pjm and the clean power plan in new jersey...mar 09, 2016  · 31 pjm©2016 2020 state by state...

48
PJM©2016 PJM and the Clean Power Plan in New Jersey March 9, 2016 Paul M. Sotkiewicz, Ph.D. Senior Economic Policy Advisor PJM Interconnection

Upload: others

Post on 07-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

PJM and the Clean Power Plan in

New Jersey

March 9, 2016

Paul M. Sotkiewicz, Ph.D.

Senior Economic Policy Advisor

PJM Interconnection

Page 2: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 2

PJM as Part of the Eastern Interconnection

As of 1/2016

• 27% of generation in Eastern Interconnection

• 28% of load in Eastern Interconnection

• 20% of transmission assets in Eastern Interconnection

Key Statistics

Member companies 960+

Millions of people served 61

Peak load in megawatts 165,492

MW of generating capacity 171,648

Miles of transmission lines 72,075

2014 GWh of annual energy 792,580

Generation sources 1,304

Square miles of territory 243,417

States served 13 + DC 21% of U.S.

GDP produced

in PJM

Page 3: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 3

PJM Evolution

Page 4: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 4

PJM ‒ Focus on Just 3 Things

Market Operation • Energy

• Capacity

• Ancillary Services

Regional Planning • 15-Year Outlook

Reliability •Grid Operations

•Supply/Demand

Balance

•Transmission

monitoring

2

1

3

Page 5: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 5

PJM’s Role as a Regional Transmission Organization

Page 6: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 6

Market Design Philosophy

• Incentive-based

• Security constrained unit commitment and dispatch

• Bilateral transactions and self-supply properly form the

bulk of trades

• Participants should have all available options to meet

their needs

• Energy is the market focus

• Transparent pricing and customer confidence are

critical to investment

Page 7: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 7

PJM Markets and Their Interaction

Page 8: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 8

PJM Wholesale Cost

Page 9: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

Recent Market Trends to Consider

with Clean Power Plan Compliance

Page 10: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 10

Declining Electricity Demand Growth

Without EKPC 2011-2014

Page 11: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 11

Resulting Generation Retirements

Page 12: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 12

Responsiveness of Capacity Market

Page 13: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 13

Queued Interconnection Requests

December 31, 2015

Page 14: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 14

Cumulative Capacity Resource Additions

Page 15: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 15

Least Cost Dispatch Subject to Constraints

• System operations conducted through dispatch of generation that minimizes bid production cost while respecting generator and transmission or regulatory constraints:

– Balance supply and demand

– Physical limits of transmission facilities

– Reserves and other reliability requirements

– Power quality requirements (e.g., voltage levels, frequency)

– Generators’ schedules (e.g., maintenance outages)

– Emissions limitations or hours-of-operation constraints

– Other physical, regulatory, or market requirements

Page 16: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 16

Overview of Generation Dispatch

Supply offers submitted by EGUs to RTO

Incre

asin

g C

ost

Aggregate

Load Forecast

Committed

(Scheduled)

Generators Unit output varied to match

constantly changing demand

Supply

Offers

Offers stacked by cost; cheapest units scheduled based on expected

demand and constraints Units dispatched in real time by the RTO

• EGU availability (limits, retirement) affects the amount of supply offered to meet demand

• Changing EGU costs (and thus offers) affect frequency and magnitude of utilization in RTO

• Utilization of EGUs directly impacts fuel usage, and thus emissions produced by each EGU

Page 17: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 17

Matching Supply to Demand Over the Day R T O L o a d (M W )

7 0 0 0 0

8 0 0 0 0

9 0 0 0 0

1 0 0 0 0 0

1 1 0 0 0 0

1 2 0 0 0 0

1 3 0 0 0 0

1 4 0 0 0 0

1 5 0 0 0 0

Tim

e (

EP

T)

