PENDING PROJECTS SUMMARY (March 3, 2020) This update provides a summary of all proposed major developments within the City of Petaluma. The development summary tables are separated by Commercial Projects, Mixed Use Projects, Residential Projects and Annexations. Please contact the developer directly for project details such as construction timing, cost and availability.
DEFINITIONS OF STATUS CATEGORIES IN PLANNING PROCESS: Formal project application has been filed for one or more discretionary planning approvals. Residential projects of fewer than two units are not included unless Planning Commission approval is required, nor are non-residential projects that do not result in new development.
ALL PLANNING APPROVALS: The project has received all discretionary approvals from the city, with no appeals pending.
IN PLAN CHECK: The project has received all planning approvals; construction drawings have been submitted to the Building Division.
UNDER CONSTRUCTION: The project has received all planning approvals; final plans approved; building and other permits have been issued; may be under construction.
INACTIVE: Action by applicant needed; more than six months passed since request for action made by staff.
NOTE: This list was prepared by the City of Petaluma Planning Division for informational purposes only. The City does not warrant the accuracy of the information provided.
PLANNER CONTACT INFORMATION HH – Heather Hines, Planning Manager, 707-778-4316, [email protected]
BB – Brittany Ann Bendix, Deputy Planning Manager, 707-778-4314, [email protected] EU – Emmanuel Ursu, Principal Planner, 707-778-4401, [email protected]
AH – Aaron Hollister, Senior Planner, [email protected] TR – Tiffany Robbe, Senior Planner, 707-778-4318, [email protected]
KR – Krystle Rizzi, Associate Planner, 707-778-4472, [email protected] DB – David Brosky, Associate Planner, 707-778-4340, [email protected] ER – Eric Roberts, Assistant Planner, 707-778-4317, [email protected]
![Page 2: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/2.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
Commerical
1 Project: Brooks Note Winery - PLMA-19-0007
Daniel Welles
Summit Engineering, Inc., 463 Aviation
Blvd, Ste 209, Santa Rosa, CA 95403
006-163-015 426 Petaluma Blvd All Planning Approvals 10/2/2019 T-5
The project proposes a winery production facility with
ancillary tasting room and events. The project will
utilize the existing structure at 426 Petaluma
Boulevard North, with some exterior modifications to
the facades. The proposed production facility will be
approximately 4700 sq ft and tasting room will be
2300 square feet.
7,000 KR
2 Project: Wasatch Storage Facility SPAR - PLSR-19-0017
Scott Wyckoff
801-692-1417150-020-008 85 Corona Road In Planning Process 9/10/2019
PCD Rancho
Arroyo Business
Center
New construction of a two-story storage facility
containing 686 storage units, 900 square feet of office
and retail space, and retaining the 14,774 square foot
building location on eastern portion of the parcel
90,540 KR
3 Project: Adobe Road Winery - PLMA-18-0003
Kevin Buckler
707-939-7967008-069-002 1 C Street In Plan Check 3/26/2018 T-5
New construction of a two-story 15,848 square foot
building containing a winery, tasting room, private
event space and a motorsports gallery, collectively
operated as the Adobe Road Winery. The proposal
also includes improvements to the public frontages
along C Street and First Street.
15,848 sf BB
4 Project: 1395 N. McDowell Boulevard SPAR - PLSR-18-0002
Hank Malak
626-583-8348
007-411-0191395 N. McDowell
Blvd. In Plan Check 1/23/2018
PUD - Redwood
Technology Center
New 6,378 square foot 4-unit commercial building on
a vacant building pad established by the Redwood
Techonology Center PUD.
6,378 sf BB
5 Project: Valero Gas Station - PLMA-18-0001
Ed Hale
760-884-7011
007-061-043 &
042
532 E. Washington
StreetIn Plan Check 1/23/2018 MU1A
Demolition of existing gas station and consturction of
a new one in its place, including a convenience store
and smog station
3,036 sf BB
6 Project: McDonald's Remodel - PLSR-17-0030
Stantec Architecture, Inc.
