pipe route
TRANSCRIPT
-
7/29/2019 pipe route
1/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
TABLE OF CONTENTS
1.0 INTRODUCTION .................................................................................................................1
1.1 Background ......................................................................................................................1
1.2 Purpose .............................................................................................................................4
1.3 Project Description ...........................................................................................................4
2.0 ROUTE SELECTION ..........................................................................................................6
2.1 Methodology ....................................................................................................................6
2.2 General Alignment Considerations...................................................................................6
2.3 Exclusion ..................................................................................6
2.4 Evaluation Criteria ...................................................................................................7
2.4.1 Customer Connection .............................................................................................72.4.2 Constructability ......................................................................................................9
2.4.3 Clearance/Permit from Relevant Competent Authorities .......................................9
2.4.4 Schedule Compliance .............................................................................................9
2.4.5 Construction Cost ...................................................................................................9
3.0 ALTERNATIVE ALIGNMENTS .................................................................................10
3.1 Description of Alignments .............................................................................................10
3.2 Evaluation of Alignments ...............................................................................................11
4.0 CONCLUSIONS AND RECOMMENDATIONS ............................................................16
APPENDIX A SITE PHOTOS
APENDIX B MISCELLANEOUS
LIST OF FIGURES
Figure FIG. 1a Original Proposed Alignment .............................................................................2
Figure FIG. 1b Original Proposed Alignment Aerial View ........................................................3
Figure FIG. 2 Project Location .................................................................................................5
Figure FIG. 3 Alternative Alignment A1 .................................................................................12
Figure FIG. 4 Alternative Alignment A2 .................................................................................13
Figure FIG. 5 Alternative Alignment A3 .................................................................................14
Figure FIG. 6 Alternative Alignment A4 .................................................................................15
-
7/29/2019 pipe route
2/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
1.0 INTRODUCTION
1.1 BackgroundIn the continuing effort to increase the use of NEWater for non-potable use, the Singapore
Public Utilities Board (PUB) is planning to expand and extend the existing NEWater
supply network to meet the demands from the proposed Sports Hub (when completed) and
the growing demands for NEWater from existing/new commercial/industrial
establishments/developments along Beach Road, Kallang and Bendemeer areas,
PUB has called for consultancy services in the engineering studies, detailed planning,
design, supervision and management of the construction and commissioning for the
Proposed 500mm/300mm Diameter NEWater Pipelines from Bras Basah Road to
Sports Hub and Bendemeer and the contract was awarded to Fong Consult Pte Ltd
(FCPL).
In laying out the process for finalising the pipeline route, FCPL started by looking at the
originally proposed pipeline alignment (Figures FIG.1a & FIG.1b). However, preliminary
consultation with the Land Transport Authority (LTA) revealed that segment of the
proposed pipelines routed along Kallang Avenue was found to be within the protection
reserveof the Singapore Underground Road System (SURS) and LTA commented that the
proposed pipelines shall be realigned to avoid encroachment into the SURS protection
reserve.
In light of the abovementioned key restriction and other possible constrictions (such as
conflicts with underground utilities/structures, constructability issues etc), potential
pipeline corridors, primarily to avoid the SURS protection reserve within this area, have
been explored and alternative alignment options were developed, considered and evaluated.
-
7/29/2019 pipe route
3/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
FIG.1A
-
7/29/2019 pipe route
4/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
SportsHubU?C
FIG. 1b ORIGINAL PROPOSED ALIGNMENT AERIAL VIEW
-
7/29/2019 pipe route
5/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
1.2 PurposeThe purpose of this report is to describe the pipeline route selection methodology
employed to select the final alignment for the construction of the proposed NEWater
pipeline project.
The study was conducted by FCPL to identify and recommend the feasible final pipeline
alignment.
1.3
Project Description
The proposed NEWater pipelines consist of 500mm/300mm diameter distribution
pipelines to extend the current supply network to serve the proposed Sports Hub and
existing / potential users in Beach Road, Kallang and Bendemeer areas.
The project includes supply, delivery, laying, testing and commissioning of the NEWater
pipelines, appurtenances and associated ancillary works.
