planning to avoid a catastrophe
TRANSCRIPT
Tullow Oil: Planning to avoid a catastrophe
Tullow Oil
Planning to avoid a catastropheSeptember 2019
Tullow Oil: Planning to avoid a catastrophe
WELL ENGINEERING AS PART OF CONTROLS AND BARRIERS
Slide 2
• The critical role Drilling Engineering has in the “prevention side” of the “Loss of Containment” bow-tie.
• The key inputs and outputs for safe and effective well design• OGP 463 – Key recommendations for incident reduction
Tullow Oil: Planning to avoid a catastrophe
OGP Deepwater Wells: Global Industry Response Group Report 463 May 2011
In July 2010, the International Association of Oil and Gas Producers (OGP) formed a group in the aftermath of the tragic accidents on the Macondo prospect, Montara and other similar accidents.
Previously the industry had drilled 14,000 deep water wells without a major incident but, these accidents were a stark reminder of the risk inherent in such operations.
The OGP report 463 identified three areas to focus improvements:-
• Prevention: developing better capabilities and practice in well engineering design and well operations management in order to reduce the likelihood of future incidents;
• Intervention: improving well capping response readiness (in the event of an incident) and to study further the need for, and feasibility of, global containment solutions;
• Response: delivering effective and fit-for-purpose oil spill response preparedness and capability.
LEARNING FROM INCIDENTS
Slide 3
Tullow Oil: Planning to avoid a catastrophe
• A 3 Tier Review Process : - Regular Self Audit - Independent Oversight- Regulator
• Human Competency Management: - Formal Competency Management System- Deeper understanding and awareness of Well control
• Recognition of existing National and International Standards.
• Improved Technical and Operational Practice for the overall governance of Well Construction
- Well Management System with Management of Change process, full well life –cycle- Operator “Technical Authority”- Well Control Bridging documents established between Operator and Drilling Contractor
• Two Barrier Policy- BOP as 1 barrier. Configuration / Certification. Redundancy. Function and pressure testing
• Creation of a permanent Wells Expert Committee (WEC)
KEY OGP 463 “PREVENTION” RECOMMENDATIONS
Slide 4
Tullow Oil: Planning to avoid a catastrophe
• Most Operating Companies now have a Management System that defines Policies, Standards and Guidelines for planning and execution of well work.
• Many Operating Companies define a Process that defines tasks that must be executed when planning a well.
• Most operating Companies now have a Competency Management System
• Tasks must be performed by competent professional engineers with adherence to Policies, Standards, and Guidelines.
• Human Factors Training and Scenario Based Well control training are being implemented to improve depth and breadth of well control training.
• Often peer reviews are used as means of ensuring process is followed and ideas and issues are not overlooked.
• Some Operators use “Well Examination” as part of the 3 Tier Review
• The objectives of the systematic approach is to assure best practice is applied.
• Most Operators now have a “Barrier Policy”
• BOP certification and functionality is addressed rigorously – including verification and pressure testing.
