performance review of new outer drain, nyrstar myra falls · dear nicole, 1 introduction and terms...
TRANSCRIPT
ROBERTSON GEOCONSULTANTS INC. A Robertson Group Company
Consulting Engineers and Scientists for the Mining Industry Suite 640, 580 Hornby St., Vancouver BC, Canada V6C 3B6
Phone (604) 684-8072 Fax (604) 684-8073 www.robertsongeoconsultants.com
Page 1
December 28th
, 2016
RGC Report No: 212010/3
Environment Department
Nyrstar Myra Falls
Attention: Nicole Pesonen
RE: Performance Review Of New Outer Drain, Nyrstar Myra Falls
Dear Nicole,
1 Introduction and Terms of Reference
This letter report summarizes the results of a performance review (including hydraulic
testing) of the New Outer Drain (NOD) at Nyrstar Myra Falls (NMF). This review was
completed by Robertson GeoConsultants (RGC) from October 2015 to June 2016.
Provided here are monitoring data for that period and recommendations for future
operation of the NOD.
Hydraulic testing was completed as part of developing a site-wide seepage control plan
for NMF. The hydraulic testing campaign consisted of systematically varying flow from
the different sections of the NOD while monitoring water levels, groundwater quality,
and water quality in Myra Creek. The objective of this investigation was to evaluate the
effectiveness of the NOD to capture seepage flows during various hydraulic regimes and
to determine appropriate settings for the drain system.
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 2
2 Background
The NOD was constructed in 2004 and 2005 as part of the Seismic Upgrade Project
(Klohn Crippen, 2006). The NOD was constructed to replace the Area II Outer Drain
should it be damaged during construction of the Seismic Upgrade Berm. The NOD was
also intended to improve performance of the Area II Outer Drain system by reducing the
bypass of impacted groundwater to Myra Creek between Stations 1+050 m to 1+250 m
(Klohn Crippen, 2004).
Figure 1 shows a location plan of the Old TDF and the various elements comprising the
NOD system. The NOD consists of a system of three separate drain sections referred to
as (i) Short Drain, (ii) Medium Drain and (iii) Long Drain. Each section consists of 450
mm and 550 mm diameter perforated drain pipes in a trench backfilled with minus 10
mm granular fill.
Flows from the Short, Medium, and Long Drains are directed into a solid pipe that
conveys water to Pumphouse #4. Electronically-controlled sluice gates were installed on
the discharge pipe of each of these new drain sections to control the flow out of the drain.
These gates are adjusted manually at Pumphouse #4.
Each of the NOD drains is typically run well below full capacity. In 2014 and 2015, the
NOD system was mostly run at a setting of “10-0-10”, representing 10% opening for the
Medium Drain, 0% opening for the Short Drain and 10% opening for the Long Drain.
Note that the Short Drain at a 0% setting is equivalent to 0.5% opening.
The Old TDF Drain System was previously tested by Marsland Environmental Associates
(Marsland, 2011). Hydraulic testing was completed from September to November 2010
and consisted of testing the different portions of the NOD under three different gate valve
settings (0%, 20%, and 100%). Marsland (2011) recommends setting the drain system at
a minimum of 10-0-5 (i.e., Medium Drain at 10%, Short Drain at 0%, and Long Drain at
5%).
The Marsland study has several limitations:
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 3
Testing was completed over a short period of time (September to November), so
the study was not able to address the effects of seasonal variations on drain
performance.
Monitoring of hydraulic gradients and water quality south of Myra Creek were
not possible at the time, as wells MW13-16S/D and MW13-18S/D had not been
installed in 2010.
Monitoring of hydraulic gradients and water quality between the creek and the
drain system were limited to a single location (i.e., the Long Drain at well cluster
MW-A to MW-F) because groundwater monitoring wells located between Myra
Creek and the New Medium Outer Drain (MW13-14S/D and MW13-15S/D) were
not yet installed in 2010.
