plans and schedule for qxf giorgio ambrosio and paolo ferracin joint larp/cm20 hilumi meeting napa...

15
Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404 Work supported by the US LHC Accelerator Research Program (LARP) through US Department of Energy contracts DE-AC02-07CH11359, DE-AC02-98CH10886, DE-AC02-05CH11231, and DE-AC02-76SF00515

Upload: eileen-whitehead

Post on 17-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

Plans and schedule for QXF

Giorgio Ambrosio and Paolo Ferracin

Joint LARP/CM20 HiLumi meetingNapa Valley, CA, USA

8-10 April, 2013

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404Work supported by the US LHC Accelerator Research Program (LARP) through US Department of Energy contracts DE-AC02-07CH11359, DE-AC02-98CH10886, DE-AC02-05CH11231, and DE-AC02-76SF00515

Page 2: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

AGENDA

09/04/2013G. Ambrosio and P. Ferracin 2

Start Duration Title Presenter8:30 1:00 QXF plans and schedule P. Ferracin, G. Ambrosio

9:30 30 CERN QXF conductor procurement and cable R&D A. Ballarino (by phone)10:00 30 Coffee10:30 30 LARP conductor procurement A. Ghosh11:00 30 LARP QXF cable R&D D. Dietderich11:30 30 Winding tests D. Dietderich, S. Izquierdo Bermudez12:00 30 Cable Insulation development D. Dietderich, P. Ferracin12:30 1:00 Lunch

13:30 30 Requirements (electrical, cooling, dose, geometry) P. Ferracin, G. Ambrosio14:00 30 Protection systems for Nb3Sn magnets and threshold R. Denz14:30 30 2D magnetic analysis and coil cross-section F. Borgnolutti15:00 30 3D magnetic analysis and coil end design S. Izquierdo Bermudez15:30 30 Coffee

16:00 30 Coil fabrication D. Cheng16:30 30 Coil tooling M. Yu, J. Schmalzle, P. Ferracin17:00 30 QXF support structure and mechanical analysis M. Juchno, H. Felice17:30 30 QXF integration P. Ferracin18:00 30 QXF quench protection G. Ambrosio

Page 3: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF statusCable R&D

• Target criteria established– Mechanical stability during winding– Stability current Is ≥ 3*Iop

– RRR after cabling > 150– No shear planes in micrograph images

• First iteration completed in 03/2013– Winding tests, cross-section images, extracted strand meas.

• No cable reached all targets• Second iteration has started

– Cabling, winding tests, micrograph images in 04/2013– Extracted strand measurements in 05/2013– Cable parameters for first set of coils by end of 05/2013

• Cable R&D will continue (PIT strand, improved parameters…)

09/04/2013G. Ambrosio and P. Ferracin 3

Page 4: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF statusInsulation R&D

• First ten-stack measurements in 03/12– Either too thin (LARP) or too thick (CERN)

• Thickness optimization in progress• Target 125-150 micron

09/04/2013G. Ambrosio and P. Ferracin 4

Page 5: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF statusCoil design and magnetic design

• First iteration completed• 2D magnetic analysis

– Coil cross-section and yoke design– Magnetic shimming

• 3D magnetic analysis (OPERA and Roxie)– Peak field– 3D Field quality

• 3D CAD model– Coil (turns and blocks)– End spacers (Roxie and BEND)

09/04/2013G. Ambrosio and P. Ferracin 5

0 5 10 15 20 25 300

5

10

15

20

z [mm]

x [m

m]

1

25

6

34

7 8

Page 6: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF statusCoil fabrication tooling

• First iteration of pole and end-shoes design completed

• Design of W&C and R&I started in 03/2013

09/04/2013G. Ambrosio and P. Ferracin 6

Page 7: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF statusSupport structure

• 2D optimization completed– Update of the structure (alignment assembly features)– Alignment key– Dimensions of the components– LHe vessel mechanical analysis– Effect of coil deformation on field quality

• 3D analysis started• 3D CAD modelling in progress• Integration, LHe vessel containment, length