916-669-5928
007-350-015259 N. McDowell
Blvd. Building Permit Issued 10/4/2017 C2
Demolish and reconstruct the existing McDonald's
Restaurant. Net increase of 14 sf. 4,456 sf AH
7 Project: Washington Square Façade Remodel - PLSR-17-0023
Nick Carter
916-383-3333
007-280-055373 S. McDowell
Blvd. All Planning Approvals 8/29/2017 C2
Façade remodel for a portion of the Washington
Square Shopping Center. 50,000 sf of the 200,000
sf shopping center BB
8 Project: Cagwin and Dorward - PLMA-16-0013
Greg LeDoux & Associates
707-795-8855
005-040-0550 Lakeville
HighwayUnder Construction 10/31/2016
PCD Park
Central/Park
Sqaure
New commercial building to accommodate Cagwin
and Dorward Landscaping. Project includes office and
landscape maintenance operations for approx. 100
employees
22,727 sq/ft TR
Page 1 3/2/2020
![Page 3: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/3.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
9 Project: Labcon Warehouse Addition - PLSR-16-0007
Greg LeDoux & Associates
707-795-8855
005-040-039 3200 Lakeville Under Construction 2/16/2016 BP
Addition and associated site improvements including
landscaping, parking facilities, frontage improvements
along Cader Lane and Lakeville Highway.
40,000 sq/ft TR
10 Project: 76 Gas Station Remodel - PLSR-15-0013
Muthana Ibraim
MI Architects, INC.
925-287-1174 x1
007-412-0154998 Petaluma
Blvd. N Under Construction 5/13/2015 C2
Demolition of gas station and construction of a
convenience store, self serve car wash and storage
area.
2,179 sq/ft fueling canopy HH
11 Project: Floathouse - PLSR-14-0013
Greg Sabourin
Petaluma Small Craft Center
007-142-018 150 Weller St. In Plan Check 5/8/2014
SMART Rail
Station Master
Plan
Floating rental office and dock in the turning basin &
restroom facility in Cavanagh Landing Park. 440 sf HH
12 Project: Hansel Toyota Expansion and Remodel - PLSR-14-0009
Henry Hansel
150-020-033 and
-034, -035
1125 Auto Center
Drive Under Construction 5/1/2014 PCD - Auto Center
Expansion to the north and west for showroom, sales
and offices from 14,786 sf to 25,404 sf 25,404 sf HH
13 Project: Petaluma Poultry Expansion - PLSR-14-0004
Petaluma Poultry, Steve Lafranchi,
2700 Lakeville
Hwy. Under Construction 2/3/2014 BP
Addition for office space, parking, and site design
modifications and addition of second shift 4,000 sq/ft HH
14 Project: Petaluman Hotel - PLSR-13-0019
Ross Jones
707-971-9400
007-582-009 2 Petaluma Blvd. S In Planning Process. Waiting on
revisions. 10/31/2013 MU2
Construction of a 54 room boutique hotel
48256 sf TR
15 Project: Safeway Fuel Center - PLSR-13-0012
Santec Architecture
Gary Semling, 707-765-1660,
gary.semling @stantec.com
007-280-046335 S McDowell
Blvd. In Plan Check 7/25/2013 C2
New gas station including 8 dispensers, 16 fuel
stations, canopy and convenience store. 697 sf HH
16 Project: Home 2 Suites - PLSR-18-0025
Matthew Sherrill
Basin Street Properties
707-283-0780
007-411-0341205 Redwood
WayIn Plan Check 8/9/2018
PUD - Redwood
Technology Center
New construction of a 85,802 sf hotel on a vacant pad
established by the Redwood Technology Center PUD.
The hotel will contain 140 guestrooms.
85,802 sf BB
17 Project: BioMarin PLSR-19-0010
Shar Zamanpour
BioMarin
415-382-5726
7770 Lindaro Street
San Rafael, CA 94901
005-280-0091700 S McDowell
BlvdAll Planning Approvals 5/15/2019 Lakeville PCD
Proposed commercial research and development
facility including two buildings, approx. 32,000 and
40,000 square feet on the vacant 5.89-acre project
site.
