performance based payments (pbps) webcast 8.2… · \⠀搀尩 liquidating performance-based...

80
One AFMC…Powering the World’s Greatest Air Force PERFORMANCE BASED PAYMENTS (PBPs) Hosted By: Defense Pricing and Contracting Sponsored By: Defense Acquisition University Presented By: Derek Kuba AFMC/PKF Unclassified

Upload: others

Post on 19-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

  • One AFMC… Powering the World’s Greatest Air Force

    PERFORMANCE BASED PAYMENTS (PBPs)

    Hosted By:Defense Pricing and Contracting

    Sponsored By:Defense Acquisition University

    Presented By:Derek KubaAFMC/PKF

    Unclassified

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Contents

    2

    • PBP Overview• Developing PBP Events & Completion Criteria• Valuing PBP Events• PBP Clauses

    Unclassified

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Overview

    3Unclassified

  • One AFMC… Powering the World’s Greatest Air Force

    Basic Terms/Concepts

    4Unclassified

    • Generally, two types of payments:– Contract Financing Payment - a Government

    disbursement “Funding” made under a contract clause or other authorization prior to acceptance of supplies or services by the Government.

    – Invoice Payment - a Government disbursement made under a contract or other authorization for supplies or services accepted by the Government.

  • One AFMC… Powering the World’s Greatest Air Force

    Basic Terms/Concepts

    5Unclassified

    • Liquidation (of contract financing payments)- Process of lowering the outstanding balance

    of financing payments and converting some portion of them to partial or final (i.e. non-refundable) payment status

    - Un-Liquidated contract financing payments must be returned in the event of termination*

    * To the extent that they have not yet been earned through partial or complete performance

    (Reference: FAR 32.1004(d))

    PresenterPresentation Notes (d) Liquidating performance-based finance payments. Performance-based amounts shall be liquidated by deducting a percentage or a designated dollar amount from the delivery payments. The contracting officer shall specify the liquidation rate or designated dollar amount in the contract. The method of liquidation shall ensure complete liquidation no later than final payment.           (1) If the contracting officer establishes the performance-based payments on a delivery item basis, the liquidation amount for each line item is the percent of that delivery item price that was previously paid under performance-based finance payments or the designated dollar amount.           (2) If the performance-based finance payments are on a whole contract basis, liquidation is by predesignated liquidation amounts or liquidation percentages.

  • One AFMC… Powering the World’s Greatest Air Force

    Basic Terms/Concepts

    6Unclassified

    • Customary Contract FinancingAgency deemed financing that’s available for use by the Contracting Officer that generally do not require specific reviews or approvals by higher Management.

    • Unusual Contract FinancingFinancing that’s not deemed customary by the agency but is legal and proper and requiresreviews or approvals by higher Management.

  • One AFMC… Powering the World’s Greatest Air Force

    Basic Terms/Concepts

    7Unclassified

    • Contract “Financing Methods” are not applicable to Cost-Reimbursable Contracts– Cost-Reimbursable contracts generally paid every

    two weeks, plus fee

    • Two General Categories of Contract Financing– Non-Commercial Item Financing– Commercial Item Financing

  • One AFMC… Powering the World’s Greatest Air Force

    Methods

    8Unclassified

    Non-CommercialItem Financing

    FAR 32.1

    CommercialItem Financing

    FAR 32.2

    Government Contract Financing

    PerformanceBased

    Payments

    ProgressPayments

    AdvancePayments

    LoanGuarantees

    AdvancePayments

    InstallmentPayments

    InterimPayments

    Invoice Payments are NOT Financing

  • One AFMC… Powering the World’s Greatest Air Force

    Conditions for Customary Financing

    9Unclassified

    • Period of performance– 6 months or > (large business)– 4 months or > (small business)

    • Contract Price– $2.5M or > (large business)– > simplified acquisition threshold (small

    business)

    PresenterPresentation Notes

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Definition

    10Unclassified

    • Contract financing payments for non-commercial purchases that are payments made on the basis of

    (1) performance measured by objective, quantifiable methods;(2) accomplishment of defined events; or(3) other quantifiable measures of results.

    (Reference FAR 32.10)

    PresenterPresentation NotesAs defined by the FAR, PBP are finance payments that are for noncommercial items and are made on the basis of performance. The most frequently used method is the accomplishment of defined events.

  • One AFMC… Powering the World’s Greatest Air Force

    FAR PBP Policy

    11

    • “Preferred” method of financing• Contract financing not payment for accepted items • Fully recoverable in the event of default• Treated like progress payments for government accounting

    purposes and not subject to interest penalty provisions of prompt payment

    • May be used on competitive negotiations (though not on sealed bids)

    • Not used for architect-engineer services or construction, or for shipbuilding or ship conversion, alteration, or repair, when the contracts provide for progress payments based upon a percentage or stage of completion

    Unclassified

    PresenterPresentation NotesPBPs are not payments for deliverable items. They are fully recoverable in the event of default and they are treated like progress payments for government accounting purposes.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Criteria For Use

    12Unclassified

    • Shall be used only if the following are met:

    – Contracting Officer and contractor agree onPBP terms

    – Fixed-price type contract– Contract cannot also provided for progress

    payments

    PresenterPresentation NotesThey shall be used if the CO and contractor agree on PBP terms. They cannot be used in conjunction with any other method of financing. May be used on competitive negotiations.

  • One AFMC… Powering the World’s Greatest Air Force

    DFARs 2020 Changes & Impacts

    13Unclassified

    • The PBP “cost limitation” clause previously at 252.232-7012/13 is no longer used to constrain PBP payments to cost incurred

    – PBPs can no longer be conditioned upon costs– Very significant change that results in the need to thoroughly vet

    expenditure profiles, analyze PBP values, and analyze whether events should be cumulative versus severable

    • Contractor financial statements shall be in accordance with Generally Accepted Accounting Principles

    • While title is still preferred for security, there are other alternatives that can be used depending on a company’s accounting system

    PresenterPresentation NotesAs of the issuance of the latest rule change (Apr 8, 2020), the contractor’s financial statements must be in compliance with GAAP. Law dictates that this does not grant DCAA the authority to audit compliance with GAAP.

    New rule eliminates the ability to limit PBPs on the basis of incurred costs on the action to which they are applied.

  • One AFMC… Powering the World’s Greatest Air Force

    Planning for PBP

    14Unclassified

    • Assess potential for PBP during contract planning

    • Include PBP as part of pricing effort– Educate team members up front regarding good

    PBP events & criteria, purpose of financing, etc.

    – Do not separate PBP negotiations from price negotiations

    • Also, be prepared for number of elements to be negotiated, e.g. event content, criteria, %/dollars, etc., as this can add time to the pre-award schedule

  • One AFMC… Powering the World’s Greatest Air Force

    Planning for PBP

    15Unclassified

    • Communicate expectations to Contractor early– Need for detailed program schedule– Types of events (should propose specific events)– Frequency of events (include planned completion date)– Completion criteria– Monthly expenditure profile

    • Government and Contractor Must Agree on PBP terms – or possibly resort to Progress Payments

  • One AFMC… Powering the World’s Greatest Air Force

    Planning for PBP

    16Unclassified

    • If Converting to PBPs (FAR 32.005 (a)(2))– Consideration is required for changes to, or the addition of, contract financing after award (including an undefinitized contract where progress payments are provided at award)– Amount of new consideration:

    • Monetary or nonmonetary means, provided the value is adequate• The fair and reasonable consideration should approximate the amount by

    which the price would have been less had the contract financing terms been contained in the initial contract.

    • In the absence of definite information on this point, the contracting officer should apply the following criteria in evaluating whether the proposed new consideration is adequate:

    – Value to the contractor of the anticipated amount and duration of the contract financing at the imputed financial costs of the equivalent working capital– The estimated profit rate to be earned through contract performance

    PresenterPresentation NotesDoing PBPs on UCAs is very challenging, but is possible. Would recommend it only be done in circumstances where you have easily definable events/criteria and good production history where monthly costs are easy to determine and anticipate.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Key Steps

    17Unclassified

    1. Establish Detailed Program Schedule2. Identify Key Performance Milestones (PBP

    Events)3. Establish Completion Criteria for PBP

    Events4. Determine/Evaluate Monthly Expenditure

    Profile5. Establish Event Values and Create Win-Win

    Scenario6. Develop Special Contract Provisions

  • One AFMC… Powering the World’s Greatest Air Force

    Developing PBP Events & Completion Criteria

    18Unclassified

  • One AFMC… Powering the World’s Greatest Air Force

    FAR Requirements for PBP Events

    19Unclassified

    • Basis may be specifically described event or some measurable criterion of performance

    • Events must be integral, necessary part of performance

    • Events must be identified, with description of what constitutes successful completion

    • Events need not be critical, but performance must be readily verifiable

    PresenterPresentation NotesIn terms of procedures, the CO must set up a set of defined events that have completion criteria and associated payment events.

