plug & play · the plug and play project instead focuses on the costs that current differing...

27
Plug & Play Facilitating grid connection of low emissions technologies CONSULTATION SUMMARY PAPER FEBRUARY 2017

Upload: others

Post on 20-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

Plug & PlayFacilitating grid connection of low emissions technologies

CONSULTATION SUMMARY PAPER FEBRUARY 2017

Page 2: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

i

ClimateWorksAustralialSeedAdvisoryFebruary2017

PlugandPlay ExecutiveSummary

Harmonisedrequirementsforconnectionstoallelectricitydistributionnetworksareakeypartofensuringthattheinnovativetechnologiesandbusinessmodelsrequiredtomeetclimatetargetsanddriveenergyproductivitycancontributetotheirfullpotentialinprovidingourenergyneedsinthefuture.

Harmonisedrequirementsshouldleadtolesscostlyconnectionrequirements,moreresponsivetothedevelopmentofnewtechnologies.Eliminatingunnecessarycoststoconsumersandthewidereconomyshouldincreaseconsumeruptakeofnewtechnologies.Thisincludesnewtechnologiesthatcanreducegreenhousegasemissionssuchasdistributedelectricitygeneration,storage,demandmanagementequipmentandelectricvehiclecharginginfrastructure.Removingunnecessarycostsfromgridconnectionscancreateavirtuouscircle–supportingAustraliainmeetingourpolicyobjectivesinenergyproductivityandemissionsreduction.Removingunnecessarytechnicalrequirementsfromgridconnectionscanalsosupportproductdevelopmentandtheuptakeofinnovation,aswemovefromsmallerlocaltolargernationalmarketsforequipmentandtechnology.

ForAustraliatoplayitsfairshareintheglobaleffortagainstclimatechangewemustensurethattheinnovativetechnologiesandbusinessmodelsrequiredtomeetclimatetargetsanddriveenergyproductivitycanreadilyparticipateintheenergymarket.

TheobjectiveofthePlugandPlayprojectistoidentifyanddrivetheimplementationofinstitutionalandpolicysolutionstomakegridconnectionsforexistingandemergingtechnologiesasstraightforwardandcosteffectiveaspossibleforcustomersandproponents,whilesafeguardingelectricitysupply.

Thispaperoutlinesthefindingsfromthefirststageoftheprojectwherewehavelookedatthecurrentconnectionrequirementsandprocessesandthebarriersandunnecessarycoststheyimposeontheconnectionoflowemissiontechnologiestotheelectricitynetwork.Thepaperisinformedbydesktopresearchandinitialconsultationswithstakeholdersfromthepropertysector,energyserviceproviders,manufacturersandsuppliersofequipment,andfundersofrenewableenergyprojects.ItbuildsonpreviousworkbyClimateWorksAustraliaandSeedAdvisoryinthearea.Wewillbeseekingfurtherinputfromstakeholdersinthesecondstageoftheprojectproposedtofinishinmid-2017.

Duringthesecondstageoftheproject,wewillundertakefurtherconsultationtoidentifyandtesttheproposedsolutionswithkeystakeholdersandrefinetheseintoafinalreportinmid-2017,settingoutasolutionsroadmap.Itwillidentifythekeyactorsandtheirrolesinenactingthesolution,aswellasdocumentinternationalexamplesofsolutionstotheidentifiedbarriers.Subsequentphaseswillfocusonimplementationtheagreedsolutions.

Page 3: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

ii

Aboutus

ClimateWorksAustraliaClimateWorksAustraliaisaleadingindependentorganisationactingasabridgebetweenresearchandactiontoidentify,modelandenableend-to-endsolutionstoclimatechange.

Sinceourlaunchin2009,ClimateWorkshasmadesignificantprogressandearnedareputationasagenuineandimpartialadvisertokeydecisionmakersfromallsidesofpoliticsandbusiness.Ourcollaborativeapproachtosolutionsthatwilldeliverthegreatestimpactencompassesathoroughunderstandingoftheconstraintsofgovernmentsandthepracticalneedsofbusiness.

Wedothisbylookingforinnovativeopportunitiestoreducegreenhousegasemissions,analysingtheirpotential,resolvingobstaclesandhelpingtofacilitateconditionsforourtransitiontoaprosperous,netzeroemissionsfutureby2050.

ClimateWorkswasco-foundedbyTheMyerFoundationandMonashUniversityandworkswithintheMonashSustainableDevelopmentInstitute.

SeedAdvisorySeedAdvisoryisacommercialadvisoryfirmspecialisingintheenergysector,withexpertiseinstrategy,riskmanagement,policydevelopmentandcommercialmanagement.

Sinceourlaunchin2008wehaveadvisedenergymarketparticipants–newandprospective–onthecommercialandregulatoryimplicationsoftheirpotentialinvestmentsinconventionalandrenewabletechnologies.Wehavealsoadvisednationalandstategovernmentsontheinteractionoftheirenergy-relatedpoliciesandotherareasofgovernmentpolicy,suchastherelationshipbetweensmartmeteringandAustralianPrivacylaw,ortheimpactonelectricvehicleuptakeoflocalregulationanddistributionbusinesspracticesaffectingresidentialandcommercialconnectionavailabilityandcost.

AcknowledgmentofSupport

ClimateWorksAustraliaandSeedAdvisorywouldliketothankthoseexpertswhohaveprovidedinputtotheconsultationsundertakenforthisproject.

WewouldalsoliketothanktheAustralianEnergyCouncil(AEC)foritsfinancialsupportofthisproject,anditsmembersfortheirparticipationintheconsultationsundertaken.ForafulllistofthoseconsultedpleaseseeAppendix2.

Page 4: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

iii

Contents

1.Abouttheproject...........................................................................................1

2.Whyfocusonconnectionrequirements?......................................................2

2.1Otherbarriers...............................................................................................3

3.Theelectricitysystemischanging..................................................................4

3.1Customersarebecomingactiveparticipantsinthesystem.........................4

3.2Thedistributors’challenge...........................................................................5

3.3Meetingourenergyproductivityandemissionsreductionobjectives........5

4.Currentconnectionrequirements..................................................................7

4.1WhathappensduringaConnectionApplication?........................................8

5.Impactofthecurrentconnectionprocess...................................................11

5.1Coststobusinessandconsumers...............................................................11

5.2Impactonuptake.......................................................................................12

5.3Inefficiencieswheninstallinginmultiplelocations....................................12

5.4Variationsinrequirementsreducescompetitioninequipmentmarkets..13

5.5Impactoninnovationandtechnicalchange..............................................14

5.6Riskofunfairmarketadvantage................................................................14

6.Characteristicsofpreferredsolutions..........................................................15

6.1Consistentnationalstandard:rareexceptions..........................................15

6.2Minimumperformancestandards,setindependently..............................16

6.3Responsivenesstotechnologicalchange...................................................17

6.4Competitiveneutrality...............................................................................18

7.Whatnext?...................................................................................................19

8.References....................................................................................................20

Appendix1:Summaryofenergymarketreformprocesses.............................20

Appendix2:Stakeholderengagement.............................................................22

Page 5: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

1

1. Abouttheproject ClimateWorksAustraliaandSeedAdvisorycommencedthePlugandPlayprojectinSeptember2016.Theoverallobjectiveoftheprojectistoidentifyinstitutionalandpolicysolutionswhichwouldmakeconnectiontothegridforexistingandemergingnewtechnologiesasstraightforwardandcosteffectiveaspossible,whilesafeguardingtheperformanceofthegrid.

Theprojectfocuseson:

• identifyingandaddressingthesourceofbarrierstoinstallationandunnecessarycosts

• describingthewiderimpactsofcurrentrequirementsandprocessesforconnectiontothegridonuptakeandenergyproductivity

• consideringhowstandardsandrequirementsintheelectricityindustryareset,interpretedandapplied

• proposingsolutionstocreategridconnectionprocessesthatwillensurethatnetworkedelectricityissecure,affordableandlowemission

Thisprojectwillundertakeabroadanalysisoftheimpactsonthemarketofthecurrentsituationforconnectionsofembeddedgenerationandstorage,onuptakeofthesetechnologiesandoncapacitytomeetourenergyproductivityandemissionsreductionobjectives.

Thisprojectwillnotlookatspecifictechnicalrequirementsoftheelectricitydistributionnetworkservicesproviders(distributors).Issuesaboutthesetechnicalrequirementsarewell-documented.DistributorshavebeenobligedtopublishtheirownrequirementssinceOctober2014,andourpreviouswork,andthatofothers,hasanalysedthedifferences.Ourpreviousworkfound'evenwithinjurisdictions,distributorstakemateriallydifferentapproachesto…connectingembeddedgenerationtotheirnetwork’.(ClimateWorksAustralia(CWA),PropertyCouncilofAustralia(PCA)andSeedAdvisory2015).Similarly,Energeia’sworkfortheCleanEnergyCouncil(CEC)foundthat‘Technicalrequirementsareinconsistentacrossnetworks’(CEC2016).

ThePlugandPlayprojectinsteadfocusesonthecoststhatcurrentdifferingrequirementsimposeonconnectionproponentsandthewidereconomy,andonalternativemodelsthatcouldreducethesecostswhilemaintainingthesafetyandperformanceofthenetworks.

Ourworktodatehasconfirmedourinitialthinkingthatvariationinrequirementsandprocessesbetweendifferentdistributorsisactingasabarriertotheadoptionofnewtechnologiesandimposingadditionalcosts.Thisdiscussionpaperexplainstheissuesarisingfromthecurrentconnectionrequirementsandprocessesandotherresultsarisingfromourinitialconsultations.

