PDC / Architects, Engineers & General Contractors Forum May 8, 2018 3:00pm – 5:00pm AGENDA Start Topic Lead 3:00 Welcome / Overview Robin Burr 3:15 General & Campus Updates Ken Nye 3:30 Changes in Practice and Expectations Gary Giglio Bryan Romney Colin Moore Michael Beck 3:50 Projects Project Metrics Upcoming Projects o Infrastructure & Energy Team o Main Campus & Research Park Team o Health Sciences Team Robin Burr Bob Simonton & Team Liz Blackner & Team Nils Eddy & Team 4:15 Q & A All 5:00 Close

Upload: others

Post on 30-Sep-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

PDC / Architects, Engineers & General Contractors Forum May 8, 2018 3:00pm – 5:00pm

AGENDA Start Topic

Lead

3:00

Welcome / Overview

Robin Burr

3:15

General & Campus Updates

Ken Nye

3:30

Changes in Practice and Expectations

Gary Giglio Bryan Romney Colin Moore Michael Beck

3:50

Projects

• Project Metrics

• Upcoming Projects

o Infrastructure & Energy Team

o Main Campus & Research Park Team

o Health Sciences Team

Robin Burr Bob Simonton & Team

Liz Blackner & Team

Nils Eddy & Team

4:15

Q & A

All

5:00

Close

Page 2: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

PLANNING, DESIGN & CONSTRUCTION DEPARTMENT

The University of Utah Planning, Design & Construction is transitioning its online bidding service to BidSync.

• Bids will be posted on BidSync beginning on May 8, 2018.

• Vendors may register at www.bidsync.com.

• It is free to access and bid on our projects on BidSync.

• Bid notifications will be made on SciQuest until July, 2018. However, bids will not be accepted on SciQuest.

• If you currently have an account on BidSync make sure your firm contacts

are up to date so you receive bid invitations.

• For questions regarding how to set up an account or regarding current bid postings feel free to contact BidSync at 1-800-990-9339 or email [email protected]

• Check BidSync regularly for new bids.

• The University Hospital is currently using BidSync.

• University Purchasing is slated to start using BidSync in July, 2018.

Transition to BidSync

Page 3: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

Requirements for Code Reviews During Construction March 5, 2018

Office of the Building Official

Bryan M Romney – Building Official V. Randall Turpin University Services Building 1795 E. South Campus Drive, Room 211 Salt Lake City, Utah 84112-9404 Phone: (801) 581-5953 / (801) 581-6081 Fax / [email protected]

The University of Utah as a State of Utah Agency is required to comply with the adopted Construction and Fire Codes listed in Title 15A of the Utah Code. In accordance with the International Building Code, the building official is to review and approve the construction documents and issue a permit (2015 IBC Section 107.3). Once the construction documents are stamped by the building official as “Reviewed for Code Compliance” and the permit is issued, construction may commence and will be inspected as requested by the permit holder to ascertain compliance with the provisions of the code (2015 IBC Section 110.1). During the course of construction, various changes to the scope of work typically occur. These changes include Addenda, Request for Information (RFI), Architect Supplemental Instructions (ASI), Construction Change Directives (CCD), Requests for Proposal (RFP), Change Orders (CO), Revised Drawings (RD) and marked-up shop drawings (MSD). Additionally, as a condition listed on the approved set of construction documents, deferred submittals are required to be reviewed by the building official. All these changes are to be handled in a very specific manner because of the potential that the changes may have certain code compliance requirements. The code stipulates that any change to the code approved set of construction documents are to resubmitted to the building official for review and approval (2015 IBC Section 107.4). However, it would seem unreasonable to require every change to a project during construction be approved by the building official. Some changes are not significant nor do they materially alter the approved construction documents. Provided the changes do not materially alter compliance with the code, resubmittal to the building official would not be required. For the purposes of this Code Instruction, Materially Alter is defined as any change, alteration or modification to the code approved construction documents, as determined by the building official, in accordance with Chart 1, or that causes the project to be in noncompliance with the adopted codes of Utah, or causes an unreasonable risk to the health, safety, and welfare of the building occupants and public. In accordance with the requirements of the code, once the Registered Design Professional in Responsible Charge (RDPRC) has determined that a material alteration to the code approved documents is anticipated, an amended set of construction documents shall be resubmitted to the building official for approval. The changes are not to be installed until approval is given by the building official (2015 IBC 107.4). The following outlines the procedure for resubmittal of an amended set of construction documents:

The RDPRC shall submit the specific changed PDF documents sealed and signed by the appropriate design professional as a “Code Review” task in Unifier.