  • One AFMC… Powering the World’s Greatest Air Force

    FAR Requirements for PBP Events

    20Unclassified

    • Events may be cumulative or severable*– Severable – successful completion is

    independent of other events– Cumulative – successful completion is

    dependent upon previous accomplishment of another event (must identify dependent event)

    * Note – This is an area where the best of intentions can lead to unintended consequences, which will be discussed in later slides

    Typical PBPs contain both severableand cumulative events

  • One AFMC… Powering the World’s Greatest Air Force

    FAR Guidelines for PBP Events

    21Unclassified

    • Whole Contract or Deliverable Item Basis– Whole Contract – financing payments are

    applicable to entire contract– Deliverable Item – financing payments are

    applicable to a specific individual deliverable item

    PresenterPresentation NotesEvents may be made on a whole contract or deliverable item basis. For example, if you are buying aircraft you could set up a schedule of events that would apply to each individual aircraft. Otherwise, the whole contract basis would imply a lot of items that would get tracked together for payment purposes.

  • One AFMC… Powering the World’s Greatest Air Force

    FAR Guidelines for PBP Events

    22Unclassified

    • Not designed to reward for performance above contract requirements

    • Signing of contracts shall not be used as basis for event

  • One AFMC… Powering the World’s Greatest Air Force

    How to Develop Events/Criteria

    23Unclassified

    • PBP Key Step 1 – Establish detailed program schedule – Work with Program Management & technical

    personnel– What is program critical path?– What are key activities that must be completed

    to ensure contract delivery?– Are there significant subcontractor activities?– Utilize Integrated Master Plan & Schedule

  • One AFMC… Powering the World’s Greatest Air Force

    How to Develop Events/Criteria

    24Unclassified

    • PBP Key Step 2 – Identify Key Performance Milestones – PBP Events

    – Use Defense Contract Management Agency (DCMA), Program Management & Technical Personnel

    – Use Meaningful and Objective Events

    – Consider Whether Events Should be Cumulative or Severable

    – Structure Events on Whole Lot or Line Item Basis (Contract must be one or other)

  • One AFMC… Powering the World’s Greatest Air Force

    How to Develop Events/Criteria

    25Unclassified

    • PBP Key Step 2 – Identify Key Performance Milestones – PBP Events (cont)– Consider Frequency of Events (& burden to

    administer)– Use Appropriate Anticipated Event Completion

    Dates– Don’t Use Prime Contract Award to Trigger a PBP– Don’t Use Invoices to Trigger a PBP

  • One AFMC… Powering the World’s Greatest Air Force

    How to Develop Events/Criteria

    26Unclassified

    • PBP Key Step 3 – Establish Completion Criteria for PBP Events

    – Use Specific, Objective and Clear Criteria

    – Make Sure Criteria for Cumulative Events Identifies Related Events

    – Obtain DCMA Input

    – Identify Appropriate Person/Organization for Verification of Events

    • First three steps are an iterative process• Contractor may take first cut at events/criteria• Each event must have an associated completion

    criterion!

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Exercise

    27Unclassified

    Examples of PBP Events &Completion Criteria

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 1

    28Unclassified

    Event: Award of Contract F33657-03-C-0001

    Completion Criteria: Complete upon contractor signature on contract

    Is this a good or bad event?A. GoodB. Bad, cannot do per FAR 32.10004

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 1

    29Unclassified

    Event: Award of Contract F33657-03-C-0001

    Completion Criteria: Complete upon contractor signature on contract

    Is this a good or bad event?A. GoodB. Bad, cannot do per FAR 32.10004

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 2

    30Unclassified

    Event: Award of Subcontract #xyz

    Completion Criteria: Complete upon subcontractor signature on subcontract

    Choose the best answer from the following:A. Good event and criteria.B. Okay, but consider significance of subcontract & “value” of event. Event should be cumulative.C. Okay, but consider significance of subcontract & “value” of event. Event should be severable.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 2

    31Unclassified

    Event: Award of Subcontract #xyz

    Completion Criteria: Complete upon subcontractor signature on subcontract

    Choose the best answer from the following:A. Good event and criteria.B. Okay, but consider significance of subcontract & “value” of event. Event should be cumulative.C. Okay, but consider significance of subcontract & “value” of event. Event should be severable.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 3

    32Unclassified

    Event: Initiate testing of avionics software

    Completion Criteria: Aircraft arrives in test station #12

    Choose the best answer from the following:A. Good event and criteria.B. Bad event, but good criteria.C. Good event, but bad criteria.D. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 3

    33Unclassified

    Event: Initiate testing of avionics software

    Completion Criteria: Aircraft arrives in test station #12

    Choose the best answer from the following:A. Good event and criteria.B. Bad event, but good criteria.C. Good event, but bad criteria.D. Bad event and criteria.

    PresenterPresentation NotesWhat does “initiate” mean? No accomplishment of anything. Did anything significant happen before they initiated the testing? If so, why not make that the criteria?

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 4

    34Unclassified

    Event: Completion of fabrication of forward fuselage

    Completion Criteria: 100,000 hours charged to work order 387 as verified by DCMA

    Choose the best answer from the following:A. Good event and criteria, but should be cumulative to another event.B. Bad event, but good criteria and should be cumulative to another event.C. Good event, but bad criteria and should be cumulative to another event.D. Good event, but bad criteria and should be a severable event.E. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 4

    35Unclassified

    Event: Completion of fabrication of forward fuselage

    Completion Criteria: 100,000 hours charged to work order 387 as verified by DCMA

    Choose the best answer from the following:A. Good event and criteria, but should be cumulative to another event.B. Bad event, but good criteria and should be cumulative to another event.C. Good event, but bad criteria and should be cumulative to another event.D. Good event, but bad criteria and should be a severable event.E. Bad event and criteria.

    PresenterPresentation NotesWhat would be good criteria?

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 5

    36Unclassified

    Event: Fabrication complete for forward fuselage

    Completion Criteria: Shop inspection record indicates an earned operation for fabrication as signed off by DCMA. (Cumulative to Event #4)

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be severable.C. Good event, but bad criteria.D. Good event, but bad criteria and should be a severable

    event.E. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 5

    37Unclassified

    Event: Fabrication complete for forward fuselage

    Completion Criteria: Shop inspection record indicates an earned operation for fabrication as signed off by DCMA. (Cumulative to Event #4)

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be severable.C. Good event, but bad criteria.D. Good event, but bad criteria and should be a severable

    event.E. Bad event and criteria.

    PresenterPresentation NotesThere may be more detailed documents internal to DCMA that define the completion criteria

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 6

    38Unclassified

    Event: Attendance at Management Status Review (MSR)

    Completion Criteria: Administrative Contracting Officer validates meeting minutes which show the contractor’s attendance at the MSRChoose the best answer from the following:

    A. Good event and criteria.B. Good event and criteria, but should be severable.C. Good event, but bad criteria.D. Good event and criteria, but should be cumulative.E. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 6

    39Unclassified

    Event: Attendance at Management Status Review (MSR)

    Completion Criteria: Administrative Contracting Officer validates meeting minutes which show the contractor’s attendance at the MSRChoose the best answer from the following:

    A. Good event and criteria.B. Good event and criteria, but should be severable.C. Good event, but bad criteria.D. Good event and criteria, but should be cumulative.E. Bad event and criteria.

    PresenterPresentation NotesThis one is kind of tricky. You could use this as an event, if you really thought it showed progress. Otherwise, you might want to assign a very nominal value to it.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 7

    40Unclassified

    Event: Completion of PMR

    Completion Criteria: Mutual agreement that contractor action items are closed

    Choose the best answer from the following:A. Good event and criteria.B. Meetings should never be used.C. Good event, but bad criteria.D. Meetings are tricky events and care should be taken

    when using them. What is the proposed value?E. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 7

    41Unclassified

    Event: Completion of PMR

    Completion Criteria: Mutual agreement that contractor action items are closed

    Choose the best answer from the following:A. Good event and criteria.B. Meetings should never be used.C. Good event, but bad criteria.D. Meetings are tricky events and care should be taken

    when using them. What is the proposed value?E. Bad event and criteria.

    PresenterPresentation NotesThis could be PMR, CDR, etc. (Major review)Discussion on how completion criteria can affect the event itself (and the program).

