ped-bike project development transportation

14
1|Ped-Bike Project Development PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION Date September 8, 2020 To Zef Wagner, PBOT From Nick Gross, Amy Griffiths, and Susan Wright; Kittelson & Associates, Inc. Robert Rippee; Aligned Engineering Tom Wiser; Wiser Rail Engineering Project NW 9 th Avenue (NW Naito Parkway to NW Overton Street) Subject Final Concept Development Summary Document Introduction The NW 9 th Avenue (NW Naito Parkway to NW Overton Street) project is located in NW Portland and serves as a key connection from Naito Parkway to the Pearl District neighborhood. NW 9 th Avenue, NW Naito Parkway, and NW Overton Street are designated city bikeways as identified in the City of Portland’s Transportation System Plan (Reference 1). Today, the short 250-foot segment of NW 9 th Avenue, connecting NW Naito Parkway to NW Overton Street is not equipped with bicycle facilities and the existing curb-to-curb cross section is constrained due to the oversized center median located on the northeast side of the railroad. Furthermore, the existing roadway surface and at-grade railroad crossing is severely deteriorated resulting in an unpleasant and potentially hazardous crossing for all modes of transportation. Figure 1 illustrates the project area and adjacent tax lot information. Purpose The purpose of the NW 9 th Avenue (NW Naito Parkway to NW Overton Street) project is to fill the existing bicycle facility network gap by providing a low-stress separated facility, improve the deficient pavement conditions and enhance the existing railroad crossing to meet American’s with Disability Act (ADA) requirements.

Upload: others

Post on 12-May-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

1|Ped-Bike Project Development

PED-BIKE PROJECT

DEVELOPMENT TRANSPORTATION

Date September 8, 2020

To Zef Wagner, PBOT

From Nick Gross, Amy Griffiths, and Susan Wright; Kittelson & Associates, Inc.

Robert Rippee; Aligned Engineering

Tom Wiser; Wiser Rail Engineering

Project NW 9th Avenue (NW Naito Parkway to NW Overton Street)

Subject Final Concept Development Summary Document

Introduction

The NW 9th Avenue (NW Naito Parkway to NW Overton Street) project is located in NW Portland and

serves as a key connection from Naito Parkway to the Pearl District neighborhood. NW 9th Avenue, NW

Naito Parkway, and NW Overton Street are designated city bikeways as identified in the City of Portland’s

Transportation System Plan (Reference 1). Today, the short 250-foot segment of NW 9th Avenue,

connecting NW Naito Parkway to NW Overton Street is not equipped with bicycle facilities and the

existing curb-to-curb cross section is constrained due to the oversized center median located on the

northeast side of the railroad. Furthermore, the existing roadway surface and at-grade railroad crossing is

severely deteriorated resulting in an unpleasant and potentially hazardous crossing for all modes of

transportation.

Figure 1 illustrates the project area and adjacent tax lot information.

Purpose

The purpose of the NW 9th Avenue (NW Naito Parkway to NW Overton Street) project is to fill the existing

bicycle facility network gap by providing a low-stress separated facility, improve the deficient pavement

conditions and enhance the existing railroad crossing to meet American’s with Disability Act (ADA)

requirements.

Page 2: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

J

J

0 201020

Scale: 1" = 20'

NW

9T

H A

VE

R

A

IL

R

O

A

D

Portland, Oregon 1

NW 9th Avenue - Field Plan June 2020

Figure

N

W

O

V

E

R

T

O

N

S

T

R

E

E

T

NW

N

AIT

O P

AR

KW

AY

PROJECT AREA

AutoCAD SHX Text
S
Page 3: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

3| Ped-Bike Project Development

Background

The project team conducted an extensive background review of existing planning and design

documents relevant to the development of a conceptual design for the NW 9th Avenue (NW Naito

Parkway to NW Overton Street) project including:

GIS Tax Lot Data,

NW 9th Avenue, NW Park Avenue, and NW Overton Street Planned Bicycle Facility Improvements,

NW Naito Parkway/NW 9th Avenue Intersection As-Built Plans intersection, and

NW River District Quiet Zone Plan

Based on a review of the planning and design documents noted above, the conceptual design for NW

9th Avenue (NW Naito Parkway to NW Overton Street) was developed to be integrated seamlessly into

the recent bicycle facility improvements along NW Naito Parkway, future planned bicycle facility

improvements along NW Overton Street and NW 9th Avenue (south of NW Overton Street), while

maintaining the NW River District Quiet Zone Plan requirements set for the project area.

A detailed summary of the Background Planning and Design Documents reviewed is included in

Appendix “A”.

