planning & monitoring. the purpose of planning and monitoring to ensure that the project is...

25
Planning & Monitoring

Upload: silvia-patrick

Post on 17-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Planning & Monitoring

Page 2: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

The Purpose of Planning and Monitoring

• To ensure that the project is produced on time, within the cost constraints and at the quality required.

Page 3: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Planning Objectives

• Analyse• Anticipate• Schedule resources• Co-ordination and control • Feedback.

Page 4: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Analyse

• This entails envisaging how the job will be done, in what order and with what resources

• The total job is then reduced to a number of manageable activities.

Page 5: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Anticipate

• This involves foreseeing any potential difficulties and making arrangements to overcome them.

Page 6: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Schedule resources

• This will enable the best use to be made of all resources, – these being money, men, materials, machines and

management.

Page 7: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Co-ordination and Control

• For any project to be successful it must be co-ordinated and controlled in order to ensure that the right resources are available when they are required.

Page 8: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Feedback

• Information and data on the project must be kept so that it can be used for future projects, thereby learning from the previous works.

Page 9: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Types of Planning and Monitoring

• Factors to be considered:

Page 10: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Design Information Planning

• looks at the stages of design: feasibility, sketch and detailed design.

• lays down the dates when information and drawings are required to be received by the Contractor from the design team.

Page 11: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Site Activity Planning (Construction Programme)

• This shows when the activities for individual operations are scheduled to start and finish on site.

• Can include the programmed timings and the actual timings.

Page 12: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Resource Planning

• Involves the allocation of the five m's of money, men, materials, machines and management to the activities on the programme.

• The resources available will either dictate the time scale for the project, or the time scale of the project will dictate the resources that are needed in order to complete by a certain date.

Page 13: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Financial Cost Planning

• This should show the anticipated costs throughout the duration of the project

• It will show how much money is required and when it will be called upon in order to finance the construction costs

• It must also show actual costs to be compared to those that are anticipated, thereby showing if the project is within the allocated budget, i.e. Cash flows and S-curves.

Page 14: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Planning Factors & SequenceInception Feasibility Proposal Programme

Purpose

Requirements

Option

Costs

Planning Permission

Resources Available

Design

LA Approval

Method Statement

Calculation Sheets

Work Programme

Page 15: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Procedure

• Determine what is required to be done• Break down the complete job into separate

operations• Determine the ways that each of those

operations can be carried out• Select the most appropriate method

(alternatively produce a method statement for each method).

Page 16: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

• Place them in the sequence that they are to occur

• Determine what, if any, plant is required for each operation

• Determine the operatives required to carry out each operation (Remember to include plant operator)

• Determine if any special requirements apply.

Page 17: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Method Statement

This is a detailed schedule that considers alternative proposals and makes recommendations. It considers time, costs and technique for each method of carrying out the work and the resources necessary to perform the major activities in the project.

Page 18: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Methods of Programming

• Bar or Gantt Chart • Critical Path (Networks). Known as Activity-

on-arrow • Precedence Diagrams. Known as Activity-on-

the-node.

Page 19: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Bar or Gantt Charts

This depicts each operation as a bar on a chart. The length of the bar shows the time that the operation is expected to take. It shows the starting time and the finishing time.

Page 20: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

ID Task Name Duration

1 Set-up Site 2 days

2 Site Strip 1 day

3 ExcavateFounds 4 days

4 Lay Founds 1 day

5 Brickwork to DPC 3 days

6 Excavate Drainage 1 day

T W T F S S M T W T F S S M T W T F S S M T W T F19 May '03 26 May '03 02 Jun '03 09 Jun '03

Page 21: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality
Page 22: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Critical Path - Activity-on-arrow

Page 23: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Precedence Diagrams Activity-on-the-node

Page 24: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Earliest Start Earliest Finish

Latest Start Latest Finish

Total Float Free Float

Activity

Duration Activity Number

Precedence Box

Page 25: Planning & Monitoring. The Purpose of Planning and Monitoring To ensure that the project is produced on time, within the cost constraints and at the quality

Exercise

Produce a method statement and bar chart for the construction of a single dwelling. State any assumptions made.