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 8

    42Unclassified

    Event: 6 Months prior to delivery

    Completion Criteria: DCMA reviews the Contractor’s Master Scheduling Plan (MSP) and confirms the current projections of delivery at not more than 6 months from the date of review.

    Choose the best answer from the following:A. Good event and criteria.B. Good event, but bad criteria.C. Bad event, but good criteria.D. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 8

    43Unclassified

    Event: 6 Months prior to delivery

    Completion Criteria: DCMA reviews the Contractor’s Master Scheduling Plan (MSP) and confirms the current projections of delivery at not more than 6 months from the date of review.

    Choose the best answer from the following:A. Good event and criteria.B. Good event, but bad criteria.C. Bad event, but good criteria.D. Bad event and criteria.

    PresenterPresentation NotesThis may be okay in the commercial market (customary), but it is not okay in PBPs

    Bad - time does not constitute progress

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 9

    44Unclassified

    Event: Aircraft moved to paint facility

    Completion Criteria: Aircraft assembly completed per Contractor’s major assembly sequence chart and aircraft moved to paint facility. Assembly verified by DCMA. (Cumulative to event #5).

    Choose the best answer from the following:A. Good event and criteria.B. Good event, but bad criteria.C. Bad event, but good criteria.D. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 9

    45Unclassified

    Event: Aircraft moved to paint facility

    Completion Criteria: Aircraft assembly completed per Contractor’s major assembly sequence chart and aircraft moved to paint facility. Assembly verified by DCMA. (Cumulative to event #5).

    Choose the best answer from the following:A. Good event and criteria.B. Good event, but bad criteria.C. Bad event, but good criteria.D. Bad event and criteria.

    PresenterPresentation NotesGood, but why not use completion?

    The event alone is not a good event, but with the completion criteria it is okayThe event should have been Completion of Aircraft AssemblyBeware of Begin or Initiate anything

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 10

    46Unclassified

    Event: Delivery of Aircraft #1

    Completion Criteria: Execution of DD Form 250

    Choose the best answer from the following:A. Good event and criteria.B. Good event, but bad criteria.C. Bad event, but good criteria.D. Bad event and criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 10

    47Unclassified

    Event: Delivery of Aircraft #1

    Completion Criteria: Execution of DD Form 250

    Choose the best answer from the following:A. Good event and criteria.B. Good event, but bad criteria.C. Bad event, but good criteria.D. Bad event and criteria.

    PresenterPresentation NotesBad - PBPs are contract financing payments NOT payments for accepted items- FAR 32.1001

    They are going to be paid – it is a liquidation payment, not a financing payment.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 11

    48Unclassified

    Event: APU Engine Delivery

    Completion Criteria: Delivery of APU Engine to Prime Contractor. The APU Engine must be delivered and accepted defect free. (Severable)Choose the best answer from the following:

    A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Bad event, but good criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 11

    49Unclassified

    Event: APU Engine Delivery

    Completion Criteria: Delivery of APU Engine to Prime Contractor. The APU Engine must be delivered and accepted defect free. (Severable)Choose the best answer from the following:

    A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Bad event, but good criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 12

    50Unclassified

    Event: Receipt of all Production Material

    Completion Criteria: Longest lead time part, Decoder, Part #X11115AC has been received or is being reported as “Late” on the weekly Material Action Report.

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Bad event, but good criteria.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 12

    51Unclassified

    Event: Receipt of all Production Material

    Completion Criteria: Longest lead time part, Decoder, Part #X11115AC has been received or is being reported as “Late” on the weekly Material Action Report.

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Bad event, but good criteria.

    PresenterPresentation NotesBad, the part is either delivered or it is late!

    How do you make this a good event? The event is not in itself bad, the completion criteria made it meaningless.Other examples of P.O.s – common upfront event

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 13

    52Unclassified

    Event: Main landing gear bulkhead frames machined

    Completion Criteria: Shipset of 10 bulkhead frames complete through machining, document stamped/signed by DCMA.

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Good event and criteria, but should be severable.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 13

    53Unclassified

    Event: Main landing gear bulkhead frames machined

    Completion Criteria: Shipset of 10 bulkhead frames complete through machining, document stamped/signed by DCMA.

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Good event and criteria, but should be severable.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 14

    54Unclassified

    Event: Completed 50 percent of software coding

    Completion Criteria: Completion of 5,000 lines of code based on initial estimate of 10,000 lines of code.

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Good event and criteria, but should be severable.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Example 14

    55Unclassified

    Event: Completed 50 percent of software coding

    Completion Criteria: Completion of 5,000 lines of code based on initial estimate of 10,000 lines of code.

    Choose the best answer from the following:A. Good event and criteria.B. Good event and criteria, but should be cumulative.C. Good event, but bad criteria.D. Bad event and criteria.E. Good event and criteria, but should be severable.

    PresenterPresentation NotesBad. The 10,000 lines of code was just the original estimate. Is 5,000 50% of the real software requirement?

  • One AFMC… Powering the World’s Greatest Air Force

    Cumulative versus Severable Determination

    56Unclassified

    • Categorizing events as severable can have unintended consequences for the Government

    – If a severable event is priced based on an expenditure profile and performed early, the company will likely receive costs for activities that are scheduled to take place in the future

    – One way to mitigate this is to include in the PBP clause that the contractor cannot be paid for a severable event before a certain date or X days early from the PBP scheduled date

  • One AFMC… Powering the World’s Greatest Air Force

    Cumulative vs Severable Determination

    57Unclassified

    Unintended Consequence of Severable Events Example

    MonthCumulative Cost

    Expenditures PBP EventPBP Event

    ValueCumulative

    PBPsCumulative (C) or Severable (S)

    Jan $100Feb $150 Event 1 $100 $100 SMar $500Apr $900 Event 2 $600 $700 SMay $1,000Jun $1,500 Event 3 $200 $900 SJul $1,700 Event 4 $600 $1,500 S

    MonthCumulative Cost

    Expenditures PBP EventPBP Event

    ValueCumulative

    PBPsCumulative (C) or Severable (S)

    Jan $100Feb $150 Event 1 and 4 $100 & $600 $700 SMar $500 Event 3 $200 $900 SApr $900 Event 2 $600 $1,500 SMay $1,000Jun $1,500Jul $1,700

    Negotiated

    Actual

    • As can be seen from the above example, negotiating all severable events has resulted in PBP payments that are in excess of costs for four months

  • One AFMC… Powering the World’s Greatest Air Force

    Cumulative vs Severable Determination

    58Unclassified

    Mitigating Unintended Consequences

    MonthCumulative Cost

    Expenditures PBP EventPBP Event

    ValueCumulative

    PBPsCumulative (C) or Severable (S)

    Jan $100Feb $150 Event 1 $100 $100 SMar $500Apr $900 Event 2 $600 $700 C to 1May $1,000Jun $1,500 Event 3 $200 $900 SJul $1,700 Event 4 $600 $1,500 C to 2

    MonthCumulative Cost

    Expenditures PBP EventPBP Event

    ValueCumulative

    PBPsCumulative (C) or Severable (S)

    Jan $100Feb $150 Event 1 $100 $100 SMar $500 Event 3 $200 $300 SApr $900 Event 2 $600 $900 C to 1May $1,000 Event 4 $600 $1,500 C to 2Jun $1,500Jul $1,700

    Negotiated

    Actual

    • By changing two of the events to cumulative, the contracting officer was able to reduce the number of months where PBPs exceeded costs incurred to one month

  • One AFMC… Powering the World’s Greatest Air Force

    Cumulative vs Severable Determination

    59Unclassified

    Mitigating Unintended ConsequencesMonth

    Cumulative Cost Expenditures PBP Event

    PBP Event Value

    Cumulative PBPs

    Cumulative (C) or Severable (S)

    Jan $100Feb $150 Event 1 $100 $100 SMar $500Apr $900 Event 2 $600 $700 C to 1May $1,000Jun $1,500 Event 3 $200 $900 SJul $1,700 Event 4 $600 $1,500 C to 2**Clause language includes stipulation that event 4 cannot be paid earlier than 30 days before the PBP scheduled date.

    MonthCumulative Cost

    Expenditures PBP EventPBP Event

    ValueCumulative

    PBPsCumulative (C) or Severable (S)

    Jan $100Feb $150 Event 1 $100 $100 SMar $500 Event 3 $200 $300 SApr $900 Event 2 $600 $900 C to 1May $1,000Jun $1,500 Event 4 $600 $1,500 C to 2*Jul $1,700*Clause language includes stipulation that event 4 cannot be paid earlier than 30 days before the PBP scheduled date.

    Actual

    Negotiated

    • Further, by including language within the PBP clause that restricts the contractor to only receiving Event 4 payment 30 days early, the contracting officer has eliminated an advanced payment situation.