ClimateWorksAustraliaandSeedAdvisorywillbeseekingfurtherinputfromstakeholderstocollaborativelydevelopinstitutionalandpolicysolutions,beforeengagingwithdecisionmakerstoassistthosecollaboratingwithuscanadvocateforreform.

Page 6: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

2

2. Whyfocusonconnectionrequirements? TheinitialfocusofthePlugandPlayprojectwillbeontheimpactsofconnectionrequirementsandprocesses;andtheirvariationacrossAustralia.Thefocusoftheprojectstemsfromanumberofissues:

•AmajortransformationinthestructureofAustralia’selectricitysectoristakingshape.Thistransformationisbasedoncustomers’interestinandabilitytogeneratetheirownrenewableenergyand,lookingforward,ontheabilityofcustomerstomanagetheirinteractionswiththegrid.Inthefuture,customersarelikelytocollectivelyprovidearangeofservicespreviouslyrestrictedtolargespecialisedgenerationunits.Newtechnologiesandservicesarebeingdevelopedatarapidratewithtrialsforinnovativetechnologiesunderway.

• Federalandstatepolicytoincreaserenewablegenerationanddecreaseemissionsacrosstheeconomyiscombiningwithrapidlydecreasingcostsoflowcarbontechnologies,andconsumers’desiretoachievegreaterenergyindependence,tofuelthistransformation.Suchpolicywillresultinfurthershiftsinthenumber(andtype)ofconnections.

• Australia’sfifteendistributorshavevariedconnectionrequirementsforrenewableenergygenerationandstoragetechnologies.Ourownwork(CWAetal2015),andworkfortheFutureProofinginAustralia’sElectricityDistributionIndustryProject(CEC2014)haveextensivelydocumentedtheextentofvariationintheseconnectionrequirementsandprocesses.

• Thevariationinrequirementscreatescomplexityandthusadditionalcostsforcustomers,projectproponentsanddistributors.Insomecasesitcanleadtotheabandonmentofotherwiseattractiveprojects.TherecentAll-EnergyConferenceidentifieddelaysinthecustomerdecisionmakingprocessandintheconnectionprocessassourcesofincreasedinstallationcosts.

• Thevariationinrequirementsmayhaveaparticularimpactonthecommercialsector.Thereisahighlevelofambitionwithinthesectortorefurbishexistinginstallationsand/orinstalldistributedrenewablegeneration,asthishasbecomemorefinanciallyattractive.Installationatscaleispotentiallymorecost-effectivethansmall-scaleinstallations.However,stakeholdershaveidentifieddifficultiesduetovaryingconnectionrequirementsandprocesses.DistributorsacrosstheNationalElectricityMarketacceptsmallinverterconnectedsystemsprovidedtheinvertercomplieswithAS4777;nosimilarharmonisedrequirementsexistformid-sizesystemsbelow30MW.

• Developmentsinbehindthemeterapplicationscompetewithservicescurrentlyorpotentiallyprovidedbydistributorsand/orgenerators.Realisingthefullpotentialofnewtechnologieswillrequireashiftfromsmall,localnetworkmarketstoanationalmarket:platformeconomiesarebestrealisedatscale.Newtechnologiesandservicescanshiftwhobenefitsfromthediversityofcustomerbehaviour–thecustomer,thedistributororthemarket.Currentconnectionprocesseswhichrequireindividualdistributorstomanagethesafetyandperformanceoftheirnetworksmaybeasourceofpotentialcompetitivedisadvantagetonewentrantsandcustomers–evenundertherecentlyintroducedring-fencingguideline1.

• Finally,stakeholderfeedbacksuggeststousthatourelectricitymarketscurrentlylacksupportforinnovationintechnologiesandservicesforbothnewmarketentrantsandexistingmarketparticipants.

1.TheAustralianElectricityRegulator(AER)hasintroducedthering-fencingguidelinetoensurefunctionalseparationoftheprovisionofdirectcontrolservicesbydistributorsfromtheirprovisionofotherservicesandtopromotecompetitionintheprovisionofelectricityservices.

Page 7: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

3

Australia’svariableconnectionrequirementsraisepublicpolicyquestionsaboutthecostsimposedonallnetworkconnections;thecostsofreducingcompetitionintheequipmentmarketbylimitingavailablemarkets;and,therelationshipbetweenthedistributor’sdecisioninadoptingitsownrequirementsandthewiderimplicationsforcompetitionbetweendistributorsanddistributedenergyproviders.Asitcurrentlystandsthere’snooversightoftheappropriatenessofdistributors’requirements.Thereisnomechanismtocheckwhethertherequirementsstrikethecorrectbalancebetweenreducingrisksandthecoststheyimposeonconnectionsandthecommunityasawhole.

Harmonisingconnectionrequirementsandaddressingthewayinwhichthoserequirementsaredevelopedwillmakethetransformationofourenergysystemeasier,cheaperandmoreequitable.Itcouldallowconnectionrequirementstobemoreresponsivetotherateoftechnicalchange.

2.1OtherbarriersWerecognisetheexistenceofarangeofbarrierstotheuptakeofembeddedgenerationandthedevelopmentoffurthermarket-basedservicesenvisagedaspartofthewiderenergymarkettransformation.Ourstakeholdershavenominatedthefollowingkeyconcerns:

• Noexistingplatformormechanismtoeffectivelyrewardgridsecurity/demandmanagementservicesforservicesthatarenotreadilyincludedincurrentdemandmanagementprograms.

• Currentwholesaleelectricitypricespresentlittleincentivetosellintothegrid,evenforlarger,morecost-effectiveinstallations.

• Distributorscontinuetoimposesignificantbarrierstoexportsfromaconnection,totheextentthatconnectionproponentsnowroutinelysizetheirinstallationssoastoremainwithintheenvelopeoftheproperty’suse,regardlessofthepotentialscalebenefitsoflargerinstallations.Aggregationmechanismsinthewholesalemarketareunsuitableforportfolioscombiningloadandgeneration,andonlyasmallnumberofretailersarepreparedtoaggregateacustomers’supplyanddemandacrossthecustomer’sportfolio.

• Therearestillnoeffectivemechanismstoaddressthe“lastin,worstdressed”approachtothecostsofupgradingalocalnetworkimposedonaconnectionproponent.Standardcontracts,requiredbyChapter5oftheNationalElectricityRules,aresilentonmechanismstoaddressthisissue(CWAetal2015).

• Islanding–thatis,theabilityofapropertytocontinuetoself-generatewherethelocalnetworkhasfailed–representsasignificantpotentialbenefitforpropertieswherethepropertymightrequirepowerintheeventofalocalnetworkfailure.Exampleswherethismightbeofbenefitinclude:localemergencycentres;otherlocationswheresignificantnumbersofpeoplemightbepresentatthetimeofafailureormightcongregateafterfailure;etc.However,distributorscurrentlyareunwillingtoconsiderislandingapartfromsomesmall,localisedtrialschieflyinvolvingresidentialcustomers2.

However,theseissuesaresecondarytotheimportanceofestablishingacost-effectiveconnectionprocess.Intheabsenceofcost-effectiveconnections,someinstallationswillnotgoahead,whileotherswillbesmallerthanoptimal,givensitecharacteristics.

2.Forexample:http://www.ausnetservices.com.au/CA257D1D007678E1/All/41F5DC5437B4E7C2CA257F3A0020577041F5DC5437B4E7C2CA257F3A00205770/$file/160419%20Mooroolbark%20trial%20launch%20%20FINAL.pdf

Page 8: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

4

3. Theelectricitysystemischanging

3.1CustomersarebecomingactiveparticipantsinthesystemMassadoptionofdistributedsolarPVgeneration,especiallyintheresidentialsector,hasdrivenatrendtowardsmoreactivecustomerparticipationintheelectricitysystem.TheEnergyNetworksAustralia(ENA)andCSIRO’sElectricityNetworkTransformationRoadmapprojectfocusesontheneedtoplaceconsumersbothresidentialandcommercialatthecentreofnetworkplanningtomanagethetransitionfrompassiveconsumersofelectricity,togeneratorsandtradersofelectricity(ENAandCSIRO2016).

Figure1:TotalinstalledcapacityofrooftopPVandIPSSintheNEM(AEMO,2016b)

Inresponse,theelectricityindustryisshiftingtowardsamorecustomercentricmodelwherecustomers’choicesandactionsareincreasinglyimportant.Regulatorsandpolicymakersareundertakingarangeofreformsinmeteringandinformationprovision.TheresearchandpolicyreformprocessesunderwayaddressingawiderangeofissuesaresummarisedinAppendix1.

BatterystoragetechnologiesnowenteringtheAustralianmarketarelikelytofollowasimilartrendwithahighlevelofinitialconsumerinterestandconsumerpricespredictedtodecreaserapidly(MorganStanleyResearch2016).AEMOcurrentlypredictsthatbatterystoragecapacitywillincreasefromalmostzeronowto6.6GWhoverthenexttwentyyears,whilerooftopsolarPVisprojectedtoincrease350percentfrom4.3GWto19GWoverthesameperiod(2016b)3.Theseprojections,whichmaybeconservativegivenpreviousexperiencewiththerateofsolarPVuptakerelativetoinitialprojections,implyahighnumberofrelativelysmallconnectionsintheshorttomediumterm.Bytheendof2016,therewerealready1.6millionsmallsolarPVsystemsinstalledinAustralia,mostofwhichwereconnectedintheNEM.(CleanEnergyRegulator2017).

3.Thistotal19GWofsolarPVincludes3.8GWexpectedtobeintegratedwithbatteries.

Page 9: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

5

3.2Thedistributors’challengeAsthetraditionalstaticnetworkoflarge-scalecentralisedgenerationevolvestorespondtoactiveconsumerswhogeneratetheirownelectricity,distributorsfacesignificantchallengestotheircurrentoperatingmodelandtothemanagementofthesafetyandperformanceoftheirnetworks.Thedistributors’requirementstomanagethisarediscussedinSection04.Thesechallengesincludeasignificantmismatchbetweenconsumptionandtheproductionprofiles,requiringtwo-wayflowstobefacilitatedinlocalnetworkareasandacrossnetworks.

Rapidchangesinnetdemandduetotransitoryweatherconditionsaremorecommon,changingwholesalemarketdynamics.InsomesituationsandweatherconditionssolarPVcanreducenetworkpeaks.However,theflowsfromembeddedgenerationcanbeunpredictable,overalladdingtothecomplexityofmanagingthenetwork.CombiningsolarPVwithbatteriescanmitigatethetechnicalchallengespresentedbyincreasedlevelsofdistributedenergygeneration,forexample,byallowingcustomerstoreducetheirexportsintothenetworkbystoringtheirenergyproductionforuseatpeakconsumptionperiods.4However,networkchallengesarelikelytoremain.

IfcustomersincludemanagementsystemswiththeirsolarPVandbatterysystem(integratedinthebattery,orasathirdpartyproviderservice),thencustomerscanco-ordinatetheirdemandandgenerationwiththemarket.Thesemanagementservicesseektooptimisewhenthecustomerexportselectricityandwhentheyimportit–eitherforuseorstorage.Thisfurtherincreasesthepotentialfortheirnetdemandtochangefrommomenttomoment.

Allthesedynamicscanalternetworkinvestmentrequirementsandwholesaleenergydemand.Thecombinationofembeddedgeneration,storageandmanagementsystemscancompetewithservicescurrentlyorpotentiallyprovidedbydistributorsand/orgenerators,whichcanchangewhobenefitsfromthediversityofcustomerbehaviour–thecustomer,thedistributororthemarket.

3.3MeetingourenergyproductivityandemissionsreductionobjectivesChangestoourelectricitysystemwillbeintegraltomakingouruseofenergymoreproductiveandreducingouremissions.TheCouncilofAustralianGovernments(COAG)hascommittedtoagoalofimprovingAustralia’senergyproductivityby40percentby2030.TheNationalEnergyProductivityPlanoutlinesaseriesofinitiativestoreachthisgoalinordertoreducecoststoconsumers,maintainingAustralianbusiness’competitivenessandreducinggreenhousegasemissions.5

Australia’sratificationoftheParisAgreementon9November2016commitsAustraliatoanemissionsreductionpathwayinlinewithconstrainingglobalwarmingtowellunder2degrees.Australiahasalsocommittedtobepartofcollectiveglobalactiontoreachnetzeroemissions.AnalysisindicatesthatdoingAustralia’sfairsharerequiresachievingnetzeroemissionsacrosstheAustralianeconomyby2050.6

ClimateWorksDeepDecarbonisationPathwaysreportdemonstrateshowthisgoalcanbeachievedwhilemaintainingeconomicgrowththroughfourpillarsofdecarbonisation.

4.TherecentEnergyTransformationRoadmappresentation(ENAandCSIRO2016),forexample,raisedthepossibilitythat,dependingonthewayinwhichtariffsarestructured,andthemanagementofcustomerdiversity,peaknetworkrequirementscouldbeshiftedtotimeperiodsimmediatelybeforepeakpowerratescutin,orimmediatelyafteroff-peakpowerratescommence.5.COAGEnergyCouncil,20156.Forexamplethelong-termcarbonbudgetproposedbytheClimateChangeAuthority(CCA2014,Chapter8)willrequirenetzeroby2050givencurrentemissionrates.

Page 10: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

6

Figure2:The4pillarsofDecarbonisation

Gridconnectedlowcarbontechnologiesplayacentralroleinachievinganetzeroeconomy.Distributedrenewablegenerationcontributestowardsdecarbonisationofthegrid,whiledemandmanagementequipmentcontributestoambitiousenergyefficiency,andstoragetechnologiessupportnetworkstabilitywithhigherpenetrationofrenewablegeneration.Electricvehiclecharginginfrastructuresupportsfuelswitchingfrompetroleumtolowcarbonelectricity.

ASBECandClimateWorksAustralia’srecentreportLowCarbon:HighPerformance,onemissionsreductionpotentialintheAustralianbuiltenvironmentsectorfoundthatinstallationofcommercialandresidentialdistributedsolargenerationcouldcontributeareductionof50MtCO2eby2030.Thiswoulddeliver18percentofAustralia’scurrent2030emissionsreductiontarget.7

7.ASBEC2016,LowCarbonHighPerformance.

Page 11: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

7

4.Currentconnectionrequirements

Statelegislationconfersondistributorstheresponsibilityformanagingthesafetyandperformanceofthenetworkwithinlocaljurisdictionalguidelines,andthepowerstocontrolcustomerconnectionsinlinewiththeseresponsibilities.Somestatesimposesymmetricrightsandobligationsoncustomerswhouseanetwork;inothers,customers’responsibilitiesoutweightheirrightswhenconnectingtothenetwork.

Distributorssettechnicalconnectionrequirementstoallowthemtomeettheirresponsibilitiestomanagetheirnetwork.TherequirementsfitwithintheNationalElectricityRuleswhichhasthreedifferentconnectionprocessesforproposedinstallationsthatarethefocusofthisproject.Installationsunder30kW,whicharecoveredbytheAustralianStandardAS4777(seebreakoutbelow),followtheprocessforabasicconnection.Largerinstallationsunder5MWmayfollowastandardornegotiatedconnectionprocess.WithinthebroadguidelinesintheNER,eachdistributoremploystheirownprocessesfornegotiatingtheconnectionofnon-standardinstallations.Mostinstallationsabove30MWsarecoveredbyChapter5oftheNER.

Eachdistributor’srequirementsgovernthetypeandperformanceoftheequipmentthatcanbeconnected,andthelevelofprotectionrequiredforaninstallationtobeapprovedinthatdistributor’sfranchisearea.TherequirementsmayberelevantAustralianStandards,internationalstandards,requirementsspecifictothedistributor,orsomecombinationofthese.Connectedequipmentmustbecertifiedascompliantwiththerelevantrequirement(s).Requirementsvaryfromnetworktonetwork.Thedifferencesbetweendistributors’requirementsandtheissuestheycreatearewelldocumented8.

AustralianStandardsaimtoacceptrelevantinternationalStandards,oracceptwithmodificationswhererequiredforAustralianconditions.WheretheAustralianmarketisaheadofdevelopmentofinternationalstandards,astandardisdevelopedindependently.Forexample,StandardsAustraliaisdevelopingastandardforresidentialbatterystorageinstallationsintheabsenceofarelevantinternationalstandardapplicabletotheAustralianmarket.Oncethatstandardisavailable,however,there’snoguaranteethatnetworkswillallowinstallationsconsistentwiththestandardtoproceedwithoutotherlocalrequirements.

Asitcurrentlystands,there’snooversightof,ormechanismtoreview,theappropriatenessofdistributors’requirementsandthecoststheymayimposeonconnections,orthecommunityasawhole.Proponentshavetheabilitytocontestthedistributor’sdecisionsoncemade,butthisreviewisonlypossibleinstallationbyinstallation.

Insettingrequirementsforequipmentthatdifferfromthoseadoptedbyotherdistributors,orrelevantAustralianorinternationalstandards,thelocaldistributorisassertingitsjudgementthatuniquerequirementsareneededtoaddressconditionswithinitsnetwork.Thedistributormayhavespecificrequirementsinparticularareascharacterisedbypoorlyperforming,vulnerableoroldinfrastructure.However,stakeholdershaveraisedconcernswithinourconsultationsthatthesejudgementsarenotalwaysappropriate9.

8.ClimateWorksAustralia,PropertyCouncilofAustraliaandSeedAdvisory,ImplementingtheConnectingEmbeddedGenerationRule:ProjectOutcomesReport,May2015Energeia,EmbeddedGenerationGridConnectionStandardsScopingStudy:Task3B.1,May20169.Insomeinstances,stakeholdershaveexperiencedresponsesfromdistributorswhereolderversionsofcurrenttechnologiesweremandatedinpreferencetobetterperforming,morerecentversions.

Page 12: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

8

4.1Whathappensduringaconnectionapplication?Thediagramonthefollowingpage(Figure3)isastylisedrepresentationoftheconnectionprocess(otherthanforverysmallapplicationscoveredbyAS4777)foraconnectionapplicationinadistributionnetwork.Atypicaldescriptionoftheconnectionprocesswilloutlinethevarioussteps.Thisdiagram,incontrast,focussesonthedecisionpointsinaconnectionapplicationarisingfromthedistributor’stechnicalrequirements:

• Self-assessment:Theproponent’sself-assessmentthattheapplicationcomplieswiththedistributor’sspecificrequirements.

• Thedistributor’sassessmentoftheapplicationagainstitsownmandatedrequirements.

