pipeline wetlands report ver 1 - terratest - lombards kop reservoir... · this tool is a...

38
MAY 2015 Prepared by: TERRATEST (PTY) LTD PO Box794 Hilton 3245 033 3436700 [email protected] D.J. Alletson SURVEY OF THE WETLANDS AND DRAINAGE LINE ALONG THE ROUTES OF LOMBARDSKOP PIPELINE UPGRADES AND RELACEMENTS INTHE VICINITY OF LADYSMITH, KWAZULU- NATAL TOGETHER WITH IMPACT ASSESSMENT AND MITIGATORY RECOMMENDATIONS

Upload: trinhdung

Post on 25-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

MAY 2015

Prepared by:

TERRATEST (PTY) LTD

PO Box794

Hilton

3245

033 3436700

[email protected]

D.J. Alletson

SURVEY OF THE WETLANDS AND DRAINAGE LINE ALONG

THE ROUTES OF LOMBARDSKOP PIPELINE UPGRADES AND

RELACEMENTS INTHE VICINITY OF LADYSMITH, KWAZULU-

NATAL TOGETHER WITH IMPACT ASSESSMENT

AND MITIGATORY RECOMMENDATIONS

VERIFICATION PAGE

Form

4.3.1

Rev 13

SURVEY OF THE WETLANDS AND DRAINAGE LINE ALONG THE ROUTES OF

LOMBARDSKOP PIPELINE UPGRADES AND RELACEMENTS INTHE VICINITY

OF LADYSMITH, KWAZULU-NATAL TOGETHER WITH IMPACT ASSESSMENT

AND MITIGATORY RECOMMENDATIONS

JGI NO. :

41556

DATE :

May 2015

REPORT STATUS :

Final

CARRIED OUT BY : COMMISSIONED BY :

Terratest (Pty) Ltd

P O Box 794

Hilton

3245

MBONA, SAUNDERS AND WIUM (PTY) LTD

28 St Patricks Road

Scottsville

PIETERMARITZBURG

South Africa

Tel: (033) 343 6789 Tel +27 (0) 33 395 0920

Fax: (033) 343 6788 Fax +27 (0) 33 395 0921

Email: [email protected] Email: [email protected]

AUTHOR : CLIENT CONTACT PERSON :

D.J. Alletson C. Mitchell

SYNOPSIS :

This report documents the findings of environmental studies done at the sites of stream and

wetland crossings along the routes of two bulk water pipelines to Lombardskop near Ladysmith,

KwaZulu-Natal. Both desktop studies and field surveys were undertaken. The findings were that

the project should not have any significant environmental impacts but that precautions will have to

be taken to ensure that the watercourses and wetlands are not impacted upon. Mitigation

guidelines are put forward.

KEY WORDS :

Pipeline upgrade, Environmental Studies, Impact Assessment, Mitigation Guidelines.

© COPYRIGHT: Terratest (Pty) Ltd.

QUALITY VERIFICATION

This report has been prepared under the controls established by a quality management system

that meets the requirements of ISO9001: 2008 which has been independently certified by DEKRA

Certification under certificate number 90906882

Verification Capacity Name Signature Date

By Author Specialist Ecologist D.J. Alletson

21/05/2015

Checked by Environmental Consultant J. Richardson

21/05/2015

Authorised by Executive Associate M. van Rooyen

21/05/2015

Terratest (Pty) Ltd

TABLE OF CONTENTS

1. INTRODUCTION ........................................................................................................... 1

2. PROJECT DESCRIPTION AND STUDY AREA ............................................................. 1

3. STUDY PROCEDURES ................................................................................................. 3

3.1 Study Outline .......................................................................................................... 3

3.2 Risk Assessment .................................................................................................... 3

3.3 Wetland Assessment .............................................................................................. 4

4 STUDY FINDINGS ......................................................................................................... 5

4.1 Desktop Studies ...................................................................................................... 5

4.1.1 Vegetation ....................................................................................................... 5

4.1.2 Conservation data ............................................................................................ 5

4.1.3 Wetlands .......................................................................................................... 5

4.1.4 Other data ........................................................................................................ 5

4.2 Site Studies............................................................................................................. 7

4.2.1 Existing Pipeline Crossing Points ..................................................................... 8

4.2.2 New Pipeline Crossing Points ........................................................................ 13

4.2.3 Proposed Alternative Pipeline Route Crossings ............................................. 21

5 CONSIDERATION OF RISK LEVELS AS PER THE DEPARTMENT OF WATER AND

SANITATION MODEL ......................................................................................................... 22

6 CONSIDERATION OF THE PRESENT ECOLOGICAL STATE OF THE LARGER

WETLANDS IN THE VICINITY OF THE PROPOSED PIPELINE ROUTE .......................... 23

7 CONSIDERATION OF POTENTIAL IMPACTS ON THE WETLANDS AS A

CONSEQUENCE OF THE PROPOSED PIPELINE UPGRADES AND COSTRUCTION .... 25

7.1 Impacts on Stream and Wetland Crossings ............................................................... 25

7.2 Impacts at the Klip River and Floodplain Crossing Sites ............................................ 27

8 SUMMARY .................................................................................................................. 29

9 REFERENCES ............................................................................................................ 29

APPENDIX I: DEFINITION OF TERMS USED IN IMPACT ASSESSMENT ........................ 31

Terratest (Pty) Ltd

-1-

SURVEY OF THE WETLANDS AND DRAINAGE LINE ALONG THE ROUTES OF

PIPELINE UPGRADES AND RELACEMENTS INTHE VICINITY OF

LOMBARDSKOP LADYSMITH, KWAZULU-NATAL TOGETHER WITH IMPACT

ASSESSMENT

AND MITIGATORY RECOMMENDATIONS

1. INTRODUCTION

The Emnambithi/Ladysmith Municipality (the Municipality) is proposing to upgrade the bulk

potable water pipeline which links the Ezakheni Reservoir and a new Lombardskop Reservoir

which will be situated close to the existing one.

The proposed development of this water scheme triggers a number of activities listed under

the Environmental Impact Assessment Regulations (2014) which were promulgated under the

National Environmental Management Act (Act 107 of 1998). Prior to the commencement of

the proposed project, it will be necessary for the applicant (the Municipality) to obtain

Environmental Authorization, which is subject to a Basic Assessment being undertaken, from

the Department of Economic Development, Tourism and Environmental Affairs (EDTEA).

Terratest (Pty) Ltd have been appointed by the Municipality to apply for the required

authorization. This report is a part of that assessment process and is intended to provide an

understanding of the project in regard to wetlands and drainage line crossings.

The findings of this study are that most of the watercourses in the study area are already

degraded to varying degrees but that some features of environmental conservation value are

present. However, the existing pipelines have had very little discernible impact on the

watercourse crossings and hence there is little reason why the new lines should have impacts

provided that the construction is properly undertaken. Recommendations intended to help

reduce potential impacts along the routes are put forward.