RGC completed further drain testing between October 2015 and June 2016. This testing
was completed over an extended period of time (from October 2015 to June 2016) and it
benefited from additional monitoring wells (i.e. the ‘MW13’ well series; see RGC,
2013).The results of RGC’s drain testing are summarized below.
3 Performance Review of New Outer Drain System
A total of nineteen (19) tests were performed during various hydrogeological conditions
including:
Late summer low flow.
Fall moderate flow.
Winter low flow.
Spring Freshet.
High flow (or storm) events.
Sluice gate positions for each section of the NOD were varied systematically during each
hydraulic regime while hydraulic performance (water levels), groundwater quality, and
water quality in Myra Creek were monitored.
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 4
3.1 Methods
Groundwater levels were measured manually before and after varying drain settings at
the following locations:
Upstream of the NOD at the Old TDF.
Adjacent to the NOD (Hillside and Creekside).
In standpipes completed right along the NOD.
Downstream (south-east) of Myra Creek
Myra Creek water levels were monitored as follows:
Automated measurements in fifteen (15) minute intervals at the car bridge using a
pressure transducer,
Manual depth-to-water readings taken off a marked rebar installed within the
creek (initial top-of-rebar survey completed by NMF personnel), and
Creek levels surveyed directly by NMF personnel at locations aligned with
groundwater monitoring points.
Water quality sampling allows evaluating drain performance as seepage bypass can be
detected in the form of increased metal concentrations. Groundwater quality samples
were collected at select monitoring wells:
Creekside of the NOD at MW13-14S and MW13-15S.
South of Myra Creek at MW13-16S and MW13-18S.
Water quality in Myra Creek was sampled during the drain testing campaign as follows:
Grab samples at Station 0+800 North and South and at TP4 North and South,
analyzed on site for total Zn by NMF personnel.
Daily water quality samples for Zn downstream of the site at MC-TP4 using an
automated, on-site Atomic Absorption (AA) Spectrophotometer.
After a primary survey had been completed, drain settings were varied and samples taken
once equilibrium had been reached.
3.2 Hydraulic Performance
Hydraulic performance of the drain system was evaluated by measuring groundwater and
surface water levels and examining the resulting hydraulic gradients. The NOD is
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 5
considered to be effective in capturing groundwater seepage if water levels in the drain
are below the river level and adjacent groundwater levels, i.e. hydraulic gradients are
reversed and are directed towards the NOD.
Figures 2a and 2b show detailed water level plots for surveys performed on December 10,
2015 and May 10, 2016 respectively. A complete set of longitudinal water level sections
for all testing completed by RGC as part of this study is provided in Appendix A. These
cross-sections show the elevation of the following:
Short, Medium, and Long Drains.
Myra Creek bed.
Water surface level of Myra Creek.
Water levels in the NOD obtained from standpipe piezometers P1 to P5.
Water levels in observation wells MW13-14S and MW13-15S.
In general, the drain is providing hydraulic control (i.e. prevents seepage by-pass) if the
water levels measured in the drain (orange line) is higher than the creek level (blue line).
The NOD was set to 5/0/5 on December 10th
, 2015. Figure 2a shows that hydraulic heads
measured in standpipes next to the NOD (P1 to P5) are above the nearby creek level and
groundwater levels in downgradient monitoring wells. This suggests that the NOD was
not able to provide full hydraulic control during this testing event as the general hydraulic
gradient is directed from the drain towards Myra Creek.
Transverse sectional plots of water levels were also created at standpipes P4 (A–A’) and
P5 (B-B’) (see Figure 1 for location) to further illustrate the groundwater flow field near
the drain system. Figures 3a and 3b show transverse sections (along flow path) for P4 and
P5 respectively on December 10, 2015 (drain set to 5/0/5). It is evident that creek levels
are slightly below the water level in the drain system, indicating that flow is towards the
creek. This suggests that impacted groundwater from the Old TDF reach is partially
bypassing the NOD at this section.