32,000 sf research and
office; 40,00 sf
warehouse
HH
Page 2 3/2/2020
![Page 4: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/4.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
Mixed Use
18 Project: Scannell Mixed Use Development - PLMA-20-0001
Matt Anderson
Scannell Properties
3468 Mt. Diablo Blvd, Suite B-1115
Lafayette, CA 94549
136-010-024 &
007-171-023
500 Lakeville
Street and 500
Hopper Street
In Planning Process 2/10/2020River Dependent
Industrial
The application is to develop the 39.22 acre site with a
mix of commercial office and residential uses. The
proposal also includes improvements to Hopper Street
and will create a new public riverfront greenway with
multi-use trail along the McNear Channel and
Petaluma River.
275 units; 190,000 gsf of
commercial office useBB
19 Project: East Washington Place SPAR and ZTA - PLMA-19-0009
Norman W. Sears
SGPA Architecture and Planning
200 Pine Street, Studio 500
San Francisco, CA 94104
007-241-002,
007-473-001,
007-251-001,
007-031-001
401 Kenilworth
Drive
In Planning Process. Waiting on
revisions.12/19/2019 MU1B
Site Plan and Architectural Review for two new single
story buildings on vacant pads, site landscaping and
hardscape improvements, updated exterior colors and
finishes, and changes to the Master Signage Program.
Project also includes a Zoning Text amendment to
pursue free standing freeway oriented signs.
BB
20 Project: 132 Petaluma Blvd. Historic SPAR - PLSR-18-0029
Richard Perlstein
Polsky Perlstein Architects
006-282-007132 Petaluma
Blvd. N
In Planning Process. Waiting on
revisions.10/4/2018 T-5
Site Plan and architectural Review for renovation of a
commercial building with a new residential
component. 2,1948 sf of commercial;
2 dwelling unitsBB
21 Project: Omahony Mixed Use Building - PLMA-17-0009
Paul Foley/Mike Omahony
131 Liberty St LLC
415-451-4841
006-361-030 131 Liberty Street In Plan Check 11/14/2017 MU2
Tentative Subdivision Map/Site Plan and Architectural
Review for Mixed Use Development 1,500 sf commerical and
10 residential unitsAH
22 Project: Riverfront 2010 - 11-TSM-0130-CR
Riverfront, LLC
Frank Marinello
136-010-027 500 Hopper Street Under Construction 2/10/2011 T4/T5/CS
Tentative Subdivision Map for Mixed Use
Development that includes 273 Residential units (134
single family, 39 town homes, 100 apartments) hotel
with 120 rooms, 60,000 sq.ft. office, 30,000 sq/ft on a
vacant 35.7 acre site.
273 Residential units (134
single family, 39 town
homes, 100 apartments)
hotel with 120 rooms,
60,000 sq.ft. office,
30,000 sq/ft
EU
23 Project: North River Apartments - PLSR-15-0015
AG Spanos Corp
Karen Garrett
209-955-2574
006-163 -040, -
041
368 and 402
Petaluma Blvd. N In Plan Check 6/1/2015 T5
184 new residential units on a 3.92-acre property
located at the intersection of Petaluma Blvd North and
Oak Street. The project includes the extension of Oak
Street and Water Street North, a new Class I multi-use
path along the Petaluma River, and an emergency
vehicle access roadway to the vicinity of Washington
Street
184 residential units BB
24 Project: Haystack Pacifica - PLMA-16-0001
Carey Algaze
Pacifica Companies
619-296-9000
007-143-003 and
004, 007, 014,
015
215 Weller Street All Planning Approvals 1/7/2013 T5/T6
178 new residential units with 14,516 sq/ft of
commercial at corners. 178 residential units and
14,516 sf of commercialTR
Page 3 3/2/2020
![Page 5: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/5.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
25 Project: Deer Creek Village - 09-SPC-0091
Merlone Geier Management
Mike Grehl
858-259-9909
007-380-005 and
-027
N. McDowell Blvd.
btwn Lynch Creek
and Rainier Ave.