2. PROJECT DESCRIPTION AND STUDY AREA

The project consists of the following components:

• The upgrading of the existing pipeline from the Ezakheni Reservoir to a point near the

Ntombi Spruit Crossing. The length of this section is 5.75 km;

• The construction of a new 450 mm – 500 mm steel pipeline from the Ntombi Spruit

crossing through to a new reservoir to be built on Lombardskop. This line will run very

close to an existing line for much of its length but will include some new sections

including a new crossing point under the Klip River. Its length, depending on the final

route option selected, will be approximately 7.7 km.

The details of the above key points are indicated below and are shown in Figure 1.

• Ezakheni Reservoir. 28° 38' 23.0" S 29° 50' 18.5"E

This reservoir is taken as the starting point for the pipeline routes.

• Ntombi Spruit Crossing. 28° 35' 55.2" S 29° 49' 3.7" E

Terratest (Pty) Ltd

-2-

The transition from older existing pipeline to a proposed new pipeline will take place at

a point near the Ntombispruit.

• Lombardskop Reservoir. 28° 33' 35.0" S 29° 51' 25.1" E

This reservoir is the endpoint of the pipelines.

Figure 1. Localities of the project area in relation to the town of Ladysmith.

Terratest (Pty) Ltd

-3-

3. STUDY PROCEDURES

3.1 Study Outline

The study for the stream crossing sites along the pipelines was done in a series of phases

which were as follows:

• Desktop study. A preliminary investigation of the route was undertaken using aerial

and Google Earth imagery in order to determine possible sites of wetland or drainage

line crossings. Then attention was given to the Ezemvelo KZN Wildlife Minset planning

database, to the provincial wetland database, to the NFEPA (National Freshwater

Ecosystem Protected Areas) database, and to the vegetation type for the area. The

purpose of these database searches was to look for any recognised wetland-related

sites of conservation sensitivity. The terrestrial vegetation types and terrestrial fauna

were therefore largely ignored.

• Site surveys. The entire pipeline route, with the exception of a few points where it

passes over hilltops, which would not have wetlands, was traversed in order to gain

first hand understanding of the conditions on the ground. Each of the sites noted in

the desktop study was visited and assessed, and other sites, which had been missed,

were looked for. Attention was paid to the vegetation and to waterways and wetlands.

• Reporting. The findings of the above two phases were documented and the potential

impacts of the construction operations and associated mitigatory measures were

considered.

3.2 Risk Assessment

The National Water Act (Act 36 of 1988) and its regulations call for the issue of a Water Use

Licence under certain conditions where a development or other activity may impact on a water

resource. The two key Sections in this regard are Section 21 (c) which covers activities which

may “impede or divert” the flow of water in a watercourse. The key trigger distances for

consideration of an activity are 32m for a watercourse and 500m for a wetland.

In order for the potential impacts of the new pipeline to be assessed use was made of the

Department of Water and Sanitation’s Risk Assessment model to determine whether any

streams or wetlands were likely to be placed at risk as a result of the construction process.

This tool is a spreadsheet-based model which considers the possible impacts of an activity on

a water resource. Risks or other relevant conditions are assigned a numeric score and these

scores are then manipulated to produce a final rating. The ratings vary in value from 1 to 300

and are divided into three classes as shown in Table 1.

Table 1. Department of Water and Sanitation rating table for impacts on water resources.

Terratest (Pty) Ltd

-4-

RATING CLASS MANAGEMENT DESCRIPTION

1 – 55 (L) Low Risk Acceptable as is or consider requirement for

mitigation. Impact to watercourses and resource

quality small and easily mitigated. Wetlands may be

excluded.

56 – 169 M) Moderate

Risk

Risk and impact on watercourses are notably and

require mitigation measures on a higher level, which

costs more and require specialist input. Wetlands

are excluded.

170 – 300 (H) High Risk Always involves wetlands. Watercourse(s)

impacts by the activity are such that they

impose a long-term threat on a large scale

and lowering of the Reserve.

3.3 Wetland Assessment

It is usual for an estimation of the Present Ecological State of each system to be made.

Normally this would be done by means of a model such as WET-Health and this has done for

the Klip River floodplain in the vicinity of the pipeline route. However, the model was not

applied to the whole of the system both as the system is so large and as the data available is

minimal. However, the potential changes of the pipeline construction are likely to be miniscule

and so, while the modelling of the system is not perfect, it is considered to be sufficient to

provide some understanding of the floodplain in that area. The classes generated by the model

are as indicated in Table 2.

Table 2. Wetland categories from the WET-Health model

Terratest (Pty) Ltd

-5-

4 STUDY FINDINGS

4.1 Desktop Studies

4.1.1 Vegetation

The vegetation surrounding all the sites is transitional between Northern KwaZulu-Natal Moist

Grassland (Gs 4) and KwaZulu-Natal (Gs 6) by Mucina and Rutherford (2006). These two

types are in areas of moderate rainfall (750 mm – 850 mm per annum) are generally not rich

in wetlands other than in the lower lying area along river valleys. The vegetation descriptions

given make no reference to wetlands.

The wetlands which are present at some of the crossing points are classified as “Alluvial

Wetlands: Temperate Alluvial Vegetation” in the KZN Wetlands database and as “Natural” in

the NFEPA database.

4.1.2 Conservation data

The Ezemvelo KZN Wildlife Minset database was interrogated to search for wetland-related

conservation priorities. It was found that, other than for some of the wetlands in the area,

nothing relevant to this study was listed.

4.1.3 Wetlands

The Ezemvelo KZN Wildlife and NFEPA wetland databases contain the same spatial data and

so no differences are indicated. Two large wetland systems are indicated. The first of these,

in the direction of water flow, is an open valley bottom system in the Mbulwana area. See

Figure 2. It is immediately apparent that the mapping is inaccurate as the indicated area

includes a considerable amount of built development and roads which are on hillsides.

Despite this the site was marked for field investigation at a later stage.

The second wetland area indicated is the floodplain of the Klip River on the south-eastern

outskirts of Ladysmith. Again the mapping appears to be inaccurate in terms of the included

infrastructure and also of the ground contours in the demarcated area. It was apparent

however, that there are wetland patches present and that in situ inspection would be

necessary.

In addition to the large database-mapped wetlands, the desktop study also revealed a number

of smaller systems which are within 500m of the pipeline routes and these were also noted for

further investigation. It was found that those marked “1” and “2” in Figure 2 are on the opposite

side of the railway line and river to the pipeline and so will not be affected by the project.

4.1.4 Other data

(i) Transformation. All of the pipeline route with the exception of a small part of the

Klip River floodplain was classified as “Transformed”.

(ii) Threatened Ecosystems. No threatened ecosystems, as listed in the SANBI

database, are present anywhere near the pipeline routes.

(iii) Game Reserves, Nature Reserves, and Wildlife Conservancies. No nature

conservation areas are present anywhere near the pipeline routes.

Terratest (Pty) Ltd

-6-

Figure 2. Distribution of wetlands along the pipeline routes. See text for

explanation of wetlands “1” and “2”.