The whole project is to be completed in two phases. Phase 1 works involve connection
and commissioning of NEWater supply to the proposed Sports Hub is scheduled to be
completed within 18 months to meet the opening of the Sports Hub in April 2014whilstthe whole project is scheduled to be completed within 24 months from the commencement
date of the project construction contract.
The proposed pipelines start from Beach Road, near to the junction with Bras Basah Road,
where the point of connection to the supply source located. The proposed pipelinescorridor of interest are; the commercial establishments/developments along Beach Road,
which runs through three areas, i.e. the Downtown Core, the Rochor and Kallang Areas of
the Central Region; the Kallang Riverside development, the proposed Sports Hub and the
existing industrial estates / new industrial park developments at Lavender, Kallang and
Bendemeer areas. Location of the project area is shown in Figure 2. Due to the unique
geographical location of this region which is bounded by waterways, it is inevitable that
segments of the proposed pipelines will need to be routed across the Rochor and Kallang
River in order to reach it intended destinations.
-
7/29/2019 pipe route
6/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
FIG. 2 PROJECT LOCATION
-
7/29/2019 pipe route
7/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
2.0 ROUTE SELECTION
2.1 Methodology
The alternative pipeline alignments were evaluated using the criteria established in Section
2.4 to determine the preferred route.
In general, the considerations taken to select the final route include avoiding sensitive
utilities/ buildings/structures and conversation areas; reducing disturbance to the
traffic/stakeholders, compliance with engineering /construction/relevant competent
authorities/agencies requirements and meeting the budget, completion date and economicbenefits of this project.
2.2 General Alignment Considerations
In most cases, the proposed pipeline shall be laid in Public Streets and aligned within the
Road Reserve.For laying of pipelines in public streets, the installation is normally by open
trench method. At major river/canal crossing and crossing of major road with high traffic
volume where installation by open trench method is infeasible, trenchless construction
such as pipe jacking method is employed to install the pipeline across.
2.3 Exclusion
The following segments of the proposed alignments are not included for alternative
alignment consideration;
i) Proposed alignment along Beach Road - As the points of connection along BeachRoad contribute substantially to the overall demands, the segment of the proposed
pipelines routed along Beach Road is therefore not included for alternative alignment
consideration.
ii) Proposed 300mm diameter pipelines connect to the constructed pipeline alongStadium Link which were laid in advance in conjunction with the Kallang Riverside
Development infrastructure works. The pipeline alignment along this segment is
therefore final.
Hence, the areas focus for potential alternative alignments considerations are Crawford
Street, Kallang, Lavender, Boon Keng and Bendemeer areas.
-
7/29/2019 pipe route
8/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
2.4 Evaluation Criteria
2.4.1 Customer Connection
i) Proximity to Existing Users
This criterion is used to evaluate the proximity of the proposed route to the
existing users. An existing user is a current customer who can be converted to
NEWater from potable water.
ii) Proximity to Future Users
This criterion is used to evaluate the proximity of the proposed route to
planned development which could utilize NEWater to minimize its new
demands on the potable water system.
2.4.2 Constructability
i) Utility ConflictsExisting utility mapping and field verifications by means of site
reconnaissance and conducting of trial holes are used to identify areas that
might have major utility conflicts that could impact constructability. Over
ground utilities/ structures and existing or planned major underground services
are identified along each potential pipeline alignment.
ii) Clearance from Existing Bridge StructureIn accordance with LTA requirement, the proposed pipeline shall maintain a
minimum horizontal clearance of 10m from the edge of existing vehicular
bridge structure. Existing vehicular bridge structural are identified along each
potential pipeline alignment.
iii) Proximity to Existing/Planned Underground Road/Rail InfrastructureThe proposed pipelines shall avoid laying in close proximity to existing and
planned underground road/rail infrastructures such as the existing Crawford
underpass, KPE and the proposed N-S Expressway, SURS, DTL3 etc.
