pipeline design and construction

86
Pipeline Design & Construction Construction Step by Step

Upload: arnela-hodzic

Post on 01-Nov-2014

186 views

Category:

Documents


20 download

DESCRIPTION

Pipeline Design

TRANSCRIPT

Page 1: Pipeline Design and construction

Pipeline Design &ConstructionConstruction

Step by Step

Page 2: Pipeline Design and construction

195.401 Generalrequirements (Subpart F)

(c) Except as provided in 195.5, nooperator may operate any part of anyof the following pipelines unless it wasof the following pipelines unless it wasdesigned and constructed asrequired by this part: §195.5 Conversion

to service subject tothis part.

Page 3: Pipeline Design and construction

195.401 Generalrequirements (Subpart F)

(c)(1) An interstate pipeline, other thanlow-stress, on which construction waslow-stress, on which construction wasbegun after March 31, 1970, thattransports hazardous liquid.

Page 4: Pipeline Design and construction

195.401 Generalrequirements (Subpart F)

(2) An interstate offshore gatheringline, other than low-stress, on whichconstruction was begun after July 31,

(c)

construction was begun after July 31,1977, that transports hazardous liquid.

Page 5: Pipeline Design and construction

195.401 Generalrequirements (Subpart F)(c)(3) An intrastate pipeline, other thanlow-stress, on which construction wasbegun after October 20, 1985, thatbegun after October 20, 1985, thattransports hazardous liquid.

(4) A pipeline, on which constructionwas begun after July 11, 1991, thattransports carbon dioxide.

Page 6: Pipeline Design and construction

195.401 Generalrequirements (Subpart F)

(c)(5) A low-stress pipeline on whichconstruction was begun after August 10,1994.1994.

Page 7: Pipeline Design and construction

Pipelines from theWell to the Refinery and Market

Page 8: Pipeline Design and construction

Part 195Subpart C

DesignRequirements

Page 9: Pipeline Design and construction

195.100 Scope.

This subpart prescribes minimumdesign requirements for newpipeline systems constructed withsteel pipe and for relocating,steel pipe and for relocating,replacing, or otherwise changingexisting systems …

Page 10: Pipeline Design and construction

195.401 Generalrequirements.

(c) Except as provided in 195.5, nooperator may operate any part of anyof the following pipelines unless it was

§195.5 Conversionto service subject to

this part.

of the following pipelines unless it wasdesigned and constructed asrequired by this part:

Page 11: Pipeline Design and construction

195.401 Generalrequirements.

(c)(1) An interstate pipeline, other thanlow-stress, on which construction waslow-stress, on which construction wasbegun after March 31, 1970, thattransports hazardous liquid.

Page 12: Pipeline Design and construction

195.401 Generalrequirements.

(2) An interstate offshore gatheringline, other than low-stress, on whichconstruction was begun after July 31,

(c)

construction was begun after July 31,1977, that transports hazardous liquid.

Page 13: Pipeline Design and construction

195.401 Generalrequirements.(c)(3) An intrastate pipeline, other thanlow-stress, on which construction wasbegun after October 20, 1985, thatbegun after October 20, 1985, thattransports hazardous liquid.

(4) A pipeline, on which constructionwas begun after July 11, 1991, thattransports carbon dioxide.

Page 14: Pipeline Design and construction

195.401 Generalrequirements.

(c)(5) A low-stress pipeline on whichconstruction was begun after August 10,1994.1994.

Page 15: Pipeline Design and construction

195.106 Internal designpressure.

P = (2 St/OD)* x E x F

* 2 St/O.D. Used to determine low stress

E = seam joint factorF = design factor

Page 16: Pipeline Design and construction

Part 195Subpart D

Construction

Page 17: Pipeline Design and construction

Pipeline Construction Sequence

Page 18: Pipeline Design and construction

195.200 Scope.

This subpart prescribes minimumrequirements for constructing newpipeline systems constructed withsteel pipe and for relocating,steel pipe and for relocating,replacing, or otherwise changingexisting systems …

Page 19: Pipeline Design and construction

Pipeline Construction

1. Surveying. The right-of-way isa narrow strip of land thatcontains the pipeline(s) and iswhere all onsite constructionactivities occur. After a planned orproposed route is determined, it isproposed route is determined, it issurveyed to determine theparameters that will be needed tocomplete the project.

§195.210 Pipeline location.

Page 20: Pipeline Design and construction

195.210 Pipeline location.

ROW must be selected to avoid,as far as practicable:areas containing private dwellingsindustrial buildingsindustrial buildingsplaces of public

assembly

Page 21: Pipeline Design and construction

195.210 Pipeline location.

Pipeline may not be locatedwithin 50 feet of any:private dwellingindustrial buildingindustrial buildingplaces of public assembly

unless 12” of cover is added.

