PLANNING FOR LOCAL INDUSTRIAL INVOLVEMENT FOR NEW NPP
DEVELOPMENT IN INDONESIA
Jupiter Sitorus Pane, Dharu Dewi, Yarianto National Nuclear Energy Agency of indonesia
Presented at
Technical Meeting on Industrial Involvement and Localization for New Nuclear Power Plant Construction.
Crowne Plaza Hotel, Qingdao, China, 26 to 29 August 2014
Outline • Introduction
• Localization/National Participation
• Criteria for Selecting National Participation
• Assessment of Quality and local content
• Supply chain of Civil Construction Industires
• Estimation of National Industrial Participation
• Conclusion
Introduction • Indonesia has experienced constructing three
research reactors and performing various Pre-Feasibility Studies for the preparation of first nuclear power plant.
• One of the benefit for constructing Nuclear Power Plant in developing countries like Indonesia include local industrial participation or involvement that could provide positive social impact to industry and public.
• This presentation provide information regarding Indonesian experiences in estimating local industrial participation and supply chains.
• Manufacturing using foreign engineering in the local area.
• Manufacturing through technology transferring in the local areas
• Manufacturing through technical collaboration in the local areas
Localization / National Participation
• Manufacturing through joint venture with co brand in the local areas
• Manufacturing using by imported parts or raw material in the local areas
• National labor participation to services and construction
Localization/ National Participation
Criteria for Selecting Local
Industrial Participation
• Are their profiles relevant to NPPs construction?
• Are there potential investment capability to participate in a NPP Project?
• Are there relevant experiences of the national industries in high technology project?
• Are there national industries experiences in the large conventional power plants?
Assessment of Quality and
local content Local Industries shall fulfill:
• SNI (Indonesia National Standard ) requirement: for safety.
• ISO with other certified special requirements such as SNI, ASME NQA-1, OHSAS 18000, ISO14000 and NBBI for civil works.
• Portland V for building material
Assessment of Quality and
Local Content • Architecture: ISO 9001:2002, OHSAS
18001:1999, ASME NQA-1 (quality control)
• Manufacturing industries: ISO 9001, ISO 14001 ASMe Stamp (U, U2,S,R,NB, PP) and BS 5500
Supply Chain of Civil
Construction Industries
NPP Construction
Civil Construction
Civil Construction Industries
Steel Structure Industries
Cement Industry Supporting
Material Industries Steel Industries
Civil Construction Industries • PT. Adhi Karya
• PT. Waskita Karya
• PT. Hutama Karya
• PT. Wijaya Karya
• PT. Nindya Karya
• PT. Pembangunan Perumahan
• PT. Krakatau Engineering
• PT. Bangun Total Persada
Civil Construction
Industries Supply Chain
NPP Construction
Civil Construction Industries
PT. Adhi Karya
Experiences : • Port of Inalum • Bride of
Suramadu • Tn. Abang
Market • Istiqlal Mousque • etc
PT. Waskita Karya PT. Hutama Karya PT. Pembangunan
Perumahan PT. Krakatau Engineering
PT. Total Bangun Persada
Experiences : Lahendong Geothermal PP Muara Karang CPP Port Research Reactor Serpong Port and dam
Experiences : • Segara Mini
Hydro • Cirompang Mini
Hidro • Kendari CPP • Ampana CPP • Port • Building
Experiences : • KDL CCPP 3x40 • GPP 90MW • Talang Duku
GPP 65 MW • Port and Dum • Building
Experiences • EPO GPP 2x40
Gunung Megang Sumatra Selatan
• WHRG Power Plant 2 x 14 MW PT. Meratus jaya
• Urea dan Amonia Plant
Experiences : • Building • Hotel & Office • Apartment • Etc.
