pipeline activity.pdf

Upload: dndudc

Post on 06-Feb-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/21/2019 Pipeline Activity.pdf

    1/45

    PIPELINE ACTIVITIES

    BY

    TIRUPATI,INDIA

  • 7/21/2019 Pipeline Activity.pdf

    2/45

    pe ne :pe ne :

    TransportationTransportation ofof liquidsliquids andand gasesgases fromfrom oneone

    ..

  • 7/21/2019 Pipeline Activity.pdf

    3/45

    Survey

    Pipe line activity :

    Unloading & stocking of pipes at site

    Marking

    Trench excavation

    Blasting

    contd

  • 7/21/2019 Pipeline Activity.pdf

    4/45

    Sand bedding

    pe ower ng

    Laying, joining

    Back filling

    Sand encasing

    pec a s x ng

    contd

  • 7/21/2019 Pipeline Activity.pdf

    5/45

    Pedestals, thrust blocks & valve chambers

    Hydro testing

    Commissioning

    Final measurement

    Reconciliation

  • 7/21/2019 Pipeline Activity.pdf

    6/45

    TYPE OF PIPES

  • 7/21/2019 Pipeline Activity.pdf

    7/45

    Mild steel (MS)

    ass re n orcemen p as c

    Ductile iron DI

    Cast iron (CI)

    High density poly ethylene (HDPE)

    Poly vinyl chloride (PVC)

  • 7/21/2019 Pipeline Activity.pdf

    8/45

    Pre stressed concrete (PSC)

    Reinforcement cement concrete (RCC)

    Bar wra ed steel c linder (BWSC)

    Galvanized iron (GI)

    Low alloy pipe (LA)

  • 7/21/2019 Pipeline Activity.pdf

    9/45

    PVC pipe MS pipe GI pipe

  • 7/21/2019 Pipeline Activity.pdf

    10/45

    p pe p pe p pe

  • 7/21/2019 Pipeline Activity.pdf

    11/45

    TRENCH EXCAVATION

  • 7/21/2019 Pipeline Activity.pdf

    12/45

    Obtain work permit before starting excavation work.

    Marking is to be made

    Excavate trench up to required level with free working

    slopes for stability.

    1:1 clay, muram & boulders etc1:2 hard muram

    NOTE: Slope not requiredfor soft & hard rock

  • 7/21/2019 Pipeline Activity.pdf

    13/45

    TRANSPORTATIONRANSPORTATION

    OF

    MATERIAL TO SITE

  • 7/21/2019 Pipeline Activity.pdf

    14/45

    Pipes shall be transported to the site of laying and stacked

    avoid damage to the coating

    Suitable gap during pipe stacking should be left at proper

    intervals to permit access from one side to the other

  • 7/21/2019 Pipeline Activity.pdf

    15/45

    Each pipe & special should be properly stacked at

    cause any damage to their outer coating.

  • 7/21/2019 Pipeline Activity.pdf

    16/45

  • 7/21/2019 Pipeline Activity.pdf

    17/45

    PIPE HANDLING

  • 7/21/2019 Pipeline Activity.pdf

    18/45

    manual pipe handling :

    e ore an ng t e p pe,

    work men should wear

    1. Ro es used to lift the material must be in ood condition

    and it should not be let over sharp edges

    2. Ensure that the persons are moved away from the pit while

    placing the pipe (if it is heavy)

    3. while handling materials in the wet season, ensure that the

    materials are free from slush as it may cause slipping.

  • 7/21/2019 Pipeline Activity.pdf

    19/45

    Pipe handling by machinery

    Slings should be in good condition and free from defects,

    Ensure proper clamping of slings, these are provided on

    same direction on free len th

    Ensure ro er visibilit for the crane.

  • 7/21/2019 Pipeline Activity.pdf

    20/45

    C.I D.I PIPES

    LOWERING, LAYING JOINING

  • 7/21/2019 Pipeline Activity.pdf

    21/45

    Pipes should be lowered slowly in to the trench by means ofchain ulle block and tri od standor cranes or with thehelp of ropes.

    socket. Spigot end shall be lubricated with good quality of

    grease or oil, then the spigot shall be slipped into socket by.

    S i ot ends of all i es shall face u stream irres ective of

    the direction of water flow.

  • 7/21/2019 Pipeline Activity.pdf

    22/45

  • 7/21/2019 Pipeline Activity.pdf

    23/45

    GRP PIPESRP PIPES

    LOWERING, LAYING

    AND

    JOININGOINING

  • 7/21/2019 Pipeline Activity.pdf

    24/45

    Lowering and laying :

    pe s a e a n ry con t on an un er no c rcumstancesthey shall rest on sludgy bedding. Pipes shall rest continuously

    on the bottom of the trench.