Once reviewed and approved, the building official will stamp the documents as “Reviewed for Code Compliance” or acknowledge code compliance.

Page 4: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

Requirements for Code Reviews During Construction March 5, 2018

P a g e 2 | 3

Approved documents will be returned to the RDPRC for distribution. Chart 1 identifies various changes to projects during construction which require resubmittal documentation for code review and approval by the building official. Chart 1 is not representative of every possible change which could occur. Chart 1 should be considered as a basic guideline for the (RDPRC), contractors and project managers to determine resubmittal requirements.

CHART 1 Changes during Construction - Requirements for Code Compliance Resubmittal

Item

Nu

mb

er

Change Item

Resu

bm

itta

l

Req

uir

ed

Resu

bm

itta

l

No

t

Req

uir

ed

1. All Deferred Submittals X 2. All changes which require structural engineering calculations X 3. Clarifications or interpretations by RDPRC X 4. Construction means and methods by contractor X 5. Temporary power connections, temporary air handlers, temporary

bulk oxygen tanks, temporary shoring supporting an existing building, temporary exiting from an existing building

X

6. RFI’s, ASI’s and Substitutions for equipment, products, materials which have not been part of the code approved construction documents

X

7. New details adding clarification to already code approved construction documents. RDPRC to document justification for nonmaterial change.

X

8. Final routing configurations of ducts, conduits, pipes, etc. where shown diagrammatically on the code approved construction documents, provided the routing has no code requirements such as seismic bracing, penetrations of smoke or fire rated assemblies, or other modifications which affect code compliance.

X

9. Dimensional changes to rooms or other building components that do not include changes to structural components, fire or smoke rated assemblies, or minimum room requirements of the codes

X

10. Relocation of doors, windows, electrical switches and receptacles, plumbing fixtures, etc. which do not trigger code required minimum dimensions or opening fire resistance rating requirements

X

11. Relocation or reconfiguration of casework, shelving or other fixed furnishings & equipment which use approved anchorage details and do not trigger code required minimum dimensions for access or structural loading

X

Page 5: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

Requirements for Code Reviews During Construction March 5, 2018

P a g e 3 | 3

12. Door hardware changes which require electromagnetic locking or egress controlled systems

X

13. All changes to fire or smoke resistance rated assemblies which involve openings or penetrations not shown on the code approved construction documents

X

14. Modifications to site grading, curbs, parking or sidewalks which affect accessibility, emergency access, or building occupant exit discharge requirements

X

15. Changes to the fire water main lines X

16. ASI’s which clarify missing or conflicting information on the code approved construction documents which do not cause a change to the design intent or code violation

X

17. Changes to clearance requirements between new and existing site utility lines, such as modifications to inverts that reduce slope of drain below minimum requirements.

X

18. Trenching immediately adjacent to structural footings X 19. ASI’s clarifying finish materials that do not conflict with IBC

requirements X

20. Deletion of any smoke/fire dampers X 21. Reclassification of horizontal or wall assemblies which affect the fire

resistance ratings X

22. Changes to the fire sprinkler system which affect the hydraulic calculations

X

23. Changes to the air balance or air flow of any building space which result in a non-compliant condition.

X

24. Relocation of supply or return or exhaust registers which do not create a non-compliant condition

X

25. Changes to temporary fire-resistance rated partitions X 26. All changes to the code approved construction documents which

affect compliance with IBC Chapter 11 requirements X

27. Relocating electrical receptacles and switches which do not create a noncompliant NEC requirement

X

28. Changes to equipment which do not change design intent to the code approved construction documents

X

29. Changes to electrical equipment or drawings resulting in a noncompliant code condition

X

30. Modifications to proprietary or manufactured items which do not create a non-compliant condition.

X

31. Relocating or deleting electrical receptacles and switches which do not create a non-compliant condition

X

Page 6: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

Owner, Architect, Contractor (OAC) Meeting Agenda & Constraint Log

05-02-2018

The intent and purpose of an OAC meeting varies dramatically from project to project, even within the same organization. In order to standardize, set expectations and develop a higher level of transparency for our internal teams, clients and industry partners, the following provide direction on how to conduct an OAC meeting. As it pertains to the management of U of U projects, the purpose of the weekly OAC meeting is as follows:

