.
Change Order
Procedures used to manage and control the baseline.Change Management
The formal, documented procedure that defines how change will bemanaged.
Change Control System
People responsible for approving, rejecting, or deferring changerequests.
Change Control Board DefinitionTerm
Glossary
Glossary GL-3 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
Performing the planned risk response (PMBOK® 11.6.3.2).Corrective Action
The right to literary property, giving authors, composers, and othercreators the sole right to reproduce and distribute their work for a limitedperiod of time.
Copyright
Is discovery, where you narrow down or weed out thoughts, data, etc.,produced during the diverging stage as you head towards reaching asingle conclusion. Judgmental and critical thinking are necessaryduring this stage.
Convergence
Clarification and mutual agreement on the structure and requirements ofthe contract prior to the signing of the contract (PMBOK® 12.4.2.1).
Contract Negotiation
The process of planning, forming, and administering an agreement to buyand sell goods and services from one party to another.
Contract Management
A model law developed in the United States to standardize commercialcontracting among the states.
Contract Law (UniformCommercial Code [UCC])
Completion and settlement of the contract, including resolution of alloutstanding items (PMBOK® 12.6).
Contract Closeout
The power that the principal confers on the agent to act on his or herbehalf to enter into a contract.
Contract Authority
Process of ensuring that the seller’s performance meets contractualrequirements (PMBOK® 12.5).
Contract Administration
An agreement that establishes an enforceable legal relationship betweentwo parties; a mutual exchange of promises. Synonymous withagreement. The elements of a contract are agreement(offer/acceptance), competent parties, mutual consideration, and legalpurpose.
Contract
A separately planned quantity used to allow for future situations which mybe planned for only in part (sometimes called “known unknowns).Contingency reserves may involve cost, schedule, or both. Contingencyreserves are intended to reduce the impact of missing cost or scheduleobjectives. Contingency reserves are normally included in the project’scost and schedule baselines. (PMBOK® Glossary 160)
Contingency Reserve
Defining action steps to be taken if an identified risk event should occur .Contingency Planning
Risk mitigation strategy in which funds are held in a separate account forfuture use; based on a percentage of the overall cost of the project.
Contingency
Risk mitigation strategy in which tasks are added to the WBS; the tasksare estimated, scheduled, costed, and priced.
Containment
Factors that will limit the project management team’s options (PMBOK® 4.1.1.4).
Constraints
Something of value.Consideration
Damages that do not flow directly and immediately from the act of aparty, but only from some of the consequences or results of the act.Example: The client's point-of-sale system is down for four hours due toa software problem. As a result, the client claims to have lost hundredsof thousands of dollars due to lost sales.
Consequential Damages
DefinitionTerm
Glossary
Glossary GL-4 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
The passing of judgment on an issue under consideration. Theact of reaching a conclusion or making up one's mind.
Decision
Compensation recoverable for a wrong or an injury. See also actualdamages; consequential damages; liquidated damages.
Damages
Individual or organization who will use the project product (PMBOK® 2.2).Customer
Calculates a single, deterministic early and late start and finish date foreach activity based on specified, sequential network logic and a singleduration estimate. Float is calculated to determine which activities havethe least scheduling flexibility (PMBOK® 6.4.2.1).
Critical Path Method (CPM)
Any approach using network parameters to determine the critical path.Critical Path Analysis
In a project network diagram, the series of activities that determines theearliest completion of the project. The critical path will generally changefrom time to time as activities are completed ahead of or behindschedule. The critical path is usually defined as those activities with afloat less than or equal to a specified value, often zero.
Critical Path
Decrease total project duration after analyzing alternatives to determinehow to get the maximum duration compression for the least cost.
Crashing
(1) Any difference between the estimated cost of an activity and theactual cost of that activity. (2) In earned value, BCWP less ACWP.
Cost Variance (CV)
A type of contract in which the buyer reimburses the seller for the seller’sallowable costs (allowable costs are defined by the contract), and theseller earns its profit if it meets defined performance criteria.
Cost-Plus-Incentive Fee(CPIF) Contract
A type of contract in which the buyer reimburses the seller for the seller’sallowable costs (allowable costs are defined by the contract) plus a fixedamount of profit (fee).
Cost-Plus-Fixed Fee (CPFF)Contract
A type of contract in which the seller gets reimbursed for costs ofproducing the item and gets paid a fee for winning the contract.
