phmsa western region overview tempe, az august 20, 2014

55
U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration PHMSA Western Region Overview Tempe, AZ August 20, 2014

Upload: orson-clemons

Post on 02-Jan-2016

21 views

Category:

Documents


1 download

DESCRIPTION

PHMSA Western Region Overview Tempe, AZ August 20, 2014. PHMSA Region Updates. Relatively Quiet Y ear for Accidents but busy 2010-2012 Total Switch to Integrated Inspection Process (II) Use the Integrated Inspection Assistant Tool (IA) - PowerPoint PPT Presentation

TRANSCRIPT

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

PHMSA Western Region

OverviewTempe, AZ

August 20, 2014

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

PHMSA Region Updates

• Relatively Quiet Year for Accidents but busy 2010-2012

• Total Switch to Integrated Inspection Process (II)• Use the Integrated Inspection Assistant Tool (IA)• Continued Construction Oversight of pipeline

boom in MT, WY and NE Colorado• Aging Workforce and More Departures • Focus was on:

– Lesson Learned from Near Misses and Accidents

– Jump on even smallest incidents hard and anticipate questions, e.g. flooding, Bakken crude

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

PHMSA Region Contacts & SMEs

• Chris Hoidal – Director of Western Region

• Bryn Karaus – Western Region Counsel

• Huy Nguyen, Jeff Gilliam, Terry Larson– Supervisors

• Peter Katchmar – Accident Coordinator

• Ross Reineke – Construction Coordinator

• Tom Finch and David Mulligan – Community Assistance and Technical

Services (CATS)

• David Mulligan and Kim Nguyen - Inspection Assistant Power Users

• Dustin Hubbard and Claude Allen - PDM and Mapping Issues

• Jerry Kenerson – Safety Related Condition Follow-up

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

PHMSA Regions

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Western Region OfficesWestern Region Office –

16 Engineers

12300 West Dakota Avenue, Suite 110

Lakewood, CO 80228

720-963-3160

Satellite offices in:

Cheyenne, WY (Accident Investigator)

Billings, MT (1 engineer)

Reno, NV (1 engineer)

Ontario, CA (3 engineers)

Anchorage, AK (5 engineers)

One Regional Attorney – DC

Openings – One Engineer/Inspector

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Recap of Western RegionPriorities – (2010-2013)

– Continue to roll on more accidents, even low level ones

• Multiple Orders completed or finishing up.

– Construction Oversight of Bakken Field pipelines (Intense public scrutiny due to commodity characteristics)

– Get Better at II, IA and tweak process – Better not great

– Finish CRMs and DIMP - COMPLETED

– Do more IMP validations in field (mandated by HQ)

• Moving to Next Level of IMP (Focus on Prevention and Mitigation Measures)

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Incidents Continue to Set Pipeline Safety Agenda

Integrity Management Regulations prompted by:

Olympic Pipeline Rupture in Bellingham, WA (6/10/99)

El Paso Pipeline Explosion in Carlsbad, NM (8/19/00)

PG&E Pipeline Fire in San Bruno, CA (9/9/10)

SCADA/CRM, remote valves, and Leak detection prompted and/or reinforced by the above and the more recent failures

Enbridge Pipeline Spill in Marshall, MI (7/25/10)

Chevron Pipeline Spills (Salt Lake City) June/Dec 2010

Exxon/Mobil Spill into Yellowstone River (7/1/11)

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

2013/2014 Accidents – High Profile

• Recent Accidents and Near Misses:

– 7/2/13 – P66 Seminoe P/L, Crow Nation, Wyoming

– 9/10/14 – Alyeska failure of encapsulation, MP 38

– 3/31/14 – Plymouth, WA LNG Plant –WUTC (lead) and PHMSA investigating

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

P66 Seminoe Pipeline SpillCrow Nation near Lodge Grass, MT

July 2, 2013• Compression and buckling of 8-inch refined

products line resulted in 600 BBLs released on to Crow Nation land

• Crow Nation cooperative but demanding of P66. Wanted routine updates from PHMSA

• Terrain was hilly but not particularly steep, evidence of soil movement

• No CAO issued due to fast response by operator and couldn’t add anything

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Crow Nation Rupture – Rolling Hills

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

P66 Actions Taken• Replaced 500 feet of pipe.

• Relieved stress on over 4000 feet of pipe based on Geotechnical Engineer evaluation.

• Installed additional strain gauges in the area of the failure post stress relief and monitor for a year to validate if there was movement.

• Stand up test to ensure no other seepers in area.

• Perform weekly aerial patrols on pipeline until the completion of a deformation/strain tool and other slope movement areas remediated.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Seminoe Pipeline Lesson Learned

• Ground movement doesn’t need to be a sudden catastrophic slope failure to fail pipe

• ILIs should be selected to look for deformation, ovality, and wrinkles caused by ground movement

• Remember to treat incidents on Sovereign Nations differently

• Companies must consider land movement and water crossings in their IMP preventative and mitigative measures.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Alyeska Vent Encapsulation Failure

September 2013• Large 10-inch diameter coupon of carrier pipe found in

Valdez Back Pressure Valve

• Recent ILI data showed that it had come from recently installed vent encapsulation over 400 miles to north

• No release but encapsulation and hole sleeved. It appears epoxy in sleeve expanded and pushed carrier pipe inwards

• Over 100 of these had been put on during previous 2 years

• Simulated encapusulation in Fairbanks yard failed

• Issued Order to investigate other encapsulations on pipe requiring additional testing, ILI runs, and repairs

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Vent Encapsulation Photos

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Sleeved encapsulation at MP 385.77

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

• Don’t use untried methods of repair that don’t follow manufacturers guidelines.

• Need boots on ground – neither us or JPO knew these were being put on.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

P66 Spill “Out of Service” Pipeline Spill

Wilmington, CA – March 17, 2014

On March 17, 2014, Phillips (P66) is notified by emergency responders of crude oil leaking up from below pavement in a residential area of Wilmington, California. While leak was close to a P66 Wilmington refinery, they didn’t think it was theirs.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

P66 Wilmington, CA spill

• On March 18th, P66 excavated the leaking pipeline and determined it was actually their line. P66 had purchased the pipeline from the previous operator in 1998. P66 thought it had been properly abandoned and purged prior to their purchase.

• The leaking pipeline was a 10-inch diameter, 0.25 inch thick wall, carbon steel pipe installed in 1952. The cause of failure was an internal “pinhole” corrosion leak on a weld.

• P66 estimates that 39 barrels of crude oil was released and recovered. Estimated property damage reported $400,900.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

• Pipelines are either active or abandoned. There is no “out of service” or “idled” designation for pipelines under Parts 192 or 195.

• Even if the previous operator says lines were abandoned make sure you review how it was done and confirm it is actually isolated, cleaned and purged.

• Treat idled lines like active lines under IMP.

• California Congresswoman may propose legislation clarifying and confirming status of pipelines.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Williams LNG FaciltyPlymouth, WA – March 31,

2014

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

– Look at pre-liquefaction processes or any processes that could affect LNG facility

– Evacuation zones are much wider than is common knowledge

– Change must be focus, e.g. this plant had had its adsorbers recently overhauled

– Good State Agents Garner Public Confidence and are Priceless to PHMSA (WUTC will cover in more detail)

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Accidents w/ Oversight Impact July 2011- June 2013

• Exxon Mobil Silvertip Pipeline Spill – July 1, 2011

• TransCanada Bison Pipeline Rupture – July 20, 2012

• Chevron Willard Bay, Utah Spill – March 2013

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Exxon Mobil Pipeline SpillJuly 1, 2011

• Exxon Mobil Pipeline spills 1500 BBLs into Yellowstone River during record flooding.

• CAO issued 7/5 to take out of service until they put HDD under Yellowstone River, did water crossing surveys and remediation, rework SCADA training and abnormal operating procedures.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

ExxonMobil Silvertip – July 2011

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Preliminary Findings– ExxonMobil Silvertip pipeline released estimated

1500 barrels of crude oil into the Yellowstone River near Laurel, Montana; Est. $42M damages

– River scour is cause of ruptured pipeline

– EMPL was aware of the flood conditions

– EMPL detected pressure drop at river and shut pipeline pumps down in 7 minutes

– Despite having numerous remote actuated valves at rivers, controllers took 56 minutes after first alarm to close valve adjacent to river allowing crude oil to drain into the river

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Montana Governor’s Task Force

• Reason for Study: As a result of the July 2, 2011 crude oil spill into the Yellowstone River, ensure the integrity of petroleum pipelines at major water crossings that affect rivers in Montana.