(iv) Important Bird Areas. Important Birds Areas have been designated at sites where

the avifauna is of particular value, either in regard to bird diversity, or as habitat for

2

1

Terratest (Pty) Ltd

-7-

migratory or rare bird species. No such areas are listed anywhere within a 20 km

radius of the pipeline and so no concern is raised in this regard.

(v) Fish in the Klip River. Since the 1970s, Ezemvelo KZN Wildlife has conducted a

number of fish surveys in the Klip River. Other than for alien species only the

following indigenous species have been recorded downstream of the Windsor dam:

Sharptooth Catfish Clarias gariepinus

Mocambique Tilapia Oreochromis mossambicus

Chubby-headed barb Barbus anoplus

NOTE: All of these species are common and widespread. The Mocambique Tilapia

is classified as “Near Threatened” as the genetic integrity of the species is at risk

as a result of hybridisation with alien Tilapia species. However, the construction of

the proposed pipeline will not impact on it in any way.

It is recognised that the Tugela River, into which the Klip River flows, contains two

endemic fish species. One of these, the Natal Scaly (Labeobarbus natalensis), is

a KwaZulu-Natal endemic and the other, the Tugela Labeo (Labeo

rubromaculatus), is a Tugela River basin endemic. However, the Klip River has two

large waterfalls in its lower reaches (below Ladysmith) and the fish have not been

able to penetrate upstream past them.

4.2 Site Studies

As indicated, all of the pipeline route, with the exception of the hilltops, was visited. This was

made possible by the existence of roads and tracks along much of the route and only in a few

places was it necessary to walk any distance. Particular care was taken to visit the sites which

had been identified in the desktop study but further sites were also searched for. At each

wetland or stream crossing photographs were taken and note was made of the conditions.

The crossings listed below extend from the Ezakheni reservoir onwards.

NOTE: The sites within the Klip River floodplain area (Sites 9 to 14) and in other wide systems

(Sites 1, 2, 15, 16, and 17) are indicated by single points. However, since the floodplain is

expansive, consideration was given to, not just the point, but also to potential impacts along

the pipeline route on either side of the point.

Terratest (Pty) Ltd

-8-

4.2.1 Existing Pipeline Crossing Points

See Figure 2 for the locations of the crossing points.

Figure 2. Pipeline crossing points along the existing pipeline route.

• Site 1

Terratest (Pty) Ltd

-9-

Position: 28° 37' 56.2"S. 29° 50' 16.3"E

Description: This crossing point is on the Davelspruit. The stream is wide and has multiple

channels. Sediment infill as a result of catchment erosion is extensive. The area is

extensively grazed by livestock so, at the time of the visit the vegetation was low. The

stream channel is invaded by River Bean (Sesbania punicea). At the time of the visit the

system was largely dry.

Downstream of the crossing site the stream channel has been used as a borrow pit for

provision of a soil or rock material.

Crossing Details: No pipeline markers were seen at the site and there was no visible

evidence of any damage to the system as a result of the crossing.

Photograph 1. Site 1. Davelspruit

crossing point. The absence of

markers meant that the precise

point could not be determined.

• Site 2.

Position: 28° 37' 42.1"S. 29° 50' 14.6"E

Description: This site lies within a wetland area included in the NFEPA database. The

system is large and diffuse. The topography is generally low with gradients being very

gentle (<3.5%). It is apparent that it has been extensively transformed by human activities

including cultivation for production of crops. At present only parts are still cultivated but

some of the pipeline route has been used in this way.

An estimate of the Present ecological State (PES) has been made. See Section 6.

Crossing Details: No markers were found but there is no evidence of any damage to the

system as a result of the line being present.

• Site 3.

Position: 28° 37' 16.1"S. 29° 50' 11.5"E

Description: This site lies at the point where a small stream is crossed and is a short

distance (140 m) downstream of a dam whose primary function is now stock watering.

The stream probably has near perennial flow although the amount of water will be minimal

in the dry season and in dry years may cease altogether. Wetland obligate plants seen at

Terratest (Pty) Ltd

-10-

the site included sedges (Cyperaceae), Knotweed (Persicaria sp.) and a tall grass

(Sporobolus sp?).

Crossing Details: The crossing point is marked with markers and a valve chamber is

present. A footpath/track crosses the stream immediately alongside the pipeline. The site

shows no indications of having been impacted upon by the line which is buried under the

stream.

Photograph 2. Site 3. A route marker

is visible and the valve chamber is

indicated by the arrow.

• Site 4.

Position: 28° 36' 36.7"S. 29° 50’ 8.3"E

Description: This site is the point at which the pipeline passes through the Hermanspruit.

The slopes on either side of the channel are moderately steep but appear to be stable. At

the time of the visit there was no surface water visible and so it is apparent that the system

is seasonal.

Photograph 3. Site 4. A route marker

(arrow) and a valve chamber are

visible.

Crossing Details: The stream channel is stable and is well armoured with boulders. The

pipeline is buried and does not appear to be affecting the channel in any way.

• Site 5.

Terratest (Pty) Ltd

-11-

Position: 28° 36' 16.4"S. 29° 50’ 1.2"E

Description: This site is located on a very small drainage line which will only flow naturally

at times of high rainfall. A small dam has been constructed to retain some of these flows.

However, water leakage from a valve chamber on the line, as well as leakage from a

nearby tap, have led to a situation where there is permanent water and a community of

hygrophilous plants has developed below the crossing.

Crossing Details: The site lies alongside a narrow road/track and the pipeline route is

plainly indicated by the valve chamber and a marker. Apart from the changes arising out

of the two water leaks, the crossing does not seem to have affected the drainage line in

any way.

Photograph 4. Site 5. Note the zone

of green vegetation established as a

result of the leaks from the valve

chamber and from a running tap.

• Site 6.

Position: 28° 36' 3.2"S. 29° 49’ 20.6" E

Description: This site lies on a small unnamed stream. Flow, or at least standing pools of

water, are probably perennial. At the time of the site visit the vegetation in the channel

upstream of the crossing was green but a valve chamber at the site was full of water so it

is probable that some leakage is contributing to downstream flows. The vegetation was

heavily grazed by livestock but does appear to be dominated by grasses rather than by

hygrophilous species.

Terratest (Pty) Ltd

-12-

Photograph 5. Site 6. The pipeline

marker and the valve chamber are

clearly visible. Leakage from the latter

may be contributing to the green

vegetation.

Crossing Details: The site is well marked by both a marker and by the valve chamber. There

is no erosion or other evidence to suggest that it is having any adverse impact on the drainage

line.

• Site 7.

Position: 28° 35' 55.8"S. 29° 49’ 4.6"E

Description: This site lies on the Ntombispruit and is immediately upstream of a road

crossing. A valve chamber is located within the macro channel of the stream but there is

no indication that leakage is having any effect on the system. After the crossing the line

continues northwards and a marker situated some 35 m north of the bridge is taken as

being the end point of the existing pipeline.

This site is indicated as being within a wetland system which is linked to the floodplain of

the Klip River. While the mapping is plainly inaccurate, the site is within a wetland system

and is likely to be inundated at times.