Under Construction 3/29/2009 MU1B
345,000 sq/ft commercial center and associated site
improvements.
345,000 sq/ft HH
Page 4 3/2/2020
![Page 6: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/6.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
Residential
26 Project: DRG Casa Grande - PLMA-19-0006
Doyle Heaton
Falcon Point Assoc, 3496 Buskik Avenue,
#104, Pleasant Hill, CA 94532
017-040-020 &
059
240 & 250 Casa
GrandeIn Planning Process 10/15/2018 R4
The project proposes 35 single-family residential units;
30 market rate and 5 affordable on the 4.5 acre site.
The project also includes establishment of a PUD and
will require a subdivision map.
35 residential units AH
27 Project: Vartnaw Ranch - PLMA-19-0004
Geoff McComic
RBMC Advisors, 1500 3rd Street, Suite B1,
Napa, CA 94559
415-332-3868
019-210-032 149 McNear Ave In Planning Process 9/26/2019 R4
Demolish all existing on-site structures (including
three single-family dwellings) and the construction of
56 residential units on the 4.09-acre site. All five
parcels that comprise the project site would be
merged, and the property would be re-subdivided via
a one-lot parcel map that would establish the
proposed condominium ownership structure for each
of the 56 units in the project.
56 residential units AH
28 Project: 109 Ellis Street- PLSR-18-0030
Jerry Kler Architects
415-332-3868 007-361-003 109 Ellis Street All Planning Approvals 10/15/2018 PUD 13 unit apartment complex 13 residential units AH
29 Project: Deer Creek Residential - PLMA-18-0005
Merlone Geier Management
Mike Grehl
858-259-9909
007-380-034 0 N McDowell All Planning Approvals 10/1/2018 MU1B
New construction of a 129-unit residential
development within five three-story buildings on 4.71
acres. The project will provide up to 194 off-street
parking spaces.
129 residential units BB
30 Project: Olin Residence- PLSR-18-0027
Alan Olin
[email protected] 118 Kimberly Way
In Planning Process. Waiting on
applicant response.9/5/2018 MU2
New 2,461 square foot Single Family home within the
South Hills General Plan sub area, subject to hillside
ordinance.
2,461 square foot single
family dwellingBB
31 Project: Baywood Apartments - PLSR-18-0016
Matt Taylor
Farrell-Faber
707-579-3811
005-060-0422592 Casa Grande
Road In Planning Process 5/31/2018 R5
Proposal for 299 apartments in 27 different three-
story buildings. Project includes a recreation center
and indoor pool and all associated site improvements. 299 units BB
32 Project: PEP Housing Senior Housing - PLSR-18-0006
Robert W. Hayes
415-332-0999008-530-007
951 Petaluma Blvd
SIn Plan Check 2/26/2018 T5
Demolition of all existing buildings/site features and
construcion of affordable housing units in new two to
three story struncture with a manager's unit and one
two-story community building
53 dwelling units and 1
manager's unit.BB
33 Project: Sepaher Residential Building - PLMA-17-0008
Nick Lee
Nick Lee Architecture
415-378-4337
007-154-013315 Lakeville
Street In Plan Check 9/13/2017 MU1A
New building containing 4 residential units and
associated parking on site. Application includes a CUP
to allow for residential on the ground floor. 4 dwelling units BB
34 Project: Williams Residential Historic SPAR - PLSR-16-0039
Peter Williams
[email protected] 006-214-014
331 Kentucky
Street In Plan Check 12/27/2016 R3
Modifications to an existing single family residence
including a 1st floor rear addition and conversion of
exiting attic space into 2nd floor livingspace. single family dwelling BB
Page 5 3/2/2020
![Page 7: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/7.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
35 Project: Brody Ranch Subdivision - PLMA-15-0007
DeNova Homes
Trent Sanson
925-685-0110
trent@denovahomes .com
137-061-042 360 Corona Road Under Construction 11/30/2015 PUD - Brody Ranch
Development of 199 units consisting of 59 detached
single family residences, one duplex and 138
condominiums 199 dwelling units EU
36 Project: East Washington Commons - PLSR-15-0036
Jerry Kler
Jerry Kler Architects
415-332-3868
007-022-033,
055, 058
817, 822, 825 E.
