Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
1 Date:
10/27/15
Direction Photo
Taken:
Southwest
Photo Taken By:
JBH1
Description:
Looking southwest
on Copper Park Lane
viewing clearing and
grubbing of area
south of Copper Park
Lane prior to
excavation.
Photo No.
2 Date:
10/29/15
Direction Photo
Taken:
Southeast
Photo Taken By:
JBH1
Description:
Looking southeast at
the sump and pump
system dewatering
the ditch just east of
the North Basin.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
3 Date:
10/29/15
Direction Photo
Taken:
East
Photo Taken By:
JBH1
Description:
Looking east at the
sump and pump
dewatering system in
the East Basin.
Photo No.
4 Date:
10/30/15
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west at the
excavation in SSEA-
13.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
5 Date:
10/30/15
Direction Photo
Taken:
Photo Taken By:
JBH1
Description:
Looking downward at
the excavated depth
in SSEA-13.
Photo No.
6 Date:
10/30/15
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south at the
filling of the
excavated area of
SSEA-14 with A-9
(limestone) material.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
7 Date:
11/2/15
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south at the
tracking pad located
west of the East
Basin.
Photo No.
8 Date:
11/2/15
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west
backfilling SSEA 1
with limestone.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
9 Date:
10/3/15
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Looking north at long
reach excavator
excavating to design
grades in the East
Basin.
Photo No.
10 Date:
10/3/15
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Looking north at
surveying depth of
excavation in East
Basin.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
11 Date:
11/4/15
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south access
to the WDNR Service
Center being
maintained.
Photo No.
12 Date:
11/4/15
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south
material excavated
from the East Basin
being placed in the
West Basin.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
13 Date:
11/5/15
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Looking north
barricades on
HWY 27 while
excavating SSAE 9,
and cleaning out the
culvert beneath the
HWY.
Photo No.
14 Date:
11/5/15
Direction Photo
Taken:
East
Photo Taken By:
JBH1
Description:
Looking east cleaning
out the culvert
beneath HWY 27.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
15 Date:
11/6/15
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west placing
A-9 (limestone
gravel) in the
excavation of SSAE-
17.
Photo No.
16 Date:
11/6/15
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Looking north topsoil
being placed on top
of A9 material in
SSEA-17.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
17 Date:
11/9/15
Direction Photo
Taken:
East
Photo Taken By:
JBH1
Description:
Looking east North
Basin with trench
installed.
Photo No.
18 Date:
11/9/15
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Looking north fabric
placed below light rip
rap between the
North Basin (shown)
and the East Basin.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
19 Date:
11/10/15
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south
feathering ditch
slopes in East Basin.
Photo No.
20 Date:
11/11/15
Direction Photo
Taken:
Photo Taken By:
JBH1
Description:
Looking downward
water entering the
East Basin from the
North Basin through
the rip rap.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
21 Date:
11/11/15
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Looking north light
rip rap area at the
northeast corner of
the East Basin
receiving fabric prior
to light rip rap
installation.
Photo No.
22 Date:
11/12/15
Direction Photo
Taken:
East
Photo Taken By:
JBH1
Description:
Looking east Emat
placed on the upland
sloped area east of
the light rip rap area
between the North
and East Basins.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
23 Date:
11/13/15
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south 60”
culvert being
installed across
Copper Park Lane.
Photo No.
24 Date:
11/13/15
Direction Photo
Taken:
Southeast
Photo Taken By:
JBH1
Description:
Looking southeast
former East Basin
with Emat placed in
ditch and rip rap at
the northwest comer.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
25 Date:
11/16/15
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west A7
material being placed
into the Geocell mat
on the east berm of
the East Basin
Photo No.
26 Date:
11/17/15
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west grading
the east-west ditch.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
27 Date:
11/18/15
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west Emat
placed in East-West
ditch.
Photo No.
28 Date:
11/19/15
Direction Photo
Taken:
East
Photo Taken By:
JBH1
Description:
Looking east at the
overflow area from
the former East Basin
to wetland.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
29 Date:
12/3/15
Direction Photo
Taken:
Southeast
Photo Taken By:
JBH1
Description:
Looking southeast
straw mulch covers
high-ground to the
northwest of the
former East Basin.
Photo No.
30 Date:
12/3/15
Direction Photo
Taken:
East
Photo Taken By:
JBH1
Description:
Looking east straw
mulch cover high-
ground and Emat
covers the ditch line
in the former North
Basin.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
31 Date:
6/13/16
Direction Photo
Taken:
Northwest
Photo Taken By:
JBH1
Description:
Looking northwest at
hand spraying
herbicide on targeted
vegetation in the
former east basin and
wetland
Photo No.
32 Date:
6/14/16
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description: Looking
west at the grading
activities in the west
basin. The backhoe
fills an off-road haul
truck which deposits
the fill in front of a
dozer for spreading.
The pump that
dewatered the west
basin is shown on the
right hand side of the
photograph.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
33 Date:
6/14/16
Direction Photo
Taken:
Northwest
Photo Taken By:
JBH1
Description:
Looking northwest at
the west basin and the
dozer grading fill to
grade. Note the GIS
antennae on the dozer
blade used for grade
elevation.
Photo No.
34 Date:
6/15/16
Direction Photo
Taken:
Southwest
Photo Taken By:
JBH1
Description:
Looking southwest at
Emat placed in center
of recently filled
ditch north of the
west basin.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
35 Date:
6/15/16
Direction Photo
Taken:
South
Photo Taken By:
JBH1
Description:
Looking south at the
west basin with Emat
installed in the
perimeter ditches.
Photo No.
36 Date:
6/15/16
Direction Photo
Taken:
Southwest
Photo Taken By:
JBH1
Description:
Looking southwest at
the west basin
showing the two
gradual swales and
low areas on the
north side of the area.
Emat is shown in the
ditch lines heading
north.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
37 Date:
6/15/16
Direction Photo
Taken:
West
Photo Taken By:
JBH1
Description:
Looking west at
careful placement of
limestone rip rap in
the prescribed area
north of the culvert
under Copper Park
Lane.
Photo No.
38 Date:
9/16/16
Direction Photo
Taken:
West
Photo Taken By:
Rio Tinto
Description:
Erosion control
features were
removed from the site
on 9/16/16. This
view shows the area
south of Copper Park
Lane.
Photographic Log
Client’s Name:
Flambeau Mining Company Site Location:
Copper Park Business and Recreation Area Project No.
14F779
X:\GB\IE\2014\14F779-00\15000 Audiovisual\Copper Park Doc Rpt - 2016\Photo Log-all.docx
Photo No.
39 Date:
9/16/16
Direction Photo
Taken:
North
Photo Taken By:
JBH1
Description:
Erosion control
features were
removed from the site
on 9/16/16. This
view shows the area
west of wetland #7.