Cost-Plus-Award Fee(CPAF)
A type of contract in which the seller gets reimbursed for the cost ofproducing the item and also gets a fee calculated as a percentage ofcost. Not permitted in contracts with the federal government.
Cost-Plus-a-Percentage-of-Cost (CPPC)
The ratio of budgeted costs to actual costs (BCWP/ACWP). CPI is oftenused to predict the magnitude of a possible cost overrun using thefollowing formula: original cost estimate/CPI = projected cost atcompletion. See also earned value.
Cost Performance Index(CPI)
The costs incurred to ensure quality. The cost of quality includes qualityplanning, quality control, quality assurance, and rework.
Cost of Quality
Estimating the cost of the resources needed to complete projectactivities.
Cost Estimating
Controlling changes to the project budget.Cost Control
Allocating the cost estimates to individual project components.Cost Budgeting
Time-phased budget used to measure and monitor cost performance onthe project (PMBOK® 7.3.3.1).
Cost Baseline
The expenditure of funds that result directly from production products andestablishing an infrastructure to provide services. A (direct) cost can betraced to the finished product or service.
Cost (or direct cost)
DefinitionTerm
Glossary
Glossary GL-5 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
The number of labor units required to complete an activity or otherproject element. Usually expressed as staff hours, staff days or staffweeks. Should not be confused with duration.
Effort
Process of training and developing knowledge, skills, and character byformal schooling.
Education
See definition 1 under earned value.Earned Value Analysis
The physical work accomplished plus the authorized budget for this work.The sum of the approved cost estimates for activities completed during agiven period. Previously called budgeted cost of work performed(BCWP) for and activity or group of activities. (PMBOK® p. 201).
Earned Value (EV)
In the critical path method, the earliest possible point in time on which theuncompleted portions of an activity (or the project) can start, based onthe network logic and any schedule constraints; early start dates canchange as the project progresses and changes are made to the projectplan.
Early Start (ES)
In the critical path method, the earliest possible point in time on which theuncompleted portions of an activity (or the project) can finish based onthe network logic and any schedule constraints; early finish dates canchange as the project progresses and changes are made to the projectplan.
Early Finish (EF)
The number of work periods (not including holidays or other nonworkingperiods) required to complete an activity or other project element; usuallyexpressed as workdays or workweeks; sometimes incorrectly equatedwith elapsed time.
Duration
A formal, written agreement between business functions to establishresponsibilities, obligations, and actions in performing a project.
Document of Understanding
Divergence is exploratory, used to generate a lot of ideas. Creativethinking is necessary during the diverging stage.
Divergence
A method that spreads the cost of a long-lived asset over its entireservice life.
Depreciation
Something necessarily consequent on something else.Dependency
Any measurable, tangible, verifiable outcome, result, or item that must beproduced to complete a project or part of a project; often used morenarrowly in reference to an external deliverable, which is a deliverablethat is subject to approval by the project sponsor or customer.
Deliverable
The seller's invoicing the buyer some period of time after the deliverablehas been completed for the convenience of one or both of the parties.
Delayed Invoicing
The buyer's making payment to the seller some period of time after thedeliverable has been accepted for the convenience of one or both of theparties.
Deferred Payment
A deficiency in something essential to the proper use of a product.Defect
The act of reaching a conclusion or making up one's mindDefault
Process used to develop the PBS/WBS by subdividing the major projectdeliverables into smaller, more manageable components until thedeliverables are defined in sufficient detail to support future projectactivities.
Decomposition
DefinitionTerm
Glossary
Glossary GL-6 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
Amount of time that an activity can be delayed from its early start withoutdelaying the project end date.
Float
Characteristic of an individual able to meet conflict and opposition flexibly.Flexible-Cohering
A type of contract in which the buyer pays the seller a set amount, asdefined by the contract, and the seller can earn an additional amount if itmeets defined performance criteria.
Fixed-Price-Incentive Fee(FPIF) Contract
See firm-fixed-price contract.Fixed-Price Contract
A type of contract in which the buyer pays the seller a set amount, asdefined by the contract, regardless of the seller’s costs.
Firm-Fixed-Price (FFP)Contract
The character or condition of being finished, complete, and conclusive.Finality of Acceptance
Is communication to a person about his or her behavior.Feedback
Doing activities in parallel that normally would be done in sequence.Fast Tracking
Making it easier to explain difficult ideas.Facilitating Understanding
Making it easier to exchange information.Facilitating Communication
Focusing attention and energy outside oneself.Extraversion
Risks beyond the control or influence of the project team External Risks
The funds a company spends in order to sell services and products.Examples include rent, utilities, depreciation, and so forth.
