Pipeline Project News
Andrew Emhof Facilities Engineer, Interstate Marketing
National Fuel Gas Supply Corp.
Empire Pipeline, Inc.
PIOGA Technical Conference
August 23, 2016
National Fuel Gas Company
• 2.3 Tcfe Proved Reserves (1)
• 785,000 net acres in Marcellus Shale
• 3 million Bbls/year of crude oil
production in California
• $1.2 billion midstream investments
since 2010
• Coordinated infrastructure build-out
in Appalachia with NFG Upstream
• 740,000 Utility customer accounts
Upstream
Midstream
Downstream
(1) Total proved reserves are as of September 30, 2015. 2
Interstate Marketing Facilities Planning
What do we do?
• Determine capacity through existing facilities
• Meter stations
• Compressor stations
• Pipeline segments and systems
• Evaluate and design expansion projects to create incremental capacity
• Act as liaison between Engineering, Gas Control, and Operations
• Manage and maintain all capacity postings
3
2015 Expansion Projects
Westside
Expansion &
Modernization
West Side Expansion & Modernization
• Capacity: 175,000 Dth/d
• Market:
• Range Resources
• Seneca Resources
• Interconnects:
• Mercer (TGP Station 219)
• Holbrook (TETCO)
• Facilities:
• 3,550 HP of new compression
• 23.3 Miles of 24” replacement pipeline
• Placed into service: November 2015
Mercer
Holbrook
Delivery Point 5
2015 Expansion Projects
Northern Access 2015
• Capacity: 140,000 Dth/d
• Market:
• Lease of Capacity to TGP
• Interconnects:
• Niagara (TCPL)
• Facilities:
• 15,400 HP of compression at Hinsdale CS
• 7,700 HP of compression at Concord CS
• Various M&R facilities
• Placed into service: December 2015
Northern
Access
2015
Clermont
Niagara
(TCPL)
Delivery Point
7
Future Expansion Projects
Line D Expansion
• Capacity: 77,500 Dth/d
• Market:
• Increased On-System Demand
• Transportation Path: Lamont (TGP 300 Line) to Erie, PA region
• Facilities:
• 4,140 HP of compression at new Keelor CS
• Lamont M&R Upgrades and station modifications
• Satisfied FERC Prior Notice Blanket Requirements in February
• Targeted in-service: April 2017
Delivery Point
Line D
Expansion Erie
North East
Lamont
Warren
10
Line D Expansion: Project Milestones
• Fall 2014: Open season held
• 77,500 Dth/d of capacity subscribed
• December 21, 2015: Applied for FERC Prior Notice Blanket Certificate
• February 26, 2016: Received FERC approval
• Summer 2016: Commence initial construction activities
• Keelor CS site development
• Complete pipeline MAOP remediation work
• Early Fall 2016: Anticipate PADEP Air Permit
• Fall 2016-Winter 2017: Anticipate construction of mechanical facilities
• Installation of new compressors at Keelor CS
• Finish Bowen and Lamont upgrades
• Commission new facilities
• April 1, 2017: Projected in-service date
11
Future Expansion Projects
Northern Access
• Capacity:
• 497,000 Dth/d on NFGSC
• 350,000 Dth/d on Empire
• Market:
• Seneca Resources
• Transportation Path: Seneca’s Clermont production area to TGP 200 Line and Chippawa (TCPL)
• Facilities:
• 99.0 Miles of 16” and 24” pipeline
• New 22,214 HP Pendleton CS
• Enhanced 5,350 HP Porterville CS
• Dehydration facility
• Various M&R facilities
• Targeted in-service: November 2017
Delivery Point
Northern
Access
Chippawa
(TCPL)
Clermont
TGP 200
Line
13
Northern Access: Project Milestones
• Summer 2014: Open season held
• Capacity subscribed by foundation shipper
• Summer 2014-Winter 2015: Conducted environmental and engineering studies
• July 24, 2014: Began FERC Pre-filing process
• March 17, 2015: Submitted initial FERC 7(b)/7(c) applications
• Summer 2015-Winter 2016: Conduct right-of-way negotiations
• November 2, 2015: Submitted amended FERC 7(b)/7(c) applications
• Relocated Pendleton Compressor Station
• February 2016: Submitted NYS DEC 401 Water Quality Certification application
• July 27, 2016: Received FERC Environmental Assessment
• Late October 2016: Anticipate FERC certificate
• Early March 2017: Anticipate NYS Water Quality Certificate and air permits
• March 2017: Anticipate starting construction of facilities
• November 1, 2017: Projected in-service date
14
Northern Access: FERC Environmental Assessment
• EA Issued July 27, 2016
• Based on FERC’s analysis, the Northern Access project would have no significant environmental impact
• NFG and Empire have developed comprehensive construction plan in its 7(c) application
• 69% of total pipeline route co-located with existing facilities
• FERC Staff proposed 26 recommendations, including:
• Modifications to plan must be submitted to and approved by Director of Office of Energy Projects
• Constructed facilities shall be as shown in EA
• Must have at least one Environmental Inspector per construction spread
• Must develop environmental complaint resolution procedure
15
Potential Future Expansions
To Iroquois
Line N to
REX
IGT
Line N to
Rover/Nexus
Empire
North
Extension
To
TCPL
Supply
North
18
Potential Future Expansions
Empire North Expansion
• Open Season held Fall 2015
• Currently negotiating precedent agreements
Line N Expansion
• Replacement of remaining older-vintage pipeline, increasing System Maximum Operating Pressure
• Expand or develop new interconnections with other pipelines (Columbia, DTI, NEXUS, Rover, TETCO, TGP)
• Develop market-area delivery points
Production-related expansions
• Replacement/expansion of existing pipelines in Marcellus/Utica Shale fairway
• Development of new facilities for delivery to TGP, Transco, or Canada
Additional Capacity to TransCanada Pipeline
• Utilizing NFGSC corridors and facilities
19