Washington Street In Plan Check 12/21/2015 MU1A
SPAR and CUP for a new 3 story, 24-unit residential
project on 3 parcels, including 2 floors of residential
over ground floor parking and street level tenant
amenities. 24 dwelling units HH
37 Project: Riverbend Crossing PUD, SPAR and Subdivision - PLMA-19-0003
Steve Lafranchi
707-762-3122007-041-006 529 Madison In Planning Process 3/20/2019 R3
Tentative map, PUD Zoning Amendment (PUD and
SPAR for a 29 lot single family residential development
29 dwelling units AH
38 Project: Addison Ranch Apartments - 13-SPC-0122
GALA Construction
Gary Whitesides
916-719-5902
007-610-005
007-610-006
007-610-029
007-610-019
and
007-610-031
200 Greenbriar
Circle Under Construction 9/22/2014 R4
Add an additional 100 multi-family units in an existing
apartment complex.
100 dwelling units TR
39 Project: Davidon Homes - 03-TSM-0396-CR
Davidon Homes
Steve Abbs
019-120-040,
041
Windsor and D
Street
In Planning Process. Revised project
submitted and under review7/21/2014 R1
New construction of 28 single family detached units
and development of open space for future expansion
of Helen Putnam Park.
28 dwelling units HH
40 Project: Sid Commons 03-GPA-0379-CR
Mark Johnson
Acclaim Homes
650-324-9439
019-010-006
and 007, 008,
009
End of Graylawn In Planning Process 12/15/2014 R4 & PUD
New 278 unit apartment complex
278 dwelling units TR
41 Project: Sunnyslope II / the Oaks at Sunnyslope 03-TSM-0460-CR
Lafferty Communities 019-203-008674 Sunnyslope
Road In Plan Check and under construction 8/11/2014
PUD - Sunnyslope
II
The Oaks at Sunnyslope 18 single family pacrcels in
multiple phases. SPAR required for 17 lots and existing
historic house on lot 18. Lots 1-6 and 10-18 have
received SPAR approval as of October 2018. Site
Grading and Construction of lower homes is
underway.
18 dwelling units BB/TR
42 Project: Quarry Heights (Lomas) 09-GPA-0560-CR, 06-SPC-0615-CR
KB Homes
925-983-4522,
019-210-010
019-210-011
019-220-027
019-220-012
Petaluma Blvd. S
(Dutra Quarry)
142 townhome units and 40 SFD are
complete. Remaining 90 SFD not yet
under constrution
2/28/2006PUD- Quarry
Heights
272 new single family and townhomes. 91 single-
family dwellings to be constructed. 272 dwelling units TR
43 Project: Dailey Single Family Dwelling - PLSR-19-0003
Derek Dailey
530-570-9755
008-630-052 123 Kimberly Way All Planning Approvals 1/17/2019PUD - Country
Club Estates
Major SPAR for a new single family home in the
Country Club Estates PUD single family dwelling KR
Page 6 3/2/2020
![Page 8: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/8.jpg)
Map # Applicant APN Project Location Status Date Filed Zoning Description Units/SQFT Planner
44 Project: Sartori Historic SPAR - PLSR-19-0002
Steve Lafranchi
707-762-3122005-250-044
1416 Casa Grande
RoadIn Planning Process 1/2/2019 R2
Proposal to retain existing historic house, subdivide
property into seven parcels, rezone to a PUD, and
pursue SPAR for development of six new homes. 6 dwelling units EU
45 Project: Luchetti Residence Garage Replacement PLSR-19-0001
Brent Russell
[email protected] 245 Keokuk In Plan Check 1/8/2019
R3; Oakhill
Brewster Historic
District
Removal of addition at rear, new construction of
garage and ADU.single family dwelling and
ADUHH
46 Project: 107 6th Street - PLSR-18-0033
Charisse Rathle
415-238-8682
008-104-016 107 6th Street In Planning Process 12/26/2018R3; A Street
Historic District
New garage with approx. 480 sf ADU above. Includes
interior remodel and 2-story expansions at the side
and rear.