• Safeinthislocation?Thedistributor’sassessmentoftheapplicationinrelationtothenetworkcharacteristicsofthelocationforwhichtheinstallationisproposed

• Meetingadditionalrequirementsofthelocation:Ifnecessary,thedistributor’srequirementsforremediationoforaugmentationtothelocalnetworktoenabletheinstallationtoproceed.

Thediagramalsodescribes,ataveryhighlevel,theproponent’savenuesforclarifyingordisputingadistributor’sdecision,wheretheseexist.Thisdiagramhasbeenusedinourinitialconsultationswithstakeholderstoassistusinidentifyingandclassifyingproponents’experiences.

Standardisedrequirementsforsmall-scalePVCOAGadoptedtheAustralianStandardAS4777(anditssuccessors)astheprimarytechnicalrequirementforabasicconnectionforsmallscalePV.AS4777mandatesinverterconnectionforallcomplyingsolarPVinstallations.Initsmorerecentversionsithasaddedadditionalfunctionalityrelatingtothemanagementofthenetwork.ThisuseofaharmonisedstandardhasfacilitatedthewidespreadinstallationofsmallscalesolarPVpenetrationinEasternAustralia.

However,somedistributorsaddadditionalrequirementsforconnectionscoveredbyAS4777,forinstanceiftheirnetworkhasahighpenetrationofsolargeneration.Distributorswhowishtoreduceexportsintothenetworkfromahighpresencesolargenerationhaverespondedinanumberofways.Thedistributormaylimitthesizeofthesystemtoasetsizeorasizelessthanthatcustomer’sconsumptionenvelope;theymayrequirethatbatteriesareinstalledaspartofthesystemortheymaynotpermitfurthersolarPVinstallationsinspecificareasintheirnetwork.Othersincludeanadditionalassessmentstepbeforeasmall-scaleapplicationisformallyprocessed;orlongerwaitingperiodsthanforabasicconnectionapplicationaspartoftheassessmentperiod.

Page 13: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

9

Figure3Stylisedrepresentationoftheconnectionprocessforaconnectionapplicationinadistributionnetwork

Self-assessmentFirst,aproponentassesseswhethertheproposedconnectionissafeandcompliantwiththedistributors’requirements,basedonthedistributor’spublishedmaterials,beforemakinganapplication.

Theproponentmayhavedifficultydecidingiftheproposedinstallationiscompliantduetolackofclarityinthedistributor’sinformationabouttheirrequirements.Forexample,ifadistributor’srequirementsrefertoawidegroupofstandardswithadditionalrequirementstheproponentmayhavetomakeajudgementbetweenapparentlydifferingrequirements,andmaynotbeconfidentthattheirjudgementonwhichapplieswillbeacceptabletothedistributor.Thisisdiscussedinourearlierwork(CWAetal2015)andtheEnergeiastudyfortheCEC(2016).

Theequipmentconfigurationproposedmayhavebeenacceptableandsuccessfullyinstalledelsewhere,butthelocaldistributormayhavedifferentrequirements.There’snorecoursetoanotherauthorityintheeventthatadistributor’srequirementsruleoutequipmentconsistentwithotherdistributors’requirements,Australianstandardsorcomparableinternationalstandards.

Thedistributor’sassessmentSecond,inmakinganapplication,theproponentisaskingthedistributorwhetheritagreesthattheconnectionapplicationmeetsitsrequirements.Ifthedistributorrefusesanapplicationonthesegrounds,aconnectionproponenthasrecoursetotheNER’sdisputeresolutionprocedures,shouldtheproponentchoosetopursueadispute.Thedistributortowhichtheconnectionapplicationisbeingmadeistheonlyauthorityonrequirementsforitsnetwork.

Someofthestakeholderswehaveinterviewedhavearguedthatambiguitiesindistributor’spublishedmaterialsmakethisstepasdifficultforthedistributorasitisforproponents.Intheabsenceofclearrequirements,thedefaultpositioncanbearejectionofacompliantapplication,ratherthantheexerciseofjudgementintheinterpretationofvagueorambiguousrequirements.

Page 14: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

10

Typically,thisstepintheprocessisnotdifferentiatedfromadecisiononwhethertheproposedinstallationissafeatagivenlocation.Wehavedistinguishedbetweenthetwobecausetheoutcomesoffailingeachofthesearedifferent.Ifadistributordecidestheconnectiondoesnotmeetitsrequirementsitmayrejecttheconnectionapplication,requireanamendmenttotheproposedconfigurationorequipmentorrequirefurtherstudies.

Ifnetworkcharacteristicsrequiresignificantadditionalprotectionequipment,oraninvestmentinnetworkaugmentation,thedistributormustspecifytherequirements,and,inthecaseofnetworkaugmentationworks,provideanestimateofthecostsoftheworksrequired.

Safeinthislocation?Alllocationsinanynetworkcannotsupportallconnectionapplications:networkcharacteristicsdifferbylocationandovertime.Adistributor’sintimateknowledgeofprevailingconditionsinthelocalnetwork,andmoreadvancedconnectionapplicationsrelatingtothesamelocationmeanthedistributoristheobviousarbiterofthesafetyofanapplicationinrelationtoanygivenlocation.

AsweunderstandtherequirementsoftheNER,ifaninstallationwouldnotbesafebecauseofthelocalconditions,adistributorshouldimposespecificrequirementsontheconnectionapplicationorrequiretheconnectionproponenttofunddownstreamworksinthedistributionnetwork.Inthefirstcase,thoserequirementsareintendedtobringintocompliancetheproposedconnectionandthedistributor’ssitespecificrequirements.Inpractice,connectionproponentscontinuetopointtooccasionswhereabanonallexportsintothenetworkhasbeenimposed,ratherthantherequirementsforexportstobeacceptableintherelevantsectionofthenetworkbeingspecified.AconnectionproponentcanusetheNER’sdisputeresolutionprocedurestodisputetheadditionalrequirements,ortocontestadistributor’srefusaltocontemplatetheapplicationattheproposedlocation.

MeetingadditionalrequirementsofthelocationWherethenetworkrequiresadditionalinvestmenttomaketheinstallationsafeinthatlocation,insomestatestheconnectionproponentmaychooseitsowncontractortoundertaketheworks,orrequirethedistributortoseekcompetitivequotesfortheworksrequired.Theproponentcanchoosenottoproceedwiththeapplicationifthecostsaretoohigh,ormaychoosetodisputethedistributor’srequirementsundertheNERdisputeresolutionprocedures.Iftheproponentgoesaheadwiththeworktheyhavearighttocollectfromfutureconnectionscontributionstosharedinfrastructureinvestments,but,intheabsenceofco-operationfromthedistributor,thatrightisunenforceable(CWAetal2015)10.

Aconnectionproponenthasonlyalimitedabilitytopredictthedistributor’sspecificationofitsdownstreamrequirements,excepttotheextentthatthedistributor’sDistributionAnnualPlanningReportprovidessomecurrentinsightintolocalconditions.Distributorshavearguedthatlocalconditionscanchangesorapidlythatthetaskofkeepingpubliclyavailablematerialsonlocalstatusup-to-dateisanoneroustask.

10.Noneofthemodelcontractsrequiredtobepublishedbythedistributorsandreviewedinthereportmadeanyreferencetothepotentialfortherecoveryofexpendituresonnetworkaugmentationfromfutureconnections.

Page 15: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

11

5.Impactofthecurrentconnectionprocess

Customersconnectingnewtechnologiesundercurrentprocessesbearunnecessarycosts–whethermeasuredinthetimetoconnect,ordirectcostsofconnection,orboth.

VaryingrequirementsfromdistributorsfragmenttheAustralianmarketintostateandlocalnetworkareas.Thisfragmentedmarketdirectlyincreasesthecostsofequipment.Thefurthercostsitimposesonstandardisationandlearningbydoingareadragonenergyandnationalproductivityandinnovation.

Further,thesecostsrepresentareductionincustomerwelfare.Thestatusquoalsohindersbusinesses–thedistributorsandallthoseinvolvedwithofferingtechnologiesandservices.Thesecostsreducetheuptakeofnewtechnologiesand,byextension,limittheachievementofAustralia’semissionsreductionandenergyproductivitygoals.Inthefollowingsections,we’vesummarisedobservationsaroundthecurrentconnectionprocessfromouranalysisandconsultationstodate.

5.1CoststobusinessandconsumersInconsistentandnon-transparentrequirementsfortheconnectionoftechnologiestothegridimposecostsandreducethebenefitsavailablefromharmonisation.Ambiguityortheabsenceofawrittendescriptionofdistributor’srequirementsincreasesthedifficultyofaninstallation.Restrictingtheequipmentapprovedforusedecreasescompetitionintheequipmentmarketandhence,mayincreasecoststocustomers.

Givenprojectedcustomeruptakeofrenewableenergyovertheshorttomediumterm,anyreductionintransactioncostsassociatedwithmoreconsistent,transparentandbalancedconnectionrequirementsislikelytodeliversignificantaggregatedcostsavings.Forexample,AEMO’sprojectionsfortheNEFRsuggestcommercialandindustrialcustomerswillinstallaround25,000solarPVsystemsoverthenext10years,addingaround1GWtototalsolarPVinstalledintheNEM.