Planned Bicycle Facility Improvements

NW Overton Street is identified as a Tier 1 project in the City of Portland’s Northwest in Motion Plan

(Reference 2). Tier 1 projects are considered the highest priorities for funding and implementation over

the next five years and are projects that have been developed to a higher level of readiness through the

Northwest in Motion Plan. The NW Overton Street Tier 1 bicycle facility improvement project will convert

NW Overton Street to a vehicular one-way eastbound configuration; however, bicycles will be able to

travel bi-directional on NW Overton Street. A conceptual design for buffered bike lanes along NW 9th

Avenue (south of NW Overton Street) is also under review by the City of Portland and identified as a near-

term project in the City’s Transportation System Plan.

NW River District Quiet Zone Plan

As illustrated in Figure 1, an existing raised median is located on the northeast and southwest sides of the

railroad. The median is in place to prohibit vehicles from by-passing the activated railroad gate arms

during a locomotive crossing. As a designated “Quiet Zone” locomotive horns are not routinely or

required to be sounded during a locomotive crossing.

The design for the median located on the northeast side of the railroad identified in the NW River District

Quiet Zone Plan was implemented to accommodate southbound freight and postal service vehicles

turning onto NW 9th Avenue from NW Naito Parkway. Since the NW River District Quiet Zone Plan was

adopted, the NW 9th Avenue/NW Naito Parkway intersection and approaching segments to the

intersection have been reconstructed, converting the previous 5 lane cross section to a 3 lane cross

section with buffered bike lanes. As a result, the vehicular travel lanes have been shifted to the northeast,

providing additional turning clearance for a northwest bound left-turning vehicle from NW Naito Parkway

onto NW 9th Avenue.

Page 4: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

4| Ped-Bike Project Development

Field Visit and Reporting

The project team conducted a field visit to the project site on March 9, 2020 to document existing

physical and operational conditions of the project site and to develop a further understanding of the

curb-to-curb constraints, cross section elements, railroad infrastructure, and adjacent bicycle facilities. A

detailed summary of field observations, photographs, and field measurements recorded by the project

team is included in Appendix “B”.

Existing Conditions

Today, the existing cross section of NW 9th Avenue (NW Naito Parkway to NW Overton Street) consists of

two travel lanes (varying widths) and a raised center median (varying width); however, no dedicated

bicycle facilities are provided. The curb-to-curb cross section width is approximately 44 feet. Exhibit 1

illustrates the existing roadway cross section.

Exhibit 1: Existing Roadway Cross Section

As illustrated in Figure 1 and Exhibit 1, the cross section elements and associated widths vary on the

northeast and southwest sides of the railroad. To the northeast, the existing raised median is

approximately 11 feet at its widest point (closest to the railroad), tapering down to a width of

approximately 1-foot (closest to NW Naito Parkway). The adjacent travel lane width on the northwest side

of the median fluctuates and narrows to a width of approximately 19 feet closest to the railroad.

On the southwest side of the railroad, the curb-to-curb cross section is generally consistent including two

travel lanes at approximately 20 feet and a 1.5-foot wide raised center median. Closest to the railroad,

the travel lane on the northwest side of the raised center median is approximately 19 feet and the travel

lane on the southeast side is approximately 24 feet.

Railroad Infrastructure

The existing crossing is composed of rubber OMNI crossing panels on the two-track crossing. It utilizes two

cantilevers with six sets of flashing-lights on each and two automatic gates. Combined with the raised

concrete center medians, the railroad infrastructure meets the qualifications for a FRA mandated quiet

zone.

11’ 12’12’ 19’ 14’

44’

SidewalkTravel Lane

(width varies)

Median

(width varies)

Travel Lane

(width varies) Sidewalk

Page 5: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

5| Ped-Bike Project Development

Conceptual Design

The concept design for NW 9th Avenue has been developed to a 5-10% concept level and is intended to

support future grant applications for funding and implementation. The conceptual design relies on the

opportunity to reconstruct the median located on the northeast and southwest sides of the railroad in

order to free up space for bicycle facilities within the existing curb-to-curb cross section. Exhibit 2 illustrates

the proposed cross section.

Exhibit 2: Proposed Roadway Cross Section

As illustrated in Exhibit 2, the concept proposes to reconstruct and relocate the existing medians on the

northeast and southwest sides of the railroad to a width of approximately 1-foot, consistent with the

design requirements identified in the NW River District Quiet Zone Plan1.

