pca case no. 2016-39/aa641 glencore finance (bermuda) …pca case no. 2016-39/aa641 glencore finance...

279
PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) VS The Plurinational State of Bolivia (Respondent) BOLIVIA’S PRELIMINARY OBJECTIONS, STATEMENT OF DEFENCE, AND REPLY ON BIFURCATION 18 December 2017 Members of the Tribunal: Prof. Ricardo Ramírez Hernández Prof. John Y. Gotanda Prof. Philippe Sands 32 rue de Monceau 75008 Paris, France

Upload: others

Post on 11-Jan-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

PCA Case No. 2016-39/AA641

Glencore Finance (Bermuda) Ltd.

(Claimant)

– VS –

The Plurinational State of Bolivia

(Respondent)

BOLIVIA’S PRELIMINARY OBJECTIONS, STATEMENT OF

DEFENCE, AND REPLY ON BIFURCATION

18 December 2017

Members of the Tribunal:

Prof. Ricardo Ramírez Hernández

Prof. John Y. Gotanda

Prof. Philippe Sands

32 rue de Monceau

75008 Paris, France

Page 2: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

TABLE OF CONTENTS

Page

-i-

BOLIVIA’S PRELIMINARY OBJECTIONS, STATEMENT OF DEFENCE, AND

REPLY ON BIFURCATION..................................................................................................I

1. INTRODUCTION .................................................................................................................... 2

2. GLENCORE INTERNATIONAL’S IRREGULAR ACQUISITION OF THE

ASSETS AND THE UNSUSTAINABLE VIOLENCE IN THE REGION OF

COLQUIRI FORCED BOLIVIA TO REVERT THE ASSETS .............................................. 5

2.1 Prior To The Privatization, Bolivia Successfully Operated The Assets Through

COMIBOL And Its Affiliates ...................................................................................... 7

2.1.1 During The Time COMIBOL Operated The Colquiri Mine, The State Maintained

Good Relations With The Independent Mining Workers Of The Region ............ 7

2.1.2 During The 1970-1990s, Bolivia Made Important Investments In The Smelters12

2.2 Between 1994 And 1997, While Former President Sánchez de Lozada Was In Office,

Bolivia Sought To Privatize The Smelters And The Colquiri Mine .......................... 15

2.3 Taking Advantage Of Policies Put In Place While In Office, Sánchez De Lozada

Acquired The Colquiri Mine Lease And The Antimony Smelter .............................. 18

2.3.1 Sánchez De Lozada, Through Comsur, Bid For And Acquired The Colquiri Mine

Lease In 1999-2000 ............................................................................................ 18

2.3.2 Sánchez De Lozada, Through Comsur, Bid For And Acquired The Antimony

Smelter In 2000-2001 ......................................................................................... 20

2.4 The Tin Smelter Was Acquired By Allied Deals In Highly Irregular Circumstances

And Subsequently Transferred To Sánchez De Lozada ............................................. 23

2.4.1 Allied Deals Acquired The Tin Smelter In Highly Irregular Circumstances ..... 23

2.4.2 The Bankruptcy And Fraud Scandal Involving Allied Deals In 2002 Set The

Stage For The Acquisition Of The Tin Smelter By Comsur .............................. 26

2.5 In 2005, At The Height Of Political Change In Bolivia, And When The Reversion

Was Foreseeable, Glencore International Acquired The Smelters And Mine Lease

From Former President Sánchez De Lozada .............................................................. 29

2.5.1 Comsur’s Operation Of The Colquiri Mine Lease Created Tensions With The

Mining Cooperativas And The Unions At Colquiri ........................................... 30

2.5.2 The Historic Social Changes That Led To The Empowerment Of New And

Fundamental Social Actors In Bolivia Further Impacted Operations At Colquiri

............................................................................................................................ 33

2.5.3 Glencore International Purchased The Assets From Sánchez De Lozada And

Assigned Them To Glencore Bermuda Without Compensation ........................ 39

2.5.4 Glencore International Assigned The Assets To Glencore Bermuda When It Was

Highly Likely That The State Would Take Action Against The Assets ............ 44

2.5.5 Despite The Acquisition Of The Smelters And The Mine Lease, Glencore Did

Not Make Any Substantial Investment During Its Operation Of These Assets . 48

2.6 Bolivia Reverted The Assets For Public Purposes ..................................................... 49

2.6.1 Bolivia Reverted The Tin Smelter Due To The Irregularities In The Privatization

Process ................................................................................................................ 49

Page 3: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

TABLE OF CONTENTS

Page

-ii-

2.6.2 Bolivia Reverted The Antimony Smelter Due To Its Inactivity ......................... 51

2.6.3 Due To The Social Crisis Created By Sinchi Wayra At The Colquiri Mine, The

State Was Left With No Other Choice But To Revert The Mine Lease ............ 53

2.7 Bolivia Has Negotiated With Glencore International In Good Faith ......................... 77

2.8 The State Made Significant Investments After The Reversion Of The Smelters And

The Reversion Of The Mine Lease ............................................................................ 80

2.8.1 In Order To Increase Their Capacity, The State Made Large Investments At The

Tin Smelter ......................................................................................................... 80

2.8.2 The State Has Invested In The Colquiri Mine And Managed To Solve The Social

Crisis Created With The Mining Cooperatives .................................................. 81

3. THE LAW APPLICABLE TO THE DISPUTE ..................................................................... 82

4. THE CLAIMS ARE NOT SUBJECT TO JURISDICTION AND ARE

INADMISSIBLE .................................................................................................................... 84

4.1 The Tribunal Lacks Jurisdiction Because Glencore Bermuda Made No Investment In

Bolivia ........................................................................................................................ 85

4.1.1 The Treaty Extends Arbitral Jurisdiction Only To Companies Or Individuals

That Actively Invest ........................................................................................... 87

4.1.2 Glencore Bermuda Made No Investment In Bolivia, Much Less The Active

Investment Required By The Treaty .................................................................. 90

4.2 The Tribunal Lacks Jurisdiction Because Glencore Bermuda Committed An Abuse Of

Process By Receiving The Investment When The Dispute Was Foreseeable ............ 94

4.2.1 Structuring An Investment To Obtain Treaty Protection When A Dispute Is

Foreseeable Constitutes An Abuse Of Process ................................................... 95

4.2.2 Glencore International Rerouted Its Investment Through Bermuda When A

Dispute With Bolivia Was Foreseeable .............................................................. 98

4.3 The Tribunal Lacks Jurisdiction Because The Assets Subject To Dispute Were

Illegally Privatized ................................................................................................... 103

4.3.1 The Privatization Of The Assets Was Illegal Under Bolivian Law And Contrary

To International Public Policy .......................................................................... 103

4.3.2 Claimant Brings Its Claims With Unclean Hands Because The Privatizations

Were Illegal ...................................................................................................... 106

4.4 The Tribunal Lacks Jurisdiction Because The Claimant Is, In Reality, A Swiss

Company Not Subject To Treaty Protection Or, Alternatively, Because It Cannot

Bring Claims Based On Indirectly Held Rights ....................................................... 109

4.4.1 The Treaty Excludes Jurisdiction Asserted On The Basis Of Corporate

Formalities When The Real Party In Interest Is Not Protected ........................ 110

4.4.2 The Corporate Veil Must Be Pierced Because Glencore Bermuda Is An Empty

Shell Hiding The True Party In Interest ........................................................... 112

4.4.3 Even If (Quod Non) The Corporate Veil Protects Glencore Bermuda,

International Law Does Not Allow It To Bring Claims For Its Indirect

Investment ........................................................................................................ 114

Page 4: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

TABLE OF CONTENTS

Page

-iii-

4.5 The Tribunal Lacks Jurisdiction Because The Dispute Concerns Contracts With

Mandatory ICC Arbitration Clauses And Diplomatic Claims Exclusions ............... 117

4.5.1 An Investment Arbitral Tribunal Has No Jurisdiction Over Contract Claims

Recast As Treaty Breaches When The Contracts Provide For An Alternative

Forum ............................................................................................................... 119

4.5.2 Claimant’s Claims Concern Obligations Under The Smelter Privatization

Contracts And The Colquiri Lease ................................................................... 120

4.6 The Tribunal Lacks Jurisdiction Over The Tin Stock Claims Because They Were

Never Notified To Bolivia ........................................................................................ 122

5. BOLIVIA’S REQUEST FOR BIFURCATION SHOULD BE GRANTED ........................ 125

5.1 Granting Bifurcation Prevents States From Having To Defend Themselves When

There Is No Jurisdiction And Ensures Efficient Resolution Of Disputes ................ 126

5.2 Bolivia’s Objections Comply With All The Requirements For An Order On

Bifurcation ................................................................................................................ 129

6. BOLIVIA’S CONDUCT WAS CONSISTENT WITH THE TREATY AND

INTERNATIONAL LAW .................................................................................................... 131

6.1 Bolivia Did Not Expropriate The Assets But Instead Exercised Its Rights Under

Bolivian Law And Under The Police Powers Doctrine ........................................... 132

6.1.1 Bolivia Carried Out A Legitimate Exercise Of Its Police Powers To Enforce The

Law And To Maintain Public Safety ................................................................ 133

6.1.2 If The Reversions Were Expropriations (Quod Non), They Were Lawful ....... 143

6.2 Bolivia Provided Full Protection And Security To The Assets At All Times .......... 154

6.2.1 Full Protection And Security Requires Only Lawful And Reasonable Measures

In Response To A Threat Of Permanent Physical Impairment ........................ 154

6.2.2 Bolivia Took All Actions That Were Reasonably Available In Light Of The

Severe Social Conflict And Limitations From Human Rights Law ................. 158

6.2.3 The Colquiri Mine Lease Contract Adds Nothing To The Full Protection And

Security Standard .............................................................................................. 164

6.3 Although Claimant’s Fair And Equitable Treatment Allegations Are Redundant,

Bolivia Provided Fair And Equitable Treatment To The Assets At All Times ........ 165

6.3.1 Bolivia Satisfied Glencore Bermuda’s Legitimate Expectations At All Times 166

6.3.2 Bolivia Acted Transparently, Predictably, And With Respect For Due Process

.......................................................................................................................... 171

6.3.3 Bolivia Acted In Good Faith When Intervening At The Colquiri Mine And When

Issuing The Reversion ...................................................................................... 175

6.3.4 Claimant’s Allegation Of Administrative Negligence And Inconsistency Is

Legally And Factually Vacuous ....................................................................... 177

7. IF THE TRIBUNAL WERE TO CONSIDER THAT IT HAS JURISDICTION

OVER THIS DISPUTE AND THAT BOLIVIA BREACHED THE TREATY

(QUOD NON), IT SHOULD, NONETHELESS, FIND THAT CLAIMANT’S

CLAIMED DAMAGES ARE HIGHLY SPECULATIVE AND UNCERTAIN AND

THAT, IN ANY EVENT, ITS VALUATIONS ARE HYPOTHETICAL AND

FLAWED .............................................................................................................................. 178

Page 5: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

TABLE OF CONTENTS

Page

-iv-

7.1 Claimant’s Valuations Are So Speculative That Claimant Has Failed To Establish

Any Damage Sufficiently Certain To Warrant Compensation Under International Law

.................................................................................................................................. 180

7.1.1 Under International Law, It Is Claimant’s Burden To Prove Its Damages With

Certainty ........................................................................................................... 180

7.1.2 Through Its Highly Speculative And Unrealistic Valuation, Claimant Has Not

Proven Its Damages Claims With Certainty ..................................................... 184

7.2 Even If The Damages Claimed For The Mine Lease Reversion Were Certain (Quod

Non), They Were Not Caused By Bolivia But Rather By Claimant’s Own Acts .... 198

7.3 Even If The Damages Claimed Were Certain (Quod Non), Claimant’s Valuations Are

Flawed And Grossly Inflated ................................................................................... 202

7.3.1 The Plain Terms Of The Treaty Establish The Applicable Principles Of

Compensation ................................................................................................... 203

7.3.2 Claimant Adopts Incorrect Valuation Dates For The Mine Lease And The

Antimony Smelter ............................................................................................ 206

7.3.3 Compass Lexecon’s Valuations Ignore Key Premises For The Valuation Of

Mining Assets ................................................................................................... 212

7.3.4 Compass Lexecon’s Valuation Of Colquiri Is Flawed As It Is Based On

Unrealistic And Incorrect Assumptions Concerning Key Value Drivers ......... 223

7.3.5 Compass Lexecon’s Valuation Of The Tin Smelter Is Flawed As It Is Based On

Unrealistic And Incorrect Assumptions ........................................................... 240

7.3.6 Compass Lexecon’s Estimate Of The FMV Of The Antimony Smelter Is

Incorrect Because It Is Based On A Valuation (Performed By Ms Russo) Which

Is Methodologically Flawed And Disregards Key Variables That Make This

Asset Valueless ................................................................................................. 250

7.3.7 Compass Lexecon’s Valuation Of The Tin Stock ............................................ 258

7.4 Claimant’s Claim For Interest Is Grossly Inflated ................................................... 259

7.4.1 Were The Tribunal To Award Interest To Claimant (Quod Non), It Should Apply

A Risk-Free Interest Rate To Avoid Overcompensation .................................. 260

7.4.2 Claimant Can, At Most, Claim Simple Interest ................................................ 265

7.5 Any Damages Awarded To Claimant For Colquiri And The Tin Smelter (Quod Non)

Must Be Significantly Reduced To Reflect Claimant’s Contribution To Its Own

Losses ....................................................................................................................... 268

7.5.1 As A Matter Of Law, Compensation Shall Be Significantly Reduced Where The

Alleged Victim Contributed To Its Own Losses .............................................. 268

7.5.2 As A Matter Of Fact, Claimant’s Behavior Materially Contributed To Its Alleged

Losses In Relation To Colquiri And The Tin Smelter ...................................... 270

8. PRAYER FOR RELIEF ....................................................................................................... 272

8.1 On The Forthcoming Procedural Steps .................................................................... 272

8.2 On Jurisdiction And Admissibility ........................................................................... 272

8.3 On The Merits .......................................................................................................... 273

Page 6: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

1

1. Pursuant to the Procedural Calendar adopted by the Tribunal in Procedural Order No. 1, the

Plurinational State of Bolivia (“Bolivia” or the “State”) hereby submits its Preliminary

Objections, Statement of Defence, And Reply On Bifurcation (the “Statement of Defence”)

in response to the Statement of Claim of Glencore Finance (Bermuda) Ltd. (“Claimant” or

“Glencore Bermuda”) (Claimant and Respondent are jointly referred to herein as the

“Parties”) filed on 15 August 2017 (the “Statement of Claim”).

2. Bolivia submits together with its Statement of Defence:

a. Factual exhibits R-16 to R-268, together with a consolidated list of factual exhibits;

b. Legal authorities RLA-1 to RLA-130, together with a list of legal authorities;

c. The witness statement of Mr Carlos Romero Bonifaz, Minister of Government of

Bolivia (“Romero”);

d. The witness statement of Mr Andrés Cachi, former cooperativista and current

employee at the State’s Empresa Minera Colquiri (“Cachi”);

e. The witness statement of Mr Joaquín Mamani, worker at the Colquiri Mine at the time

it was controlled by Sinchi Wayra (Glencore International AG’s subsidiary in Bolivia)

and one of the leaders of the Sindicato Mixto de Trabajadores Mineros de

Colquiri (“Mamani”);

f. The witness statement of Eng Ramiro Villavicencio Niño de Guzmán, former employee

at Sinchi Wayra and current general manager of the State company Empresa

Metalúrgica Vinto (“Villavicencio”);

g. The witness statement of Eng David Alejandro Moreira, former employee at Sinchi

Wayra and current general manager at the State company Empresa Minera Colquiri

(“Moreira”);

h. The expert report of Mr Diego Mirones. Mr Mirones holds a Degree in Architecture

from the Facultad de Arquitectura, Universidad de San Andrés, in Bolivia, and has

over 30 years of experience as a real estate appraiser in Oruro (“Mirones”);

i. The expert report of Prof Neil Rigby, Bolivia’s mining expert in this arbitration. Prof

Rigby is a PhD from the University of Wales and also a founding partner of SRK (UK),

a leading international consulting firm that provides advice in the mining and metals

industry (“SRK”); and

Page 7: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

2

j. The expert report of Dr Daniel Flores, Bolivia’s valuation expert in this arbitration. Dr

Flores is a PhD in Economics from Boston University and a managing partner at Econ

One Research (“Econ One”).

1. INTRODUCTION

3. An utterly opportunistic claim. Claimant attempts to use this investment arbitration as an

unmerited insurance policy against its own poor judgment and mismanagement. It asks this

Tribunal to ignore the facts that (i) Claimant brings an investment arbitration without having

invested a single dime in Bolivia; (ii) it received transfer of its Bolivian assets when fully

cognizant that great controversy permeated those assets; (iii) its mismanagement of its so-

called investment led directly to the reversions of which it complains in this arbitration; and

(iv) it now seeks some US$ 447.9 million (plus interest) in compensation even though it

valued the Bolivian assets at no more than US$ 10 million when it obtained them in 2005.

4. A blatant abuse of the international system for the protection of investments. It was not

Glencore Bermuda, the nominal Claimant, but its parent company, Glencore International AG

(“Glencore International”), that invested in Bolivia in early 2005. Glencore International

simply assigned to Glencore Bermuda, for no compensation whatsoever, the mining assets

that are the subject of this arbitration—the Vinto tin smelter (the “Tin Smelter”), the Vinto

antimony smelter (the “Antimony Smelter”), and the Colquiri mine lease (the “Mine Lease”)

(jointly referred to as the “Assets”). Glencore International itself negotiated the acquisition,

managed the Assets, and negotiated with Bolivia when those Assets were reverted. Glencore

Bermuda had no involvement whatsoever with the Assets until Glencore International decided

to pursue an investment treaty claim against Bolivia.

5. An investment rooted in the highly irregular and openly critizised privatization. When

Glencore International made its investment in Bolivia in 2005, it was fully aware of the

controversies surrounding the Assets. It knew that it was acquiring the Assets from disgraced

former President Gonzalo Sánchez de Lozada (and has deliberately concealed the terms of

that transaction), and it knew the latter had obtained the Assets as the result of a privatization

process from 1999-2001 that remained highly controversial due to its irregularities. Glencore

International also knew that, as part of that 1999-2001 privatization process, Bolivia received

a net payment of US$ 0 for Assets that Claimant now alleges are worth US$ 447.9 million

(plus interest).

6. Chronicle of a reversion foretold. When it acquired the Assets, Glencore International knew

about the likelihood of severe social conflict at the Colquiri Mine. Following the privatization

of the Colquiri Mine, unemployed former mine workers were forced to work informally as

Page 8: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

3

independent workers, providing an essential source of mine labour. As the independent

workers began demanding more rights to work in the mine, an often uncontrollable conflict

with the formal mine workers emerged. And, after 2003, as the Movimiento al Socialismo

party gained increasing political power, with the support of informal mine workers from

across Bolivia, these tensions became still more intense and unmanagable. It was at this

moment that Glencore International entered Bolivia and acquired the Assets.

7. All flanks covered. Fully cognizant of its extremely risky investment, Glencore International

took measures that would allow it to benefit from the risk. Bolivia understands that Glencore

International took out political risk insurance for the Tin Smelter and suspects it did so for the

Antimony Smelter and Colquiri Mine Lease as well, and that it later collected on these

policies. It also transferred its Assets to a Bermudan holding company so that it could attempt

to claim investment treaty protection when the entirely foreseeable disputes arose.

8. Glencore International’s wrongdoing encouraged the cooperativistas to take over the

Colquiri Mine. Glencore International’s mismanagement of the Assets, most notably of the

Colquiri Mine Lease, directly led to their reversion. Glencore International did nothing to

quell the escalating conflict between the informal mine workers and the formal employees. It

constantly ceded to demands of the informal workers for ever greater working areas in the

Colquiri Mine, even while laying off formal workers. In early 2012, this long-brewing

conflict erupted, when the informal workers violently seized control of the mine, demanding

permanent control of the entire facility, and the formal workers equally insisted that nothing

further be given to the informal workers.

9. The Rosario Agreement (entered by Glencore International) sparked waves of violence.

Although the Government of Bolivia managed to negotiate an accord that promised to stop

the violence, Glencore International deliberately subverted these efforts. Just as Bolivia was

completing negotiations with the competing factions, Glencore International offered control

of the Rosario vein of the Colquiri Mine to one sector of independent workers. As a result,

the violence reignited and spread beyond the mine itself, to blockades on major roads and

mass protests. At this point, the only solution to re-establish public safety and order was to

remove Glencore International from the Colquiri Mine.

10. Glencore International’s wrongdoings also led to the reversion of the Smelters. Similar

blunders on the part of Glencore International led to the reversion of the Tin and Antimony

Smelters. The Antimony Smelter was reverted because Glencore International simply ignored

the plain terms of the privatization agreement requiring the Smelter be put to productive use,

which Glencore International never did during the five years it held that Asset. And the Tin

Page 9: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

4

Smelter was reverted because Glencore International purchased an Asset that had gone

through an irregular privatization process, a fact that Glencore International knew at the time

of purchase.

11. The deal of the century. Glencore International’s carelessness with the Assets was

unsurprising since it considered the Assets to be of limited economic value, except perhaps as

the basis of insurance and arbitral claims. When Glencore International purchased the Assets

in March 2005, it assumed they had a combined value of no more than US$ 10 million. This

is a far cry from the US$ 447.9 million (before interest) Claimant now seeks in this arbitration,

a figure approximately 45 times greater. Since Glencore International held the assets for only

two to seven years, it proposes it received a 72% compound annual rate of return. But, if

anything, the Assets would have lost value over time, as the Colquiri Mine Lease had a fixed

30-year term and Glencore International effectively made no investment in that or any of the

other Assets.

12. The irregular circumstances in which the Assets were privatized and Glencore International’s

wrongdoings left the State with no choice but to revert them (Section 2).

13. The Tribunal lacks jurisdiction to hear Claimant’s claims. In addition to these

irregularities, the Swiss Glencore International is abusing Claimant’s legal personality in

order to obtain the protection of the UK-Bolivia Bilateral Investment Treaty (the “Treaty”).

As a result, and on the the basis of the law applicable to this dispute (Section 3), the Tribunal

does not have jurisdiction over Claimant’s claims, which, in any event, are inadmissible

(Section 4). Because Bolivia’s objections to jurisdiction dispose of Claimant’s entire case,

the Tribunal must order the bifurcation of the proceedings and rule upon them as a preliminary

matter (Section 5).

14. Bolivia’s legitimate reaction. In the alternative, Claimant’s claims fail on the merits

(Section 6). Bolivia’s decision to revert the Assets did not breach any of its international

obligations. On the contrary, the reversion of the Assets was the logical response to (i) the

irregular privatization of the Tin Smelter, (ii) the inactivity of the Antimony Smelter over the

years, and (iii) the social conflict created at Colquiri.

15. A valuation based on unrealistic assumptions. In the further alternative, Claimant’s

valuation of the Assets is utterly flawed (Section 7). The reason for the gross mismatch

between Glencore International’s Asset valuation at the time of purchase and Claimant’s

valuation for this arbitration is clear. Claimant assumes earnings for the Assets that utterly

outstrip their actual historical performance. For the Colquiri Mine, it projects earnings that

Page 10: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

5

exceed by five times the average earnings during Glencore International’s ownership. For the

Tin Smelter, it projects earnings that exceed by three times the average earnings during

Glencore International’s ownership. Through this technique, it inflates value, seeking to

obtain in this arbitration returns it never could have received as the owner of the Assets.

16. The miraculous triennial plan. To support its unrealistic valuation for the Colquiri Mine

Lease, Glencore International relies only on a single 2011 triennial planning document that

lacks even a basic analysis of its economic viability. This lone document was never presented

to the management of Colquiri and received no internal approvals, no investment

authorizations, and no expenditure authorizations. Unsurprisingly, none of these proposal

went anywhere, even prior to the Mine Lease reversion. Even though this document bears no

relationship with any plans for the Colquiri Mine, Glencore International build its speculative

valuation solely on its feeble foundations.

17. Bolivia’s prayer for relief. For all these reasons, the Tribunal should reject Claimant’s

claims and order Claimant to reimburse the costs incurred by Bolivia in this arbitration

(Section 8).

2. GLENCORE INTERNATIONAL’S IRREGULAR ACQUISITION OF THE ASSETS

AND THE UNSUSTAINABLE VIOLENCE IN THE REGION OF COLQUIRI

FORCED BOLIVIA TO REVERT THE ASSETS

18. Claimant’s claims concern Bolivia’s decision to revert the Assets acquired by Glencore

International from Compañía Minera del Sur (“Comsur”), a company controlled by former

president of Bolivia, Gonzalo Sánchez de Lozada. The Assets consist of:

a. A world renowned Tin smelter and the Antimony Smelter located near the city of Oruro

and (jointly, the “Smelters”); and

b. The Colquiri mine, a tin mine active since the XIX century located in the Department

of La Paz (the “Mine”). The Mine operates in a very particular social context, as it is

located underground beneath the village of Colquiri.

19. In support of its claims in this arbitration, Claimant submitted a summary of the relevant facts

skewed towards showing Glencore as a blameless investor, suffering harm at the hand of the

State, as the result of what it claims were sudden and surprising measures taken against its

investments. This is an incomplete and often untruthful narrative, and Claimant’s attempt to

gloss over key circumstances leading to the reversion of the Assets cannot succeed. As

explained below, in its presentation of the facts, Claimant fails to take into account the

Page 11: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

6

defining sociological aspects of the Bolivian mining sector, as well as the troubled political

history of the State before, during, and subsequent to the Privatization.

20. In fact, prior to the Privatization, the Corporación Minera de Bolivia (“COMIBOL”),

Bolivia’s mining state entity, was actively involved in the profitable operation of the Colquiri

Mine and maintained good relationships with the local independent mining workers. In

parallel, due to the investments made by Bolivia in the Assets, the Tin Smelter gained

worldwide renown for its high grade tin, whilst the Antimony Smelter was an active plant

processing the raw material generated by local production (Section 2.1).

21. During President Sánchez de Lozada’s first term in office, between 1993 and 1997, Bolivia

sought to capitalize the Assets. Due, at least in part, to the strong and vocal opposition of the

local population to such process, capitalization was abandoned – but not without having

provided Sánchez de Lozada with a priceless opportunity to gain intimate knowledge of the

Assets (Section 2.2).

22. The self-serving conduct adopted by President Sánchez de Lozada while in office was

perpetuated thereafter. Taking advantage of the policies he helped establish, and likely relying

on his knowledge of the Assets, Sánchez de Lozada participated in the tender processes for

the Assets. He acquired – irregularly – the Colquiri Mine lease and the Antimony Smelter in

2000-2001 (Section 2.3).

23. Sánchez de Lozada’s irregular acquisitions did not stop there. Following the illegal

privatization of the Tin Smelter in 2000, its new owner Allied Deals plc (“Allied Deals”) was

embroiled in a large fraud scandal and became bankrupt. This provided Sánchez de Lozada

with the perfect opportunity to purchase the Tin Smelter for a fraction of what had already

been an unjustifiably low purchase price (Section 2.4).

24. During Comsur’s operatorship of the Colquiri Mine, tensions steadily increased between the

cooperativistas and the workers of the company, and reached a pinnacle following Sánchez

de Lozada’s resignation and flight to the US (where he currently resides pending an extradition

request). In this context, where it was plainly foreseeable that the State would take action

against the Assets, the Swiss Glencore International (Claimant’s parent company) acquired,

inter alia, the Smelters and the Colquiri Mine. Indeed, Glencore International’s founder, Marc

Rich, was a close friend of Sánchez de Lozada. Marc Rich even obtained the Bolivian

citizenship in 1983 in order to avoid extradition to face criminal charges in the US.

Immediately following the acquisition, Glencore International transferred the Assets to

Page 12: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

7

Claimant for no compensation through a complex corporate structure, thus artificially creating

foreign ownership to protect the Assets (Section 2.5).

25. In this context of political change, and as a result of the irregularities in the Privatization, as

well as the unsustainable violence in the region, the State was compelled to revert the Assets.

Bolivia reverted the Tin Smelter in February 2007, due to its illegal privatization, the

Antimony Smelter in May 2010, due to its inactivity, and the Colquiri Mine in June 2012, as

a solution to the serious social conflict created by Glencore International’s subsidiary, Sinchi

Wayra (Section 2.6).

26. Following the reversion of the Assets, Bolivia negotiated in good faith with Glencore

International. Claimant, in turn, has acted in bad faith by revealing confidential details of the

negotiations between the State and its parent company (Section 2.7).

27. In the years thereafter, Bolivia has carried out significant investments in the Smelters and at

the Mine, and has deployed significant efforts to manage the social relations at Colquiri

(Section 2.8).

2.1 Prior To The Privatization, Bolivia Successfully Operated The Assets Through

COMIBOL And Its Affiliates

28. Before Sánchez de Lozada implemented the policies that led Bolivia to divest from strategic

sectors in the 1990s (described in section 2.2 below), the Assets relevant to this dispute were

operated by COMIBOL and its affiliates.

29. Prior to the Privatization, COMIBOL actively sought to operate the Mine in a profitable way

and to maintain good relationships with the independent mining workers in the region (who

would later organize themselves in cooperativas) (Section 2.1.1). Likewise, prior to the

Privatization, COMIBOL made significant investments in the Tin Smelter—achieving

historical maximum levels of production—and processed concentrates at the Antimony

Smelter (Section 2.2.2).

2.1.1 During The Time COMIBOL Operated The Colquiri Mine, The State Maintained Good

Relations With The Independent Mining Workers Of The Region

30. The Colquiri Mine is located in the municipality of the same name, in the Province of

Inquisivi—Department of La Paz—226 km from La Paz, and 70 km from the city of Oruro.

As noted by Paribas, one of the consultants employed by the State during the Privatization

process, the Colquiri Mine had been active since the 1850s. At that time, the production of

Page 13: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

8

the Mine was focused on silver. Then, “[t]owards the turn of the century tin became the

predominant product and was subsequently replaced by zinc as the major output.”1

31. The concessions comprising the Colquiri Mine are located underground, beneath the town of

Colquiri.2 Given that it has been active for over a century, the Mine is accessible from several

mouths of mine and tunnels scattered throughout the town and nearby. The following map

shows a general view of the Mine and the approximate areas where old tunnels and mouths of

mine exist. Leaving aside the new tailings dam (put in place by Comsur around 2001), the

configuration of the Mine has remained the same since before the Privatization.

Map of Colquiri and the Mine as of 2016. In red, approximate location of areas where old

mouths of the Mine and tunnels are located3

32. COMIBOL, however, was not working alone at the Mine. Since the 1980s, independent and

informal mining workers, then known as subsidiarios or arrendatarios, worked in surface

areas of the Mine under COMIBOL’s supervision.

1 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 121.

2 Map of the concessions of the Colquiri Mine, R-88.

3 Map of Colquiri (Google Earth, 2016), R-89.

Page 14: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

9

33. Independent mining workers, such as the subsidiarios—who, in other regions of Bolivia, were

organized in mining cooperatives or cooperativas mineras—are a common fixture in the

Bolivian mining sector. According to a study published in 2008 by the Centro de

Documentación e Información Bolivia, “[u]na característica de la minería boliviana, que

sólo se encuentra en este país, es la importancia del sector cooperativista dentro del sector

minero en su totalidad. Así, el número de cooperativistas, que se estima actualmente, llega

aproximadamente a 60.000 personas, representando el 90% del empleo minero nacional.”4

34. The cooperativistas and subsidiarios emerged as a significant social group in all large mines

in Bolivia,5 as a result of the crisis of the mining sector in the 1980s. Most of the

cooperativistas were former employees of COMIBOL.6 This social phenomenon became

particularly serious with public divestment from the mining sector in the 1980s and 1990s. In

fact, under Law 1.777 of 1997 (the “1997 Mining Code”), “[l]a Corporación Minera de

Bolivia es una empresa pública, autárquica, dependiente de la Secretaría Nacional de

Minería, encargada de la dirección y administración superiores de la minería estatal. Esta

entidad dirige y administra, sin realizar directamente actividades mineras, y solo mediante

4 J. Michard, “Cooperativas mineras en Bolivia”, CEDIB, 2008, R-90, p. 8 (Unofficial translation: “one characteristic of

Bolivian mining, which can only be found in this country, is the preponderance of the cooperatives within the mining

sector. Thus, the estimated current number of cooperativistas amounts to some 60,000 people, which represents 90%

of the national mining workforce”) (emphasis added).

5 See, for instance, Paribas, Legal and institutional diagnostic of Vinto, the Oruro Plant, Huanuni and Colquiri, R-91, p.

6 of the report on the mines (“En el centro minero de Huanuni se encuentran vigentes contratos que COMIBOL ha

suscrito con los cooperativistas mineros (cooperativas formadas a partir de ex trabajadores de COMIBOL que fueron

despedidos como consecuencia de la aplicación del D.S. 21060 del año 1985)- Existen cerca de 300 cooperativistas

mineros agrupados en cooperativas”) (Unofficial translation: “Several contracts which COMIBOL had concluded with

the mining cooperativistas (cooperatives formed by former workers of COMIBOL who had been laid off as a result of

the enforcement of S.D 21060 of 1985) were in force at the Huanuni mining centre. There are around 300 mining

cooperativistas organized in cooperatives”).