1. To inform the discussion around the schedule critical path, to identify constraints to achieving the schedule critical path and tracking individual commitments to removing constraints so that schedule dates are maintained.

2. With few exceptions, all topics of discussion in an OAC tie to a schedule activity, and it is rigor around maintaining the critical path schedule that the OAC should focus.

3. A Constraint Log will be used to manage issues that have the potential to impact schedule. Typical issues include RFI’s, Submittals, Procurement/Long lead items (60-90 days out), fabrication, delivery of materials and equipment, Coordination, design direction, PCO/CO’s, Owner decision deadlines, etc….all issues generated from these sources and others will be managed using a Constraint Log.

4. OAC meetings are not the place to point blame, revisit the history of a particular issue or to generate solutions by committee. It is to identify the potential constraint, who will resolve it and when the resolution will be provided.

5. Typical project lists should be used as they too have a role in the oversight of a project and tie to Unifier. Lists however, are not the tool to by which to manage, but a constraint log is because it joins important information into a single format.

6. Other topics of discussion that also need to be a part of an OAC, but not necessarily in a constraint log can include safety; GC and subcontractor Quality Control; AHJ Quality Assurance (including deficiency notices and inspections), PACE plans, client concerns, etc.

7. Finally, each project team needs to determine what works best for them, so if there is a new innovation or approach to managing the OAC, it is encouraged and should be explored.

8. OAC meeting minutes are to be uploaded into Unifier within 72 hours of the meeting conclusion. It is the expectation of the University that everyone that attends the meeting will review the meeting minutes and respond with comment or indicate no exception taken within 72 hours.

Page 7: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

OAC Meeting Agenda – Part A, U of U Mandated Discussion Topics

1. Critical Path Schedule Review

a. Review CP (incl. CP’s for interim completion dates and milestones) and all activities within 14 (this timeline can be adjusted to suit team needs) days of CP

b. Review 3 week (or whatever is agreed upon by the Owner’s Representative) rolling schedule (4.7.9 Updates)

i. Review long lead items c. Review Schedule of Submittals (4.7.10) d. Schedule Recovery (4.7.11) e. Review Contract Time Extension Requests (4.7.12(1)) f. Review Re-ordering, Resequencing and Changing Activity Durations (4.7.12(2)) g. Review Changes in Contract Time (4.7.12(3))

2. Constraint Log – All items potentially impacting the Critical Path 3. Coordination Log – Everything else

Part B, Possible Discussion Topics (team/project determinant)

4. Submittal List – Shop Drawings, Product Data/Samples, Substitution Requests 5. RFI List 6. Procurement/Long Lead Items 7. Anticipated Scope Changes – ASI’s, Owner requests, etc…. 8. PR’s/CO’s 9. Applications for Payment 10. Leed/Sustainability/Energy 11. Weatherization 12. Site Logistics/SWPPP 13. Owner Commissioning 14. BIM 15. Transition to Sustainable Operations 16. Owner Departments – UIT/Space Planning/Start-up; Services/ClinTech 17. Cash Flow 18. Quality Control 19. Quality Assurance/Inspections 20. PACE Plans

Page 8: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

5/9/2018

#Critical

Path Item?Pull From Start Date

or End DateSchedule

IDImpacted Activity

Submittal/RFI PR/CCD/ASI

NumberImpacted Area Scope Owner

Design Team (A/E)

GC Ball in Court Notification Date

Schedule Start Date

Schedule End Date

Commitment Date

Commitment/Schedule Date Variance

Days to Critical

Total FloatBall in Court

Start DateStatus Date Closed Action Items/Comments

Open Issues 0 Green = 21-30Closed Issues 0 Yellow = 6-20Total Issues 0 Red = 5 and under

Initial Name Company

CONSTRAINT LOG

RESPONSIBLE PARTY

Who is currently responsible?