Crossing Details: The site is well marked by both a marker and by the valve chamber.

Access from the nearby road is readily available.

Photograph 6. Site 7. The

crossing point is to the left of the

road where a marker and a valve

chamber are visible. The arrow

indicates the positions of the

marker and is taken to be the end

of the “existing” pipeline.

Terratest (Pty) Ltd

-13-

4.2.2 New Pipeline Crossing Points

The section of pipeline which is considered below is designated as “new” although in situ

examination of the route revealed that an existing pipeline is already present along most of its

length. See Figure 3 for the crossing points along the new pipeline route.

The starting point of the new line has been indicated by the client as being at the end of the

existing pipeline covered in Section 4.2.1 above. While the alignment of this line was followed,

an alternative route is also suggested for a part of its length so as to avoid some wetland

areas.

Much of the new pipeline route, between Site 9 and Site14 lies within the Klip River floodplain.

This is a large wetland system but is now only inundated by exceptionally large flow events.

The soil is very clay-rich and is hard when dry. It is assumed to be alluvial in origin. Much of

the area has been cultivated in the past although, along the pipeline routes examined here,

there is now no such activity. However, the area is heavily grazed by livestock which consists

primarily of cattle and a lesser number of goats. The vegetation which now covers much of

the area is a species-poor medium-to-tall grassland community. Thatch grass (Hyparrhenia

hirta) and Turpentine grass (Cymbopogon sp.) predominate but short species such as Kweek

(Cynodon dactylon) and Buffalo grass (Paspalum sp.) are also widespread. Forbs are

generally scarce but a few scattered Hypoxis and Berkheya were noted. All were withered and

senescent and full identification was not possible. Scattered stands of tall Eucalyptus trees

are planted in rows and are probably remnant traces of past human activity.

Of importance on the floodplain are some wet areas. These may be small (<10 m2) or else

may be several hectares in extent. The origin of the water which sustains them is not apparent.

With the special exception of Site 12, no surface water was visible, and tall wetland plants are

generally absent. Thus the wet patches are considered to be unchannelled floodplain

hygrophilous grasslands. Their degree of wetness probably varies considerably, and some

may even be seasonal or ephemeral. Situated some 350 m from Site 9 is a vestigial oxbow

which probably remains permanently wet. However, it will not be affected in any way by the

proposed development.

Throughout the system it is common to find greener vegetation in the furrows left by the old

cultivation. In some cases these may be drawing water from the wet patches but most are

probably just localised reservoirs of pooled rainwater and are not linked to ground water in

any way. A large drainage canal, which originates in the housing area on the eastern side of

the floodplain, runs parallel to Mandela Drive and then turns southwards to pass across the

floodplain and into the Klip River.

The Klip River floodplain is considered further in Section 6.

Terratest (Pty) Ltd

-14-

Figure 3. Pipeline crossing points along the “new” and alternate pipeline routes.

Terratest (Pty) Ltd

-15-

• Sites 8a and 8b.

Positions: 28° 35' 54.9"S. 29° 49’ 3.7" E and 28° 35' 51.9"S. 29° 49’ 6.2" E

Description: These two sites are the locations of places where the new line would cross

channels of the Ntombispruit system. As such they are within the mapped wetland system

which is referred to above. Site 8a is visible in Photograph 6 and lies on the opposite side

of the road to the indicated marker. The channel in each case is open with a sand/gravel

bed and banks which are covered by tall grasses. They were dry at the time of the visit

and so only seasonal flows are indicated.

Crossing Details: Based on the observations made at Site 7, it appears that a pipeline

buried below the channel beds would have no impact on the system in the medium to long

term.

• Site 9.

Position: 28° 35' 49.6"S. 29° 49’ 9.6" E

Description: This site lies in an area which has some wetland characteristics. While the

soils were too hard to be augered, it was clear that they have a very high clay content and

are probably alluvial. The vegetation is dominated by tall grass species but they had been

trampled and grazed and identification could not be done. No evidence of the existing

pipeline could be found.

Crossing Details: The soils in the area are clay rich and were very hard at the time of the

visit. However vehicle tracks made in the wet season indicate that the surface is much

softer at that time. The soils are alluvial and are linked to the floodplain of the Klip River.

• Site 10.

Position: 28° 35' 41.0"S. 29° 49’ 12.6" E

Description: The site lies about 35 m off the indicated alignment of the new pipeline. It

does however mark the location of an existing pipeline marker and a valve chamber which

is leaking water to an extent which is sufficient to have created a small wetland. The

leakage has been persistent enough for a stand of bulrushes (Typha capensis) to have

developed. This plant is a wetland obligate species and it is thought that propagules would

have been brought to the site by water birds.

Terratest (Pty) Ltd

-16-

Photograph 7. Site 10. The stand of

bulrushes near the pipeline marker

and valve chamber is indicated.

This wetland patch was delineated and has an area of 0.25 ha. It is, however, totally

unnatural and termite mounds situated a few metres away from its edge are dry to a depth

of at least 1,5 m, thus indicating that the ground water is not widespread.

Crossing Details: Apart from the wetland at the site of the valve chamber there are no

other traces of the pipeline. It can therefore by assumed that no long term environmental

damage is being done.

• Site 11.

Position: 28° 35' 30.3"S. 29° 49’ 17.0" E

Description: Site 11 is the point at which the existing pipeline crosses the Klip River

although the new pipeline route is some 75 m to the east. There are markers on both

banks and so the placement of the old line is clear. The active channel is deeply incised

and the present water surface is approximately five metres below the surrounding

floodplain area. The vegetation on the banks of the primary channel is greener than that

on the upper floodplain and so a deep (2 m from surface) ground water surface is

suggested. The vegetation along the crest of the channel is dominated by grasses

including Thatch grass (Hyparrhenia hirta) but the lower banks also have a variety of small

bushes and some trees. Species noted included Willows (Salix Sp.), Silver poplar

(Populus x canescens), Paperbark thorn (Acacia sieberiana), Pale-bark Sweet Thorn (A.

natalita), and Gum trees (Eucalyptus sp.).

Crossing Details: Other than for the two pipeline markers, there is no trace of the pipeline

at the site. It is therefore apparent that the line is now having no impact at that point. On

the basis of this observation there is no clear cause for concern if the new line is placed

75 m further downstream.

Terratest (Pty) Ltd

-17-

Photograph 8. Site 11. Site of the

present pipeline crossing. The

picture was taken from the site of

a marker and the marker on the

opposite is indicated (arrow).

Otherwise there is no visible trace

of the line.

• Site 12.

Position: 28° 35' 17.7"S. 29° 49’ 22.6" E

Description: This site marks the location of an existing marker and valve chamber while

the indicated new pipeline route is some 65 m to the east. The pipe within the chamber

leaks and a large (± 2 ha) wetland has developed in the area. This wetland is well

developed and now supports populations of several bird species which are either wetland

obligate or near obligate. Included are Grey Crowned Cranes (Balearica regulorum), Red-

billed Teal (Anas erythrorhynca), Black-headed Heron (Ardea melanocephala), Great

Egret (Egretta alba), Sacred Ibis (Threskionis aethiopicus) and a variety of weavers,

bishop birds, and warblers. The greater part of the vegetation consisted of sedges and

grasses. The crane species is Red Data listed.