6 See, also, Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August

1999, RPA-4, p. 35 (“The ‘Cooperativistas’ are usually people living nearby the mines, coming from miners’ families

and poorly educated. They work in a very traditional social context and all lack technical guidance in the exploitation

process (the cooperatives do not have, generally speaking, an engineer or a geologist to guide them). Many of them are

ex- COMIBOL miners, laid out after the mid-80s' commodity crisis”). See, also, J. Michard, “Cooperativas mineras en

Bolivia”, CEDIB, 2008, R-90, p.12 (“A pesar de que en su artículo 34 la [Ley General de Sociedades Cooperativas]

declare que las minas de propiedad estatal serán administradas preferentemente por cooperativas, las minas fueron

administradas y explotadas por la Corporación Minera de Bolivia (Comibol) a partir del 1952, hasta la crisis de la

Comibol y su desmantelamiento que se inició en el 1985 con la promulgación del Decreto Supremo No. 21060. A partir

de esta fecha, la Comibol dejó poco a poco sus actividades de producción, despidiendo a miles de trabajadores

"relocalizados", situación ratificada por el nuevo Código de Minería de 1997 que estipula que la Comibol no puede

realizar operaciones directas de producción, sino sólo administrar las concesiones mediante contratos de

arrendamiento o de riesgo compartido”) (Unofficial translation: “Although article 34 of the [General Law on

Cooperatives Companies] provides that State-owned mines shall be administered preferably by cooperatives, mines

were managed and exploited by the Bolivian Mining Corporation (Comibol) as of 1952 until the crisis of Comibol and

its dismantling which commenced in 1985 with the enactment of Supreme Decree No. 21060. From this date, Comibol

progressively stepped away from its production activities and laid off thousands of “relocated” employees, a situation

that was ratified by the new Mining Code of 1997 which provides that Comibol cannot carry out direct operations of

production, but can only administer the concessions through lease contracts or shared risk contracts”).

Page 15: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

10

contratos de riesgo compartido, prestación de servicios o arrendamiento […].”7 The new

role of COMIBOL under the 1997 Mining Code greatly increased the number of cooperativas

around Bolivia.

35. Bolivia’s witness, Mr Cachi, one of the subsidiarios at Colquiri before the Privatization,

explains how the subsidiarios worked with COMIBOL:

COMIBOL, además, tenía arrendadas distintas áreas de la Mina a una

organización de mineros independientes que en esa época eran conocidos como

subsidiarios. El término “subsidiario” ha sido utilizado desde tiempos remotos para

referirse a las personas que subsisten del trabajo informal de una mina. A diferencia

de los trabajadores, los subsidiarios no gozan de estabilidad laboral ni beneficios

sociales. La organización de subsidiarios recibía de la empresa la autorización

para explotar distintas zonas y la entrega de algunos implementos mínimos. A

cambio, los subsidiarios vendían a la empresa la totalidad del mineral extraído (a

un precio que tenía en cuenta deducciones por (i) los implementos recibidos y (ii)

las regalías que debíamos pagar a la empresa por la explotación de ese mineral).

En algunos casos, recibíamos menos de la mitad del valor comercial del mineral

extraído. En esa época, éramos aproximadamente 200 subsidiarios.8

36. Subsidiarios and cooperativistas often had informal contracts with COMIBOL and the mining

companies. For instance, during the 1990s, COMIBOL entered into an agreement with the

“[t]rabajadores Mineros Contratistas de Colquiri,” (i.e., the subsidiarios) for “el

arrendamiento de yacimientos mineros para su exploración, reconocimiento, desarrollo,

explotación, beneficio y comercialización de los minerales existentes […].”9 Their lease

agreement clearly delineated the areas granted to the subsidiarios (it explicitly stated that “las

áreas que no están especificadas en el presente contrato, claramente señaladas en los planos

respectivos, permanecen bajo el dominio y control exclusivo de COMIBOL”10) and provided

7 Bolivian Mining Code, Law 1.777 of 17 March 1997, R-4, Article 91 (emphasis added) (Unofficial translation: “[t]he

Bolivian Mining Corporation is a public company, self-governed and dependent on the National Secretary of Mining,

in charge of the high management and administration of State mining. This entity manages and administers, without

directly carrying out any mining activities, and only through shared risk, services, or lease agreements”).

8 Cachi, ¶ 9 (Unofficial translation: “In addition, COMIBOL had leased different areas in the Mine to an organization of

independent mining workers who were known at that time as subsidiarios. The term “subsidiario” has been used since

ancient times to refer to people who live off informal work in a mine. Unlike workers, subsidiarios do not benefit from

employment stability or social benefits. The subsidiarios organization used to receive from the company the

authorisation to exploit different zones and the delivery of certain basic tools. In exchange, subsidiarios would sell to

the company the entirety of the extracted ore (at a price which took into account certain discounts for: (i) the tools

received and (ii) the royalties that we had to pay to the company for the exploitation of that ore). In some cases, we

received less than half the commercial value of the extracted ore. At that time, we were approximately 200

subsidiarios”). See, also, Mamani, ¶ 9.

9 Public Deed No. 50/98, lease agreement between COMIBOL and the subsidiarios of the Colquiri Mine of 10 July 1998,

R-92, clause 3 (Unofficial translation: “the lease of mineral deposits for their exploration, recognition, development,

exploitation, benefit and sale of the existing ore […]”). See, also, Public Deed No. 003/2000, amendment to the lease

agreement between COMIBOL and the subsidiarios of the Colquiri Mine of 5 January 2000, R-93.

10 Public Deed No. 50/98, lease agreement between COMIBOL and the subsidiarios of the Colquiri Mine of 10 July 1998,

R-92, clause 10 (emphasis added) (Unofficial translation: “the areas that are not specified in the present contract,

clearly marked in the respective plans, remain under the exclusive possession and control of COMIBOL”).

Page 16: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

11

that their activity was subject to “la supervisión técnica de los ingenieros de COMIBOL.”11

This agreement—initially valid for a period of 2 years— was subsequently amended after the

Privatization in order to extend its validity until 2018.12

37. In order to operate the Mine and to properly manage its relations with the subsidiarios,

COMIBOL employed a significant workforce at Colquiri. The Paribas report prepared for the

Privatization confirms that, “[a]s of end-May 1999, the total workforce amounted to 510

people (excluding health and education services), from 670 at end-August 1998, 165 of which

were working in the mine, 180 in the mill and 170 in the administration and services on the

surface.”13 Mr Joaquin Mamani, a former subsidiario and Colquiri employee following the

Privatization, explains that a high number of COMIBOL employees was crucial to secure a

sustainable operation and a good relationship with the subsidiarios.14

38. As a result of COMIBOL’s operation of the Mine and supervision of the subsidiarios’ activity,

operations at Colquiri progressed smoothly prior to the Privatization.15 As noted by Paribas,

the Mine produced 3.121 tons of tin concentrate and 15.622 tons of zinc concentrate in 1998.

These results were consistent with production in previous years.

11 Public Deed No. 50/98, lease agreement between COMIBOL and the subsidiarios of the Colquiri Mine of 10 July 1998,

R-92, clause 8 (b) (Unofficial translation: “the technical supervision of COMIBOL’s engineers”).

12 Public Deed No. 131/2000, lease agreement between Comibol and the Cooperativa 26 de febrero of 13 October 2000,

R-94, clause 5 (“A petición de la Cooperativa y en virtud de los planes y proyectos de explotación que tiene, COMIBOL

resuelve ampliar el plazo de vigencia del contrato hasta veinte años computables a partir de la fecha de suscripción del

contrato principal No. 50/98 de diez/cero siete/[98]”) (Unofficial translation: “Pursuant to the Cooperativa’s request

and in light of its exploitation plans and projects, COMIBOL decides to extend the contract term to twenty years as of

the date of execution of the main contract No. 50/98 of ten/zero seven/[98]”). See, also, section 2.5.1 below.

13 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 118.

14 Mamani, ¶ 8 (“Como anticipé, antes de comenzar a trabajar para Comsur en el año 2002, trabajé en la Mina como

subsidiario por más de diez años. Para entonces, la COMIBOL controlaba de cerca las áreas operadas por los

subsidiarios gracias a su alto número de empleados que podían vigilar el perímetro estas áreas. Recuerdo que, antes

de la privatización de la Mina, la COMIBOL alcanzó a tener unos 600 empleados”) (Unofficial translation: “As

mentioned above, before starting to work for Comsur in 2002, I worked in the Mine as a subsidiario for more than ten

years. By then, COMIBOL closely controlled the areas operated by subsidiarios through a high number of employees

who could survey the perimeter of these areas. I remember that, before the privatization of the Mine, COMIBOL had

up to 600 workers”).

15 Cachi, ¶ 10; Mamani, ¶ 9.

Page 17: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

12

Colquiri Tin and Zinc Production as of the time of the Privatization16

2.1.2 During The 1970-1990s, Bolivia Made Important Investments In The Smelters

39. By the time of the Privatization in early 2000, the State had made important investments that

made the Tin Smelter a world renowned plant.

40. The Tin Smelter was built between 1968 and 1970 near the city of Oruro by the State company

Empresa Nacional de Fundiciones (“ENAF”). Over the course of its first decade of

operations, ENAF invested over US$ 148 million in the Tin Smelter. These investments were

critical to expand production at the Smelter and, in fact, by 1981, ENAF reached a production

of 16.390 metric tons of high grade tin and 3.431 metric tons of low grade tin.17

16 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, pp. 130-131.

17 See Villavicencio, ¶ 27.

Page 18: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

13

Investments made by ENAF during the 1970s and 1980s18

41. Between 1987 and 1988, after a severe crisis in the mining sector in the 1980s (which also

affected the Smelters), ENAF carried out a study to improve production. Likewise, and in

order to fully implement the results of this study, ENAF invested over US$ 17 million in the

Tin Smelter between 1989 and 1994.19 As Bolivia’s witness, Eng Villavicencio, the current

general manager of the State’s Empresa Metalúrgica Vinto (“EMV”) explains, these

improvements enabled ENAF to become a world reference in metallic tin production.20 This

was confirmed by Paribas during the Privatization: “EMV tin is highly appreciated worldwide

because of its quality. The company has never had problems finding markets for its

production, and it obtains important premiums over international tin prices.”21

42. In 1999, prior to the Privatization, Paribas noted that the Tin Smelter was “configured to carry

out only high-grade treatment, its production capacity being 20,000 t/year.”22 Likewise, the

investments carried out by ENAF over the course of the last decade enabled the company to

reach historical maximum levels of production.

18 Empresa Metalúrgica Vinto Annual Report 1993-1994, R-43, p. 17.

19 Villavicencio, ¶ 32.

20 Villavicencio, ¶ 34 (“La apuesta por incorporar tecnología de punta en el proceso productivo fue vital: el cambio del

proceso en refinación del metal de electrólisis a cristalizadores chinos permitió, en primera instancia, trabajar con la

cantidad necesaria de personal en la planta y la refinación óptima del producto (estaño de grado A1 99.95% Sn),

consiguiéndose, de esa manera, reducir los costos de producción de forma directamente proporcional en función del

tonelaje tratado”) (Unofficial translation: “The decision to incorporate state-of-art technology in the production process

was crucial: the change from the electrolysis process of metal refining to Chinese crystallizers allowed, first, to work

with the necessary amount of staff in in the smalter and the optimal refinement of the product (tin of grade A1 99.95%

Sn), thus directly permitting to reduce production costs proportionally to the tonnage treated”).

21 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 38.

22 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 27.

Page 19: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

14

EMV’s Tin Production between 1993-1999.23 In red, historic record year for high

grade tin production.

43. In turn, prior to the Privatization, the State secured the activity of the Antimony Smelter in

order to process domestic production.24 The Antimony Smelter was built in 1976, also by

ENAF. The initial capacity of the Smelter—which was designed to treat high grade

sulphurous antimony concentrates—exceeded 5.000 tons.25

44. Contrary to what Claimant asserts,26 in August 1990, “the plant started operations again.”27

The resumption of operations followed significant upgrades to its systems,28 where “EMV

carried out a new technological design for the production of trioxide of antimony from

sulphurous concentrates, with the repairing of rotating furnace and the construction of new

23 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 38.

24 Villavicencio, ¶ 93 (“Con vistas a la privatización de las operaciones, hicimos inversiones entre 1999 y 2000 para

rehabilitar la maquinaria e infraestructura. Así, en 2001, la Fundidora de Antimonio tenía nuevamente una capacidad

de producción de entre 4.000 a 6.000 toneladas anuales de trióxido de antimonio”) (Unofficial translation: “In

preparation for the privatization of operations between 1999 and 2000 we made investments to rehabilitate the

equipment and infrastructure. Thus, in 2001, the Antimony Smelter had once again a production capacity of between

4,000 and 6,000 annual tons of antimony trioxide”).

25 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 61.

26 Statement of Claim, ¶ 59 (“[The Antimony Smelter] had been inaugurated in 1976 but it had only been operative during

the late 1970s and the 1980s.”).

27 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 61.

28 Villavicencio, ¶ 92 (“Durante los años que estuvo operativa (esto es, entre 1990 y 1999), la Fundidora de Antimonio

alcanzó una producción anual promedio de entre 4.000 y 6.000 toneladas anuales de trióxido de antimonio. El nivel de

producción se mantuvo estable por una década (esto es, hasta el año 1999) […]”) (Unofficial translation: “During the

years it operated (that is, between 1990 and 1999), the Antimony Smelter reached an average annual production of

between 4.000 and 6.000 annual tons of antimony trioxide. The production level remained stable for a decade (that is,

until 1999) […]”).

Page 20: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

15

continuous feeding systems for the furnace and equipment to gather gases and other

emissions.”29

Production volumes of the Antimony Smelter during the nineties30

* * *

45. In sum, at the time of the Privatization, the Colquiri Mine was producing significant amounts

of tin and zinc concentrate in peaceful collaborations with the subsidiarios, the Tin Smelter

was a valuable asset producing world-renowned high-grade tin, and the Antimony Smelter

was an active plant that could process significant amounts of antimony coming from local

production. These results were possible thanks to the large investments the State made over

more than three decades.

2.2 Between 1994 And 1997, While Former President Sánchez de Lozada Was In Office,

Bolivia Sought To Privatize The Smelters And The Colquiri Mine

46. The Colquiri Mine, Tin Smelter and Antimony Smelter described above were transferred to

the private sector in the late 1990s and early 2000s, as a result of the neoliberal policies which

drove successive governments, starting in 1985. Former President Sánchez de Lozada31 was

a key architect of these policies, which he then took advantage of at the end of his term in

office.

29 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 61.

30 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 67.

31 For a comprehensive description of Sánchez de Lozada, see Barcelona Centre for International Affairs, “Gonzalo

Sánchez de Lozada”, R-95; Los Tiempos, De Trump a Goni: cuando los millonarios llegan el poder, press article of 6

March 2017, R-96.

Page 21: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

16

47. The first step towards the privatization process of Bolivia’s industrial sector was the Paz

Estenssoro government’s enactment of Supreme Decree No. 21.060 of 29 August 1985. This

Decree provided, inter alia, for the “descentralización de la Corporación Minera de Bolivia”

through the creation of four affiliated companies.32 For the following two and a half years, as

Minister for Planning and Coordination of President Paz Estenssoro, Sánchez de Lozada was

responsible for the implementation this Supreme Decree.33

48. The economic policies of the Paz Estenssoro administration were in line with Minister

Sánchez de Lozada’s personal interests as a businessman. Such policies opened the door to

the participation of the private sector in the operation and functioning of State-owned

companies, and set the stage for the transfer of the latter to the former. Thus, the

administration ushered in what would be one of the most “radical” and “innovative”

neoliberal restructuring processes in Latin America.34

49. The economic policies of the Paz Estenssoro government were further developed and

reinforced by the centrist government of Jaime Paz Zamora, which enacted Law No. 1.330 of

24 April 1992 (the “Privatization Law”). Such law “autoriza a las instituciones, entidades

y empresas del sector público enajenar los bienes, valores, acciones y derechos de su

propiedad y transferirlos a personas naturales y colectivas nacionales o extranjeras, o

aportar los mismos a la constitución de nuevas sociedades anónimas mixtas.”35

50. After taking office as President in August 1993, Sánchez de Lozada promulgated Law No.

1.544 of 21 March 1994 (the “Capitalization Law”), which enabled his administration to

32 Supreme Decree No. 21.060 of 29 August 1985, R-2, Article 102 (Unofficial translation: “decentralization of the

Bolivian Mining Corporation”).

33 The Paz Estenssoro government’s second step was to enact Supreme Decree No. 21.377 of 25 August 1986, R-97, which

further modified the structure and functions of COMIBOL in order to ensure the continuity and profitability of its

operations. Pursuant to Article 2 of said Supreme Decree, “[l]as operaciones de la Corporación Minera de Bolivia se

efectuarán únicamente mediante unidades descentralizadas con autonomía de gestión, de acuerdo a las siguientes

formas de administración: a) Gestión directa de empresas subsidiarias de minería y metalurgia; b) Contratos de

arrendamiento con sociedades cooperativas conformadas preferentemente por trabajadores de la Corporación Minera

de Bolivia; c) Otro tipo de contratos establecidos en la legislación minera vigente, preservando el patrimonio de la

Corporación Minera de Bolivia y la propiedad estatal sobre los grupos mineros nacionalizados.” (Unofficial

translation: “[t]he operations of the Bolivian Mining Corporation shall be carried out exclusively through decentralized

units with management autonomy, in accordance with the following types of administration: a) Direct management of

mining and metallurgic affiliated companies; b) Lease agreements with cooperative companies formed preferably by

workers of the Bolivian Mining Corporation; c) Other types of contracts established pursuant to the mining legislation

in force, preserving the assets of the Bolivian Mining Corporation and State ownership of the nationalized mining

groups”).

34 B. Kohl, “Challenges to Neoliberal Hegemony in Bolivia”, Antipode, volume 38, issue 2, R-98, p. 305.

35 Law No 1,330, 24 April 1992, published in the Gaceta Oficial No 1,735, C-58, Article 1 (emphasis added) (Unofficial

translation: “authorizes the institutions, entities and companies of the public sector to transfer the property, assets,

shares and ownership rights and to transfer them to natural or legal, national or foreign persons, or to use them as

contribution to the constitution of new private-public partnerships”).

Page 22: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

17

increase even further the private sector’s involvement in, and control, over state-owned

companies. This law was aimed at “la conversión en sociedades de economía mixta, de

acuerdo a disposiciones en vigencia, de Yacimientos Petrolíferos Fiscales Bolivianos (YPFB),

Empresa Nacional de Electricidad (ENDE), Empresa Nacional de Telecomunicaciones

(ENTEL), Empresa Nacional de Ferrocariles (ENFE) y Empresa Metalúrgica Vinto.”36

51. Determined to transfer the State’s assets to the private sector, in parallel, the Sánchez de

Lozada administration enacted Supreme Decree No. 23.991, regulating the Privatization Law.

Pursuant to Article 1 thereof, “[t]odas las empresas y demás entidades públicas, propietarias

de unidades económicas, activos, bienes, valores, acciones y derechos, se someten, a partir

de la promulgación del presente decreto supremo, a procesos de reordenamiento, de acuerdo

a las normas contenidas en este cuerpo legal.”37

52. Sánchez de Lozada’s main target was COMIBOL, whose status and functions he altered

beyond the comparatively more modest steps towards decentralization taken by prior

administrations. On 17 March 1997, the 1997 Mining Code was enacted, requiring

COMIBOL to cease direct participation in mining activities and instead turn them over to the

private sector.38

36 Law No. 1.544 of 21 March 1994, R-8, Article 2 (emphasis added) (Unofficial translation: “the conversion to public-

private partnerships, pursuant to provisions in force, of Yacimientos Petrolíferos Fiscales Bolivianos (YPFB), Empresa

Nacional de Electricidad (ENDE), Empresa Nacional de Telecomunicaciones (ENTEL), Empresa Nacional de

Ferrocariles (ENFE) and Empresa Metalúrgica Vinto”). The Sánchez de Lozada administration reportedly capitalized

or privatized as many as 42 State-owned companies, i.e., more than half the total number of transfers to the private

sector occurring between 1985 and 2005. See L. Mendoza, Tres grupos de poder y 55 actores participaron en la

privatización en Bolivia, press article of 22 October 2017, R-99, p. 4.

37 Supreme Decree No. 23.991 of 10 April 1995, R-100, Article 1 (emphasis added) (Unofficial translation: “[a]ll

companies and other public entities, owners of economic units, assets, property, shares and rights, shall submit

themselves, as of the enactment of the present supreme decree, to reorganization processes, pursuant to the rules

provided in this statute”).

38 Bolivian Mining Code, Law 1.777 of 17 March 1997, R-4, Article 91 (“La Corporación Minera de Bolivia es una

empresa pública, autárquica, dependiente de la Secretaría Nacional de Minería, encargada de la dirección y

administración superiores de la minería estatal. Esta entidad dirige y administra, sin realizar directamente actividades

mineras, y solo mediante contratos de riesgo compartido, prestación de servicios o arrendamiento: a) Los grupos

mineros nacionalizados por Decreto Supremo No. 3223 de 31 de octubre de 1952, elevado a rango de Ley el 29 de

octubre de 1956; b) Las demás concesiones mineras obtenidas o adquiridas a cualquier título; c) Los residuos minero

-metalúrgicos provenientes de las concesiones mineras mencionadas en los incisos anteriores; d) Las plantas de

concentración, volatilización, fundición, refinación, plantas hidroeléctricas y otras de su propiedad; y e) El Cerro Rico

de Potosí, sus bocaminas, desmontes, colas, escorias, relaves, pallacos y terrenos francos del mismo, respetando

derechos preconstituidos”) (emphasis added) (Unofficial translation: “[t]he Bolivian Mining Corporation is a public

company, self-governed and dependent on the National Secretary of Mining, in charge of the high management and

administration of State mining. This entity manages and administers, without directly carrying out any mining activities,

and only through shared risk, services, or lease agreements: a) The mining groups nationalized by Supreme Decree No.

3223 of 31 October 1952, given the status of law on 29 October 1956; b) The other mining concessions obtained or

acquired under any title; c) The mining – metallurgic waste coming from the aforementioned mining concessions; d)

Concentration, volatilization, smelting, refining, hydroelectric plants and others of its ownership; and e) El Cerro Rico

de Potosí, its mine mouths, cuttings, tailings, slag, concentrate and loam fields of the same, observing pre-existing

rights”).

Page 23: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

18

53. The process set out in the Capitalization Law commenced in earnest in September 1995, when

four companies presented their credentials and were preselected as a result, for the

capitalization of EMV. Glencore International was one of them.39 Claimant’s suggestion that

Glencore International’s first brush with Bolivia was in the mid-2000s, when it “sought new

opportunities in the region”40 thus glosses over Glencore International’s Bolivian experience

in the early 1990s.

54. The tender process was declared void in June 1997. In fact, no economic offers were

submitted by the preselected companies, at least in part because of the public and vocal

disagreement expressed by the EMV, Huanuni and Colquiri workers with the potential

capitalization and execution of contratos de riesgo compartido (joint venture contracts). The

situation was such, in fact, that the due diligence team of one of the potential bidders was

prevented accessing the Colquiri site and had to withdraw “in the interest of their physical

safety.”41

2.3 Taking Advantage Of Policies Put In Place While In Office, Sánchez De Lozada

Acquired The Colquiri Mine Lease And The Antimony Smelter

55. In June 1999, the Banzer Suárez administration initiated the process of privatizing several key

State-owned companies. In this context, Sánchez de Lozada held himself free to profit from

the policies he had put in place and the intimate knowledge of the assets that he had acquired

while in office. Through his company Comsur,42 he bid for, and acquired the valuable

Colquiri Mine Lease (Section 2.3.1) and the Antimony Smelter (Section 2.3.2), both in

irregular circumstances.

2.3.1 Sánchez De Lozada, Through Comsur, Bid For And Acquired The Colquiri Mine Lease

In 1999-2000

56. Sánchez de Lozada participated in the tender process for the Colquiri Mine Lease through his

company, Comsur, and acquired the Asset under extremely favourable conditions.

39 Letter from Glencore International to the Minister for Capitalization of 20 October 1995, R-101.

40 Statement of Claim, ¶ 33.

41 N.M. Rotschild & Sons Limited, Capitalization of E.M. Vinto and transfer of operating control over COMIBOL

properties to private sector initiative, R-102, p. 5.

42 International Finance Corporation, “IFC approves US$99.05 million financing for five projects in Latin America”, press

release, R-103.

Page 24: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

19

57. The terms of reference for the tender of the Colquiri Mine (the “Terms of Reference”)43 were

sold to only two potential bidders: Comsur and the Brazilian company Paranapanema S.A.44

However, only one bid was actually received,45 from a consortium made up of Comsur and

the Commonwealth Development Corporation (“CDC”) (together, the “Consortium”).46

58. The Qualifying Commission proceeded to review and validate the Consortium’s economic

and technical proposal, on the basis that it was allegedly in the State’s interest.47 In so doing,

however, the Qualifying Commission did not analyse further or in any depth the economic

proposal submitted by the Consortium, nor did it consider the implications that accepting such

proposal might in fact have had “para los intereses del Estado Boliviano.”48 In particular, the

Qualifying Commission spared no thought to the fact that the lease would be awarded to the

Consortium for free and in exchange for no consideration whatsoever.49 Nor did the

Qualifying Commission reflect on the very small investment commitment offered by the

Consortium, totalling US$ 2 million for the first two years of operations.50 Likewise, the

Commission did not spare a single thought to the low percentage of royalties offered by the

Consortium, amounting to “el tres punto cinco por ciento (3.5%) del ingreso neto de

fundición.”51

43 Terms of Reference for the Public Tender for the Colquiri Mine Lease of 24 June 1999, R-104.

44 Minutes of the opening of Envelope A proposals (Colquiri) of 20 December 1999, R-105, p. 2.

45 Envelope A of the bid for the Colquiri Mine Lease submitted by the Comsur-CDC Consortium (excerpts) of 20

December 1999, R-106.

46 Comsur held 51% of the shares, whilst CDC held the remaining 49%. See Statement of Claim, footnote 28, p. 12;

Minutes of the opening of Envelope A proposals (Colquiri) of 20 December 1999, R-105, p. 1; Minutes of the opening

of Envelope B proposals (Tin Smelter, Antimony Smelter, Colquiri Mine Lease) of 20 December 1999, R-107, p. 6.

47 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 6 (“El precio

ofertado por el Consorcio COMSUR –CDC resulta conveniente para los intereses del Estado Boliviano y al no existir

un precio mínimo según el informe del Banco de Inversión puede considerarse como una propuesta positiva”)

(Unofficial translation: “The price offered by the COMSUR – CDC Consortium is convenient for the Bolivian State’s

interests and as there is no minimum price pursuant to the Investment Bank’s report, it can be considered to be a positive

proposal”).

48 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 6 (Unofficial

translation: “for the Bolivian State’s interests”).

49 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 5; Supreme

Decree No 25,631, 24 December 1999, published in the Gaceta Oficial No 2, 192, C-6, Article 2.

50 Supreme Decree No 25,631, 24 December 1999, published in the Gaceta Oficial No 2, 192, C-6, Article 2.

51 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11, Article 5.1 (Unofficial translation: “three point five per cent (3.5 %) of the net

smelting revenue”); Supreme Decree No 25,631, 24 December 1999, published in the Gaceta Oficial No 2, 192, C-6,

Article 2.

Page 25: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

20

59. Absent any competing bids and on the basis of the favourable recommendation of the

Qualifying Commission, the Banzer Suárez administration awarded the Colquiri Mine lease

to the Consortium.52 The Consortium, as operator, had the right to exploit, explore and

commercialize minerals from the Mine for a period of 30 years (including a two-year

exploration phase), and would pay a royalty of 3.5% of its net revenue.53 As explained in

section 4.3.1 below, the award to Comsur of the Colquiri Mine lease did not observe the

pertinent constitutional requirements.54

60. Following its successful bid for the Mine Lease, the Consortium incorporated a local

company: Colquiri S.A. (“Colquiri”).55 Initially, Colquiri’s shares were held by Comsur at

68% and CDC at 32%.56 As of July 2001, Comsur’s interest in Colquiri amounted to 51%,

and CDC’s to 49%.57 As explained below, Colquiri would, in time, come to own the

Antimony Smelter and to hold a controlling interest in Vinto, which owned in turn the Tin

Smelter.58

2.3.2 Sánchez De Lozada, Through Comsur, Bid For And Acquired The Antimony Smelter

In 2000-2001

61. The former President did not stop in his quest to acquire the State assets for the privatization

of which he had paved the way during his time in office. Through Colquiri, Sánchez de

Lozada also submitted a bid for and was successful in the acquisition of the Antimony Smelter

in late 2000 – early 2001.

52 Supreme Decree No 25,631, 24 December 1999, published in the Gaceta Oficial No 2, 192, C-6, p. 31.

53 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11, Articles 2.7, 4.1, 4.4, 5.1, 7.1, 8.1.2.

54 Article 59(5) of the 1967 Constitution (R-3) provided, in this regard, that one of the attributions of the legislative branch

was “[a]utorizar y aprobar la contratación de empréstitos que comprometan las rentas generales del Estado; así como

los contratos relativos a la explotación de las riquezas nacionales” (Unofficial translation: “[a]uthorize and approve

the borrowing of loans that engage the State’s general income; as well as contracts concerning the exploitation of

national resources”). It is undisputable that a lease agreement for the exploration and exploitation of the Bolivian State’s

mineral resources falls within the scope of this constitutional provision. However, the Bolivian legislative was never

consulted in this regard and never authorized nor approved the Colquiri Mine lease. See Section 4.3.1 below.

55 Statement of Claim, ¶ 30.

56 Share register of Colquiri SA, C-17, pp. 3-4. CDC would continue to hold this interest in Colquiri until March 2006.

See Put Notice from Actis (on behalf of CDC) to Glencore International of 21 March 2006, C-67.

57 Share register of Colquiri SA, C-17, pp. 3-4. See also Statement of Claim, note 28.

58 See Section 2.4.2 below.

Page 26: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

21

62. Following the failed capitalization attempt discussed in Section 2.2 above, a first, unsuccessful

public tender for the Antimony Smelter took place in 1999.59 Thereafter, a second attempt

was made at privatization in 2000,60 and, in this context, the Asset was acquired by Colquiri.

63. At the time, the context in Bolivia was not favourable for the privatization of the Antimony

Smelter and at least two Bolivian companies reportedly requested that the process be

postponed.61 However, the Banzer Suárez administration would not delay the privatization of

the Antimony Smelter any further.

64. Sánchez de Lozada’s Colquiri submitted one of the only two offers for the Smelter. 62 In fact,

Sánchez de Lozada’s only competition, Allied Deals, was disqualified and its economic and

technical proposal was never considered.63

65. The Qualifying Commission recommended accepting Colquiri’s bid, which offered only

US$ 1.1 million for the Antimony Smelter.64 Albeit small, this amount was still above the

US$ 100,000 minimum price threshold recommended by Paribas.

66. On 27 November 2000, exactly one week following the Qualifying Commission’s

recommendation, the Oruro Parliamentary Group (Brigada Parlamentaria de Oruro) wrote

to President Banzer Suárez and expressed concern at the very low price established by

59 See Supreme Decree No 25,631, 24 December 1999, published in the Gaceta Oficial No 2, 192, C-6, Article 4. See

also Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters,

the Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 8.

60 See Terms of Reference for the Second Public Tender for the Antimony Smelter of 31 July 2000, R-109. The Terms of

Reference for the original tender were modified and the invitation to tender was published on 24 August 2000.

61 Letter from the Oruro Parliamentary Group to President Bánzer Suárez of 27 November 2000, R-110. See, also, Letter

from Compañía Minera Salinas to the Minister of Foreign Trade and Investment of 30 October 2000, R-111 (“1. Los

últimos acontecimientos en el país, con los bloqueos de caminos en Oruro, han impedido la visita de nuestros socios

extranjeros a la fundición de antimonio en Vinto. 2. La inestabilidad del precio del antimonio en estos últimos meses,

sumado a las vacaciones de verano en el hemisferio norte (donde están todos los compradores) han hecho imposible

tomar decisiones en el orden financiero. 3. Tanto EMUSA como nuestra empresa, que producimos la casi totalidad del

antimonio boliviano, recién hemos reactivado nuestras operaciones; por consiguiente, precisamos de un plazo

razonable para poder participar en condiciones ecuánimes en la licitación de la fundición de antimonio de Vinto”)

(Unofficial translation: “1. Recent events in the country, with the road blockings in Oruro, have prevented the visit of

our foreign partners to the antimony smelter in Vinto. 2. The instability of the price of antimony in the latest months,

plus the summer holidays in the northern hemisphere (where all the buyers are located) have made it impossible to make

any financial decision. 2. Both EMUSA and our company, which produce the quasi totality of Bolivian antimony, have

only recently reactivated our operations; as a result, we require a reasonable period of time in order to be able to

participate under fair conditions in the tender for the Vinto antimony smelter”).