    Clearance of approximately100mm in depth and width equal

    to engt o t e co ar p us mm on ot s es s a e

    provided at the joint which shall be refilled from sides after the

    oint is made.

    The pipe should be lowered in to the trenches either by pulley

    or by means of two ropes. For road crossing or river crossingthe pipe shall laid 2.0mtr. Below the bed level. The pipe

    should be encased with300mm thicksand.

  • 7/21/2019 Pipeline Activity.pdf

    25/45

    Joining :

    1. Spigot and socket and socket joint with double water tight

    ru er r ng gas e pac ng

    2. Double socket cou lin oint with water ti ht rubber rin

    gasket packing

    3. Flanged joint is used for connecting the valves, the flanged

    joint is made from the same materials as the pipe

    4. End pipes should not kept open, the ends shall be covered up

    either by suitable cap or plug or double layer of gunny bags.

  • 7/21/2019 Pipeline Activity.pdf

    26/45

    GRP joint with Spigot & socket end

  • 7/21/2019 Pipeline Activity.pdf

    27/45

    M.S PIPES

    LOWERING, LAYING, JOINING

    PAINTINGAINTING

  • 7/21/2019 Pipeline Activity.pdf

    28/45

    Before Laying, M.S pipes should be coated with cement or

    Paintin

    1. surface cleaning :

    The pipe should be cleaned before painting with special

    epoxy thinner. This avoids oil, Greece marks on the pipe.Due to these marks the paint wasn't sticking. Inside dust can

    .

    2. primary coating

    After surface cleaning, firstprimer coating is necessary. Forthis purpose zinc phosphate primer is combined withactivator in 6:1 ratio. Zinc phosphate primer is component a

    act vator s component , so

    primer = component a + component

  • 7/21/2019 Pipeline Activity.pdf

    29/45

    3. Out side coating :

    After primary coating, out side of pipe painted with

    epoxy coa tarw c s com ne w t act vator n 4:1

    ratio.

    4. Inside :

    Foo gra e epoxy used for inside painting resistscorrosion, this is the combination ofresin & cure in 1:1ratio.

  • 7/21/2019 Pipeline Activity.pdf

    30/45

    Lowering, laying and joining of MS pipes:Lowering, laying and joining of MS pipes:

    Before welding the pipe faces shall be cleaned by scrapingBefore welding the pipe faces shall be cleaned by scraping

    by wire brushesby wire brushes

    in lining and coatingin lining and coating

    e en s o p pes s a ave eve e en s or we nge en s o p pes s a ave eve e en s or we ng

  • 7/21/2019 Pipeline Activity.pdf

    31/45

    , ., .(Gap depends up on thickness) electrodes shall be conform(Gap depends up on thickness) electrodes shall be conform

    to is 814to is 814--1991 i.e, e1991 i.e, e--60136013

    MSMS pipespipes areare manufacturedmanufactured eithereither byby electroelectro resistanceresistanceweldinweldin or or submer edsubmer ed arcarc weldinweldin rocessrocess lon itudinalllon itudinall or or

    spirallyspirally weldedwelded

    . .

  • 7/21/2019 Pipeline Activity.pdf

    32/45

    What is metal arc welding :

    In metal arc welding a metal rod is used as oneelectrode during the welding operation this metal electrode ismelted by the heat of the arc and is fused with the base metal.

    Welding defects :1. Lack of penetration,

    2. Slag inclusion,

    3. Under cut,

    . oor us on,

    5. Porosity,

    . ,

    7. Spatter,

    8. Wra in & distortion.

  • 7/21/2019 Pipeline Activity.pdf

    33/45

    HDPE PIPE

    LAYING JOINING

  • 7/21/2019 Pipeline Activity.pdf

    34/45

    FusionFusion weldingwelding isis commonlycommonly usedused inin HDPEHDPE andand isis aa

    permanentpermanent typetype ofof jointjoint

    TheThe pipespipes shallshall bebe brushedbrushed throughthrough outout toto removeremove anyany soilsoildepositeddeposited oror stonestone theirtheir inin

    PipesPipes shallshall bebe laidlaid inin drydry conditioncondition andand under under nono

    circumstancescircumstances thethe shallshall restrest onon slushslush beddinbeddin

    ClearanceClearance ofof requiredrequired depthdepth && widthwidth onon bothboth sidessides shallshall

    ,,

    afterafter thethe jointjoint isis mademade

  • 7/21/2019 Pipeline Activity.pdf

    35/45

    ForFor roadroad crossingcrossing oror riverriver crossingcrossing thethe pipepipe shallshall bebe laidlaid 22

