pipe route

Upload: hutuguo

Post on 04-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 pipe route

    1/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    TABLE OF CONTENTS

    1.0 INTRODUCTION .................................................................................................................1

    1.1 Background ......................................................................................................................1

    1.2 Purpose .............................................................................................................................4

    1.3 Project Description ...........................................................................................................4

    2.0 ROUTE SELECTION ..........................................................................................................6

    2.1 Methodology ....................................................................................................................6

    2.2 General Alignment Considerations...................................................................................6

    2.3 Exclusion ..................................................................................6

    2.4 Evaluation Criteria ...................................................................................................7

    2.4.1 Customer Connection .............................................................................................72.4.2 Constructability ......................................................................................................9

    2.4.3 Clearance/Permit from Relevant Competent Authorities .......................................9

    2.4.4 Schedule Compliance .............................................................................................9

    2.4.5 Construction Cost ...................................................................................................9

    3.0 ALTERNATIVE ALIGNMENTS .................................................................................10

    3.1 Description of Alignments .............................................................................................10

    3.2 Evaluation of Alignments ...............................................................................................11

    4.0 CONCLUSIONS AND RECOMMENDATIONS ............................................................16

    APPENDIX A SITE PHOTOS

    APENDIX B MISCELLANEOUS

    LIST OF FIGURES

    Figure FIG. 1a Original Proposed Alignment .............................................................................2

    Figure FIG. 1b Original Proposed Alignment Aerial View ........................................................3

    Figure FIG. 2 Project Location .................................................................................................5

    Figure FIG. 3 Alternative Alignment A1 .................................................................................12

    Figure FIG. 4 Alternative Alignment A2 .................................................................................13

    Figure FIG. 5 Alternative Alignment A3 .................................................................................14

    Figure FIG. 6 Alternative Alignment A4 .................................................................................15

  • 7/29/2019 pipe route

    2/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    1.0 INTRODUCTION

    1.1 BackgroundIn the continuing effort to increase the use of NEWater for non-potable use, the Singapore

    Public Utilities Board (PUB) is planning to expand and extend the existing NEWater

    supply network to meet the demands from the proposed Sports Hub (when completed) and

    the growing demands for NEWater from existing/new commercial/industrial

    establishments/developments along Beach Road, Kallang and Bendemeer areas,

    PUB has called for consultancy services in the engineering studies, detailed planning,

    design, supervision and management of the construction and commissioning for the

    Proposed 500mm/300mm Diameter NEWater Pipelines from Bras Basah Road to

    Sports Hub and Bendemeer and the contract was awarded to Fong Consult Pte Ltd

    (FCPL).

    In laying out the process for finalising the pipeline route, FCPL started by looking at the

    originally proposed pipeline alignment (Figures FIG.1a & FIG.1b). However, preliminary

    consultation with the Land Transport Authority (LTA) revealed that segment of the

    proposed pipelines routed along Kallang Avenue was found to be within the protection

    reserveof the Singapore Underground Road System (SURS) and LTA commented that the

    proposed pipelines shall be realigned to avoid encroachment into the SURS protection

    reserve.

    In light of the abovementioned key restriction and other possible constrictions (such as

    conflicts with underground utilities/structures, constructability issues etc), potential

    pipeline corridors, primarily to avoid the SURS protection reserve within this area, have

    been explored and alternative alignment options were developed, considered and evaluated.

  • 7/29/2019 pipe route

    3/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    FIG.1A

  • 7/29/2019 pipe route

    4/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    SportsHubU?C

    FIG. 1b ORIGINAL PROPOSED ALIGNMENT AERIAL VIEW

  • 7/29/2019 pipe route

    5/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    1.2 PurposeThe purpose of this report is to describe the pipeline route selection methodology

    employed to select the final alignment for the construction of the proposed NEWater

    pipeline project.

    The study was conducted by FCPL to identify and recommend the feasible final pipeline

    alignment.

    1.3

    Project Description

    The proposed NEWater pipelines consist of 500mm/300mm diameter distribution

    pipelines to extend the current supply network to serve the proposed Sports Hub and

    existing / potential users in Beach Road, Kallang and Bendemeer areas.

    The project includes supply, delivery, laying, testing and commissioning of the NEWater

    pipelines, appurtenances and associated ancillary works.