62 Report No. 001/2000 of the Qualifying Commission of the second public tender for the sale of the Antimony Smelter

of 20 November 2000, R-112, p. 1.

63 Report No. 001/2000 of the Qualifying Commission of the second public tender for the sale of the Antimony Smelter

of 20 November 2000, R-112, p. 2.

64 Report No. 001/2000 of the Qualifying Commission of the second public tender for the sale of the Antimony Smelter

of 20 November 2000, R-112, pp. 3-4.

Page 27: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

22

Paribas.65 As a result, the Oruro Parliamentary Group requested that the adjudication process

be suspended pending further evaluation and analysis.66

67. The Oruro Parliamentary Group’s concerns were echoed in the President of the Bolivian

National Senate, Leopoldo Fernández Ferreira’s letter to President Banzer Suárez.67

Similarly, on 8 December 2000, the Foreign Trade and Investment Minister, Humberto Bohrt

Artieda informed the Minister of the Presidency, Walter Guiteras Denis, of a communication

transmitted to him by the President of the Bolivian Chamber of Representatives, requesting

the immediate suspension of the adjudication process of the Antimony Smelter pending an

investigation into the minimum price proposed by Paribas.68

68. Paribas’ minimum price, inter alia, failed to take into account the recent investments that the

State had made into the Antimony Smelter. As explained in Section 2.1.2 above, the

Antimony Smelter’s operations were restarted in August 1990, as a result of the “new

technological design” implemented at the plant. 69 The State carried out further investments

65 Letter from the Oruro Parliamentary Group to President Bánzer Suárez of 27 November 2000, R-110 (“Consideramos

erróneas el proceso de fijación del precio base en $us 100.000 (Cien Mil 00/100 Dólares), por cuanto el Estado

boliviano invirtió $us. 12.000.000 (Doce Millones 00/100 Dólares), para el inicio de su funcionamiento a principios de

la década de los setenta”) (Unofficial translation: “We consider erroneous the process of determining the base price at

$us 100.000 (One Thousand 00/100 Dollars), given that the Bolivian State invested $us. 12.000.000 (Twelve Million

00/100 Dollars), for it to commence functioning at the beginning of the seventies”).

66 Letter from the Oruro Parliamentary Group to President Bánzer Suárez of 27 November 2000, R-110.

67 Letter from Leopoldo Fernández Ferreira to President Hugo Bánzer Suárez of 5 December 2000, R-113 (“Explique, si

hasta antes de la fecha prevista para la presentación de propuestas y apertura de sobres, por lo menos dos empresas

que compraron el Pliego de Condiciones solicitaron ampliación de plazo.- 2.- Explique, si las Empresas adquirientes

del Pliego que solicitaron ampliación de plazo, son empresas nacionales y si representan a algún sector.- 3.- Explique,

si se comunicó oportunamente a las Empresas Oferentes la negativa de ampliar el plazo y se comunicó que eran dos

los oferentes que solicitaron ampliación en la última semana.- 4.- Explique, cuáles las razones por las que no se amplió

el plazo, considerando que de esa manera se inhabilitan a dos oferentes nacionales”) (Unofficial translation: “Explain

if until prior to the deadline for the presentation of proposals and opening of envelopes, at least two companies which

had acquired the Terms of Reference requested an extension of the deadline.- 2.- Explain if the companies having

acquired the Terms and requested the extension of the deadline are national companies and whether they represent any

sector in particular.- 3.- Explain if the refusal to extend the deadline was promptly communicated to the Biddeing

Companies and whether the fact that two bidders requested a time extension during the last week was communicated.-

4.- Explain the reasons why the deadline was not extended, considering that as a result, two national bidders were

disqualified”).

68 Letter from Humberto Bohrt Artieda to Walter Guiteras Denis of 8 December 2000, R-114 (“Dígase al Poder Ejecutivo,

que el proceso de privatización de la Fundición de Antimonio debe suspenderse, entretanto se forme una comisión en

la que participe el Gobierno (Ministerio de Comercio Exterior, la Comisión de Desarrollo Económico (Comité de

Minería y Metalurgia) de la H. Cámara de Diputados y la Brigada Parlamentaria de Oruro a propósito de explicar por

parte de Banco de Inversiones Paribas la determinación del ridículo precio base de 100.000 $us, para la venta de la

fundición de antimonio. Al mismo tiempo revisar toda la documentación del proceso de la Licitación Pública Nacional

e Internacional”) (Unofficial translation: “Inform the Executive Power that the privatization process of the Antimony

Smelter must be suspended while a commission is set up, in which the Government (Ministry of Foreign Trade, the

Commission for Economic Development (Mining and Metallurgy Committee) of the H. House of Representatives and

the Oruro Parliamentary Group will participate with the objective of allowing the Investment Bank Paribas to explain

the fixation of the ridiculous base price of 100.000 $us, for the sale of the antimony smelter. At the same time, review

all the documentation of the process of National and International Public Tender process”).

69 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 61.

Page 28: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

23

immediately prior to the privatization.70 However, the Banzer Suárez administration forged

ahead with the privatization.

69. On 5 January 2001, the administration awarded the tender for the Antimony Smelter to

Colquiri71 and the sale purchase agreement was executed on 11 May 2001.72 This was done,

again, without observing the constitutional requirements for the execution of such

agreements.73

2.4 The Tin Smelter Was Acquired By Allied Deals In Highly Irregular Circumstances And

Subsequently Transferred To Sánchez De Lozada

70. Sánchez de Lozada also submitted a bid in the privatization of the Tin Smelter (Section 2.4.1).

Though that bid was unsuccessful, Sánchez de Lozada ultimately succeeded in acquiring the

Tin Smelter in 2002, following the fraud investigation and bankruptcy of the asset’s then-

owner (Section 2.4.2).

2.4.1 Allied Deals Acquired The Tin Smelter In Highly Irregular Circumstances

71. The Tin Smelter was privatized in a process fraught with irregularities, which favoured the

UK-based company Allied Deals.

72. Even before the privatization process was properly underway, irregularities in relation thereto

became known. For example, a letter from the Foreign Trade and Investment Ministry to the

CEO of COMIBOL, Alvaro Rejas, referred to “contactos no transparentes entre la gerencia

de COMIBOL y los directores de Allied Deals”74 as early as February 1999. This issue,

however grave, was not even considered when, some months later, Allied Deals’ low-priced

bid for the Smelter was declared successful.

73. On 20 December 1999, the Qualifying Commission proceeded to review the two package

proposals for the Tin Smelter and the Huanuni joint venture, received from the Comsur – CDC

70 Villavicencio, ¶ 93.

71 Supreme Decree No 26.042, 5 January 2001, published in the Gaceta Oficial No 2.282, C-8.

72 Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External Trade

and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9.

73 Article 59(5) of the the 1967 Constitution (R-3) provided, in this regard, that one of the attributions of the legislative

branch was “[a]utorizar y aprobar la contratación de empréstitos que comprometan las rentas generales del Estado;

así como los contratos relativos a la explotación de las riquezas nacionales” (Unofficial translation: “[a]uthorize and

approve the borrowing of loans that engage the State’s general income; as well as contracts concerning the exploitation

of national resources”). See Section 4.3.1. below.

74 Letter from Foreign Trade and Investment Minister to the Executive President of COMIBOL of 18 February 1999, R-

115 (Unofficial translation: “non-transparent contacts between COMIBOL management and the directors of Allied

Deals”).

Page 29: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

24

Consortium and Allied Deals.75 The Qualifying Commission, having reviewed the

qualifications of the two bidders to participate in the tender, proceeded to declare both of them

valid.76 However, in approving Allied Deals’ qualifications,77 the Qualifying Commission

ignored several material deficiencies invalidating the submission.78

74. The Qualifying Commission then proceeded to examine the economic proposals of the two

bidders. Paribas’ minimum price recommended for the sale of the Tin Smelter was set at US$

10 million.79 Allied Deals offered US$ 14 million for this asset.80 The Consortium made a

conditional offer, outside the scope of the Terms of Reference,81 which was in any event less

than that of Allied Deals.82

75. On this basis, on 24 December 1999, the Government awarded the Tin Smelter (as well as the

Huanuni mine joint venture) to Allied Deals.83 The sale purchase agreement for the Tin

Smelter was executed on 9 March 200084 and Allied Deals took physical possession of the

asset on 16 March 2000.

75 Notarized minutes of the opening of the Envelope A proposals (Tin Smelter, Colquiri) of 21 December 1999, R-116.

76 Notarized minutes of the opening of the Envelope A proposals (Tin Smelter, Colquiri) of 21 December 1999, R-116.

77 Notarized minutes of the opening of the Envelope A proposals (Tin Smelter, Colquiri) of 21 December 1999, R-116, p.

0002342; Report of the Qualifying Commission of the public tender for the Tin and Antimony Smelters, the Oruro

Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 20 December 1999, R-117.

78 Allied Deals did not meet the requirements of Article 2 of the Terms of Reference to be an operator. It did not provide

any evidence demonstrating that its turnover was derived from “ventas brutas provenientes de la actividad de

comercializacion de minerales, concentrados y/o metálicos en general” (Unofficial translation: “gross sales from the

commercialization of ore, concentrates and/or metals in general”). It also failed to submit evidence of “alta seguridad

y récord ambiental satisfactorios” (Unofficial translation: “satisfactory high security and environmental record”). See

Terms of Reference for the Public Tender for the Tin Smelter of 24 June 1999, R-118, Articles 2.1.2, 4.5; Amendment

No. 6 to the Terms of Reference to the Tin Smelter Tender of 2 December 1999, R-119, p. 2; Envelope A proposal

submitted by Allied Deals for the tender of the Tin Smelter of 20 December 1999, R-120, pp. 116, 139, 163, 185, 188.

79 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 4. No

minimum price was set for the Huanuni mine joint venture.

80 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 5.

81 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, pp. 5-6 (“Los

proponentes cumplieron con la documentación legal exigida en el sobre “A”, sin embargo el proponente Consorcio

COMSUR-CDC condicionó su propuesta económica, aspecto que se encuentra al margen de lo permitido en el Pliego

de Condiciones.”) (Unofficial translation: “The bidders complied with legal documentation required in envelope “A”,

however, the bidder Consortium COMSUR-CDC conditioned its economic offer, thus exceeding what is allowed by the

Terms of Reference”). See Terms of Reference for the Public Tender for the Tin Smelter of 24 June 1999, R-118.

82 Recommendation Report of the Qualifying Commission of the Public Tender for the Tin and Antimony Smelters, the

Oruro Industrial Plant, the Huanuni joint venture and Colquiri Mine Lease of 21 December 1999, R-108, p. 5.

83 Supreme Decree No 25,631, 24 December 1999, published in the Gaceta Oficial No 2, 192, C-6, p. 31.

84 Notarizations of the sale and purchase agreement of the Tin Smelter between the Ministry of External Trade and

Investment, Corporación Minera de Bolivia, Empresa Metalúrgica Vinto and Allied Deals Estaño Vinto SA, C-7.

Page 30: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

25

76. In the aftermath of the privatization, it became evident that the price offered by Allied Deals

was inadequate. Allied Deals had been gratuitously provided with a series of items which had

not been included in the inventory of Smelter (and were thus not covered by the price). This

included “repuestos en almacenes,” “estaño en proceso de fundición” and “concentrados de

estaño para fundir,” the total value of which amounted to some US$ 16,521,556.85 A report

addressed by EMV to the President of COMIBOL in July 2000 provided a breakdown of the

value of each category of such items.86

77. The total value of the items “gifted” to Allied Deals was greater than the purchase price by

US$ 1,821,556. In other words, Allied Deals was essentially paid almost US$ 2 million in

order to take possession of a going concern and of the valuable tin in its pipeline. This was

also the conclusion of the EMV report mentioned above:

De la anterior tabla de items entregados se desprende que la planta de fundición de

estaño de alta y baja ley juntamente con toda su infraestructura ha sido entregada

gratuitamente además con dólares americanos de millón ochocientos mil

adicionales.87

78. The adjudication of the Tin Smelter for this inadequate price sparked immediate outrage in

Bolivia, even before the sale purchase agreement was concluded. Several actors from Oruro,

where the Smelter is located, in fact denounced the terms of the sale and called for formal

inquiries to be made into the circumstances which could have led to them.

79. One of Oruro’s core civic organisations, the Oruro Civic Committee (Comité Cívico de Oruro)

publicly condemned what it termed an “irrational” sale and resolved to request (i) the removal

from office and prosecution of the President of COMIBOL and (ii) the reversion of the Tin

Smelter.88 On 21 February 2001, the President of the Oruro Civic Committee wrote to the

85 Report from Ms Wilma Morales Espinoza (EMV) to Eng. Rafael Delgadillo (COMIBOL) of 7 July 2000, R-121, p. 2

(Unofficial translation: “spare parts in warehouses,” “tin in smelting process” and “tin concentrates for smelting”).

86 Report from Ms Wilma Morales Espinoza (EMV) to Eng. Rafael Delgadillo (COMIBOL) of 7 July 2000, R-121, p. 2.

87 Report from Ms Wilma Morales Espinoza (EMV) to Eng. Rafael Delgadillo (COMIBOL) of 7 July 2000, R-121, p. 2

(Unofficial translation: “It appears from the table of delivered items above that the high and low grade tin smelter

together with its infrastructure has been delivered for free and with an additional one million eight hundred thousand

American dollars”).

88 Statement of the Oruro Civic Committee, R-122 (“TERCERO.- Solicitar al Gobierno la inmediata realización de

gestiones para que el daño económico infringido al Departamento de Oruro sea revertido, recuperándose el valor total

de los materiales y concentrados obsequiados al Consorcio ALLIED DEALS.”) (Unofficial translation: “THIRD.-

Request the Government to immediately take the necessary measures so that the economic damage caused to the

Department of Oruro can be reverted, thus recovering the total value of materials and concentrate gifted to the

Consortium ALLIED DEALS”).

Page 31: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

26

Comproller General (Contralor General de la República) in this connection, requesting an

investigation into “la fraudulenta compra de la Empresa Metalúrgica de Vinto – Oruro.”89

80. The Oruro Civic Committee’s call for an investigation into the sale of the Tin Smelter was

echoed by Oruro-elected Representative Pedro Rubín de Celis (a member of the Oruro

Parliamentary Group), in his letter to the General Comptroller (Contralor General de la

República) of 10 May 2001.90 Representative Rubín de Celis also questioned the award of

the Huanuni mine joint venture to Allied Deals and presented a formal request for information

against the then-Minister for Economic Development, Carlos Saavedra Bruno, in this

connection.91

81. The issue was even brought directly to the attention of President Banzer Suárez on 23 May

2001.92 Yet Bolivia’s executive did not take any actions in connection with the irregular

privatization of the Tin Smelter and, on 21 November 2001, the sale purchase agreement

concluded between Allied Deals, COMIBOL, and EMV was notarized.93 As in the case of

the Antimony Smelter, this was done, again, without observing the constitutional

requirements for the execution of such agreements.94

82. However, Allied Deals would shortly turn out to have been a bad choice for the privatization

of the Tin Smelter and the resulting public scandal would once again bring to the forefront the

issue of the Tin Smelter’s illegal privatization.

2.4.2 The Bankruptcy And Fraud Scandal Involving Allied Deals In 2002 Set The Stage For

The Acquisition Of The Tin Smelter By Comsur

83. After some two years of poor management, Allied Deals became bankrupt and was the subject

of a major fraud investigation in the UK. This paved the way for Sánchez de Lozada finally

to acquire the Tin Smelter.

89 Letter from the President of the Oruro Civic Committee to the Contralor General de la República of 21 February 2001,

R-123 (Unofficial translation: “the fraudulent acquisition of Empresa Metalúrgica de Vinto – Oruro”).

90 Letter from Representative Pedro Rubín de Celis to the Contralor General de la República of 10 May 2001, R-124.

91 Formal complaint by Representative Pedro Rubín de Celis against Minister Carlos Saavedra Bruno, R-125.

92 Letter from the Oruro Central Obrera to President Banzer Suárez of 23 May 2001, R-126.

93 Notarizations of the sale and purchase agreement of the Tin Smelter between the Ministry of External Trade and

Investment, Corporación Minera de Bolivia, Empresa Metalúrgica Vinto and Allied Deals Estaño Vinto SA, C-7.

94 Article 59 (5) of the 1967 Constitution (R-3) provided, in this regard, that one of the attributions of the legislative branch

was “[a]utorizar y aprobar la contratación de empréstitos que comprometan las rentas generales del Estado; así como

los contratos relativos a la explotación de las riquezas nacionales” (Unofficial translation: “[a]uthorize and approve

the borrowing of loans that engage the State’s general income; as well as contracts concerning the exploitation of

national resources”). See Section 4.3.1 below.

Page 32: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

27

84. Allied Deals changed its name to RBG Resources plc (“RBG”) on 5 October 2001.95 The

company’s plight commenced in January 2002, when its long-term auditor

PriceWaterhouseCoopers resigned citing a breakdown in the relationship of trust which

should exist between the directors of a company and its auditors.96 RBG subsequently became

the subject of enquiries by the City of London police, which ultimately referred the case to

the Serious Fraud Office, because of the size of the alleged fraud and its complexity.97 In

early May, a petition for the winding up of RBG was submitted to and upheld by the High

Court of Justice in London, which proceeded to appoint Grant Thornton as provisional

liquidator of RBG.98

85. In Bolivia, the bankruptcy of RBG brought up once again the matter of the illegal privatization

of the Tin Smelter and prompted renewed calls for investigation. Oruro-elected Senator

Carlos Sandy Antezana (from Movimiento al Socialismo—“MAS”), with the support of party

leader and future President Evo Morales, requested that Chancellor Carlos Saavedra Bruno

resign from office, on account of having permitted the illegal sale of Vinto and Huanuni while

serving as Foreign Trade Minister.99 In addition, members of the MAS transmitted evidence

of the Chancellor’s corruption to the Unidad Técnica de Lucha Contra La Corrupción

(Technical Unit for the Fight Against Corruption) for investigation.100 In this context, Vice-

President Mesa Gisbert was asked to have Chancellor Saavedra to step down.

86. The bankruptcy of RBG also posed a serious socio-economic problem, in light of the over

1.200 jobs provided by the Tin Smelter and the Huanuni mine, which ensured the livelihood

of over 30.000 people. In this context, the State was called to intervene in order to avoid the

bankruptcy of the Smelter. 101 The President of the Oruro Parliamentary Group, José Sánchez

95 Notarization of the change of name of Complejo Vinto of 30 August 2002, C-45, p. 3.

96 RBG Resources Plc (In liquidation) v. Rastogi [2005] ADR.L.R. 05/24, Judgment of 24 May 2005, R-127, ¶ 2.

PriceWaterhouseCoopers expressed concern that the accounts it had audited may have included non-existent

transactions. See Times Online, SFO raids offices of Rastogi metals firm, press article of 7 May 2002, R-128; Yahoo

Finance, SFO probes failed metal trader, press article of 3 May 2002, R-129.

97 Financial Times, Fraud Office raids metal producer over accounts, press article of 4 May 2002, R-130; The Guardian,

SFO raids $ 1bn metal trader, press article of 4 May 2002, R-131 (“the criminal investigation is believed to centre

around allegations of faked invoices, used to persuade banks to extend credit lines. The credit was then used to cover

losses on the London Metal Exchange and to buy assets in Bolivia and Romania, it is alleged”).

98 RBG Resources Plc (In liquidation) v. Rastogi [2005] ADR.L.R. 05/24, Judgment of 24 May 2005, R-127, ¶ 5; Letter

from Mike Jervis (Grant Thornton) to Juan Carlos Valdívia Crespo (RBG Estaño Vinto) of 15 May 2002, R-132; Fax

from Bolivia’s Ambassador to the UK to the Foreign Relations Minister of 21 May 2002, R-133, pp. 1, 2.

99 La Razón Digital, El MAS pide la renuncia del Canciller Saavedra, press article of 8 November 2002, R-134; El Diario,

MAS pide la renuncia del Canciller de la Republica, press release of 4 December 2002, R-135.

100 El Mundo, MAS presentó las pruebas de corrupción contra Canciller, press release of 4 December 2002, R-136.

101 DDHH pide que el Estado intervenga, Brigada Parlamentaria pide preservar fuentes de trabajo, press article, R-137;

La Patria, Gobierno: Vinto tiene que seguir funcionando, press article of 18 May 2002, R-138.

Page 33: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

28

Aguilar, was described in the Bolivian press as stating that “una reversión de la empresa

metalúrgica de Vinto, a favor del Estado, podría ser el paso más viable, pero es necesario

analizar las condiciones, porque si se anula contrato es preciso establecer en qué

condiciones.”102

87. The situation in fact subsequently became tense, with the cooperativistas threatening to take

possession of the Tin Smelter and mine if they were not paid what they were owed.103

88. On 15 May 2002, the State intervened in the operations of the Huanuni mine joint venture.104

In the aftermath, on 20 May 2002, the Federación Regional de Cooperativas Mineras

Huanuni requested that the sale purchase contract for the Tin Smelter be declared null and

void and that the State recover the Smelter:

Que también de acuerdo al Convenio del 30/06/01, se revise el Contrato de Riesgo

Compartido de Huanuni, según el punto cuarto y se anule en Contrato arriba

mencionado y Huanuni sea Revertido al Estado y posteriormente [sic] sé

Cooperativise, y la Empresa Metalúrgica de VINTO por ser pieza clave en la

Economía del Occidente Boliviano, por ser un mercado de garantía para nuestros

concentrados debe volver a manos del estado.105

89. But the Quiroga administration did not intervene at Vinto, despite its promises to guarantee

the social stability and safeguard the patrimony of Oruro.106 Instead, the administration

accepted the sale of the Tin Smelter to a private buyer107 and was kept apprised of the

liquidators’ efforts towards such transaction, as shown by an internal report dated 15 May

2002:

Los liquidadores están DESESPERADOS en encontrar un comprador para las

minas, y están contemplando ofrecer Vinto y Huanuni a COMSUR. Me preguntaron

cuál sería el impacto de esto dada la situación política del país con las elecciones

102 DDHH pide que el Estado intervenga, Brigada Parlamentaria pide preservar fuentes de trabajo, press article, R-137

(Unofficial translation: “a reversion of the Vinto metallurgical company in favour of the State could be the most viable

option, but it is necessary to analyse the conditions, because if the contract is nullified and voided it is necessary to

determine under what conditions”).

103 La Patria, Cooperativistas amenazan con la toma de la empresa, press article, R-139.

104 See La Prensa, Empresa RBG Huanuni fue intervenida por Comibol, press article of 16 May 2002, R-140; El Diario,

Centro minero Huanuni vuelve a manos del Estado Boliviano, press article of 14 November 2002, R-141.

105 Letter from the Federación Regional de Cooperativas Mineras de Huanuni to President Quiroga Ramírez of 20 May

2002, R-142 (emphasis added) (Unofficial translation: “Also pursuant to the Agreement of 30/06/01, the Shared Risk

Contract of Huanuni be revised in accordance with item four and the aforementioned Contract be nullified and voided

and Huanuni Reverted to the State and subsequently be cooperativised, and Empresa Metalúrgica VINTO, given its key

role in Bolivian occidental economy and its being a security market for our concentrates, must be returned to the State”).

106 Agreement between the Comité de defensa del patrimonio orureño and the Executive regarding EMV of 7 June 2002,

R-143.

107 La Patria, Allied Deals negocia libremente transferencia de fundición Vinto, press article of 26 May 2002, R-144.

Page 34: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

29

y si COMIBOL podría ayudarlos en negociar esta venta con ellos. Para salir de

esta crisis es necesario involucrar a COMSUR y explorar la esta posibilidad.108

90. Ultimately, even though at least one other company had submitted a proposal to acquire the

Tin Smelter,109 an agreement was reached for the sale of this asset to Sánchez de Lozada’s

Comsur on 1 June 2002.110 The sale price was reportedly some US$ 6 million,111 i.e., less

than half the already low privatization price and only slightly more than half of Comsur’s

original offering price. Thus, Sánchez de Lozada ultimately secured the Tin Smelter at a

fraction of the price it was worth, and irrespective of the fact that, in early summer 2002, he

was in the midst of his second presidential campaign.

2.5 In 2005, At The Height Of Political Change In Bolivia, And When The Reversion Was

Foreseeable, Glencore International Acquired The Smelters And Mine Lease From

Former President Sánchez De Lozada

91. The particular social context in which operations at the Colquiri Mine were carried out before

the Privatization and the relation with the cooperativas required special attention and

significant resources from COMIBOL. Comsur nevertheless neglected this aspect of the

Colquiri Mine operation, which led to deep and increasing tensions between the

cooperativistas and the workers of the company (Section 2.5.1).

92. The poorly managed social relations at Colquiri encouraged the cooperativistas to further their

interest in taking over the Mine. This situation worsened, in particular, as a result of the

important changes in the State’s political landscape after October 2003, when President

Sánchez de Lozada was forced to resign from office and flee the country amidst political

unrest and country-wide protests (Section 2.5.2).

93. In this context, in 2005, Glencore International acquired the companies controlling the Assets

from Sánchez de Lozada, and then assigned them to Claimant without compensation

(Section 2.5.3). By this time, it was evident that the State would take action against the Assets

(Section 2.5.4), which would explain Glencore International’s decision not to invest in them

following their acquisition (Section 2.5.5).

108 RBG Case Report to the Minister of Economic Development and the President of COMIBOL of 15 May 2002, R-145,

p. 2 (Unofficial translation: “The liquidators are DESPERATE to find a buyer for the mines and are contemplating

offering Vinto and Huanuni to COMSUR. They asked me what would be the impact of this given the political situation

in the country with the elections and whether COMIBOL could help negotiate the sale with them. To exit this crisis it

is necessary to involve COMSUR and explore this possibility”). See also La Patria, Hasta el fin de mes se definirá futuro

de Fundición de Vinto y mina Huanuni, press article of 18 May 2002, R-146.

109 Letter from Expromin S.A. to the Minister of Economic Development and COMIBOL of 22 May 2002, R-147; La

Patria, Allied Deals negocia libremente transferencia de fundición Vinto, press article of 26 May 2002, R-144.

110 Letter from Grant Thornton to the Minister of Economic Development of 7 June 2002, R-148.

111 La Patria, Liquidador de Allied Deals pidió $US 6 millones por Vinto y Huanuni, press article of 2 June 2002, R-149;

La Prensa, Comsur será operadora de Vinto, es dueña del 51% de las acciones, press article of 6 June 2002, R-150.

Page 35: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

30

2.5.1 Comsur’s Operation Of The Colquiri Mine Lease Created Tensions With The Mining

Cooperativas And The Unions At Colquiri

94. By the time Glencore International acquired the Mine Lease from Sánchez de Lozada,

Comsur’s poor management of social relations at Colquiri had already created tensions

between the subsidiarios (now organized as cooperativistas) and the workers of the company.

95. Shortly after the execution of the Mine Lease, Comsur took over operations at Colquiri and

implemented significant changes in the way COMIBOL had operated the Mine. Both Mr

Cachi and Mr Mamani—who were working at Colquiri at the time—recall that Comsur

decided to lay off all former COMIBOL workers (including, notably, those belonging to the

local workers union).112 Comsur gradually replaced the former workers over the first years of

operations, never reaching the same number of employees—even though that would have

been necessary to properly operate the Mine and manage the relations of the company with

the cooperativistas.

96. Comsur’s strategic decision had a significant impact on community relations at Colquiri.

97. On the one hand, the population and economy of the town of Colquiri relied exclusively on

the Mine. Having been laid off, most of the former COMIBOL workers were forced to join

the ranks of the subsidiarios, who, by then, had decided to organize themselves in

cooperativas. Though a number of cooperativas operated at the Mine, the largest and most

organised ones were the Cooperativa 26 de Febrero (still operating inside the Mine today)

and the Cooperativa 21 de Diciembre (operating at the old tailings dam). In Mr Cachi’s

words:

Como consecuencia de este despido masivo, la mayoría de los trabajadores que no

fueron contratados por Comsur pasaron a engrosar las filas de los subsidiarios.

Esto alteró la proporción de los trabajadores de la Mina. Si antes de la

privatización había 1 subsidiario por cada 3 trabajadores, la proporción ahora era

la inversa. Ante este crecimiento, y para organizarnos colectivamente, decidimos

formar la Cooperativa 26 de Febrero. Hacia el año 2004, la Cooperativa ya

contaba con más de 600 socios. En el 2009, ya contábamos con 940 socios.113

98. On the other hand, given the lack of human resources, Comsur was keen to work with the

recently formed cooperativas in order to carry out specific tasks at the Mine. This situation

112 Cachi, ¶ 12; Mamani, ¶ 11.

113 Cachi, ¶¶ 13-14 (Unofficial translation: “As a result of this massive lay-off, the majority of workers not hired by Comsur

joined the lines of the subsidiarios. This altered the proportion of workers of the Mine. If before the privatization there

was 1 subsidiario for every 3 workers, the proportion was now reversed. Given this increase, and in order to organize

ourselves collectively, we decided to create the Cooperativa 26 de Febrero. Around 2004, the Cooperativa comprised

more than 600 partners. In 2009, we had 940 partners”).

Page 36: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

31

enabled the cooperativistas to better understand the operations of the company at the lower

levels of the Mine. As Mr Mamani recalls:

Por otra parte, y para evitar el pago de cargas laborales, Comsur decidió realizar

trabajos temporales de rehabilitación con los cooperativistas en los niveles

inferiores de la Mina que eran explotados al mismo tiempo por los trabajadores de

la empresa. Esto fue un error. Por un lado, al permitirles explotar al mismo tiempo

un mismo nivel, generó choques entre cooperativistas y empleados. Por otro lado,

consentir la entrada de personas ajenas a la empresa a los niveles inferiores de la

Mina permitió a los cooperativistas conocer en detalle su estructura e identificar

los turnos del personal de vigilancia y los horarios en los cuales no habría

empleados (normalmente entre los distintos turnos, cuando se realizan las

explosiones). Los cooperativistas también pudieron identificar accesos clandestinos

a los niveles inferiores (sobre todo a través de los ductos de ventilación).114

99. With a growing number of cooperativistas, and without the proper human resources to keep

them in check, controlling the Mine gradually became more difficult for Comsur over the

years. Moreover, both Mr Mamani and Mr Cachi confirm that, unlike COMIBOL, Comsur

handled its relations with the cooperativas in an erratic manner, which often benefited the

cooperativas. This made it easier for the latter to both (i) operate in new areas with Comsur’s

approval and (ii) illegally access areas in which the company’s employees worked.115

Tellingly, on 13 October 2000 (shortly after the execution of the Mine Lease116), COMIBOL

granted new areas of the Mine for exploitation to the Cooperativa 26 de Febrero (with

Comsur’s approval) and extended the validity of this agreement until 2018.117

114 Mamani, ¶ 12 (Unofficial translation: “On the other hand, and in order to avoid paying employment costs, Comsur

decided to carry out temporary rehabilitation works with the cooperativistas in the inferior levels of the Mine, exploited

at the same time by the company’s workers. This was a mistake. On the one hand, by allowing them to exploit at the

same time the same level, clashes were generated between cooperativistas and employees. On the other hand,

consenting to the entrance of persons outside the company to the lower levels of the Mine permitted the cooperativistas

to learn its structure in detail and identify the shifts of the surveillance personnel and the times at which there would be

no employees (normally between the shifts, when explosions are detonated). The cooperativistas could also identify

clandestine access ways to the lower levels (particularly through ventilation conducts)”).

115 Mamani, ¶ 15 (“Otro de los problemas ocasionados por la llegada de Comsur fue su falta de reacción ante la toma

paulatina, por parte de los cooperativistas, de nuevas partes de la Mina. En vez de defender sus intereses en la Mina (y

los intereses de sus trabajadores), como lo hacía la COMIBOL, Comsur comenzó a firmar acuerdos con la Cooperativa

26 de Febrero para ceder áreas que ya habían sido desarrolladas por los trabajadores. Estos acuerdos eran firmados

y negociados a nuestras espaldas y nunca eran socializados con los trabajadores de la empresa.”) (Unofficial

translation: “Another problem generated by the arrival of Comsur was its lack of reaction to the gradual takeover by

the cooperativistas of new areas of the Mine. Instead of defending its interests in the Mine (and those of its workers),

as done by COMIBOL, Comsur started to sign agreements with the Cooperativa 26 de Febrero to assign areas that had

already been developed by workers. These agreements were signed and negotiated behind our backs and were never

in consultation with the company’s workers”).

116 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11.

117 Public Deed No. 131/2000, lease agreement between Comibol and the Cooperativa 26 de febrero of 13 October 2000,

R-94, clause 5 (“A petición de la Cooperativa y en virtud de los planes y proyectos de explotación que tiene, COMIBOL

resuelve ampliar el plazo de vigencia del contrato hasta veinte años computables a partir de la fecha de suscripción del

contrato principal No. 50/98 de diez/cero siete/[98]”) (Unofficial translation: “Pursuant to the Cooperativa’s request

Page 37: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

32

100. The poorly managed community relations at Colquiri led to rising tensions between the

cooperativas and the mining workers. While some sectors of the community demanded

further “[c]oncesi[ones] de Área de trabajo para Organización de Cooperativa Minera para

trabajadores que viven en Colquiri sin fuente de trabajo,”118 the company workers were

outraged by the increasing demands of the cooperativistas. As put by Mr Mamani, Comsur

operated the Mine in a way that “generaba constantes enfrentamientos entre los empleados

de la mina y los cooperativistas, protestas por parte de la población civil e interrupciones en

la operación de la Mina.”119

101. In addition, under Comsur’s administration, the cooperativistas “bajaban a niveles inferiores

de la Mina para robar (lo que llamamos en quechua juquear) más y mejor mineral […].