Page 9: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

Project # Project Name Project Budget Project ManagerA/E

Selected?Contractor Selected?

Infrastructure Team22018 Sidewalk Improvements Mario Capecchi Dr. 1,300,000$ Astrid Paredes Y N22147 Wasatch Drive Area Road Rebuild 3,500,000$ Astrid Paredes Y N22179 New Parking Lot by Eccles Broadcast 2,700,000$ Astrid Paredes Y N22177 Storm Water Retention - Drainage Systems 1,892,000$ Astrid Paredes Y N22058 Secondary Water System of Landscape Irrigation 2,000,000$ Brett Petersen Y N22039 Red Butte Garden Parking Lot Expansion 450,000$ Brett Petersen Y N22040 Red Butte Garden Service Road 370,000$ Brett Petersen Y N22174 Chilled Water Distribution to Marriott Library & Social Work 1,400,000$ Jon Jefferson Y N22115 E Village 1400 Ct Culinary Water Main Isolation Valves 90,000$ Jon Jefferson Y IP22110 MEB Parking 2.5 MW Solar Canopy TBD Scott Jefferson N N22009 Fine Arts West Electrical Service Replacement 375,000$ Scott Jefferson Y N22017 Emergency Generators and Life Safety Transfer Switches 2,200,000$ Scott Jefferson Y N22145 Bldg. 533, EIHG - Emergency Generator Replacement 1,300,000$ Scott Jefferson Y N

TBD Biology Fumehood & HVAC Upgrade - Design Only 250,000$ Steve Laraway N NTBD HTW Plant Seismic Upgrade - Equipment Bracing 1,493,700$ Steve Laraway N N

21675 HTW Plant Replace Boiler #3 4,012,000$ Steve Laraway Y IP21910 South Biology Lab Space 1,650,000$ Steve Laraway Y N21945 HTW Boiler 3 Demo & Seismic Bracing 1,900,000$ Steve Laraway Y N22005 Merrill Engineering Remove HVAC from Roof 2,700,000$ Steve Laraway Y N21916 Eyring Chemistry South Tower East Fumehood Upgrade 1,870,000$ Steve Laraway Y N21910 Biology - Create Lab in Room 201 1,650,000$ Steve Laraway Y N

Main Campus and Research Park Team22114 Life Sciences Building 3,500,000$ Andrea Cavrag N N22181 North Chemistry Building Reroof 2,600,000$ Andrea Cavrag Y N22072 Chemistry Building 4th Floor West Lab Rebuild 3,500,000$ Andrea Cavrag Y N22143 Chemistry 3rd Floor East Lab Rebuild 3,400,000$ Andrea Cavrag Y N

TBD Merrill Engineering Bldg. Curtain Wall Replacement 3,500,000$ Andrew Heiner N N22194 Student Services Bldg. Room 15 Remodel 154,000$ Andrew Heiner Y N22127 Eye Wash Stations 850,000$ Andrew Heiner Y N22146 NHMU South Terrace Shade Structure 179,000$ Christin Robbins N N22148 NHMU Canyon Acoustical Enhancements 150,000$ Christin Robbins N N22190 Dermatology Lab & Office Remodel 525,000$ Christin Robbins Y N

TBD Film & Media Arts Upgrade TBD Desslie Andreason N N22198 Rice Eccles Stadium Concession Hoods 350,000$ Desslie Andreason N N22116 Huntsman Center Improvements 375,000$ Desslie Andreason Y N22162 CRCC Business Cafe Remodel 200,000$ Desslie Andreason Y N22085 Women's Soccer & Men's Lacrosse Stadium 4,500,000$ Mark Grabl IP IP22199 Bldg. 73 HVAC, Elevator, Fire Protection & Remodel 4,000,000$ Mark Grabl N N

Health Sciences Team22200 Wintrobe Bldg. Rooms 327 & 327a Remodel 132,000$ Harry Corsi N N22195 Huntsman Cancer Hospital Proton Therapy Building 8,000,000$ Harry Corsi IP N