Figures 4a and 4b show another set of cross-sectional water level plots for testing
performed on May 10, 2016 with a drain setting of 10/0/10. This transverse section
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 6
clearly illustrates that the drain has effected a reversal in local groundwater flow (from
Myra Creek towards the drain) and hence provides adequate hydraulic control.
Table 1 summarizes all the drain testing performed by RGC and indicates whether the
individual sections of the NOD system are providing hydraulic control along Myra Creek.
Analyzing all longitudinal cross-sections suggests that the NOD generally provides
adequate hydraulic control and effectively captures shallow seepage flows when sluice
gates are set to 10-0-10 (Medium, Short, and Long Drain) or higher. Lower settings, that
is further restricting flow from the drain system (5-0-5), have only proven to work for one
survey during low flow conditions (4,370 L/s in Myra Creek).
Note that periods of unfavourable hydraulic conditions do not necessarily imply that
seepage immediately discharges into Myra Creek. It was estimated that travel times for
contaminants are in the order of 4 to 10 days for a distance of around 15 m between the
NOD and Myra Creek. If hydraulic gradients are reversed, contaminant transport is also
reversed. Hence it is important to analyze water quality data collected during testing and
routinely over longer periods of time.
3.3 Water Quality Performance
Water quality was sampled at MW13-14S (Medium NOD) on May 10 and May 24, 2016
with total Zn concentrations of 2.0 mg/L Zn and 1.5 mg/L Zn, respectively. These
samples were taken during spring freshet with drain settings of 10/0/10 and 30/0/10,
respectively. Hydraulic gradients are directed towards the drain suggesting that the NOD
was able to intercept the majority of seepage flows at the time of measurement. The
moderate Zn concentrations, however, indicate some seepage bypass occurring. At
MW13-15S, Zn concentrations of 0.2 mg/L Zn and 0.08 mg/L Zn were observed on May
10th
and May 24th
, 2016. These data suggest little bypass at the downstream end of the
Medium Drain.
A review of routine water quality monitoring performed within the Lower Old TDF
Reach (not shown here) suggests the following:
Groundwater in the Myra Valley aquifer (MVA) beneath the Old TDF is highly-
impacted by seepage from WRDs #1 and #6. For example, up to 23 mg/L Zn has
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 7
been observed in groundwater from well TD13-05D. This screened in the shallow
MVA sediments upgradient of the NOD.
Groundwater immediately upstream of the drain at MW-A (deep) and MW-D
(shallow) was characterized by total Zn concentrations of 26.7 mg/L Zn and 20.1
mg/L Zn, respectively. These data are for September 2015. Zn concentrations are
usually higher in the deeper monitoring well, MW-A.
Groundwater on the creek-side of the Long Drain at MW-C (deep) and MW-F
(shallow) has shown Zn concentrations of up to 14.6 mg/L Zn and 3.9 mg/L Zn,
respectively (see Figure 5). Zn concentrations are generally higher in the deeper
monitoring well (MW-C). Zn concentrations in both wells varies, yet no
correlation between Zn concentrations and Myra Creek flows is evident.
MW13-14S/D between Myra Creek and the Medium Drain has shown Zn
concentrations of up to 17.5 mg/L Zn (MW13-14S) and 15.5 mg/L mg/L Zn
(MW13-14D) (see Figure 5). Again, water quality varies over time but there is no
apparent trend or correlation with creek flows is evident. This suggests that some
performance of the Medium Drain at this location varies and seepage is
bypassing.
MW13-15S/D between Myra Creek and the downstream end of the Medium
Drain has shown Zn concentrations of up to 0.9 mg/L Zn (MW13-15S) and 0.03
mg/L Zn (MW13-15D). This suggests that the drain at this location is performing
well and/or dilution from the creek is occurring.