  • One AFMC… Powering the World’s Greatest Air Force

    Valuing PBP Events & Creating a Win-Win Scenario

    60Unclassified

  • One AFMC… Powering the World’s Greatest Air Force

    FAR Requirements for Valuing Events

    61Unclassified

    • Total PBPs must reflect prudent contract financing only to extent needed for contract performance

    • Total PBPs shall not exceed 90%* of contract price or delivery item price

    • Contracting Officer (CO) must establish a rational basis for PBP amounts

    *90% is not an entitlement, but rather negotiable

  • One AFMC… Powering the World’s Greatest Air Force

    FAR Requirements for Valuing Events

    62Unclassified

    • CO must ensure the total contract price is fair and reasonable, considering all factors (including the cost to the treasury)

    • CO must ensure amounts are commensurate with the value of the event/criteria and are not expected to result in an unreasonably low or negative level of contractor investment in the contract

  • One AFMC… Powering the World’s Greatest Air Force

    Negative Contractor Investment in the Contract

    63Unclassified

    Example of Front Loaded PBP

    $-

    $1,000

    $2,000

    $3,000

    $4,000

    $5,000

    1 3 5 7 9 11 13 15 17 19

    Thou

    sand

    s

    Month

    Front Loaded PBP

    Cum Cost (Expenditures)

    Cum Prog Pay (80%Cost)

    In this example, every month, the company gets paid inexcess of incurred costs – what is the incentive to deliver?