TBD Hospital NBICU Family Space 2,620,000$ Harry Corsi N NTBD Huntsman Cancer Hospital Pre-Clinical/Biomedical Research 1,500,000$ Harry Corsi N N

21502 U Health Interventional Radiology Addition 14,000,000$ Harry Corsi Y N22193 U-Health Interior Wayfinding 3,000,000$ Krin Kirijas Y N21977 Williams Building 4th Floor Tenant Improvement TBD Krin Kirijas N N22172 BRPB Lab Remodel TBD Krin Kirijas N N22074 Orthopaedics Center Research Addition 2,900,000$ Mike Wessman N N21504 School of Medicine Abatement and Demolition 12,000,000$ Mike Wessman Y N

TBD Hospital Clinics 1, 2 & 3 Remodel TBD Nils Eddy N NTBD Hospital Emergency Dept. Expansion 4,785,000$ Nils Eddy N NTBD Madsen Clinic Level 3 Remodel - Family Space 3,124,000$ Nils Eddy N N

21589 Medical Education & Discovery (MED) 185,000,000$ Nils Eddy Y N22139 U Health Redwood Clinic HVAC Upgrade 3,000,000$ Rick Johansen Y N

Planning TeamResearch Park Master Plan TBD TBD N N/AIntermodal Transit Hub Study TBD TBD N N/A

IP = In Process

The University of UtahPlanning, Design & Construction

Projects Needing A/E and/or ContractorMay 8, 2018

Page 10: PDC / Architects, Engineers & General Contractors Forum · PDC / Architects, Engineers & General Contractors Forum . May 8, 2018 . 3:00pm – 5:00pm . AGENDA . Start Topic Lead 3:00

Robin BurrCDCO

Ken NyeDeputy CDCO

TEAM. LEADERSHIP

Updated: May 3, 2018

Contracts

Heather HendersonContracts

Administrator

Polly AllesContracts Assistant

Unifier

Jeff RecordSr. Bus Analyst

John NaylorSr. Bus data

Analyst

Shared Services

UIT, GIS, Land Surveying,

CAD / Revit, Sharepoint

BusinessSupport

Infrastructure, Energy, Red Butte

Gardens

Harry CorsiPM

Nils EddyProgram Manager

OPENPM

Mike Wessman

PM

Krin KirijasPM

General Health

Sciences

OPEN Assoc. Project

Manager

Rick Johansen

PM

Sherri Somers

Project Ass’t

Shireen GhorbaniAssoc. Director,Public Relations Communications

CommunicationsOrganizational Development

Abeni Czajkowski

CommSpecialist

Mary Ellen Allen

Prog. Mgr.

Robin BurrInterim Director

Campus Planning

Tami WolfgangPlanner

Andrew King Sr. Planner

Charles ShepherdPlanner

Campus Planning

Blaine OsborneExecutive Assistant

AdministrativeSupport

Shannon Failner

Admin Ass’t

Michelle KeddingtonAdmin Ass’t

Randi PorterReception

Gary GiglioDirector

Design & ConstSupport

Floyd CorbinFinancial Analyst

Jeff KuehndahlFinancial Analyst

Nana Amoah Ewusi-

Emmim Fin. Analyst

Brenda DiazFinancial Analyst

Bob SimontonDirectorDesign &

Construction

Christian Johansen

Project Ass’t

Astrid Paredes

PM

Jon JeffersonPM

Brett Petersen

PM

Scott Jefferson

PM

Liz BlacknerDirectorDesign &

Construction

Mark GrablPM

Andrea Cavrag

PM

Christin Robbins

PM

Andrew Heiner

PM

DesslieAndreason

PM

Main CampusResearch Park

Lori KazcKaPM

Carley Bradbury

Project Ass’t

Rochelle RandazzoDirectorProject

Finance/Acctng

Shivali KhopkarAccountant

Project Fin/Acct’gSupport

Mary DupaixFin Support

Steve Laraway

PM

Transformation

Bryan RomneyBuilding Official

Design & Construction

Support

Michael BeckQC / Safety

Mgr.

Colin Moore Cost Engineer

Sam AugustineEnergy/

Sustainability Manager