Expense (also known asindirect costs)
Statements of “not included” for a future system.Exclusions
The expected additional cost needed to complete an activity, a group ofactivities, or the project. Most techniques for forecasting ETC includesome adjustment to the original estimate based on project performanceto date. Also called “estimated to complete.” See also earned value andestimate at completion.
Estimate to Complete (ETC)
The expected total cost of an activity, a group of activities, or the projectwhen the defined scope of work has been completed. Most techniquesfor forecasting EAC include some adjustment of the original costestimate based on project performance to date. Also shown as“estimated at completion.” Often shown as EAC = Actuals-to-date + ETC.See also earned value and estimate to complete.
Estimate at Completion(EAC)
An assessment of the likely quantitative result. Usually applied to projectcosts and durations, an estimate should always include some indicationof accuracy (for example ± x percent). Usually used with a modifier (forexample, preliminary, conceptual, feasibility). Some application areashave specific modifiers that imply particular accuracy ranges (forexample, order-of-magnitude estimate, budget estimate, and definitiveestimate in engineering and construction projects).
Estimate
The deposit of something into the care of a mutually agreed-uponcustodian for delivery to the grantee on some defined set of conditions.
Escrow
Organizing and managing a business undertaking.Entrepreneurial
Behaviors displayed by individual team members sometimes at theexpense of the rest of the team and its objectives.
Emotional Issues: Causes ofSelf-Oriented EmotionalBehavior
Number of calendar days over which the task occurs.Elapsed Time
DefinitionTerm
Glossary
Glossary GL-7 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
Risks the project team can control or influence .Internal Risks
Characteristic of an extravert; interested and concerned about a widerange of areas rather than being interested only in a few areas.
Interests Have Breadth
A behavioral response to the exercise of power. Influence isachieved through the use of power.
Influence
Compensation for loss or damage.Indemnity
The amount remaining after all revenues are accounted for and all costsand expenses are deducted.
Income (also called profit, netincome, and net profit)
Being part of; being involved.Inclusion
Having no personal reference or connection. Showing no emotion.Impersonal
When behavior produces or contributes to positive outcomes, it isconsidered a strength. When it produces or causes negative outcomes, itis considered a weakness. A weakness in some cases might be anoverdone strength.
Identify your strengths andweaknesses incommunicating with others
Nondelivery of a product or nonpayment of an obligation due as a meansof applying pressure to the receiving party.
Holdback
Groupthink is defined as a mode of thinking in which group members'premature striving for agreement somehow overrides their ability(motivation) to realistically appraise alternative courses of action.
Groupthink
The amount remaining after all revenues are accounted for and all directcosts are deducted, but before all indirect expenses are deducted.
Gross Profit
A grave error, caused by negligence or incompetence, with significantnegative consequences.
Gross Mistake
The country or state law applicable to the contract.Governing Law
A non-overhead-related expense not directly attributable to a singleproject. This account is generally used by administrative and seniormanagement.
General and Administrative
Staff are grouped hierarchically by specialty with each employee havingone clear supervisor; a conventional line organization (PMBOK® 2.3.3). Ina functional organization, each employee has one supervisor. Functionalorganizations still have projects, but the scope of the project is limited tothe boundaries of the organizational unit.
Functional OrganizationalStructure
The amount of time an activity can be delayed without delaying the earlystart of any immediately following activities.
Free Float
An intentional perversion of the truth; a false representation.Fraud
Having common interests or beliefs.Fraternal
Predicting future project status and progress (PMBOK® 10.3).Forecasting
An act of God or irresistible force or inevitable accident that could not beavoided by the exercise of due care. Examples: earthquake, fire, flood,hurricane, and third-party labor dispute/strike.
Force Majeure
Influenced or dependent on previously existing terms or agreements; anintentional failure of a party to enforce, or willingly delay enforcement of,a contract requirement, usually done for an act of immediate or futureconsideration from the other party.
Forbearance
DefinitionTerm
Glossary
Glossary GL-8 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
A sum stipulated and agreed upon by the parties at the time they enteredthe contract as an estimate of the actual damages the harmed party willsuffer as a result of not meeting an obligation. Note: If a party fails tomeet the specified obligation but pays the liquidated damages, he or shecannot be considered in default of the contract for not meeting thatobligation.