Proposed Bicycle Facility Improvements

As part of the roadway reconstruction, the cross section is proposed to be restriped to include two 11-foot

travel lanes (including one-foot shy distance from curbs), two 7.5-foot bike lanes with 3-foot buffers

including raised concrete delineators with flex-posts, and a 1-foot center median island. In constrained

locations, the buffer may be required to be reduced; however, the 7.5-foot bike lane is proposed to

remain throughout the project extents.

Based on the Bicycle Level of Traffic Stress (BLTS) methodology, the proposed cross section and

associated bicycle facility will achieve a BLTS 1 score due to the posted speed of 25mph, number of

travel lanes, bicycle facility width, and buffer space (vertical and horizontal). The BLTS 1 score is regarded

as a suitable facility for people biking at all ages and abilities.

Conceptual Design

Figure 2 illustrates the 2D conceptual design for NW 9th Avenue (NW Naito Parkway to NW Overton

Street). Exhibit 3 illustrates a 3D bird’s eye perspective of the recommended improvements.

1 The final design should be refined to further meet the detailed requirements identified in the NW River District Quiet Zone Plan

11’ 7.5’7.5’ 12’

1’

12’ 3’3’ 11’

44’

Sidewalk Bike Lane Travel Lane(including shy)

Bike Lane SidewalkBu

ffer

Buffe

rTravel Lane(including shy)

Page 6: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

J

J

0 201020

Scale: 1" = 20'

RAISED CENTER MEDIAN

ISLAND (WITH 1-FOOT SHY

ON BOTH SIDES)

NW

9T

H A

VE

R

A

IL

R

O

A

D

Portland, Oregon 2

NW 9th Avenue - Improvement Plan September 2020

Figure

N

W

O

V

E

R

T

O

N

S

T

R

E

E

T

NW

N

AIT

O P

AR

KW

AY

11.0'

7.5'

3.0'

3.0'

3.0'

7.5'

3.0'

1.0'

RELOCATE

RAISED CENTER

MEDIAN ISLAND

44.0'

7.5'

THE CROSSING PANELS

SHOULD BE EXTENDED 3'

BEYOND EDGE OF

SIDEWALK WHEN RAILROAD

REBUILDS CROSSING

CONCRETE TRAFFIC

SEPARATORS

TRACKS

NO

TRAIN HORN

DO NOT

STOP

ON

TRACKS

R8-8

2

W10-3L

TRACKS

2

DO NOT

STOP

ON

TRACKS

R8-8

DO NOT

STOP

ON

TRACKS

R8-8

W10-1

INSTALL DO

NOT STOP ON

TRACKS SIGN

(R8-8)

EXISTING NO

PARKING

(R8-3) SIGN

TO REMAIN

EXISTING

NO PARKING

(R8-3) SIGN

TO REMAIN

INSTALL SIDE ROAD

AWS (W10-3L)

INSTALL

NEW AWPM

IN LANE

INSTALL NEW

BICYCLE AWPM

(50' IN ADVANCE

OF SCL)

DO NOT

STOP

ON

TRACKS

R8-8

EXISTING NO

PARKING (R8-3)

AND DO NOT

STOP ON TRACKS

(R8-8) SIGNS TO

REMAIN

EXISTING NO TRAIN

HORN (W10-9P) AND

NO PARKING (R8-3)

SIGNS TO REMAIN. ADD

AWS (W10-1) SIGN

FUTURE NEED TORELOCATE EXISTINGLIGHT POLE OUTSIDEOF SIDEWALK

EXISTING RAILROAD

FLASHING-LIGHT

SIGNAL WITH

AUTOMATIC GATE,

X-BUCK (R15-1) AND

2-TRACKS (R15-2P)

SIGNS TO REMAIN

REPLACE TACTILE STRIPS PER

ODOT RD758, 12'-8" FROM

OUTSIDE RAIL (4 LOCATIONS)

INSTALL DO NOT STOP ON

TRACKS SIGN (R8-8)

EXISTING NO PARKING

(R8-3) SIGN TO REMAIN

INSTALL NEW AWPM

125' FROM SCL AND

JUST PRIOR TO THE

CROSSWALK

EXISTING AWS

(W10-1), NO TRAIN

HORN (W10-9P)

SIGNS TO REMAIN

INSTALL NEW BICYCLE

AWPM (50' IN

ADVANCE OF SCL)

EXISTING NO

PARKING (R8-3)

SIGN TO REMAIN

EXISTING

RAILROAD

CANTILEVER

TO REMAIN

EXISTING SIDE

ROAD AWS TO

REMAIN

(W10-3R)

EXISTING DO NOT

STOP ON TRACKS

(R8-8) SIGN TO

REMAIN

EXISTING

RAILROAD

CANTILEVER

TO REMAIN

EXISTING RAILROAD

FLASHING-LIGHT SIGNAL

WITH AUTOMATIC GATE,

X-BUCK (R15-1) AND

2-TRACKS (R15-2P)

SIGNS TO REMAIN

12.75'

W10-1

R R

W15-1

W15-1

W10-3R

R R

W10-9P

SAWCUT EXISTING

SIDEWALK A MIN. OF 2' AND

REPLACE WITH ASPHALT.