Page 22: Pipeline Design and construction

Pipeline Construction

1. Maps & Materials.Once the pipeline issurveyed, ROW ispurchased, alignmentsheets (maps) are drawnsheets (maps) are drawnand material lists aregenerated.

§195.202 Compliance with specifications orstandards.

§195.206 Material inspection.

Page 23: Pipeline Design and construction

195.202 Compliance withspecifications or standards.

Each pipeline system must be constructed inaccordance with comprehensive writtenspecifications or standards that are consistentspecifications or standards that are consistentwith the requirementsof this part.

Page 24: Pipeline Design and construction

195.206 Materialinspection.

No pipe or other componentmay be installed unless ithas been visually inspected atsite.site.

Page 25: Pipeline Design and construction

Pipeline Construction

2. Clearing & Grubbing.The ROW is cleared ofbrush and trees, andleveled to give workersand equipment access toand equipment access tobuild, inspect andmaintain the pipeline.

Page 26: Pipeline Design and construction

Track-Type Tractor or Dozer

Page 27: Pipeline Design and construction

195.204 Inspection - general.Inspection must be provided to

ensure the installation of pipe orpipeline systems in accordancewith the requirements of thiswith the requirements of thissubpart.

Page 28: Pipeline Design and construction

195.204 Inspection - general.No person may be used to

perform inspections unless thatperson has been trained and isqualified in the phase ofqualified in the phase ofconstruction to be inspected.

Page 29: Pipeline Design and construction

Pipeline Construction

3. Right-of-way preparation. Theright-of-way will be graded, andpads may be built to allow for themovement of ditchers, additionalequipment, materials and otherpipeline construction activities.pipeline construction activities.

Page 30: Pipeline Design and construction

Pipeline Construction

4. Hauling and stringing thepipe. Lengths of pipe are movedfrom stockpile sites to the right-of-way. They are lined up along theright-of-way, ready for welding.right-of-way, ready for welding.

Page 31: Pipeline Design and construction

Stringing

Stringing is the delivery and distribution of linepipe where it is needed on the right-of-way andwhen it is needed

Page 32: Pipeline Design and construction

Pipeline Construction5. Bending the pipe. A pipeline mustcross over hills and curve aroundspecial places such as lakes andsacred sites. A specialized pipe-bending machine is used to bendsome pipe to the shape of the land.some pipe to the shape of the land.The pipe retains its strength andremains circular where it is bentbecause of the characteristics of steeland the bending techniques used.

Page 33: Pipeline Design and construction

Bending

Page 34: Pipeline Design and construction

Hydraulic Pipe BendingMachines

PneumaticBendingMandrel

Page 35: Pipeline Design and construction

Bent to Fit

The pipe must be bent to reflect the generalcontours of the right-of-way.

Page 36: Pipeline Design and construction

195.212 Bending of pipe.

Pipe may not have a wrinkle bend. Each field bend must comply withthe following:

Page 37: Pipeline Design and construction

195.212 Bending of pipe.

not impair serviceability have a smooth contour pipe with longitudinal weld, must bein neutral axis unless--in neutral axis unless--made with internalmandrel

pipe is <12” or hasdiameter to w.t. ratio<70

Page 38: Pipeline Design and construction

Pipeline Construction

6. Welding. A technique whereanother metal is melted and usedto join lengths of pipe. Automaticwelding machines are used wherepossible and some hand weldingalso takes place. A rigorous qualityalso takes place. A rigorous qualityassurance and quality controlprogram is followed to ensure thestrength and quality of the welding.

Page 39: Pipeline Design and construction

Welding

Page 40: Pipeline Design and construction

External Line-upClampsBeveling

Machine

PneumaticInternal

Lineup Clamp

Page 41: Pipeline Design and construction

Automatic External Welder

Page 42: Pipeline Design and construction

Automatic Internal Welder

Page 43: Pipeline Design and construction

Pipe Facing Machine

Page 44: Pipeline Design and construction

Welding Truck Rig

Page 45: Pipeline Design and construction

Welder Tractor

Page 46: Pipeline Design and construction

The Pipe Gang

The workers responsible forpositioning the pipe, aligning it, andmaking the initial welds.

Page 47: Pipeline Design and construction

Firing Line

The workers responsible for the filler pass and thecap bead, which complete the joint

Page 48: Pipeline Design and construction

195.208 Welding ofsupports and braces.

May NOT be welded to pipe whichoperates over 100 psig.

Page 49: Pipeline Design and construction

Good Weld?