    Chart13

    5000081256500

    1500002036116288.8

    45000042035.3155633628.252448

    1233035119931.09924831295944.8793986496

    2233035217592.654239564174074.123391651

    2833035315956.191526207252764.953220966

    3333035418632.017287206334905.613829765

    3733035755471.327745419604377.062196335

    39330351807201.085410331445760.86832826

    40330352120402.937334971696322.34986798

    41830352425846.135806261940676.90864501

    43080352783684.97884992226947.98307992

    44080353177455.483329962541964.38666397

    44830353587604.53197512870083.62558008

    45330353967148.058481673173718.44678534

    45680354261233.159325693408986.52746055

    45880354409385.159325693527508.12746055

    46030354446271.159325693557016.92746055

    46130354477409.159325693581927.32746055

    46180354501009.159325693600807.32746055

    Front Loaded PBP

    Cum Cost (Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded PBP

    Sheet1

    0.150.80.15

    cumulativeProg Paycum90%

    mocostpricecostpricePBPcum PBP

    1$ 10,000.00$ 11,500$ 10,000$ 8,000$ 11,50010,350.00$ 10,350

    2$ 50,000.00$ 57,500$ 60,000$ 48,000$ 69,00051,750.00$ 62,100

    3$ 100,000.00$ 115,000$ 160,000$ 128,000$ 184,000103,500.00$ 165,600

    4$ 250,000.00$ 287,500$ 410,000$ 328,000$ 471,500258,750.00$ 424,350

    5$ 500,000.00$ 575,000$ 910,000$ 728,000$ 1,046,500517,500.00$ 941,850

    6$ 250,000.00$ 287,500$ 1,160,000$ 928,000$ 1,334,000258,750.00$ 1,200,600

    7$ 100,000.00$ 115,000$ 1,260,000$ 1,008,000$ 1,449,000103,500.00$ 1,304,100

    8$ 50,000.00$ 57,500$ 1,310,000$ 1,048,000$ 1,506,50051,750.00$ 1,355,850

    9$ 10,000.00$ 11,500$ 1,320,000$ 1,056,000$ 1,518,00010,350.00$ 1,366,200

    $ 1,320,000.00

    cum costcum PBPcum Prog Pay

    $ 10,000$ 10,350$ 8,000

    $ 60,000$ 62,100$ 48,000

    $ 160,000$ 165,600$ 128,000

    $ 410,000$ 424,350$ 328,000

    $ 910,000$ 941,850$ 728,000

    $ 1,160,000$ 1,200,600$ 928,000

    $ 1,260,000$ 1,304,100$ 1,008,000

    $ 1,310,000$ 1,355,850$ 1,048,000

    $ 1,320,000$ 1,366,200$ 1,056,000

    Sheet2

    profit0.180.08

    0.90.8

    mocumcumcumcum

    costcostPBPPBPPP

    1$ 8,125$ 8,125$ 8,629$ 7,898$ 6,500

    2$ 12,236$ 20,361$ 21,623$ 19,791$ 16,289

    3$ 21,674$ 42,035$ 44,642$ 40,858$ 33,628

    4$ 77,896$ 119,931$ 127,367$ 116,573$ 95,945

    5$ 97,662$ 217,593$ 231,083$ 211,500$ 174,074

    6$ 98,364$ 315,956$ 335,545$ 307,109$ 252,765

    7$ 102,676$ 418,632$ 444,587$ 406,910$ 334,906

    8$ 336,839$ 755,471$ 802,311$ 734,318$ 604,377

    9$ 1,051,730$ 1,807,201$ 1,919,248$ 1,756,599$ 1,445,761

    10$ 313,202$ 2,120,403$ 2,251,868$ 2,061,032$ 1,696,322

    11$ 305,443$ 2,425,846$ 2,576,249$ 2,357,922$ 1,940,677

    12$ 357,839$ 2,783,685$ 2,956,273$ 2,705,742$ 2,226,948

    13$ 393,771$ 3,177,455$ 3,374,458$ 3,088,487$ 2,541,964

    14$ 410,149$ 3,587,605$ 3,810,036$ 3,487,152$ 2,870,084

    15$ 379,544$ 3,967,148$ 4,213,111$ 3,856,068$ 3,173,718

    16$ 294,085$ 4,261,233$ 4,525,430$ 4,141,919$ 3,408,987

    17$ 148,152$ 4,409,385$ 4,682,767$ 4,285,922$ 3,527,508

    18$ 36,886$ 4,446,271$ 4,721,940$ 4,321,776$ 3,557,017

    19$ 31,138$ 4,477,409$ 4,755,009$ 4,352,042$ 3,581,927

    20$ 23,600$ 4,501,009$ 4,780,072$ 4,374,981$ 3,600,807

    $ 4,501,009

    1

    Front Loaded

    mocumcumcum

    PBPcostcostPBPPP

    $ 50,0001$ 8,125$ 8,125$ 50,000$ 6,500

    $ 100,0002$ 12,236$ 20,361$ 150,000$ 16,289

    $ 300,0003$ 21,674$ 42,035$ 450,000$ 33,628

    $ 783,0354$ 77,896$ 119,931$ 1,233,035$ 95,945

    $ 1,000,0005$ 97,662$ 217,593$ 2,233,035$ 174,074

    $ 600,0006$ 98,364$ 315,956$ 2,833,035$ 252,765

    $ 500,0007$ 102,676$ 418,632$ 3,333,035$ 334,906

    $ 400,0008$ 336,839$ 755,471$ 3,733,035$ 604,377

    $ 200,0009$ 1,051,730$ 1,807,201$ 3,933,035$ 1,445,761

    $ 100,00010$ 313,202$ 2,120,403$ 4,033,035$ 1,696,322

    $ 150,00011$ 305,443$ 2,425,846$ 4,183,035$ 1,940,677

    $ 125,00012$ 357,839$ 2,783,685$ 4,308,035$ 2,226,948

    $ 100,00013$ 393,771$ 3,177,455$ 4,408,035$ 2,541,964

    7500014$ 410,149$ 3,587,605$ 4,483,035$ 2,870,084

    5000015$ 379,544$ 3,967,148$ 4,533,035$ 3,173,718

    3500016$ 294,085$ 4,261,233$ 4,568,035$ 3,408,987

    2000017$ 148,152$ 4,409,385$ 4,588,035$ 3,527,508

    1500018$ 36,886$ 4,446,271$ 4,603,035$ 3,557,017

    1000019$ 31,138$ 4,477,409$ 4,613,035$ 3,581,927

    500020$ 23,600$ 4,501,009$ 4,618,035$ 3,600,807

    $ 4,618,035$ 4,501,009

    Price5,311,190.81

    profit0.11

    0.90.8

    real

    Front Loadedmocum Frontcumcumcum

    Exp CurvecostLoaded ExpPBPPPcost

    $ 50,0001$ 8,125$ 50,000$ 49,950$ 6,500$ 8,125

    $ 100,0002$ 12,236$ 150,000$ 149,850$ 16,289$ 20,361

    $ 300,0003$ 21,674$ 450,000$ 449,550$ 33,628$ 42,035

    $ 783,0354$ 77,896$ 1,233,035$ 1,231,802$ 95,945$ 119,931

    $ 1,000,0005$ 97,662$ 2,233,035$ 2,230,802$ 174,074$ 217,593

    $ 600,0006$ 98,364$ 2,833,035$ 2,830,202$ 252,765$ 315,956

    $ 500,0007$ 102,676$ 3,333,035$ 3,329,702$ 334,906$ 418,632

    $ 400,0008$ 336,839$ 3,733,035$ 3,729,302$ 604,377$ 755,471

    $ 200,0009$ 1,051,730$ 3,933,035$ 3,929,102$ 1,445,761$ 1,807,201

    $ 100,00010$ 313,202$ 4,033,035$ 4,029,002$ 1,696,322$ 2,120,403

    $ 150,00011$ 305,443$ 4,183,035$ 4,178,852$ 1,940,677$ 2,425,846

    $ 125,00012$ 357,839$ 4,308,035$ 4,303,727$ 2,226,948$ 2,783,685

    $ 100,00013$ 393,771$ 4,408,035$ 4,403,627$ 2,541,964$ 3,177,455

    7500014$ 410,149$ 4,483,035$ 4,478,552$ 2,870,084$ 3,587,605

    5000015$ 379,544$ 4,533,035$ 4,528,502$ 3,173,718$ 3,967,148

    3500016$ 294,085$ 4,568,035$ 4,563,467$ 3,408,987$ 4,261,233

    2000017$ 148,152$ 4,588,035$ 4,583,447$ 3,527,508$ 4,409,385

    1500018$ 36,886$ 4,603,035$ 4,598,432$ 3,557,017$ 4,446,271

    1000019$ 31,138$ 4,613,035$ 4,608,422$ 3,581,927$ 4,477,409

    500020$ 23,600$ 4,618,035$ 4,613,417$ 3,600,807$ 4,501,009

    $ 4,501,009

    Sheet2

    Front Loaded PBP

    Cum Cost (Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded PBP

    Sheet3

    Cum PBP

    Front Loaded Cum Cost

    Real Cum Cost (Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded Expenditure Profile

    Cum Cost (Expenditures)

    Cum PBP (90% Price, 18% Profit)

    Cum PBP (90% Price, 8% Profit)

    Cum Prog Pay (80% Cost)

    Month

    90% Monthly PBP Examples

  • One AFMC… Powering the World’s Greatest Air Force

    When does Contractor Investment Become Negative or Unreasonably Low?

    64Unclassified

    $-

    $1,000

    $2,000

    $3,000

    $4,000

    $5,000

    $6,000

    1 3 5 7 9 11 13 15 17 19

    Thou

    sand

    s

    Month

    90% Monthly PBP Examples

    Cum PBP (90% Price,18% Profit)

    Cum Cost (Expenditures)

    Cum PBP (90% Price,8% Profit)

    Cum Prog Pay (80%Cost)

    Profit, Payment Frequency and Lag Time affect Investment

    Chart14

    8628.7581257897.56500

    21623.3822036119790.89216288.8

    44641.5051247242035.3155640858.3267243233628.252448

    127366.827401707119931.099248312116573.02846935995944.8793986496

    231083.398802417217592.654239564211500.059920856174074.123391651

    335545.475400832315956.191526207307109.418163473252764.953220966

    444587.202359013418632.017287206406910.320803164334905.613829765

    802310.550065635755471.327745419734318.130568547604377.062196335

    1919247.552705771807201.085410331756599.455018841445760.86832826

    2251867.919449742120402.937334972061031.655089591696322.34986798

    2576248.596226252425846.135806262357922.444003691940676.90864501

    2956273.447538592783684.97884992705741.79944212226947.98307992

    3374457.723296423177455.483329963088486.729796722541964.38666397

    3810036.012957563587604.53197513487151.60507982870083.62558008

    4213111.238107533967148.058481673856067.912844183173718.44678534

    4525429.615203884261233.159325694141918.630864573408986.52746055

    4682767.039203884409385.159325694285922.374864573527508.12746055

    4721939.971203884446271.159325694321775.566864573557016.92746055

    4755008.527203884477409.159325694352041.702864573581927.32746055

    4780071.727203884501009.159325694374980.902864573600807.32746055

    Cum PBP (90% Price, 18% Profit)

    Cum Cost (Expenditures)

    Cum PBP (90% Price, 8% Profit)

    Cum Prog Pay (80% Cost)

