pm 02- production planning system

24
Production Planning Production Planning System Victor A. Villegas S. [email protected]

Upload: rafael-hernandez

Post on 28-Jan-2016

215 views

Category:

Documents


0 download

DESCRIPTION

Talk about the all diagram in production area.

TRANSCRIPT

Page 1: PM 02- Production Planning System

Production Planning

Production Planning System

Victor A. Villegas S. [email protected]

Page 2: PM 02- Production Planning System

What is the purpose of

production planning?

Page 3: PM 02- Production Planning System

The purpose of planning

To ensure business profitability by organizing

the use of production factors

Processes

Machinery

Equipment

Labour skills

Material

to satisfy demand with the right products, at the

time required, with quality, and as economically

as possible

Page 4: PM 02- Production Planning System

The purpose of planning

Demand Resources

Page 5: PM 02- Production Planning System

What do we need to

know to do the plans?

Page 6: PM 02- Production Planning System

Planning system questions

What are we going to make?

What do we already have?

What does it take to make it?

What do we need to get?

These are also known as questions of priority

and capacity

Page 7: PM 02- Production Planning System

Planning system questions

Priority “The relative importance of jobs, i.e., the sequence in

which jobs should be worked on” —APICS Dictionary

In this case, what products, in what quantities and when are they needed

Capacity “The capability of a worker, machine, work center,

plant or organization to produce output per time period”

—APICS Dictionary

The capability of manufacturing to produce goods and services

Page 8: PM 02- Production Planning System

The key is to match

Priorities Capacity What is needed,

When, How much

Capability to produce what is needed when its

needed

Page 9: PM 02- Production Planning System

So, what does the

production planning

system look like?

Page 10: PM 02- Production Planning System

Planning and Control Hierarchy

Material Requirements

Planning (MRP)

Master Production Schedule

(MPS)

Production Activity Control (PAC)

Sales and Operations Planning (S&OP)

Strategic Business

Plan

Tim

e S

co

pe

Level of Detail Low High

Short

Long

Master Plan

Planning Phase

Implementation phase

Page 11: PM 02- Production Planning System

Planning and Control Hierarchy

Strategic Business Plan

Statement of the major goals and objectives to be achieved by the company over a long period, i.e. two to ten or more years

Defines markets, product lines, etc.

General direction about how objectives are going to be achieved

Based on long-range forecasts

Receives inputs from Marketing, Production, Engineering and Finance, and then provides them with direction and coordination

Page 12: PM 02- Production Planning System

Planning and Control Hierarchy

Production Plan

Quantities of each

product that must be

produced in each period

Desired inventory level

Resources or equipment,

labor, and material

needed in each period

The availability of

resources needed

Sales & Operations Plan

Strategic Business Plan

Marketing Plan

Production Plan

Detailed Sales Plan

Master Production Schedule

J.R. Tony Arnold, Introduction to Materials Management, 4th edition, Prentice-Hall, 2004

Annual

Monthly

Weekly or daily

Page 13: PM 02- Production Planning System

Planning and Control Hierarchy

Master Production Schedule (MPS)

Plan for the production of individual items

Breaks down the production plan to show the quantity of each item to be made during each period

The level of detail is higher than in the Production Plan

Break down from families of products to end items

Shorter time periods, e.g. weeks vs. months

Planning horizon extends from 3 to 18 months, but it depends mainly on purchasing and manufacturing lead times

Page 14: PM 02- Production Planning System

Planning and Control Hierarchy

Material Requirement Planning (MRP)

Plan for the production or purchasing of specific components used in making the items in the MPS

High level of detail, establishing the times at which each component is needed to make each end item

Planning horizon is directly related to manufacturing and purchasing lead times

Page 15: PM 02- Production Planning System

Planning and Control Hierarchy

Purchasing and Production Activity Control

(PAC)

This is the implementation and control phase

Production controls the flow of work through the factory detailing specific orders to produce items from the Material Requirements Plan

Purchasing controls the flow of raw materials into the factory detailing the items to be purchased rather than produced

Planning horizon is very short, usually from a day to a month, and it is reviewed daily

Page 16: PM 02- Production Planning System

Planning and Control Hierarchy

Capacity Management

At each level of the planning and control system, reconciliation with resources must be made

There is a calculation of resources needed for the priority plan, and a process of finding methods to make capacity available

Inadequate resources = missed production schedules

Resources significantly exceed planned production = idle resources and extra cost

Must obtain the right resources or change the plan

Page 17: PM 02- Production Planning System

Planning and Control Hierarchy

Material Requirements

Planning (MRP)

Rough-Cut Capacity Planning (RCCP)

Master Production Schedule

(MPS)

Capacity Requirements

Planning (CRP)

Production Activity Control (PAC)

Operation Sequencing

Resource Requirement

Planning (RRP)

Sales and Operations Planning (S&OP)

Capacity Management

Priority Management

Input/Output Control

Strategic Business

Plan

At each level, there are three questions:

What are the priorities?

What capacity is available?

How can differences be resolved?

Page 18: PM 02- Production Planning System

Capacity Planning Levels

Resource Planning

Long-range capacity resource requirements

Translates priorities from the production plan into

some total measure of capacity, such as gross labor

hours

Adjusting capacity involves changing staff levels,

capital equipment, product design or other facilities

If it is not possible to create a resource plan for the

production plan, the production plan has to be

changed

Page 19: PM 02- Production Planning System

Capacity Planning Levels

Rough-cut Capacity Planning (RCCP)

The primary source of information is the MPS

Its purposes include

Verifying the feasibility of the MPS

Provide warnings of bottlenecks

Ensure utilization of work centers

Advise vendors of capacity requirements

Page 20: PM 02- Production Planning System

Capacity Planning Levels

Capacity Requirements Planning (CRP)

The primary source of information is the MRP

Shows a greater level of detail than RCCP

Its main concern are the individual orders at

work centers

Calculates work center loads and labor

requirements for each period

Page 21: PM 02- Production Planning System

Is there a software that

can support the

production planning

process?

Page 22: PM 02- Production Planning System

Manufacturing Resource Planning (MRP II)

“A method for the effective planning of all

resources of a manufacturing company”

—APICS Dictionary

Objective: to integrate the resources of an

organization

Page 23: PM 02- Production Planning System

Manufacturing Resource Planning (MRP II) Business Plan

Sales and Operations Plan

Marketing Plan

Production Plan

Resources OK?

Master Schedule

Material Requirements Plan

Resources OK?

Production Activity Control

Performance Measures

Purchasing

Sales Plan

Fe

ed

ba

ck

Fe

ed

ba

ck

Clo

se

d lo

op

MR

P

J.R. Tony Arnold, Introduction to Materials Management, 4th edition, Prentice-Hall, 2004

Yes

Yes

No

No

Page 24: PM 02- Production Planning System

Production Planning

Production Planning System

Victor A. Villegas S. [email protected]