Liquidated Damages
Concerned with the cost of the resources needed to complete projectactivities and the effects of project decisions on the cost of using theproject product (PMBOK® 7).
Life-Cycle Costing
The condition of being responsible for a possible or actual loss.Liability
All debts and moneys owed to others by a company.Liabilities
Support-type activity (for example, vendor or customer liaison) that doesnot readily lend itself to measurement of discrete accomplishment;generally characterized by a uniform rate of activity over a specific periodof time.
Level of Effort
A letter format agreement that authorizes contract performance to startfor a limited scope and time while final negotiations are taking place.Note: Previously known as "letter of intent."
Letter of Authorization
The causes of variances, the reasoning behind the corrective actionschosen, and other types of lessons learned documented so they becomepart of the historical database for the project and other projects of theperforming organization (PMBOK® 4.3.3.3).
Lessons Learned
The underlying purpose of the contract must be allowed by law.Legal Purpose
Involves persuading or influencing other people to set aside fora period of time their individual concerns and to pursue acommon goal that is important for the welfare of the group.
Leadership
A modification of a logical relationship that causes an acceleration ordelay, respectively of the successor task. Any of the dependencies mightrequire specification of a lead or a lag to accurately define therelationship.
Leads and Lags
Establishing direction, aligning people, and motivating and inspiring(PMBOK® 2.4.1).
Leading
In the critical path method, the latest possible point in time that an activitycan begin without delaying a specific milestone (usually the project finishdate).
Late Start (LS)
A defect that existed at the time of acceptance but that could not bediscovered by reasonable inspection or test.
Latent Defect
In the critical path method, the latest possible point in time that an activitycan be completed without delaying a specific milestone (usually theproject finish date).
Late Finish (LF)
Characteristic of a person who prefers to make a decision rather thanpostpone it.
Judging Means Deciding
Persons who gather by looking for possibilities, meanings, andrelationships between and among things.
Intuitive Types
Focusing attention and energy inside oneself.Introversion
DefinitionTerm
Glossary
Glossary GL-9 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
A method of calculating earnings that does not consider the effect oftaxes on the earnings.
Net Earnings before Taxes(NEBT)
Can be described as the process through which two parties move fromdiverse positions to a point of mutual agreement by means ofdiscussions.
Negotiation
Conferring with others in order to come to terms or reach an agreement(PMBOK® 2.4.3).
Negotiating
Path through the network with low total float.Near-Critical Path
Risk evaluation method using simulation to exercise the frequencydistribution “thousands of times.” The cumulative frequency distributionwill identify the probability of achieving a particular date (task or project)or cost (task or project) within a probability range.
Monte Carlo Technique
A form of market structure in which one or only a few firms dominate thetotal sales of a product or service.
Monopoly
A change to a document or understanding.Modification
A generic agreement containing the base definitions and terms andconditions, which can be used as a base for generation of the finalagreement.
Model Agreement
Identify the scheduled start or completion of major deliverables and keyexternal interfaces (PMBOK® 6.4.3.1).
Milestone Charts
A significant event in the project, usually completion of a majordeliverable.
Milestone
A person who serves as teacher or coach; an advisor.Mentor
The documentation of mutually agreed-to statement of facts, intentions,procedures, and parameters for future actions and matters ofcoordination. Also, the documentation of mutual understanding of anissue by two or more parties.
Memorandum ofUnderstanding
Project manager shares responsibility with functional managers to assignpriorities and direct the work of the people assigned to the project; ablend of functional and projectized structure (PMBOK® 2.3.3).
Matrix OrganizationalStructure
The factor applied to get from cost to final price.Markup
The actual percentage earned on a project.Margin
Producing key results expected by stakeholders (PMBOK® 2.4.1).Managing
A separately planned quantity used to allow for future situations which mybe planned for only in part (sometimes called “known unknowns).Management reserves may involve cost or schedule. Managementreserves are intended to reduce the risk of missing cost or scheduleobjectives. Use of management reserves requires a change to theproject’s cost baselines. (PMBOK® Glossary 165)
Management Reserve
Determining whether a particular product can be producedcost-effectively by the performing organization (PMBOK® 12.1.2.1).