Crossing Details: The leak from the pipeline has contributed to the formation of a large

wetland with areas of open water. Apart from this feature there is no other evidence of the

line since there is no soil erosion of any sort.

Photograph 9. Site 12. The open

water near the valve chamber is

visible and the body of the wetland

lies in the background.

Terratest (Pty) Ltd

-18-

Photograph 10. Site 12. The

valve chamber which is leaking the

water, and the pipeline marker are

shown.

• Site 13.

Position: 28° 35' 22.0"S. 29° 49’ 41.1" E

Description: Site 13 is taken to be at the point where some yellow painted stones were

seen and is assumed to be the point where the pipeline turns toward the north. These

stones were the only marker found and are situated some 50 m from the drainage canal

leading from the direction of Mandela Drive.

Crossing Details: There is no soil erosion of any sort visible at the site and the vegetation

is the same as that in the surrounds.

Photograph 11. Site 13. The

painted stones which mark the site

are shown.

• Site 14.

Position: 28° 35' 13.1” S. 29° 49’ 45.2” E

Description: Site 14 is the point where the pipeline passes under Mandela Drive and then

passes under the drainage canal there. No markers or other traces of the line were found

and so no description is given.

• Site 15.

Position: 28° 35' 8.8” S. 29° 49’ 51.1” E

Terratest (Pty) Ltd

-19-

Description: Site 15 is the point where the pipeline passes under the road coming in from

Colenso (P325). No markers were found but it is clear that no erosion has been caused

to that area.

South and east of the site are areas of wetland which discharge toward the nearby

floodplain. However, since the elevation above the river is too great for water in the area

to be derived from riverine flooding, it is apparent that the flows are from Mbulwana Hill to

the east. The drainage from the higher areas is largely in discrete channels but on the

lower slopes the system becomes very diffuse in its lower areas and, as with the floodplain,

much of it has been cultivated in the past. Recent human activities have greatly

transformed the area but it was probably originally an unchannelled toeslope seepage

system. However, it is now partially channelised, either as a consequence of soil erosion

gullies, or as a result of deliberate drain excavation.

Photograph 12. Site 15.

Drainage ditch/channel alongside

Road P325. No markers were

seen but the pipeline is thought to

be just to the right of the ditch.

Crossing Details: No pipeline markers were found but, since no impacts which could be

considered to have arisen from the pipeline were seen, it is taken that conditions are

conducive to problem-free construction.

• Site 16.

Position: 28° 34' 4.9” S. 29° 50’ 7.2” E

Description: From Site 15 the pipeline route runs up the hill and parallel to the road. At

Site 16 it must pass through a broad (± 250 m) drainage line which consists of multiple

small channels and gullies. The largest of these is at the point indicated but others emerge

from the nearby housing area and from the open space to the north of the primary channel.

This drainage line flows down to the Pound Spruit. At the crossing site much of the surface

is open and it is clear that soil erosion is taking place. The substrate of the system is

generally fine silts and gravels which overlie shales and mudstones.

Crossing Details: The existing pipeline route is clearly indicated by markers and by valve

chambers. The route of the proposed new line lies very close to the existing line and so it

is assumed that the same servitude will be used. There are no indications of any erosion

or other damage which may have resulted from the existing line and so it is clear that

construction can be done in an impact-free manner.

Terratest (Pty) Ltd

-20-

Photograph 13. Site 16. View

along the pipeline route at Site 16.

Two markers and a valve chamber

are visible. Water leaking from the

chamber is supporting a small

hygrophilous plant community.

The primary channels flows under

the bridge which is visible.

• Site 17.

Position: 28° 33' 52.2” S. 29° 50’ 11.7” E

Description: The drainage line which is crossed at Site 17 is a further tributary of the Pound

Spruit. The primary channel is crossed by means of a pipe bridge but secondary channels

to the north near some houses result in the whole crossing being some 350 m wide. As

with Site 16, vegetation is sparse and the bare soils are being eroded.

Crossing Details: The route of the new pipeline is shown as being exactly along that of the

old line. This implies that the pipe bridge will be used again and so there will be no new

impacts arising out of the construction process.

Photograph 14. Site 17. Pipe

bridge at Site 17. The sparse

vegetation and some bare soil

areas are shown.

• Sites 18a to 18d.

Description: Over a distance of approximately 650 m along Road P32 the pipeline route

traverses four minor drainage lines which are no more than local dongas. These are all

very small and, as they have not been impacted upon in any way by the existing line, are

further ignored.

Following on from the Site 18 points, the pipeline route encounters no further stream or

wetland crossings.

Terratest (Pty) Ltd

-21-

4.2.3 Proposed Alternative Pipeline Route Crossings

It appears that sections of the proposed new pipeline route will pass through wetlands that

could be avoided. Since this situation is undesirable from an environmental perspective, some

small re-alignment alternatives are suggested below. See Figure 4 for detail of the proposed

alternative pipeline route. it is to be noted that this proposal is conceptual only and that the

position of the line could be easily shifted.

Figure 4. Detail of the proposed alternative route for the new pipeline in the vicinity of the

Klip River.

• Site 8c.

Position: 28° 35' 50.2” S. 29° 49’ 4.5” E

Description: This site is on a part of the same drainage line as are Sites 8b and 8c and is

similar to them.

Terratest (Pty) Ltd

-22-

Crossing Details: Based on the observations made at Site 8, it appears that a pipeline

buried below the channel bed would have no impact on the system in the medium to long

term.

From this site, the alternative route would proceed directly to Site 10. In doing so it would

pass through an area that does not include the wetland system that is present at Site 9.

Instead it would pass through an area of scrubby woody vegetation and grassland. Then

from Site 10 the route would continue on a line close to the cemetery boundary and, at the

corner post, would swing across to use the same crossing point, at or near Site 11, as the

given new line alignment.

• Site 19.

Position: 28° 35' 27.4” S. 29° 49’ 21.2” E

Description: Some 80 m to `100 m after crossing the Klip River the alternative route would

turn eastwards and continue for some 150 m before turning north again to join the given

new alignment at Site 20.

The purpose of this detour would be to route the line around the large wetland area

associated with Site 12. It is recognised that the wetland will largely dry out if the present

pipeline is decommissioned but there is some evidence that the area was a wet patch prior

to 2010 which is when the spread of the new wetland is first apparent in Google Earth

images. If this was in fact the case, then the alternative route suggested here will avoid a

wet area that is likely to persist in the future.

5 CONSIDERATION OF RISK LEVELS AS PER THE DEPARTMENT OF WATER

AND SANITATION MODEL

The Department of Water and Sanitation risk assessment model was applied to each of the

seven crossing sites and the results are indicated in Table 3 below.