Page 50: Pipeline Design and construction

Radiography

195.234 Welds:Nondestructive testing.

Page 51: Pipeline Design and construction

Field Joint Coating

195.561 Whenmust I inspect pipecoating used for

Mill coated pipe has a cutback of 6-9 inches at theend of the pipe to not interfere with welding. Thiscutback must be coated once the weld is complete.

195.557 Whichpipelines must

coating used forexternal corrosioncontrol?195.581 Whichpipelines must Iprotect againstatmosphericcorrosion and whatcoating materialmay I use?

pipelines musthave coating forexternal corrosioncontrol?195.559 Whatcoating materialmay I use forexternal corrosioncontrol?

Page 52: Pipeline Design and construction

Pipeline Construction

7. Digging the trench. The waythe trench or ditch is dug, andwhat equipment is used,depends mainly on the type ofsoil. Alternates include bucketsoil. Alternates include bucketwheel trenchers. Other diggingequipment will includebackhoes or trackhoes

195.246 Installation of pipe in a ditch.195.248 Cover over buried pipeline.195.250 Clearance between pipe andunderground structures.

Page 53: Pipeline Design and construction

Hydraulic Excavator orTrackhoe

Page 54: Pipeline Design and construction

Backhoe or Rubber-Tired Hoe

Page 55: Pipeline Design and construction

Trencher or Ditching Machine

Page 56: Pipeline Design and construction

Ditching or Trenching

Page 57: Pipeline Design and construction

First Rule of Holes:

When you’re in one . . . STOPDIGGING!!!

Page 58: Pipeline Design and construction

Trench Boxes

Page 59: Pipeline Design and construction

TAPSTrans-Alaska Pipeline System

In thiscase the

pipeline isnot

loweredin-It’s

Supported aboveground by vertical support members

loweredup!

Page 60: Pipeline Design and construction

Pipeline Construction

8. Lowering the pipe.Tractors with special arms calledsidebooms are used to lower the pipeinto the trench. Care is taken to avoiddamaging the pipe and its exteriordamaging the pipe and its exteriorcoating.

Page 61: Pipeline Design and construction

Pipeline Construction

8. Lowering the pipe.Different tools are used to helpfacilitate the lowering in process.These include slings, rollers, cradlesand pipe tongs. As the pipe isand pipe tongs. As the pipe islowered in, a holiday detector or“jeep” is used to locate voids in thecoating.

Page 62: Pipeline Design and construction

Pipelayer or Sideboom

Page 63: Pipeline Design and construction

Lowering In

195.246 Installation of pipe in a ditch.195.248 Cover over buried pipeline.195.250 Clearance between pipe andunderground structures.

Page 64: Pipeline Design and construction

Fabrication

9. Installing valves and specialfittings. Valves and otherconnections are part of a pipeline.These assemblies are installed asthe pipeline is constructed. Theythe pipeline is constructed. Theyinclude shut-off valves that canblock off sections of the pipelinefor maintenance.

195.254 Aboveground components.195.256 Crossing of railroads and highways.195.258 Valves: General.195.260 Valves: Location.

Page 65: Pipeline Design and construction

Pipeline Construction

10. Crossings. A pipeline will needto cross rivers and streams, roads,railroads and other pipelines. Plansare developed in advance. Watercrossings can be completed either by"open cut" techniques or by horizontal"open cut" techniques or by horizontaldirectional drilling.

Page 66: Pipeline Design and construction

Pipeline Construction

10. Crossings. (CONTINUED)The selection of a crossing methoddepends upon site specific criteriasuch as fish habitat, water flow, andsoil conditions such as rocks and boulders. Generally,horizontal directional drilling is selected for major riverhorizontal directional drilling is selected for major rivercrossings where local soil conditions permit the technique.

195.256 Crossing of railroads and highways.

Page 67: Pipeline Design and construction

BoringMachine

DirectionalDrillingMachine

Page 68: Pipeline Design and construction

Horizontal Drilling Rig

Page 69: Pipeline Design and construction

Directional Drilling

Page 70: Pipeline Design and construction

Pipeline Construction

11. Backfilling the trench.Before testing the pipeline, theditch is backfilled. Sometimes theexcavated soil is used to fill thetrench and sometimes othertrench and sometimes otherselected backfill is used. Care istaken to protect the pipe coatingfrom potential damage.

195.252 Backfilling.

Page 71: Pipeline Design and construction

Backfilling

Page 72: Pipeline Design and construction

Track-Type Tractor orDozer

Padding Machine

Page 73: Pipeline Design and construction

Tie-In12. Tie-in. Collective term for the construction tasksbypassed by regular crews on pipeline construction. Tie-inincludes welding road and river crossing, valves, portions ofthe pipeline left disconnected for hydrostatic testing, andother fabrication assemblies, as well as taping and coatingthe welds.