Directcostreductionsfromharmonisingconnectionrequirementsareexpectedtobesubstantial.Thereductioninconsumers’installationscosts–fromthefirst10yearsofanationallyconsistentsetoftechnicalrequirementsforgridconnectionsforsmalltomedium(30kWto5MW)embeddedgenerators-couldbeworthatleast$140m($2016),accordingtoestimatespreparedbyEnergeiafortheFuture-ProofinginAustralia’sElectricityDistributionIndustryProject(FPDI)(CEC2016).AEMO’sprojecteduptakeofsolarPVbycommercialandindustrialcustomersinthe2016NationalElectricityForecastingReportisaround20percenthigherthantheestimateEnergeia’susesinitsbenefitcalculation:onalike-for-likebasis,savingswouldbe20percenthigher(SeedAdvisorycalculationbasedonAEMO2016b).11

Whicheveroftheseestimatesareused,thebenefitsfromchangestotherequirementsforgridconnectionsareunderstated,becausetheyonlyconsidercurrentlevelsofinstallation.Broadeningnationallyconsistentrequirementstolargerandsmallerconnectionswouldincreasedirectbenefits,andlowercostswouldbelikelytoincreasethenumberofinstallationsofembeddedgeneratorsofallsizes.Reducingthecostofinstallationscanhaveequityimplications–somecustomerscurrentlyexcludedfrominstallingtheirownrenewableenergycouldaffordtodosoandsavemoneyacrossthelifeofthesystem.

11.TheestimatehasbeencalculatedbasedonAEMO’sprojectionsforadditionstosolarPVinstalledbyCommercialandIndustrialcustomers,assumingthesameaveragesizeinstallationandsimilarcostsperinstallationasusedbyEnergeia.AEMO’sandEnergeia’sprojectionshavedifferentinitialtrajectories,butovera10yearperiod,thenumberofinstallationsassumedtounderlieAEMO’scalculationsisaround20percenthigherthanEnergeia’sprojectionforthesameperiod.

Page 16: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

12

5.2ImpactonuptakeIncreasingthenumberofinstallationsandreducingthecostscouldcreatearangeoffurthereconomy-widebenefits,improvingenergyproductivity,increasingtheuptakeofrenewableenergyandcontributingtonationalobjectivesforreducedemissions.Lowercoststocustomersincreasedemand:theprogressofresidentialsolarPVinstallationsshowsusjusthowpotentthiseffectcanbe.If,forexample,wetakeAEMO’sassumptionsthatcustomers’responsivenesstopricechangesis0.1percentforeverypercentagechange,thenforevery10percentreductionininstallationcostsachieved,thenumberofinstallationsincreasesby1percent(calculationsbasedonAEMO2016b).Overa10yearperiodcustomerswillinstallaroundanextra2,100systems,oraround86MWoffurthersolarPV,ifusingEnergeia’sestimateforannualinstallations(CEC2016).TheincreaseislargerusingAEMO’sprojections,byaround10MW12.

Conversely,delaysandcostsinachievinginstallationsreducedemand.Forlargerpotentialinstallations,thistakesanumberofforms.Theconnectionproponentcouldreducetheirambition,reducingthescaleoftheprojectproposedeithertoaddresspotentialnetworkissues,orinresponsetodirectdistributorfeedbackonanapplication.Or,theprojectmaybeabandoned;inthecommercialpropertysector,projecttimelinesandconnectionapplicationtimelinesarestillinconsistent,despiterecentreformstoconnectionapplicationprocesses.Thecostsofdelayingaprojecttypicallyfaroutweighthebenefitsofembeddedgeneration:timeconsumingconnectionprocessesdirectlyreduceproponents’interest.

Stakeholdershavealsomentioneddistributorrequirementsthatdirectlylimitembeddeddistribution,withouttakingintoaccounttheindividualinstallation.Anexampleisdistributors’useofanabsolute,undiversifiedcapacitylimit,wherethetotalcombinedinstalledcapacityofsolarPV,batteryandinverterinstallationsisrestrictedtobelowadefinedlimit,regardlessofthelikelypatternofconsumptionandproductiononthecustomer’spremise.

Informedbytheirexperiencesinothermarkets,customersexpectbehind-the-meterinstallationstofollowrapidlyafterthepurchasedecision.Stakeholdershavereportedtousthedifficultiesconfrontingretailerssimultaneouslymanagingcustomerexpectationsforclose-to-immediateinstallationanddistributorprocesses,insomecasesrequiring60businessdaysprocessingtime.Managingtheseprocessesimposesadditionalcostsonretailersand,ultimately,allcustomers;andthedelaysmayreducethepotentialsizeandgrowthofacurrentlyimmaturemarket,ifcustomers’experiencesarenegativeintheearlystagesofthemarket.

5.3InefficiencieswheninstallinginmultiplelocationsThecurrentsituationhasobviousimplicationsforproponentsaimingatstate-wideornationalroll-out.Thedifferencesfromonedistributortothenextmeanthateachprojectwillbetoagreaterorlesserextentunique.Designs,procurementandinstallationcostswillallbemoreexpensivethanwouldotherwisebethecase.LargersolarPVinstallationsaresubjecttosignificantlylongerdelaysthansmallresidentialinstallations.Thedelaysintroducesignificantlagsintoinstallers’businessesrelativetothepipelineforsmallresidentialsolarPVinstallations.

Alternatively,aproponentcouldinvesttimeandcostup-fronttoseekdistributors’agreementtoacommondesign.Thereis,however,ariskthatthemostonerousdistributorrequirements(orthedistributortheleastwillingtonegotiate)setthebarforallinstallations.Thiswouldimposeunnecessaryexpenseonthetotalproject,and,forsomeprojects,reducethelikelihoodoftheprojectproceeding.

12.Incalculatingtheimpacts,we’veassumedAEMO’sprojectionsarebasedoncurrentconnectionprocessesandtimelines.

Page 17: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

13

Inthecommercialpropertysector,hightransactioncostsresultingfrominconsistentrequirementsfromdistributortodistributor,non-transparentandcomplexconnectionrequirementsandprocessesallremainsignificantbarriers.Thisisparticularlytrueforbusinesseswithsitesspreadacrossdifferentdistributors.Consequently,despitehighlevelsofambitioninthesector,commercialsolarPVinstallationsinAustraliaareprogressingataslowerthandesiredrate.Projectsareapproachedonanindividualbasis,evenwhenthepropertyownerormanagerrecognisesthepotentialbenefitsofapproachingprojectsaspartofawiderprogramofwork.Installationratesaresloweventhoughrooftopsolarshouldbeacost-effectiveinvestmentformanybuildingowners,especiallythosewithlargeunutilisedroofspacessuchaslargeretailandindustrialassets.

Theinabilitytoachieveeconomiesofscaleisnotlimitedtotheconnectionproponent.Banksandfundmanagerswiththegoalofincreasingtheirlendingtorenewableenergyprojectsseeharmonisationaspartofaprocessthatshiftsprojectfinancingfromthecurrent,highcost,bespokemodeltoasimplereplicablemodelwithaprojectpipelinetosupportefficientfundingapproaches.Incontrastwiththecurrentmodel,areplicablemodelforprojectdevelopmentwouldsimplifyprojectdocumentation,duediligenceandsecuritisation,decreasefinancingcostsandincreasefinanceavailability.

5.4VariationsinrequirementsreducescompetitioninequipmentmarketsTheAustralianmarketforconnectionequipmentisnotlarge;iflocaldistributorsadoptdifferentrequirements,themarketfortheaffectedequipmentisreducedtofragmentedlocalmarkets.WehaveheardfromequipmentmanufacturerswhochoosenottocompeteintheAustralianmarket,becauseofthecostsofparticipation13.ThestatusquoaffectsnotonlytheavailabilityofproductsintheAustralianmarketbutalsothedepthofproductandserviceoffering,particularlywheredistributorshaveuniquerequirements.Lowerproductavailabilityresultsinlesscompetition,andinturn,highercosts.WehavealsoheardfromastakeholderwhereAustralianinstallationsinaninternationalroll-outofidenticalfacilitieshavetheunenviablepositionofdominatingthelistof“10mostexpensiveinstalls”internationally.Thestakeholderstatedthiswaslargelyowingtodifferencesincostofequipment,drivenbyalackofcompetitioninthemarketplaceinAustraliaforcertifiedequipment,andreinforcedbythehighcostofcertification14.

LimitedcompetitionintheAustralianmarket,combinedwiththehighcostofcertifyingequipmentforAustralianrequirements,resultedinasingleavailablecertifiedmodelintheAustralianmarketofaspecifictransformer.ThattransformercostmorethanfourtimesthecostofthesameequipmentintheJapanesemarket.GivenalimitednumberofexpectedinstallationsthecostsofcertificationspecificallyfortheAustralianmarketmeanstherewouldbenopaybackforthecustomerinimportingandcertifyinganalternativetransformerforherownuse.AndthefragmentationoftheAustralianmarketreducestheincentiveforothermanufacturerstocompetewiththeexistingcertifiedmodel.

Insummary,installationtechnologiesinAustraliacanbesignificantlymoreexpensivethaninothersimilarcountries,becausethechoiceofequipmentcertifiedtoAustralianStandardsislimited,asaresultofacombinationofthesmallsizeoftheAustralianmarket,theextensivedifferencesinnetworks’requirementsandthecostsofcertification.

13.Thesamecouldbesaidwhere,forexample,StandardsAustraliaadoptsmateriallydifferentstandardsfromtheprevailinginternationalstandards:customersbearcostsfromareductioninsupplierstotheAustralianmarketplace,whiledifferentstandardsmayprovidenocommensuratebenefittocustomersorthecommunitymorebroadly.14.Thisinformationwasprovidedduringstakeholderconsultations.

