  • 8/13/2019 PDOC-53-2013-RA-04

    1/11

    ClientTHYNA PETROLEUM

    SERVICES7 Avenue Abdelrahmen El GhafikiBP 069 / 3069

    Sfax-HachedSfax (Tunisia)Phone: 216 74 229 999 - Fax: 216 74 299 916

    TENDER REFERENCE

    PUR/TEN/02/2013

    ConstructorHALWANI COMPANY Ltd

    INDUSTRIAL AND METALCONSTRUCTION

    Zone Industrielle Madagascar Prs SomatraCP 3000Sfax (Tunisia)

    Phone: 216 74 497 166/010 - Fax: 216 74 497 795

    DOCUMENT No.

    PDOC-53/2013-RA-04

    Project Title:

    LOADING / OFFLOADING STATIONSAND METERING SKIDS INSTALLATION

    AT TANK BATTERY / GUEBIBA BASE & TRAPSA

    RISK ASSEMEMENT Rev. 00

  • 8/13/2019 PDOC-53-2013-RA-04

    2/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 2 of 11

    Job Number : OF 053/2013

    Task or Work activities : Supply and Erection of Trucks loading and

    offloading steel stations at Tank Battery / Guebiba

    base & Trapsa, including procurement and

    pre-construction will all Civil & Steel Works

    needs.

    Site(s) : TANK BATTERY StationGUEBIBA BaseTRAPSA Terminal

    Equipment to be used : Civil Works:

    Concrete Mixer Truck, Concrete Pump, Hoses /Concrete shoots, Concrete buckets, AirCompressor, Survey Equipment, Level, TotalStation ( Surveying instrument for checking thelevels & distances ), Masonry Accessories,Wheel Barrows, Concrete Vibrators

    Erection Steel Works:

    L dd M bil S ff ld H d t l F klift

  • 8/13/2019 PDOC-53-2013-RA-04

    3/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 3 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 3 of 11

    # ACTIVITYSequence ofworking

    activities

    HAZARDSThe potential to causeharm (heath, Injury,

    Property damage,environment etc.)

    CONSEQUANCES(The harm whichcould possibly

    occur)

    RISK RATINGCONTROL MEASURESDescribe controls that are required to be taken RESIDUAL RISK

    F S R F S R

    1 Vehicle/Equipmentmovementinside therestricted area

    Vehicle movement Driver

    Labors

    Forman

    2 3 HIGH Close supervision

    Identify vehicle routes

    Vehicle to leave the area once job is complete

    Journey Management system to be implemented

    1 2 LOW

    2 ManualExcavation

    Employees working

    near the pits

    Environmental hazard

    H2S

    Labors

    Forman

    2 3 HIGH All heavy machinery / vehicles should not be

    allowed working without assessing banks man

    Carry out a physical survey to whole surrounding

    area

    Limited workers allow to work at one location

    Close supervision

    1 1 LOW

    3 Mechanicalexcavation

    Employees working

    near the moving

    equipment/trench

    Environmental hazard

    Equipment moving

    Driver

    Labors

    Forman

    2 3 HIGH Emergency procedure and contingency plan to be

    in place and cascaded to all crew members and

    really available at sit locations

    Primary and secondary assembly point to be

    assigned by considering the prevailing

    Close supervision

    1 1 LOW

  • 8/13/2019 PDOC-53-2013-RA-04

    4/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 4 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 4 of 11

    4 Lifting operationand installationof pre-cast

    foundations andslabsfoundations andslabs into thetrench

    Lifting

    Wind speed

    Labors

    Forman

    3 3 HIGH Close supervision

    Identify rigging location

    Lifting machine placement shall be at safe

    distance from live lines/equipment

    Lifting machine leave the plant once complete the

    job

    1 1 LOW

    5 Mixing &Pouring ofconcrete

    Cement

    Moving parts of the

    rotating mixer

    Labors

    Forman

    2 3 HIGH Close supervision 1 1 LOW

    6 Back filling andCompacting ofsand & Gatch

    Moving Equipment

    operation

    Dust

    Vibration

    Impact/Hitting from

    compacting machine

    Labors

    Forman

    Operator

    2 3 HIGH All rotating parts of the machine should be in

    place

    Avoid long time exposure to dust/vibration:

    frequent rests

    Employ a minimum hand grip to observe less

    vibration

    1 2 LOW

  • 8/13/2019 PDOC-53-2013-RA-04

    5/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 5 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 5 of 11

    7 Erection ofprecastelements with

    mobile/crane

    fall of person from

    height

    Failure of slings or

    other lifting gears

    Electrocution from

    portable hand tools

    Cut and bruise

    injuries to erectors

    Unsafe lifting and

    fixing by erectors

    Untrained erectors

    Miss communication

    between rigger, tirfor

    lifters and crane

    operator.

    Structural failure

    Collapse of edge

    protection

    Erector

    Forman

    2 3 HIGH All works to be carried out as per approved

    method statement document

    All crane lifts to be controlled by a competent and

    authorize signaler/Banks man.

    The crane will be tested and certified as per

    manufacturers recommendations and statuary

    regulations.

    All lifting gear (Slings, chain, etc.) to be tested.

    Daily before the start of work Forman should

    visually examine all lifting gears for any defects:

    Responsibility Site Forman

    Only competent erectors to be used for the

    structure erection

    Mutually understandable signals to be used

    between crane operator and rigger. If necessary use

    the walky talkie

    All erectors to use full body harness and latch

    them to the standard lifeline

    Forman should inspect the precast structure on

    arrive for any crack or defects than can lead to thecollapse of it during erection

    All the workers and staff should have specifics

    site safety induction by safety officer and records to

    be kept.