    The whole project is to be completed in two phases. Phase 1 works involve connection

    and commissioning of NEWater supply to the proposed Sports Hub is scheduled to be

    completed within 18 months to meet the opening of the Sports Hub in April 2014whilstthe whole project is scheduled to be completed within 24 months from the commencement

    date of the project construction contract.

    The proposed pipelines start from Beach Road, near to the junction with Bras Basah Road,

    where the point of connection to the supply source located. The proposed pipelinescorridor of interest are; the commercial establishments/developments along Beach Road,

    which runs through three areas, i.e. the Downtown Core, the Rochor and Kallang Areas of

    the Central Region; the Kallang Riverside development, the proposed Sports Hub and the

    existing industrial estates / new industrial park developments at Lavender, Kallang and

    Bendemeer areas. Location of the project area is shown in Figure 2. Due to the unique

    geographical location of this region which is bounded by waterways, it is inevitable that

    segments of the proposed pipelines will need to be routed across the Rochor and Kallang

    River in order to reach it intended destinations.

  • 7/29/2019 pipe route

    6/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    FIG. 2 PROJECT LOCATION

  • 7/29/2019 pipe route

    7/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    2.0 ROUTE SELECTION

    2.1 Methodology

    The alternative pipeline alignments were evaluated using the criteria established in Section

    2.4 to determine the preferred route.

    In general, the considerations taken to select the final route include avoiding sensitive

    utilities/ buildings/structures and conversation areas; reducing disturbance to the

    traffic/stakeholders, compliance with engineering /construction/relevant competent

    authorities/agencies requirements and meeting the budget, completion date and economicbenefits of this project.

    2.2 General Alignment Considerations

    In most cases, the proposed pipeline shall be laid in Public Streets and aligned within the

    Road Reserve.For laying of pipelines in public streets, the installation is normally by open

    trench method. At major river/canal crossing and crossing of major road with high traffic

    volume where installation by open trench method is infeasible, trenchless construction

    such as pipe jacking method is employed to install the pipeline across.

    2.3 Exclusion

    The following segments of the proposed alignments are not included for alternative

    alignment consideration;

    i) Proposed alignment along Beach Road - As the points of connection along BeachRoad contribute substantially to the overall demands, the segment of the proposed

    pipelines routed along Beach Road is therefore not included for alternative alignment

    consideration.

    ii) Proposed 300mm diameter pipelines connect to the constructed pipeline alongStadium Link which were laid in advance in conjunction with the Kallang Riverside

    Development infrastructure works. The pipeline alignment along this segment is

    therefore final.

    Hence, the areas focus for potential alternative alignments considerations are Crawford

    Street, Kallang, Lavender, Boon Keng and Bendemeer areas.

  • 7/29/2019 pipe route

    8/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    2.4 Evaluation Criteria

    2.4.1 Customer Connection

    i) Proximity to Existing Users

    This criterion is used to evaluate the proximity of the proposed route to the

    existing users. An existing user is a current customer who can be converted to

    NEWater from potable water.

    ii) Proximity to Future Users

    This criterion is used to evaluate the proximity of the proposed route to

    planned development which could utilize NEWater to minimize its new

    demands on the potable water system.

    2.4.2 Constructability

    i) Utility ConflictsExisting utility mapping and field verifications by means of site

    reconnaissance and conducting of trial holes are used to identify areas that

    might have major utility conflicts that could impact constructability. Over

    ground utilities/ structures and existing or planned major underground services

    are identified along each potential pipeline alignment.

    ii) Clearance from Existing Bridge StructureIn accordance with LTA requirement, the proposed pipeline shall maintain a

    minimum horizontal clearance of 10m from the edge of existing vehicular

    bridge structure. Existing vehicular bridge structural are identified along each

    potential pipeline alignment.

    iii) Proximity to Existing/Planned Underground Road/Rail InfrastructureThe proposed pipelines shall avoid laying in close proximity to existing and

    planned underground road/rail infrastructures such as the existing Crawford

    underpass, KPE and the proposed N-S Expressway, SURS, DTL3 etc.