Zn concentrations in groundwater downstream of Myra Creek at MW13-18S/D
(Figure 6) are around 0.1 mg/L Zn or lower. These concentrations suggest minor
reflect relatively unimpacted conditions.
3.4 Loading to Myra Creek
In order to quantify contaminant loads within various sections of Myra Creek, results of
detailed water quality sampling along Myra Creek (“Myra Creek profiles”) were
analyzed. Between 2012 and 2016, a total of thirty-three (33) water quality sampling
campaigns were undertaken during open water season. Each sampling event consisted of
collecting water samples from Myra Creek at twenty (20) equally-spaced stations ranging
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 8
from upstream at the car bridge (station MC-S11) to the downstream end of the site at
station MC-TP4. Samples were collected on the north bank of the creek and, on several
occasions, also on the south bank.
Figures 6a and 6b show Zn loads within the various reaches of Myra Creek for every
sampling event from 2012 to 2016. Total Zn loads within the creek range from 4.8 kg/day
(in July 2014) to 77.4 kg/day in February 2015. Zn loading in Myra Creek within the
Lower Old TDF Reach (shown in yellow) varies from ~0 kg/d (September 2014) to 14.4
kg/d in August 2015. The creek is protected by the NOD in this area.
There is no clear pattern evident during which conditions the Lower Old TDF Reach is
contributing larger Zn loads to Myra Creek. This suggests that the performance of the
NOD is variable and that seepage bypass is occurring. Note that wells MW13-14S/D (at
Station MC 1+250 between Myra Creek and the Medium NOD) has shown elevated Zn
concentrations.
On average, these loads represent around 10% of the total Zn load within Myra Creek
detected at MC-TP4. Therefore, it can be concluded that the NOD system effectively
captures the majority of highly contaminated seepage flows in the lower Old TDF reach
migrating towards Myra Creek.
4 Key Findings and Recommendations
4.1 Key Findings
The Lower Old TDF Reach has an existing seepage interception system (SIS) that
consists of the Old Outer Drain and the NOD. Both drains are adjacent to Myra Creek
and are located about 1 to 2 m below the creek bed. Further upstream, the Inner Drain
captures seepage from the portion of WRD#1 that is buried by tailings in the Old TDF.
The key findings from the hydraulic testing of the NOD in the Lower Old TDF Reach are
summarized here:
Analysis of water level measurements within the NOD, surrounding aquifer, and
Myra Creek suggests that the NOD generally provides adequate hydraulic control
when sluice gates are set to 10-0-10 (Medium, Short, and Long Drain) or higher.
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 9
In other words, hydraulic gradients are generally directed towards the drain
system suggesting that shallow seepage flow is largely captured.
Groundwater sampling of monitoring wells screened between Myra Creek and the
NOD indicate that some seepage is regularly bypassing the NOD at selected
locations, e.g. near Station MC 1+250 (Medium NOD). Monitoring wells at the
downstream end of the Medium NOD, however, show only slightly elevated Zn
concentrations, which suggests that the drain is performing well at this location
and/or dilution from the creek is occurring. This indicates that there is spatial and
temporal variability in the performance of the drain system.
Sampling of Myra Creek shows that Zn loading is regularly entering Myra Creek
within the Lower Old TDF Reach. Bypass appears to vary temporally with no
clear pattern. The Zn load contribution from the Lower Old TDF Reach, however,
only represents about 10% of the overall load found in Myra Creek.
Groundwater downstream of Myra Creek is relatively unimpacted indicating that
there is very limited underflow of impacted groundwater leaving the mine site.
These findings demonstrate that the NOD is generally working as intended, capturing the
majority of the contaminant plume migrating underneath the Old TDF. Select monitoring
wells between the drain system and the creek are elevated in zinc and seepage is regularly
bypassing at certain locations. However, water quality surveys along Myra Creek suggest
that the resulting Zn loading to Myra Creek along this Lower Old TDF reach is relatively
small. It appears that unfavourable hydraulic conditions only last for a short period of
time (say a few days) and hydraulic gradients are reversed shortly after resulting in
relatively low net by-pass.
