pedestrian walkback tunnel, finishes package washington dulles international airport

47
Pedestrian Walkback Tunnel, Finishes Package Washington Dulles International Airport Dulles Pedestrian Walkback Tunnel, Finishes Package Washington Dulles International Airport Pete Dahl Construction Management Senior Thesis, Spring 2004 Penn State University

Upload: piper

Post on 15-Jan-2016

33 views

Category:

Documents


1 download

DESCRIPTION

Dulles Pedestrian Walkback Tunnel, Finishes Package Washington Dulles International Airport. Pedestrian Walkback Tunnel, Finishes Package Washington Dulles International Airport. Presentation. Pete Dahl Construction Management. Senior Thesis, Spring 2004 Penn State University. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Pedestrian Walkback Tunnel, Finishes Package

Washington Dulles International Airport

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Page 2: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Pedestrian Walkback Tunnel, Finishes Package

Introduction

Project Background

Breadth Study: Soil Retention System

Breadth Study: Curtain Wall System

Depth Study: Airport Project Delivery

Conclusions

Page 3: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Intended Use:“Allow passengers the choice of a short walk between the Main Terminal and Concourse B, or transport via Mobile Lounge”

About the Project…

Key Issues:

1) Two levels below grade, Tunnel and Basement Level, 60,000 CY of bedrock to be removed from the site

Page 4: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Key Issues:

2) Entire North Face of façade is glazed curtain wall

3) Pedestrian Walkback Tunnel Project is split up into 4 separate “packages”

About the Project…

Page 5: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Tunnel Shell, Connector A under separate contracts

Existing Conditions for the Finishes Package:

Project Design

Finishes in the Tunnel to recall the swooping roof of the main terminal

Rendering of Tunnel:

Page 6: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Owner: Metropolitan Washington Airports Authority (MWAA)

Owner’s Representative: Parsons Management Consultant (PMC)

Design Consultant: PMC Design

Project Team

General Contractor: Hensel Phelps Construction Co. (HPCC)

Major Subcontractors:

Soil Retention System: Berkel & Co. Contractors

Rock Grinding: J.H. Becker Co.

Earth Removal: Strittmatter Contracting, LLC

Engineer: Earth Tech

Architect: Giuliani Associates

Page 7: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project Organization

OwnerMetropolitan Washington Airport Authority

General ContractorHensel Phelps Construction Company

Owner’s RepresentativeParsons Management Consultant

EngineerEarth Tech

Subcontractors

Design ConsultantPMC Design

ArchitectGiuliani Associates

Fee-Based Contract

Fee-Based Contract

Lump Sum Contract

Lump Sum Contract

Page 8: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project ExecutionProjects are broken into phases, or “Packages”, in this case…

Combined to form “Finishes Package”

Tunnel ShellConnector AConnector B, Tunnel Interior FinishesAPM Tunnel

Page 9: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project Site

Existing Concourse B

Existing Main Concourse

Connector A (NIC)

Connector B

Tunnel Shell (NIC)

“Portal” (Tunnel Entrance) “Object Free Zone”

ACTIVETAXIWAY

ACTIVETAXIWAY

Tunnel Finishes

Page 10: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project Cost

For the Finishes Package alone…

Cost: approx. $25,000,000

Size: Connector B: Four Stories – 20,000 SF

Tunnel: 750 ft long x 30 ft wide – approx. 22,500 SF

Schedule: October 2002 – December 2004

For the Pedestrian Walkback Tunnel project…

Cost: $50,000,000

Schedule: Spring 1998, Design began

December 2004, expected completion

Page 11: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project Timeline

Page 12: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Construction Process

• Drill and place tiebacks

• Spray 1st layer of shotcrete

• Tighten and test tiebacks

• Spray 2nd layer of shotcrete

• Rock Grinder grinds rock in 7’ lifts

• Spoils excavated with Excavator in 7’ lifts

7 repetitions to reach an overall depth of 44’

Page 13: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Original Design8” Shotcrete wall with tiebacks on a 7’ x 7’ grid

4” Shotcrete w/ WWF

Constraints/IssuesNo setback allowed

Highly fractured, weathered rock

Poor RQD

Heavy surcharge loads

Existing Concourse B adjacent to site

Install Tiebacks

4” Shotcrete w/ WWF

Waterproofing with foundations

Page 14: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

System AnalysisPost-Construction

Extremely weathered rock

Frequent minor collapses

Additional shotcrete

Groundwater issue

Sump pumps, temp. plumbing

Holding tanks

Carbon filtration process, fuel spill

Page 15: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Alternate System SelectionSuggested systems, from geotech report:

Braced Walls using Wales and Struts

Soldier Beams & Lagging

Braced Sheeting

Bored-Pile Walls

Diaphragm/Slurry Wall

Page 16: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Alternate System SelectionDiaphragm/Slurry Wall

Major Issue: Rocky subgrade conditions

Solution: The Big Dig in Boston, MA:

Similar soil conditions

Hydromills/Rock Mills

Clamshell bucket removes spoils

Page 17: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Image courtesy of www.bigdig.com

Excavate the Trench

Fill Trench with Slurry

Place Rebar Cage

Pump Concrete… …While Removing Slurry

Fill in all Adjacent Panels

Page 18: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Alternate System Design

Using the same design conditions for the shotcrete & tiebacks

• Terzaghi and Peck Trapezoidal Apparent Earth Pressure Diagram, as recommended by the Geotech

GRADE

BOTTOM OF EXCAVATION44

Designed a beam with 1’ unit width to form a wall of multiple vertical beams

• 44’ Height of Excavation

Page 19: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Alternate System DesignInput the 1’ width beam into STAAD

• Design reinforcing for the wall based on,

• STAAD results

• ACI

Page 20: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Impacts on Sequencing

Old: CYCLE: Grind, Excavate, Shotcrete, Tiebacks, Shotcrete

New: Construct entire slurry wall before excavation begins

CYCLE: Grind, Excavate, Tiebacks

Page 21: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Schedule Impacts

Old: 8 month duration, due to Differing Site Conditions

New: 3 weeks at front end for slurry wall

3-4 days per lift = 5-6 weeks total!

3 weeks

+ 5-6 weeks

8-9 weeks ~2 months!

~6 MONTH

DIFFERENCE

Page 22: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Cost Impacts

Including,

• Rock Grinding: ~$400,000

• Excavation: ~$500,000

OLD SYSTEM:~$2,000,000

NEW SYSTEM:~$1,350,000

COST SAVINGS:

$650,000

Page 23: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

ConclusionsEfficient use of slurry wall in most locations on the project

However,

Alternate system on South side at Concourse B, and at the Tunnel connection

Shotcrete problems vs. Slurry wall problems

The original shotcrete design is justified in its application

on this project.

Page 24: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

OverviewPermanent building systems

• Greater impact on the building’s overall performance

Long-term owner, long-term building

• Improving quality will have lasting effects

• Security vs Energy Efficiency

• Life-cycle costs

Minor components, major impacts

Example: Curtain Wall System

-Glazing

Page 25: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Modeling the original designCurtain Wall modeled into ENERGY10 software

• Double glazed system

• 1/4” glass with low-e coating

• 1/2” airspace

• 1/4” glass

• 2 layers of 1/8” sandwich a polyvinyl membrane

• improves soundproofing

• improves security

• U-value: 0.509 BTU/(hr-SF-F)

Page 26: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Change impacts of various components

Value Engineering

Coatings:

• Low-e

Shading:

• Add shading system

Layers of Glazing:

• Triple glazing

Page 27: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Cost Impacts

Low-e Coating Window Shading Triple Glazing

Annual Energy Use ~12% ~7% ~1%

Annual Energy Cost ~$570 ~$135 ~$50

Initial cost ~$3600 ~$7,000 ~$15,000

Rate of Return ~6.5 years ~50 years ~300 years

Page 28: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

ConclusionsEvaluate the importance of Energy Efficiency with respect to…

• the actual application

• the initial cost

• the operating cost

The original glazing design holds the most value to the owner

in this application.

Page 29: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project EvaluationMajor elements of the design

• Retention System

• Structural System

• Building Enclosure

• Project Delivery?

Design of the Project Delivery Process…

• Affects: Pre-design through close-out

• Impacts:

• Level of coordination

• Methods of communication

• Overall project success

Page 30: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Overview – A Project Delivery SystemProject Delivery Selection

• Owner Decision

• Impacts seen throughout the Pedestrian Walkback Tunnel project

Define impacts on Pedestrian Walkback Tunnel project

Analyze the impacts on other airport projects

Identify common tensions

Applicability to other market sectors…

Page 31: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Project Delivery SelectionElements affecting the Project Delivery Process

Owner experience, capabilities

-e.g. Multiple projects for MWAA; construction staffing

Source of funding

-e.g. Public bonds for MWAA

Project complexity

-e.g. Tunnel Construction is unique

Project timeline

-e.g. Not urgent; compare to data center, pharmaceuticals

Page 32: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

OwnerMetropolitan Washington Airport Authority

General ContractorHensel Phelps Construction Company

Owner’s RepresentativeParsons Management Consultant

EngineerEarth Tech

Subcontractors

Design ConsultantPMC Design

ArchitectGiuliani Associates

Fee-Based Contract

Fee-Based Contract

Lump Sum Contract

Lump Sum Contract

Contracted directly with the owner

The ‘Packaged’ Project Team

Page 33: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

OwnerMWAA

General ContractorHPCC

Owner’s RepresentativesPMC, PMC Design

EngineerEarth Tech Design Team

General Contractor

Owner’s Representatives

Design Team

General Contractor

Owner’s RepresentativesFinishes Package

All Entities are Contracted Directly with the Owner

Tunnel Shell

Package

Connector A Package

Page 34: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Dulles Airport

Pedestrian Walkback Tunnel

MWAA

Tunnel Shell

Connector A

Tunnel Finishes

Connector B

West APM Tunnel

OtherProjects

OtherProjects

Page 35: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Commonalities to other Airport ProjectsData Collection

Survey

• Sent to airports across the country

• Gathering information from multiple airport projects

Results

• Four International Airports:

• Washington Dulles International Airport

• Baltimore Washington International Airport

• Miami International Airport

• Seattle-Tacoma International Airport

Page 36: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Key questions:

How was the project awarded?