Page 18: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

14

5.5ImpactoninnovationandtechnicalchangeLocaltechnicalstandardsettingforconnectionofequipmentlimitstheabilityofnewmodelsornewtechnologies-includingthosedemonstratingsuperiorperformanceandsafety-toenterthemarket.Issuesidentifiedduringourconsultationsinclude:

• ExistingAustralianStandardsareslowtoadapttotechnicalchange.Forexample,asinverterdesignschange,therequirementthatallsmallsolarPVinstallationscomplywithAS4777shutsnewerdesignsoutofthemarketuntilthatstandardisupdatedtorecognisethechangestodesigns.

• Weareawareofbusinesseswithmoreadvancedmodelinverterswhohavebeenadvisedthatthebestandmostproductiveroutetomarketisthroughinternationalcertification,followedbyAustralianmarketentry,ratherthanenteringtheAustralianmarketdirectly.

• Internationalequipmentmanufacturers’decisionstoparticipateintheAustralianmarketareinformedbythescaleoftheavailablemarketandthecostofcompliancetospecificAustralianrequirements.StakeholdersrepresentingAustraliantechnologydevelopershavestatedthatthestatusquorestrictsmarketentry.

• ThecostofcertificationinAustraliaishigh(particularlywhenconsideringthesizeofthemarket),andstakeholdersmentionedinstancesofsomedistributorsacceptingAustralianStandardsastheonlyacceptablecertificationregardlessofcertificationinothermarkets.

• Newbusinessmodelsfacedifficultiesingettingestablished,especiallyforstatewideornationalbusinessofferingscrossingmultipledistributionbusinesses.

5.6RiskofunfairmarketadvantageStakeholdershavealsoexpressedconcernsthatasaresultoftherequirementsadoptedbyindividualdistributors,innovationinproductsandservicesmaybelimitedtothedistributionbusinessesthemselves-providinganunfairmarketadvantage.We’vealsobeentoldofdistributorsrequiringextensiveandcompetitivelysensitiveinformationaboutthesoftwarebeinginstalledwithsolarPV/batterybundles,aswellasdistributorrequirementsthatseektorestrictsmallresidentialcustomersfromexportingfromtheequipmentinstalled.Similarly,we’veheardconcernsfrombusinessesthattheremaybetheselectiveapplicationofdistributorrequirements–oneruleforthedistributor’sownbusinesses,andoneforconnectionapplicationsbyunrelatedbusinesses.

Akeyquestionrelatestowhetherthestatusquoisconsistentwithcompetitioninnetworkservicesprovidedbehindthemeter.Intheabsenceofanyoversightofdistributors’individualrequirements,itisnotclearwhetheritis.Currentstatelegislationprovidesnooversightmechanismfordistributors’requirements,orthebalanceofsafety,performanceandcompetitiveaccessachievedintheapplicationofthoserequirements.AsidefromfuturerulechangesextendingthecoverageoftheNERtonetworks’requirements,theonlymechanismcurrentlyavailableundertheNERisadisputebetweenaconnectionproponentandthenetworkonaspecificapplication.

Clarityontherelationshipbetweendistributors’requirementsandthecompetitivelandscapeisunlikelytoresultfromconnectiondisputes,becausecustomers’abilitytodisputetherequirementsislimited;thedisputeresolutionprocessesundertheNERareavailableonlyonacase-by-casebasisandinrelationtospecificconnectionapplications;anddisputeresolutionprocessesareonlyavailableonceaconnectionapplicationhasbeenmade.Projectsthatdon’tproceedtotheapplicationstagebecausetheproponent’sassessmentofthenetwork’srequirementsisunfavourabletotheprojectproceeding,havenorecoursetoadjudicationofanysort.

15.Someoftheseeffortsappearpoorlydesigned:customerundertakingsnottoexportaredifficulttoenforceifthecustomeratthepremisechanges,whilerequirementsonretailerstoenterintoundertakingsacustomerdoesnotexportareunlikelytosurviveacustomer’schangeofretailer.But,morerelevantly,limitationsofthissortappeartobeinconsistentwiththetreatmentofsmallcustomersundertheNER,andraisematerialquestionsaboutcompetitiveneutrality.Inprohibitingacustomerexportingthroughtheirretailerorathirdparty,isthenetworkeffectivelypositioningitselfastheonlypossibleproviderofthisvaluestreamtothecustomer?

Page 19: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

15

6.CharacteristicsofpreferredsolutionsInordertominimisecostsandmaximiseuptakeoflowcarbongridconnectedtechnologies,webelievethatnewinstitutionalsolutionsarerequiredtoreplacethecurrentnetwork-by-networkprocess.Thesesolutionsshouldideallyminimisedelayandreduceupfrontandtransactioncostsofinstallationasfarasispractical,whilemaintainingsafetyandsecurityofthenetwork.Thiswouldbeasubstantialpublicbenefit–installingembeddedgenerationandstoragecanhelpAustraliatransformourenergysystemandreduceemissions.Harmonisedrequirementswillmakethiseasier,cheaperandmoreequitable.

Wehaveidentifiedsomecharacteristicsofanapproachwhichcandeliverontheseobjectivesmoresothanthestatusquo,andwe’vehadanearlylookatalternativeinstitutionalmodelsasaguidetowhatthismightbe.Inthenextstageofthisproject,ourobjectiveistodevelopalternativeinstitutionalmodelsinlinewithourpreferredcharacteristics,todevelopapreferredalternativetothestatusquowithstakeholders.

Consideringstandardsasprovidingaminimumacceptablesolutionoraperformancebasedspecification,ratherthandefiningtheonlyacceptablesolution,couldbeasolutionintimesofrapidtechnologicalchange.

6.1Consistentnationalstandard:rareexceptionsAconsistent,clearandtransparentnationalconnectionstandardwouldreducethecostandmarketimpactsofthecurrentarrangements,providebenefitstocustomersandtheeconomy,andunblockuptakeofnewtechnologies.State-basedsolutions,liketheproposalbyErgonEnergy,EnergexandtheQueenslandgovernment(2016)potentiallyoffereasierstepsforward,butthisproposalandothergovernmentproposalsofwhichweareaware,donotfullyaddresstheissue-especiallyforbusinesseswithanationalfootprint,andinrelationtocompetitionintheequipmentmarket.

Nationalstandardsmustexplicitlybalanceriskstosafetyandnetworkperformance,costsandwiderpolicyobjectives:Thereisacosttobothinappropriatelyhighandinappropriatelylowstandards,andtheprocessusedtodevelopnetworkstandardsneedstorecognisethesecosts16.Theperformanceoftheelectricitysystemasawholeneedstobeconsidered,inadditiontolocaldistributorrequirements,accordingtoAEMO’srecentworkoninvertersettings(2016a)anditsFuturePowerSystemSecurityProgram(2016c).AEMO’sinitialworksuggestedthatundercertainspecificcircumstancescurrentlocaldistributorrequirementsmaybeinconsistentwithsystem-widerequirements:forexample,distributors’requirementsforinverterstorespondtounder-frequencyeventsbydisconnectingcouldcontributetotheworseningofsystem-wideperformance.

Thedistributormayhavespecificrequirementsinparticularareascharacterisedbypoorlyperforming,vulnerableoroldinfrastructure:inourview,thesecharacteristicsshouldbeaddressedatalocallevel,notthroughadistributor-widestandard.

It’salsoimportantthatnetworkstandardsreflectconditionsinthenetworkswheretherearealargenumberofconnectionsandwherethemajoreconomicactivityis,thatis,inhighlymeshedurbannetworks,highperformingbyinternationalstandards.Settingnetworkstandardsbasedontheperformanceoftheleastwellperformingareasofthenetworkwouldresultinnetworkrequirements‘levellingup’tomeetthemostonerouscurrentrequirements.Ourviewisthattheoppositeshouldbethecase:nationalnetworkstandardsshouldbesetattheminimumconsistentwiththesafetyandperformanceofnetworks,andareaswhereexceptionstothosestandardsareappropriateshouldeitherbeexplicitlyexcised(foraperiod)fromthecoverageofthestandards,ordealtwithonanexceptionsbasis.Thisistheappropriateuseofthetestastowhetheranapplicationissafeattheproposedlocation,thethirdofthetestsinourdiagraminSection4.16.InthecourseofthedebatesurroundingthechangestoconnectionprocessesinChapter5oftheNER,astakeholderrepresentativeclaimeditwasamatterofsomepridethattheautomaticconnectionthresholdintheNERScheduleswasasonerousasitis.Toaneconomist,ofcourse,astandardsetsohighitcanneverprofitablybeimplementedisineffectiveandexpensiveregulation,notadesirableoutcome.

Page 20: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

16

6.2Minimumperformancestandards,setindependentlyConsistenttechnicalstandardsforequipmentwouldbebestsupported,asinotherindustries,bycommonstandardssupportedbyindependentandcosteffectivetestingandcertificationacceptedacrossAustralia.StandardsAustraliaacknowledgesthatinrelationtotherepresentationonitsCommitteesdevelopingstandardsfortheelectricityindustry,therepresentationoforganisationsdirectlyrepresentingcustomers’interestshasdwindledovertime,leavingtheCommittees’membershipdominatedbydistributorrepresentatives.