Make-or-Buy Analysis
The act of applying updates, changes, and fixes to a product.Maintenance
Greatness in size or measurable quantity.Magnitude
The act of carrying on a suit in a court of law.Litigation
DefinitionTerm
Glossary
Glossary GL-10 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
The time frame before a contract is awarded. The activities of the buyerand the seller before a contract is awarded. Phase 1 of the contractmanagement process.
Preaward
Is the ability to get someone else to do something you wantdone, or the ability to make things happen or get things donethe way you want.
Power
The time frame after a contract has been awarded. The activities of thebuyer and the seller after a contract has been awarded. Phase 3 of thecontract management process.
Postaward
The physical work scheduled, plus the authorized budget to accomplishthe scheduled work. Previously, this was called the budgeted cost of workscheduled (BCWS). (PMBOK® p 204)
Planned Value (PV)
Meetings held to assess project status or progress (PMBOK® 10.3.2.1).Performance Reviews
Collecting and disseminating performance information to providestakeholders with information about how resources are being used toachieve project objectives (PMBOK® 10.3).
Performance Reporting
A monetary guarantee that the contractor will perform according tocontract terms.
Performance Bond
Awareness, comprehension; insight or intuition; discernment. To takenotice of; observe to achieve understanding.
Perceptions
Compensation to be paid in case of nonperformance of the conditions ofa contract.
Penalties
A government grant giving an inventor the exclusive right to make or sellhis or her invention for a limited period of time.
Patent
The right to reuse (that is, remarket, modify, enhance, and preparederivative works based on) all material prepared under a buyer's directionand control.
Ownership
The interest or stake the owners have in a company; the sum of theowners’ original investment plus the accumulation of all profits that havebeen retained (not distributed to stockholders) in the company sinceinception.
Owners’ Equity
A statement in a contract that specifies which provision should control ifthe contract or related contracts or agreements contain conflicting orinconsistent provisions.
Order of Precedence
A person who manages to achieve his or her goals.Operator
An unequivocal and intentionally communicated statement of proposedterms made to another party. A proposal is normally a written offer by aseller describing its offering terms.
Offer
Unsophisticated technique that uses the severity scores of the top 10 riskevents plus the sum of the scores; the normalized risk score then equalsrisk score (sum of severity ratings) times 10, divided by the number ofrisk events.
Normalized Risk Score
Failure of a party to meet an expectation or a contractual commitment.Nonperformance
DefinitionTerm
Glossary
Glossary GL-11 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
Collection of generally sequential project phases (PMBOK® 2.1).Project Life Cycle
Project manager has full authority to assign priorities and direct the workof individuals assigned to the project (PMBOK® 2.3.3). There areadvantages and disadvantages: The project manager controls theresources. Directing work is easier without battling the functionalmanager, but few organizations have these structures given the expenseinvolved and loss of efficiencies.
Projectized OrganizationalStructure
A subset of project management that includes the processes required toensure that the project is completed within the approved budget. Itconsists of resource planning, cost estimating, cost budgeting, and costcontrol.
Project Cost Management
A repository for the project management system of a project. Thisrepository includes all the agreements, plans and procedures to befollowed by the project, and all of the project management productsproduced by these plans and procedures. Abbreviated “PCB.”
Project Control Book
Process used to monitor, evaluate, and compare the project’s plannedresults with its actual results to determine the status of cost, schedule,and technical performance objectives.
Project Control
Process that provides for acceptance of the project by the client/projectsponsor and includes completion of project records, final revision andissuance of documentation to reflect completion criteria, and retention ofessential project documentation.
Project Closeout
Clear statement of project intent; provides a preliminary delineation ofroles and responsibilities; serves as a reference of authority for the futureof the project.
Project Charter
A temporary endeavor undertaken to create a unique product or service.Temporary means that every project has a definite beginning and adefinite end. Unique means that the product or service is different insome distinguishing way from all similar products and services.(PMBOK® 1.2)
Project
Describing what the project team has accomplished (PMBOK® 10.3).Progress Reporting
Uses sequential network logic and a weighted average duration estimateto calculate project duration (PMBOK® 6.4.2.1).
Program Evaluation andReview Technique (PERT)
A group of interrelated projects managed together.Program
Identifying which project needs can best be met by procuring products orservices outside the project organization (PMBOK® 12.1).
Procurement Planning
Knowledge shared between two parties regarding a private matter,usually implying consent or concurrence. Note: When two parties signan agreement, there is privity between them.