The table suggests that the risk of impacts on the crossing sites, with the exception of Site 11

is “Low”. The risk at Site11 is rated as being “Medium” for the following reasons:

• The Klip River is a large perennial river and has the capacity to carry contaminated

water further than does a small stream or a wetland which has diffuse flow.

• Because the river is larger than any other in the study area, any long term instream

impacts will be difficult to determine.

• Impacts at the site could easily spread and affect a larger area.

Table 3. Risk assessment criteria at crossing sites. Scoring based on both the desktop study

findings and the field survey.

Crossing

Site

Impact Risk

Rating Severity Consequence Likelihood Significance

1 1 4 8 32 L

Terratest (Pty) Ltd

-23-

2 1.25 4.25 8 34 L

3 1 4 8 32 L

4 1 4 8 32 L

5 1 4 8 32 L

6 1 4 8 32 L

7 1 4 8 32 L

8 1 4 8 32 L

9 1.25 4 8 34 L

10 1 4 8 32 L

11 1.75 6.75 10 67.5 M

12 1.5 5.5 8 44 L

13 1 4 8 32 L

14 1 4 8 32 L

15 1 4 8 32 L

16 1 4 8 32 L

17 1 4 8 32 L

18 1 4 4 16 L

19 1 4 8 32 L

20 1 4 8 32 L

The table suggests that the risk of impacts on the crossing sites, with the exception of Site 11

is “Low”. The risk rating at Site11 is rated as being “Medium” for the following reasons:

• The Klip River is a large perennial river and has the capacity to carry contaminated

water further than does a small stream or a wetland which has diffuse flow.

• Because the river is larger than any other in the study area, any long term instream

impacts will be difficult to determine.

• Impacts at the site could easily spread and affect a larger area.

6 CONSIDERATION OF THE PRESENT ECOLOGICAL STATE OF THE LARGER

WETLANDS IN THE VICINITY OF THE PROPOSED PIPELINE ROUTE

As indicated in Section 3 above, only that section of the floodplain around the pipeline route

was subject to actual WET-Health modelling. The area considered was 55 ha in extent and

the following assumptions were made:

• Inundation of the floodplain as a result of flooding by the Klip River has been very

severely curtailed as a consequence of the Windsor Dam and the Qedusizi Dam Flood

Retention Wall.

• In the past, almost the entire selected area was subject to cultivation but now most has

been abandoned.

• Canalisation of floodplain flows is negligible. The presence of the Mandela Drive

drainage canal is recognised but the greater part of the flow through it is derived from

Terratest (Pty) Ltd

-24-

the hinterland. It does, however, contribute to reduction of lateral inputs and also to

some limited drying of the floodplain in its vicinity. The latter impact is likely to have

been reduced as the soils in that area are clay-rich and so will be relatively

impermeable.

• Invasion by alien weed species is minimal.

• Grazing by livestock keeps the grass sward lower than might otherwise be the case

and so water losses by surface evaporation are likely to be slightly enhanced.

The outputs from the assessments are split into three categories which are Hydrology,

Geomorphology, and Vegetation and are shown in Table 4. The categories are derived from

Table 3.

The wetland at Site 2 was assessed on the basis of professional experience and was scored

as shown in Table 4. The following assumptions were made:

• The wetland in its natural state would be classified as an unchannelled hillslope seep.

• The hydrology in the system has been adversely affected by both a dam and by erosion

of the stream channel banks at its base.

• There are now erosion gullies within the wetland.

• Parts of the area have been cultivated.

• Much of the original vegetation has been replaced by grasses which are encouraged

by regular veld burning.

The wetland at Site 15 was assessed on the basis of professional experience and was scored

as shown in Table 4. The following assumptions were made:

• The wetland in its natural state would be classified as an unchannelled hillslope seep.

• The hydrology in the system has been adversely affected by residential development

and a school.

• There are now erosion gullies within the wetland.

• Parts of the area have been cultivated.

• Much of the original vegetation has been replaced by grasses which are encouraged

by regular veld burning.

Table 4. WET-Health scores for the three larger wetland systems.

Floodplain Crossing Site 2

Wetland Area

Crossing Site 15

Wetland Area

Score PES

Category PES Category PES Category

Area modelled (ha) 55 n/a n/a n/a

Hydrology 10.0 F C D

Terratest (Pty) Ltd

-25-

Geomorphology 9.0 F E E

Vegetation 3.8 C D D

Mean Score 7.6 n/a

n/a n/a

Health Class E D D

The systems are regarded as being stable over the next five years and no change in the

trajectory of change is anticipated.

The modelling process suggests that the primary driver of the condition of the primary wetland

in the study area is reduction inundation of the floodplain as a result of the two named dams.

The past agriculture and consequent loss of indigenous vegetation were found to have a far

lesser effect on the score. The poor condition of the site, together with the observation that

the present pipeline has had virtually no impacts on the system other than to make it wetter

as a result of leakage, suggest that the new pipeline should also have very few impacts if

construction is done with due care.

NOTE: The best developed wetland patch in the area modelled exists primarily as a result of

water leakage. Presumably the water losses will cease with the new pipeline and so the wet

area will largely dry out. As the site supports a Red Data listed bird species (Grey Crowned

Crane Balearica regulorum) the change may be regarded as a negative impact on biodiversity.

7 CONSIDERATION OF POTENTIAL IMPACTS ON THE WETLANDS AS A

CONSEQUENCE OF THE PROPOSED PIPELINE UPGRADES AND

COSTRUCTION

Since there are already pipelines in the ground along all of the study area routes it is possible to consider the long term consequences of the previous construction operations by using the existing conditions as a guideline. In no instance was it possible to find impacts on wetland or stream crossings, or elsewhere, which could be attributed to the pipelines. Thus it is possible to state that, if the new construction work is done correctly, the impacts that will arise as a consequence of the proposed upgrades are likely to be minor or even negligible. As a part of the impact assessment process, attention was given to the scores derived in the risk rating model (Section 7 above). However, since the term “Risk” is not precisely defined it was unclear as to where to apply it in the more conventional impact assessment framework. Finally it was determined that it would be most useful to align it with the “Significance” assessment since a risk which is rated as “High” may logically be assumed to be “Significant”.

7.1 Impacts on Stream and Wetland Crossings

The key issue at the stream and wetland crossing sites is the need to undertake excavations within the various watercourses. The foreseen potential impacts associated with such work are as follows:

• Deposition of soil or other sediment into the watercourse where it will be washed

downstream into either wetlands or the Klip River.

• Possible damage to the riparian surrounds.

Terratest (Pty) Ltd

-26-

• Possible spillage of wet cement/concrete into the watercourse.

• Deposition of solid waste such as plastics, scrap metal and the like into the

watercourse.

These impacts are assessed as shown in Table 5.

Table 5. Assessment of potential impacts at stream and wetland crossing sites. Refer to

Appendix I for definitions of the terms used.