How was the project funded?

What type of contract was used?

What were the effects of phasing or packaging on the project?

Additional questions alluded to the relationship developed between project team members

-Corresponds to the number of change orders, schedule extensions and general communication

Commonalities to other Airport Projects

Page 37: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Respondents:

Primarily contractors, an architect

Common Responses:

Use a contractor selection method based on Best Value

• Low Bid is insufficient

• Funding source not a barrier – eg. BWI

Use a lump sum contract

• If quantities are unknown, use Unit Price – eg. Excavation

Commonalities to other Airport Projects

Page 38: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Responses cont.:

Packaging common throughout the Airport market sector

• Due to increased communication between packages

• As a result…significant cost growth

Phasing less common

• Less cost growth seen, as on BWI (NO cost growth)

• Better relationship between Owner’s Rep and GC

Commonalities to other Airport Projects

Page 39: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

AnalysisA change is needed…

The first steps:

• Owner decisions related to Project Delivery have the ability to create, or relieve, tensions in the project team

• How does an owner know if a decision will negatively impact their project?

• More owners must be educated to understand impacts of their decisions

Page 40: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Owner Education

Impact on the Project Possible Results

Low Bidder Highly competitive bidsChange orders are a major issue

Best Value

Contractors are encouraged to find the best way to deliver the project

Change orders are less frequent

Owner and contractor interests are more closely aligned

Help more owners to realize the impacts of…

• Contractor Selection Criteria

Page 41: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Owner Education

Impact on the Project Possible Results

Lump Sum Highly competitive bidsChange orders more likely

Unit Price

Undefined quantity – owner pays for work performed, w/in scope

DSC change orders smaller due to predefined unit price

Less competitiveOwner gets what they pay for, good or bad

Help more owners to realize the impacts of…

• Type of Contracts

Page 42: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Owner Education

Impact on the Project Possible Results

NoneEntire project is bid at one time

Lower bids due to economies of scale

Decrease in coordination required on project

Phasing

Entire project is bid at one time

Lower bids, decreased coordination

Phasing requirements define sequencing

Contractor understands/buys-in to owner’s interests in phasing

PackagingProject is bid out at different times in packages

Higher bids due to increased coordination, mobilization impacts

• Fast-Tracking the project

Page 43: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

ConclusionsA fundamental change is needed.

Until then,

Owner education is key

Allowing for,

Decreased tensions

Better relationships within team

Less wasteful projects

Better product delivered to the owner

Page 44: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Presentation SummaryAnalyzing the Pedestrian Walkback Tunnel,

• Soil Retention System Slurry Wall

• Significant issues eliminated

• Cost and schedule decreased

More importantly,

Analysis focuses around the owner’s needs and requirements and their definition of value

• Curtain Wall System

• Low-e, double glazed windows are optimal

• Project Delivery Systems Analysis

• Further education

• Increase awareness of the impacts of owner decisions

Page 45: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

QUESTIONS?

Page 46: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Impacts

Cost

Costs can be justified through the savings of time from the duration of the excavation, and also the redesign of formwork for the concrete foundation walls.

Old: SRS original cost: approx. $700,000

Change Orders: nearly $700,000

-DOUBLES the original cost of the system

-Due to Flooding and Earth Movement

New: 20,000 SF @ $10/SF = $200,000 for trench and slurry

2000 CY concrete, 1500 tons of rebar = $250,000

Rock Grinding: $400,000 (unchanged)

Excavation: $500,000 (unchanged)

Page 47: Pedestrian Walkback Tunnel,           Finishes Package Washington Dulles International Airport

Introduction

Project Background

Soil Retention System

Curtain Wall System

Airport Project Delivery

Conclusions

Dulles Pedestrian Walkback Tunnel, Finishes PackageWashington Dulles International Airport

Pete Dahl

Construction Management

Senior Thesis, Spring 2004

Penn State University

Impacts

Schedule

Old: 8 month duration 7 lifts ~ 1 month per lift

New: 3 weeks added at the front end of the project for slurry wall

-Mobilization: 1 week

-100 lf/day @ 400 lf = 4 days ~ 1 week

-Demobilization: 1 week

Better flow of work due to decreased activities on site

-2 rock grinders: 2 days

-Full use of loader and excavator

-Tiebacks installed in 2 days

3-4 days per lift = 5-6 weeks total!