Asimismo, ante la falta de seguridad de Comsur, los cooperativistas frecuentemente

robábamos materiales de los trabajadores (como explosivo anfo y barras de perforación), lo

que causaba el descontento de los trabajadores que, en algunos casos, debían reponer estos

materiales.”120

102. The intensity of the tensions made necessary the intervention of the State at various times.

For example, on 14 January 2004, officers from the Ministry of Mines and COMIBOL visited

Colquiri “ante el inminente conflicto de enfrentamiento entre trabajadores mineros de la

Empresa Minera Colquiri y los Extrabajadores de la misma Empresa Relocalizados y los

trabajadores de la Cooperativa Virgen del Carmen [i.e., a recently and non-registered

cooperativa].”121 The tensions were further deepened by claims that the Mine Lease may

have been awarded to Comsur in irregular circumstances.122 The intervention of the State in

this context ensured that a major conflict did not occur.

and in light of its exploitation plans and projects, COMIBOL decides to extend the contract term to twenty years as of

the date of execution of the main contract No. 50/98 of ten/zero seven/[98]”).

118 Operative votes of the Neighbourhood Associations of Colquiri of 30 June 2005, R-151 (Unofficial translation:

“[c]oncessi[ons] of working Areas to Mining Cooperative Organization for workers who live in Colquiri without a

source of work ”).

119 Mamani, ¶ 17 (Unofficial translation: “generated constant confrontations between the mine workers and

cooperativistas, protests by the civil population and interruptions in the Mine operations”).

120 Cachi, ¶¶ 20-21 (Unofficial translation: “descended to lower levels of the Mine to steal (what we call in Quechua

juquear) more and better ore […]. Likewise, given the lack of Comsur security, we cooperativistas frequently stole

materials from workers (like anfo explosive and drill rods), which made workers unhappy and, in some cases, made

them have to replace the materials”).

121 Internal Memorandum from COMIBOL to the Ministry of Mines of 23 January 2004, R-152, p. 1 (Unofficial translation:

“in light ofthe imminent confrontation between mining workers of Empresa Minera Colquiri and Former Relocated

Workers of the same company and workers of the Cooperativa Virgen del Carmen”).

122 Internal Memorandum from COMIBOL to the Ministry of Mines of 23 January 2004, R-152, p. 2 (“Que La Comisión

de Gobierno envié a la Delegada Presidencial Anticorrupción (ZARINA) lic. Lupe Cajias el Contrato de Arrendamiento

firmado entre COMSUR y la COMIBOL, para que esta instancia de Gobierno, emita su opinión respecto a los alcances

de dicho CONTRATO”) (Unofficial translation: “That the Government Commission send to the Anticorruption

Page 38: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

33

103. Likewise, on 16 April 2005, COMIBOL officers attended a meeting with cooperativistas and

Comsur directors in order to determine new working areas at the old tailings dam. The nature

of the cooperativistas’ demands clearly evidenced Comsur’s lack of control over the situation:

[E]n el lugar en compañía de los Directivos de la Cooperativa […] y socios de la

Cooperativa se recorre el sector solicitado 70 % del total de las colas,

aproximadamente 170 metros al sur de su anterior solicitud, en vista de esta

situación se realizó un levantamiento topográfico del sector, se encontró algunos

socios que vienen explotando las colas en forma rudimentaria, paralelamente se

reunieron en una asamblea de emergencia, a cuya finalización nos dan a conocer

sus resoluciones solicitando el 100% de las colas, indican que son oriundos de la

zona y otros argumentos, finalmente solicitan la continuidad de las negociaciones

en el lugar, caso contrario levantaran su cuarto intermedio.123

104. As discussed below, these demands would only increase—and, consequently, would lead to

conflicts at Colquiri—with the political and social changes that Bolivia underwent since 2003,

when then-President Sánchez de Lozada fled the country amidst protests and riots in response

to the policies he implemented which benefitted private investment in strategic sectors.

2.5.2 The Historic Social Changes That Led To The Empowerment Of New And Fundamental

Social Actors In Bolivia Further Impacted Operations At Colquiri

105. In its Statement of Claim, Claimant implies that, by the time Glencore International acquired

the Assets, Bolivia was a State open to new foreign private investment in the mining sector.124

This, however, is inaccurate. Comsur’s lack of proper management of community relations

at Colquiri was already encouraging the cooperativas to further their interests, including by

possibly taking over the Mine. In addition, the political transformations that the Bolivian

society had been undergoing since late 2003 empowered these organizations as a fundamental

social actor in the country. As Mr Mamani recalls:

[E]l sector cooperativista tomó mucha fuerza en el país al convertirse en uno de los

mayores grupos de oposición y protesta contra el gobierno del expresidente Sánchez

Presidential Delegate (ZARINA) attorney Lupe Cajias the Lease Contract concluded between COMSUR and

COMIBOL, so that this governmental entity may issue its opinion on the scope of the aforementioned CONTRACT”).

123 Letter from COMIBOL Technical Manager to the President of COMIBOL of 20 April 2005, R-153 (Unofficial

translation: “[T]here, accompanied by Directors of the Cooperative […] and partners of the Cooperativa, we went

through the requested sector 70% of the total amount of tailings, approximately 170 meters to the south from its previous

request, in view of this situation a topographic survey of the sector was carried out, several partners were found to

exploit the tailings in a rudimentary way, in parallel they met in an emergency assembly, after which they communicated

their resolutions requiring 100% of the tailings, they indicate that they are locals of this place and other arguments,

finally they require continuity in negotiations in the area, otherwise they will end the truce”).

124 Statement of Claim, ¶¶ 19-26.

Page 39: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

34

de Lozada por los planes de privatización y exportación de recursos naturales

(conocidos en Bolivia como la “Guerra del Gas”).125

106. As a matter of fact, on 6 August 2002—having taking full advantage, through Comsur, of the

Privatization policies put in place during his first tenure—Gonzalo Sánchez de Lozada

commenced his second term in office. Given that Bolivia has the largest reserves of natural

gas in the region, one of the main goals of his second government was to secure agreements

with foreign investors in order to export this natural resource on a large scale.

107. These policies were, however, met with countrywide social unrest and protests (especially, in

La Paz). This overwhelming opposition to Sánchez de Lozada “came as little surprise,”126

according to the press. Indeed, by the beginning of 2003, less than a year after coming to

power, the Sánchez de Lozada administration was actively opposed by the indigenous

communities across the country (led by Evo Morales’ MAS) and even lacked the support of

the military to carry out the investment plans in the gas sector.127 The press further reported

that the miners and cooperativas massively arrived in El Alto (near La Paz) to join other social

sectors in the protest.128 The support given by miners and cooperativas to the protests

explains, in great part, the scale of the conflict.129 As put by one academic study:

125 Mamani, ¶ 19 (Unofficial translation: “[T]he cooperatives sector gained considerable strength in the country when it

became one of the major opposition and protest groups against the government of former president Sánchez de Lozada

because of the plans for privatization and exporting natural resources (known as the ‘Gas War’ in Bolivia)”.

126 BBC News, Bolivia Gas Plans Trigger Unrest, press article of 16 September 2003, R-154.

127 The Economist, Highly Flammable, press article of 11 September 2003, R-155 (“Pacific LNG believes the project,

which involves spending $3.1 billion to build pipelines and a coastal terminal, is economical only if the gas goes through

a Chilean port, most probably Patillos […]. Government studies also prefer this route. But nationalists oppose it […].

Even if this obstacle is surmounted, left-leaning Indian leaders do not want the gas sold at all. Many believe that, if it

is, the United States and multinational oil companies will benefit from cheap gas at Bolivia's expense. And few trust the

government to spend gas revenues wisely. Indeed, few trust it on any issue. Despite reinforcing his coalition government

in August, President Gonzalo Sánchez de Lozada is still deeply unpopular. Some analysts think he may be toppled by

the armed forces if he opts for the Chilean gas route. With nervous politeness, Mr Sánchez has invited the military men

to carry out their own study of the project's potential benefits”).

128 VoltaireNet, 57 muertos en Masacre del 9 al 13 de octubre, press article of 14 October 2003, R-156; El País, Decenas

de tanques protegen el palacio presidencial de Bolivia ante las revueltas, press article of 15 October 2003, R-157 (“Los

vecinos, sin embargo, esperan con mucho temor la anunciada llegada de los indígenas de Achacachi, que marchaban

ayer hacia la capital con viejos fusiles Mauser, y la llegada de otros miles de colonos del norte de La Paz y trabajadores

de Oruro, que se acercan por la carretera troncal. Cerca de medio millar de mineros del centro productor de estaño,

Huanuni, lograron llegar a La Paz”) (Unofficial translation: “However, neighbours expect with great fear the

announced arrival of the indigenous community of Achacachi that was marching yesterday towards the capital carrying

old Mauser rifles, and the arrival of other thousands of colonists from the north of La Paz and workers from Oruro who

are approaching via the main highway. Around half a thousand miners from the tin production centre of Huanuni were

able to arrive to La Paz”).

129 La Patria, Libro refleja aporte de cooperativas mineras en la Guerra del Gas, press article of 24 November 2015, R-

158 (“Florencio Coca Cuizara, fue ejecutivo de la Fencomin, durante los años en que se suscitaron los conflictos por

la ‘Guerra del Gas’ (2002-2004), […]. ‘Es necesario hablar de cuáles fueron los roles de la minería estatal, la privada

y la cooperativizada que fue la que se enfrentó al gobierno de ese entonces, lo que menciono en el libro es la

participación de las cooperativas mineras en el proceso de cambio del Estado Plurinacional, es importante conocer

cuántos muertos tuvimos como sector y que esta información la conozca la niñez la juventud y todo el pueblo’, indicó

Coca”) (Unofficial translation: “Florencio Coca Cuizara was the manager of Fencomin during the years of the ‘Gas

War’ conflicts (2002-2004), […]. ‘It is necessary to speak about the roles of State, private and the cooperativa mining,

Page 40: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

35

La presencia en El Alto de La Paz de los 800 mineros de Huanuni y de más de 3.000

cooperativistas mineros, fue altamente significativa en momentos decisivos de la

insurrección popular que se desató en octubre de 2003 contra el gobierno de

Gonzalo Sánchez de Lozada y que tuvo su epicentro en esa ciudad del departamento

de La Paz. No sólo se notó la presencia, en toda la semana que duró el

levantamiento popular, de los pobladores de los barrios mineros de relocalizados,

principalmente de Santiago II, uno de los lugares donde se produjeron mayores

enfrentamientos con el ejército, sino de trabajadores mineros asalariados y

cooperativistas llegados desde Huanuni y otras minas. Así, octubre fue sin duda un

momento de revelación de “acumulaciones sociales previas”, aunque no sólo para

el sector minero, sino para el conjunto de los sectores populares en Bolivia […].130

108. The situation reached a critical point in October 2003, when thousands of protestors

congregated in La Paz demanding that Sánchez de Lozada abandon his natural gas export

project and resign from office. By 11 October, the Government’s attempts to quash the

mobilisation, including by installing blockades around the country, had left approximately 64

people dead and more than 400 wounded.131

109. As a result of these events, on 17 October 2003, Sánchez de Lozada was forced to resign from

office.132 That same day, he fled the country and sought asylum in the United States.133 To

date, Sánchez de Lozada has an outstanding summons to appear before the Bolivian Courts

which is the one that confronted the government of that time. In this book, I mention the participation of the mining

cooperatives in the change process of the Plurinational State. It is important to know how many people died in the

sector and to share this information with the children, the young and the entire population’, indicated Coca”).

130 M. Cajías de la Vega, “Crisis, Diáspora y Reconstitución de la Memoria Histórica de los Mineros Bolivianos” in Revista

de Estudios Transfronterizos, Vol. X, No. 2 (2010), R-159, 87 (Unofficial translation: “The presence in El Alto and La

Paz of 800 miners of Huanuni and more than 3,000 mining cooperativistas was very significant in decisive moments of

the popular uprising triggered in October 2003 against the government of Gonzalo Sánchez de Lozada and the epicentre

of which was in that city of the department of La Paz. Not only was the presence of residents of neighbourhoods of

relocated miners noted during the entire week of the popular uprising, in particular from Santiago II, one of the places

where major confrontations with the army took place – but also the presence of mining employees and cooperativistas

from Huanuni and other mines. Thus, October was undoubtedly a moment of revelation of ‘previous social

accumulations’, not only in the mining sector but also in all popular sectors in Bolivia”).

131 BBC Mundo, La guerra del gas se cobra otra vida, press article of 11 October 2003, R-160 (“Los manifestantes de la

ciudad de El Alto, cuyas protestas se iniciaron en oposición a la venta de gas natural, han comenzado a pedir también

la renuncia de Sánchez de Lozada, durante cuyo gobierno de algo más de 14 meses, las violentas protestas dejaron un

saldo de 68 muertos y unos 300 heridos”) (Unofficial translation: “Demonstrators of the city of El Alto, who originally

protested against the sale of natural gas, also started to demand Sánchez de Lozada’s resignation. These

demonstrations took place during Sánchez de Lozada’s administration, which lasted a bit more than 14 months, and the

violent protests left a toll of 68 dead and around 300 wounded”).

132 El País, 18 October 2003, Goni deja 134 muertos en 14 meses de gestión; El Deber, 16 February 2013, Por qué tantas

muertes en democracia?, press articles, R-12.

133 El Clarín, Bolivia:renunció el presidente Sánchez de Lozada, press article of 17 October 2003, R-161 (“El presidente

de Bolivia, Gonzalo Sánchez de Lozada, envió hoy al Congreso su renuncia al cargo, tras las protestas que causaron

77 muertos y unos 400 heridos. El mandatario, de 73 años, se encontraba esta noche en la ciudad sureña Santa Cruz

de la Sierra aparentemente para viajar a otro país, probablemente Estados Unidos”) (Unofficial translation: “The

President of Bolivia, Gonzalo Sánchez de Lozada, sent today his resignation to Congress, following the protests which

resulted in 77 dead and around 400 wounded people. The leader, aged 73, was in the southern city of Santa Cruz de la

Sierra that night, apparently to travel to another country, probably the United States”).

Page 41: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

36

for the tragic events that occurred during his second term in office, and Bolivia’s request for

extradition is still pending before the US authorities.134

110. That same day, 17 October 2003, the Bolivian Congress swore in Mr Carlos Mesa, Sánchez

de Lozada’s Vice-President. In his inaugural speech, Mr Mesa laid out a series of policies to

be implemented in order to overcome the social and political crisis created by Sánchez de

Lozada. Mr Mesa’s government agenda (which would later be known as La Agenda de

Octubre) prioritized, inter alia, the debate as to whether a new constituent assembly was to

be organized and promised that the Bolivian citizens would be free to decide the way in which

the natural resources of the State (including the mining sector) would be managed and

exploited. In Mr Mesa’s words:

Una Asamblea Constituyente ahora, quiere decir que vamos a discutir qué país

queremos y cuáles son las reglas del juego sobre las que este país va a funcionar

una vez que ese proceso se lleve adelante. Esto quiere decir que todos y cada uno

de nosotros, debemos llevar a la Asamblea Constituyente elementos centrales de

forma y de fondo que definirán temas esenciales sobre nuestros recursos naturales,

sobre la tierra, sobre la concepción de la participación democrática ciudadana,

sobre la estructura del funcionamiento de un mecanismo de representación como es

el Congreso Nacional, sobre todos los temas que nos importan.135

111. In this context, social sectors opposing private control of the strategic sectors of the State

(including the mining sector) were already prominent in 2003. In particular, by 2003,

President Morales’ MAS (whose agenda included “la realización de una Asamblea

Constituyente, a través de la convocatoria a asambleas populares comunales, provinciales.

etc. en que participarían organizaciones sociales con el fin de defender la soberanía y

refundar la nación“136) was already seen as one of the “nuevas fuerzas políticas

importantes”137 of the country. Likewise, as discussed above, the cooperativas became

critical social actors in Bolivian politics.138

134 See, for instance, La Razón, EEUU admite proceso de extradición de Goni, press article of 16 February 2016, R-13.

135 Speech of Mr Carlos Mesa Gibert before the Bolivian Congress of 17 October 2003, R-162, p. 3 (Unofficial translation:

“A Constituent Assembly now means that we will discuss about what country we want and what rules will govern the

functioning of this country as this process goes on. This means that each and every one of us, must provide the

Constituent Assembly with the main formal and substantial elements that will define the essential themes regarding our

natural resources, about the land, about the conception of democratic citizen participation, about the operational

structure of a representation mechanism such as the National Congress, about all the issues that matter to us”).

136 Fundación Boliviana para la Capacitación Democrática y la Investigación, “Opiniones y análisis sobre las elecciones

presidenciales de 2002”, 2002, R-163, p. 58 (Unofficial translation: “carrying out a Constituent Assembly, by convening

popular assemblies at the communal, provicial etc. levels in which social organizations would participate in order to

defend sovereignty and refound the nation”).

137 Fundación Boliviana para la Capacitación Democrática y la Investigación, “Opiniones y análisis sobre las elecciones

presidenciales de 2002”, 2002, R-163, p. 49 (Unofficial translation: “new important political forces”).

138 M. Cajías de la Vega, “Crisis, Diáspora y Reconstitución de la Memoria Histórica de los Mineros Bolivianos” in Revista

de Estudios Transfronterizos, Vol. X, No. 2 (2010), R-159; VoltaireNet, 57 muertos en Masacre del 9 al 13 de octubre,

Page 42: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

37

112. President Mesa’s government advanced a policy of recovering State control of strategic

sectors.139 Yet his government was temporary. After Mesa’s resignation in 2005 (amid

protests against private investment in the hydrocarbons sector),140 the interim government of

Eduardo Rodríguez organized presidential elections that same year. The political programme

of MAS candidate Evo Morales, widely known in Bolivia since the beginning of the decade,

openly called for a constituent assembly141 and for the participation of the State in strategic

sectors. Concretely, in regard to the mining sector, and in line with the policies espoused

since the immediately prior elections,142 MAS sought to “[r]efundar la Corporación Minera

de Bolivia (COMIBOL), como empresa estatal con autonomía de gestión y de derecho

público, con capacidad para convertirse en actor principal en la actividad productiva del

sector.”143

113. On 19 December 2005, with an overwhelming majority of the votes, Evo Morales was elected

President of Bolivia.144 Important developments in Bolivian politics followed this event:

114. On the one hand, in June 2006, the new government published a national development plan.

As laid down in MAS’ political programme, the national development plan stressed the

importance of “un nuevo rol del Estado donde participe directamente en proyectos

estratégicos, promueva la actividad productiva de las organizaciones sociales y

comunitarias, garantice el desarrollo de la iniciativa privada, y realice un mejor uso y destino

press article of 14 October 2003, R-156; El País, Decenas de tanques protegen el palacio presidencial de Bolivia ante

las revueltas, press article of 15 October 2003, R-157 (“Los vecinos, sin embargo, esperan con mucho temor la

anunciada llegada de los indígenas de Achacachi, que marchaban ayer hacia la capital con viejos fusiles Mauser, y la

llegada de otros miles de colonos del norte de La Paz y trabajadores de Oruro, que se acercan por la carretera troncal.

Cerca de medio millar de mineros del centro productor de estaño, Huanuni, lograron llegar a La Paz”) (Unofficial

translation: “However, neighbours expect with great fear the announced arrival of the indigenous community of

Achacachi that was marching yesterday towards the capital carrying old Mauser rifles, and the arrival of other

thousands of colonists from the north of La Paz and workers from Oruro who are approaching via the main highway.

Around half a thousand miners from the tin production centre of Huanuni were able to arrive to La Paz”).

139 See, for instance, La Nación, Anuncian un amplio triunfo del sí en el referéndum sobre el gas en Bolivia, press article

of 18 July 2004, R-164.

140 El Mundo, Presidente de Bolivia presenta su renuncia ante su incapacidad para contener la ola de protestas, press

article of 7 June 2005, R-165.

141 Political Program of Movimiento Al Socialismo of November 2005, R-166, p. 54 (“El MAS propone la Asamblea

Popular Constituyente formada por representantes de las organizaciones sociales que se reúnan con el mandato expreso

de elaborar una Constitución del pueblo y para el pueblo de Bolivia”) (Unofficial translation: “MAS proposes a

Constituent Popular Assembly formed by representatives of the social organisations to meet with the express mandate

of elaborating a Constitution by the people and for the people of Bolivia”).

142 Fundación Boliviana para la Capacitación Democrática y la Investigación, “Opiniones y análisis sobre las elecciones

presidenciales de 2002”, 2002, R-163, p. 58.

143 Political Program of Movimiento Al Socialismo of November 2005, R-166, p. 19 (Unofficial translation: “[r]efound the

Bolivian Mining Corporation (COMIBOL), as a State company of public law with administrative autonomy, with the

capacity to become the main actor of the production activity of the sector”).

144 BBC Mundo, Morales se declara ganador, press article of 19 December 2005, R-167; Georgetown University, Results

of the Presidential Election held on December 18, 2005, R-5.

Page 43: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

38

del excedente económico.”145 The development plan further aimed to put an end to the effects

of the Privatization in the country.146

115. The national development plan was later enacted by means of Supreme Decree 29.272

of 2007. This norm confirmed “[e]l rol activo del Estado” in the mining sector and the

promotion of “una actividad minera planificada, racional, inclusiva, moderna, sistematizada,

y socialmente aceptable, en la que participen de manera armónica e integral el sector público,

pueblos indígenas, originarios, comunidades campesinas y los otros subsectores: grande,

mediano, chico y cooperativo.”147

116. On the other hand, in August 2006, pursuant to one of the fundamental points of Mesa’s

Agenda de Octubre, President Morales called for elections of a constituent assembly.148 The

new constitution was enacted on 7 February 2009.149 The Constitution envisioned the State

as assuming “el control y la dirección sobre la exploración, explotación, industrialización,

transporte y comercialización de los recursos naturales estratégicos a través de entidades

públicas, cooperativas o comunitarias.”150 In addition, as Claimant mentions, the new

Constitution mandated the renegotiation of all existing rights over mining concessions.151

117. In this context of significant political changes in Bolivia, as discussed in the section below,

Glencore International decided to acquire the Assets from the fleeing Sánchez de Lozada and

assign them to Claimant without compensation.

118. In sum, by early 2005, “[t]he overthrow of the main champion of neo-liberal economics in

2003, the rise of Evo Morales, the palpable shift of politics to the left throughout the country

and the decline of the traditional party structure has left the business environment clouded

145 Bolivia’s National Development Plan of 2006, R-168, p. 105 (Unofficial translation: “a new State role, in which it

directly participates in strategic projects, promotes the production activity of social and community organizations,

guarantees the development of private initiative, and gives a better use and destination to the economic surplus”).

146 Bolivia’s National Development Plan of 2006, R-168, p. 9.

147 Supreme Decree No. 29272 of 12 September 2007, R-169, p. 160 (Unofficial translation: “[t]he State’s active role [in

the mining sector and the promotion of] a mining activity which is planned, rational, inclusive, modern, systemised and

socially acceptable, in which may participate in a harminosed and wholesome manner the public sector, indigenous

communities, rural communities and other subsectors: large, medium, small and cooperative”).

148 El Universo, Bolivia inaugura Asamblea Constituyente que pretende refundar el país, press article of 6 August 2006,

R-170; Law of 6 March 2006, R-6.

149 Constitution of Bolivia of 7 February 2009, C-95.

150 Constitution of Bolivia of 7 February 2009, C-95, Article 351 (I) (emphasis added) (Unofficial translation: “the control

and direction over the exploration, exploitation, industrialization, transport and sale of strategic natural resources

through public, cooperative or community entities”).

151 Statement of Claim, ¶ 76 (“A new Constitution came into effect in February 2009 (the 2009 Constitution), mandating

the renegotiation of existing mining concessions”).

Page 44: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

39

with uncertainty.”152 It was therefore foreseeable that the State could take action against

businesses in the mining sector, and, in particular, the Assets.

119. Glencore International decided to acquire the Assets nonetheless.

2.5.3 Glencore International Purchased The Assets From Sánchez De Lozada And Assigned

Them To Glencore Bermuda Without Compensation

120. Having resigned from office and fled Bolivia in October 2003, Sánchez de Lozada sought to

divest some of the assets that he held through Comsur. For this purpose, he retained newly-

incorporated Argent Partners Limited153 to assist with securing bids for the subsidiaries and

affiliates of Andean Resources S.A. 154 This is how, ultimately, Glencore International (and

not Claimant155) came to acquire the Assets.

121. It bears recalling that Sánchez de Lozada was, reportedly, a close friend of Marc Rich, the

founder of Glencore International. Mr Rich had left the US in the early 1980s, and would

never return to face trial on charges of fraud. In order to avoid extradition, Mr Rich acquired

Bolivian citizenship in 1983. 156 Thereafter, throughout the 1980s and 1990s, Mr Rich carried

out business in Bolivia through various wholly-owned Swiss companies, and enjoyed a

privileged relationship with the executive and COMIBOL.

122. At the time of Glencore International’s acquisition, on the one hand, Andean Resources fully

owned Minera S.A.157 In turn, Minera fully owned Panamanian companies Iris Mines and

Metals S.A., Shattuck Trading & Co. Inc. and Kempsey S.A.,158 which, together, held 100%

152 Business Monitor International, Risk Summary - Bolivia, 14 January 2005, R-171.

153 Argent Partners Limited is not a “leading international advisory firm,” as indicated by Claimant. At the time, it was a

single-partner organization, founded in 2002. See Argent Partners Webpage, “Partners”, available at

http://www.argentpartners.com/partners, R-172.

154 Process Letter from Argent Partners (Mr Simkin) to Glencore International (Mr Eskdale) of 30 April 2004, C-62, pp. 1-

2 (“Andean Resources S.A. (“ARSA” or the “Company”) has retained Argent Partners Limited […] to assist it in

exploring its strategic and financial alternatives in connection with a possible negotiated transaction involving the

Company’s subsidiaries and affiliates, including the Company’s interest in Minera S.A.”).

155 See Statement of Claim, ¶¶ 34-36, referring to Glencore, and not Glencore Bermuda, as the party participating in the

bid for Sánchez de Lozada’s companies. See also Section 4.1 below.

156 Supreme Resolution No. 198045 of 27 May 1983, R-173; House Report No. 454, “Justice Undone - Clemency Decisions

in Clinton White House”, US Congressional Serial Set (Serial No. 14778), 107th Congress, 2nd session, R-174, p. 124.

157 Minera S.A., Minutes of Shareholders’ Meeting of 23 February 2016, R-175, p. 2.

158 Certificate of the Secretary of Iris Mines and Metals SA of 19 May 2011, C-14; Certificate of the Secretary of Shattuck

Trading Co Inc of 1 February 2012, C-15.

Page 45: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

40

of Comsur’s shares.159 In addition to being the chairman of Minera, Sánchez de Lozada’s

(indirect) ownership and control of this corporate structure was a matter of public record.160

123. On the other hand, Comsur held 51% of the shares of Colquiri S.A.,161 whilst the latter

company owned the Colquiri Mine lease and the Antimony Smelter, and held a 99.97%

interest in Vinto, which owned in turn the Tin Smelter.162 This ownership chain is represented

schematically below:

159 Companía Minera del Sur S.A., Minutes of Extraordinary Shareholders’ Meeting of 25 February 2005, R-176; IFC,

Summary of Project Information: Sinchi Wayra of 18 April 2017, R-177 (“Compania Minera Del Sur S.A. (“Comsur”)

is an unlisted Bolivian company 100% owned by Panamanian company Iris Mines and Metal S.A. (“Iris”). Iris is in

turn owned by Minera S.A. (“Minera”), a Panamanian company which is the sponsor and guarantor of the project.

Both Iris and Minera are unlisted.”). See also Nueva Economía, Una poderosa minera activa de bolsa, press article of

13 July 2008, R-178.

160 Bloomberg, Company overview of Minera S.A. of 7 December 2017, R-179. See e.g. Bolivia.com, Goni vendió

COMSUR, press article of 5 February 2005, R-14; La Razón, Goni sigue siendo un rey de la minería, press article of 14

October 2013, R-180. See also Orvana announces commencement of development at Don Mario Gold Project and

executive appointments, press release of 4 March 2002, R-181, p. 2 (“Mr. de Lozada has had almost 40 years of

experience as a mining entrepreneur in Bolivia and Argentina. Mr. de Lozada is active in Bolivian politics. He is the

controlling shareholder of Minera S.A., a holding company with extensive mining, processing and smelting assets in

Bolivia and Argentina. Comsur is a subsidiary of Minera S.A.”).

161 The remaining 49% interest was held by CDC until March 2006. Put Notice from Actis (on behalf of CDC) to Glencore

International of 21 March 2006, C-67; Statement of Claim, ¶ 38.

162 See Share register of Colquiri SA, C-17; Share register of Complejo Metalúrgico Vinto, C-18.

Page 46: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

41

124. According to Claimant, Glencore International purchased the Panamanian companies

described above between 30 January and 2 March 2005, and gained full indirect ownership of

the Mine and Smelters by 2 March 2005. 163

125. Claimant submits no evidence of the amount Glencore International paid in the transactions

described above. In fact, it submits almost no evidence at all regarding the details of a

transaction that remains shrouded in mystery. However, the deal is rumoured to have hovered

around some US$ 220 million for the entirety of the companies and assets owned by

Minera.164

126. Compounding the mystery, a longtime close associate of Sánchez de Lozada, Jorge Szasz

Pianta,165 remained on the boards of Comsur,166 Colquiri,167 and Vinto168 after the supposed

sale to Glencore, even while Glencore International replaced the remaining board members.

We suspect that he was acting as a proxy to protect Sánchez de Lozada’s remaining rights in

Comsur, Colquiri, and Vinto, per the terms of the sales contracts between Minera and

Glencore International (which have deliberately been withheld). We reserve all our rights in

this regard.

127. Because of the mysteries surrounding Sánchez de Lozada’s transaction with Glencore

International (as well as the privatization of the Assets), Bolivia has sought further

information in the possession of Sánchez de Lozada through a 28 U.S. Code § 1782 action

before the U.S. federal courts.169 It informed Claimant of this action on 12 December 2017.

Because Sánchez de Lozada is neither a party to this arbitration nor under the control of any

party, the unique information he possesses about the transaction would otherwise be

unavailable to inform the Tribunal’s analysis.

163 Statement of Claim, ¶ 36.

164 In September 2017, discovery was sought against law firm Gibson, Dunn & Crutcher LLP in connection with its

representation of the sellers in the transaction between COMSUR and Glencore. The petitioners reported the value of

the deal to be of approximately US$ 220 million. See United States District Court, Southern District of New York, In

re application of Julio Miguel Orlandini-Agreda and Compañía Minera Orlandini Ltda. for an order directing discovery

from Gibson, Dunn & Crutcher LLP of 25 September 2017, R-182, ¶ 9.

165 Mr. Szasz Pianta has been a member of Sánchez de Lozada’s circle at least since 1989. Certificate of Election of New

Directors and Board Members of Kaydon Enterprises S.A. of 26 June 1989, R-183, p. 4; Companía Minera San Jose

S.A. Certificate of Election of New Directors and Board Members of 22 May 1992, R-184, p. 4.

166 Minutes of Sinchi Wayra S.A. Shareholders’ Meeting of 25 February 2010, R-185, p. 4.

167 Minutes of Colquiri S.A. Shareholders' Meeting of 25 February 2010, R-186, p. 5.

168 Minutes of Shareholders' Meeting of Complejo Metalúrgico Vinto S.A. of 11 March 2010, R-187, p. 4.

169 In Re: Application of the Plurinational State of Bolivia for an Order directing Discovery from Gonzalo Sanchez De

Lozada Y Sanchez De Bustamante Pursuant to 28 U.S.C. § 1782, United States District Court for the Eastern District of

Virginia, No. 1:17-mc-00030, 6 December 2017.