Assessment parameter Extent

CERTAINTY Moderate to High

PROBABILITY Highly Probable

IMPACT Moderate

SIGNIFICANCE Moderate to High

SPATIAL EXTENT Site to Local

TIME PERIOD Construction Phase to

Short Term

EFFECT Negative

NEED FOR MITIGATION High

LOCALITY OF

MITIGATION On Site

Such impacts would be unacceptable without mitigation. Therefore, in order to minimise

(mitigate) the impacts the following recommendations are put forward:

• Prior to the start of operations the contractor must produce a method statement

indicating how the construction process will be undertaken. Most important in this

statement will be consideration of the impacts on the watercourse crossings and the

associated mitigation measures.

• The construction camp(s) may not be sited within 100 m of a wetland.

• Ideally, the construction work should be done in the dry season when plants are

senescent and stream flows are at their lowest.

• If concrete or cement are to be mixed at the site then it must be done in a place where

no uncured product can flow into a watercourse in an uncontrolled manner.

• Precautions are to be taken in regard to spillage of any hydrocarbon (fuels, oils,

greases) on the site. Care must be taken in their use but spill clean-up facilities must

also be on hand at all times.

• The watercourses and their surrounds must be protected against inputs of soil or other

sediment through proper use of stormwater management structures along the pipeline

route.

• Where sections of pipe are to be decommissioned they should be left in the ground

unless the new pipe will be laid in the same place. The reason for this recommendation

is that of avoiding opening unnecessary second trenches through the crossing areas.

Terratest (Pty) Ltd

-27-

• At the end of the construction phase, the entire pipeline servitude, including the various

working areas, must be fully revegetated to match the pre-construction condition.

• The site must be kept clear of alien weeds species until such time as the area is fully

covered with a viable sward of grasses and other indigenous vegetation.

• A monitoring programme must be set up to keep a check on the condition of the site

for at least two years after the completion of construction. During this time all sites

should be checked at least twice per annum. Any observed impacts from the operation

must be corrected with immediate effect. Responsibility for the monitoring and the

follow-up operations must lie with the pipeline operator who may appoint a contractor

to do the work.

• All conditions and requirements of the project Environmental Management Plan (EMP)

must be adhered to.

If the mitigatory measures are adhered to then the impacts will be reduced as indicated in

Table 6.

Table 6. Assessment of potential impacts at stream and wetland crossing sites.

Assessment parameter Extent

CERTAINTY Moderate to High

PROBABILITY Highly Probable

IMPACT No Impact to Low

SIGNIFICANCE Low

SPATIAL EXTENT Site to Local

TIME PERIOD Construction Phase

EFFECT Negative

NEED FOR MITIGATION n/a

LOCALITY OF

MITIGATION n/a

7.2 Impacts at the Klip River and Floodplain Crossing Sites

The Klip River and its associated floodplain areas on both banks must be regarded as being

of especial environmental sensitivity. The reasons for this are for both the intrinsic values of

any river and floodplain, and for the fact that impacts there could potentially expand and affect

extensive downstream areas. The following impacts may be anticipated:

• Loss of biodiversity at the site, particularly through allowing the establishment of alien

plant species.

• Deposition of soil or other sediment into the system from where it will be washed

downstream.

• Possible damage to the riparian surrounds.

• Risk of initiating erosion gullies which could spread into the floodplain.

• Possible spillage of wet cement/concrete into the watercourse.

Terratest (Pty) Ltd

-28-

• Deposition of solid waste such as plastics, scrap metal and the like into the

watercourse.

These impacts are assessed as shown in Table 7.

Table 7. Assessment of potential impacts at Crossing Site 5. Refer to Appendix I for definitions

of the terms used.

Assessment parameter Extent

CERTAINTY Moderate to High

PROBABILITY Highly Probable

IMPACT High

SIGNIFICANCE High to very High

SPATIAL EXTENT Site to Regional

TIME PERIOD Construction Phase to

Long Term

EFFECT Negative

NEED FOR MITIGATION Obligatory

LOCALITY OF MITIGATION On Site

• Prior to the start of operations the contractor must produce a method statement

indicating how the construction process will be undertaken. Most important in this

statement will be consideration of the impacts on the river and the associated

mitigation measures that will be used.

• It is recommended that the bulk of the construction work at this site be done in the

winter season when the risk of flooding is at its lowest.

• The working servitude is to be kept as small as possible. It is recommended that an

appropriate specialist demarcate the working area and that an exclusion fence be set

up so as to contain the operations.

• Precautions are to be taken in regard to spillage of any hydrocarbon (fuels, oils,

greases) on the site. Care must be taken in their use but spill cleanup facilities must

also be on hand at all times.

• The river must be protected against inputs of soil or other sediment through proper use

of stormwater management structures.

• The section of pipeline which is to be decommissioned must be left in the ground so

as to minimise the extent of excavations in the area.

• Especial care must be taken in regard to the stability of the river banks once the

pipeline has been installed. It is strongly recommended that the rehabilitation

measures be undertaken with emphasis on the use of plants to protect the river bank.

Hard structures such as gabions and mattresses should be avoided if possible since

they may well lead to bank erosion in the long term.

• At the end of the construction phase, the site must be fully revegetated to match the

pre-construction condition.

Terratest (Pty) Ltd

-29-

• The site must be kept clear of alien weeds species until such time as the area is fully

covered with a viable sward of grasses and other indigenous vegetation.

• A monitoring programme must be set up to keep a check on the condition of the site

for at least two years after the completion of construction. During this time the sites

should be checked at least three times per annum. Any observed impacts from the

operation must be corrected with immediate effect. Responsibility for the monitoring

and the follow-up operations must lie with the pipeline operator who may appoint a

contractor to do the work.

• All conditions and requirements of the project Environmental Management Plan (EMP)

must be adhered to.

If the mitigatory measures are adhered to then the impacts will be reduced as indicated in

Table 8.

Table 8. Assessment of potential impacts at Crossing Site 5. Refer to Appendix I for definitions

of the terms used.

Assessment parameter Extent

CERTAINTY Moderate to High

PROBABILITY Highly Probable

IMPACT No Impact to Low

SIGNIFICANCE Low

SPATIAL EXTENT Site

TIME PERIOD Construction Phase to

Short Term

EFFECT Negative

NEED FOR MITIGATION n/a

LOCALITY OF MITIGATION n/a

8 SUMMARY

This study on the stream and wetland crossings along the designated pipeline routes has

found no potential impacts that could be considered to be fatal flaws. Despite this, there is

substantial environmental sensitivity, with the watercourses and their surrounds being the

primary features of concern. The potential impacts on the systems have been assessed. Key

concerns include damage to the wetland and riparian vegetation, and to the deposition of

sediment and waste materials into the systems. It will be possible to mitigate against the

impacts and recommendations in this regard have been put forward. In order to assist the

future contractor(s), some distinction has been made between the smaller systems and the

Klip River and floodplain, and each is dealt with according to its characteristics. If the

recommendations are adhered to then the road upgrade project should have no long lasting

effects at all.