0:3

9

1:1

9

1:5

9

2:3

9

3:1

9

3:5

9

4:3

9

5:1

9

5:5

9

6:3

9

7:1

9

7:5

9

8:3

9

9:1

9

9:5

9

10

:39

11

:19

11

:59

12

:39

13

:19

13

:59

14

:39

15

:19

15

:59

16

:39

17

:19

17

:59

18

:39

19

:19

19

:59

20

:39

21

:19

21

:59

22

:39

23

:19

$5 $10

$15 $20

$25 $30 $35 $40 $45

$10

$50

Inst

an

tan

eou

s D

ema

nd

(M

W) Bids are sorted in increasing order,

then generation is dispatched

to meet load

Page 18: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 18

Generation Dispatch Over Multiple Areas (1) (e.g., This could be two states in an RTO)

Transmission Line Limit = 400MW

Gen1: 200MW @ $50 Gen2: 300MW @ $30 Gen3: 400MW @ $80 Gen4: 200MW @ $10 Gen5: 100MW @ $40

G3 G1

G2

G4

G5

200 MW

300 MW

100 MW

400 MW FLOW

Area 1: Load = 200 MW Area 2: Load = 400 MW

Area 1: Gen = 600 MW Area 2: Gen = 0 MW @ $100 Market Clearing Price in both areas is $40/MWh

Load Payment in Area 1 = $8,000

Load Payment in Area 2 = $16,000

Gen 2 paid $12,000

Gen 4 paid $8,000

Gen 5 paid $4,000

Page 19: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 19

Generation Dispatch Over Multiple Areas (2)

Transmission Line Limit = 400MW

Gen1: 200MW @ $50 Gen2: 300MW @ $30 Gen3: 400MW @ $80 Gen4: 200MW @ $10 Gen5: 100MW @ $40

G3 G1

G2

G4

G5

200 MW

300 MW

200 MW

100 MW

600 MW FLOW

Area 1: Load = 200 MW Area 2: Load = 600 MW

Area 1: Gen = 800 MW Area 2: Gen = 0 MW

Page 20: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 20

Generation Dispatch Over Multiple Areas (3)

Transmission Line Limit = 400MW

Gen1: 200MW @ $50 Gen2: 300MW @ $30 Gen3: 400MW @ $80 Gen4: 200MW @ $10 Gen5: 100MW @ $40

G3 G1

G2

G4

G5

200 MW

300 MW

100 MW

400 MW FLOW

Area 1: Load = 200 MW Area 2: Load = 600 MW

Area 1: Gen = 600 MW Area 2: Gen = 200 MW @ 100

200 MW

Market Clearing Price Area 1 = $40/MWh

Market Clearing Price Area 2 = $80/MWh

Load Payment in Area 1 = $8000, Area 2 = $48,000

Gen 2 paid $12,000

Gen 4 paid $8,000

Gen 5 paid $4,000

Area 2 Gen

Paid $20,000

Page 21: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 21

Changing Energy Market Trends

* Source: Monitoring

Analytics, LLC. 2015

State of the Market

Report for PJM.

March 10, 2016.

2015 – 4th Quarter

Page 22: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 22

Declining Emission Rates

0

1

2

3

4

5

6

7

8

9

900

950

1,000

1,050

1,100

1,150

1,200

1,250

1,300

1,350

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

SO2 and NOx (lbs/MWh)

CO2 (lbs/MWh)

CarbonDioxideSulfur Dioxide

PJM System Average Emissions

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

780

800

820

840

860

880

900

920

Oct Nov Dec

2015 – 4th Quarter

Page 23: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 23

Implications for CPP Planning

• Regional markets dispatch EGUs on the basis of cost, providing economic and reliability benefits

• The Clean Power Plan will internalize carbon costs; this will affect a regional market’s “economic merit order” (EGU dispatch order):

– Generally, EGUs with higher emissions will be more costly to use

• Modifications to dispatch order may cause electricity generation and emissions to:

– Occur in different amounts

– Occur in different geographic locations (sometimes in different states)

• Decision-makers will need to determine: – Relative advantage of compliance plan structure & path (mass or rate)

– Benefits of coordinating compliance plans with neighboring states

– Multi-pollutant ramifications

Page 24: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

Implications for NJ: Observations from the PJM Analysis of

the Proposed Clean Power Plan

March 2015

Page 25: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 25

More Information and Scenario Results

PJM Economic Analysis of the EPA Clean Power Plan Proposal:

• http://www.pjm.com/~/media/documents/reports/20150302-pjm-interconnection-

economic-analysis-of-the-epa-clean-power-plan-proposal.ashx

State-Level Detail:

• http://www.pjm.com/~/media/documents/reports/20150302-state-level-detail-pjm-

economic-analysis-of-epas-proposed-clean-power-plan.ashx

Page 26: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 26

Sources of CO2 Emissions

Steam Turbine

Coal 85%

NGCC 14%

Oil/Gas Steam

1%

Total CO2 : 442 Million Tons

Steam Turbine

Coal 28%

NGCC 71%

Oil/Gas Steam

1%

2012 PJM CPP Covered Sources

Source: EPA Emissions Goal Computation TSD

2012 New Jersey CPP Covered Sources

Total CO2 : 12 Million Tons

Page 27: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 27

Interim Compliance Period Reductions

PA 31%

OH 24%

WV 13%

IL 11%

MD 6%

VA 6%

DE 1%

IN 3% NJ

2%

KY 2%

NC, MI, TN 1%

• New Jersey accounts for about 2.8 million

short tons of CO2 reductions by 2029 or 2.5

percent of the total required reductions in

PJM

• Of the total 115 millions tons of required

PJM reductions nearly 50 million tons are

from resources that have either announced

retirement or planned to convert from coal to

gas since 2012

• Within New Jersey 0.25 million short tons

are attributed to resources that will have

retired before 2020

• Retirements announced prior to EPA’s

guidance provide an implicit credit and

significantly reduce the burden of

compliance since load will be served by a

mixture of existing and new sources.

2020-2029 Emissions Reduction by State

*DC does not have a compliance obligation. The portion of Tennessee in PJM does not have any sources

covered by the proposed rule.

Total CO2 : 115 Million Tons

Page 28: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 28

PJM Interconnection Queue Statistics

Coal 3%

Natural Gas 66%

Nuclear 3%

Other 2%

Solar 4%

Wind 21%

Other Renewabl

e 1%

Total MWe: 62 GW

Natural Gas

90.5%

Other 1.6%

Solar 7.5%

Wind 0.4%

Total MWe: 6.8 GW

PJM Active Queue Projects by Energy Capability Active* Queue Projects in New Jersey

*New Projects identified based on having an FEAS\SIS\FSA\ISA, not currently suspended, and that result in an increase in output at the point of interconnection.

PJM included queue project W4-009 (Woodbridge Energy Center) and W4-015 (West

Deptford Power Project) in the emissions rate goal computation resulting in a more

conservative rate and mass target

Page 29: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 29

Existing Source vs. New Source Standards

111(d) 111(b)

Relevant dates Interim compliance 2020-2029. Final compliance

2030 and beyond

Scheduled promulgation January 2015

Units impacted • Existing and Under-construction: ST Coal, NGCC,

ST Gas/Oil, High-utilization CT Gas/Oil, IGCC and

some CHP

• Units under 111(b) not subject to 111(d) but could

be included at a state’s discretion

• New Gas-Fired CT, fossil-fired utility boilers and

IGCC units

• CTs running under a 33% capacity factor are

exempt

Standard • State-based compliance with a CO2 emissions

rate target or converted to a mass-based target

• Options for regional compliance

Federal compliance (NSPS):

• Large CT - 1,000 lbs/MWh

• Steam Turbine and IGCC:

• 1,100 lbs/MWh (12 mos.)

• 1,000-1,050 lbs/MWh (84 mos.)

Impact on units Reduced net energy market revenues Potentially

CO2 allowance price or restrictions on unit operation

New gas/dual fuel CCs meet limit

New coal units require partial carbon capture

and sequestration or similar to meet limits

Page 30: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 30

Emissions Reductions from RE & EE

2020 2025 2029

Other 0.0% 1.3% 2.5%

Natural Gas 68.7% 53.8% 51.6%

Coal 31.3% 44.9% 45.9%

0%10%20%30%40%50%60%70%80%90%

100%

2020 2025 2029

Other 5.2% 3.1% 4.0%

NGCC 60.0% 66.9% 70.2%

Coal 34.8% 30.1% 25.8%

0%10%20%30%40%50%60%70%80%90%

100%

Energy Displacement due to Wind Resources Energy Displacement due to Energy Efficiency