Wehaveidentifiedmodelsforsettingharmonisedrequirementssupportedbyappropriatetestingandcertification.ThesecovertheregulatedsolutionrepresentedbytheAustralianCommunicationsandMediaAuthority(ACMA);thecoordinatedapproachadoptedbyAustraliangasnetworkswhichrelyonStandardsAustralia’sstandardsasthebasisforindustrystandards18;andtheaviationsectorapproachwhichreliesoninternationalstandardsandmodifiesthemonlywherestrictlynecessaryforAustralianconditions.

Telecommunicationsandtransportareregulatedbythefederalgovernment,butthegasindustry’sapproachsuggeststhatstateregulatedindustriescanarriveatanationalapproach,ifindustry(andthelocalregulators)havethewilltodoso.

17.Earlyintheprocessofopeningtelecommunicationstocompetition,theincumbentoperatorinsistedonrestrictingconnectedequipmenttoequipmentitmanufactured.18.Inothermarkets,competitionextendstothedevelopmentofstandardsthemselves,withcompetentorganisationscompetingfortherighttodevelopstandardsonbehalfofindustryorganisationsandregulators.

TechnicalstandardsinthetelecommunicationsindustryTherearealternativemodelsavailablethatbetteraddressquestionsofcompetitiveadvantage.Forexample,atthebeginningofthetelecommunicationindustry’stransformation,theincumbentAustraliannetworkoperatorwasthearbiterofallequipmentthatcouldbeconnectedtoitsnetwork17.Inthetelecommunicationssector,theincumbentwasnational,whichmeantthateconomiccostsimposedbyitsrestrictionswerelowerrelativetothosecurrentlyresultingfromthedifferingrequirementsamongelectricitydistributionnetworks.Thecompanieslockedoutofthemarket–equipmentmanufacturersinparticular–werelarge,internationalbusinessesandthecustomerswererepresentedinitiallybylargeinternationalbusinesses,likeOptusandVodafone.Thequestion–whenwastheincumbentappropriatelysafeguardingitsnetwork’sperformanceandsafety,andwhenwerethereanti-competitiveimplicationsfromtheincumbent’sdecisions–wasresolvedbymovingthedevelopmentoftechnicalstandardstoanindependentregulatoryauthority.

TheAustralianCommunicationsandMediaAuthority(ACMA)haslegislativeresponsibilityfor,amongotherthings,licensingandregulatingtelecommunicationscarriers,certainstandardsfortelecommunicationsequipmentandcabling,andelementsofnetworkperformance(interference,forexample).ACMA’srequiredapproachtothetechnicalstandardsisthatthestandardsarethelowestlevelconsistentwiththesafeperformanceofthenetwork,anditsenforcementprogramadoptsarisk-basedapproachtoitspriorities.

ACMAhasanaccreditedradiocommunicationscompliancelaboratorythatcarriesoutcompliancetestingofradiocommunicationsdevices.Itsmainpurposeistosupportindustrycompliancewithregulatoryarrangementssuchastheradiocommunicationsstandardscomplianceandlabellingarrangements.ThelaboratoryisaccreditedbytheNationalAssociationofTestingAuthorities(NATA)forassessingcompliancewithcompliancelevelstwoandthreeforthefullrangeofACMAstandardsandequivalentinternationalstandards.

Page 21: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

17

Insomecases,theregulatoryauthorityhasitsowntestingfacilities,althoughtestingisnotrestrictedtothosefacilities.Inothercases,theindustrybodyownsatestingfacility,operatedasafor-profitbusinessincompetitionwithothertestfacilities.

6.3ResponsivenesstotechnologicalchangeThedevelopment,adoptionandrevisionofstandardsintheelectricitysectorwouldbenefitfrombeingrevisedtoallowformorerapidturnaroundtimes.Alternatively,theprocesscouldfocusonestablishingminimumrequirementsorperformance-basedrequirements,ratherthanmandatoryrequirements.Thiswouldallowcustomerstobenefitfrominnovativetechnologicaldevelopments.

DiscussionsaboutworkonaninstallationstandardforsmallscalebatteryinstallationsataStandardsAustraliaworkshopinAugust2016highlightedthechallengesofthecurrentstandardsprocess,thepaceoftechnologicaldevelopmentandthepotentialcoststoconsumers(andmanufacturers).OneoftheCommitteemembersdiscussedtheclaimsbysomebatterymodelstohavetechnicalsafeguardsagainstcommonriskstoahouseholdfromabatterymalfunctionorotherincidents.Intheabsenceofaperformancestandard,however,themodelsmakingtheseclaimscouldnotbetested;and,asaresult,theinstallationrequirementsforsmallbatteriescouldnotdifferentiatebetweenequipmentwithorwithouttheclaimedsafeguards.Asaresult,installationrequirementsarelikelytobebasedontheleastsafemodels.Thiswouldmeanthedistributormayrequireadditionalmeasuresforallinstallations;forthoseofferingsuperiorperformance,thoserequirementsarelikelytobeoverlyonerous.

Some,butnotall,batteriesofferadditionalsafetyfeaturesthatreducetheriskoffiretoacceptablelevels,forexample.Ifthestandardoradistributordoesnotdifferentiatebetweenthosewithandthosewithoutthesefeatures,allbatteriesmayberequiredtobeinstalledexternallyinametalfireproofcabinet.Thisrequirementcreatesextracostsforallbatteriesinstalled,andstopsbatterieswiththeadditionalfeaturesbenefittingfromthosefeatures.Stakeholders’experienceofamendingAustralianstandardsinresponsetotechnicaldevelopmentssuggeststhatamendmenttocaptureindustrydevelopmentswillbedifficultandtimeconsuming.

EquipmentstandardsintheAustraliangasindustryAustraliangasnetworksshareequipmentstandardsacrossAustralia.ThecurrentprocessforqualifyingequipmentforconnectiontoanAustraliangasnetworkisbasedonStandardsAustralia’sdevelopmentofrelevantstandards(althoughthereareconcernsaboutthespeedofStandardsAustralia’scurrentprocesses,andtherepresentativenessofStandardsAustralia’scommitteememberships).Equipmentsubjecttoaspecificstandardistestedandcertifiedbyoneofanumberofcompetingaccreditedfacilities.TheAustralianGasAssociationoperatesanaccreditedfacility.Accreditedfacilitiesareauditedregularly,typicallybythestate-basedtechnicalregulator,toensuretestproceduresareappropriate.CertifiedequipmentcanbeconnectedtoanygasnetworkinAustralia.

Gasnetworks’safetyandperformance,likeelectricitydistributionnetworks,isastateresponsibility.However,co-ordinationeffortsbythetechnicalregulatorshaveresultedintechnicalregulationconvergingtoanationalmodel,eventhoughstatelegislationdiffersinthepowersandprocessesappliedfromstatetostatebythedesignatedtechnicalregulator.

Insomestates,additionalcertificationprocesseshavebeenintroducedwheretheequipmentforwhichcertificationisbeingsoughtisnotexpectedtobeinstalledinsignificantvolumes.Thisadditionalcertificationcategoryisapossiblemodelfornewtechnologiesintheearlystagesofdevelopment,orwherethereareonlyasmallnumberofcertifiedproductsavailableintheAustralianmarket.

Page 22: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

18

Thereisalsoaneedtoconsiderthecurrentprocessesforsettingindividualnetworks’requirements,whichrelyonindividualdistributorsandtheircapacitytoassesstechnologiesandtheimplicationsfortheirnetworks.Thenextstageoftheprojectwillconsiderfurtherwhetherthestatusquoisappropriateandcostefficientduringaperiodofrapidtechnologicalchange.Thiswillincludewhetherindividualdistributorshavethecapacitytokeepupwiththedevelopmentsinthemarketplace,andifitiscosteffectiveforindividualdistributorstoduplicatesuchactivity.

6.4CompetitiveneutralityDistributorsareincreasinglyseekingtodeliverbehind-the-meterservicestomanagedemandandinvestmentintheirnetworkaswellasforcommercialbenefit.Therisktocompetitiveneutralityfromdistributors’controloftheirownconnectionrequirementsandtheabsenceofanyeffectiveoversightofthoserequirements,ortheirapplication,hasthepotentialtobecomeasignificantissue.

Currently,adistributordecideswhetheraparticularinstallationortypeofinstallationissafe,subjecttothelocaljurisdictionalframework.Thedistributoralsodeterminestheconditionsunderwhichtheproposedconnectioncanbemade,andconsequentlythedirectcostoftheconnection.Thisallocationofresponsibilitymaycreateconflictsforcompetitiveneutralitybetweenthedistributor’sregulatedbusiness,itsunregulatedbusinessanditspotentialcompetitors.Giventhereislittleoversightofdistributors’technicalrequirementsortheirdecisionmaking,thecurrentprocessoffersfewavenuestoeffectivelycontestdistributordecisions.Thiswilltendtodecreasetheprovider’sconfidencethattherewillbecompetitiveneutralityforpotentialproductsandservicesbehindthemeter.

TheEnergeiareport(CEC2016)includesacommentfromonerespondenttotheirstakeholdersurveythattheRing-FencingGuidelinewillensurecompetitiveneutralityindistributors’requirements.However,theGuidelinedoesnotdiscussthepotentialconflictofinterestfromthedistributorsactingasgatekeeperstotheirnetworksforserviceswiththepotentialtocompetewiththeirownservices.

Page 23: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

19

7.Whatnext?