Page 47: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

42

128. Immediately after completing the transactions described above, Glencore International

proceeded to assign “all of the rights, assets and interest acquired from the purchase to its

wholly-owned subsidiary Glencore Bermuda.”170

129. Claimant does not submit any evidence that consideration was paid in exchange for this

assignment. Nor does any other evidence on the record suggest that the assignment would

have been anything else other than gratuitous. In particular, the agreement through which the

shares were transferred by Glencore International to Claimant displays no payment or

consideration of any sort from the latter in exchange for the assignment.171

130. In this connection, on 16 February 2005, COMIBOL wrote to the CEO of Comsur, Jaime

Urjel Dalence, and expressed its unease regarding the transactions that Glencore International

was engaging in:

De conformidad con las publicaciones en la prensa, COMIBOL ha tomado

conocimiento que la totalidad de las acciones de COMSUR han sido transferidas a

la GLENCORE, aspecto que nos coloca en una posición de alerta y preocupación

por este tipo de transacciones, que deberían ser comunicadas oficialmente a

COMIBOL en el marco de los contratos de Riesgo Compartido y Arrendamiento

existentes con la Compañía Minera del Sur (COMSUR).172

131. The response was swift and patronizing: the object of the transfer had not been Comsur itself,

but foreign companies “que no afectan de manera alguna a Comsur o a sus relaciones

contractantes.”173

132. Thereafter, between September and October 2005, presumably in an attempt to smooth over

the relationship with COMIBOL, negotiations were carried out between COMIBOL, Comsur

and Colquiri “con objeto de considerar mejoras en los ingresos económicos para COMIBOL,

en relación al contrato de Riesgo Compartido de la mina Bolívar, y los contratos de

arrendamiento de las minas Porco y Colquiri.”174 Likewise, in March 2006, further

170 Statement of Claim, ¶ 37, 314; Notice of Assignment from Glencore International to CDC of 23 May 2005, C-66.

171 Assignment and Assumption Agreements between Glencore International and Glencore Bermuda of 7 March 2005, C-

64.

172 Letter from COMIBOL to Comsur (Sinchi Wayra) of 16 February 2005, R-188, p. 1 (Unofficial translation: “In

accordance with publications in the press, COMIBOL has become aware that the entirety of COMSUR’s shares has

been transferred to Glencore, situation which causes us alarm and concern over this type of transactions which should

be officially communicated to COMIBOL in the framework of the Shared Risk and Lease contracts concluded with

Compañía Minera (COMSUR)”).

173 Letter from Comsur (Sinchi Wayra) to COMIBOL of 17 February 2005, R-189, p. 1 (Unofficial translation: “which do

not affect in any way Comsur or its contracting relations”).

174 Minutes of the conclusion of the meetings held between COMIBOL, COMSUR and Compañía Minera Colquiri S.A. of

11 October 2005, R-190 (Unofficial translation: “with the aim of considering improvements in COMIBOL’s economic

benefits, in relation to the Shared Risk contract of the Bolívar mine, and the lease contracts of the Porco and Colquiri

Page 48: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

43

negotiations were carried out between COMIBOL and Colquiri “para que se efectúe una

revisión y renegociación del Contrato de Arrendamiento del Centro Minero Colquiri suscrito

con la Compañía Minera Colquiri S.A. buscando una mejor participación económica para la

[COMIBOL].”175

133. Such negotiations belie Claimant’s assertion that “the Ministry of Mining and Metallurgy […]

expressly wrote to Glencore’s representatives to express its ‘favorable predisposition towards

the development of new investments in the mining sector’.”176 As a matter of fact, far from

amounting to the warm welcome that Claimant describes, the letter in question simply

conveyed to Glencore that the administration was considering modifications to the fiscal

regime applicable to the mining sector:

Sobre el particular, deseo manifestarle que el Viceministerio a mi cargo tiene una

predisposición favorable a que se concreten nuevas inversiones en el sector minero.

Sin embargo, y con el ánimo de configurar adecuadamente el contexto de política

minera que actualmente está llevando adelante el Gobierno de Bolivia, debo

comunicarle que uno de los temas que es objeto de análisis y que con seguridad

conducirá a la realización de ajustes es el régimen impositivo minero, bajo la

concepción de que el mecanismo más idóneo para brindar seguridad jurídica a las

inversiones mineras es posibilitar que las regiones productoras perciban de forma

justa y directa los beneficios que la actividad minera otorga.177

134. A second letter included in the same document cited by Claimant confirms that, instead of

welcoming Glencore International, the Bolivian government was simply communicating to it

that the assets it was acquiring would be the object of legislative and contractual

modifications:

Es de conocimiento nuestro que su Empresa se encuentra en negociaciones de las

acciones de COMSUR, por lo que consideramos importante hacer conocer a ustedes

que COMIBOL, tiene firmado con esa empresa un contrato de riesgo compartido

(Joint Venture), en la mina de su propiedad denominada “Bolivar”, asimismo 2

contratos de arrendamiento en las localidades de Colquiri y Porco.

mines”). See also COMIBOL Board Resolution No. 3285/2005 of 1 November 2005, R-191; COMIBOL Board

Resolution No. 3387/2006 of 28 March 2006, R-192.

175 COMIBOL Board Resolution No. 3387/2006 of 28 March 2006, R-192 (Unofficial translation: “in order to revise and

renegotiate the Lease Contract for the Colquiri Mining Centre concluded with Compañía Minera Colquiri S.A. seeking

a better economic return [for COMIBOL]”).

176 Statement of Claim, ¶ 35; Letter from the Vice Minister of Mining to Glencore of 17 January 2005, C-63.

177 Letter from the Vice Minister of Mining to Glencore of 17 January 2005, C-63, p. 1 (emphasis added) (Unofficial

translation: “Regarding this issue, I wish to inform you that the Vice-ministry under my responsibility is favourable to

the realisation of new investments in the mining sector. However, and with the aim of correctly presenting the context

of the mining policy which is currently being promoted by the Bolivian Government, I must inform you that one of the

issues that is being examined and that will certainly lead to the implementation of adjustments, is the mining fiscal

regime, under the notion that the most suitable mechanism to provide legal security to mining investments is to allow

producing regions to access, in a just and direct way, the profits resulting from the mining activity”).

Page 49: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

44

Es importante hacer conocer que en cumplimento de las cláusulas contractuales,

tiene que ser de conocimiento de COMIBOL cualquier modificación de la

personería jurídica y/o paquete accionario de dicha empresa.

Por otro lado les informamos que COMIBOL en un plazo corto se verá en la

necesidad de plantear la revisión de los mencionados contratos.178

135. Thus, Claimant’s depiction of the facts does not correspond to the reality of Glencore

International’s arrival in Bolivia. In fact, Glencore International’s attempts to smooth things

over in Bolivia were doomed to fail from the start and the company must have known it at the

time – which is why the negotiations were commenced in the first place.

2.5.4 Glencore International Assigned The Assets To Glencore Bermuda When It Was Highly

Likely That The State Would Take Action Against The Assets

136. It was evident when Glencore International made its purchase that the long and troubled

history of such Assets would inevitably prompt the State to take action against them. This

prospect was not only highly likely but in fact specifically foreseen by Glencore International.

It was against this background that Glencore International transferred the Assets to Glencore

Bermuda.

137. As previously explained, after concluding the transaction to acquire the Assets, Glencore

International assigned “all of the rights, assets and interest acquired from the purchase to its

wholly-owned subsidiary Glencore Bermuda.”179 Glencore Bermuda was incorporated in a

jurisdiction subject to the Treaty that Claimant has invoked in the present dispute.

138. Recognizing the high risk of a dispute, we understand that Glencore International then

proceeded to take out political risk insurance against precisely the sort of actions that Claimant

now alleges Bolivia took. We understand that it obtained insurance from a syndicate led by

Lloyd’s for the Tin Smelter and suspect it likely obtained similar insurance for the Antimony

Smelter and Colquiri Mine Lease.

139. Glencore International did so as part of its general policy of obtaining insurance whenever it

considered that political risk was significant. As Glencore International’s 2011 prospectus

reveals, “Glencore [sought] to remain diversified and where possible to obtain political risk

178 Letter from the Vice Minister of Mining to Glencore of 17 January 2005, C-63, p. 2 (Unofficial translation: “It has come

to our knowledge that your Company is negotiating [regarding] COMSUR’s shares. This is why we consider it

important to inform you that COMIBOL has concluded a shared risk contract (Joint Venture) with that company

regarding its mine named “Bolivar”, as well as 2 lease contracts in the towns of Colquiri and Porco. It is important to

inform you that pursuant to the contractual provisions, COMIBOL must be informed of any modification in the legal

status and/or shareholding structure of the aforementioned company. On the other hand, we inform you that COMIBOL

will shortly be compelled to propose the revision of the aforementioned contracts”).

179 Statement of Claim, ¶¶ 37, 314; Notice of Assignment from Glencore International to CDC of 23 May 2005, C-66.

Page 50: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

45

insurance from creditworthy financial institutions in situations where Glencore believes that

obtaining such insurance is financially prudent.”180 From Glencore International’s

perspective, Bolivia was precisely such a situation.

140. As these actions reflected, Glencore International confronted strong indications by early 2005

that the Assets were likely to become the subject of a dispute with Bolivia.

141. First, concerns over the legality of the privatization of the Tin Smelter had been highly

publicized since the privatization of the Smelter and more acutely so since 2001-2002,

following Sánchez de Lozada’s acquisition thereof.

142. As discussed in Section 2.4.1 above, following the adjudication of the sales contract to Allied

Deals, local organizations and unions in Oruro181 as well as members of the Bolivian

Parliament182 called for investigations to be carried out prior to the conclusion of the sale

purchase agreement. Indeed, everything suggested that the price to be paid in consideration

for the Tin Smelter was inexplicably low. The Banzer Suárez administration paid no mind to

such calls for investigation and proceeded to validate the tender process and conclude the sale.

143. Thereafter, as discussed in Section 2.4.2 above, the public outrage did not diminish. The press

reported that members of the Bolivian Parliament, including MAS members, had requested

180 Prospectus of Glencore International plc of 3 May 2011, R-193, p. 57.

181 Statement of the Oruro Civic Committee, R-122 (“TERCERO.- Solicitar al Gobierno la inmediata realización de

gestiones para que el daño económico infringido al Departamento de Oruro sea revertido, recuperándose el valor total

de los materiales y concentrados obsequiados al Consorcio ALLIED DEALS.”) (Unofficial translation: “THIRD.-

Request the Government to immediately take the necessary measures so that the economic harm caused to the

Department of Oruro can be reverted, thus recovering the total value of materials and concentrate gifted to the

Consortium ALLIED DEALS”). See, also, Letter from the Oruro Central Obrera to President Banzer Suárez of 23 May

2001, R-126 (“la clase trabajadora y lodos los sectores del pueblo de Oruro, nos encontramos agobiados por el hambre

y la miseria que reina en nuestro sociedad debido a que nuestro patrimonio y que constituía FUENTE DE TRABAJO,

ha sido enajenado ilegalmente y en un monto absolutamente exiguo constituyendo un engaño en la venta del Complejo

Metalúrgico de Vinto a la Empresa [Allied Deals]”) (Unofficial translation: “the working class and all sectors of the

people of Oruro are overwhelmed by the hunger and misery that reigns in our society given that our asset, which

constituted a SOURCE OF WORK, has been transferred illegally and for a completely inadequate amount, which

amounts to fraud in the sale of Complejo Metalúrgico de Vinto to the company [Allied Deals]”).

182 Letter from Representative Pedro Rubín de Celis to the Contralor General de la República of 10 May 2001, R-124, p.

2 (“En el numeral 5 del documento denominado ‘acta de Entendimiento’ en fecha de 2 de marzo de 2000 por los

Presidentes de Vinto y COMIBOL, por una parte, y por el representante de ALLIED DEALS PLC dice textualmente:

‘la vendedora depositará, a la brevedad posible en sus almacenes – estaño e incluir estaño metálico dentro de los ítems

ofertados en la venta de la Fundidora’. De esta manera, los compradores obtuvieron en forma fraudulenta el dinero

para comprar la propia fundición en forma de estaño en circuito, en concentrados y en metálico por un valor de [US$

11,477,539]. A ello habrá que añadir las 500 toneladas de estaño metálico entregadas a favor de la compradora como

respaldo al valor ajustado del material en circuito y al valor ajustado de los activos fijos”) (Unofficial translation: “Item

5 of the document named ‘minutes of Understanding’ of 2 March 2000 [executed] by the Presidents of Vinto and

COMIBOL, on the one hand, and by the representative of ALLIED DEALS PLC, literally says: ‘the seller will deposit

shortly in its warehouses – tin and include metallic tin within the items offered in the sale of the Smelter. This way, the

buyers obtained fraudulently the money to buy the smelter itself in the form of pipeline tin, in concentrates and metal

for the amount of [US$ 11,477,539]. To this must be added 500 tons of metallic tin delivered in favor of the buyer as a

guarantee of the adjusted value of the pipeline material and the adjusted value of fixed assets”). See, also, Formal

complaint by Representative Pedro Rubín de Celis against Minister Carlos Saavedra Bruno, R-125.

Page 51: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

46

“una reversión de la empresa metalúrgica Vinto, a favor del Estado”183 (a request backed by

cooperativistas from Huanuni,184 also controlled at the time by RGB185).

144. Second, the social and political transformations that took place in Bolivia after Sánchez de

Lozada’s resignation in October 2003, described in Section 2.5.2 above, also made State

measures against the Assets likely.

145. In fact, the new policies of the Bolivian Government envisioned the State as “responsable de

las riquezas mineralógicas que se encuentren en el suelo y subsuelo cualquiera sea su origen

y su aplicación será regulada por la ley”186 and aimed to end the perverse effect the

Privatization and the Capitalization had had on the country. Put differently, as a result of the

events of October 2003, the Government actively sought to dismantle the economic premises

under which the State had functioned for over two decades.187 This policy had significant

implications in the way relations with investors in the mining sector would unfold.

146. One, it was public knowledge since 2001 that the Tin Smelter had been privatized in dubious

circumstances. It was therefore to be expected that the State would decide to redress the

irregularities that led to this privatization (expressly mentioned in the Government’s

Development Plan188), especially if such irregularities had caused economic harm to the State.

147. Two, the conception of an active State in the mining sector was incompatible with an inactive

Antimony Smelter in the hands of private investors. As explained in Section 2.6.2 below,

183 DDHH pide que el Estado intervenga, Brigada Parlamentaria pide preservar fuentes de trabajo, press article, R-137

(Unofficial translation: “a reversion of the Vinto metallurgical company in favour of the State”).

184 See, for instance, La Patria, Cooperativistas amenazan con la toma de la empresa, press article, R-139.

185 Letter from the Federación Regional de Cooperativas Mineras de Huanuni to President Quiroga Ramírez of 20 May

2002, R-142.

186 Constitution of Bolivia of 7 February 2009, C-95, article 369 (Unofficial translation: “responsible for the mineral

resources located in the soil and sub-soil irrespective of their origin and its application will be regulated by law”).

187 Bolivia’s National Development Plan of 2006, R-168, p. 4 (“El objetivo principal está centrado, por lo tanto, en la

supresión de las causas que originan la desigualdad y la exclusión social en el país, lo que significa cambiar el patrón

primario exportador y los fundamentos del colonialismo y el neoliberalismo que lo sustentan. Es decir, desmontar, no

sólo los dispositivos económicos, sino también los políticos y culturales, coloniales y neoliberales, erigidos por la

cultura dominante, que se encuentran diseminados en los intersticios más profundos de la organización del Estado y

también en la mente de las personas a través de la práctica social individual en detrimento de la solidaridad y la

complementariedad. El cambio del patrón primario exportador es, por lo tanto, una condición imprescindible para

revertir la desigualdad y la exclusión de la población indígena, urbana y rural; erradicar la pobreza en el país y

desmontar tales dispositivos”) (Unofficial translation: “As a result, the main objective is focused on eliminating the

causes that generate inequality and social exclusion in the country, which means changing the primary pattern of exports

and the foundations of colonialism and neoliberalism that support it. That is to say, to dismantle not only the economic

mechanisms but also the political and cultural, colonial and neoliberal ones, erected by the dominant culture, that are

scattered in the most deep interstices of the State’s organization and also in the mind of the people through individual

social practice, to the detriment of solidarity and complementarity. The change in the primary pattern of exports is thus

an essential requirement to revert the inequality and exclusion of indigenous, urban and rural communities, to eradicate

poverty in the country and dismantle such mechanisms”).

188 Bolivia’s National Development Plan of 2006, R-168, p. 232.

Page 52: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

47

under the new position and function of the State in the mining sector, such situation was

simply untenable. In addition, concerns over irregularities in the privatization of the

Antimony Smelter were public knowledge since, at least, 2000.189

148. Three, the new Constitution and mining policies of the State empowered and emboldened the

cooperativas as crucial actors of the mining sector in Bolivia (as a matter of fact, as per the

new policies of the Government, the State would carry out “una actividad minera planificada

[…] socialmente aceptable, en la que participen de manera armónica e integral el sector

público, pueblos indígenas, originarios, comunidades campesinas y los otros subsectores:

grande, mediano, chico y cooperativo”190). This was unsurprising since, as discussed above,

the massive presence of cooperativistas in the demonstrations of late 2003 was instrumental

in forcing Sánchez de Lozada to resign.191

149. In this context, keeping good relations with the cooperativista sector at Colquiri was

fundamental to secure continuity of the Mine Lease. However, as of 2003, such continuity

had already been compromised by Comsur’s poor management of social relations at the

Mine.192 The mismanagement of this volatile situation continued through Glencore

International’s acquisition of the Assets, and beyond.

189 Letter from the Oruro Parliamentary Group to President Bánzer Suárez of 27 November 2000, R-110; Letter from

Leopoldo Fernández Ferreira to President Hugo Bánzer Suárez of 5 December 2000, R-113; Letter from Humberto

Bohrt Artieda to Walter Guiteras Denis of 8 December 2000, R-114.

190 Supreme Decree No. 29272 of 12 September 2007, R-169, p. 176 (Unofficial translation: “a mining activity which is

planned […], socially acceptable, in which may participate in a harmonised and wholesome manner the public sector,

indigenous communities, rural communities and other subsectors: large, medium, small and cooperative”).

191 M. Cajías de la Vega, “Crisis, Diáspora y Reconstitución de la Memoria Histórica de los Mineros Bolivianos” in Revista

de Estudios Transfronterizos, Vol. X, No. 2 (2010), R-159, p. 87 (“La presencia en El Alto de La Paz de los 800 mineros

de Huanuni y de más de 3.000 cooperativistas mineros, fue altamente significativa en momentos decisivos de la

insurrección popular que se desató en octubre de 2003 contra el gobierno de Gonzalo Sánchez de Lozada y que tuvo su

epicentro en esa ciudad del departamento de La Paz. No sólo se notó la presencia, en toda la semana que duró el

levantamiento popular, de los pobladores de los barrios mineros de relocalizados, principalmente de Santiago II, uno

de los lugares donde se produjeron mayores enfrentamientos con el ejército, sino de trabajadores mineros asalariados

y cooperativistas llegados desde Huanuni y otras minas. Así, octubre fue sin duda un momento de revelación de

“acumulaciones sociales previas”, aunque no sólo para el sector minero, sino para el conjunto de los sectores

populares en Bolivia […]”) (Unofficial translation: “The presence in El Alto and La Paz of 800 miners of Huanuni and

more than 3,000 mining cooperativistas was very significant in decisive moments of the popular uprising triggered in

October 2003 against the government of Gonzalo Sánchez de Lozada and the epicentre of which was in that city of the

department of La Paz. Not only was the presence of residents of neighbourhoods of relocated miners noted during the

entire week of the popular uprising, in particular from Santiago II, one of the places where major confrontations with

the army took place – but also the presence of mining employees and cooperativistas from Huanuni and other mines.

Thus, October was undoubtedly a moment of revelation of ‘previous social accumulations’, not only in the mining sector

but also in all popular sectors in Bolivia”).

192 See section 2.5.1 above.

Page 53: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

48

150. In sum, given the particular social and political context in which Glencore International

transferred the Assets to Glencore Bermuda, it could have reasonably been expected that the

State would take action in connection with those Assets.

2.5.5 Despite The Acquisition Of The Smelters And The Mine Lease, Glencore Did Not Make

Any Substantial Investment During Its Operation Of These Assets

151. Contrary to what Claimant implies, Glencore merely held indirect ownership in companies

that controlled the Assets and never made significant investments in Bolivia prior to the

reversion.

152. First, no substantial investment was made by Glencore during the time it controlled the Mine.

As a matter of fact, it is quite revealing that Claimant is unable to point to any significant

investments made prior to the reversion of the Mine Lease. None of the projects listed as

investments by Claimant in its Statement of Claim was even started, much less completed, as

of the time of the reversion. If Colquiri indeed “worked on constructing a new tailings

plant”193 and “sought to construct a new tailings dam,”194 the fact of the matter is that such

plant and dam were never built. If Colquiri indeed “planned on doubling the capacity of the

concentrator plant,”195 such project was, in reality, never carried out. And if Colquiri did

“design[] a principal access ramp that would connect the surface level to a new wider

gallery,”196 the fact is that such project was less ambitious than presented today and had barely

started in 2012.197

153. Second, as Eng Villavicencio confirms, the expenditures made by Sinchi Wayra in the Tin

Smelter between 2005 and 2007 were only aimed at maintaining productions levels and could

hardly be characterized as an investment.198 Just as Comsur had done since the Privatization,

Sinchi Wayra benefitted from the important investments made by the State in the 1980s-

1990s. It bears recalling that these investments allowed the EMV to levels of production

before the Privatization,199 which were never equaled by either Comsur or Sinchi Wayra

thereafter.

193 Statement of Claim, ¶ 52.

194 Statement of Claim, ¶ 57.

195 Statement of Claim, ¶ 53.

196 Statement of Claim, ¶ 55.

197 Moreira, ¶ 46.

198 Villavicencio, ¶¶ 39-43.

199 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, pp. 26-27 (“Constructed in 1968-70, the plant had, in its initial configuration, a capacity to produce 7,000

Page 54: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

49

154. Third, it is undisputed that Glencore only used the Antimony Smelter “as a storage facility”200

and never sought to reactivate production. Nor did Glencore seek to increase the production

levels that the Smelter had recorded during the nineties, prior to the Privatization.201

2.6 Bolivia Reverted The Assets For Public Purposes

155. As discussed above, Glencore was assigned the Assets by Glencore International in times of

great social and political transformations in Bolivia. As had been foreseeable since, at least,

2005, the State decided to revert the Assets:

In February 2007, the State reverted the Tin Smelter due to the irregularities which

had affected the Privatization (Section 2.6.1);

In May 2010, due to its inactivity, the State reverted the Antimony Smelter

(Section 2.6.2); and

In June 2012, in order to solve the serious social conflict created at the Colquiri

Mine by Glencore’s subsidiary, Sinchi Wayra, the State reverted the Mine Lease

(Section 2.6.3).

2.6.1 Bolivia Reverted The Tin Smelter Due To The Irregularities In The Privatization

Process

156. The new political context in Bolivia after the Guerra del Gas and Sánchez de Lozada’s

resignation led the State to take further actions concerning the Assets. This was unsurprising

since, as discussed above, the ownership of the Assets had been a sensitive matter in Bolivia

from the very moment they were privatized.202

157. Faced with inquiries about Sánchez de Lozada’s involvement in the transfer of the Assets to

Glencore International, its subsidiary Sinchi Wayra (controlling the Assets) was not inclined

metric tons/year of refined tin. This original plant was later expanded to an installed capacity of 11,000 and then 20,000

t/year. The capacity of the smelter increased to 30,000 t/year, through the installation of 10,000 tons of low-grade

treatment capacity between 1977 and 1980. The plant is currently configured to carry out only high-grade treatment,

its production capacity being 20,000 t/year. The technology used for the engineering of the tin treatment plant has all

been devised and installed by the German company Klockner, through various contracts”).

200 Statement of Claim, ¶ 59.

201 Paribas, 1999, Privatisation of Bolivian mining assets, Confidential Information Memorandum of 16 August 1999,

RPA-4, p. 61 (“in 1989 EMV carried out a new technological design for the production of trioxide of antimony from

sulfurous concentrates, with the repairing of rotating furnace and the construction of new continuous feeding systems

for the furnace and equipment to gather gases and other emissions. The overhaul of the plant was made jointly with

Laurel Industries Inc., with whom EMV signed a Toll Conversion Contract in 1990. Later that year the plant was

converted to be natural gas fired, for cost and quality reasons, and in August the plant started operations again”).

202 Bolivia.com, Goni vendió COMSUR, press article of 5 February 2005, R-14.

Page 55: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

50

to cooperate with the Bolivian authorities. As a matter of fact, when, on 16 February 2005,

COMIBOL expressed concerns over the fact that the transfer to Glencore had not been

properly notified to the authorities,203 Sinchi Wayra simply responded indicating that “las

acciones de Comsur S.A., sea en parte o en su totalidad, no han sido transferidas a ninguna

persona individual o colectiva.”204

158. Likewise, when members of the Bolivian Parliament became aware of the transactions

between Glencore International and Sánchez de Lozada, and requested information in this

regard in November 2006,205 Sinchi Wayra only provided “documentation confirming the

existence of Glencore International as a private share company governed under the laws of

Switzerland as well as detailing the identity of Glencore International’s shareholders and

subsidiaries, including Glencore Bermuda.”206 Sinchi Wayra’s attitude towards the

Government’s inquiries reveals that Glencore International and Claimant were aware of the

political risk that acquiring assets from a fleeing president represented.

159. In this context, on 9 February 2007, the State issued a decree ordering the reversion of the Tin

Smelter (the “Tin Smelter Reversion Decree”),207 taking into account the irregularities of the

Privatization discussed in section 2.4.1 above. In particular, the Tin Smelter Reversion Decree

stressed that, despite “[e]l monto de la adjudicación de $us14.751.349,- (CATORCE

MILLONES SETECIENTOS CINCUENTA Y UN MIL TRESCIENTOS CUARENTA Y NUEVE

00/100 DÓLARES AMERICANOS), […] Allied Deals PLC se ha beneficiado además con la

entrega ilegal de estaño metálico en circuito, concentrados, materiales y repuestos por más

de $us16.000.000.- (DIECISEIS MILLONES 00/100 DÓLARES AMERICANOS) […].”208 As

a result, the Reversion Decree concluded that “la Fundición de Estaño Vinto fue entregada a

203 Letter from COMIBOL to Comsur (Sinchi Wayra) of 16 February 2005, R-188.

204 Letter from Comsur (Sinchi Wayra) to COMIBOL of 17 February 2005, R-189 (Unofficial translation: “Comsur S.A.’s

shares have not, either partially or in their entiorety, been transferred to any individual or collective person”).

205 Request for written report from Senator Velásquez of 30 November 2006, C-68.

206 Eskdale, ¶ 41.

207 Supreme Decree No 29.026 of 7 February 2007, C-20.

208 Supreme Decree No 29.026 of 7 February 2007, C-20, recitals (Unofficial translation: “[despite t]he adjudication

amount of $us14,751,349,- (FOURTEEN MILLION SEVEN HUNDRED AND FIFTY-ONE THOUSAND THREE

HUNDRED AND FORTY-NINE 00/100 AMERICAN DOLLARS) […] Allied Deals PLC has furthermore benefited from

the illegal delivery of metallic tin in circuit, concentrate, materials and spare parts for more than $us16.000.000.-

(SIXTEEN MILLION 00/100 AMERICAN DOLLARS)”).

Page 56: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

51

la extinta empresa Allied Deals PLC (en situación de quiebra en su país de origen),

ocasionando un gravísimo daño a la propiedad del Estado boliviano.”209

160. Claimant complains about the fact that, on 9 February 2007, the Bolivian armed forces and

police were present during the implementation of the Tin Smelter Reversion Decree.210

However, Claimant glosses over the fact that their presence was in fact necessary to ensure

the peaceful transfer of the Tin Smelter, in light of Sinchi Wayra’s resistance to the reversion.

161. It is worth emphasizing that Claimant suffered no economic loss from the Tin Smelter

reversion. It is our understanding that it cashed out a political risk insurance policy held by a

syndicate of several international financial institutions headed by Lloyd’s. This is why

Glencore International’s 2011 prospectus said that “in 2007, the Bolivian government

nationalised a smelter owned by a subsidiary of Glencore” but “no material losses were

sustained and Glencore continues to do business in Bolivia.”211

2.6.2 Bolivia Reverted The Antimony Smelter Due To Its Inactivity

162. Even though the legal regulation for the Privatization provided for “la producción, las

exportaciones, el empleo y la productividad”212 as its goals, it is undisputed that neither

Comsur nor Glencore International sought to make the Antimony Smelter a productive asset.

163. Furthermore, as explained in Section 2.5.2 above, on 7 February 2009, Bolivia enacted a new

Constitution. Pursuant to Article 396 thereof, the State is “responsable de las riquezas

mineralógicas que se encuentren en el suelo y subsuelo cualquiera sea su origen y su

aplicación será regulada por la ley” and “ejercerá control y fiscalización en toda la cadena

productiva minera.”213 These new principles governing the activity of the State in the mining

sector were also supported by the Government’s development plan.214

209 Supreme Decree No 29.026 of 7 February 2007, C-20, recitals (Unofficial translation: “the Vinto Tin Smelter was

delivered to the extinct company Allied Deals PLC (bankrupt in its country of origin), causing serious harm to the

Bolivian State’s property”).

210 Statement of Claim, ¶ 66.

211 Prospectus of Glencore International plc of 3 May 2011, R-193, p. 13.

212 Supreme Decree No. 23991, Art. 2(c) (Unofficial translation: “production, exports, employment and productivity”).

213 Constitution of Bolivia of 7 February 2009, C-95, article 369 (Unofficial translation: “responsible for the mineral

resources located in the soil and sub-soil irrespective of their origin and its application will be regulated by law […and]

will control and audit the entirety of the mining production chain”).

214 Supreme Decree No. 29272 of 12 September 2007, R-169, p. 160 (“La intervención del Estado en el desarrollo minero

será con facultades de control, fiscalización y promoción en todo el circuito productivo, desde la otorgación de

concesiones mineras hasta la industrialización, restituyendo a COMIBOL su rol productivo y mejorando la

participación del Estado en los beneficios de la actividad minera vía régimen impositivo. Asimismo, la intervención del

Estado se manifestará en control y participación en la implementación de medidas que contribuyan a un mejor

desempeño ambiental sostenible de los operadores mineros”) (Unofficial translation: “The State’s intervention in mining

Page 57: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

52

164. At the time the State started to implement these new policies, it had become evident that

Glencore had no interest in reactivating production at the Antimony Smelter. Neither Comsur

nor Sinchi Wayra sought to use this facility as anything other than a “storage facility for the

Colquiri Mine”215 tin concentrates. In the eyes of the State, this was contrary to its position

as active promoter of the mining sector, and went even against the rationale of the

Privatization itself.

165. As a matter of fact, the Assets were privatized to achieve economic growth for the State by

way of private investment-driven increases in productivity. Indeed, per the Terms of

Reference, incorporated into the contract,216 for the privatization of the Antimony Smelter,

“[l]a Licitación tiene por objeto la transferencia a título oneroso de los Activos y Derechos

de la fundición de antimonio de la Empresa Metalúrgica Vinto, en favor de una empresa

especializada con capacidad económica, financiera y técnica, que permita el ingreso de

capital, tecnología, prácticas comerciales y de gestión privada, posibilitando a la Fundición

continuar la producción, constituyéndose en una fuente de generación de empleo y tributos,

en apoyo a la actividad minera de explotación y concentración de antimonio en el país.”217

166. In sum, the inactivity of the Antimony Smelter under the privatization contract was

unacceptable for the State. The resulting tension was compounded by the widely publicized

and heavily criticized irregularities which the Privatization had been fraught with. As a result,

on 1 May 2010, Bolivia issued a decree reverting the Antimony Smelter (the “Antimony

Smelter Reversion Decree”), noting the asset’s inactive status despite the commitments

undertaken by the acquirer.218

development shall be with the functions of control, audit and promotion in any production process, from the granting of

mining concessions until industrialization, restoring to COMIBOL its productive role and improving the State’s

participation in the mining activity through the tax regime. Similarly, the State’s intervention will reflect in the control

of and participation in the implementation of measures that contribute to a sustainable environmental performance of

mining operators”).

215 Statement of Claim, ¶ 59.

216 Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External Trade

and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9, 23(1),

p. 21.

217 Terms of Reference for the Second Public Tender for the Antimony Smelter of 31 July 2000, R-109, article 1.4

(Unofficial translation: “[t]he Bid’s object is to transfer in exchange for consideration the Assets and Rights of the

Antimony Smelter of the Vinto Metallurgical Company to a specialized company with economic, financial and technical

capacity, that will allow the inflow of capital, technology, commercial practices and private management, permitting

the Smelter to continue production, becoming a source for the generation of employment and tax, in support of the

mining activity of exploitation and concentration of antimony in the country”).

218 Supreme Decree No 499 of 1 May 2010, C-26, recitals (“Que en los últimos años se evidenció la inactividad productiva

de la Planta Metalúrgica Vinto Antimonio, así como su desmantelamiento, no obstante haberse estipulado en el pliego

de condiciones las obligaciones de invertir y fortalecer la Empresa Metalúrgica Vinto Antimonio con capacidad

económica, financiera y técnica, que permita el ingreso de capital, tecnología, prácticas comerciales y de gestión

privada, posibilitando a la Fundición continuar la producción, constituyéndose en una fuente de generación de empleo,

Page 58: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

53

167. Pursuant to this Decree, “[s]e revierte al dominio del Estado Plurinacional de Bolivia la

Planta de Vinto Antimonio, con todos sus activos actuales,”219 i.e., including the tin

concentrates stored at the Antimony Smelter (the “Tin Stock”). Consistent with this

understanding of the Decree, on 14 May 2010, Glencore International sent a letter to the

Bolivian President complaining about the “nacionalización de la planta de antimonio,”220

without referring to the Tin Stock.