OPSI 2b.1 and OPSI 2a used to calculate displacement percentage OPSI 2b.2 and OPSI 2a used to calculate displacement percentage

Page 31: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 31

2020 State by State Compliance Scenario:

Resource Summary

State compliance was only evaluated for compliance with the 2020 interim target

Driver OPSI 2a/2c PJM 4/9 PJM 7/11

Renewables Modeled 88.8 GWh (Thousands) 46.5 GWh (Thousands) 46.5 GWh (Thousands)

111(b) NGCC 14.5 GW 14.5 GW 2.8 GW

Nuclear 33.4 GW 33.4 GW 33.4 GW

Natural Gas Price Economic Forecast Economic Forecast Economic Forecast

Energy Efficiency

Modeled

26.3 GWh (Thousands) 7.9 GWh (Thousands) 7.9 GWh (Thousands)

Description Achieve State RPS and

EPA EE Targets

Low Growth in

Renewables and EE

Limited New Resources

Page 32: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 32

Modeling the Proposed Rule

Used PROMOD for simulation modeling

• PROMOD models hourly security constrained economic generation commitment and dispatch

• Assumptions consistent with 2014 RTEP Market Efficiency Analysis

• Regional Dispatch of PJM Generators to serve PJM load

Regional Compliance

• No one state needs to comply in isolation, but in aggregate the region cannot exceed the regional mass- or rate-target

• Iterate on a single PJM-wide CO2 price until the region is in compliance

State-by-State Compliance

• Each state (12 states in the simulation) has its own unique CO2 price

• Simultaneously iterate on individual state CO2 prices until all states are in compliance

Page 33: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 33

State-By-State vs Regional Compliance

*DC does not have a compliance obligation. The portion of Tennessee in PJM does not have any sources covered by the proposed rule. The portion of Michigan in PJM has a single covered source (Covert

Generating Station) and was not studied for state-by-state compliance.

Page 34: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 34

Sensitivity of Costs Due to RE, EE & NGCC

$35.8 $36.7

$4.5 $4.9

$11.7 $10.1

$20.0

$25.0

$30.0

$35.0

$40.0

$45.0

$50.0

$55.0

Regional Compliance State Compliance

Limited Resource Entry

Lower Renewable Growth

Achieve RPS and EPA EE Targets

$31.8 $32.7

$4.4 $4.6

$10.8 $9.5

$20.0

$25.0

$30.0

$35.0

$40.0

$45.0

$50.0

$55.0

Regional Compliance State Compliance

Limited Resource Entry

Lower Renewable Growth

Achieve RPS and EPA EE Targets

Locational Marginal Price ($/MWh) Wholesale Load Energy Cost ($Billions)

Page 35: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 35

At-Risk Generation

7,521

14,797

6,407

13,353

10,500 13,086

3,614

2,805

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

RegionalCompliance

StateCompliance

RegionalCompliance

StateCompliance

RegionalCompliance

StateCompliance

0.6 - 0.75 Net CONE

Achieve State RPS

and EPA EE Targets

Limited New Resource

Entry

Lower Renewable

and EE Growth

Reduce EE by

18.5 Thousand

GWh

Reduce

Renewables by

42.2 Thousand

GWh

Reduce NGCC

by 11.7 GW

MW

CO2

Price is

$0/Ton

Page 36: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

Regional Compliance Approaches:

Emissions Rate Based (PJM 10)

vs.

Mass-Based (PJM 4)

(Note: The Final CPP models rate a bit differently)

Page 37: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 37

Rate-Based vs Mass-Based Compliance

Impact on Locational Marginal Prices

$62.1

$75.4

$54.4

$66.2

$0.0

$10.0

$20.0

$30.0

$40.0

$50.0

$60.0

$70.0

$80.0

2025 2029

Mass Based

Rate Based

LMP ($/MWh)