• Primary Purpose: Collaborate with State of Montana to compile an inventory of petroleum pipelines at water crossings and determine if they are currently safe.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Other Purposes of Survey and Lessons Learned

• Determine if additional steps are required before Spring 2012 run off.

• Determine adequacy of pipeline operators’ patrolling methods and remedial actions at water crossings

• Develop recommendations regarding:

– Enhance PHMSA inspection guidance to ensure operators are meeting all aspects of regulations, particularly with respect to protecting their pipelines from water-related damage.

– Identify possible regulatory changes to PHMSA leadership expanding the requirements for water crossings.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

TransCanada Bison RuptureNear Gillette, WY

July 20, 2012• Pipeline ruptured within 6 months of being

put into service

• Pipeline was first pipeline to be put into service using the Alternative MAOP regulation

• CAO issued on 7/21 requiring DCVG, completion of ILI run and remediation digs.

• Metallurgical analysis

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Bison Pipeline Rupture – 7/20/11

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

TransCanada Lesson Learned• Pipeline companies still need to ensure there is

good quality control during all phases of construction.

• The defect can manifest itself before the baseline pig run, in this case 6 months, can be analyzed

– Happened within a few days after being smart pigged

• DCVG revealed other areas of “lowering in” damage.

• Relative low Charpy value in steel (still met API 5L)

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Chevron Pipeline SpillMarch 18, 2013

• Chevron Products Pipeline spilled 500+ BBLs adjacent to Willard Bay due to corrosion near longitudinal seam

• split on Low Frequency ERW pipe.

• CAO issued 3/22 to reduce pressure, hydrotest LFERW pipeline in area of Willard Bay, notify emergency responders and stakeholders during start up, and conduct metallurgical examination of failed pipe.

• Will expand CAO scope based on these findings.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Chevron Northwest Products _ Willard Bay, UT – March 2013

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

– Ensure that IMP program reflects all of line pipe

• Match up alignment sheets with corporate IMP plans

– Just because LFERW has not failed doesn’t mean it’s not seam susceptible

• Spike Hydros do have place

– Can not communicate enough – Keep logs of contacts

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Older Accidents w/ Oversight Impact

June 2010- June 2011 • Major Accidents:

– Bridger Lake Spill April 2010

– Chevron Crude Oil Spill June 2010

– Chevron Crude Oil Spill in December 2010

– Alyeska PS9 Tank Overfill in May 2010

– Alyeska PS1 Corrosion Leak at PS1 in January 2011

– PG&E San Bruno, CA explosion in September 2010

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Pipeline SpillApril 5, 2010

• Unknown crude oil line spills 2000 BBL near Mt View, WY

• CAO issued 4/28 to take out of service until O&M, OQ, and ILI conducted. Tank allowed to come back into service.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lessons Learned

• Inspectors missed this pipeline by not looking around for new pipelines when in the area

• Check out pipeline facilities in person; we called about this one and took operator’s word of regulatory exemption without verifying

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Another High Profile Accident in Alaska

• Alyeska Pump Station (PS) 9 – May 25, 2010– Overfilled Breakout Tank at PS 9– 5000 BBLs spilled out vents and into containment area.– Failed Unit Power System (UPS) prevented

communications, tank monitoring and valve control.– Tank appears to be damaged.– Issued a CAO requiring full time monitoring at PS9 and

staffing by OQ personnel at site. Verification that pipeline could operate without PS 9 relief.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Photo of Alyeska Spill

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lessons Learned

• Maintain Close Working Relationship with State and Federal OSCs

• Move Fast – Have an Enforcement Strategy to Move Quickly

• Focus on Change During Inspections

• Ensure Operators have Some or Sufficient Qualified Individuals Present During All Maintenance Operations

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Chevron – Salt Lake City, June 12, 2010 • Approx 750 BBL of crude spill into Salt Lake City creeks and small lakes on

June 11/12, 2010.

