pert/activity diagrams, completion probability and the z score source: bob hugg, thinking in project...

10
PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

Upload: leon-shaw

Post on 17-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

1

PERT/Activity Diagrams,Completion Probability

and the Z ScoreSource: Bob Hugg, Thinking in Project Management Terms

Page 2: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

2

• Define the goal of the project and the tasks required to complete it

• Place tasks in a logical order and determine the critical path– The critical path is the longest time path through the

network of tasks• Generate a set of duration estimates for each task– An optimistic, a most likely, and a pessimistic– Label as a, b, c, or as TO, TL, TP

PERT/CPM

Page 3: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

3

• TE = (TP + 4TL + TO)/6• Complete the above for all tasks• The sum of duration of tasks on the critical

path will determine the project duration

Calculate PERT for each task

Page 4: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

4

• Standard deviation is the average deviation from the estimated time– As a general rule: the higher the SD, the greater the amount

of uncertainty)– SD = (TP – TO)/6

• Variance reflects the speared of a value over a normal distribution– V = (SD)2

• SD and V are very useful in determining the probability of a project meeting its desired completion time

Calculate standard deviation and variance

Page 5: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

5

Sample table for the estimates

Page 6: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

6

Consider the following tasks and activity diagram

Page 7: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

7

Populate table with sample data

Page 8: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

8

Table of estimates with start dates

Page 9: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

9

• A wealth of information in the above table– Critical tasks, non-critical tasks, best and worst estimates

and the expected duration for each, SD and V values• Calculate probability of project completion on a

desired date1. S: the sum of all expected durations on the critical path2. V: the sum of all variances on the critical path3. D: Select a desired completion time4. Compute Z = (D-S)/√v5. Look up the value of Z (e.g., here)

Determine completion probability

Page 10: PERT/Activity Diagrams, Completion Probability and the Z Score Source: Bob Hugg, Thinking in Project Management Terms 1

10

• What is the probability of completing the project in 15 days?

• Z = (D-S) /√V = (15 – 15.51) / √2.51 = -0.51/1.59 Z = -.321• A corresponding probability value for Z is 37.7%• There is 38% probability that the project will be

completed within 15 days of the start day

An example