Page 74: Pipeline Design and construction

Pipeline Construction

13. Testing. A variety of methodswill be used to ensure the integrity ofthe assembled pipeline and tocomply with code.

195.304 Test pressure.195.305 Testing of components.195.307 Pressure testing aboveground breakout tanks.195.306 Test medium.195.308 Testing of tie-ins.195.310 Records.

Page 75: Pipeline Design and construction

Pipeline Construction

14. Dewatering. If water is used asa test medium, dewatering of thepipeline is done with dewateringpigs. The water should bedisposed of in an environmentallydisposed of in an environmentallysensitive manner.

Page 76: Pipeline Design and construction

Pipeline Construction

15. Cleaning up. Thepipeline right-of-way andtemporary facilities such ascamps will be reclaimed.

Page 77: Pipeline Design and construction

The continuous growth of energy consumption and the difficultiesin establishing new ROW’s for transmission power lines and metalpipelines increase the tendency to site them along the sameroutes. Consequently, electromagnetic problems can arise.

Electromagnetic InteractionsBetween Power Transmission

Lines and Pipelines

•Electric shocks to people who contact the pipeline

•Damage to pipeline insulating coating, insulatingjoints and cathodic protection systems

Page 78: Pipeline Design and construction

The continuous growth of energy consumption and the difficultiesin establishing new ROW’s for transmission power lines and metalpipelines increase the tendency to site them along the sameroutes. Consequently, electromagnetic problems can arise.

Electromagnetic InteractionsBetween Power Transmission

Lines and Pipelines

Induced voltages can beproduced through capacitive,inductive and conductivecouplings with the power line

Intensity depends on the powerline, pipeline and soilcharacteristics… and geometricconfiguration between the powerline and the pipeline.

•Electric shocks to people who contact the pipeline

•Damage to pipeline insulating coating, insulatingjoints and cathodic protection systems

line and the pipeline.

Voltages can be produced undernormal operating conditions andduring short-circuit occurrencesat the power line

Page 79: Pipeline Design and construction

Electromagnetic InteractionsBetween Power Transmission

Lines and Pipelines

•Pipeline induced voltages should be compared to safety limitsestablished by industry codes.

•Underground sections of pipeline checked with respect to therisks of damage to pipeline coating.risks of damage to pipeline coating.

•Above-ground sections checked for risks of potential electricshocks to people.

•Voltage across insulating joints compared to the voltagewithstand capability.

•Cathodic protection systems checked for maximum voltages attheir connection to the pipeline.

Page 80: Pipeline Design and construction

Other Safety Considerations• When driving on the Right-of-Way - watch out for

HEAVY EQUIPMENT!

Page 81: Pipeline Design and construction

Other Safety Considerations

Wild animals are about in the woods – be careful!

Page 82: Pipeline Design and construction

Other Safety Considerations

• Overhead power lines and equipment-don’t be incontact with equipment or stand near (water, mudother conductors)

• Wear proper personal protective equipment• Beware of lengths of welded pipe on skids without• Beware of lengths of welded pipe on skids without

proper cribbing• Don’t stand near pipe being lifted from ground• Don’t stand near pipe truck being unloaded

– Note improperly chocked pipe

Page 83: Pipeline Design and construction

Other Safety Considerations

• Sideboom A-frames don’t fall up• Sidebooms can flip over when lifting pipe• Sidebooms can roll over backward on an incline• Be aware of worn cables or slings• Hydraulic hoses can break causing unintended• Hydraulic hoses can break causing unintended

equipment movement

Page 84: Pipeline Design and construction

Other Safety Considerations

• Be aware of trenching and shoring safety precautions– Don’t stand near the edge of an excavation– Don’t enter an unsafe excavation– Equipment vibrations can cause a cave-in

• Welding can cause a “flash”• Welding can cause a “flash”– Welding at night near glass can reflect the same

damaging radiation• Avoid touching the “tail” of the “jeep”

Page 85: Pipeline Design and construction

Pipeline Construction Sequence

Page 86: Pipeline Design and construction

• Construction spreads - what’s going on during construction:• Surveying, staking & pre-construction condition documentation• Environmental Mitigation• Relocation/replacement – precautions near/over live lines• Clearing, stumping, grubbing & grading• Stringing & bending• Welding & Coating• Trenching, double ditching/HDD & bores• Trenching, double ditching/HDD & bores• Road and stream x-ings (rip-rap, flume & trench, etc.,)• Lowering-in• Tie-ins• catheading• Coatings, corrosion & backfill• Hydro (pre & post testing), de-water, clean & dry• Purging• Commissioning• Hot taps & stopples• Final clean-up