single family dwelling and
ADUBB
47 Project: Corona Station SPAR, TM, ZA, IS - PLMA-18-0006
Todd Kurtin (Lomas-Corona Station)
310-230-9278137-061-019
890 N. Mcdowell
Blvd. In Planning Process 12/4/2018 MU1B
Zoning Text Amendment, Major Subdivision, and Site
Plan and Architectural review of new 112 units single
family residential development adjacent to the future
SMART station.
112 dwelling units HH
48 Project: Pettigrew ADU and Porch, Historic SPAR - PLSR-19-0007
Chris Lynch
MAD Architecture
707-481-7410
006-201-009309/307 Walnut
StreetBuilding Permit Issued 4/29/2019
R3/Oakhill
Brewster
Project proposes to construct a new ADU at the
location of an existing ADU on the property. Proposal
also includes construction of a carport and a
restoration of the front porch on the primary dwelling.
ADU AH
Page 7 3/2/2020
![Page 9: PENDING PROJECTS SUMMARY (March 3, 2020) DEFINITIONS … · 12/3/2019 · DB – David Brosky, Associate Planner, 707-7 78-4340, dbrosky@cityofpetaluma.org ER – Eric Roberts, Assistant](https://reader034.vdocuments.us/reader034/viewer/2022052002/6015a6754d10f67ba267f587/html5/thumbnails/9.jpg)
46
28
38
31
3547
4339
29
26
36
45
30
32
48
42
37
4433
40
41
27
34
4
10
3
17
1
8
11
12
16
9
6
13
14
15
5
2
7
20
25
19
2423
21
2218
City of Petaluma - Planning DivisionMap of Major Development Projects
March 3, 2020Commercial Projects Residential Projects
Mixed Use Projects AnnexationsNo new annexation projectsas of March 3, 2020
Data source: Sonoma County, City of Petaluma May 2019$ 0 0.65 1.30.325 Miles
1. Brooks Note Winery2. Wasatch Storage Facility3. Adobe Road Winery4. 1395 N. McDowell Boulevard SPAR5. Valero Gas Station6. McDonald's Remodel7. Washington Square Façade Remodel8. Cagwin and Dorward9. Labcon Warehouse Addition10. 76 Gas Station Remodel11. Floathouse12. Hansel Toyota Expansion and Remodel13. Petaluma Poultry Expansion14. Petaluman Hotel15. Safeway Fuel Center16. Home 2 Suites17. Biomarin
18. Scannell Mixed Use Development19. East Washington Place SPAR and ZTA20. 132 Petaluma Blvd Historic SPAR21. Omahony Mixed Use Building22. Riverfront 201023. North River Apartments24. Haystack Pacifica25. Deer Creek Village
26. DRG Casa Grande27. Vartnaw Ranch28. 109 Ellis Street29. Deer Creek Residential30. Olin Residence31. Baywood Apartments32. PEP Housing Senior Housing33. Sepaher Residential Building34. Williams Residential Historic SPAR35. Brody Ranch Subdivision36. East Washington Commons37. Riverbend Crossing PUD and Subdivision38. Addison Ranch Apartments39. Davidon Homes40. Sid Commons41. Sunnyslope II42. Quarry Heights43. Dailey Single Family Dwelling44. Sartori Historic SPAR45. Luchetti Residence Garage46. 107 6th Street47. Corona Station SPAR TM ZA IS48. Pettigrew ADU and Porch Historic SPAR