Privity
The principal seller performing under the contract.Prime Contractor
Forecasting where difficulties might arise.Predicting Potential ProblemAreas
Method of constructing a project network diagram using nodes torepresent activities and connecting them with arrows that showdependencies; also called activity-on-node.
Precedence DiagrammingMethod (PDM)
DefinitionTerm
Glossary
Glossary GL-12 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
The total funds received from the sales of products or services.Revenue
Description of the types of resources required and in what quantities foreach element of the WBS (PMBOK® 7.1.3.1).
Resource Requirements
A form of network analysis in which scheduling decisions (start and finishdates) are driven by resource management concerns (PMBOK®
6.4.2.4).
Resource Leveling
Provision in the project plan to mitigate cost and schedule risk (PMBOK® 11.5).
Reserve
Statement of desire for a future system.Requirements
Legal actions for enforcing a right or compensating a wrong.Remedies
Dependencies that exist between activities.Relationships
A mutual exchange of trade or other concessions or privileges betweentwo parties.
Reciprocity
Identifying which quality standards are relevant to the project anddetermining how to satisfy them (PMBOK® 8.1).
Quality Planning
Evaluating overall project performance on a regular basis to provideconfidence that the project will satisfy the relevant quality standards(PMBOK® 8.2).
Quality Assurance
Measuring the probability and consequences of risks and estimating theirimplications for project objectives. (PMBOK® 11.4).
Quantitative Risk Analysis
Performing a qualitative analysis of risks and the conditions to prioritizetheir efforts on project objectives. (PMBOK® 11.3).
Qualitative Risk Analysis
Material on which the copyright or patent right has expired and that isavailable for unrestricted use. Property owned by a state or nationalgovernment.
Public Domain
Owned by a particular person; relating to a certain owner.Proprietary
A definition of the business opportunity that is to be accomplished in aproject; includes a statement of the business need, a set of requirements,and a schedule.
Proposition
A person who helps bring about or further the growth or establishment ofa project or an organization.
Promoter
People who plan, implement, and monitor the work being performed forthe client/project sponsor.
Project Team
People with an interest or role in the project.Project Stakeholders
The planned dates for performing activities and meeting milestones(PMBOK® 6.4.3.1).
Project Schedule
Quantifiable criteria that must be met for the project to be consideredsuccessful (PMBOK® 5.2.3.2).
Project Objectives
Schematic display of the project’s activities and the logical relationships(dependencies) among them.
Project Network Diagram
Individual accountable for the project who is the single point of contact forthe project and is responsible for identifying potential stakeholders.
Project Manager
Applying knowledge, skills, and tools to project activities, subprojects,and programs to meet or exceed stakeholder needs and expectations.
Project Management DefinitionTerm
Glossary
Glossary GL-13 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
A strategic process for identifying and managing possible future eventswhich may influence project performance and results. The process isapplied throughout the project life cycle and is most valuable whenstarted early
Risk Management
Used to summarize risk events and their status.Risk Log
A formal facilitated workshop intended to identify risks to the project.Risk Identification Workshop(RIW)
The product of a risk identification workshop; it lists risks by focus area,risk drivers, risk owners, actions required to facilitate evaluation of risks,and a preliminary prioritization of the risks identified.
Risk Identification Report(RIR)
Determining which risks are likely to affect the project and documentingthe characteristics of each risk. (PMBOK® p 207).
Risk Identification
A potential source of risk.Risk Focus Area
A consistent way to relate probability and impact with respect to a givenrisk event.
Risk Event Severity Matrix
The likelihood (expressed as a percentage) that a possible risk event willoccur.
Risk Event Probability
The effect imposed on a project if a risk event occurs.Risk Event Impact
A possible occurrence that, if it does happen, will impact the achievementof project objectives.
Risk Event
Determining the probability of occurrence, the magnitude of loss orimpact of each identified risk event, and the severity of risk.
Risk Evaluation
A condition that increases the probability of impact to a project objective.Risk Driver
Used to provide a description of a risk identified in the risk identificationreport.
Risk Control Form (RCF)
Monitoring and managing risk.Risk Control
A checklist of potential focus areas and risk drivers; most checklists havean evaluation capability, and some offer mitigation suggestions.
Risk Checklist
Risk evaluation technique that makes use of a checklist of risk sourcesagainst which selected conditions in a proposal or concept are compared.In some business units, tools are available to facilitate the comparison,provide a score, and in some cases suggest mitigation approaches.
