    DEVELOPMENT PROCESS

    DEVELOPMENT OF LAND PROCESS

    DEVELOPMENT CONTROL BUILDING APPROVAL PROCESS

    Referral for comments

    if required or publicparticipation exerciseif required

    Applicant /

    Architect

    Consultant

    Nausori Town

    Council

    DTCP

    (if required)Ministry of Environment forEIA, CEMP & OEMPCentral Board ofHealth for noxiousindustryDirector National

    Roads

    Details Plans after

    Approval in

    Principle

    Applicant

    Minister

    Disallo Allow

    If further

    informatio

    n or plan

    amendme

    nt

    Assess inrelation to TPAct GeneralProvisions &comments

    Consented to

    in principle

    subject to

    condition (if

    Consented to

    subject to

    conditions (for

    detail plans or

    refused)

    NOTES:Timelines for Department Town & Country Planning Processing.

    1. If outline building application is first submitted and EIA/CEMP & OEMP/Traffic Management Plan etc required 6 8+ weeks

    2. If detail application submitted and EIA/CEMP/OEMP and any other relevant comment sought required6 8+ weeks

    3. Time lapse between approval in principle ad submission of detail plans & EIA, CEMP, OEMP etc3 6+ months

    4. For detail plans submitted with EIA/CEMP/OEMP etc after approval in principle granted

  • 8/6/2019 Planning Dept1

    2/4

    REZONING PROCESS

    FORWARD PLANNING:(a)Approved Town Planning Scheme Amendment (Rezoning)

    (a) Approved Town Planning Scheme Amendment (Rezoning)

    Ap

    Decisionconveyed Ministers decision conveyed

    ApplicantApplication forRezoning by Director Town &Country Planning

    Provisional Approval by DTCP

    and Suspension of the subjectsite from the Approved Scheme

    Public Notification in

    gazette and newspaper

    One (1) month objection

    Final Approval

    by DTCPAppeal to Minister

    under Section 5(2)

    (d) and he decides;

    Public Notification in

    gazette consecutive

    Submission of objection(s)

    and consideration by

    DTCP; public hearing

    convened if required &

    Objector/local authority

    Notes:

    (a) The average timeline to complete the process is 2-3 months if there is no further consultation.

    (b) The process will exceed the average timeline if consultation with other authorities is done and if the

    public notification is delayed because of late payment of advertising charges by an applicant.

  • 8/6/2019 Planning Dept1

    3/4

    SUB-DIVISION OF LAND PROCESS

    SUBDIVISION OF LAND APPLICATIONS UNDER SUBDIVISION LAND ACT CAP 140A) Subdivision of a Scheme Plan to Approval of Survey Plan

    If required

    If appeal allowed application

    resubmitted to DTCP

    NOTES:

    Application(SchemePlan byapplicantor

    DTCP Consultation forcomments

    Local AuthorityMunicipal/ Rural Local

    Authority

    Director National RoadsDept. Water & SewerageDept of EnvironmentCentral Board of HealthMin of Agriculture-LandUseFiji Sugar Ind TribunalFiji Sugar CorporationLand & Water ResourceNative Land Trust BoardLands DepartmentAirports Fiji Ltd (AFL)Dept of Mineral

    Titles issued by Registraof Titles/leases by land-

    lords- NLTB/DoL/HA etc

    Appeal toMinister

    (Ifapplicantdecides to

    Minister

    decides:

    Decision Approved subjectto conditions or

    Engineering Plans(EP) by Consultantif required

    EP approvedsubject to conditionphysical &construction workscommence and

    Survey Plan (SP) byReg. Surveyor

    Dept. of LandComputation Office

    Director of Landsapproves SP

    Timeline for the various stages of the process1. Receive, register and referral of application to Local Authority & other agencies

    5 10 days2. Comments from local authority/other ministries/dept and agencies

    30 60+ days3. Decision on application b DTCP (depending on scale of subdivision) after comments received

    2 5 days4. Submission of Engineering Plans after Scheme Plan s approved

    1 6+ months5. Comments sought from local authority /PWD DNR & Dept Water & Sewerage

    30 60+ da s