    Month

    90% Monthly PBP Examples

    Sheet1

    0.150.80.15

    cumulativeProg Paycum90%

    mocostpricecostpricePBPcum PBP

    1$ 10,000.00$ 11,500$ 10,000$ 8,000$ 11,50010,350.00$ 10,350

    2$ 50,000.00$ 57,500$ 60,000$ 48,000$ 69,00051,750.00$ 62,100

    3$ 100,000.00$ 115,000$ 160,000$ 128,000$ 184,000103,500.00$ 165,600

    4$ 250,000.00$ 287,500$ 410,000$ 328,000$ 471,500258,750.00$ 424,350

    5$ 500,000.00$ 575,000$ 910,000$ 728,000$ 1,046,500517,500.00$ 941,850

    6$ 250,000.00$ 287,500$ 1,160,000$ 928,000$ 1,334,000258,750.00$ 1,200,600

    7$ 100,000.00$ 115,000$ 1,260,000$ 1,008,000$ 1,449,000103,500.00$ 1,304,100

    8$ 50,000.00$ 57,500$ 1,310,000$ 1,048,000$ 1,506,50051,750.00$ 1,355,850

    9$ 10,000.00$ 11,500$ 1,320,000$ 1,056,000$ 1,518,00010,350.00$ 1,366,200

    $ 1,320,000.00

    cum costcum PBPcum Prog Pay

    $ 10,000$ 10,350$ 8,000

    $ 60,000$ 62,100$ 48,000

    $ 160,000$ 165,600$ 128,000

    $ 410,000$ 424,350$ 328,000

    $ 910,000$ 941,850$ 728,000

    $ 1,160,000$ 1,200,600$ 928,000

    $ 1,260,000$ 1,304,100$ 1,008,000

    $ 1,310,000$ 1,355,850$ 1,048,000

    $ 1,320,000$ 1,366,200$ 1,056,000

    Sheet2

    profit0.180.08

    0.90.8

    mocumcumcumcum

    costcostPBPPBPPP

    1$ 8,125$ 8,125$ 8,629$ 7,898$ 6,500

    2$ 12,236$ 20,361$ 21,623$ 19,791$ 16,289

    3$ 21,674$ 42,035$ 44,642$ 40,858$ 33,628

    4$ 77,896$ 119,931$ 127,367$ 116,573$ 95,945

    5$ 97,662$ 217,593$ 231,083$ 211,500$ 174,074

    6$ 98,364$ 315,956$ 335,545$ 307,109$ 252,765

    7$ 102,676$ 418,632$ 444,587$ 406,910$ 334,906

    8$ 336,839$ 755,471$ 802,311$ 734,318$ 604,377

    9$ 1,051,730$ 1,807,201$ 1,919,248$ 1,756,599$ 1,445,761

    10$ 313,202$ 2,120,403$ 2,251,868$ 2,061,032$ 1,696,322

    11$ 305,443$ 2,425,846$ 2,576,249$ 2,357,922$ 1,940,677

    12$ 357,839$ 2,783,685$ 2,956,273$ 2,705,742$ 2,226,948

    13$ 393,771$ 3,177,455$ 3,374,458$ 3,088,487$ 2,541,964

    14$ 410,149$ 3,587,605$ 3,810,036$ 3,487,152$ 2,870,084

    15$ 379,544$ 3,967,148$ 4,213,111$ 3,856,068$ 3,173,718

    16$ 294,085$ 4,261,233$ 4,525,430$ 4,141,919$ 3,408,987

    17$ 148,152$ 4,409,385$ 4,682,767$ 4,285,922$ 3,527,508

    18$ 36,886$ 4,446,271$ 4,721,940$ 4,321,776$ 3,557,017

    19$ 31,138$ 4,477,409$ 4,755,009$ 4,352,042$ 3,581,927

    20$ 23,600$ 4,501,009$ 4,780,072$ 4,374,981$ 3,600,807

    $ 4,501,009

    1

    Front Loaded

    mocumcumcum

    PBPcostcostPBPPP

    $ 50,0001$ 8,125$ 8,125$ 50,000$ 6,500

    $ 100,0002$ 12,236$ 20,361$ 150,000$ 16,289

    $ 300,0003$ 21,674$ 42,035$ 450,000$ 33,628

    $ 783,0354$ 77,896$ 119,931$ 1,233,035$ 95,945

    $ 1,000,0005$ 97,662$ 217,593$ 2,233,035$ 174,074

    $ 600,0006$ 98,364$ 315,956$ 2,833,035$ 252,765

    $ 500,0007$ 102,676$ 418,632$ 3,333,035$ 334,906

    $ 400,0008$ 336,839$ 755,471$ 3,733,035$ 604,377

    $ 200,0009$ 1,051,730$ 1,807,201$ 3,933,035$ 1,445,761

    $ 100,00010$ 313,202$ 2,120,403$ 4,033,035$ 1,696,322

    $ 150,00011$ 305,443$ 2,425,846$ 4,183,035$ 1,940,677

    $ 125,00012$ 357,839$ 2,783,685$ 4,308,035$ 2,226,948

    $ 100,00013$ 393,771$ 3,177,455$ 4,408,035$ 2,541,964

    7500014$ 410,149$ 3,587,605$ 4,483,035$ 2,870,084

    5000015$ 379,544$ 3,967,148$ 4,533,035$ 3,173,718

    3500016$ 294,085$ 4,261,233$ 4,568,035$ 3,408,987

    2000017$ 148,152$ 4,409,385$ 4,588,035$ 3,527,508

    1500018$ 36,886$ 4,446,271$ 4,603,035$ 3,557,017

    1000019$ 31,138$ 4,477,409$ 4,613,035$ 3,581,927

    500020$ 23,600$ 4,501,009$ 4,618,035$ 3,600,807

    $ 4,618,035$ 4,501,009

    Price5,311,190.81

    profit0.11

    0.90.8

    real

    Front Loadedmocum Frontcumcumcum

    Exp CurvecostLoaded ExpPBPPPcost

    $ 50,0001$ 8,125$ 50,000$ 49,950$ 6,500$ 8,125

    $ 100,0002$ 12,236$ 150,000$ 149,850$ 16,289$ 20,361

    $ 300,0003$ 21,674$ 450,000$ 449,550$ 33,628$ 42,035

    $ 783,0354$ 77,896$ 1,233,035$ 1,231,802$ 95,945$ 119,931

    $ 1,000,0005$ 97,662$ 2,233,035$ 2,230,802$ 174,074$ 217,593

    $ 600,0006$ 98,364$ 2,833,035$ 2,830,202$ 252,765$ 315,956

    $ 500,0007$ 102,676$ 3,333,035$ 3,329,702$ 334,906$ 418,632

    $ 400,0008$ 336,839$ 3,733,035$ 3,729,302$ 604,377$ 755,471

    $ 200,0009$ 1,051,730$ 3,933,035$ 3,929,102$ 1,445,761$ 1,807,201

    $ 100,00010$ 313,202$ 4,033,035$ 4,029,002$ 1,696,322$ 2,120,403

    $ 150,00011$ 305,443$ 4,183,035$ 4,178,852$ 1,940,677$ 2,425,846

    $ 125,00012$ 357,839$ 4,308,035$ 4,303,727$ 2,226,948$ 2,783,685

    $ 100,00013$ 393,771$ 4,408,035$ 4,403,627$ 2,541,964$ 3,177,455

    7500014$ 410,149$ 4,483,035$ 4,478,552$ 2,870,084$ 3,587,605

    5000015$ 379,544$ 4,533,035$ 4,528,502$ 3,173,718$ 3,967,148

    3500016$ 294,085$ 4,568,035$ 4,563,467$ 3,408,987$ 4,261,233

    2000017$ 148,152$ 4,588,035$ 4,583,447$ 3,527,508$ 4,409,385

    1500018$ 36,886$ 4,603,035$ 4,598,432$ 3,557,017$ 4,446,271

    1000019$ 31,138$ 4,613,035$ 4,608,422$ 3,581,927$ 4,477,409

    500020$ 23,600$ 4,618,035$ 4,613,417$ 3,600,807$ 4,501,009

    $ 4,501,009

    Sheet2

    Front Loaded PBP

    Cum Cost (Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded PBP

    Sheet3

    Cum PBP

    Front Loaded Cum Cost

    Real Cum Cost (Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded Expenditure Profile

    Cum PBP (90% Price, 18% Profit)

    Cum Cost (Expenditures)

    Cum PBP (90% Price, 8% Profit)

    Cum Prog Pay (80% Cost)

    Month

    90% Monthly PBP Examples

  • One AFMC… Powering the World’s Greatest Air Force

    How to Value Events

    65Unclassified

    • Generally, most proposed PBP “values” are based on an expenditure profile– Contract financing assists contractor in

    payment of cost related to performance– Events should be significant and reflect true

    performance on contract– Unrealistic to “cost” out events such as,

    “completion of fabrication of forward fuselage”– Due to this reality, it is critical to ensure that the

    expenditure profile is analyzed to ensure it is not front loaded

  • One AFMC… Powering the World’s Greatest Air Force

    How to Value Events

    66Unclassified

    • PBP Key Step #4 – Determine/Evaluate Monthly Expenditure Profile– Obtain Contractor Expenditure Profile– Validate Expenditure Profile

    • Should reflect same profile as contract proposal• Should not be front loaded• Should not include termination liability• Defense Contract Audit Agency (DCAA) can help• Consider contract history (very important, especially

    in a recurring production program situation)

    PresenterPresentation NotesHighlight how to compare the cost expenditure profile to the proposal as a sanity check to make sure that they run in parallel.

  • One AFMC… Powering the World’s Greatest Air Force

    Importance of Expenditure Profile

    67Unclassified

    Example of Front Loaded Expenditure Profile

    $-$1,000$2,000$3,000$4,000$5,000$6,000$7,000$8,000

    1 3 5 7 9 11 13 15 17 19

    Thou

    sand

    s

    Month

    Cum PBP

    Front Loaded CumCost Real Cum Cost (ActualExpenditures)Cum Prog Pay (80%Cost)

    Due to front loaded expenditure profile, cumulative PBPs are well in excess of actual cumulative cost

    Chart2

    999001000002032616260.8

    4995005000006069148552.8

    9990001000000186326149060.8

    17982001800000452311361848.8

    29970003000000850967680773.6

    3896100390000013765991101279.2

    4661212.122466587821791621743329.6

    5260612.122526587831024202481936

    5760112.122576587838047853043828

    6084787.122609087845033503602680

    6384487.122639087849557153964572

    6584287.12265908785313553.843043644250843.07443491

    6709162.12267158785707324.34752374565859.47801896

    6809062.12268158786117473.396168844893978.71693507

    6873997.12268808786497016.922675415197613.53814033

    6923947.12269308786791102.023519435432881.61881554

    6963907.12269708786939254.023519435551403.21881554

    6993877.12270008786976140.023519435580912.01881554

    7013857.12270208787007278.023519435605822.41881554

    7023847.12270308787030878.023519435624702.41881554

    Cum PBP

    Front Loaded Cum Cost

    Real Cum Cost (Actual Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded Expenditure Profile