  • 7/29/2019 pipe route

    9/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    iv) Proximity to Existing Building/ StructureThe construction of the proposed pipelines shall avoid laying in close

    proximity to existing building and structures.

    v) Proximity to Protected/Conservation AreasThe construction of the proposed pipelines shall avoid laying in close

    proximity to conservation areas such as Crawford Bridge and protected areas

    such as the substation etc.

    vi)

    Proximity to TreeTrees along the potential pipeline alignments are mapped and categorized.

    Alignment in proximity to trees is not preferable and shall be avoided

    because construction activities associated with pipeline installation around

    trees require clearances and is slower. Additional cost incurred if felling and

    transplant of tree is required.

    vii) Road ConditionThe road condition along the alignments is to be noted. Alignments that

    require opening of newly constructed/resurfaced road shall be avoided.

    viii) Viable Traffic Diversion ImplementationAs the project is located in densely built up urban areas, potential conflicts

    between traffic and construction is anticipated. The construction is more

    accomplishable if traffic can be diverted.

    ix) Adequate Space for Construction Work AreaThe proposed pipelines shall lay in location with adequate space for the

    required construction work areas and operations so that works can be carried

    out safely with minimal inconvenience to the stakeholders, road-users and

    general public affected by the works.

    The nominal work space width required for open trench pipelaying is 3.3 m

    on the assumption of using a 2.5m wide excavator and dump truck. The

  • 7/29/2019 pipe route

    10/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    nominal trench width is conservatively assume at 1.5m/1.3m for

    500mm/300mm diameter pipe respectively.

    The dimension for shaft related to pipe jacking is assume at a maximum of

    4m x 8m.

    x) Overlap with Other Public Works ProjectsAlignments that overlap with other public works projects such as road

    widening, infrastructure development project etc. provide an opportunity to

    reduce the cost and disturbance associated with both projects so long as good

    coordination is establish. In this respect, alignments that overlap with other

    public works projects are deemed preferable to those that do not.

    2.4.3 Clearance/Permit from Relevant Competent Authorities / Agencies

    Obtaining the required clearances/permits for construction from the relevant

    competent authorities/agencies for the alignments is crucial otherwise the

    alignment would be considered not practicable. Alignments that within road serve

    that minimize the need for long-lead time permits are preferable to those that

    require additional permitting effort.

    2.4.4 Schedule Compliance

    This criterion is used to assess whether Phase 1 of the Project can complete within

    Eighteen (18) calendar months from the commencement date of the project

    construction contract otherwise the alignment would not be practical.

    2.4.5 Construction Cost

    This criterion is used to assess projected construction costs, which comprise the

    cost to construct conveyance facilities necessary to deliver NEWater to the

    customers. These facilities include pipelines and appurtenances.

    Pipeline costs vary by the overall length of pipeline required by the given

    alignment. Shorter routes are preferable to longer routes. Major under crossings are

    identified for each alignment, because these add considerable construction costs

    for that alignment.

  • 7/29/2019 pipe route

    11/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    3.0 ALTERNATIVE ALIGNMENTS

    A total of four alternative alignment options (A1, A2, A3 and A4) at Crawford Street,

    Kallang, Lavender, Boon Keng and Bendemeer areas were developed (FIG.3 to FIG. 6).

    3.1 DESCRIPTION OF ALIGNMENTS

    In general, the alternative alignments, as compared to the original proposed alignment,

    were developed primarily to avoid the SURS Protection Reserve which conflicts with the

    segments of pipeline that run along Kallang Avenue, Kallang Junction, Boon Keng Road

    and Bendemeer Road in the original proposed alignment.

    i) Alternative A1

    The proposed alternative alignment is to route the pipelines from Kallang Road to

    Lavender Street and run along Lavender Street, detour to Bendemeer Road and

    terminate at Boon Keng Road and Bendemeer Road near the Micron Building.

    Please refer to figure Fig. 3 for details.

    ii) Alternative A2

    The proposed alternative alignment is to route the pipelines along Crawford Street

    after turning from Beach Road, run across the Crawford Bridge and across the

    junction with Kallang Road/Lavender Street and align the pipelines along

    Lavender Street, detour to Bendemeer Road and terminate at Boon Keng Road and

    Bendemeer Road near the Micron Building. Please refer to figure Fig. 4 for details.

    iii) Alternative A3

    The proposed alternative alignment is to route the pipelines along the river bank of

    Kallang Riverside Park after crossing the Rochor River. The pipelines branch-off

    northbound and southbound near Sir Arthurs Bridge. The southbound pipelines to

    Sports Hub follow the original proposed alignment. The Northbound pipelines cut

    across Kallang Road, run along the river bank of Kallang River, route along Boon

    Keng Road and detour to Bendemeer Road and terminate near the Micron Building.