168. It was instead Colquiri, Glencore International’s subsidiary, who sent several letters to the

Bolivian authorities requesting the Tin Stock to be returned.221 No further actions were taken

in this regard by other Glencore International affiliates, nor were any legal remedies sought.

2.6.3 Due To The Social Crisis Created By Sinchi Wayra At The Colquiri Mine, The State

Was Left With No Other Choice But To Revert The Mine Lease

169. Colquiri—now under Glencore International’s control through Sinchi Wayra—mismanaged

and aggravated the social conflicts at the Mine it inherited from Comsur (Section 2.6.3.1).

This situation led to an unprecedented social conflict at the Mine in 2012 (Section 2.6.3.2).

In order to solve the conflict created by Glencore—in particular, derived from the agreements

it secured with the cooperativistas—the State had no choice but to negotiate with the Colquiri

union leaders and the cooperativistas and to revert the Mine Lease (Section 2.6.3.3).

2.6.3.1 During The Time Glencore International Controlled The Colquiri Mine, The Tensions

Between Cooperativistas And Workers Increased

170. Glencore International inherited the problems created by Comsur’s mismanagement of the

social conflicts at the Colquiri Mine, as explained in Section 2.5.1 above. These problems

were not resolved in the following years. On the contrary, under Sinchi Wayra’s

administration, and in the new political context arising in Bolivia since 2003, the

tributos y de externalidades, en apoyo a la actividad minera de explotación y concentración de antimonio en el país”)

(Unofficial translation: “In recent years, the inactivity of the Metallurgical Company Vinto Antimonio became obvious,

as well as its dismantling, notwithstanding that the terms of reference provided for the obligation to invest in and

reinforce the Metallurgical Company Vinto Antimonio with economic, financial and technical capacity, that would allow

the inflow of capital, technology, commercial practices and private management, permitting the Smelter to continue

production, becoming a source for the generation of employment and tax, in support of the mining activity of exploitation

and concentration of antimony in the country”).

219 Supreme Decree No 499 of 1 May 2010, C-26, article 1 (emphasis added) (Unofficial translation: “[t]he Vinto Antimony

Smelter, and all its assets, are reverted to the ownership of the Plurinational State of Bolivia”).

220 Letters from Glencore (Mr Mate and Mr Glasenberg) to the President of Bolivia (Mr Morales Ayma) and the Ministry

of Mining (Mr Pimentel Castillo) of 14 May 2010, C-27 (Unofficial translation: “nationalization of the antimony

smelter”).

221 Letter from Colquiri SA (Mr Capriles Tejada) to Ministry of Mining (Mr Pimentel Castillo) of 3 May 2010, C-28; Letter

from Ministry of Mining (Mr Pimentel Castillo) to EMV (Mr Ramiro Villavicencio) of 5 May 2010, C-29.

Page 59: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

54

cooperativistas’ ambitions to take over new parts of the Mine gradually increased, whilst

conflicts with the mine workers of the company worsened.

171. Claimant, based on Mr Eskdale’s statement,222 links the Reversion of the Mine Lease to

alleged attempts of the cooperativistas to steal ore and tools from the Mine in April 2012.223

Claimant even attempts to portray the cooperativistas as “private groups of miners who carry

out mining activities for their own benefit in the area,”224 with no relation to Sinchi Wayra’s

operation at the Mine. This characterization of the facts is inaccurate.

172. Contrary to what Claimant implies, “[c]on Sinchi Wayra, la seguridad de la Mina decreció

aún más y la aprobación del trabajo de los cooperativistas por parte de la empresa fue mayor.

Esto causó que el descontento de los trabajadores se tornara, en algunos casos, violento,

sobre todo al interior de la Mina, cuando los trabajadores y los cooperativistas se

encontraban en la misma área. Los enfrentamientos entre trabajadores y cooperativistas se

hicieron más y más frecuentes.”225

173. Colquiri, now controlled by Sinchi Wayra, had, since 2005, been aware of—and complied

with—the agreements entered into by COMIBOL and the cooperativas for the official

assignment of certain areas of operation at the Mine (with Comsur’s approval).226 In

particular, Colquiri was aware of the existence of the October 2000 agreement, under which

areas of the Mine had been assigned to the Cooperativa 26 de Febrero until 2018.227

174. Furthermore, documents from Colquiri confirm that the company was aware of the tensions

between the cooperativas and the company’s workers since 2005 and that this situation had

222 Eskdale, ¶ 74 (“On 1 April 2012, I was informed by Mr Capriles that a group of about one hundred people violently and

unlawfully entered the Colquiri Mine”).

223 Statement of Claim, ¶ 87 (“On 1 April 2012, a group of about one hundred local independent miners, known as

cooperativistas, unlawfully entered the Colquiri Mine and stole minerals as well as mining equipment”).

224 Statement of Claim, ¶ 87.

225 Cachi, ¶ 24 (Unofficial translation: “[u]nder Sinchi Wayra, security in the Mine diminished even more and the approval

of the cooperativistas’ work by the company was more significant. This led, in some cases, to the workers’ discontent

becoming violent, in particular within the Mine, when workers and cooperativistas met in the same area. Confrontations

between workers and cooperativistas became more and more frequent”).

226 See Public Deed No. 003/2000, amendment to the lease agreement between COMIBOL and the subsidiarios of the

Colquiri Mine of 5 January 2000, R-93; Public Deed No. 131/2000, lease agreement between Comibol and the

Cooperativa 26 de febrero of 13 October 2000, R-94.

227 Public Deed No. 131/2000, lease agreement between Comibol and the Cooperativa 26 de febrero of 13 October 2000,

R-94, clause 5 (“A petición de la Cooperativa y en virtud de los planes y proyectos de explotación que tiene, COMIBOL

resuelve ampliar el plazo de vigencia del contrato hasta veinte años computables a partir de la fecha de suscripción del

contrato principal No. 50/98 de diez/cero siete/[98]”) (Unofficial translation: “Pursuant to the Cooperativa’s request

and in light of its exploitation plans and projects, COMIBOL decides to extend the contract term to twenty years as of

the date of execution of the main contract No. 50/98 of ten/zero seven/[98]”).

Page 60: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

55

not prevented it from working with the cooperativistas and assigning them more areas at the

Mine.

175. For instance, in its annual operations report for 2005, Colquiri mentioned that, during this

year, “se produjeron paros esporádicos de labores por parte de los trabajadores, por apoyo

a disposiciones de sus entidades matrices y debido a amenazas de las que fueron objeto por

parte de otros sectores en defensa de sus fuentes de trabajo, así como intervenciones y

presiones de parte de las dos cooperativas que trabajan, una en la mina y, la otra en las colas

antiguas.”228 Similar situations took place in 2006, as shown by the annual operations report

for that year.229

176. Sinchi Wayra did not request the State’s intervention in order to alleviate the pressure exerted

by the cooperativas. On the contrary, on 8 September 2006, Sinchi Wayra advised

COMIBOL that “la Compañía Minera Colquiri S.A. está negociando con cada una de las

cooperativas afiliadas a [la Central de Cooperativas Mineras de Colquiri] acuerdos para

asignarles áreas de trabajo en lugares que no interfieran el normal desenvolvimiento de las

labores de producción de la empresa.”230

177. By 2008, the Cooperativa 26 de Febrero was authorized to operate in areas covering almost

all of the surface of the Mine.

228 Colquiri S.A. Annual Report for 2005, November 2005, R-194, p. 1 (emphasis added) (Unofficial translation: “work

was occasionally stopped by the workers, in support of measures of their parent entities and due to threats received

from other sectors in defense of their sources of work, as well as interventions and pressure from the two cooperatives

which work, one in the mine and the other one at the old tailings dam”).

229 Colquiri S.A. Annual Report for 2006 of 27 November 2006, R-195, p.1 (“Durante la gestión las relaciones laborales

en la mina fueron razonables, produciéndose paros esporádicos de labores por parte de los trabajadores que afectaron

la producción, por apoyo a disposiciones de sus entidades matrices y debido a amenazas de las que fueron objeto por

parte de otros sectores en defensa de sus fuentes de trabajo, así como un conflicto con las cooperativas que trabajan,

una en la mina y, la otra en las colas antiguas”) (emphasis added) (Unofficial translation: “During the operations,

working relations in the mine were reasonable. Work was occasionally stopped by the workers, in support of measures

of their parent entities and due to threats received from other sectors in defense of their sources of work, as well as

interventions and pressure from the two cooperatives which work, one in the mine and the other one at the old tailings

dam. This affected production.”).

230 Letter fom Sinchi Wayra to COMIBOL of 8 September 2006, R-196 (Unofficial translation: “Compañía Minera

Colquiri S.A. is negotiating with each of the cooperatives that are affiliated to [the Association of Mining Cooperatives

of Colquiri] agreements to allocate to them working areas in locations which will not interfere with the normal

production operations of the company”).

Page 61: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

56

Plan of the Colquiri Mine as of 2008 – In green, areas in which the company

authorized the presence of the Cooperativa 26 de Febrero.231

178. Internal Colquiri documents further confirm that Sinchi Wayra often yielded to the

cooperativas’ demands, even if this decision was not welcomed among the workers of the

company. Mr Cachi recalls, in this regard, that, in or around 2008 “y con el fin de ejercer

presión sobre Sinchi Wayra para obtener nuevas áreas, nos tomamos la subestación eléctrica

Elfeo que suministra energía a toda la población. Con ello, Sinchi Wayra accedió a darnos

más niveles inferiores. Firmamos nuevos convenios con la empresa que nos permitieron

llegar a trabajar en el nivel 285.”232 Indeed, contemporary internal reports show that, in 2007

and 2008, cooperativistas from the Cooperativa 26 de febrero started working as deep as at

level -285 with the approval of Colquiri.233

231 Plan of areas assigned by Sinchi Wayra to the cooperativas as of 2008, R-197.

232 Cachi, ¶ 25 (Unofficial translation: “and with the aim of exerting pressure over Sinchi Wayra in order to obtain new

areas, we took control of the Elfeo sub-station, which supplies energy to the entire population. As a result, Sinchi Wayra

agreed to allocate to us additional lower levels. We signed further agreements with the company, allowing us to work

at level 285”).

233 See, for instance, Colquiri internal report concerning ore bought and/or transported for the Cooperativa 26 de Febrero

of 15 December 2007, R-198; Colquiri internal report concerning ore bought and/or transported for the Cooperativa 26

de Febrero of 21 April 2008, R-199; Colquiri internal report concerning ore bought and/or transported for the

Cooperativa 26 de Febrero of 17 April 2007, R-200; Proof of payment for the transport of ore for the Cooperativa 26

de Febrero of 21 October 2007, R-201; Proof of payment for the transport of ore for the Cooperativa 26 de Febrero of

20 November 2007, R-202; Proof of payment for the transport of ore for the Cooperativa 26 de Febrero of 7 January

2008, R-203; Colquiri internal report concerning ore transported for the Cooperativa 26 de Febrero of 25 May 2008,

R-204; Colquiri internal report concerning ore transported for the Cooperativa 26 de Febrero of 29 June 2008, R-205.

Page 62: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

57

Colquiri internal report of transportation of concentrates from the Cooperativa 26 de Febrero.

In red, the levels at which the cooperativistas were working as of 2008234

179. Over the course of 2007, COMIBOL followed up with Colquiri on several requests made by

the cooperativas to gain access to new areas of the Mine in order to “incrementar volúmenes

de productividad con sistema de explotación masiva de minerales de estaño y zinc.”235 No

alarm bells were rung at the time. Instead of properly alerting the authorities about the risks

these agreements entailed, Colquiri simply informed in its annual operation reports for 2007

and 2008 that the company secured “el apoyo a la Cooperativa 26 de Febrero para rehabilitar

infraestructura independiente de extracción de minerales y la creación de incentivos para

234 Colquiri internal report concerning ore bought and/or transported for the Cooperativa 26 de Febrero of 21 April 2008,

R-199, p. 4.

235 Letter from COMIBOL to Colquiri of 4 June 2007, R-206 (“Mediante carta s/n de fecha 23/05/07, la Cooperativa

Minera ‘26 de Febrero’ Ltda. ha presentado a la Corporación Minera de Bolivia el Plan de Rehabilitación Cuadro

Maestro – Rampa Incalacaya Sección Chojña, con la finalidad de incrementar volúmenes de productividad con sistema

de explotación masiva de minerales de estaño y zinc, requiriendo para su implementación de mecanización materiales

y equipamiento; asimismo, solicita una reunión conjunta entre COMIBOL, la Cia. Minera Colquiri y la citada

cooperativa. En este sentido, tenemos a bien invitar a usted a la citada reunión que se realizará el día martes 5 del

presente mes a horas 18:00 p.m. en dependencias de la Gerencia Técnica y de Proyectos, 4to piso de COMIBOL”)

(Unofficial translation: “By letter w/n of 23/05/07, the Mining Cooperative ‘26 de Febrero’ Ltda. has presented to the

Bolivian Mining Corporation the Rehabilitation Masterplan – Incalacaya Ramp Chojña Section, with the purpose of

increasing production volumes using the system of massive exploitation of tin and zinc ore, requiring for its

implementation machinery, materials and equipment; likewise, it requests a joint meeting between COMIBOL,

Compañía Minera Colquiri and the aforementioned cooperative. In this sense, we invite you to this meeting that will

take place on Tuesday the 5th day of this month at 6 p.m. at the premises of the Technical Management and Projects

department, 4th floor of COMIBOL”). See, also, Letter from COMIBOL to Colquiri of 3 September 2007, R-207 (“Los

ex trabajadores de la Empresa Minera Colquiri han solicitado a la Corporación Minera de Bolivia una orden de cateo

para el área denominada Socavón Inca, ubicada en la población civil de Colquiri. En el marco del contrato de

arrendamiento que tenemos suscrito, nos permitimos consultar a usted si el indicado socavón pretendido por dicha

organización de ex trabajadores no afectan las operaciones ni las instalaciones de la Compañía Minera Colquiri”)

(Unofficial translation: “Former workers of Empresa Minera Colquiri have requested from the Bolivian Mining

Corporation a search warrant for the Inca tunnel area, located in the village of Colquiri. In the framework of the lease

contract that we concluded, we query if the indicated tunnel requested by this organization of former workers does not

affect the operations or the facilities of Compañía Minera Colquiri”).

Page 63: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

58

concentrar su producción en el zinc”236 and that “las cooperativas mineras del sector siguen

demandando a la empresa que se les entregue más áreas de trabajo.”237

180. Sinchi Wayra appeared to ignore the risks these agreements represented for the Mine

operation, on the one hand, and the relations between the cooperativistas and the workers of

the company, on the other hand. In Mr Mamani’s words, “[c]omo trabajadores, nunca vimos

con buenos ojos este tipo de acuerdos ya que, con el conocimiento que los cooperativistas

habían adquirido del interior de la Mina, sabíamos que se aprovecharían para robar mineral

y materiales y hacerse a zonas que estaban siendo explotadas por la empresa.”238 The

evidence shows that this practice was not abandoned by Sinchi Wayra, even though, by the

time Glencore International acquired the Mine Lease, such practice had already created long-

lasting tensions between cooperativistas and mining workers.

181. In any event, if Sinchi Wayra allowed the presence of cooperativistas in the areas of the Mine

Lease, it was also because it had an interest in working closely with them. In times of low

international prices for tin, working with cooperativistas was more appealing than having a

large payroll at the company. Unlike mining workers, cooperativistas “no gozan de

estabilidad laboral ni beneficios sociales.”239

182. That was precisely the case in 2009. Faced with a depressed international market for tin,240

Colquiri attempted to lay off part of its employees while at the same time it negotiated a deal

with the Cooperativa 26 de Febrero for the assignment of a deeper level of the Mine (-325).241

236 Colquiri S.A. Annual Report for 2007 of 18 December 2007, R-208, p. 2 (Unofficial translation: “support to Cooperativa

26 de Febrero to rehabilitate the infrastructure for independent mineral extraction and the creation of incentives to

focus its production on zinc”).

237 Colquiri S.A. Annual Report for 2008 of 22 January 2009, R-209, p. 2 (Unofficial translation: “the mining cooperatives

in the sector continue to request that the company award them more working areas”).

238 Mamani, ¶ 16 (Unofficial translation: “[a]s workers, we never welcomed this type of agreements, because, in light of

the knowledge that the cooperativistas had acquired of the interior of the Mine, we knew that they would take the

opportunity to steal ore and equipment materials and enter areas that were being exploited by the company”).

239 Cachi, ¶ 9 (Unofficial translation: “do not benefit from employment stability or social benefits”).

240 See Compass Lexecon Price Forecasts, CLEX-30, tab “Historical”.

241 Public Deed No. 0215/2009, amendment to the lease agreement between COMIBOL and the Cooperativa 26 de Febrero

of 21 October 2009, R-210, clause 3.

Page 64: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

59

Cross section of the Mine.242 In Red, inferior levels assigned by Sinchi Wayra to the

Cooperativa 26 de Febrero in 2009

183. This situation sparked outrage and unrest among the members of the union workers. As

Mr Mamani recalls, “en el año 2009, realizamos movilizaciones masivas en Colquiri (impulsadas

por el Sindicato de Trabajadores Mineros de Colquiri […]) para evitar la cooperativización de la

Mina y exigir que la empresa nos garantizara estabilidad laboral.”243 In view of Sinchi Wayra’s

plan to benefit the cooperativas, in January 2009, the Federación de Sindicatos de

Trabajadores Mineros de Bolivia (the “FSTMB”) threatened to “expulsar a estas

transnacionales y los trabajadores mineros tomaremos los yacimientos mineralógicos para

nacionalizarlos con ayuda del Gobierno Central.”244

184. In parallel, the cooperativas—which, as discussed earlier, were strong political actors in the

country since 2003—demanded more from a passive Sinchi Wayra. As Mr Cachi explains,

“[e]sta facilidad para obtener nuevas áreas de trabajo [facilitated by Sinchi Wayra] aumentó

la ambición de los cooperativistas por acceder a áreas más atractivas en las que el trabajo

era menos difícil.”245

242 Transversal section of the Colquiri Mine, R-211.

243 Mamani, ¶ 20 (Unofficial translation: “in 2009 we carried out massive mobilizations in Colquiri (boosted by the

[Colquiri Mining Union]) to prevent the cooperativization of the Mine and demand that the company guarantee our

employment stability”).

244 Press release of the Federación Sindical de Trabajadores Mineros de Bolivia of 9 January 2009, R-20 (Unofficial

translation: “expel these transnationals and us mining workers will take the ore deposits to nationalize them with the

assistance of the Central Government”).

245 Cachi, ¶ 18 (Unofficial translations: “[t]his ease in obtaining new working areas [facilitated by Sinchi Wayra] increased

the cooperativistas’ ambition to access more attractive areas in which work was less difficult”).

Page 65: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

60

185. This situation was far from ideal in the eyes of Sinchi Wayra’s workers, in particular since it

practically amounted to the invasion of areas where the company was operating.246 These

takeover attempts resulted in even more violent confrontations between the workers and the

cooperativistas over the course of 2010247 and 2011. As Mr Cachi recalls:

Con el tiempo, los altercados violentos entre trabajadores, la empresa de seguridad

y los cooperativistas aumentaron. Recuerdo que, a principios de 2011, tuvimos un

enfrentamiento con el personal de seguridad y los ingenieros de la empresa. Cinco

personas resultaron gravemente heridas. En otra ocasión, un conductor de una

volqueta quiso atropellar a los cooperativistas que estaban saliendo de la Mina por

la rampa blanca. Los cooperativistas agarraron al operador y lo querían dinamitar.

El operador se liberó al explicarles que solo cumplía las órdenes de sus jefes.248

186. In sum, under the administration of Sinchi Wayra, Colquiri’s consistent and considerable

leniency with the cooperativas over the years aggravated tensions with the mining workers

and encouraged them to request and take over new areas at the Mine. At the same time,

Colquiri’s conduct progressively made operating the Mine considerably more difficult.

187. Encouraged, the cooperativistas decided to take over the Mine in 2012.

246 Mamani, ¶ 22 (“En resumen, la pasividad de la empresa, la ambición de los cooperativistas y el abandono al que fueron

sometidos los trabajadores por parte de Sinchi Wayra hicieron que los ataques a nuestros compañeros aumentaran

dramáticamente y las cooperativas se hicieran a áreas más importantes de la Mina. Así ocurrió, por ejemplo, hacia

finales de 2011, cuando era frecuente encontrar cooperativistas juqeando en los niveles 405 hacia abajo (unos de los

más profundos de la mina). Para el año 2012, ya había reportes de que los cooperativistas estaban extrayendo minerales

en el nivel 535”) (Unofficial translation: “In sum, the company’s passiveness, the ambition of the cooperativistas and

the neglect of the workers by Sinchi Wayra led to a dramatic increase in the attacks against our colleagues and allowed

the cooperatives to reach more important areas in the Mine. This happened for example, in late 2011, when it was

normal to find cooperativistas stealing at levels 405 and below (one of the deepest in the mine). By 2012, there were

already reports that the cooperativistas were extracting ore at level 535”).

247 Colquiri annual operations report for 2010, R-212, p. 2 (“En cuanto a la relación con la comunidad se aprecia un

crecimiento poblacional por migración laboral y vegetativa de fuerza de trabajo local, que busca la actividad minera

como ‘alternativa’ a las actividades agropecuarias tradicionales. Por tanto, existe presión sobre las operaciones

mineras que se manifiestan en Solicitudes de áreas para laboreo minero, puestos de trabajo que están ocasionando

invasiones de áreas y parajes no autorizados. Estos conflictos sociales a veces se confunden con los laborales propios

de la empresa generando un clima de conflicto. Para enfrentar estas situaciones se desarrolla un método de trabajo en

base al Relacionamiento Social - Institucional que ha permitido controlar estos problemas sociales y que deberá

consolidarse ‘en el futuro, dada la complejidad de los problemas sociales que se generan permanentemente”) (emphasis

added) (Unofficial translation: “Regarding the relation with the community, there is a notable increase in population

due to the employment and natural migration of the local workforce, which seeks mining activity as an ‘alternative’ to

traditional agricultural activities. As a result, there is pressure on mining operations, manifested in Requests for areas

to carry out mining work, work stations that are generating incursions into non-authorized areas and sites. These social

conflicts are sometimes confused with the employment conflicts of the company itself, thus generating a conflictual

environment. To face these situations a working method is developed on the basis of Social–Institutional Relationships,

which has allowed control over this social problem and that which will have to be consolidated in the future, given the

complexity of the social problems that are permanently generated”).

248 Cachi, ¶ 30 (Unofficial translation: “With time, the violent confrontations between workers, the security company and

the cooperativistas increased. I recall that, in early 2011, we had a confrontation with the security staff and the

company’s engineers. As a result, five people were seriously injured. On another occasion, the driver of a dump truck

tried to run over the cooperativistas who were exiting the mine through the white ramp. The cooperativistas grabbed

the driver and were willing to blow him up. The driver was freed when he explained that he was just following orders

from his superiors”).

Page 66: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

61

2.6.3.2 The Violence Created By Glencore At Colquiri In 2012 Left The State With No Choice But To

Revert The Mine Lease

188. The complex social conflict that Sinchi Wayra’s operatorship aggravated throughout the years

reached its pinnacle in mid-2012.

189. Between 1 and 3 April 2012, members of the Cooperativa 26 de Febrero entered the Colquiri

Mine and, as had occurred on previous occasions, stole materials and ore from the areas where

Colquiri was operating, and violently confronted some of the company’s workers. This was

neither unsurprising nor uncommon as, in Mr Cachi’s words, “[p]ara finales de 2011, los

cooperativistas teníamos prácticamente el control de la Mina.”249

190. On 3 April 2012, and given that hundreds of cooperativistas had perpetrated acts of violence,

Colquiri wrote to COMIBOL requesting the State’s intervention.250 Though Claimant seeks

to suggest that the Bolivian Government would have been unresponsive, purportedly in light

of Colquiri’s rights under the Mine Lease,251 it is Colquiri’s own admission that “[d]ichas

perturbaciones al desenvolvimiento de la operación minera señalada, han sido atendidas en

gran medida y hasta el momento por nuestra empresa”252 (that is, without involving the

State’s institutions by its own decision).

191. In that letter, Colquiri further requested that COMIBOL “tome las medidas necesarias para

mantener la pacifica posesión y el orden público en el distrito minero de Colquiri, tal como

establece el contrato de arrendamiento.”253 COMIBOL, however, was not in a position to

provide a timely and satisfactory solution to Colquiri’s demand at a time when the

Cooperativa 26 de Febrero’s knowledge and control of the interior of the Mine had been

increasing for years. Colquiri was asking COMIBOL to resolve a structural problem in a

matter of days.

192. Sinchi Wayra’s directors were aware that the incursions of the cooperativas within the Mine

would not be an easy situation to resolve, as no course of action could please both the

cooperativistas and Colquiri’s workers. In fact, in the course of a meeting which took place

249 Cachi, ¶ 31 (Unofficial translation: “[b]y the end of 2011, we the cooperativistas practically controlled the Mine”).

250 Letter from Colquiri SA (Mr Capriles Tejada) to Comibol (Mr Córdova Eguivar) of 3 April 2012, C-30.

251 Statement of Claim, ¶ 88.

252 Letter from Colquiri SA (Mr Capriles Tejada) to Comibol (Mr Córdova Eguivar) of 3 April 2012, C-30 (Unofficial

translation: “[s]uch disturbances to the ongoing mining operation indicated have been addressed so far and to a large

extent by our company”).

253 Letter from Colquiri SA (Mr Capriles Tejada) to Comibol (Mr Córdova Eguivar) of 3 April 2012, C-30 (Unofficial

translation: “adopt the necessary measures to maintain the peaceful possession and public order in the Colquiri mining

district, as established in the lease agreement”).

Page 67: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

62

on 22 May 2012 between Sinchi Wayra’s management and several union representatives of

Colquiri, “[l]os sindicatos demanda[ron] que la empresa inicie acciones legales contra los

jukus [i.e. the thieves] de Colquiri por el robo de minerales e implementos/insumos de trabajo,

además del daño a las instalaciones productivas (indicamos [i.e. Sinchi Wayra] que esto

generaría más conflictos con las cooperativas, pero ellos indican estar cansados de esta

incertidumbre).”254

193. That same day, COMIBOL officials met with Sinchi Wayra in order to advance further in the

negotiations concerning the migration of Colquiri’s rights to a joint venture scheme. In that

meeting, COMIBOL officers advised that the proposed contract was sent to the entity’s

technical and administrative units in order to speed up its negotiation. They further informed

Sinchi Wayra that it was likely that “[Héctor] Cordova [COMIBOL’s director] presionara [a

Sinchi Wayra] para sacar una versión final hasta la próxima semana, que incorpore los

comentarios de las Gerencias Técnica y Administrativa.”255 Sinchi Wayra’s internal reports

on COMIBOL’s intention to close this negotiation as soon as practical are thus dispositive of

Claimant’s assertion that “the government […] suggested that Colquiri be excluded from the

new contractual framework [and] such an exclusion meant nationalization.”256

194. On 30 May 2012, the situation escalated and spiralled out of control. As both Mr Cachi and

Mr Mamani recall, approximately one thousand cooperativistas from the Cooperativa 26 de

Febrero violently took control over the Colquiri Mine, which they accessed through the main

amongst the old mouths of the Mine (Sanjuanillo) and other old mouths located near and

around the village.

Nuestra ambición como cooperativistas por obtener la totalidad del control de la

Mina fue creciendo y llegó a su punto máximo a mediados de 2012. Concretamente,

el 30 de mayo de 2012, los cooperativistas de la Cooperativa 26 de Febrero

decidimos tomar la Mina. Ese día, unos 1.200 cooperativistas ingresamos a la Mina

por las bocaminas San Juanillo y El Triunfo. Los trabajadores de la Mina se

opusieron a nuestra entrada, lo que ocasionó un enfrentamiento violento. Estos

254 Email from Glencore International (Mr Hartmann) to Glencore International (Mr Eskdale) and Sinchi Wayra (Mr

Capriles) of 22 May 2012, C-110, p. 2 (emphasis added) (Unofficial translation: “[t]he unions request[ed] that the

company initiate legal action against jukus [i.e. the thieves] of Colquiri for the theft of ore and tools/work implements,

in addition to damage caused to production units (we [i.e. Sinchi Wayra] indicated that this would generate more

conflicts with the cooperatives but they indicated that they were tired of this uncertainty)”).

255 Email from Glencore International (Mr Hartmann) to Glencore International (Mr Eskdale) and Sinchi Wayra (Mr

Capriles) of 22 May 2012, C-110, p. 3 (Unofficial translation: “[Héctor] Cordova [COMIBOL’s director] would

pressure [Sinchi Wayra] to produce a final version by the following week, incorporating the comments of the Technical

and Administrative Direction”).

256 Statement of Claim, ¶ 90.

Page 68: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

63

enfrentamientos se prolongaron durante aproximadamente dos días y dejaron un

saldo de más de 15 heridos.257

195. The violence of the confrontation and the tragic result of 15 wounded258 prompted a strong

reaction from the company’s workers, who organized a union general assembly that same

day.259 In letters sent to the Bolivian President, the Minister of Mines, and the Director of

COMIBOL, the Sindicato Mixto de Trabajadores Mineros de Colquiri (the “STMC”) advised

the Government, inter alia, that:

Damos un plazo de 24 hrs. al gobierno central y al ministerio de minería para que

dé la solución inmediata al problema ocurrido en Colquiri ya que este problema

puede traer mayores consecuencias fatales a la familia minera en Colquiri.

[D]e no tener una respuesta favorable hacia los trabajadores mineros asalariados

nos veremos obligados a retomar nuestras fuentes de trabajo y de darse cualquier

hecho lamentable ya sea con pérdidas humanas y materiales responsabilizaremos

al gobierno actual y a los actores principales quienes promovieron el

avasallamiento de nuestras fuentes de trabajo sin respetar nuestra constitución

política del estado.260

257 Cachi, ¶¶ 32-33 (Unofficial translation: “Our ambition as cooperativistas to obtain complete control over the Mine

gradually increased and reached its peak in mid-2012. Specifically, on 30 May 2012, we the cooperativistas of

Cooperativa 26 de Febrero decided to take control over the Mine. That day, some 1.200 cooperativistas entered the

Mine through the San Juanillo and El Triunfo mine mouths. The Mine workers blocked our entrance, which led to a

violent confrontation. Confrontations lasted during approximately two days and left more than 15 people wounded”).

See, also, Mamani, ¶ 25 (“En la mañana del 30 de mayo de 2012, cuando nos encontrábamos trabajando en el interior

de la Mina, fuimos alertados de que un gran número de cooperativistas (aproximadamente 1200) estaba ingresando

por el sector El Triunfo (una antigua bocamina) y que otros se estaban dirigiendo al nivel de extracción de la Mina

(que es la bocamina principal que queda en el nivel 165, conocido como Sanjuanillo). Los cooperativistas fueron muy

violentos y nos atacaron con palos, piedras y dinamita, hiriendo a algunos de los compañeros que estaban trabajando

en ese turno al interior de la mina”) (Unofficial translation: “On the morning of 30 May 2012, while we were working

in the interior of the Mine, we were alerted that a large number of cooperativistas (approximately 1.200) were entering

through the El Triunfo sector (a former mine mouth) and that there were others who were going towards the extraction

level of the Mine (which is the mouth at level 165, known as Sanjuanillo). The cooperativistas were very violent and

attacked us with sticks, stones and dynamite, injuring some of our colleagues who were working during that shift inside

the Mine”).

258 La Patria, Cooperativistas toman mina en Colquiri y hieren a siete mineros, press article of 31 May 2012, R-21.

259 Mamani, ¶ 26 (“El 30 de mayo, los miembros del STMC [Sindicato de Trabajadores Mineros de Colquiri] nos reunimos

en una asamblea general de emergencia y enviamos cartas al Presidente del Estado, al Ministro de Minería y

Metalurgia y al Presidente de la COMIBOL pidiendo una solución que nos garantizara nuestras fuentes de trabajo”).

See, also, Press release from the Federación Sindical de Trabajadores de Mineros de Bolivia of 31 May 2012, R-23

(Unofficial translation: “On 30 May, we the members of the [Colquiri Mining Union] met at a general emergency

assembly and sent letters to the President of the State, the Ministry of Mines and Metallurgy and the President of

COMIBOL, requesting a solution to guarantee our work sources”).

260 Letters from the Sindicato Mixto de Trabajadores Mineros Colquiri to the President of Bolivia (Mr Morales), the

Ministry of Mining (Mr Virreira), and Comibol (Mr Córdova) of 30 May 2012, C-111 (Unofficial translation: “We give

a delay of 24h to the central government and the ministry of mines to provide an immediate solution to the problem

occurring in Colquiri, given that this problem may bring major fatal consequences to the mining family in Colquiri.

[A]bsent a favourable answer to the mining workers we will be forced to take control over our work sources and, should

any unfortunate event occur, be it human or material losses, we will hold responsible the current government as well as

the leading actors who fostered the subjugation of our work sources without respecting the political constitution of our

State”).