-
7/29/2019 pipe route
9/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
iv) Proximity to Existing Building/ StructureThe construction of the proposed pipelines shall avoid laying in close
proximity to existing building and structures.
v) Proximity to Protected/Conservation AreasThe construction of the proposed pipelines shall avoid laying in close
proximity to conservation areas such as Crawford Bridge and protected areas
such as the substation etc.
vi)
Proximity to TreeTrees along the potential pipeline alignments are mapped and categorized.
Alignment in proximity to trees is not preferable and shall be avoided
because construction activities associated with pipeline installation around
trees require clearances and is slower. Additional cost incurred if felling and
transplant of tree is required.
vii) Road ConditionThe road condition along the alignments is to be noted. Alignments that
require opening of newly constructed/resurfaced road shall be avoided.
viii) Viable Traffic Diversion ImplementationAs the project is located in densely built up urban areas, potential conflicts
between traffic and construction is anticipated. The construction is more
accomplishable if traffic can be diverted.
ix) Adequate Space for Construction Work AreaThe proposed pipelines shall lay in location with adequate space for the
required construction work areas and operations so that works can be carried
out safely with minimal inconvenience to the stakeholders, road-users and
general public affected by the works.
The nominal work space width required for open trench pipelaying is 3.3 m
on the assumption of using a 2.5m wide excavator and dump truck. The
-
7/29/2019 pipe route
10/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
nominal trench width is conservatively assume at 1.5m/1.3m for
500mm/300mm diameter pipe respectively.
The dimension for shaft related to pipe jacking is assume at a maximum of
4m x 8m.
x) Overlap with Other Public Works ProjectsAlignments that overlap with other public works projects such as road
widening, infrastructure development project etc. provide an opportunity to
reduce the cost and disturbance associated with both projects so long as good
coordination is establish. In this respect, alignments that overlap with other
public works projects are deemed preferable to those that do not.
2.4.3 Clearance/Permit from Relevant Competent Authorities / Agencies
Obtaining the required clearances/permits for construction from the relevant
competent authorities/agencies for the alignments is crucial otherwise the
alignment would be considered not practicable. Alignments that within road serve
that minimize the need for long-lead time permits are preferable to those that
require additional permitting effort.
2.4.4 Schedule Compliance
This criterion is used to assess whether Phase 1 of the Project can complete within
Eighteen (18) calendar months from the commencement date of the project
construction contract otherwise the alignment would not be practical.
2.4.5 Construction Cost
This criterion is used to assess projected construction costs, which comprise the
cost to construct conveyance facilities necessary to deliver NEWater to the
customers. These facilities include pipelines and appurtenances.
Pipeline costs vary by the overall length of pipeline required by the given
alignment. Shorter routes are preferable to longer routes. Major under crossings are
identified for each alignment, because these add considerable construction costs
for that alignment.
-
7/29/2019 pipe route
11/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
3.0 ALTERNATIVE ALIGNMENTS
A total of four alternative alignment options (A1, A2, A3 and A4) at Crawford Street,
Kallang, Lavender, Boon Keng and Bendemeer areas were developed (FIG.3 to FIG. 6).
3.1 DESCRIPTION OF ALIGNMENTS
In general, the alternative alignments, as compared to the original proposed alignment,
were developed primarily to avoid the SURS Protection Reserve which conflicts with the
segments of pipeline that run along Kallang Avenue, Kallang Junction, Boon Keng Road
and Bendemeer Road in the original proposed alignment.
i) Alternative A1
The proposed alternative alignment is to route the pipelines from Kallang Road to
Lavender Street and run along Lavender Street, detour to Bendemeer Road and
terminate at Boon Keng Road and Bendemeer Road near the Micron Building.
Please refer to figure Fig. 3 for details.
ii) Alternative A2
The proposed alternative alignment is to route the pipelines along Crawford Street
after turning from Beach Road, run across the Crawford Bridge and across the
junction with Kallang Road/Lavender Street and align the pipelines along
Lavender Street, detour to Bendemeer Road and terminate at Boon Keng Road and
Bendemeer Road near the Micron Building. Please refer to figure Fig. 4 for details.
iii) Alternative A3
The proposed alternative alignment is to route the pipelines along the river bank of
Kallang Riverside Park after crossing the Rochor River. The pipelines branch-off
northbound and southbound near Sir Arthurs Bridge. The southbound pipelines to
Sports Hub follow the original proposed alignment. The Northbound pipelines cut
across Kallang Road, run along the river bank of Kallang River, route along Boon
Keng Road and detour to Bendemeer Road and terminate near the Micron Building.