    Please refer to figure Fig. 5 for details.

  • 7/29/2019 pipe route

    12/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    iv) Alternative A4The proposed alternative alignment is to branch-off the pipelines after crossing

    Kallang River. The southbound pipelines to Sports Hub follow the original

    proposed alignment. The Northbound pipelines run along Geylang Road, detour to

    Geylang Lorong 1, run along Boon Keng Road to Bendemeer Road and terminate

    near the Micron Building. Please refer to figure Fig. 6 for details.

    3.2 EVALUATION OF ALIGNMENTS

    The rating scale for each criterion is established as follows;

    Scale Definition

    1 Undesirable / Impractical

    2 Moderate

    3 Acceptable

    4 Desirable / Practical

    The criticality and priority of each criterion is weighted equally.

    Summary of alternative alignment Evaluation is tabulated as below;

    Table 1 Rating

    Clause Criteria A1 A2 A3 A4

    2.4.1 Customer Connection

    i) Proximity to Existing Users 3 3 2 2ii)Proximity to Future Users 4 4 2 2

    2.4.2 Constructability

    i) Utility Conflicts 3 3 2 2ii) Clearance from Existing Bridge Structure 2 1 2 2iii) Proximity to Existing/Planned

    Underground Road/Rail Infrastructure

    2 2 2 2

    iv) Proximity to Existing Building/ Structure 3 3 2 3v) Proximity to Protected/Conservation Areas 4 1 4 4vi) Proximity to Tree 3 3 1 3vii)Road Condition 3 3 3 3viii)Viable Traffic Diversion Implementation 2 2 3 3ix) Adequate Space for Construction Work Area 3 3 3 3x) Overlap with Other Public Works Projects 3 3 2 2

    2.4.3 Clearance/Permit from Relevant Competent

    Authorities/Agencies

    2 1 1 2

    2.4.4 Schedule Compliance 3 2 2 2

    2.4.5 Construction Cost 3 3 3 3

    Average Rating 2.87 2.47 2.27 2.53

  • 7/29/2019 pipe route

    13/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

  • 7/29/2019 pipe route

    14/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

  • 7/29/2019 pipe route

    15/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

  • 7/29/2019 pipe route

    16/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

  • 7/29/2019 pipe route

    17/17

    Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer

    FINAL PIPELINE ROUTING ANALYSIS REPORT

    4.0 CONCLUSIONS AND RECOMMENDATIONS

    The routing analysis consisted of evaluating pipeline alignments based on the criteria

    defined in Section 2.4 in the areas as highlighted in this report.

    The evaluation included site reconnaissance, conducting of trial holes to identified

    utilities/services conflicts and desktop analysis. Potential pipeline corridors were

    identified and four alternative alignment options were developed for consideration and

    evaluation.

    Following is the tabulation of the average overall rating of the alternative alignmentsevaluation;

    Alternative

    Alignment

    Average

    Overall

    Rating

    Ranking

    A1 2.87 1

    A2 2.47 3

    A3 2.27 4

    A4 2.53 2

    Based on the evaluation and the final scoring, the final preferred alignment, Alternative

    A1, is recommended to deliver NEWater to the proposed Sports Hub, Beach Road,

    Kallang and Bendemeer areas.

    Although there are still pending authorities clearances for the selected final preferred

    alignment, it is however anticipated that major changes to the final preferred route are not

    likely as it has been assessed to be more feasible amongst the alternative alignment options

    explored. Nevertheless, minor amendments to the alignment to improve localised

    outcomes are expected. As these changes are assessed, investigated and approved,

    subsequent revisions to the final preferred alignment will be made.

    A separate report, document no. FC/PUB/PSK/1125/HS/001, on hydraulic modeling was

    performed on the final preferred alignment to optimize pipe diameters for the distribution

    pipes.