Steel And Steel Structure
Industries • PT. Krakatau Steel
• PT. Gunung Garuda (PT. Gunung Steel Group)
• PT. Cilegon Fabricators
• PT. Ometraco Arya Samantha
• PT. Amarta Karya
• PT. Arkon Prima Indonesia
• PT. Gunawan Dian Jaya Steel
Civil Construction
Industries Supply Chain
NPP Construction
Steel and Steel Structure
PT. Krakatau Steel PT. Gunung Steel
Group PT. Cilegon Fabrication
PT. Ometraco Arya Samanta
Experiences : • Build PT
Krakatau Daya Listrik (Power Plant)
Experiences : • Supply the
project of PT. Krakatau Engineering
• Supply the project of PT. Krakatau Posco
Experiences : • Suralaya CPP • Bukit Asam CPP • Belawan CPP • PLTGU Cilegon,
Muara Karang dan Tg. Periok
Experiences • CCPP Tambal
Lorok project , Semarang.
• Paison-Besuki CPP
• Gresik CPP • Petero Kimia
Gresik • Kamojang , Jabar
Cement Industries • PT. Semen Padang
• PT. Semen Gresik
• PT. Semen Tonasa
• PT. Semen Baturaja
• PT. Semen Holchim Indonesia
• PT. Indocement Tunggal Perkasa TBk
• PT. Semen Andalas
• PT. Semen Bosowa
• PT. Semen Kupang
Civil Construction
Industries Supply Chain
NPP Construction
Cement
PT. Semen Padang PT. Semen Baturaja
Palembang
PT. Semen Holchim Indonesia
PT.. Semen Gresik
Experiences : • Waste heat
recovery power generation at Indarung
• CPP construction at teluk sirih
Experiences : • No information
to build electrical generation plant
Experiences : • Cilacap
CPP(2006) • Paiton CPP • Labuan CPP • Indramayu CPP • Muara Tawar
CPP
Experiences • Sudimoro CPP
Pacitan • Paiton CPP
Probolinggo • Sluke CPP
Rembang
Civil Construction
Industries Supply Chain
NPP Construction
Cement
PT. Semen Padang PT. Semen Baturaja
Palembang PT. Semen Holchiim
Indonesia PT.. Semen Gresik
Product type and capacity • Type I Portland Cement
(ordinary Portlant Ceme • Nt • Type II Portland Cement • Type III Portland
Cement • Type V Portland Cement • Oil Weld Cement
Product type and capacity • Type I Portland Cement
(about 375000 ton/year • Portland Cement
Composite 875000 ton/year
Product type and capacity • Portland Ceomposite
Cement (about 3169.97 ton/year)
• Ordinary Portland Cement1.328.312 ton
• Concrete Ready Mix 45 million m
Product type and capacity • Ordinary Portland
Cement (about 2.876.3000 box
• Portland Cement 8.763.700 Cement
• Special Blended Cement (with order)
Oil
Oil
Oil
Oil
Coal
Coal
Coal
Coal
19
Estimation of Local Industrial Involvement
Energy Projection with High Scenario (without limited unit of NPP*)
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
2010
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
2034
2036
2038
2040
2042
2044
2046
2048
2050
MW
Capacity of NPP (MW)
* PLTN dibebaskan muncul kapan dan dengan jumlah berapa saja
Energy Projection with High Scenario
(with limit 2 unit of NPP per year**)
0
2000
4000
6000
8000
10000
12000
14000
2010 2017 2024 2031 2038 2045
MW
Capacity of NPP (MW)
** PLTN ditasi waktu (mulai 2027) dan jumlah kemunculan (2 unit/tahun)
Estimation of Local
Industrial Involvement Road map of construction:
NPP (unit#) #1,#2 #3,#4 #5,#6 #7,#8 #9,#10
Year of construction
2027 2034 2037 2040 2043
Contract type Turn-key Turn-key Split package
Split package
Split package
Local content 30 35 40 60 80
Conclusion • Indonesia has already identify industries that
fulfill criteria to participate on civil
construction of new nuclear Power Plant
since they have experiences to build
conventional power plant and
implemented national and international
code and standard.
• Depend on the national nuclear energy
policy, the participation of local industries
could increase with the increase of number
of NPP construction.