Page 38: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 38

Rate-Based vs Mass-Based Compliance

Impact to Fuel and O&M Expense

$29.5

$35.7

$28.6

$34.0

$0.0

$5.0

$10.0

$15.0

$20.0

$25.0

$30.0

$35.0

$40.0

2025 2029

Rate Compliant Mass Compliant

$Billions

Page 39: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 39

Rate-Based vs Mass-Based Compliance

Impact on NGCC Unit Operation

59.1%

83.9% 78.1%

44.5%

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

70.0%

80.0%

90.0%

Rate Compliant Mass Compliant

111(b)

111(d)

Capacity Factor (%)

Page 40: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

Clean Power Plan

Proposed Rule Versus Final Rule Key Differences and how PJM’s Economic Analysis is Impacted

Page 41: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 41

Proposed Rule vs Final Rule

Proposed Rule Final Rule

Relevant dates Interim compliance 2020-2029. Final

Compliance 2030 and beyond

Interim compliance 2022-2029. Final Compliance

2030 and beyond

Units impacted Existing and Under-construction: ST

Coal, NGCC, ST Gas/Oil, High-

utilization SCT Gas/Oil, IGCC and

some CHP.

Existing and Under-construction: ST Coal, NGCC,

ST Gas/Oil, some IGCC and CHP units

Standard and

compliance

• Individual state-based compliance

with emissions rate or mass

targets

• Multi-state based compliance with

emissions rate or mass targets

• Individual state-based compliance with

emissions rate or mass targets

• Multi-State compliance with emissions rate or

mass targets

• Trading or state-measures (mass-based)

• Trade-ready (Individual state plan)

• Federally enforceable rate targets

• State enforced operational limitations on

specific units

Page 42: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 42

Target Setting: Proposed Rule vs Final Rule

Phased-In Switching from Coal to Existing and UC NGCC starting in 2022

Incremental Renewables

constructed January 2013 and beyond

Coal Resource Heat Rate

Improvements

By 2022

Switching from coal to Existing and UC NGCC

by 2020

EE assumed to grow up to 1.5%

per annum starting in 2017

Existing and Incremental

Renewables and 5.8% Credit for

Nuclear

Coal Resource Heat Rate

Improvements

By 2020

Proposed Rule: State Portfolio Rate Final Rule: EGU Sub-category Rates

Page 43: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 43

Final Rule Target Setting Procedure

Sub-category rate

• EPA building blocks used to set national sub-category emissions rate targets for natural gas combined cycles and fossil (Oil, Gas, Coal) steam resources

State Rate

• State goal rates based on average of national sub-category rates weighted by in-state 2012 fossil steam and NGCC generation

State Mass

• State mass targets based on product of state goal rate and 2012 baseline generation + MWh credit for assumed over-build of renewables in sub-regions

Page 44: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

Clean Power Plan Analysis Update

Page 45: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 45

What Are we Being Asked

What will be the economic and reliability impacts to

states

What is my state’s bottom line due to trading versus not using a trading option

What happens to resource diversity and what does it

mean for baseload resources

What is the difference between an

emissions market trading seam and an electric

market seam

What happens if my plan diverges from what most of

the other PJM states submit in their compliance

plans

Alright, trading makes sense but rate or mass

Page 46: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 46

How is PJM Identifying Answers

Page 47: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016 47

What Information will Answer these Questions

Reliability

Capacity added /retired by LDA and RTO

region

Transfer capability for reactive interfaces

Generation and Load Deliverability tests

results

Electric Market

Locational marginal prices and energy

market load payments

Facility level transmission congestion

Percentage of generation by prime mover and fuel type

Environmental

Carbon dioxide prices, total allowance supply/demand

Resource entry capital costs

Emission rate credit production and consumption

Detailed Results by Individual State and/or PJM region

Page 48: PJM and the Clean Power Plan in New Jersey...Mar 09, 2016  · 31 PJM©2016 2020 State by State Compliance Scenario: Resource Summary State compliance was only evaluated for compliance

PJM©2016

Final Rule Analysis Timeline

March Present Reference

Model Results

PJM State Agencies

April 30 Complete

Compliance Analysis

Assessment including high

priority sensitivities

Discussions with OPSI, stakeholders and air regulators

May 31 Publish compliance pathways report

Through Q3 Additional Reliability

Analysis

Coordination work with

MISO

Additional Economic

Sensitivities