Risk Assessment Checklist(RACL)
Used to keep track of the action plan for each risk event; there is oneRAL for each risk event.
Risk Action Log (RAL)
A possible undesirable and unplanned event that could result in theproject’s not meeting one or more of its objectives.
Risk
Synonymous with ownership as it applies to materials that are consideredintellectual property, including code, program listings, reports,documentation, programming tools, drawings, and similar works; it doesnot include licensed programs.
Rights in Data
Claims, power, or privileges to which a party is justly entitled; can belegally enforceable.
Rights
Formal management actions that promote or reinforce desired behavior(PMBOK® 9.3.2.3).
Reward and RecognitionSystems
DefinitionTerm
Glossary
Glossary GL-14 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
One source among others in a competitive marketplace that, forjustifiable reason, is found to be most worthy to receive a contract award.
Single Source
Selling expenses result from a company’s efforts to make sales, such assales commissions. General and administrative expenses are expensesincurred to support the operations of a company, such as utilities, rent,and so forth.
Selling, General, andAdministrative Expenses(SG&A)
The difference between the amount of work performed and what wasplanned or scheduled.
Schedule Variance (SV)
A measure used to calculate performance efficiency with respect toschedule. BCWP/BCWS.
Schedule Performance Index(SPI)
The approved project schedule; provides the basis for measuring andreporting schedule performance (PMBOK® 6.5.1.1).
Schedule Baseline
Planned dates for performing activities and meeting milestones.Schedule
A share of proceeds paid to a proprietor, author, or inventor by thosedoing business under some right belonging to that proprietor, author, orinventor.
Royalties
Assigning roles (who does what) and responsibilities (who decides what)to appropriate project stakeholders; uses a responsibility assignmentmatrix (RAM) (PMBOK® 9.1.3.1).
Role and ResponsibilityAssignments
Developing procedures and techniques to enhance opportunities andreduce threats to the project’s objectives. (PMBOK® 11.5).
Risk Response Planning
Person assigned primary responsibility to mitigate a particular risk eventand keep the project team informed of the status of efforts; the ownershould be the person who controls the source of the risk.
Risk Owner
Monitoring residual risk, identifying new risks, executing risk reductionplans, and evaluating their effectiveness throughout the project life cycle.Generally occurs in the life-cycle phases, starting with delivery anddevelopment and continuing through the end of the project life cycle;consists of all efforts to execute the risk management plan, iterate the riskmodel, and improve or achieve effective management of risk on a givenproject. PMBOK® 11.6).
Risk Monitoring and Control
The four-step interactive process that is focused on risk identification,evaluation, mitigation, and monitoring and applied throughout the projectlife cycle.
Risk Model
A facilitated workshop intended to identify and develop risk mitigationoptions and actions.
Risk Mitigation Workshop
The product of a risk management workshop; contents include alternativepropositions considered, recommended mitigation plans, problems,recommended contingency actions and costs, recommended actionplans, and risk evaluation.
Risk Mitigation Report (RMR)
Risk response strategy that decreases risk by lowering the probability of arisk event’s occurrence or reducing the effect of the risk should it occur.
Risk Mitigation
Deciding how to approach and plan risk management activities for aproject. (PMBOK® 11.1).
Risk Management Planning
Documenting the procedures to be used to manage risk throughout theproject (PMBOK® 11.1.3).
Risk Management Plan
DefinitionTerm
Glossary
Glossary GL-15 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
Clause in a contract that defines the circumstances under which one orboth of the parties can end the agreement. Termination might be forcause when one party does not do something called for in the contract,causing the other party to terminate (for example, the client fails to paythe bill). Usually termination requires written notice within a certain periodof time (for example, 60 days).
Termination
Relates to observable behaviors and core values that help shape one’sleadership and management styles.
Temperament Defined
What the team believes will happen.Team Predictions
Enhancing the ability of stakeholders to contribute as individuals as wellas enhancing the ability of the team to function as a team.
Team Development
Sets broad performance objectives, the roles and responsibilities for theproject team, and ground rules for the team’s operation.
Team Charter
Management and individual actions taken specifically and primarily toimprove team performance (PMBOK® 9.3.2.1).
Team-Building Activities
A small number of people with complementary skills who arecommitted to a common purpose, performance goals, andapproach for which they hold themselves mutually accountable.