4.2 Recommendations
The NOD in the Lower Old TDF Reach is generally working as intended and therefore
capturing the majority of seepage flows within this reach. There is currently no need to
install additional seepage control measures. RGC recommends the following for the
operation of the existing NOD:
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 10
Operation of the NOD should continue at settings of 10/0/10
(Medium/Short/Long) as it appears to effectively protect Myra Creek.
Improve water management on site, that is provide enough treatment and/or
storage capacity to continue operation of the Inner Drain and NOD during high
flow events.
Continue routine (quarterly) water quality monitoring in the Lower Old TDF
Reach to monitor drain performance and detect potential seepage bypass.
Continue monthly water quality surveys of Myra Creek to detect load increases
within the creek.
Include drain system standpipe piezometers P1 to P5 in quarterly site-wide water
level survey.
Record sluice gate settings and daily flows from Pumphouse #4 in an electronic
database.
To further improve operation of the NOD system, RGC recommends continuous
monitoring of the hydraulic performance of the NOD. This monitoring network would
include the following:
Installation of pressure transducers in drain standpipe piezometers P1, P2, P3, P4,
and P5.
Installation of pressure transducers in monitoring wells screened between the
NOD and Myra Creek, more specifically MW-F, MW13-14S, and MW13-15S.
Placement of barometric pressure logger in vicinity of the NOD.
Manual groundwater level measurements in standpipe piezometers P1 to P5 in
conjunction with quarterly groundwater surveys.
RGC recommends downloading water level logger data quarterly and conducting a yearly
review of the NOD performance. Continuous monitoring of the hydraulic performance of
the NOD would allow the following:
Document the performance of the NOD.
Further identify under which circumstances unfavorable hydraulic conditions
exist at the NOD and determine their duration.
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 11
Reconcile results of water quality surveys conducted routinely in Myra Creek
(MC-TP4) with hydraulic performance monitoring of the NOD.
Monitor NOD performance during planned testing of the Lynx Seepage
Interception System.
Nyrstar Myra Falls
Performance Review Of New Outer Drain December 2016
Page 12
5 Closure
We trust that the information provided in this letter report meets your requirements.
Please contact the undersigned if you have any questions regarding the content or require
further information.
Best Regards,
ROBERTSON GEOCONSULTANTS INC.
Alex Trapp
Alex Trapp, M.Sc. Christoph Wels, Ph.D., M.Sc., P.Geo.
Water Resources Engineer Principal Hydrogeologist
6 References
Marsland Environmental Associates (2011), Myra Falls Operations, Report on the TDF
Under Drain, May 2011.
Klohn Crippen (2004), Myra Falls Tailings Disposal Facility, Seismic Upgrade Project –
Optimization of New Outer Drain System Layout”, Report submitted to Boliden Westmin
(Canada) Ltd., dated April 2, 2004.
Robertson GeoConsultants Inc. (2013), 2013 Hydrogeological Drilling Program Report,
Nyrstar Myra Falls , RGC Report No. 212001/4, May 2014.