ROLE OF WELL ENGINEERING AS A BARRIER AND CONTROL
Slide 5
Tullow Oil: Planning to avoid a catastrophe
WELL DELIVERY PROCESS - ENGINEERING
Slide 6
Concept Design Planning Ops Close-Out
• Initial Peer Review (Conceptual Well Cost Estimate (+/- 25%)
• Conceptual Well Design
• Kick-Off Meetings • Offset Well Review • Lessons Learned
Review • Environmental
Permitting• Contracting Strategy &
Register• Rig Identification
• Detailed Well Design & Peer Review
• Contracting & Procurement
• Consents & Permitting Register
• Relief Well Planning• P&A Design• Final Equipment & Rig
Identification• Shore Base
Inspections• Supplier Quality
Management
• Operations Readiness Review / Approval Gate
• Well Examination• Final Well Cost
Estimate (+/- 10%)• Drill Well On Paper• Capping Stack
Selection & Notification
• Subsea Well Containment Logistics Plan
• Contingency Planning• Well Operations
Management Plan• Well-Specific
Operational Plan• Well Clean-up HAZOP
Study
• Daily Reporting & Communications
• Final Preparations• Drilling Operations• Well Integrity
Checklist• Contractor
Management• Weekly Cost Reporting• Advanced Planning
Meetings & After-Action Reviews
• Failure Investigation Reporting
• Non-Conformance Reporting
• Well Examination
• End-of-Well Report• Well Performance
Memorandum• Final Well Cost
Reconciliation• Definitive Well Survey• Lessons Learnt
Register• Well Integrity
Checklist• Well Suspension/
Abandonment Schematics
• Materials & Equipment Reconciliation
• Supplier Performance Management
Tullow Oil: Planning to avoid a catastrophe
Key Inputs
KEY INPUTS INTO WELL CONCEPT DESIGN
Slide 7
Well Engineering
Geological Well Proposal
Shallow hazards Analysis
Pore Pressure / fracture gradient
Modelling
Offset Well Data
Conceptual Well Design
Casing Design
Kick Tolerance
Casing Point selection
Key Outputs
Well Engineering Management
System
Pier Review
Tullow Oil: Planning to avoid a catastrophe
Key Inputs
KEY INPUTS INTO DETAILED WELL DESIGN
Slide 8
Well Engineering
Geological Well Plan
Soil Strength Data
Equipment Specifications
Conceptual Well Design
Key Outputs
Well Engineering Management
System
Basis of Design
Met-Ocean Data
Pier Review
Tullow Oil: Planning to avoid a catastrophe
Key Inputs
KEY INPUTS INTO OPERATIONAL PLANNING
Slide 9
Well Engineering
Rig Selection & Specification
Service Company Information
Equipment Specifications
Well Eng. Basis of Design
Key Outputs
Well Engineering Management
System
Well Specific Drilling
Programme
Riser and Conductor Fatigue
analysis
Pier Review
Local Regulations and Permit inputs
Tullow Oil: Planning to avoid a catastrophe
KEY CONTINGENCY PLANNING AND PREPARATIONS
Slide 10
Well Engineering
Blow out modelling
Oil Spill Modelling
Dynamic Well Kill Modelling
Blow out Response Planning
Conceptual Well Design
Geological / Reservoir
Engineering Input
Met-Ocean Data
Soil Strength Dta
Capping and Containment logistics plan
Emergency Response Plans
Specialist Resources
Rig Specific Data
Tullow Oil: Planning to avoid a catastrophe
BLOW OUT PREVENTER TESTING AND ACCEPTANCE
Slide 11
Rig Acceptance
3rd Party BOP Verification and
Acceptance
Ongoing Operational
testing
Drilling Rig Contracted
Pre-Contract Inspection
Any safety Critical deficiencies will be
identified and closed out in advance of
contract commencement
Rig Commences /Continues to
work
Deficiencies Identified and repaired
• Key reference : API S-53
Tullow Oil: Planning to avoid a catastrophe
• In 2011 OGP 463 identified a number of important industry wide improvements focused on design and operations management that would drive a reduction in the likelihood of future incidents.
• Most Operators now fully implement these recommendations.
• Significant effort is systematically devoted to rigorous well design to ensure that the risk of a loss of containment is very small.
• Significant effort is also systematically devoted to contingency planning to ensure that in the unlikely event of a loss of containment recovery measures can be swiftly implemented .
• Acceptance testing of BOP equipment is recognised as being safety critical. Independent 3rd party verification of BOP equipment considered good practice. Regular pressure testing and function testing mandatory for most operators.
SUMMARY AND CONCLUSIONS
Slide 12
Tullow Oil: Planning to avoid a catastrophe
Tullow Oil plc9 Chiswick Park
566 Chiswick High RoadLondon, W4 5XTUnited Kingdom
Tel: +44 (0)20 3249 9000Fax: +44 (0)20 3249 8801Email: [email protected]
Web: www.tullowoil.com
Follow Tullow on: