    Seventh Five Year Plan (2016-2020)

    7FYP Implementation Progress Monitoring Indicators

    Ministry:Power, Energy & Mineral Resource

    Division:Energy & Mineral Resource

    Corporation:Bangladesh Oil, Gas & Mineral Corporation (Petrobangla)

    Executing Agency:Pashchimanchal Gas Company Limited (PGCL)

    Sl.

    No.Goals

    Target to

    attain

    Inputs indicators

    (Resources/policy

    changes etc.)

    Output indicators Impact indicators

    (1) (2) (3) (4) (5) (6)

    01. Gas

    Distribution

    Network At

    Belkuchi and

    ChauhaliUpazila

    2017~2019 Land acquisition, land

    compensation, route

    survey, land

    development, manpower

    engagement andpreparation of tender

    documents, appointment

    of contractors,

    procurement of

    materials.

    With the implementation

    of the proposed project

    about 1.79 MMCFD to

    9.09 MMCFD gas

    distribution will bepossible at Belkuchi and

    Chauhali Upazila from

    2017 to 2037 years.

    After implementation of the project, it will reduce

    deforestation and maintain environmental & ecological

    equilibrium to a greal extent.

    It has a positive impact in terms of employment in theoperation phase and construction phase that will help in

    poverty alleviation. Further, this will indirectly help in

    boosting up the national economic and social condition

    and also in increasing the productivity.

    02. Gas

    Distribution

    Network At

    Kamarkhanda

    Upazila

    2018~2020 Land acquisition, land

    compensation, route

    survey, land

    development, manpower

    engagement and

    preparation of tenderdocuments, appointment

    of contractors,

    procurement of

    materials.

    With the implementation

    of the proposed project

    about 0.60 MMCFD to

    4.50 MMCFD gas

    distribution will be

    possible at KamarkhandaUpazila from 2018 to

    2038 years.

    After implementation of the project, it will reduce

    deforestation and maintain environmental & ecological

    equilibrium to a greal extent.

    It has a positive impact in terms of employment in the

    operation phase and construction phase that will help inpoverty alleviation. Further, this will indirectly help in

    boosting up the national economic and social condition

    and also in increasing the productivity.

  • 8/10/2019 PGCL2

    2/4

    Attachment-2

    -2/4-

    Sl.

    No.Goals

    Target to

    attain

    Inputs indicators

    (Resources/policy

    changes etc.)

    Output indicators Impact indicators

    (1) (2) (3) (4) (5) (6)

    03. Vertical

    Extension of

    Bogra office

    building.Bogra (1st &

    2ndFloor).

    2015~2016 Preparation of tender

    documents, appointment

    of contractors.

    With the implementation

    of the proposed project

    the office facility to the

    employees of the Bograsales section will be

    resolved.

    After completion of the project it has a great positive

    impact over the employees of the Sirajganj sales section

    providing the proper working environment.

    Also improve the inter-personal relation and good

    communication among the employees of the area.

    04. Gas

    Distribution

    Network At

    Natore Town

    and LalpurUpazilla.

    2018~2020 Land acquisition, land

    compensation, route

    survey, land

    development, manpower

    engagement andpreparation of tender

    documents, appointment

    of contractors,

    procurement of

    materials.

    With the implementation

    of the proposed project

    about 5.82 MMCFD to

    16.05 MMCFD gas

    distribution will bepossible at Natore town

    from 2018 to 2038 years.

    After implementation of the project, it will reduce

    deforestation and maintain environmental & ecological

    equilibrium to a greal extent.

    It has a positive impact in terms of employment in theoperation phase and construction phase that will help in

    poverty alleviation. Further, this will indirectly help in

    boosting up the national economic and social condition

    and also in increasing the productivity.

    05. Gas

    Distribution

    Network at

    Rangpur Cityand its

    adjoiningarea.

    2018~2020 Land acquisition, land

    compensation, route

    survey, land

    development, manpowerengagement and

    preparation of tenderdocuments, appointmentof contractors,

    procurement of

    materials.

    With the implementation

    of the proposed project

    about 4.50 MMCFD to

    12.00 MMCFD gasdistribution will be

    possible at Natore townfrom 2018 to 2038 years.

    After implementation of the project, it will reduce

    deforestation and maintain environmental & ecological

    equilibrium to a greal extent.

    It has a positive impact in terms of employment in the

    operation phase and construction phase that will help inpoverty alleviation. Further, this will indirectly help inboosting up the national economic and social condition

    and also in increasing the productivity.

    06. Gas supply to

    Sirajganj 225

    2014~2017 Manpower engagement,

    preparation of tender

    With the implementation

    of the proposed project

    After implementation of the project it will be enhanced of

    35 MW power at National Grid and also help to reduce

  • 8/10/2019 PGCL2

    3/4

    Attachment-2

    -3/4-

    Sl.

    No.Goals

    Target to

    attain

    Inputs indicators

    (Resources/policy

    changes etc.)

    Output indicators Impact indicators

    (1) (2) (3) (4) (5) (6)

    MW

    Combined

    Cycle PowerPlant (2ndunit- Dual

    Fuel)

    documents, appointment

    of contractor,

    procurement of materials

    about 35 MMCFD gas

    supply will be possible

    at Sirajganj 225 MWCombined Cycle PowerPlant (2ndunit- Dual

    Fuel) under North-WestPower Generation

    Company.

    load shading locally and nationally.

    It has positive impact in terms of employment in theoperation phase and construction phase that will help inpoverty alleviation. Further this will indirectly help in

    boosting up the national economic and social conditionand also in increasing the productivity.

    07. Construction

    of 10 bar ring

    main

    (8"140

    Psig10.0Km) Gas

    Pipeline and

    DRS

    modification

    at Bogra

    Town.

    2016~2020 1. Procurement of

    materials.

    Construction of 10 bar

    ring main

    (8"140Psig10.0Km)Gas Pipeline at Bogra

    Town.

    2. Construction of

    03 nos DRS at Bogra

    town.

    3. Modification of

    Existing DRS at Bogra

    Town.

    With the implementation

    of the proposed project

    about 45 MMCFD gas

    supply will be possible

    at Bogra Town and alsohelp to supply gas

    distribution smoothly at

    Bogra Town

    After implementation of the project it will be reduced

    deforestation and maintain environment & ecological

    equilibrium to great extent.

    08. Construction

    of 2-StoriedofficeBuilding (6-

    storied

    foundation)

    for Sirajganj

    sales section

    2016~2019 Land acquisition, land

    compensation, routesurvey, landdevelopment and

    Preparation of tender

    documents, appointment

    of contractor

    With the implementation

    of the proposed projectthe office facility to theemployees of the

    Sirajganj sales section

    will be resolved.

    After completion of the project it has a great positive

    impact over the employees of the Sirajganj sales sectionproviding the proper working environment.

    Also improve the inter-personal relation and good

    communication among the employees of the area.

  • 8/10/2019 PGCL2

    4/4

    Attachment-2

    -4/4-

    Sl.

    No.Goals

    Target to

    attain

    Inputs indicators

    (Resources/policy

    changes etc.)

    Output indicators Impact indicators

    (1) (2) (3) (4) (5) (6)

    at Sirajganj

    Town.

    09. Gas supply to

    Sirajganj 367

    MW

    Combined

    Cycle IPP

    2015~2018 Manpower engagement,

    preparation of tender

    documents, appointment

    of contractor,

    procurement of materials

    With the implementation

    of the proposed project

    about 55 MMCFD gas

    supply will be possible

    at Sirajganj 225 MW

    Combined Cycle Power

    Plant (2ndunit- Dual

    Fuel) under North-West

    Power Generation

    Company.

    After implementation of the project it will be enhanced of

    55 MW power at National Grid and also help to reduce

    load shading locally and nationally.

    It has positive impact in terms of employment in the

    operation phase and construction phase that will help in

    poverty alleviation. Further this will indirectly help in

    boosting up the national economic and social condition

    and also in increasing the productivity.

    10. Gas supply toSirajganj 214

    MW

    Combined

    Cycle Power

    Plant

    2016~2019 Manpower engagement,preparation of tender

    documents, appointment

    of contractor,

    procurement of materials

    With the implementationof the proposed project

    about 35 MMCFD gas

    supply will be possible

    at Sirajganj 225 MW

    Combined Cycle Power

    Plant (2ndunit- Dual

    Fuel) under North-West

    Power Generation

    Company.

    After implementation of the project it will be enhanced of35 MW power at National Grid and also help to reduce

    load shading locally and nationally.

    It has positive impact in terms of employment in the

    operation phase and construction phase that will help in

    poverty alleviation. Further this will indirectly help in

    boosting up the national economic and social condition

    and also in increasing the productivity.