Former Potrero Power Plant Site Remediation
WELCOME PG&E Community Open House
Former Potrero Power Plant Site Remediation
ILLINO
IS ST.
Project Site
Hoe Down Yard CLEANUP COMPLETE
Switchyard/ Construction Yard CLEANUP COMPLETE
Tank Farm INVESTIGTATION
IN PROGRESS
Station A CLEANUP COMPLETE
N
Port Property
CLEANUP BEGINNING SUMMER 2018 OFFSHORE
SEDIMENT AREA
Northeast CLEANUP PLAN Area APPROVED
CLEANUP IN PROGRESS
Unit 3 Power Block Area
INVESTIGATION APPROVED
Port of San Francisco Property Offshore Sediment Area (SF Bay) PG&E Owned Properties Associate Capital Owned Properties Impacted by Historical MGP Activities
For illustrative purposes only. Approximate boundaries shown. Map not to scale.
Former Potrero Power Plant Site Remediation
Port Property
Station A
Tank Farm Northeast Area
Unit 3 Power Block
2
1
1
3
Associate Capital Owned Properties
Port of San Francisco Property Impacted by Historical MGP Activities
Solidification Area
Excavation Area
Northeast Area Cleanup
CLEANUP ACTIVITIES
• MGP residues on former Power Plant Property 1
are deeper and are being treated in-place
• Soil with MGP residues on Port Property are 2
shallower and will be excavated out
• A durable cover will be installed/restored 3
over the entire area
ANTICIPATED SCHEDULE
• In-place treatment: 1
July 2017 – October 2018
• Soil excavation: 2
July 2018 – November 2018
• Site restoration: 3
November 2018 – December 2018
WORK HOURS
• Monday – Friday, 7:00 AM – 6:00 PM (limited weekend and evening work, if needed)
Approximate boundaries shown. Map not to scale.
Former Potrero Power Plant Site Remediation
DRILL RIG / CRANE D
RIL
L / M
IXER
CEMENT MIX
PREPARATION
SOLIDIFIED / TREATED SOILS
Solidification Process/Equipment
1 Solidifcation mix will be injected into the ground.
2 The mix will solidify impacted soils in place
Images not to scale. For illustrative purposes only.
Former Potrero Power Plant Site Remediation
Northeast Area Cleanup: Trucking
• All efforts will be made to minimize the impact of truck traffc:
° Tires cleaned before leaving Site
° Trucks loads covered and contained for transport
° Use of approved truck routes avoiding residential neighborhoods
° Engine idling will be limited
20th St
23rd St
Cesar Chavez St
Cargo Way
Illin
ois
St
Illin
ois
St
Primary Truck Route to Highway 101 and 280
Secondary Truck Route to Highways
Truck Route to Railyard
TRUCK ROUTES
Former Potrero Power Plant Site Remediation
Offshore Sediment Cleanup (including early action)
CLEANUP ACTIVITIES
• Nearshore Area: Removal of impacted sediments and capping with natural materials
• Northern Transition Area: In-place treatment with activated carbon
• Southern Transition Area: Monitored natural recovery
• Early action: Targeted removal of wooden pilings along shoreline
ANTICIPATED SCHEDULE
• Early action: June-November 2018
• Cleanup construction: Between Summer and Fall 2019
Port Property
Station A
Tank FarmNortheastArea
Unit 3 Power Block
N
OFFSHORE SEDIMENT AREA
Associate Capital Owned Properties
Port of San Francisco Property Impacted by Historical MGP Activities
Transition Areas Where Impacts will be Addressed
Shoreline and Nearshore Areas Where Impacts Will be Addressed
Former Potrero Power Plant Site Remediation
A Healthy Marine Ecosystem
• Benthic organisms include a variety of invertebrates that live on or in underwater sediments
• They serve as an important food source for bottom-feeding fsh and some birds
• The presence of an abundant and diverse benthic community is one sign of a healthy marine ecosystem
Water
Healthy Benthic Community
Oxidized Sediment
For illustrative purposes only. Image not to scale.
Former Potrero Power Plant Site Remediation
Unit 3 Power Block
• Soil and groundwater investigations approved by Water Board in 2017
• Closure Plan/Final Remedy, including land use controls, in development
NEXT STEPS
• Summer 2018: Public review of Final Remedy
° 30-day comment period
° Fact sheet
• Fall/Winter 2018: Final Remedy approval / anticipated closure