– Two options (CERN, BNL) under study

09/04/2013G. Ambrosio and P. Ferracin 7

Page 8: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF plan and schedule• Update of coil design in 06/2013• Coil parts fabrication/optimization from 06/2013

– To be completed by end of 2013• Coil tooling

– Design completed in 05/2013– Procurement

• Parallel coil fabrication LARP-CERN– CERN: 1 Wind&Curing + 1 React&impreg– LARP: 1 Wind&Curing + 2 React&impreg

– Winding and curing by 10-11/2013• End parts optimization and test of fabrication process

– Reaction and impregnation by 02/2014• Fabrication of full practice coil starts, both at CERN and in the

US, in 03/2014– First long coil wound in 01/15

09/04/2013G. Ambrosio and P. Ferracin 8

Page 9: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF plan and scheduleCoil fabrication

• CERN– Number of coils

• 1 Cu coil• 1 practice + 5 real RRP coils• 1 practice + 5 real PIT coils

– After SQXF01

– Fabrication steps• Winding + curing + reaction +

impregnation– Fabrication time

• ~100 days (5 months) per coil• 1 coil produced every 2 months

• LARP– Number of coils

• 1 practice• 1 mirror + 4 real RRP coils

– Fabrication steps• FNAL: winding + curing• LBNL: reaction + impregnation• BNL: reaction + impregnation

– Fabrication time• ~100 days (5 months) per coil• 1 coil produced every month

09/04/2013G. Ambrosio and P. Ferracin 9

• Sequence: CERN will start with RRP coils– SQXF1 magnet will include the first available four RRP coils produced by the two

“production lines” – With the current plan, either 3 LARP + 1 CERN or 2 LARP + 2 CERN

Page 10: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF plan and schedule

• Support structure – LARP/CERN design

• Identical design for SQXF and LQXF– 2 SQXF structures fabricated and qualified at CERN

• 1 long structure fabricated and assembled by LARP– From conceptual design to assembly and qualification

• From beginning of 2013 to end of 2014• Tests

– First coil test (mirror) in 12/14• Feedback for LQXF coil fabrication (first winding in 01/15)

– First magnet test (SQXF1) in 04/15• First assembly of LQXF in 10/15

– Feed-backs from SQXF to LQXF on loading

– Then SQXF1b (RRP), SQXF2 (PIT), SQXF2b (PIT)

09/04/2013G. Ambrosio and P. Ferracin 10

Page 11: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

SQXF plan and schedule

09/04/2013G. Ambrosio and P. Ferracin 11

Page 12: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

LQXF Goals

• GOALS:– LQXF1/2: Demonstrate main features of MQXF cold

masses• Aperture, length, main requirements

– LQXF3: MQXF prototype

• DESIGN CRITERIA:– Coils, tooling design, and structure developed with SQXF:

• Same coil parts, same tooling design, same process, …– Prototype features to be defined by Design Report (2015)

09/04/2013G. Ambrosio and P. Ferracin 12

Page 13: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

PLANS

• LARP effort for demonstrating readiness for construction project (US DOE criteria)

• Fabrication plan is based on LQ and LHQ plans – Strand procurement: BNL and LBNL– Cabling: LBNL– Cable insulation: NEWT (different from LQ)– Coil W&C: FNAL– Coil R&I: BNL and FNAL– Structure & assembly: LBNL– Test: FNAL and/or BNL

09/04/2013G. Ambrosio and P. Ferracin 13

Page 14: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

Schedule

09/04/2013G. Ambrosio and P. Ferracin 14

2013 | 2014 | 2015 | 2016 | 2017

Page 15: Plans and schedule for QXF Giorgio Ambrosio and Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013 The HiLumi LHC Design

Schedule Milestones

• SQXF practice winding: 10/13• SQXF coil fabrication start: 03/14 • SQXF mirror test: 12/14• SQXF1 test: 04/15• SQXF1b test: 11/15

• LQXF coil fabrication start: 01/15• LQXF1 test: 01/16• LQXF1b test: 07/16• LQXF2 test: 01/17• LQXF2b/3 test: 07/17