    1 2 LOW

  • 8/13/2019 PDOC-53-2013-RA-04

    6/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 6 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 6 of 11

    8 Unloading ofstructure parts

    Failure of Crane,

    Slings, clutch

    Fall of persons from

    height

    Crushing injuries to

    workers caused by

    coming between

    structure parts and truck

    Overloading the crane

    Structural failure

    Impact or collision

    Labor

    Operator

    2 3 HIGH Respective supervisor/ operator should examine

    the slings

    Clutches, before starting the work.

    Cranes should have valid third party inspection

    certificate

    Clearly marking safe working load

    Labors should use ladders to go up release the

    clutch

    Labors always wear full body harness and latch

    them at Top

    Labors should be very careful during the work and

    not to put body parts under the structure part(s)

    Competent and trained operator to do the lift

    Every lift has to be pre-planned.

    2 1 LOW

    9 Scaffolding &Ladders

    Collapse of scaffold

    Fall from height

    Falling from ladders

    Falling objects

    Crane associated

    hazards

    Splinters, protruding

    nails, sharp edges

    Unsafe positioning of

    Rigger

    Operator

    Labor

    2 3 HIGH Scaffold must be erected by competent person/

    under competent supervision.

    All crane lifts to be controlled by a competent and

    authorize signaler /Banks man.

    This risk assessment must be communicated to

    the workers on site.

    An effective access/egress design is to be

    followed

    All platforms are to be fully boarded and hand

    2 2 MED

  • 8/13/2019 PDOC-53-2013-RA-04

    7/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 7 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 7 of 11

    ladders railed

    No board is to be unrestrained at its ends.

    Toe boards are to be installed on all used platform

    levels.

    Tool-retainers (boxes and buckets) to be used to

    reduce the risk of tools falling form scaffold.

    All workers in elevated positions are to wear a

    safety harness.

    Secure the ladders/ stairs properly.

    Minimize number of people in the area.

    A suitable qualified supervisor or deputy should

    be present during the erection of the scaffolds.

    Stairs should have regular landings where

    workers can rest effectively.

    Regular cleaning will be done to minimize trip

    hazards and the buildup of surplus materials on

    platforms

    10 Hot WorkOperation

    Fire and explosion

    Metal spatter

    Prolonged exposureto heat

    Gases & fumes

    Improper welding

    equipments

    Welder

    Helper

    2 3 HIGH A competent fire watch with suitable fire

    extinguishers must be Improper welding equipments

    present at hot work areaWhere possible all flammable material should be

    removed from the welding operations area.

    Only competent and authorized personnel to use

    equipment (i.e. welders, cutter/burners).

    1 1 LOW

  • 8/13/2019 PDOC-53-2013-RA-04

    8/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 8 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 8 of 11

    Free standing/without

    protection cap for Gas

    Bottles

    Incorrect PPE

    Appropriate PPE to be used when carrying out hot

    works operations

    Equipment to be well maintained and inspected

    as per Manufacturers recommendations.

    All oxy/Acetylene cutting sets must be provided

    with flash back arresters.

    Cylinders must be stored, handled and

    transported in a safe manner.

    Effective fume control equipment should be

    provided when working in confined area. (in need)

    Extra ventilation should be introduced to reduce

    the likelihood of heat stress occurrence. (in need)

    The placing of a second person on stand-by in

    case of emergency should be considered.

    Prolonged welding operations to be shielded from

    the sightline of adjacent operatives to reduce the risk

    of 'arc-eve'.

    11 Work at height Fall person

    Absence edge

    protectionTrips

    Falling object from up

    Improper Accesses

    Labor

    Staff

    2 3 HIGH Provide guardrail all the un-protected edges

    Close the open wholes property

    Arrange barricading and warning signs whereverneeded.

    Must wear full body harness and latch the

    lanyard.

    Work area very clear

    1 2 MED

  • 8/13/2019 PDOC-53-2013-RA-04

    9/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 9 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 9 of 11

    Make sure nobody can have work in the up

    Before using any access make inspection it is

    safe Secured your tools by wire rope

    12 Office Activities(Temp Cabins)

    Fire

    Poor House keeping

    Slip, trip and falls

    Poor posture

    Improper use of work

    station

    Over loading of

    electric sockets

    Trailing cables on

    walk ways

    Office Staffs 2 3 HIGH Good housekeeping habit must be enforced

    Control smoking in temporary cabins

    Ensure firefighting procedure

    Provide emergency access and keep them clear

    always.

    Train employees on manual handling and

    ergonomics where applicable.

    Use conduits for electrical cords.

    Use right kitchen wares and equipments

    Prepare emergency evacuation plan and taught

    to office staffs

    Assign trained fire warden for all areas.

    1 1 LOW

  • 8/13/2019 PDOC-53-2013-RA-04

    10/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 10 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 10 of 11

    1. Risk assessment to be made available and approved by the Owner of the project2. Method Statement to be made available and approved by the Owner of the project3. Ensure that all manpower safety inducted and know the Emergency numbers (Fire = 198 | Medical 190)

  • 8/13/2019 PDOC-53-2013-RA-04

    11/11

    HALWANI COMPANY Ltd

    AUTHOR: AKRAM FERCHICHI

    DOC.: RISK ASSESSMENT

    PROJECT: LOADING / OFFLOADING STATIONS

    Job No : 53-2013

    PDOC-53/2013-RA-04

    Rev. : 00

    Sheet : 11 of 11

    F = Frequency S = Severity R = Rating (FxS) = High (6 & 9), Medium (3 & 4), and Low (1 & 2)

    Rev. : 00 Sheet : 11 of 11