REPAIR CRACKED

SIDEWALK. (4 LOCATIONS)

66.0'

15.0'

10.0'

NO

TRAIN HORN

W10-9P

REMOVE AND REPLACE

TRAFFIC SIGNAL

VEHICLE AND BIKE

DETECTOR LOOPS

11.0'

53.8'

RAISED CENTER MEDIAN

ISLAND (WITH 1-FOOT SHY

ON BOTH SIDES)

RELOCATE

RAISED CENTER

MEDIAN ISLAND

DRAFT 2D CONCEPT DESIGN

APPLY SKIP

YDD LANE LINE

APPLY GREEN BIKE LANE

SKIP BLE-G TREATMENT

FOR NB BIKES

INSTALL NEW

LEFT/RIGHT TURN

BICYCLE STENCIL

AutoCAD SHX Text
S
AutoCAD SHX Text
panelStyle:warning.ssi
AutoCAD SHX Text
panelName:W2-1
AutoCAD SHX Text
panelQuantity:1
AutoCAD SHX Text
panelStation:none
AutoCAD SHX Text
panelMaterial:0
AutoCAD SHX Text
legendMaterial:0
AutoCAD SHX Text
panelMounting:0
AutoCAD SHX Text
panelWidthLock:0
AutoCAD SHX Text
panelHeightLock:0
AutoCAD SHX Text
marginAlign:9
AutoCAD SHX Text
panelRoundCorners:0
AutoCAD SHX Text
constructPanelMode:0
AutoCAD SHX Text
constructPanels:36|24|18
AutoCAD SHX Text
panelSizes:BIKE:18x18,MIN.:24x24,STD.:30x30,EXP.:36x36,SPCL.:48x48
AutoCAD SHX Text
panelStandard:2
AutoCAD SHX Text
levels:GSCOLORFILL|GSBWFILL|GSOUTLINE
AutoCAD SHX Text
version:2
AutoCAD SHX Text
widthRounding:1
AutoCAD SHX Text
heightRounding:1
AutoCAD SHX Text
panelShape:0
AutoCAD SHX Text
panelBorderRadius:12.000
AutoCAD SHX Text
chevronTipRadius:12.000
AutoCAD SHX Text
chevronShoulderRadius:12.000
AutoCAD SHX Text
panelStyle:warning.ssi
AutoCAD SHX Text
panelName:W2-1
AutoCAD SHX Text
panelQuantity:1
AutoCAD SHX Text
panelStation:none
AutoCAD SHX Text
panelMaterial:0
AutoCAD SHX Text
legendMaterial:0
AutoCAD SHX Text
panelMounting:0
AutoCAD SHX Text
panelWidthLock:0
AutoCAD SHX Text
panelHeightLock:0
AutoCAD SHX Text
marginAlign:9
AutoCAD SHX Text
panelRoundCorners:0
AutoCAD SHX Text
constructPanelMode:0
AutoCAD SHX Text
constructPanels:36|24|18
AutoCAD SHX Text
panelSizes:BIKE:18x18,MIN.:24x24,STD.:30x30,EXP.:36x36,SPCL.:48x48
AutoCAD SHX Text
panelStandard:2
AutoCAD SHX Text
levels:GSCOLORFILL|GSBWFILL|GSOUTLINE
AutoCAD SHX Text
version:2
AutoCAD SHX Text
widthRounding:1
AutoCAD SHX Text
heightRounding:1
AutoCAD SHX Text
panelShape:0
AutoCAD SHX Text
panelBorderRadius:12.000
AutoCAD SHX Text
chevronTipRadius:12.000
AutoCAD SHX Text
chevronShoulderRadius:12.000
Page 7: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

7|Ped-Bike Project Development

Exhibit 3: Conceptual 3D Bird’s Eye Perspective

Page 8: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

8|Ped-Bike Project Development

Recommended Improvements

As illustrated in Figure 2 and Exhibit 3, the recommended improvements for the NW 9th Avenue (NW Naito

Parkway to NW Overton Street) support a low-stress, and continuous bicycle facility treatment suitable for

all ages and abilities.