TABLES
Table 1 Summary of Hydraulic Testing of New Outer Drain
Med Short Long
5‐Oct‐15 Summer/Fall Low Flow 0.66 0.049 10/0/10 4‐Nov‐15 Fall Low/Moderate Flow 0.87 0.089 10/0/5 10‐Dec‐15 Winter High Flow 1.32 NS 5/0/5 ‐ ‐ 11‐Jan‐16 Winter Low Flow (Snow) 0.26 0.085 10/0/10 ‐ 27‐Jan‐16 High Flow Event 2.49 0.057 0/0/0 ‐ ‐10‐May‐16 Spring Freshet 1.02 0.04 10/0/10 24‐May‐16 Spring Freshet 0.94 0.034 30/0/10 6‐Jun‐16 Spring Freshet 1.23 0.039 3/0/3 ‐ ‐
7‐Oct‐15 Summer/Fall Low Flow 0.3 0.06 5/0/5 7‐Oct‐15 Summer/Fall Low Flow 0.3 0.06 0/0/0 ‐ ‐ 8‐Oct‐15 Summer/Fall Low Flow 0.41 0.067 0/5/0 ‐ ‐ 8‐Oct‐15 Summer/Fall Low Flow 0.41 0.067 0/15/0 ‐ ‐ 9‐Oct‐15 Summer/Fall Low Flow 0.76 0.042 5/0/0 ‐ ‐ 9‐Oct‐15 Summer/Fall Low Flow 0.76 0.042 5/0/5 ‐ 5‐Nov‐15 Fall Low/Moderate Flow 0.58 0.073 10/0/10 6‐Nov‐15 Fall Low/Moderate Flow 1.17 0.057 5/0/10 ‐ 12‐Jan‐16 Winter Low Flow (Snow) 0.48 0.093 5/0/5 ‐ 13‐Jan‐16 Winter Low Flow (Snow) 0.71 0.086 10/0/5 ‐ ‐ 12‐May‐16 Spring Freshet 1.16 0.035 30/0/10
T‐Zn at TP4 [mg/L]
Secondary Surveys
Hydraulic PerformanceSurvey Date Myra Creek Conditions
Pump House 4 Valve Settings MED/SHRT/LNG
Primary surveys
Pump House 4 Flow to Superpond
Myra Creek Stage at Carbridge [m]
FIGURES
G
G
G
G
!.!.
!.!.
!.
!.!.
!.!.
!.!.
!.
!.!.
!.!.
!.!.!.!.!.
!.!.
!.!.
!.!.
!.!.!.
!.!.
!.!.!.!.
!.!.
!.!.!.!.
!.
!.!.!.
!.!.!.
!.!.
!.!.
!.!.
!.!.
!.!.
!> !>
!>
!>
!>
!>!.
!.
3
3A
4
RSA DECANT
APA DECANT
STRIPDECANT
RECLAIMSANDSAREA
WRD #6
BACKFILLO/F DISCHARGE
HUT B
Amalgamated Paste Area(APA)
OLD TDF
PASTEBERM
SPILLWAY
STRIP SPILLWAY
HW Headframe
BACKFILLPLANT
QUARRY
ADIT10 LEVEL
ADIT9 LEVEL
ADIT11 LEVEL(MYRA DECLINE)
TO CAMPBELL RIVER
MYR A
CREEK
0+10
00+00
0
0+20
0
0+30
0
0+40
0
0+50
0
0+60
0
0+70
0
0+80
0
0+90
0
1+00
0
1+100
1+200
1+300
1+400
SHORT NEWOUTER DRAIN
MEDIUM NEWOUTER DRAIN
LONG NEWOUTER DRAIN
NEW OUTER DRAINDISCONNECTED
OLD OUTER DRAINDISCONNECTED
OLD OUTER DRAIN
GG
Inner Drain
Lynx Diversion Channel
CASCADE REACH
UPPER REACH
LOWER REACH
A
A'B
B'
PH#4
MW04-02
MW04-01
MW11-05S/D
MW-G
MW-FMW-E
MW-DMW-C
MW-BMW-A
MW13-17
MW13-13
MW13-12
TD13-05S/D
TD13-04S/D
TD13-03S/D
TD13-02S/D
TD13-01S/DMW13-18S/D
MW13-16S/D
MW13-15S/D
MW13-14S/D
MW13-11S/D
MW13-10S/D
MW13-09S/DMW13-08S/D
MW15-14
MW15-13S/D MW15-12S/D MW15-08S/DMW15-05S/D
MW15-04S/D
MW15-02S/D
MW15-01S/D
MW15-03S/M/D
GG
MW15-11S/D
GG
MW15-10S/D
GG
MW15-09S/D
GG
MW15-06S/D
GG
MW15-07S/M/D
MW16-03 GG
MW16-02MW16-01
P6
P5
P4
P3
P2P1
MC-TP4
300030
00
3500
3500
4000
« 0 200100Metres
Layout of New Outer Drain and Monitoring NetworkMyra Falls Mine Site
SCALE 1:2,500
Legend
Projection: Local Grid System, Mine Datum (m)Contour Interval: 5 m
Report No: 212009/1Drawn: L.R.Nyrstar Myra Falls, BC, Canada
Figure: 1Client:Project No: 212009
Last Update: Dec 23, 2016
Original File: Fig1_NOD_Monitoring_Network.mxd
Project: Contaminant Load Balance
Waste Rock Dump (WRD)
Cyclone Sand
Tailings DamsPaste TailingsCycloned Fine TailingsInner Drain
Myra CreekOld Outer Drain
Long New Outer DrainMedium New Outer DrainShort New Outer Drain
New Outer Drain (Disconnected)
Standpipe PiezometerMonitoring Well!.