    Sheet1

    0.150.80.15

    cumulativeProg Paycum90%

    mocostpricecostpricePBPcum PBP

    1$ 10,000.00$ 11,500$ 10,000$ 8,000$ 11,50010,350.00$ 10,350

    2$ 50,000.00$ 57,500$ 60,000$ 48,000$ 69,00051,750.00$ 62,100

    3$ 100,000.00$ 115,000$ 160,000$ 128,000$ 184,000103,500.00$ 165,600

    4$ 250,000.00$ 287,500$ 410,000$ 328,000$ 471,500258,750.00$ 424,350

    5$ 500,000.00$ 575,000$ 910,000$ 728,000$ 1,046,500517,500.00$ 941,850

    6$ 250,000.00$ 287,500$ 1,160,000$ 928,000$ 1,334,000258,750.00$ 1,200,600

    7$ 100,000.00$ 115,000$ 1,260,000$ 1,008,000$ 1,449,000103,500.00$ 1,304,100

    8$ 50,000.00$ 57,500$ 1,310,000$ 1,048,000$ 1,506,50051,750.00$ 1,355,850

    9$ 10,000.00$ 11,500$ 1,320,000$ 1,056,000$ 1,518,00010,350.00$ 1,366,200

    $ 1,320,000.00

    cum costcum PBPcum Prog Pay

    $ 10,000$ 10,350$ 8,000

    $ 60,000$ 62,100$ 48,000

    $ 160,000$ 165,600$ 128,000

    $ 410,000$ 424,350$ 328,000

    $ 910,000$ 941,850$ 728,000

    $ 1,160,000$ 1,200,600$ 928,000

    $ 1,260,000$ 1,304,100$ 1,008,000

    $ 1,310,000$ 1,355,850$ 1,048,000

    $ 1,320,000$ 1,366,200$ 1,056,000

    Sheet2

    profit0.180.08

    0.90.8

    mocumcumcumcum

    costcostPBPPBPPP

    1$ 8,125$ 8,125$ 8,629$ 7,898$ 6,500

    2$ 12,236$ 20,361$ 21,623$ 19,791$ 16,289

    3$ 21,674$ 42,035$ 44,642$ 40,858$ 33,628

    4$ 77,896$ 119,931$ 127,367$ 116,573$ 95,945

    5$ 97,662$ 217,593$ 231,083$ 211,500$ 174,074

    6$ 98,364$ 315,956$ 335,545$ 307,109$ 252,765

    7$ 102,676$ 418,632$ 444,587$ 406,910$ 334,906

    8$ 336,839$ 755,471$ 802,311$ 734,318$ 604,377

    9$ 1,051,730$ 1,807,201$ 1,919,248$ 1,756,599$ 1,445,761

    10$ 313,202$ 2,120,403$ 2,251,868$ 2,061,032$ 1,696,322

    11$ 305,443$ 2,425,846$ 2,576,249$ 2,357,922$ 1,940,677

    12$ 357,839$ 2,783,685$ 2,956,273$ 2,705,742$ 2,226,948

    13$ 393,771$ 3,177,455$ 3,374,458$ 3,088,487$ 2,541,964

    14$ 410,149$ 3,587,605$ 3,810,036$ 3,487,152$ 2,870,084

    15$ 379,544$ 3,967,148$ 4,213,111$ 3,856,068$ 3,173,718

    16$ 294,085$ 4,261,233$ 4,525,430$ 4,141,919$ 3,408,987

    17$ 148,152$ 4,409,385$ 4,682,767$ 4,285,922$ 3,527,508

    18$ 36,886$ 4,446,271$ 4,721,940$ 4,321,776$ 3,557,017

    19$ 31,138$ 4,477,409$ 4,755,009$ 4,352,042$ 3,581,927

    20$ 23,600$ 4,501,009$ 4,780,072$ 4,374,981$ 3,600,807

    $ 4,501,009

    1

    Front Loaded

    mocumcumcum

    PBPcostcostPBPPP

    $ 50,0001$ 8,125$ 8,125$ 50,000$ 6,500

    $ 100,0002$ 12,236$ 20,361$ 150,000$ 16,289

    $ 300,0003$ 21,674$ 42,035$ 450,000$ 33,628

    $ 783,0354$ 77,896$ 119,931$ 1,233,035$ 95,945

    $ 1,000,0005$ 97,662$ 217,593$ 2,233,035$ 174,074

    $ 600,0006$ 98,364$ 315,956$ 2,833,035$ 252,765

    $ 500,0007$ 102,676$ 418,632$ 3,333,035$ 334,906

    $ 400,0008$ 336,839$ 755,471$ 3,733,035$ 604,377

    $ 200,0009$ 1,051,730$ 1,807,201$ 3,933,035$ 1,445,761

    $ 100,00010$ 313,202$ 2,120,403$ 4,033,035$ 1,696,322

    $ 150,00011$ 305,443$ 2,425,846$ 4,183,035$ 1,940,677

    $ 125,00012$ 357,839$ 2,783,685$ 4,308,035$ 2,226,948

    $ 100,00013$ 393,771$ 3,177,455$ 4,408,035$ 2,541,964

    7500014$ 410,149$ 3,587,605$ 4,483,035$ 2,870,084

    5000015$ 379,544$ 3,967,148$ 4,533,035$ 3,173,718

    3500016$ 294,085$ 4,261,233$ 4,568,035$ 3,408,987

    2000017$ 148,152$ 4,409,385$ 4,588,035$ 3,527,508

    1500018$ 36,886$ 4,446,271$ 4,603,035$ 3,557,017

    1000019$ 31,138$ 4,477,409$ 4,613,035$ 3,581,927

    500020$ 23,600$ 4,501,009$ 4,618,035$ 3,600,807

    $ 4,618,035$ 4,501,009

    Price5,311,190.81

    profit0.11

    0.90.8

    real

    Front Loadedmocum Frontcumcumcum

    Exp CurvecostLoaded ExpPBPPPcost

    $ 100,0001$ 20,326$ 100,000$ 99,900$ 16,261$ 20,326

    $ 400,0002$ 40,365$ 500,000$ 499,500$ 48,553$ 60,691

    $ 500,0003$ 125,635$ 1,000,000$ 999,000$ 149,061$ 186,326

    $ 800,0004$ 265,985$ 1,800,000$ 1,798,200$ 361,849$ 452,311

    $ 1,200,0005$ 398,656$ 3,000,000$ 2,997,000$ 680,774$ 850,967

    $ 900,0006$ 525,632$ 3,900,000$ 3,896,100$ 1,101,279$ 1,376,599

    $ 765,8787$ 802,563$ 4,665,878$ 4,661,212$ 1,743,330$ 2,179,162

    $ 600,0008$ 923,258$ 5,265,878$ 5,260,612$ 2,481,936$ 3,102,420

    $ 500,0009$ 702,365$ 5,765,878$ 5,760,112$ 3,043,828$ 3,804,785

    $ 325,00010$ 698,565$ 6,090,878$ 6,084,787$ 3,602,680$ 4,503,350

    $ 300,00011$ 452,365$ 6,390,878$ 6,384,487$ 3,964,572$ 4,955,715

    $ 200,00012$ 357,839$ 6,590,878$ 6,584,287$ 4,250,843$ 5,313,554

    $ 125,00013$ 393,771$ 6,715,878$ 6,709,162$ 4,565,859$ 5,707,324

    10000014$ 410,149$ 6,815,878$ 6,809,062$ 4,893,979$ 6,117,473

    6500015$ 379,544$ 6,880,878$ 6,873,997$ 5,197,614$ 6,497,017

    5000016$ 294,085$ 6,930,878$ 6,923,947$ 5,432,882$ 6,791,102

    4000017$ 148,152$ 6,970,878$ 6,963,907$ 5,551,403$ 6,939,254

    3000018$ 36,886$ 7,000,878$ 6,993,877$ 5,580,912$ 6,976,140

    2000019$ 31,138$ 7,020,878$ 7,013,857$ 5,605,822$ 7,007,278

    1000020$ 23,600$ 7,030,878$ 7,023,847$ 5,624,702$ 7,030,878

    $ 7,030,878$ 7,030,878

    Sheet2

    Front Loaded PBP

    Cum Cost (Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded PBP

    Sheet3

    Cum PBP

    Front Loaded Cum Cost

    Real Cum Cost (Actual Expenditures)

    Cum Prog Pay (80% Cost)

    Month

    Example of Front Loaded Expenditure Profile

    Cum PBP (90% Price, 18% Profit)

    Cum Cost (Expenditures)

    Cum PBP (90% Price, 8% Profit)

    Cum Prog Pay (80% Cost)

    Month

    90% Monthly PBP Examples

  • One AFMC… Powering the World’s Greatest Air Force

    Valuing Events & Get to Win-Win

    68Unclassified

    • PBP Key Step #5 – Establish Event Values and Create Win-Win Scenario– Compare proposed event values to expenditure

    profile• What is relationship between PBP values and

    expenditure profile?• Will PBPs result in Advance Payments?• Does contractor have an investment in contract?

    – Evaluation Tool = PBP Analysis Model

  • One AFMC… Powering the World’s Greatest Air Force

    Ensuring Win-Win Scenario

    69Unclassified

    •PBP Trade-offs– Holding costs as fixed, trade-offs can be made

    between profit and financing that benefit both Contractor and Government

    – Since its cheaper for the Government to borrow dollars than for a company to do so• The Government can provide more financing (benefiting

    Contractor)• The Contractor can accept a lesser contract price

    (benefiting Government)• Both entities are better off from a Time Value of Money

    Standpoint!

  • One AFMC… Powering the World’s Greatest Air Force

    Ensuring Win-Win Scenario

    70Unclassified

    •PBPs & Weighted Guidelines (WGL)– No working capital adjustment– Increased contract type risk range for contracts

    w/PBPs (over those with progress payments)• Adjust contract type risk based on

    – Frequency of payments– Total amount of payments compared to max allowable– Risk of payment schedule to contractor

    – However…• Use of the PBP Tool is still mandatory, meaning:

    – a WGLs position must be developed using progress payments to establish the baseline for input into the tool

    – the tool will establish the objective profit rate/dollars for a PBP scenario

  • One AFMC… Powering the World’s Greatest Air Force

    Ensuring Win-Win Scenario

    71Unclassified

    • DFARS 232.1004 Procedures.