    PipePipe afterafter transportingtransporting toto thethe exactexact placeplace shouldshould bebe cutcut squaresquare

    byby thethe hacksawhacksaw bladeblade

    TThehe faceface ofof thethe i ei e should should bebe sli htlsli htl scra ed scra ed rior rior toto thethefusionfusion weldingwelding toto removeremove oxidizedoxidized layerlayer

    weldingwelding

  • 7/21/2019 Pipeline Activity.pdf

    36/45

    TheThe heatingheating mirrormirror // panpan shouldshould bebe heatedheated upup toto 200200 degdeg.. cc

    andand thethe surfacesurface ofof thethe panpan shouldshould bebe 210210 ++ oror 55 degdeg.. CC

    TheThe heatingheating panpan shouldshould bebe metallicmetallic plateplate whichwhich isis heatedheated upuptoto thethe re uiredre uired tem eraturetem erature eithereither bb electricalelectrical coilcoil embeddedembedded

    insideinside oror byby blowblow torchtorch

    thethe heatingheating mirrormirror // panpan withwith TeflonTeflon paperpaper onon eacheach sideside

    TheThe contactcontact pressurepressure ofof 00..22 kg/cmkg/cm22 inin eithereither sideside ifif thethe pipepipeshouldshould bebe maintainedmaintained

  • 7/21/2019 Pipeline Activity.pdf

    37/45

  • 7/21/2019 Pipeline Activity.pdf

    38/45

    InitialInitial heatingheating timetime forfor achievingachieving thethe moltenmolten rim,rim, variesvaries fromfrom

    11 toto 55 minmin dependingdepending onon thethe pipepipe wallwall thickthick && sizesize..

    Pi esPi es shouldshould bebe removedremoved fromfrom thethe heatinheatin mirrormirror // anan whenwhen

    thethe rimrim ofof thethe moltenmolten materialmaterial isis formedformed andand ensureensure thatthat thethe rimrimformationformation isis notnot excessiveexcessive..

    ImmediateImmediate jointjoint shouldshould bebe mademade byby thethe applicationapplication ofof

    moderatemoderate pressurepressure ofof approxapprox..11 toto 22 kg/cmkg/cm22 forfor 22 toto 33 secsec..

    whilewhile joining,joining, thethe pressurepressure shouldshould bebe maintainedmaintained untiluntil thethe

    ointoint isis lukeluke warmwarm..

    AfterAfter thethe pressurepressure isis relieved,relieved, thethe jointjoint shouldshould bebe allowedallowed toto

  • 7/21/2019 Pipeline Activity.pdf

    39/45

    BackBack fillfill withwith excavatedexcavated soilsoil shouldshould bebe freefree fromfrom

    c n ers,c n ers, as es,as es, s ag,s ag, re use,re use, ru s ,ru s , vege a evege a e or or organ corgan c

    metal,metal, lumpylumpy oror frozenfrozen metal,metal, bouldersboulders rocks,rocks, otherother materialsmaterialswhichwhich inin thethe opinionopinion ofof anyany authority,authority, isis deleteriousdeleterious..

    Concrete slabs over pipes :Concrete slabs over pipes :

    whenwhen pipespipes areare laid laid belowbelow roadsroads (which(which maymay bebe

    subjectedsubjected toto heavyheavy traffictraffic loads),loads), trenchestrenches shouldshould bebe coveredcovered

    ww re n orcere n orce concre econcre e s a ss a s

  • 7/21/2019 Pipeline Activity.pdf

    40/45

    GRP Lamination Details

    1. Grinding wheels, (machine)

    2. Surface,

    3. Robin,

    4. Matt5. Resin,

    6. Hardener,

    . ,

  • 7/21/2019 Pipeline Activity.pdf

    41/45

    am na on rocess :

    1. First rindthe dama ed ortion with rindin wheel.

    2. After that , mix the aerosol powderwith hardener, this

    m x ure as o e pu on amage por on, ar ener s

    used to set quickly that joint.

    3. Surface is very soft material, this has to put on that portion

    & paste with resin which is used for sticking & hardening.

  • 7/21/2019 Pipeline Activity.pdf

    42/45

    4. Matt & robin are the strength of that lamination

    process

    these both used one by one on damaged portion.

    5. The robin & matt used up to 7 times6. Resinpour on robin & matt

  • 7/21/2019 Pipeline Activity.pdf

    43/45

    Hydro Testing:

    1. After Completion of each section of pipeline, it shall be

    es e or wa er g ness e ore e ng covere n.

    2. This can be done by closing each end by means of

    valve, blank flange, cap or plug and filling the pipe with

    water.

  • 7/21/2019 Pipeline Activity.pdf

    44/45

    3. The pressure shall be raised gradually by means of a hydro

    testing pump till the pressure is at least one and half times

    t e wor ng pressure.

    4. A pressure to be specified by the authority for a duration of

    one hour.

    NOTE : In the test pressure drops after one hour

  • 7/21/2019 Pipeline Activity.pdf

    45/45

    THANK U.....