Page 69: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

64

196. The grave situation at Colquiri demanded urgent action from the Government. On 30 May

2012, police squads arrived in Colquiri,261 and COMIBOL’s President, Mr Héctor Córdova,

took measures to prevent the commercialization of the Cooperativa 26 de Febrero’s

production in the country.262 The Government also sought to act as a mediator in the conflict

between the cooperativistas and Colquiri workers, and to preserve Colquiri’s rights over the

Mine Lease. Claimant’s contention that “the government failed to intervene”263 is simply

false.

197. On 3 June 2012, the Minister of Mines, the Minister of Labour, and COMIBOL officials met

with the SMTC and the FSTMB. Given the historical and social importance of Colquiri in

Bolivia’s mining sector, the FSTMB had in fact convened a general assembly near Colquiri

two days earlier.264 By that time, the FSTMB had already decided to block the only road

connecting Colquiri to the rest of the country, as a counter-measure against the

cooperativistas.265

198. At the end of this meeting, the Government representatives and the union leaders executed

minutes of understanding. Pursuant to this agreement, the Government and the unions would

work together in order to “ha[cer] respetar los contratos mineros con derechos

261 La Razón, El Gobierno envía más policías a Colquiri para evitar conflicto, press article of 1 June 2012, R-213.

262 Página Siete, Gobierno impide salida de mineral de Colquiri, press article of 1 June 2012, R-214 (“el Gobierno impide

la salida de mineral de Colquiri para ser comercializado debido a la toma de la mina por el conflicto que existe entre

mineros y cooperativistas, dió a conocer ayer el presidente ejecutivo de la [COMIBOL], en entrevista con radio ERBOL.

La decisión se asumió el miércoles por la noche después de que el campamento de esa mina fue tomado por

cooperativistas. También la energía eléctrica fue cortada en la zona para evitar que la maquinaria funcione”)

(Unofficial translation: “the Government is preventing Colquiri ore from being transferred to be sold due to the mine

being taken over as a result of the existing conflict between miners and cooperativistas, stated the executive president

of [COMIBOL] yesterday during an interview with radio ERBOL. The decision was made on Wednesday night after

cooperativistas took control over the mine compound. Electricity was also cut in the area to prevent the machinery

from functioning”).

263 Statement of Claim, ¶ 97.

264 Mamani, ¶ 28 (“La toma de un yacimiento tan grande como Colquiri tuvo una repercusión en todo el sector minero

nacional. Muy rápidamente, varios sindicatos y organizaciones productivas rechazaron la toma de la Mina Colquiri.

Por esta misma razón, el 31 de mayo de 2012, la Federación Sindical de Trabajadores Mineros de Bolivia […], entidad

que agrupa a los distintos sindicatos mineros del país, convocó a un ampliado nacional de emergencia en la localidad

de Caracollo, a unos 39 kilómetros de la Mina, para discutir las acciones violentas de los cooperativistas”) (Unofficial

translation: “The takeover of a site as large as Colquiri had repercussions over the entire national mining sector.

Rapidly, several unions and productive organizations rejected the takeover of the Colquiri Mine. For this same reason,

on 31 May 2012, the [FSTMB], an entity formed by the different mining unions of the country, convened an emergency

national meeting in the town of Caracollo, some 39 kilometers from the Mine, to discuss the violent actions of the

cooperativistas”).

265 Mamani, ¶ 29 (“Recuerdo que, aunque ninguno de los presentes creíamos conveniente un enfrentamiento violento con

los cooperativistas, sí acordamos la necesidad de ejercer presión (incluso por la fuerza) para asegurar nuestras fuentes

de trabajo. Por este motivo, y a partir de esta fecha, la FSTMB bloqueó las rutas de Caracollo a La Paz y Colquiri (la

única vía de acceso a la Mina) y exigió la presencia de representantes del Gobierno Nacional”) (Unofficial translation:

“I recall that, although no one present thought that a violent confrontation with the cooperativistas was desirable, we

did agree that it was necessary to put pressure (including by force) to ensure our work sources. For this reason, and

from this date, FSTMB blocked the routes that lead from Caracollo to La Paz and Colquiri (the only way to access the

Mine) and demanded the presence of representatives of the National Government”).

Page 70: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

65

preconstituidos del distrito minero de Colquiri” as well as to “proteger el ejercicio del trabajo

y la estabilidad laboral.”266 As Claimant admits,267 following this meeting, the Government

worked closely with Glencore and the unions in order to prepare a proposal that could satisfy

all of the parties involved in the conflict.

199. On that same day, COMIBOL and officers from the Ministries of Mines and Labour held a

meeting with the leaders of the Cooperativa 26 de Febrero. At this meeting, the Government

first suggested to hand over the San Antonio vein to the Cooperativa 26 de Febrero to put an

end to the conflict.268 Over the following three days, in an attempt to solve the conflict, the

Government sought Sinchi Wayra’s and the unions’ support to work on this proposal, and

prepared up to 5 different offers which were then submitted to the cooperativistas.269

200. On 6 June 2012, the Minister of Mines made a last offer to the Cooperativa 26 de Febrero,

on the basis of the workers’270 and Sinchi Wayra’s commitments.271 The Government stated

that, “[e]n atención a las demandas planteadas y con el objetivo de coadyuvar en la solución

de los problemas que nos atingen, adjunto para conocimiento y consideración las notas […]

suscritas por el Presidente Ejecutivo [de Colquiri] Eduardo Capriles Tejada, donde se

compromete a crear 200 puestos de trabajo, como también ceder la veta San Antonio a su

cooperativa a través de COMIBOL.”272 The Government further advised that Sinchi Wayra

266 Minutes of understanding with the Sindicato de Trabajadores Mineros de Colquiri and the Federación Sindical de

Trabajadores Mineros de Bolivia of 3 June 2012, C-115 (Unofficial translation: “ensure the observance of mining

contracts including pre-existing rights in the mining district of Colquiri […and] protect work and employment

stability”).

267 Statement of Claim, ¶ 101.

268 La Patria, En suspenso acuerdo entre Gobierno y mineros sindicalizados y cooperativistas, press article of 4 June 2012,

C-117.

269 La Razón, Minería hace 5 ofertas, pero aun no convence a los cooperativistas, press article of 5 June 2012, R-215.

270 Mamani, ¶¶ 32-33 (“Según lo que entendimos, el Gobierno estaba buscando el apoyo de la empresa Sinchi Wayra para

entregar a los cooperativistas nuevas áreas en la Mina. Sin embargo, la prensa publicó que las conversaciones no

habían avanzado porque los representantes de la cooperativa debían consultar la propuesta con sus bases. A pesar de

lo anterior, y con el fin lograr una salida negociada al conflicto, los miembros del STMC aceptamos que Sinchi Wayra

hiciera un nuevo ofrecimiento a los cooperativistas. El 5 de junio de 2012, la compañía minera Colquiri confirmó al

Estado su intención de crear 200 nuevos puestos de trabajo en la compañía y ceder la veta San Antonio a la Cooperativa

26 de Febrero. Esta veta tiene un acceso a través de una rampa puesta en funcionamiento en 2007 por Sinchi Wayra y

puede ser explotada comercialmente en los niveles 240 y 325.”) (Unofficial translation: “From what we understood, the

Government was seeking Sinchi Wayra’s support to allocate new areas of the Mine to the cooperativistas. However,

the press reported that discussions had not progressed because the representatives of the cooperative had to consult the

proposal with their bases. This notwithstanding, and with the objective of achieving a negotiated end to the conflict, we

the members of STMC agreed that Sinchi Wayra make a new offer to the cooperativistas. On 5 June 2012, Compañía

Minera Colquiri confirmed to the State its intention to create 200 new work positions in the company and to assign the

San Antonio vein to the Cooperativa 26 de Febrero. This vein includes an access through a ramp commissioned in 2007

by Sinchi Wayra and can be commercially exploited at levels 240 and 325”).

271 Letter from Colquiri (Mr Capriles) to the Minister of Mining (Mr Virreira) and Comibol (Mr Córdova) of 5 June 2012,

C-120.

272 Letter from the Ministry of Mines to the Cooperativa 26 de Febrero of 6 June 2012, R-216 (Unofficial translation:

“[r]egarding the requests submitted and with the aim of assisting in the resolution of issues that concern us, I attach,

for your knowledge and consideration, the notes […] subscribed by the Executive President [of Colquiri] Eduardo

Page 71: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

66

“expresa su disposición a otorgar a la Cooperativa 26 de Febrero un financiamiento de hasta

US$ 1.000.000 […] más la ayuda técnica para la puesta en marcha de un ingenio,”273 and

summoned their leaders to a meeting on that same day.

201. The Government’s proposal, however, was not acceptable to the cooperativistas. Years of

mismanagement of the Mine had made it reasonable for the Cooperativa 26 de Febrero to

believe it could take over the most profitable areas of the Mine and even to expel the operator

company.274 Mr Cachi indeed recalls:

Cuando presentamos esta propuesta a las bases, hubo un rechazo casi generalizado.

Además de que consideraban que la concentración de mineral en esta veta no era

muy alta, su intención para ese entonces era tener acceso a las zonas con mayor

reserva de mineral. Por ese motivo, el acuerdo para ceder la veta San Antonio fue

rechazado por voto de los cooperativistas en Asamblea General.275

202. Claimant contends that the cooperativas did not accept the Government’s proposal because

of the Government’s “lack of response to their demands.”276 Such an assertion is both

inaccurate and nonsensical.

203. First, as explained above, the demands by the Cooperativa 26 de Febrero—and the tensions

it created with the workers of the company— were “atendidas en gran medida y hasta el

momento por nuestra empresa”, as Colquiri acknowledged.277 If Glencore decided not to

involve the Government in its relations with the cooperativas (and the treatment of their

demands), it is the only party to be blamed for the “lack of response to their demands.”278

Capriles Tejada, where he commits to create 200 working positions, as well as to assign the San Antonio vein to your

cooperative through COMIBOL”).

273 Letter from the Ministry of Mines to the Cooperativa 26 de Febrero of 6 June 2012, R-216 (Unofficial translation:

“manifests its willingness to finance the Cooperativa 26 de Febrero up to US$ 1,000,000 […] in addition to technical

assistance for the commissioning of a concentrate plant”).

274 La Patria, Colquiri: Mineros suspenden labores y cooperativistas no aceptan veta, press article of 5 June 2012, C-118

(“Entretanto, los trabajadores cooperativistas, que se reunieron en el distrito minero de Colquiri, determinaron no

aceptar la oferta de acceder a la veta ‘San Antonio’ en su totalidad y continúan con su exigencia de ‘sacar’ a la empresa

de aquella localidad minera”) (Unofficial translation: “Meanwhile, the cooperativistas who held meetings in the mining

district of Colquiri, decided not to accept the offer of the ‘San Antonio’ vein in its entirety and continue to require the

company’s ‘exit’ from the mining town”).

275 Cachi, ¶ 36 (Unofficial translation: “When we presented this proposal [from the Government and the company] to the

bases, it was largely refused. In addition to considering that the ore concentration in this vein [i.e., San Antonio] was

not very high, their intention by then was to gain access to areas with major ore reserves. For this reason, the agreement

to assign the San Antonio vein was refused by vote of the cooperativistas during a General Assembly”).

276 Statement of Claim, ¶ 98.

277 Letter from Colquiri SA (Mr Capriles Tejada) to Comibol (Mr Córdova Eguivar) of 3 April 2012, C-30 (Unofficial

translation: “have been addressed so far and to a large extent by our company”).

278 Statement of Claim, ¶ 98.

Page 72: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

67

204. Second, since the time Comsur operated the Mine, COMIBOL had followed up with Colquiri

on the situation and agreements with the cooperativas279 and had even sought to assign areas

to the cooperativistas “que no sea[n] siempre [en] Colquiri.”280 However, the particular

social context of Colquiri made such solution difficult (if not impossible) to achieve. As

Mr Cachi explains, “[e]n el caso de la Mina, los cooperativistas éramos los mismos

habitantes de Colquiri que habíamos trabajado la Mina (ya sea como trabajadores de la

empresa o subsidiarios) durante décadas. Por ello, no era extraño que algunas familias

tuvieran cooperativistas y trabajadores viviendo conjuntamente de la Mina.”281

205. Third, Claimant admits that the cooperativas are a powerful and significant actor in Bolivian

politics,282 in particular since the events in 2003 which prompted Sánchez de Lozada’s

resignation and created the basis for a new political agenda in the country.283 Given the

constitutional284 and legal285 protection to which the cooperativistas are entitled, as well as the

agreements they had entered into with COMIBOL, with both Sinchi Wayra’s and Comsur’s

approval,286 Claimant could not have reasonably expected that the Government simply expel

279 See, for instance, Letter fom Sinchi Wayra to COMIBOL of 8 September 2006, R-196; Letter from COMIBOL to

Colquiri of 4 June 2007, R-206; Letter from COMIBOL to Colquiri of 3 September 2007, R-207.

280 Internal Memorandum from COMIBOL to the Ministry of Mines of 23 January 2004, R-152, p. 4 (Unofficial translation:

“that are not always [in] Colquiri”).

281 Cachi, ¶ 15 (Unofficial translation: “[i]n the case of the Mine, we the cooperativistas were the same inhabitants of

Colquiri who had worked at the Mine (either as the company’s employees or as subsidiarios) for decades. Therefore,

it was not strange that some families had cooperativistas and mining employees living side by side off the Mine”).

282 Statement of Claim, ¶ 87.

283 See section 2.5.2 above.

284 Constitution of Bolivia of 7 February 2009, C-95, Article 351 (I) (“El Estado, asumirá el control y la dirección sobre

la exploración, explotación, industrialización, transporte y comercialización de los recursos naturales estratégicos a

través de entidades públicas, cooperativas o comunitarias, las que podrán a su vez contratar a empresas privadas y

constituir empresas mixtas”) (Unofficial translation: “The State will assume control and direction over the exploration,

exploitation, industrialization, transport and sale of strategic natural resources through public, cooperative or

community entities, which at the same time, may contract with private companies and create public-private

partnerships”).

285 Supreme Decree No. 29272 of 12 September 2007, R-169, p. 160 (“El rol activo del Estado también se expresará en su

función de protagonista y promotor de una actividad minera planificada, racional, inclusiva, moderna, sistematizada,

y socialmente aceptable, en la que participen de manera armónica e integral el sector público, pueblos indígenas,

originarios, comunidades campesinas y los otros subsectores: grande, mediano, chico y cooperativo. Además, por

tratarse de un sector estratégico para el desarrollo nacional, el Estado brindará la seguridad necesaria para su

desarrollo y expansión”) (Unofficial translation: “The State’s active role shall also be exercised through its function as

a promoter and protagonist of a mining activity which is planned, rational, inclusive, modern, systemised and socially

acceptable, in which may participate in a harminosed and wholesome manner the public sector, indigenous

communities, rural communities and other subsectors: large, medium, small and cooperative. Furthermore, considering

it is a strategic sector for the national development, the State will ensure the necessary security for its development and

expansion”).

286 See Public Deed No. 003/2000, amendment to the lease agreement between COMIBOL and the subsidiarios of the

Colquiri Mine of 5 January 2000, R-93; Public Deed No. 131/2000, lease agreement between Comibol and the

Cooperativa 26 de febrero of 13 October 2000, R-94, clause 5 (“A petición de la Cooperativa y en virtud de los planes

y proyectos de explotación que tiene, COMIBOL resuelve ampliar el plazo de vigencia del contrato hasta veinte años

computables a partir de la fecha de suscripción del contrato principal No. 50/98 de diez/cero siete/[98]”) (Unofficial

translation: “Pursuant to the Cooperativa’s request and in light of its exploitation plans and projects, COMIBOL decides

to extend the contract term to twenty years as of the date of execution of the main contract No. 50/98 of ten/zero

Page 73: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

68

them upon demand. This was all the more so given the grave social conflict created by

Colquiri—first under Comsur’s then under Sinchi Wayra’s administration—over the years.287

206. What is more, retaking control of mining assets such as the Mine by the force had proven

utterly counterproductive in the past. In fact, in 1996, during Sánchez de Lozada’s first tenure,

the military intervened at the Amayapampa project (in the Potosí Department) in order to

protect the mining concessions of the Canadian company Da Capo Resources. This action

was prompted by the uprising of the mining workers and local communities of the region

against that private investor. However, this course of action only provoked a violent

confrontation with the local population, which led to the tragic result of 7 people dead, about

a hundred wounded, and the suspension of the project.288

207. In the meantime, the rejection of the Government’s proposals by the cooperativistas caused

great consternation among the workers and their union leaders. As Mr Mamani explains, the

presence of Colquiri at the Mine, in the circumstances, did not make sense any longer, and the

reversion of the Mine Lease became an option the workers were keen to consider.

Como vimos que las negociaciones no avanzaban y que las ambiciones de la

Cooperativa 26 de Febrero no eran otras sino hacerse a la totalidad de la mina,

nos pareció que no tenía sentido que la Empresa Sinchi Wayra siguiera a cargo de

su operación. Por esta misma razón, y para evitar un enfrentamiento violento con

los cooperativistas, acordamos con el Gobierno explorar la posibilidad de revertir

la operación de la Mina a la COMIBOL. Esta misma solución ha sido aplicada en

otros proyectos mineros en Bolivia exitosamente, como fue el caso del Distrito

Minero de Huanuni. En dicho distrito, la nacionalización de los derechos de

explotación del yacimiento a favor de la COMIBOL en 2006 solucionó un grave

conflicto desatado por las ambiciones de los cooperativistas de hacerse al 100% de

la mina.289

208. Likewise, it no longer made sense for the Government to try to involve Glencore in the

negotiations. On the one hand, the cooperativistas were adamant regarding the expulsion of

seven/[98]”); COMIBOL internal report on Cooperativa minera 26 de febrero Ltda. of 25 April 2012, R-217; Public

Deed No. 0215/2009, amendment to the lease agreement between COMIBOL and the Cooperativa 26 de Febrero of 21

October 2009, R-210.

287 See Section 2.6.3.1 above.

288 See, for instance, La Razón, Amayapampa, un proyecto ‘fantasma’ , press article of 4 April 2016, R-218; La Patria, La

masacre de “Navidad”, Amayapampa y Capasirca, press article of 19 March 2014, R-219.

289 Mamani, ¶ 36 (Unofficial translation: “Since we saw that negotiations were not progressing and that the ambitions of

the Cooperativa 26 de Febrero were none other than to acquire the entirety of the mine, we thought it made no sense

for Sinchi Wayra to remain in charge of operating it. For this reason, and in order to avoid a violent confrontation with

the cooperativistas, we agreed with the Government to explore the possibility to revert the Mine’s operation to

COMIBOL. This same solution has been successfully applied in other mining projects in Bolivia, as was the case for

the Huanuni Mining District. In this district, the nationalization of exploitation rights over the deposit in favour of

COMIBOL in 2006 resolved an important conflict which had been triggered by the cooperativistas’ ambitions to take

control over 100 % of the mine”).

Page 74: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

69

the company from the Mine and were ready to keep negotiating only “con los trabajadores

asalariados y las autoridades del rubro.”290 On the other hand, the mining workers had lost

all confidence in Glencore’s ability to solve the problem and to guarantee their jobs at the

Mine. In Mr Mamani’s words, the workers advised the directors of Sinchi Wayra “nuestras

preocupaciones (sobre todo, por la forma como la empresa había venido cediendo y

entregando áreas de la Mina desde hacía mucho tiempo a los cooperativistas) y que en esos

momentos críticos no solamente se estaba jugando la estabilidad laboral de nuestros

trabajadores, sino el futuro mismo de la Mina. Para nosotros, ya era claro que Sinchi Wayra

había perdido el control de la Mina y la confianza de sus propios trabajadores.”291

209. On 7 June 2012—after the Government had discussed in La Paz the option of reverting the

Mine with both the workers292 and the cooperativistas293—the Colquiri workers and the

villagers of Colquiri convened a meeting in a square only 2 km away from the main mouth of

the Mine (still under control of the cooperativistas). This meeting quickly evolved into a great

general open council (Gran Cabildo) where the social conflict at Colquiri was to be

discussed.294 Persuaded by the magnitude of this event, a significant portion of the

290 La Patria, Colquiri: Mineros suspenden labores y cooperativistas no aceptan veta, press article of 5 June 2012, C-118

(Unofficial translation: “with the employees and the authorities of the sector”).

291 Mamani, ¶ 37 (Unofficial translation: “our concerns (in particular, regarding the manner in which the company had

been assigning and relinquishing areas of the Mine gradually and for a long time) and that during those critical

moments, the employment stability of our workers as well as the future of the Mine itself were at stake. In our opinion,

there was no doubt that Sinchi Wayra had lost control over the Mine and the trust of its own workers”).

292 La Patria, Gobierno plantea nacionalizar Colquiri para poner fin a conflicto minero, press article of 6 June 2012, R-

221 (“El Gobierno planteó ayer la nacionalización de la mina Colquiri, operada por la empresa privada Sinchi Wayra,

para poner fin al conflicto minero que se suscitó desde el pasado miércoles 30 de mayo cuando los trabajadores de la

cooperativa minera ‘26 de Febrero’ tomaron el yacimiento”) (Unofficial translation: “The Government proposed

yesterday the nationalization of the Colquiri mine, operated by the private company Sinchi Wayra, in order to put an

end to the mining conflict commenced last Wednesday 30 May when the workers of the cooperativa minera ‘26 de

Febrero’ took control over the deposit”).

293 La Razón, Virreira y cooperativa discuten ampliación de áreas de trabajo, press article of 8 June 2012, R-26 (“El

miércoles [i.e., 6 June 2012], Virreira reiteró la propuesta a la cooperativa de ‘rescindir el contrato de arrendamiento’

con la compañía privada para que la administración de la mina Colquiri pase a manos de la Corporación Minera de

Bolivia (Comibol), previo “acuerdo común” entre los cooperativistas y los trabajadores asalariados. Álvaro ratificó

que los cooperativistas ‘repudian’ la medida porque ‘en nuestro sector trabajamos sin restricción de edad y sólo

algunos serían incorporados a los asalariados’”) (Unofficial translation: “On Wednesday [i.e., 6 June 2012], Virreira

reiterated the proposal to the cooperative to ‘terminate the lease agreement’ with the private company so that the

administration of the Colquiri mine be reverted to the Bolivian Mining Corporation (Comibol), following a ‘common

agreement’ between cooperativistas and employees. Álvaro backed the idea that the cooperativistas ‘repudiate’ the

measure because ‘in our sector we work without age restrictions and only some would be incorporated as employees’”).

294 Mamani, ¶ 39 (“Entretanto, los miembros del STMC y la FSTMB nos desplazamos nuevamente hasta la población de

Colquiri, donde iniciamos una reunión en Cabildo con una masiva participación de los pobladores e instituciones vivas

del poblado (juntas vecinales, autoridades indígenas originarias, gremios, transportistas, etc.). Nuestra reunión se

instaló en la Plaza 6 de Agosto, a unos 2km de la bocamina Sanjuanillo, donde las bases de la Cooperativa 26 de

Febrero se encontraban reunidas con la presencia de algunos dirigentes que querían desvirtuar la propuesta de

nacionalización.”) (Unofficial translation: “Meanwhile, we the members of STMC and FSTMB travelled again to the

village of Colquiri, where we initiated a Council meeting attended by a great number of the village population and

central institutions of the village (neighbourhood council, authorities of indigineous communities, guilds, transporters,

etc.) Our meeting was set up in the Plaza 6 de Agosto, some 2 km from the Sanjuanillo mine mouth, where the bases of

Page 75: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

70

cooperativistas decided to take part in the Gran Cabildo in order to decide on the future of

the Mine. Mr Cachi reminds the reasons that led to this decision:

Cuando este cabildo fue convocado, algunos de los cooperativistas que estábamos

en Asamblea General en la bocamina Sanjuanillo (un 40%) decidimos abandonar

la Asamblea para unirnos al cabildo. En el cabildo, los trabajadores criticaron a la

empresa Sinchi Wayra por su manejo de las relaciones entre los trabajadores y los

cooperativistas. Además, criticaban a Sinchi Wayra por hacernos enfrentar entre

hermanos. Por estos motivos, el cabildo aprobó la nacionalización de la Mina al

ser ésta la única alternativa. Algunos de los cooperativistas estaban de acuerdo con

esta propuesta. Eso se debía a que, si el Estado retomaba el control de la Mina,

podríamos volver a trabajar en mejores condiciones (como en la época en que

COMIBOL administró la Mina). Nuestro objetivo era ingresar a la nómina de

trabajadores de la Mina y acceder a sus beneficios sociales.295

210. In fact, the Government addressed to this Gran Cabildo the same proposal that it had been

discussing with the parties in conflict in La Paz. In addition to reverting the Mine Lease, the

Government suggested to hire the cooperativistas as COMIBOL employees.296 This, as

Mr Cachi explains, represented a substantial improvement for their working conditions.297

211. At the end of this Gran Cabildo, the cooperativistas, the workers of Colquiri and the villagers

favoured the reversion of the Mine Lease.298

the Cooperativa 26 de Febrero were assembled, together with some leaders who wanted to subvert the nationalisation

proposal.”).

295 Cachi, ¶¶ 38-39 (Unofficial translation: “When this council was convened, some of us, the cooperativistas who were in

the General Assembly at the Sanjuanillo mine mouth (around 40%), decided to abandon the Assembly to join the council.

In the council, the workers criticised Sinchi Wayra for its management of relations between workers and cooperativistas.

Furthermore, they criticized Sinchi Wayra for making us fight between brothers. For these reasons, the council

approved the nationalisation of the Mine, as only alternative. Some of the cooperativistas agreed with this proposal.

This was due to the fact that if the State recovered control over the Mine, we would be able to work under better

conditions (as when COMIBOL administered the Mine). Our objective was to join the Mine’s employee ranks and have

access to their social benefits)”. See, also, Video Bolivia, Enfrentamiento en Mina Colquiri. Hay Heridos, June 2012

(Video), R-222 (“Al momento nos indican que los cooperativistas estarían divididos, ya que algunos de ellos habrían

decidido ser parte de lo que es los mineros asalariados”) (Unofficial translation: “Presently they indicate that the

cooperativistas would be divided, since some of them would have decided to join the mining employees”).

296 Proposal from the Government to the Cabildo of Colquiri, R-27 (“Esta reversión supone varios compromisos del Estado

(COMIBOL) para cumplir con los trabajadores actuales y nuevos en Colquiri. Estos compromisos son los siguientes:

mantener los puestos de trabajo de todos y cada uno de los trabajadores, mantener sus niveles salariales, mantener y

respetar sus conquistas sociales y laborales, incorporar a los ex cooperativistas a la planilla de la COMIBOL, dar a

COMIBOL el capital operativo y dar a COMIBOL el capital de inversión para el desarrollo de la mina”) (Unofficial

translation: “This reversion implies several commitments by the State (COMIBOL) towards current and new employees

in Colquiri. These commitments are the following: maintain the work positions of each and every one of the employees,

maintain their salaries, maintain and respect their social and employment achievements, incorporate the former

cooperativistas into the workforce of COMIBOL, provide COMIBOL with operational capital and provide COMIBOL

with investment capital to develop the mine”).

297 Cachi, ¶ 51.

298 Operative vote of the Gran Cabildo de Colquiri of 7 June 2012, R-17; La Patria, Mineros asalariados y cooperativistas

aceptan rescisión de contrato en Colquiri, press article of 8 June 2012, R-223 (“mineros asalariados y cooperativistas

determinaron […] aceptar la rescisión del contrato de arrendamiento de Colquiri […] para evitar enfrentamientos por

la explotación de minerales y demanda de fuentes de empleo […].Ese pronunciamiento surgió un día después que el

Gobierno pidió a ambos sectores un ‘acuerdo social’ para terminar con el conflicto que desataron los cooperativistas,

el 30 de mayo reciente, cuando tomaron esa mina en demanda de nuevas áreas de explotación”) (Unofficial translation:

Page 76: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

71

212. Glencore—who was aware of the efforts to settle the dispute undertaken by the Government299

and the probable outcome of the Gran Cabildo— decided to capitalize on the divisions among

the cooperativistas. In particular, on 7 June 2012, the same day the Gran Cabildo was taking

place at Colquiri, Glencore decided to take advantage that the Federación Nacional de

Cooperativas Mineras (“FENCOMIN”) actively opposed the reversion, and convened a

meeting in La Paz with a fraction of the members of the Cooperativa 26 de Febrero that

opposed the reversion. Glencore also secured the presence of a lower rank official from the

Ministry of Mines in this meeting (who was not very familiar with the negotiations) in order

to give the appearance of governmental support.

213. On 7 June 2012, being fully aware of the wide support in favour of the reversion of the Mine

(as Mr Eksdale confirms,)300 Glencore International, through Sinchi Wayra and Colquiri,

executed in La Paz an agreement in order to assign to the cooperativas the Rosario vein at the

Mine (the “Rosario Agreement”).301

214. In sum, contrary to Claimant’s contention, it was Sinchi Wayra who engaged in

“inconsistent”302 agreements when faced with the opposition of its own employees and a

significant part of the cooperativistas.

“mining employees and cooperativistas determined […] to accept the termination of the Colquiri lease agreement […]

to prevent confrontations due to ore exploitation and the demand for work sources […]. This statement intervened one

day after the Government requested from both sectors a ‘social agreement’ to end the conflict triggered by the

cooperativistas on 30 May when they took control over that mine, requesting additional exploitation areas”).

299 See, in particular, Mamani, ¶ 37 (“Los abogados de Bolivia me indican que la Demandante sostiene que la empresa

Sinchi Wayra no estaba al tanto de todas estas conversaciones entre el STMC, la FSTMB y el Estado que condujeron

al gobierno a contemplar la nacionalización. Me sorprende tal afirmación. La empresa Sinchi Wayra no solamente

sabía que estábamos sentados en la mesa con el Gobierno, sino que estaba informada de la propuesta que nos hizo el

gobierno. Recuerdo que, alrededor del 5 de junio de 2012, justo después de la reunión donde consideramos la

nacionalización, recibimos una llamada desde el exterior del presidente de Sinchi Wayra, quien me indicó que debíamos

rechazar las propuestas del gobierno y que la empresa privada tenía las posibilidades de garantizarnos nuestras fuentes

de trabajo”) (Unofficial translation: “Counsel for Bolivia informs me that Claimant contends that Sinchi Wayra was not

aware of all those conversations between STMC, FSTMB and the State, which led the government to contemplate the

nationalization. I am surprised by such a statement. Sinchi Wayra was not only aware that we were sat at the table

with the Government but was also informed of the proposal that the government made us. I recall that around 5 June

2012, just after the meeting where we considered the nationalization, we received an external call from the president of

Sinchi Wayra, who indicated that we had to refuse the government’s proposals and that the private company had the

ability to guarantee our work sources”).

300 Eskdale, ¶ 91 (“On or around 6 June 2012, the Minister of Mining proposed the nationalization of the Colquiri Mine.

The union workers, although initially opposed to nationalization, now favored the proposal since they were eager to

regain access to the mine and avoid more violent confrontation as well as additional days out of work”).

301 Agreement between Colquiri SA, Fedecomin, Fencomin, Central Local de Cooperativas Mineras de Colquiri,

Cooperativa Minera Collpa Cota, Cooperativa Minera Socavón Inca, and Cooperativa 26 de Febrero, C-35.

302 Statement of Claim, ¶¶ 11; 106.

Page 77: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

72

215. Glencore’s actions created significant unrest among the mining workers and cooperativistas

at Colquiri and escalated the conflict to new and unprecedented levels of violence. As Mr

Mamani recalls:

[E]l 8 de junio de 2012, descubrimos que la empresa Sinchi Wayra había negociado

en La Paz un acuerdo para entregar a varias cooperativas la veta Rosario a cambio

de levantar la toma de la Mina. Este acuerdo generó un desconcierto generalizado

entre los miembros del sindicato y confirmó nuestras sospechas de que, si la Mina

seguía en manos de la empresa privada, nada iba a asegurar nuestras fuentes de

trabajo. Por estos motivos, los miembros del STMC y la FSTMB decidimos

tomarnos por la fuerza el yacimiento minero para expulsar a los cooperativistas

que aún estaban congregados en la bocamina Sanjuanillo. Esto provocó un grave

enfrentamiento violento que duró varias horas (hasta cerca de la medianoche). Esta

situación ratificó el deseo de los miembros del sindicato y de la población de

Colquiri de que el Estado retomase el control sobre de la Mina.303

216. Blockades, public demonstrations in Oruro304 and violence between the workers and

cooperativistas ensued as a consequence of the Rosario Agreement. While the Government

had first tried to reach a compromise assigning the Rosario vein to the cooperativistas in the

following days,305 this was not acceptable for the mining unions. Conversely, nothing less

than the entire Rosario vein appeared acceptable for the cooperativistas favourable to the

Rosario Agreement. Glencore’s actions had thus led the Government to an insurmountable

impasse.306

303 Mamani, ¶¶ 41-42 (emphasis added) (Unofficial translation: “[O]n 8 June 2012, we discovered that Sinchi Wayra had

negotiated in La Paz an agreement to assign the Rosario vein to several cooperatives in exchange for lifting the takeover

of the Mine. This agreement generated generalized confusion amongst the union members and confirmed our suspicion

that if the Mine remained under the private company’s control, nothing would ensure our work sources. For these

reasons, we the members of the STMC and the FSTMB decided to take control over the mining deposit by force in order

to expel the cooperativistas that were still congregated at the Sanjuanillo mine mouth. This caused a violent

confrontation that lasted various hours (almost until midnight). This situation confirmed the will of the union members

and of the population of Colquiri for the State to recover control over the Mine”). See, also, Cachi, ¶¶ 43-44 (“En vista

de lo anterior, luego de que se conoció la firma del acuerdo para ceder la veta Rosario, los trabajadores de la empresa

anunciaron que se tomarían la Mina por la fuerza. Los cooperativistas que estábamos en Colquiri reiteramos nuestro

respaldo. Esto desató un conflicto violento entre, por un lado, los trabajadores de la Mina y la facción de los

cooperativistas que exigíamos la nacionalización y, por el otro, la otra facción de cooperativistas que querían el control

de la veta Rosario”) (Unofficial translation: “In light of the foregoing, after the conclusion of the agreement to assign

the Rosario vein became known, the company’s workers announced that they would take control over the Mine by force.