    – (b) Establishing performance-based finance payment amounts

    • (ii) The contracting officer shall analyze the performance-based payment schedule using the performance-based payments (PBP) analysis tool. The PBP analysis tool is on the DPC website in the Cost, Pricing & Finance section, Performance Based Payments - Guide Book & Analysis Tool tab, at https://www.acq.osd.mil/dpap/cpic/cp/Performance_based_payments.html

    PresenterPresentation NotesThe two step process has been eliminated by this update to the rule. Expect to see an increase in contractors requesting PBPs due to the elimination of this process.

    Note that the use of the PBP tool is still mandatory though and that this tool still compares the cash flow that the contractor would be receiving in a progress payments scenario versus a PBP scenario.

    https://www.acq.osd.mil/dpap/cpic/cp/Performance_based_payments.html

  • One AFMC… Powering the World’s Greatest Air Force

    Ensuring Win-Win Scenario

    72Unclassified

    • PBP Analysis Model– Calculates Internal Rate of Return (IRR) to contractor– Calculates the Net Present Value (NPV) of cash flows to the

    contractor under both progress payment and PBP scenarios– Calculates Cost to Government under both scenarios– Provides “win-win” solution(s)– Provides a means to convert from a progress payment

    situation to PBPs (including an undefinitized contract situation)

    – Model results are only as good as the inputs– A non-scrutinized or lightly scrutinized cost expenditure profile can

    lead to advanced payments– Model does not account for unintended consequences of making

    events severable that should be cumulative (or vice versa)

    PresenterPresentation NotesDFARS still requires the contracting officer to document how they received consideration for an improvement in the contractor’s cash flow from receiving improved financing terms.

  • One AFMC… Powering the World’s Greatest Air Force

    DFARs Update Inclusions

    73Unclassified

    • DFARS additional instructions:– The contracting officer should include in a solicitation

    both the progress payments and performance-based payments provisions and clauses prescribed in this part, when considering both types of payments methods (can only have one in resultant contract)

    – The contracting officer shall document adequate consideration received in the contracting file

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Clauses

    74Unclassified

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Special Contract Provision

    75Unclassified

    • PBP Key Step #6 Develop Special Contract Provisions

    – Provides Schedule of Events, Criteria, Amounts– Helpful to include projected completion dates– Identifies cumulative versus severable events– Identifies line item basis (or whole contract lot)– Provides instructions to Government payment office

    for multiple appropriations– Specifies the liquidation of the PBP– Reminder: May require adjustment for contract

    modifications

    PresenterPresentation NotesHere is a list of other issues to be aware of. You should provide clear instructions to the payment office addressing multiple appropriations. DFAS will want to know how the PBPs are to be liquidated. Finally, keep in mind that you will need to adjust the PBP clause when the contract gets modified.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP “I” DFARS Clause

    76Unclassified

    • Section I, 252.232-7012/7013 PBPs – Whole-Contract Basis / PBPs – Deliverable-Item Basis

    • Table showing how contractors request payments –includes reporting of incurred costs

    • Requires contractor to provide access to accounting books and records to verify incurred costs (upon Contracting Officer request)

    • Although Title is still the preferred form of security, allows Contracting Officers to accept alternate forms of security sufficient to constitute adequate security for the PBPs (in lieu of Title to the assets associated with all work up to and including the specific PBP event)

    PresenterPresentation NotesThere are some items that you should be aware of in the Section I clause for PBPs. The contractor cannot request PBPs more frequently than monthly. DFAS will make only one payment in a given month, so keep that in mind as you are determining the number of payments.

    The contractor will not be entitled to a payment prior to successfully completion of the event. If there is a government caused delay, the CO can break down the event into pieces and pay for those portions that have been successfully completed.

    PBPs must be liquidated by deducting a percentage or designated dollar amount from the delivery payment.

    The CO may reduce or suspend PBPs if the contractor fails to comply with a material contractual requirements, fails to make progress, or is delinquent in the payment of a sub.

    Finally, title (or an alternate form of security as determined by the PCO) vests with the government upon the date of the first PBP for property acquired produced before that date.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP “I” FAR Clause

    77Unclassified

    • Section I, 52.232-32 Performance-Based Payments

    – Contractor requests for PBPs not more frequently than monthly

    – Not entitled to a payment prior to successful completion of the event

    – Liquidate by deducting % or designated dollar amount from delivery payment

    – May reduce or suspend PBPs– Title (or an alternate form of security approved by the

    Contracting Officer) vests with the Government upon the date of the first PBP

    PresenterPresentation NotesThere are some items that you should be aware of in the Section I clause for PBPs. The contractor cannot request PBPs more frequently than monthly. DFAS will make only one payment in a given month, so keep that in mind as you are determining the number of payments.

    The contractor will not be entitled to a payment prior to successfully completion of the event. If there is a government caused delay, the CO can break down the event into pieces and pay for those portions that have been successfully completed.

    PBPs must be liquidated by deducting a percentage or designated dollar amount from the delivery payment.

    The CO may reduce or suspend PBPs if the contractor fails to comply with a material contractual requirements, fails to make progress, or is delinquent in the payment of a sub.

    Finally, title (or an alternate form of security as determined by the PCO) vests with the government upon the date of the first PBP for property acquired produced before that date.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Benefits

    78Unclassified

    Government• Paying for actual, meaningful performance (not presumed progress)• Potential for less administration• PBPs are self-policing • Less oversight of contractor’s accounting system necessary

    PresenterPresentation Notes The upfront work to propose/evaluate/negotiate is much greater with PBPs The validation of events can be more burdensome than progress payments

    (oversight of system still needed if Ktr has progress pay or cost type contracts.

    What are some of the benefits associated with using PBPs? For the government, we are paying for actual performance. There is the potential for less administration, and less oversight of contractors accounting system.

  • One AFMC… Powering the World’s Greatest Air Force

    PBP Benefits

    79Unclassified

    Contractor• Potential for more favorable cash flow (than is available with Progress Payments)• Greater incentive for underrunning a contract• Does not require approved accounting system• Potential for less Government oversight

    PresenterPresentation NotesPBP benefits for the contractor include the potential for an increased cash flow over what they would experience with progress payments. They have a greater incentive for under-running a contract, in that that they will still get paid the full PBP amounts even if they are under-running. PBPs do not require an approved accounting system, and of course, there is the potential for less government oversight.

  • One AFMC… Powering the World’s Greatest Air Force

    Conclusion

    80Unclassified

    By following the “Six PBP Key Steps,” teams can establish win-win PBPs that are well worth the payoff for both Government and contractor.

    Financing POCDerek Kuba, AFMC/PKF [email protected]

    PERFORMANCE BASED PAYMENTS (PBPs)PBP ContentsPBP OverviewBasic Terms/ConceptsBasic Terms/ConceptsBasic Terms/ConceptsBasic Terms/ConceptsMethodsConditions for Customary FinancingPBP Definition FAR PBP PolicyPBP Criteria For UseDFARs 2020 Changes & ImpactsPlanning for PBPPlanning for PBPPlanning for PBPPBP Key StepsDeveloping PBP Events & Completion CriteriaFAR Requirements for PBP EventsFAR Requirements for PBP EventsFAR Guidelines for PBP EventsFAR Guidelines for PBP EventsHow to Develop Events/CriteriaHow to Develop Events/CriteriaHow to Develop Events/CriteriaHow to Develop Events/CriteriaPBP ExercisePBP Example 1PBP Example 1PBP Example 2PBP Example 2PBP Example 3PBP Example 3PBP Example 4PBP Example 4PBP Example 5PBP Example 5PBP Example 6PBP Example 6PBP Example 7PBP Example 7PBP Example 8PBP Example 8PBP Example 9PBP Example 9PBP Example 10PBP Example 10PBP Example 11PBP Example 11PBP Example 12PBP Example 12PBP Example 13PBP Example 13PBP Example 14PBP Example 14Cumulative versus Severable DeterminationCumulative vs Severable DeterminationCumulative vs Severable DeterminationCumulative vs Severable DeterminationValuing PBP Events & Creating a Win-Win ScenarioFAR Requirements for Valuing EventsFAR Requirements for Valuing EventsNegative Contractor Investment in the ContractWhen does Contractor Investment Become Negative or Unreasonably Low?How to Value EventsHow to Value EventsImportance of Expenditure ProfileValuing Events & Get to Win-WinEnsuring Win-Win ScenarioEnsuring Win-Win ScenarioEnsuring Win-Win ScenarioEnsuring Win-Win ScenarioDFARs Update InclusionsPBP ClausesPBP Special Contract ProvisionPBP “I” DFARS ClausePBP “I” FAR ClausePBP BenefitsPBP BenefitsConclusion