Page 1: Photovoltaics EN

PHOTOVOLTAICS BGPHOTOVOLTAICS BG

Page 2: Photovoltaics EN

Content

• Photovoltaics in Bulgaria• Economy of Bulgaria• Geography of Bulgaria• Legislation• Technical conditions for the connection

Page 3: Photovoltaics EN

Guaranteed period of purchase

• In Bulgaria, there is a purchase of electricity produced in the

photovoltaic power stations guaranteed for 25 years

Page 4: Photovoltaics EN

Guaranteed purchase price

• Price per 1 kWh in Bulgaria 0,464 € inc. VAT since 01.04.2010

• In Bulgaria, there is 35% higher sun radiation than in midl Europe

Page 5: Photovoltaics EN

In Bulgaria, there is no permit needed for the construction of photovoltaic power stations up to 5 MW of output

Page 6: Photovoltaics EN

• Exchange rate development which is fixed on Euro as of 10.01.2006

Page 7: Photovoltaics EN

Budget deficit of Bulgaria

The Bulgarian Ministry of Finance announced that the Bulgarian budget

deficit for 2009 was 529,5 BGN M or 0,8 % of GDP.

(http://www.novinite.com/view_news.php?id=112626)

Page 8: Photovoltaics EN

Development of inflation in BulgariaDevelopment of inflation in Bulgaria

Page 9: Photovoltaics EN

State dept of Bulgaria• State dept of Bulgaria was 3,4 Mld. Euro at the end of 2009, public debt

decreased for 0,5% when compared to previous year

Page 10: Photovoltaics EN

Taxes in Bulgaria

• Value income tax of legal persons in Bulgaria is only 10%.

Page 11: Photovoltaics EN

BULGARIA

Page 12: Photovoltaics EN
Page 13: Photovoltaics EN

Distribution companies in Bulgaria

Page 14: Photovoltaics EN

Distribution companies in Bulgaria

EVN – Austrian distribution company

EON – German distribution company

ČEZ – Czech distribution company

Page 15: Photovoltaics EN

Investor applies for the connection

• In application he defines the subject which is submitting the application

• He attaches the Certificate of Land Ownership

• Indicates which PTV output he wants to install

Page 16: Photovoltaics EN

Based on application respective distribution company issues preliminary opinion

• It implies information about maximum connectable output, location, exact place of connection and technical conditions of connection

Page 17: Photovoltaics EN

Following the issue of preliminary opinion the investor is obliged to obtain all the necessary permissions and opinions of involved institutions

After their receipt the investor request the respective distribution company for the conclusion of preliminary contract on connection

Page 18: Photovoltaics EN

Documents necessary for the conclusion of preliminary contract on connection

• Standpoint of the distribution company• Admissible reserved capacity of connection• Detailed territorial plan• Environmental permissions• Standpoint of the regional inspectorate of health protection• Standpoint of authority of water resources protection• Categorisation of land, opinion on possibility of constrution• Decision of Ministry of Agriculture• Written opinion on the detailed territorial plan and preliminary contract

with the distribution company

Page 19: Photovoltaics EN

Preliminary contract on connection is a binding document fulfilling all legislative conditions necessary for the conclusion of the contract on connection.

After its conclusion the investor can apply for the Building permission. However, he must also attach projects for the building permission.

Page 20: Photovoltaics EN

After granting the building permission the investor concludes the contract with respective distribution company.

Page 21: Photovoltaics EN

After granting the building permission the investor can commence construction works and the final building approval he concludes the contract on purchase of electricity with respective distribution company.

Page 22: Photovoltaics EN

Following conditions must be met to connect PVT power station to the network :

• Connection must be conducted in accordance with Par. 3 3 of Notice Nr. 6 as of 9.6.2004 on connection of producer and consumer of electricity through transfer network IDB Nr. 74 as of 24.08.2004

• It is imperative to meet the conditions stipulated in the Notice Nr. 14, as of 15.06.2005 on the technical rules and norms, for designing and use of facilities and appliances for the production, transmission and distribution of electric energy.

Page 23: Photovoltaics EN

Requirements for the appliances which must be attached to the central:

• All building components for connecting of the facility (photovolt. Modules, invertors, commutators, etc.) must comply with EU standards and the respective Bulgarian requirements. Before conclusion of the Contract on connection there must be documents for the approval of compliance submitted

• Invertors must be connected to the three phase system – symetric-sinusoid incoming voltage

• Outgoing voltage from invertor to the network must comply with EU standards EN 50160 as well as norms defined by the Government commission for energy and water regulation. Furthermore, it must comply with qualitative requirements of electric appliances (June 2004) and Chapter VII. of Head VI. of Regulation Nr. 6 as of 9 June 2004 on Connection of producers and consumers of electricy through transmission and distribution network

Page 24: Photovoltaics EN

Measurement of electricity

• Is realised in modules „Measurement“ from GRU of power station with one indirect, static, three-phase energy meter for active and non-active energy with measurements in four quadrants which must have a possibility of storage „on factory profile“ for active and reactive energy for the 15-minute-period during 62 days

• Energy measurement for production and consumption of all objects and properties must be realised with one measurement

Page 25: Photovoltaics EN

Service zones

• There must be terminal disconnectors installed on the borderlines of the lands

• There must be GPRS connection provided for the communication with monitoring system and management of recluser with CUM

• A possibility of access to facility of photovoltaic central to EON BG staff must be attained

• Before conclusion of the Contract for employment the documents for legalisation of service zone for wireline 20 kV as well as documents on compliance for the built power station must be provided

Page 26: Photovoltaics EN

Service zones

• Before start of the 72-hour-check all newly built facilities must be included into the scheme of the respective centre for the dispatch control of facilities as well as remote controlled facilities and must dispose of functional communication with operational basis in compliance with CUM

• The constructor is aware that in case of oversupply of energy or other obstructions of the power station to the network, it can be regulated or temporarily disconnected from the network

• In accordance with Act on power supply and production of electricity it is subject to issue of licence. The licence is not requested for the appliances up to 5 MW of output.