> Transverse Section Line
A A'
Surface Water Sampling Station!.
Client:Project: Myra Falls Seepage Control Plan
Figure: 2a
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: 2b
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:
Project: 2015/2016 Site-Wide SIS Study
Figure: 3a
Report No: 212009/1Original File
Project No: 212009
Last Update: 23 June 2016
Transverse Water Level Section at P4 (A-A’)
TD13
-05D
P4
MW
13-1
4S C
or.
Cree
k
Cree
k
3,347.0
3,348.0
3,349.0
3,350.0
3,351.0
3,352.0
3,353.0
3,354.0
0 5 10 15 20 25 30 35 40
Wat
er Le
vel [
m]
25 = ~200 m
P4 Groundwater Elevation Section Dec 10, 2015
Water Level Elevation Myra Creek Bed Medium New Outer Drain
A A’
Client:
Project: 2015/2016 Site-Wide SIS Study
Figure: 3b
Report No: 212009/1Original File
Project No: 212009
Last Update: 23 June 2016
Transverse Water Level Section at P5 (B-B’)
TD13
-05D
P5
MW
13-1
5SCr
eek
Cree
k
3,347.0
3,348.0
3,349.0
3,350.0
3,351.0
3,352.0
3,353.0
3,354.0
-5 0 5 10 15 20 25 30 35 40 45
Wat
er Le
vel [
m]
25 = ~200 m
P5 Groundwater Elevation Section December 10, 2015
Water Level Elevation Myra Creek Bed Medium New Outer Drain
B B’
Client:
Project: 2015/2016 Site-Wide SIS Study
Figure: 4a
Report No: 212009/1Original File
Project No: 212009
Last Update: 23 June 2016
Transverse Water Level Section at P4 (A-A’)
TD13
-05D
P4
MW
13-1
4S C
or.