9 REFERENCES

Terratest (Pty) Ltd

-30-

MACFARLANE, D.M., KOTZE, D.C., ELLERY, W.N., WALTERS, D., KOOPMAN, V.,

GOODMAN, P., and GOGE, C. 2008. WET-Health: A technique for rapidly assessing wetland

health. WRC Report TT 340/08. Water Research Commission. Gezina.

MUCINA, L. & RUTHERFORD, M.C. (eds) 2006. The vegetation of South Africa, Lesotho and

Swaziland. Strelitzia 19. South African National Biodiversity Institute, Pretoria.

Terratest (Pty) Ltd

-31-

APPENDIX I: DEFINITION OF TERMS USED IN IMPACT ASSESSMENT

Terratest (Pty) Ltd

-32-

Assessment

Consideration Description

CERTAINTY

This criterion applies to the confidence of the assessor in making the assessment.

Low. The present degree of confidence in the relevant statement is less than 40%.

Moderate. The present degree of confidence in the relevant statement is between 40% and 80%.

High. The present degree of confidence in the relevant statement is greater than 80%.

PROBABILITY

This criterion applies to the likelihood of the anticipated impact actually happening. It may also be used in assessing the likelihood of success of a mitigatory action. Unlikely. The probability of the anticipated impact happening is low (Less than 20% probable).

Probable. The probability of the anticipated impact happening is moderate (20% - 60% probable).

Highly Probable. The probability of the anticipated impact happening is great. (60% - 99% probable).

Definite.

It is definite that the impact will take place.

IMPACT

This criterion refers to the impact in relation to its effect on a (stipulated) feature.

No Impact. There will be no discernible impact on the feature or issue under consideration.

Low. The impact on the feature or issue under consideration will be limited in terms of effect or in time.

Moderate. The impact on the feature will be such that there will be some damage done but that the feature will not be totally destroyed and that it will recover if the cause of the impact is removed.

High. The impact on the feature is such that the damage done will be considerable and enduring. Recovery from the impact could, at best, be only partial.

Very High. The impact on the feature is such that the feature will be totally destroyed and that no recovery is possible.

Unknown.

Terratest (Pty) Ltd

-33-

The nature of the impact on the feature is not understood or cannot be predicted in any reliable fashion.

SIGNIFICANCE

This criterion refers to the effect of the impact "in the larger scheme of things". EG: If a proposed dam will inundate a particular patch of vegetation then the impact on that patch of vegetation is very high as it will be totally destroyed but, if the vegetation is of a common type which has low conservation priority, then the significance of the impact is reduced.

No Significance. The impact is so inconsequential that it is of no significance at all.

Low. The impact is of low intensity or consequence. It is probably Local in effect.

Moderate. The impact is of sufficient intensity to warrant concern. There will be considerable disturbance to either the natural biota and/or to humans. Ecological processes will be only slightly affected. The impact may be apparent for some time.

High. The impact is of considerable intensity. There will be severe degradation of the environment and localised losses of entire plant and animal assemblages may occur. Ecological processes are strongly disrupted. Social impacts may be severe. Recovery will only be possible in the Long Term.

Very High. The impact is of potentially devastating intensity to both the natural environment and/or to human residents of the area. There will be total or near-total failure of ecological processes. It is unlikely that mitigation is possible in any reasonable human time scale and hence that full recovery from the impact may not be possible in any reasonable human time scale. Thus the impact must be regarded as being Permanent.

Unknown. The consequences of the impact are not understood or cannot be predicted in any reliable fashion. Probably the precautionary principle should be applied.

LEVELS OF

SPATIAL EXTENT

This criterion refers to the space within which the impact will be of consequence.

Site Level. The physical impacts of the development will not extend beyond the immediate development site. If relevant, visual impacts will only be apparent to viewers on or close to, the site.

Local Level. The impacts of the development will only be felt or be significant at the site of the development or within a short distance (roughly 500 m) of it. In the case of visual impacts the distance may be increased to about 2 kilometres but is restricted to a narrow viewscape.

Regional Level. The impacts of the development may be felt or be significant at a distance which is well removed from the site. In the case of visual impacts the viewscape may be increased to landscape width and breadth.

Terratest (Pty) Ltd

-34-

Provincial Level. The impacts of the development are sufficient so as to be significant throughout the province.

National Level. The impacts of the development are sufficient so as to be significant throughout the Republic of South Africa.

International Level. The impacts of the development are sufficient so as to be significant beyond the borders of the Republic of South Africa.

TIME PERIODS

This criterion refers to the length of time for which the impact may be apparent or in effect.

Construction phase. The time period during which geotechnical surveys and/or construction or other such work is done. Note: This phase will include all the time from the start of any geotechnical work that is done to the end of the construction period and includes any associated rehabilitation work that may be called for.

Operational phase. The time period for which the operation or development continues to function. This is of particular relevance for developments which have a very large footprint, such as timber plantations or urban expansion, or opencast mines which keep on expanding as they operate.

Short term. A period of time including the Construction Phase and up to two years further. Note: This time period is defined as it is considered that it covers the period in which the footprint of the construction operation will be sustainably revegetated and wildlife will return to the disturbed areas.

Medium term. A period of up to five years from the end of the Construction Phase. Note: This time period includes the criteria described for the Short Term but includes the time necessary for woody vegetation, if appropriate, to become established on the development area.

Long Term. A period of at least ten years, but possibly more, from the end of the Construction Phase or the Operational Phase. Note: This time period includes the criteria described for the Medium Term but includes the time necessary for trees to reach a "fair" size at which they will largely soften the appearance of the development.

Permanent. The change which would be brought about by the development cannot in any way be reversed in situ. The only mitigation options which may be available will be those which are conducted off site.

EFFECT This criterion refers to the nature of the change brought about by an impact.

Terratest (Pty) Ltd

-35-

Positive. The impact will have predominantly beneficial results or connotations.

Negative. The impact will have predominantly detrimental results or connotations.

Neutral. There will be a change but it cannot be described as being either particularly beneficial or particularly detrimental.

NEED FOR

MITIGATION

This criterion refers to the extent to which an anticipated impact will require that mitigatory action is taken.

Low. The need for mitigation is slight but the conditions demand that some effort be made.

Moderate. The need for mitigation is definite but there is not requirement for major and costly works. Any proposed mitigatory measure must have good potential to reduce the impact.

High. The need for mitigation is such that major and costly works are justifiable. Any proposed mitigatory measure must have definite and demonstrable potential for reduction of the impact before the proposed development may be given authorisation to proceed.

Obligatory. The nature of the impact is such that, unless mitigation can very largely nullify the consequences, it must be regarded as a potential fatal flaw which will halt the proposed development. If such mitigation cannot be achieved, it will be necessary to modify the development so that the impact will be reduced or even obviated.

LOCALITY OF

MITIGATION

This criterion refers to the place at which the stipulated mitigation must take place.

On Site. The necessary mitigation must be undertaken at the site of the impact.

Off Site. The necessary mitigation need not necessarily be at the site of the impact. Compensatory action may be undertaken at another, preferably similar, site on the property. Eg. Loss of a wetland due to construction of a dam may be mitigated by rehabilitation of a similar wetland in the immediate vicinity.