Team
Process used by the project manager to manage and control suppliers’responsibilities and performance on the project.
Supplier Management
A business entity that can provide a product or service as a third party,part of a client/project sponsor organization, or part of your ownorganization.
Supplier
Part of a project managed with a level of independence.Subproject
A business entity that does work for you under a contract.Subcontractor
A contract between a buyer and a seller in which the products or servicesbeing acquired are for use in a prime contract.
Subcontract
Describing where the project now stands (PMBOK® 10.3).Status Reporting
Description of the procurement item in sufficient detail to allowprospective sellers to determine if they are capable of providing the item(PMBOK® 12.1.3.2).
Statement of Work
A clear and concise documentation of a risk event; consists of a conditionand a consequence for each identified risk event.
Statement of Risk
Individual or organization who is actively involved in the project or whoseinterests might be affected, either positively or negatively, as a result ofproject execution or successful project completion.
Stakeholder
What kinds of skills are required from what kinds of individuals or groupsin what time frames (PMBOK® 9.1.1.2).
Staffing Requirements
Individual or group within the performing organization that providesfinancial resources for the project (PMBOK® 2.2).
Sponsor
Statements of commitment for a future system.Specifications
The only source in a marketplace that offers a desired product or service.There are no other choices.
Sole Source
DefinitionTerm
Glossary
Glossary GL-16 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
The items at the lowest level of the WBS (PMBOK® 5.3.3.1).Work Packages
Delivers a distinct, identifiable product or result with definite completioncriteria.
Work Element
An activity-oriented structure of the work to be done to systematicallypresent all the work on the project affecting cost, schedule, orspecifications. Each descending level represents an increasingly detaileddefinition of a project component. Project components may be productsor services.
Work Breakdown Structure(WBS)
Unplanned responses to negative risk events (PMBOK® 11.6.3.1).Workarounds
Serves as a repository for work element descriptions.WBS Dictionary
An assurance by the seller of property that the property is, or shall be, asit is represented or promised; an agreement that the seller will fix adefect. Warranty will be limited in time.
Warranty
The voluntary relinquishment of a right, privilege, or advantage.Waiver
A business entity that provides a commercial, off-the-shelf product.Vendor
The difference between the budget at completion and the estimate atcompletion. BAC–EAC.
Variation at Completion(VAC)
Comparing actual project results to planned or expected results(PMBOK® 10.3.2.2).
Variance Analysis
Amount of time a full-time equivalent (FTE) can be used for the length ofthe project.
Utilization Factor
Not authorized or justified.Unwarranted
A type of contract in which the buyer pays a fixed price for each unit ofproduct purchased.
Unit Price
Passing from one activity to another smoothly.Transition
Amount of time an activity can be delayed from its early start withoutdelaying the project finish date.
Total Float
Use of a consistent method to weigh and apply the probability and impactof risk events as a basis for establishing priority to determine the top 10risk events.
Top 10 Scoring
A measure that provides ratio of the work remaining to the budgetremaining. (BAC–BCWP)/(BAC–ACWP).
To-Complete PerformanceIndex (TCPI)
Without bias or preference. Being logical, detached, and analytical.To Be Objective
A statement in a proposal or contract that implies a seller must deliver aproduct or service in the shortest possible time.
Time Is of the Essence
A type of contract in which the buyer reimburses the seller for laborexpended and the cost of materials provided.
Time-and-Materials
Another business entity, not part of your own or the client/projectsponsor’s business.
Third Party
Terms—The essential statements on which the validity of the contractdepends. Conditions— Defined events that must occur before contingentterms in a contract become fixed.
Terms and Conditions
DefinitionTerm
Glossary
Glossary GL-17 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.
A work product that is specified in an agreement is called a deliverable
� Services work products, which are services provided by the project.
� Management work products, which are the items related to themanagement of the project
Work Time
� Technical work products, which are items produced by the projectWorks for Hire
There are three types of work products:Working Hypothesis
Any measurable, tangible, verifiable outcome, result, or item that mustbe produced by a project or sub-project.A work product that is specified in an agreement is called a deliverable
Work Products
DefinitionTerm
PMBOK" is a trademark of the Project Management Institute, Inc. which is registered in the United States and other nations.
Glossary
Glossary GL-18 © Copyright IBM Corp. 2002Course materials may not be reproduced in whole or in part
without the prior written permission of IBM.