Please refer to figure Fig. 5 for details.
-
7/29/2019 pipe route
12/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
iv) Alternative A4The proposed alternative alignment is to branch-off the pipelines after crossing
Kallang River. The southbound pipelines to Sports Hub follow the original
proposed alignment. The Northbound pipelines run along Geylang Road, detour to
Geylang Lorong 1, run along Boon Keng Road to Bendemeer Road and terminate
near the Micron Building. Please refer to figure Fig. 6 for details.
3.2 EVALUATION OF ALIGNMENTS
The rating scale for each criterion is established as follows;
Scale Definition
1 Undesirable / Impractical
2 Moderate
3 Acceptable
4 Desirable / Practical
The criticality and priority of each criterion is weighted equally.
Summary of alternative alignment Evaluation is tabulated as below;
Table 1 Rating
Clause Criteria A1 A2 A3 A4
2.4.1 Customer Connection
i) Proximity to Existing Users 3 3 2 2ii)Proximity to Future Users 4 4 2 2
2.4.2 Constructability
i) Utility Conflicts 3 3 2 2ii) Clearance from Existing Bridge Structure 2 1 2 2iii) Proximity to Existing/Planned
Underground Road/Rail Infrastructure
2 2 2 2
iv) Proximity to Existing Building/ Structure 3 3 2 3v) Proximity to Protected/Conservation Areas 4 1 4 4vi) Proximity to Tree 3 3 1 3vii)Road Condition 3 3 3 3viii)Viable Traffic Diversion Implementation 2 2 3 3ix) Adequate Space for Construction Work Area 3 3 3 3x) Overlap with Other Public Works Projects 3 3 2 2
2.4.3 Clearance/Permit from Relevant Competent
Authorities/Agencies
2 1 1 2
2.4.4 Schedule Compliance 3 2 2 2
2.4.5 Construction Cost 3 3 3 3
Average Rating 2.87 2.47 2.27 2.53
-
7/29/2019 pipe route
13/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
-
7/29/2019 pipe route
14/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
-
7/29/2019 pipe route
15/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
-
7/29/2019 pipe route
16/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
-
7/29/2019 pipe route
17/17
Proposed 500mm/300mm Diameter NEWater Pipelinesfrom Bras Basah Road To Sports Hub and Bendemeer
FINAL PIPELINE ROUTING ANALYSIS REPORT
4.0 CONCLUSIONS AND RECOMMENDATIONS
The routing analysis consisted of evaluating pipeline alignments based on the criteria
defined in Section 2.4 in the areas as highlighted in this report.
The evaluation included site reconnaissance, conducting of trial holes to identified
utilities/services conflicts and desktop analysis. Potential pipeline corridors were
identified and four alternative alignment options were developed for consideration and
evaluation.
Following is the tabulation of the average overall rating of the alternative alignmentsevaluation;
Alternative
Alignment
Average
Overall
Rating
Ranking
A1 2.87 1
A2 2.47 3
A3 2.27 4
A4 2.53 2
Based on the evaluation and the final scoring, the final preferred alignment, Alternative
A1, is recommended to deliver NEWater to the proposed Sports Hub, Beach Road,
Kallang and Bendemeer areas.
Although there are still pending authorities clearances for the selected final preferred
alignment, it is however anticipated that major changes to the final preferred route are not
likely as it has been assessed to be more feasible amongst the alternative alignment options
explored. Nevertheless, minor amendments to the alignment to improve localised
outcomes are expected. As these changes are assessed, investigated and approved,
subsequent revisions to the final preferred alignment will be made.
A separate report, document no. FC/PUB/PSK/1125/HS/001, on hydraulic modeling was
performed on the final preferred alignment to optimize pipe diameters for the distribution
pipes.