GatheringfurtherevidenceofimpactWewillworkwithacoalitionofstakeholderstobuildfurtherevidenceabouttheimpactofidentifiedbarriers.Thiswillparticularlyfocusonthecostanduptakeimpacts,ofthestatusquoonconnectionrequirements.Wewilldevelopworkablesolutionsthatcanberapidlyimplementedtounblockbarriers.

ArticulatingthesolutionWewilldevelopinstitutionalandpolicysolutionstotheissuesidentifiedthroughacollaborativeprocesswithstakeholdersacrossarangeofsectors.

Weaimtoundertakefurtherconsultationwhichwillallowtheproposedsolutionstobetestedwithkeystakeholdersandrefined.

Wewillfinaliseareportincludingasolutionsroadmapinmid-2017.Itwillidentifythekeyactorsandtheirrolesinenactingthesolution,aswellasdocumentinternationalexamplesofsolutionstotheidentifiedbarriers.

BuildingsupportforactionWewillengagewithstakeholderstopresenttheproposedsolutionsandgarnersupportforaction.Thiswillalsoincludebroaderengagementwithkeypolicymakers,regulatorsandindustryplayers,plusafocusedmediacampaign.Wewillidentifystakeholderswhowishtoformacoalitionactiveroleinimplementingthesolutions.Wewillrunaseriesofforumssothatcoalitionmemberscanengagedirectlywithkeydecisionmakersandclearlyvoicetheirsupportforreform.

ImplementationandmonitoringofreformWehavelearntfromourpreviouseffortsindrivingchangeintheenergymarketthatittakestimeandefforttoseethingsthrough.Oncesupportisbuilt,wewillcontinuetoengagewithdecisionmakerstoobserveimplementationofthedesiredoutcomesandmonitoractiononthegroundtoensurethatchangeisembeddedintopractice.

ProjectfundingClimateWorksandSeedAdvisorycurrentlyseekfundingforthisproject,fromavarietyofsourcesandarekeentodiscussthiswithinterestedparties.

Page 24: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

20

8.ReferencesAustralianEnergyMarketOperator(AEMO)2016a,ResponseofExistingPVInverterstoFrequencyDisturbances,April2016https://www.aemo.com.au/-/media/Files/PDF/Response-of-Existing-PV-Inverters-to-Frequency-Disturbances-V20.pdfAEMO2016b,NationalElectricityForecastingReport,NationalEnergyMarket.https://www.aemo.com.au/-/media/Files/Electricity/NEM/Planning_and_Forecasting/NEFR/2016/2016-National-Electricity-Forecasting-Report-NEFR.pdfAEMO2016c,FuturePowerSystemSecurityRoadshowpresentations,2016https://aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Reports/2016-FPSS-Roadshow-presentation-1.pdfAustralianSustainableBuiltEnvironmentCouncilandClimateWorksAustralia,2016,LowCarbon,HighPerformance,Sydney.http://www.asbec.asn.au/wordpress/wp-content/uploads/2016/05/160509-ASBEC-Low-Carbon-High-Performance-Full-Report.pdfCleanEnergyCouncil(CEC),2014,2013-14GridConnectionExperiencesSurveyResults,Melbourne.Task4C.1byCEC,2014http://fpdi.cleanenergycouncil.org.au/dam/cec/policy-and-advocacy/ARENA/FPDI/Grid-Connection-Experiences-Survey-Results-Report.pdfCEC,2016,EmbeddedGenerationGridConnectedStandardsScopingStudy,Melbourne.Task3B.1byEnergeia,May2016http://fpdi.cleanenergycouncil.org.au/dam/fpdi/reports/embedded-generation-study-report.pdfCleanEnergyRegulator,2017,Postcodedataforsmall-scaleinstallations.Viewed17January2017http://www.cleanenergyregulator.gov.au/RET/Forms-and-resources/Postcode-data-for-small-scale-installations#Summary-of-postcode-data

ClimateChangeAuthority,2014ReducingAustralia’sGreenhouseGasemissions–TargetsandProgressReviewFinalReport,Melbourne

ClimateWorksAustralia,PropertyCouncilofAustraliaandSeedAdvisory,May2015,ImplementingtheConnectingGenerationRule:ProjectOutcomesReport,Melbourne.http://climateworks.com.au/sites/default/files/documents/publications/implementing_the_connectin_embedded_generation_rule_report_20150507.pdfCOAGEnergyCouncil2015,NationalEnergyProductivityPlan2015-2030:BoostingCompetitiveness,ManagingCostsandReducingEmissions,Canberra.https://scer.govspace.gov.au/files/2015/12/National-Energy-Productivity-Plan-release-version-FINAL.pdfEnergyNetworksAssociation(ENA)andCommonwealthScientificandIndustrialResearchOrganisation,2015,ElectricityNetworkTransportRoadmap:InterimProgramReport,Sydney.ViewedOctober2016.http://www.energynetworks.com.au/electricity-network-transformation-roadmapErgonEnergy,EnergyQueenslandandEnergex(2016)Above30kWto5MWEmbeddedGeneratingSystemConnectionStandardforQueensland–ConsultationPaperhttps://www.ergon.com.au/__data/assets/pdf_file/0005/383144/Above-30kW-and-up-to-5MW-EG-Connection-Standard-Consultation-Paper.pdfMorganStanleyResearch,2016,AustraliaUtilitiesAsiaInsight:Solar&Batteries.

Page 25: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

21

Appendix1:Summaryofenergymarketreformprocesses

Who Process Timeline

AER

Ring-fencingGuidelines

FinalguidelinespublishedendNovember2016:

http://www.aer.gov.au/system/files/AER%20Ring-fencing%20Guideline%20-

%2030%20November%202016.pdf.

COAG

EnergyStorageRegistrationConsultation

Consultationpaperreleasedin2016:

http://coagenergycouncil.gov.au/sites/prod.energycouncil/files/publications/documents/EMTPT%20-

%202016%20Forward%20Work%20Program_2.pdf

COAG

StandAlone

EnergySystemsintheElectricity

MarketConsultation

Consultationpaperreleasedin2016:

http://coagenergycouncil.gov.au/sites/prod.energycouncil/files/publications/documents/EMTPT%20-

%202016%20Forward%20Work%20Program_2.pdf

COAG

FinkelReview

ReporttoCOAGDecember2016withfinalreport

early2017:http://coagenergycouncil.gov.au/independent-

review-reliability-and-stability-national-electricity-market.

StandardsAustralia

Energystorageinstallationstandards

DiscussionpaperreleasedforcommentJuly2016:

http://www.standards.org.au/OurOrganisation/News/Documents/Second%20Standards%20Australia%20Energy%20Storage%20Standards%20Discussion%20Pa

per%202016.pdf

StandardsAustralia

DistributedGenerationRoadmap

DiscussionpaperreleasedforcommentJuly2016:

http://www.standards.org.au/OurOrganisation/News/Documents/Standards%20Australia%20and%20the%20Future%20of%20Distributed%20Electricity%20Di

scussion%20Paper%2011%20July.pdf

Inadditiontothislist,theCompetitioninMeteringreformsareexpectedtocommencein2017andtheAEMCisconsideringawiderangeofRuleChangeproposals.

Page 26: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

22

Appendix2:Stakeholderengagement

SeedAdvisoryandClimateWorksconsultedthefollowingorganisationsduringthisproject:

ABB

AGL

AECOM

AECmembersandassociatemembers

AMPCapital

ANZ

Brookfield

CharterHall

CleanEnergyCouncil

Dexus

FrasersProperty

Goodman

TheGPTGroup

ISPT

Investa

JetCharge

Lendlease

Mirvac

OakleyGreenwood

PropertyCouncilofAustralia

Pro-utility

RedEnergy

ScentreGroup

SimplyEnergy

Stockland

Tesla

VicinityCentres

Duringtheconsultations,SeedAdvisoryandClimateWorksraisedthefollowingissuesrelatingtothelackofharmonisedrequirementsthathadbeenbroughtupinpreviousconsultations:

• Increasedcoststobusinessesandconsumers

• Downscalingofambition

• Abandonmentofprojects

• Difficultiesaccessingprojectfinance

• Reducedmarketavailabilityofproducts

• Difficultiesinrollingoutnewbusinessmodelsandtechnologies

• Limitinginnovationandpoorresponsivenesstonewtechnology

Organisationscouldeitherraisetheirownissuesorwerepromptedwiththefollowingquestions:

• Hasyourbusinessexperiencedanyoftheseimpacts?

• Whatisthecostimpactofcurrentstandardsandprocessesonyourbusiness?

• Whataretheimpactsintermsofupdateofdistributedgenerationandnewtechnologies?

• Arethereadditionalimpactswehavenotdiscussed?

Page 27: Plug & Play · The Plug and Play project instead focuses on the costs that current differing requirements impose on connection proponents and the wider economy, and on alternative

For further information about this project, contact ClimateWorks Australia:

ClimateWorks Australia 16/41 Exhibition St Melbourne Victoria 3000 PHONE +61 3 9902 0741 EMAIL: [email protected]

Published by ClimateWorks Australia Melbourne, Victoria, February 2017 © ClimateWorks Australia 2017

This work is subject to copyright. Apart from any use permitted under the Copyright Act 1968, no part may be reproduced by any process without written permission from the publisher.

This report may be downloaded at www.climateworksaustralia.org

Contact us

ClimateWorks Australia is a leading, independent research and advisory organisation helping Australia transition to net zero emissions by 2050. Founded through a partnership between Monash University and the Myer Foundation and hosted by the Monash Sustainable Development Institute.