Luis Munoz Marin Interna�onal Airport
(SJU) Carolina, PR
SJU Airport Capacity Enhancement Program $125 millions.
CHALLENGE: Planning, Coordina�on & Scheduling for an aggressive
construc�on Design-Build project during the ac�ve opera�on. I
need to provide a smooth construc�on avoiding any flight delay or
passenger inconvenience during the construc�on process. We have
to integrate a new conveyor system to handle the en�re airport
baggage demand without stop the exis�ng one un�l the
commissioning of the new system. At the same �me see all
construc�on aspects of demoli�on, interior remodela�on, new gate
bridge installa�on, new HVAC systems and improvements on
electrical, mechanical and telecommunica�ons.
Abbvie (former Abbo6 Laboratories) Barceloneta, PR
CEIBA Demoli�on Project $36 millions.
CHALLENGE: Planning, Coordina�on & Scheduling for ABBOTT north plant in Barceloneta, PR.
Planning with sec�on managers, engineer department, designers and valida�on group the
cri�cal path in the way to make no impact in the manufacturing process for the remaining
u�li�es. Developing the strategy to reach the goals making scopes for all necessary projects
and/or ac�vity and then include them within a master schedule. The result is a schedule
with over two thousands (2,000) ac�vi�es interconnected for sixteen (16) diverse concurrent
projects needed in the prepara�on for a massive demoli�on work, rerou�ng u�li�es,
coordina�on for controlled shutdowns, decommissioning works, asbestos & lead abatement
and restora�on works.
- Producing two weeks look ahead reports with milestones, total slack, ac�on list for
ac�vi�es not in CPM but needs special a6en�on to resolve issues.
- Producing a monthly stakeholder report to maintain informed the high management.
- Coordina�ng job hazard analysis between safety officer and ABBOTT personnel for entry
work permits.
- Chairman the construc�on mee�ng and coordinate all trade works.
- Looks for the en�re quality and safety of all construc�on
ac�vi�es.
Carnival Cruise Pier no. 4
Old San Juan, PR
Pier 4 (Scheduling works) - Old San Juan, San Juan, PR - $10
millions
Improvements to the tenants area and the visitors area when
leaving the cruise.
CHALANGE: All the works can not affect the cruise traffic, when a
cruise arrives they brings over 2,000 passengers and during the
visit �me they can freely move through the pier. As a scheduler, I
planned all the working period with the traffic Carnival cruise
schedule to avoid any inconvenience with the visitors, tenants and
administra�on.
Parque de Santurce and Headquarter for
Recrea�onal and Sport Department
Los Angeles Street, Santurce, PR
Parque de Santurce and Headquarter for Recreational and Sport Department
(Construction work) - Santurce, PR -$26 millions
CHALANGE: It was an unstable soil beside a lagoon where all the u�li�es was installed
over a thousands of stone columns and all other structures was build over piles. An
interes�ng project with more that 200 employees of our force and another hundreds
of other employees from the subcontractors working in harmony though a big detailed
schedule across all areas of the project.
Santurce, PR
Estacion Sagrado Corazon
TU Tren Urbano
TU Tren Urbano (Site Utilities and plaza works
- Design and Built) - Sagrado Corazón Sta-
tion, Santurce, PR -$8 millions
An important mass traffic project in Puerto Rico.
CHALLENGE: As a design-built project every day is
a new day and also new decisions, the schedule
was a dynamic waving one. With
every design change a new schedule
change occurred but the finish date
doesn't changed. It was a fast track
project with three shiEs to comply
with the milestones.
La Ventana al Mar
Ave. Dr. Ashford, San Juan, PR
La Ventana al Mar (Construction work)
Condado, PR -$4 millions
A project with a par�cular Puerto Rican governor
interest to promote the tourism.
CHALLENGE: It was an accelerated project with
no �me to delays in a very �ght staging area in the
center of The Condado. The planning was funda-
mental to avoid delays, receiving materials just at
the installa�on �me without storage in place.
Cer�fica�ons