Cree
kCr
eek
MW
13-1
6S
3,347.5
3,348.0
3,348.5
3,349.0
3,349.5
3,350.0
3,350.5
3,351.0
3,351.5
3,352.0
0 5 10 15 20 25 30 35 40
Wat
er Le
vel [
m]
25 = ~200 m
P4 Groundwater Elevation Section May 10, 2016
Water Level Elevation Myra Creek Bed Medium New Outer Drain
A A’
Client:
Project: 2015/2016 Site-Wide SIS Study
Figure: 4b
Report No: 212009/1Original File
Project No: 212009
Last Update: 23 June 2016
Transverse Water Level Section at P5 (B-B’)
TD13
-05D
P5
MW
13-1
5SCr
eek
Cree
k
MW
13-1
8S
3,347.0
3,347.5
3,348.0
3,348.5
3,349.0
3,349.5
3,350.0
3,350.5
3,351.0
3,351.5
3,352.0
-5 0 5 10 15 20 25 30 35 40 45
Wat
er Le
vel [
m]
25 = ~200 m
P5 Groundwater Elevation Section May 10, 2016
Water Level Elevation Myra Creek Bed Medium New Outer Drain
B B’
Client:
Project: 2015/2016 Site-Wide SIS Study
Figure: 5
Report No: 212009/1Original File
Project No: 212009
Last Update: 23 June 2016
Transverse Water Level Section at P5 (B-B’)
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Jul-13 Sep-13 Nov-13 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Dec-14 Feb-15 Apr-15 Jun-15 Aug-15 Oct-15 Dec-15 Feb-16 Apr-16 Jun-16
Zn (μ
g/L)
MW13-14D MW13-14S MW13-15D MW13-15S MW-C MW-F
Client:
Project: 2015/2016 Site-Wide SIS Study
Figure: 6
Report No: 212009/1Original File
Project No: 212009
Last Update: 23 June 2016
Transverse Water Level Section at P5 (B-B’)
1
10
100
1000
Jul-13 Sep-13 Nov-13 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Dec-14 Feb-15 Apr-15 Jun-15 Aug-15 Oct-15 Dec-15 Feb-16 Apr-16 Jun-16
Zn (μ
g/L)
MW13-17 MW13-18D MW13-18S MW13-16D MW13-16S
Client:Project: Contaminant Load Balance
Figure: 7a
Report No: 212009/1Original File
Project No: 212009
Last Update: Nov 2016
Zinc Loads in Myra Creek, 2012 to 2015
9,367
10,240
14,700
16,270
5,964
4,206
9,462
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12
Zinc
Load
[kg/
d]
2012 Myra Creek Zinc Loads
Lower Old TDF
Upper Old TDF
Effluent
Lynx Reach
Myra Creek Background at MC-M14,156 Myra Creek Flow Rate [L/s]
August Effluent T-Zn estimated
4,827
10,850
7,621 3,462
2,367
5,197
3,078
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13
Zinc
Load
[kg/
d]
2013 Myra Creek Zinc Loads
Lower Old TDF
Upper Old TDF
Efluent
Lynx Reach
Myra Creek Background at MC-M14,156 Myra Creek Flow Rate [L/s]
4,251
9,574
5,472
3,571
1,917 1,633
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14
Zinc
Load
[kg/
d]
2014 Myra Creek Zinc Loads
Lower Old TDF
Upper Old TDF
Effluent
Lynx Reach
Myra Creek Background at MC-M1
4,156 Myra Creek Flow Rate [L/s]
4,715
7,288
9,5528,098
4,577
2,628
2,003
2,766
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15
Zinc
Load
[kg/
d]
2015 Myra Creek Zinc Loads
Lower Old TDF
Upper Old TDF
Effluent
Lynx Reach
Myra Creek Background at MC-M1
4,156 Myra Creek Flow Rate [L/s]
4,150
Client:Project: Contaminant Load Balance
Figure: 7b
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Zinc Loads in Myra Creek, 2016
15,679
10,280 7,049
7,920
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
Apr-16 May-16 Jun-16 Jul-16
Zinc
Load
[kg/
d]
2016 Myra Creek Zinc Loads
Lower Old TDF
Upper Old TDF
Effluent
Lynx Reach
Myra Creek Background at MC-M1
4,156 Myra Creek Flow Rate [L/s]
July Effluent T-Zn estimated
APPENDIX A
NOD Hydraulic Testing Results
Client:Project: Myra Falls Seepage Control Plan
Figure: A1
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A2
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A3
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A4
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A5
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A6
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A7
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A8
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A9
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A10
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A11
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A12
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A13
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A14
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A15
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A16
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A17
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain
Client:Project: Myra Falls Seepage Control Plan
Figure: A18
Report No: 212009/1Original File
Project No: 212009
Last Update: 28 July 2016
Longitudinal Water Level SectionNew Outer Drain