• Power company built substation immediately adjacent to pipeline. Fence post directly on top of pipeline.

• Fault current burned dime sized hole in pipeline.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Damaged Pipe - Salt Lake City, June 12, 2010

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned• Roll quick and get there quick

– Personal experience is to lean into it

• Put someone embedded in Unified Command during High Profile Accidents

• Just because you are talking to Operator and FOSC doesn’t mean your message is getting out; Goes better when people know someone is in charge (people want to be in loop)

– Keep State Partner informed first

– Work with Mayors or County Commissioners

– Volunteer to Speak at Community Meetings

– Talk to Congressman

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

• We need to spend more time on the right of way

• AC and fault current mitigation not being looked at hard enough

• ROW patrol methods are not appropriate for terrain or foliage cover

• Prediction – Rulemaking for remote valve actuation, or stronger focus on the preventative and mitigative part of IMP

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Salt Lake City, Utah – December 1, 2010

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Salt Lake City, Utah – December 1, 2010

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

• Don’t have a release in same area after remedial actions

• Make sure that the operators fix or your remedial actions didn’t introduce other risks

• Outreach needs to be even greater – Now regulator’s ability is in question.

• Figure out someway to give other stakeholder input

– Worked with Mayor’s consultant

– Realize that even then, you need to give local officials some credible input – valve placement planning, extra time.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Alyeska Pump Station 1January 8, 2011

• A crude oil release was discovered on the Trans-Alaska Pipeline (TAPS) at Pump Station #1 (PS1).

• The leak source was from below ground piping that led to the basement of the of booster pump building. The piping was encased in concrete and could not be accessed.

• The TAPS could not be operated without the booster pumps so the entire pipeline system needed to be shutdown to stop the leak and enact the repairs.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Alyeska Pump Station 1

• Cold weather and lowering crude oil temperatures within the TAPS pipeline became a serious concern.

• If the temperature on TAPS got much below freezing on other sections of the 800-mile long pipeline, or on idled North Slope production lines, there was a strong possibility of other crude oil releases occurring during the shutdown period or after eventual restart of the systems

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Alyeska Lesson Learned

• PHMSA needs inspectors to focus more on station piping during IMP inspections.

• Sync up expectations with other responders; in this case we were lucky to have a long standing relationship where we were comfortable recommending line be restarted with leak.

• Sometimes it is better to let someone else take lead and work behind scenes.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

San Bruno, CA - September 9, 2010

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

PG&E, San Bruno, CA September 9, 2010

• 30 inch gas transmission pipeline in dense suburb

• Ruptured at 6:11 pm during rush hour

• 8 fatalities, over 50 injuries

• 38 homes destroyed

• Over an hour to close two valves less than a 1 ½ miles apart

• Grandfathered Pipelines (1948 and 1956) – No hydro

• PG&E used Direct Assessment

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Lesson Learned

• Feds and State Need to support each other -

• Gas IMP rule is interpreted differently by different operators, States, and Feds

• NTSB doesn’t conduct investigations – they coordinate

• Helps if you have a strong enforcement record with operator in past

• Direct Assessment is being misapplied – many companies do not know what they have in ground

• Western Region had many small operators that had not gone through and IMP review in CA.

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Integrated Inspections• System approach – contiguous, same vintage,

same risks, one or more inspection units

• Heavy focus on Preparation to determine what to ask prior to inspections

• Tap multiple experts

• Data driven approach to determine where we focus our inspection resources

• Are beginning to find common precursors to recent incidents, e.g. hydraulic changes, parallel structures, AC interference, type of assessment

- 53 -

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Integrated Inspection

• Time consuming and labor intensive – taking 6 to 15 months from start to finish

• Teams are hard to assemble and coordinate

• Operators are complaining about time to conduct

• Staff committed to inspections for months – lose management ability to re deploy staff

• Concerns that if we wait too long to conduct periodic inspections that operator will backslide

• Inconsistency on II approach between regions needs to be reduced further

- 54 -

U.S. Department of Transportation

Pipeline and Hazardous Materials Safety Administration

Questions?