Bicycle Facilities

As described previously, the conceptual design for NW 9th Avenue proposes 7.5-foot buffered bike lanes

with raised concrete delineators located within the 3-foot buffer zone. The proposed bicycle facilities are

planned to tie into the existing NW Naito Parkway bicycle facilities and future improved bicycle facilities

along NW Overton Street.

Median Modifications

All improvements for the NW 9th Avenue concept design rely on the relocation and modifications to the

existing center median. By narrowing the median to a consistent width of 1-foot, bicycle facilities can be

accommodated within the curb-to-curb cross section throughout the project extents while maintaining

the design guidance outlined in the NW River District Quiet Zone Plan and needs of the Railroad.

Roadway Resurfacing & Striping

Resurfacing the roadway through a mill and overlay process provides the opportunity to raise the railroad

tracks to match the roadway surface, reducing the current abrupt and uncomfortable railroad crossings

for all modes. As part of the roadway resurfacing, the existing loop detection for the NW 9th Avenue/NW

Naito Parkway intersection approach will be relocated.2

Railroad Infrastructure & Striping

The existing railroad infrastructure (railroad cantilever, flashing-light signal with automatic gate) is

recommended to be maintained, as improvements to the NW 9th Avenue project will not impact the

railroad infrastructure. The Portland Terminal Railroad (PTR) has proposed to replace the existing rubber

crossing panels with concrete panels. In addition, it is recommended that PTR raise the tracks to match

the roadway surface elevation as part rubber panel replacement project.

New vehicle and bicycle Advance Warning Pavement Marking (AWPM) striping is recommended to be

installed at railroad crossing approaches as well as new Stop Clearance Lines (SCL) at the gates.

As identified in Figure 2 and Exhibit 3, the concept design recommends extending the newly installed

concrete panels 3 feet beyond the edge of sidewalk when the railroad improvement project is

advanced. All four tactile warning strips at sidewalk approaches to the railroad crossing are

recommended to be replaced. Additionally, two “Do Not Stop on Tracks” signs are recommended to be

installed on the opposite side of the tracks to the vehicle movement as well as an Advance Warning

Sign’s (AWS) along NW Naito Parkway alerting motorist of the railroad crossing. Further details on railroad

improvements and modifications are included in Appendix “C”.

General Improvements

The existing light pole on the west side of the roadway (north of the railroad) is recommended to be

relocated outside of the sidewalk to create a wider and more passable walkway.

2 Railroad improvements are anticipated to be completed by railroad and are not included in planning level cost estimate.

Page 9: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

9| Ped-Bike Project Development

Truck Turning Analysis

A truck turning analysis was conducted using AutoTURN to determine the location and feasibility of

relocating the northeasterly most portion of the median on the northeast side of the railroad. Based on

conversations with PBOT, the analysis used a T-1 Fire truck for the turning movement design vehicle to

determine whether the design vehicle could turn left or right from NW Naito Parkway onto NW 9th Avenue

without impacting the proposed median location. Based on the analysis, the proposed median may be

modified as proposed without impacting truck turning. The detailed truck turning analysis and associated

figures are included in Appendix “D”.

Planning Level Cost Estimates

Planning level cost estimates were produced in PBOT agency format for the proposed improvements

associated with the NW 9th Avenue (NW Naito Parkway to NW Overton Street). The cost estimate

assumes no acquisition of ROW. Improvements made to the railroad infrastructure, including the raising

of the existing railroad and replacing rubber panels will conducted by Railroads (BNSF; UPRR; PTTR). No

environmental, parks, zoning, Bureau of Environmental Services (BES) coordination is anticipated.

Based on the preliminary planning-level cost estimate, the total cost for implementing the recommended

improvements is $473,000.

Total Construction: $211,000

Project Management: $13,000

Design Engineering: $45,000

Construction Management: $27,000

Overhead: $69,000

Total Inflation and Allowance for Design Refinement: $108,000

The detailed cost estimate breakdown in PBOT agency format is provided in Appendix “E”.

Next Steps

The recommended conceptual design considers existing conditions and planned bicycle facilities to

address the existing bicycle network gap and deficient pavement conditions along NW 9th Avenue

between NW Naito Parkway and NW Overton Street. The conceptual design has been developed based

field observations, a review of background data and existing infrastructure, input from PBOT staff, and is

intended to support PBOT in developing a grant application to secure funding for project

implementation.

Page 10: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

Appendix A

Background Planning and

Design Documents

Page 11: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

Appendix B

Field Observation &

Reporting Memo

Page 12: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

Appendix C

Final Railroad Tech Memo

Page 13: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

Appendix D

Truck Turning Analysis

Page 14: PED-BIKE PROJECT DEVELOPMENT TRANSPORTATION

Appendix E

Planning-level Cost Estimates