The cooperativistas who were in Colquiri reiterated our support. This triggered a violent conflict between, on the one

hand, the Mine workers and the cooperativistas faction requesting the nationalization, and on the other hand, the

cooperativistas faction wanting to take control over the Rosario vein”).

304 See, for instance, La Patria, Marcha de cooperativistas provoca destrozos en propiedad privada, press article of 12 June

2012, C-130.

305 See Minutes of Agreement among Fencomin, Fedecomin, Central Local de Cooperativas Mineras de Colquiri,

Cooperativa Minera Collpa Cota, Cooperativa Minera Socavón Inca, Cooperativa 26 de Febrero, The Ministry of Mining

and COMIBOL, C-129.

306 Romero, ¶ 23.

Page 78: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

73

217. On 13 June 2012, around a thousand mining workers blocked routes307 and requested from

the Government a clear statement, in light of the contradictory information published by the

press following the Rosario Agreement.308 The miners’ protest quickly evolved into a violent

confrontation during 14 and 15 June 2012.309 These events required again the intervention of

the Government as a mediator in order to definitely resolve the conflict created by Glencore.

2.6.3.3 In Order To Resolve The Violent Conflict Caused By The Rosario Agreement, The

Government Negotiated With The Cooperativistas And The Union Leaders

218. On 17 June 2017, following the violent confrontation with the cooperativistas at Colquiri, the

company’s mining workers sent a letter to the Bolivian Vice-President, ratifying their

intention to honour the Gran Cabildo resolution. In their letter, the union leaders requested

(i) a decree ordering the reversion of the Mine Lease, and (ii) measures against “el grupo

minoritario que quedó en la coop. 26 de febrero,”310 which was attempting to forcibly

implement the Rosario Agreement. The Government responded to this request by convening

a meeting between the parties in La Paz.

219. As Minister Carlos Romero, witness for Bolivia explains, the violent confrontations between

the cooperativistas and workers from Colquiri in June 2012 changed the nature of the conflict

in the eyes of the State. While, up until then, the Government was facing a mining conflict,

the outcome and the magnitude of the final violent confrontation could turn it into a social

307 Mineros de Colquiri bloquean conani exigiendo la emisión del D.S. de Nacionalización, Video (2012), R-224.

308 La Patria, Mineros bloquean Conani exigiendo nacionalizar el 100% de mina Colquiri, press article of 13 June 2012,

C-134 (“Según el secretario general del Sindicato de Trabajadores Mineros de Colquiri, Severino Estallani, no está

clara la figura de la nacionalización de la mina, pues se pretende revertir para el Estado una parte del yacimiento y

ceder otra a los cooperativistas que también estaban movilizados. Desde las 15:00 horas de ayer los mineros, que

permanecían en vigilia en Conani desde el viernes pasado con bloqueos esporádicos, decidieron obstruir

permanentemente la carretera, hasta que se efectúe una reunión con el vicepresidente del Estado Plurinacional de

Bolivia, Álvaro García Linera para que se nacionalice toda la mina”) (Unofficial translation: “According to the

secretary general of the Colquiri Mining Union, Severino Estallani, the option to nationalise the mine is not clear, since

the intention is to revert to the State part of the deposit and assign another part to the cooperativistas who were also

mobilised. Since yesterday at 15:00 the mining workers, who had been keeping watch in Conani since last Friday with

sporadic blockades, decided to block the highway permanently, until a meeting is convened with the vicepresident of

the Plurinational State of Bolivia, Álvaro García Linera, to nationalise the entire mine”).

309 La Prensa, Colquiri se convierte en un campo de batalla, press article of 15 June 2012, C-142 (“Mineros asalariados y

afiliados a la cooperativa 26 de Febrero se enfrentaron ayer con dinamita y palos por el control de la mina Colquiri,

mientras el Gobierno volvió a convocarlos para dialogar en procura de encontrar una solución al conflicto que ya lleva

dos semanas. La llegada de la noche y la explosión de cachorros de dinamita generaron zozobra entre los pobladores

de Colquiri, quienes pedían entre sollozos la llegada de efectivos policiales y la pacificación de la zona, que está

ubicada en la provincia Inquisivi, del departamento de La Paz”) (Unofficial translation: “Mining employees and

affiliates to the cooperativa 26 de Febrero clashed yesterday, [using] dynamite and sticks, over control of the Colquiri

mine, while the Government again summoned them to discuss with a viewt to find a solution to the conflict that has

already lasted two weeks. Nightfall and the explosion of dynamite sticks generated anxiety amongst Colquiri’s

population, who requested, sobbing, the arrival of police forces and the appeasement of the area, located in the province

of Inquisivi, in the department of La Paz”).

310 Letter from the Sindicato Mixto de Trabajadores Mineros de Colquiri to the Vicepresident of the Plurinational State of

Bolivia of 17 June 2012, R-28 (Unofficial translation: “the minority group that remained in the coop. 26 de febrero”).

Page 79: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

74

one. For this reason, the negotiations were henceforth led by the Government Ministry (and

Minister Romero) and not by the mining authorities.311

220. The meeting requested by the Government eventually took place on 19 June 2012 in the

premises of the Government Ministry. After a long and difficult discussion, the parties

reached an agreement pursuant to which:

a. the State would “recuperar las áreas mineras otorgadas en contrato de arrendamiento

a la Compañía Minera Colquiri S.A. para beneficio de la población boliviana en su

conjunto y de Colquiri en particular”;

b. a significant portion of “[l]a veta Rosario en forma vertical queda en poder de la

Cooperativa 26 de Febrero Ltda […]” in exchange for the rest of areas of the Mine in

which this cooperativa was operating; and

c. measures against the stealing of ore and materials at the Mine would be implemented.312

221. The text of the agreement also stressed that “[l]a viabilización de estos acuerdos exige a

ambas partes la deposición de actitudes de confrontación y la inmediata pacificación del

Distrito Minero de Colquiri.”313

222. The agreement executed under the aegis of the Government Ministry laid the foundation for

the reversion of the Mining Lease. On 20 June 2012, the Government issued Supreme Decree

No. 1.264 (the “Mine Lease Reversion Decree”),314 pursuant to which the Mine Lease was

311 Romero, ¶ 11 (“La intervención del Ministerio de Gobierno fue necesaria puesto que, en los primeros días de junio, se

produjo una grave confrontación violenta en la Mina (los medios de comunicación reportaron varios heridos y

detonaciones de dinamita en la población de Colquiri). La gravedad de los enfrentamientos hizo que, para el Gobierno,

el conflicto cambiara de naturaleza. Ya no se trataba simplemente de una disputa minera (lo que justificaba la

intervención del Ministerio de Minería y Metalurgia y COMIBOL) sino, más bien, de un conflicto social que requería

acciones urgentes y la intervención del Ministerio de Gobierno en el marco de sus competencias”) (Unofficial

translation: “The intervention of the Ministry of Government was necessary given that during the first days of June, a

serious confrontation took place in the Mine (the media reported several injured people and dynamite detonations in

the village of Colquiri). The severity of the confrontations implied, in the eyes of the Government, that the conflict had

changed in nature. It was no longer a mining dispute (which justified the intervention of the Ministry of Mines and

Metallurgy and COMIBOL) but rather a social conflict that required urgent actions and the intervention of the Ministry

of Government, within the framework of its attributions”).

312 Agreement between the Government of Bolivia, COB, Fencomin, FEDECOMIN-LP, FSTMB, Central de Cooperativas

de Colquiri, and Sindicato Mixto de Trabajadores Mineros de Colquiri of 19 June 2012, R-18 (Unofficial translation:

“[The State would] recover the mining areas leased to Compañía Minera Colquiri S.A. for the benefit of the Bolivian

population in its entirety and of Colquiri in particular’ […] ‘[A significant part of t]he Rosario vein in vertical form

remains under the control of the Cooperativa 26 de Febrero Ltda’”).

313 Agreement between the Government of Bolivia, COB, Fencomin, FEDECOMIN-LP, FSTMB, Central de Cooperativas

de Colquiri, and Sindicato Mixto de Trabajadores Mineros de Colquiri of 19 June 2012, R-18 (Unofficial translation:

“[t]he viability of these agreements requires that both parties abandon all conflictual attitude and the immediate

appeasement of the Mining District of Colquiri”).

314 Supreme Decree No 1.264 of 20 June 2012, C-39.

Page 80: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

75

reverted to the State. As noted by Minister Romero, the Mine Lease Reversion Decree granted

legal recognition to the agreements the Government had reached with cooperativistas and

mine workers the day before.315

223. Even though it was a favourable solution to the conflict, the Mine Lease Reversion Decree

and the agreement which prompted it were not entirely satisfactory for the parties. In fact,

given “la determinación de los representantes de los cooperativistas de no ceder la veta

Rosario”316 (a consequence of the Rosario Agreement negotiated by Glencore), the

Government had to face a new confrontation between the cooperativistas and the COMIBOL

workers. The actions of Sinchi Wayra were still an obstacle to the resolution of the social

conflict, even after the Reversion of the Mine. As Minister Romero recalls:

Poco tiempo después de suscribir el Acta de Acuerdo en junio de 2012, y de la

promulgación del Decreto Supremo de Reversión, se dieron nuevos enfrentamientos

entre cooperativistas y trabajadores de la Empresa Minera Colquiri (ahora

controlada por COMIBOL). Según estos reportes, y a pesar de lo negociado en

junio de 2012, los trabajadores seguían disconformes en que la veta Rosario -la

más atractiva de la Mina- estuviese casi en su totalidad en manos de los

cooperativistas. Los cooperativistas, por su parte, continuaban expresando que

tenían derecho a la referida veta, por el acuerdo obtenido con Sinchi Wayra y que

además existía un acuerdo firmado con los trabajadores con visto bueno del

Estado […].

Las tensiones volvieron a degenerar rápidamente en actos violentos en septiembre

de 2012, lo que hizo necesaria nuevamente la intervención del Ministerio a mi

cargo.317

224. In fact, after the Government delineated the areas of the Rosario vein assigned to the

Cooperativa 26 de Febrero,318 the cooperativistas alleged that the Government was not

following the agreements underlying the Mine Lease Reversion Decree. As a result, they

315 Romero, ¶ 18.

316 Mamani, ¶ 44 (Unofficial translation: “the determination of the cooperativistas’ representatives not to give up the

Rosario vein”).

317 Romero, ¶¶ 19-21 (Unofficial translation: “Shortly after we concluded the minutes of agreement in June 2012 and that

the Reversion Supreme Decree was enacted, new confrontations between cooperativistas and employees of Empresa

Minera Colquiri (now controlled by COMIBOL) took place. Following these reports, and despite the June 2012

negotiations, workers were still not satisfied with the fact that almost the totality of the Rosario vein, the most attractive

in the Mine, was under the cooperativistas’ control. As for the cooperativistas, they continued to contend that they were

entitled to that vein pursuant to the agreement signed with Sinchi Wayra and that furthermore, there was an agreement

signed with the workers that had the State’s green light […]. Tensions rapidly degenerated again in violent acts in

September 2012, and this required again the intervention of the Ministry under my responsibility”).

318 Supreme Decree No. 1.337 of 31 August 2012, R-30.

Page 81: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

76

announced massive demonstrations in La Paz, while the unions of Colquiri declared a general

strike at the Mine.319

225. Over the following days, both cooperativistas and union members from around the country

arrived in La Paz. In the meantime, the Government tried to reach an agreement that could

avoid violent confrontations such as those of June 2012.320

226. On 18 September 2012, during the protest (which quickly turned violent321), “[u]n minero

murió y otros nueve resultaron heridos cuando trabajadores de cooperativas privadas

lanzaron […] dinamita en La Paz contra la sede de la Federación Sindical de Trabajadores

Mineros de Bolivia (Fstmb) donde se encontraban los mineros asalariados de la empresa

Colquiri, con los que se disputan la veta Rosario.”322 As Minister Romero recalls, these

serious events forced a new negotiation.323

227. The Government then worked on a new partition of the Rosario vein that could satisfy the

interests of both the cooperativistas and the workers of Colquiri (now under COMIBOL’s

administration). In Minister Romero’s words, “[d]adas las expectativas que había creado

Sinchi Wayra en los cooperativistas, fue muy difícil que accedieran a un punto medio que no

implicara algo distinto a cederles el cien por ciento de la veta Rosario […]. Luego de arduas

negociaciones en los días finales de septiembre, y sobre la base de planos de las áreas de la

veta Rosario y de la Mina, finalmente logramos acordar una nueva división de la veta Rosario

satisfactoria para las partes enfrentadas.”324

319 América Economía, Se agudiza la tensión entre mineros asalariados y cooperativistas en Colquiri, press article of 16

September 2012, R-225 (“De no resolverse el problema desde este lunes ingresaremos en una huelga masiva en La

Paz”, anunció Edwin Rosales, secretario de Relaciones del Sindicato de Trabajadores de la Empresa Minera Colquiri

(EMC). Esto fue ratificado desde ese distrito por Orlando Gutiérrez, secretario de Conflictos de la misma organización.

En el otro frente, Segundino Fernández, delegado del Comité de Autodefensa de los Cooperativistas Mineros, anunció

que “este martes 120.000 mineros cooperativistas” tomarán las calles de La Paz para protestar por “el incumplimiento

y la falta de solución del Gobierno a este conflicto minero”) (Unofficial translation: “If the problem is not resolved, as

of this Monday we will go on a massive strike in La Paz’, announced Edwin Rosales, secretary of [public] relations of

the Sindicato de Trabajadores de la Empresa Minera Colquiri (EMC). This was confirmed from that district by Orlando

Gutiérrez, secretary of conflicts of the same organisation. On the other side, Segundino Fernández, delegate for the

Committee of Self-defense of the Mining Cooperativistas, announced that ‘this Tuesday 120.000 mining cooperativistas’

will protest in the streets of La Paz against the ‘non-compliance and the absence of a solution provided by the

Government to this mining conflict’”).

320 Los Tiempos, Colquiri aún dialoga y denuncian más tomas, press article of 6 September 2012, R-226.

321 Cooperativistas atacan sede de la FTSMB, video of September 2012, R-227.

322 La Patria, Guerra minera por posesión de yacimientos en Colquiri, press article of 19 September 2012, R-228

(Unofficial translation: “[o]ne miner died and another nine were injured when workers of private cooperativas launched

[…] dynamite in La Paz at the headquarters of the Federación Sindical de Trabajadores Mineros de Bolivia (Fstmb)

where the mining employees of Colquiri, with whom they are clashing over the Rosario vein, were located”).

323 Romero, ¶ 25. See, also, El Día, Baja la tensión en el conflicto de Colquiri, press article of 27 September 2012, R-229.

324 Romero, ¶¶ 23-25 (Unofficial translation: “[g]iven the expectations created by Sinchi Wayra on the part of the

cooperativistas, it was very difficult for them to agree to an intermediate solution which would imply anything other

Page 82: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

77

228. On 30 September 2012, the Government announced that a new agreement had been reached

regarding the Rosario vein. This new agreement provided for a new partition of the Rosario

vein.325 On 3 October 2012, as was the case with the Mine Lease Reversion Decree, the

government gave this new agreement legal standing through Supreme Decree 1.368 of

2012.326

229. In sum, and as both Mr Mamani and Mr Cachi confirm,327 the Government’s actions in 2012

effectively put an end to the serious social conflict created by Colquiri, under Sinchi Wayra’s

administration. As discussed below,328 since the Mine passed under the operatorship of

COMIBOL, neither tensions nor violence of the magnitude of the events in 2012 have

resurfaced. This has been the case even though a part of the Mine remains under the control

of the cooperativistas.

2.7 Bolivia Has Negotiated With Glencore International In Good Faith

230. Claimant contends that Bolivia has “acted in bad faith”329 and that “Bolivia was not intent on

actually reaching an agreement”330 with Glencore International over the course of the

negotiations that followed the reversion of the Assets (the “Negotiations”). Claimant’s

portrayal of the Negotiations is inaccurate and goes against Glencore International’s

confidentiality obligations agreed therewith.

231. First, it bears reminding that Claimant did not partake in the Negotiations. The Swiss

company Glencore International was the party negotiating with the State in the Negotiations

for almost a decade. In fact:

than to assign them one hundred per cent of the Rosario vein […]. After difficult negotiations during the final days of

September, and on the basis of plans of the areas of the Rosario vein and the Mine, we finally reached an agreement to

divide the Rosario vein that was satisfactory to both parties in conflict”).

325 Jornada, El fin del conflicto minero de Colquiri se traducirá en Decreto Supremo, press article of 1 October 2012, R-

230.

326 Supreme Decree No. 1.368 of 3 October 2012, R-32.

327 Mamani, ¶ 47; Cachi, ¶¶ 50-51.

328 See section 2.8.1 infra.

329 Statement of Claim, ¶ 222.

330 Statement of Claim, ¶ 116.

Page 83: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

78

a. On 22 February 2007, after Bolivia issued the Tin Smelter Reversion Decree,331

Glencore International sent a letter to the President of the State protesting such

measure. Negotiations with Glencore International ensued.332

b. On 14 May 2010, after Bolivia issued the Antimony Smelter Reversion Decree,333

Glencore International again sent a letter to the President of the State complaining about

this measure. In this letter, Glencore noted the good faith of the Bolivian State in the

negotiations concerning the Tin Smelter (mentioning that “en él se avanzó mucho y

falta poco para lograr un acuerdo amistoso definitivo, libre de presiones y litigios”334).

Negotiations with Glencore International, as opposed to Claimant, ensued.

c. On 27 June 2012, after Bolivia issued the Mine Lease Reversion Decree,335 Glencore

International sent a letter to the President of the State complaining about this measure.

Negotiations with Glencore International, as opposed to Claimant, ensued.336

232. Second, to accuse Bolivia of bad faith in the Negotiations simply goes against reason. Had

Glencore truly believed that negotiating with Bolivia was futile, it would have not carried out

the Negotiations with the State:

a. For almost 10 years following the issuance of the Tin Smelter Reversion Decree;

b. Over 7 years following the issuance of the Antimony Smelter Reversion Decree; and

c. Over 5 years following the issuance of the Mine Lease Reversion Decree.

233. Third, contrary to Bolivia, Claimant has acted in procedural bad faith by revealing details of

the Negotiations that are clearly protected by confidentiality agreements.

234. On the one hand, on 6 October 2008, representatives of Sinchi Wayra and Bolivia met and

executed minutes laying out the framework of the negotiations following the Tin Smelter

Reversion Decree. The provisions of this agreement would cover negotiations concerning

331 Supreme Decree No 29.026 of 7 February 2007, C-20.

332 Letter from Freshfields Bruckhaus Deringer (Mr Blackaby) to Ministry of the Presidency (Mr Quintana Taborga) of 4

April 2007, C-23.

333 Supreme Decree No 499 of 1 May 2010, C-26.

334 Letters from Glencore (Mr Mate and Mr Glasenberg) to the President of Bolivia (Mr Morales Ayma) and the Ministry

of Mining (Mr Pimentel Castillo) of 14 May 2010, C-27 (Unofficial translation: “major progress was made and little

remains to be done in order to reach an amicable and final agreement, free of pressure and disputes”).

335 Supreme Decree No 1.264 of 20 June 2012, C-39.

336 Letter from Glencore International PLC (Mr Capriles) to the Minister of Mining (Mr Virreira) of 3 July 2012, C-145.

Page 84: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

79

“Proyecto Mina Bolívar, Porco, Colquiri, y Vinto Estaño y Antimonio.”337 As regards of

confidentiality, Sinchi Wayra and the State further agreed the following:

Se acuerda que ninguna de las Partes podrá difundir, hacer uso de la información

generada durante el proceso de negociación, ante cualquier instancia judicial o

extra judicial de la República o cualquier otro país o tribunal de arbitraje

internacional o jurisdiccional.

Las Partes dejan expresa constancia que en caso de que la información llegara a

ser presentada ante cualquier foro de arbitraje o tribunal jurisdiccional, nacional

o extranjero, no se le reconocerá mérito alguno a dichos antecedentes en el proceso,

aún en el caso que sea presentada por terceros.338

235. On the other hand, Glencore International confirmed on several occasions that the content,

discussions and proposals of the Negotiations would remain confidential and would not be

submitted to any international tribunal. Indeed, Glencore advised Bolivia that its participation

in any meeting concerning the Assets “está sujeta al entendimiento acordado de que toda

discusión e información intercambiada entre las Partes (Glencore y Bolivia) será mantenida

en estricta confidencialidad y no podrá ser utilizada en ningún ámbito o foro, sea judicial o

arbitral, relacionado con la solución de controversias o demandas sobre inversiones o

semejantes.”339

236. Notwithstanding this clear commitment, Claimant (and Mr Eksdale) have disclosed

confidential information regarding the negotiations with Bolivia in these proceedings (in

particular, concerning the offers made by the State in compensation for the Tin Smelter).

337 Minutes of First Meeting of Negotiations between Bolivia and Sinchi Wayra S.A of 6 October 2008, R-231.

338 Minutes of First Meeting of Negotiations between Bolivia and Sinchi Wayra S.A of 6 October 2008, R-231, section (c)

(Unofficial translation: “It is agreed that the Parties will not diffuse, make use of the information generated during the

negotiating process, before any judicial or extrajudicial instance of the Republic or of any other country or international

arbitration or jurisdictional tribunal. The Parties attest that if this information is presented before any arbitration

forum or jurisdictional tribunal, national or foreign, no legal force will be attached to this background information in

the process, even if presented by third parties”).

339 Letter from Glencore International (Mr Eskdale) to the Ministry of Mining (Mr Navarro) attaching a letter to the Office

of the Attorney General (Mr Menacho) of 28 July 2015, C-151. See also, Letter from Glencore International (Mr

Eskdale) to the Minister of Mining (Mr Navarro) of 12 August 2015, C-152 (“Tal asistencia está sujeta al entendimiento

acordado de que toda discusión e información intercambiada entre las Partes (Glencore y Bolivia) será mantenida en

estricta confidencialidad y no podrá ser utilizada en ningún ámbito o foro, sea judicial o arbitral, relacionado con la

solución de controversias o demandas sobre inversiones o semejantes”); Letter from Glencore International to the

Minister of Mines of 18 September 2015, R-232 (“Tal asistencia está sujeta al entendimiento acordado de que toda

discusión e información intercambiada entre las Partes (Glencore y Bolivia) será mantenida en estricta

confidencialidad y no podrá ser utilizada en ningún ámbito o foro, sea judicial o arbitral, relacionado con la solución

de controversias o demandas sobre inversiones o semejantes”); Letter from Glencore International (Mr Eskdale) to the

Attorney General (Mr Arce) of 30 September 2015, C-154 (“Tal asistencia está sujeta al entendimiento acordado de

que toda discusión e información intercambiada entre las Partes (Glencore y Bolivia) será mantenida en estricta

confidencialidad y no podrá ser utilizada en ningún ámbito o foro, sea judicial o arbitral, relacionado con la solución

de controversias o demandas sobre inversiones o semejantes”) (Unofficial translation: “Such assistance is subjected to

the agreed understanding that every discussion and information exchanged between the Parties (Glencore and Bolivia)

shall be kept strictly confidential and shall not be used in any field or forum, be it judicial or arbitral, related to the

resolution of disputes or claims over investments or similar”).

Page 85: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

80

237. Bolivia reserves all of its rights in this regard and, in particular, the right to produce documents

regarding the Negotiations at a further, appropriate stage of these proceedings.

238. In any event, Bolivia confirms that, as described above, the State negotiated in good faith with

Glencore International for almost 10 years. As Mr Eskdale confirms,340 over the course of

these Negotiations, Bolivia made several offers and engaged in wilful attempts to resolve the

present dispute.

2.8 The State Made Significant Investments After The Reversion Of The Smelters And The

Reversion Of The Mine Lease

239. Following the reversion of the Assets, the State made significant investments in the Tin

Smelter (Section 2.8.1). Likewise, the State has invested in the Mine and worked closely with

COMIBOL employees and the cooperativistas in order to prevent events like the ones that led

to the Reversion (Section 2.8.2).

2.8.1 In Order To Increase Their Capacity, The State Made Large Investments At The Tin

Smelter

240. After years of private operation with no substantial investments in the Tin Smelter, the State

had to lay out a new strategy in order to modernize and ensure the viability of this asset. As

Eng Villavicencio explains, this strategy required a significant financial effort, which has been

successfully carried out in recent years.341

241. The State has invested around US$ 39 million in the Tin Smelter for the acquisition of a

vertical pit furnace for processing tin concentrates (the “Ausmelt Furnace”), in addition to 3

to US$ 4 million on sustaining investment.342 In Eng Villavicencio’s words, this state-of-the-

art equipment was instrumental in order to expand production of the Tin Smelter and to

improve the performance of the State Company EMV.343

340 Eskdale, ¶ 116.

341 Villavicencio, ¶ 44.

342 Villavicencio, ¶ 53.

343 Villavicencio, ¶¶ 47; 58.

Page 86: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

81

New Ausmelt

Furnace at

Vinto344

2.8.2 The State Has Invested In The Colquiri Mine And Managed To Solve The Social Crisis

Created With The Mining Cooperatives

242. Following the events of September 2012, Bolivia carried out significant investments in the

Mine and made significant efforts to prevent conflicts, thereby managing to solve the social

crisis between cooperatives and mining workers.

243. In fact, the State Company, Empresa Minera Colquiri, under COMIBOL’s control, has

undertaken extensive exploration programmes and investments (the most important being the

construction of a new concentrator plant and the refurbishing of the ramp at the Blanca vein.)

These investments represent approximately US$ 75.8 and US$ 11.5 million respectively.345

As a result, Colquiri’s tin production levels increased from 1.072,29 metric tons in 2012 to

4.230,95 metric tons of tin concentrates in 2016.346

244. In parallel, Colquiri has made significant efforts in order to prevent serious social conflicts

similar the ones that took place under Sinchi Wayra’s administration. This was possible, in

large part, due to the fact that COMIBOL offered the cooperativistas the possibility to join

the Mine’s workforce under the same employment conditions as those granted to other

344 Villavicencio, ¶ 50.

345 Colquiri Annual Operations Report for 2017, R-233, pp. 40-43.

346 Colquiri Annual Operations Report for 2017, R-233, p. 49.

Page 87: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

82

employees347 and to the fact that ambitious social responsibility plans were put in place by the

State company.348

245. In fact, the majority of Colquiri’s employees are currently former cooperativistas. As

mentioned in a recent Colquiri report, “[l]a nacionalización atinada por parte del Estado

Boliviano, ha dado paso a la generación de más de 800 nuevos empleos directos con trabajo

digno, se tiene más de 5.000 asegurados y beneficiarios que gozan de seguridad social a corto

plazo con calidad y calidez, convirtiendo al Seguro Delegado de la Empresa Minera Colquiri

como un verdadero Seguro Social modelo.”349

3. THE LAW APPLICABLE TO THE DISPUTE

246. Although Claimant would largely restrict the law applied in this dispute to nothing more than

the Treaty, a wider range of norms are both relevant and applicable in this arbitration.

247. Because the Treaty does not specify the applicable law, Article 35(1) of the UNCITRAL Rules

controls the issue. It provides, in this case, that “the arbitral tribunal shall apply the law

which it determines to be appropriate.”350 The appropriate law to apply includes the Treaty,

but also international human rights treaties and Bolivian law.

248. Despite the Treaty’s lack of an applicable law provision, Claimant attempts to assert that the

Treaty largely displaces any other legal norms. As Claimant argues, “[t]he application of the

substantive provisions of the Treaty, as lex specialis, is incontestable.”351

249. But this assertion is fundamentally misconceived. The principle of lex specialis applies when

it applies and not otherwise. Simply asserting that the Treaty applies as lex specialis cannot

substitute for analyzing whether it satisfies the legal requirements for lex specialis. In

347 Mamani, ¶ 47 (“A pesar de que hubo serios enfrentamientos posteriores en 2012, las tensiones entre los cooperativistas

y los trabajadores de la Mina fueron reduciéndose paulatinamente gracias a las medidas adoptadas por el Gobierno.

Esto se debió, en gran parte, a que la COMIBOL contrató a todos los cooperativistas que quisieron, de manera

voluntaria, cambiar de régimen y convertirse en trabajadores regulares de la Mina (como lo prometió el Gobierno

durante las negociaciones”) (emphasis added) (Unofficial translation: “[a]lthough there were subsequent serious

confrontations in 2012, tensions between cooperativistas and the Mine workers progressively decreased due to the

measures adopted by the Government. This was due, to a large extent, to the fact that COMIBOL hired all the

cooperativistas who voluntarily wanted, to change regime and become regular workers of the Mine (as promised by the

Government during the negotiations)”. See, also, Cachi, ¶ 50.

348 Empresa Minera Colquiri, “Minería Responsable y Sustentable”, 2017, R-234, p. 8.

349 Empresa Minera Colquiri, “Minería Responsable y Sustentable”, 2017, R-234, p. 2 (emphasis added) (Unofficial

translation: “the nationalization carried out by the Bolivian State has generated more than 800 new direct and decent

work positions. More than 5,000 are insured and benefit from social insurance in the short term with quality and

warmth, thus transforming the Delegated Insurance of Empresa Minera Colquiri into a model Social Insurance”).

350 UNCITRAL Arbitration Rules, CLA-94, Art. 35(1).

351 Statement of Claim, ¶ 120.

Page 88: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

83

particular, a treaty applies as lex specialis only when it addresses the same subject matter as

another rule of international law and does so with more specificity. This was the conclusion

of Prof. Koskenniemi in his authoritative study of legal fragmentation: “if a matter is being

regulated by a general standard as well as a more specific rule, then the latter should take

precedence over the former.”352

250. In the present dispute, the Treaty provides the legal basis for Claimant’s claims, nothing more.

Like most investment treaties, it does not address any substantive legal issues except the

general legal protections to which an investor is entitled. Thus, legal rules and principles that

address matters other than legal protections for investors do not regulate the same matter as

the Treaty. They cannot be displaced by the Treaty standards.

251. At points, Claimant seems to admit as much. It asserts that “[t]he Treaty is to be supplemented

by other rules of international law since, as the Vienna Convention provides, treaties are

‘governed by international law’ and must be interpreted in the light of ‘any relevant rules of

international law applicable.’”353

252. Bolivia agrees that the Treaty must be interpreted in light of other applicable rules of

international law. These rules include other treaties to which Bolivia is a party, including

treaties governing human rights. Thus, the Treaty provisions cannot displace, and are limited

by, Bolivia’s obligations to respect and protect human rights under, inter alia, the

International Covenant for Civil and Political Rights and the American Convention on Human

Rights.354

253. Apart from international law, Bolivian law also applies to the dispute because that law defines

the legal rights to the Assets that were held in Bolivia. It is a fundamental assumption of

investment law that domestic law creates the property and contractual rights that are subject

to international protections. Zachary Douglas explains that “[t]he law applicable to an issue

relating to the existence or scope of property rights comprising the investment is the municipal

352 United Nations International Law Commission, Fragmentation of International Law: difficulties arising from the

diversification and expansion of international law of 13 April 2006, RLA-1, ¶ 56.

353 Statement of Claim, ¶ 121.

354 International Covenant on Civil and Political Rights of 16 December 1966, RLA-2; American Convention on Human

Rights of 22 November 1969, RLA-3.

Page 89: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

84

law of the host state, including its rules of private international law.”355 Recent tribunals, like

Vestey Group356 and Emmis,357 reiterate this view.

254. Thus, the Tribunal must not narrowly focus on the Treaty provisions, but also employ other

applicable norms from international law and Bolivian law that limited these provisions.

4. THE CLAIMS ARE NOT SUBJECT TO JURISDICTION AND ARE INADMISSIBLE

255. In its Statement of Claim, Claimant does no more than make summary allegations that its

claims are admissible and subject to this Tribunal’s jurisdiction.358 It builds these allegations

on the flimsiest of evidentiary foundations, declining to submit into evidence the very

contracts through which Glencore International acquired its so-called investment or any

details about the so-called investor itself.359

256. This lack of evidence should be the cause of deepest concern and justifies the bifurcation of

these proceedings. It is Claimant’s burden to prove that its claims are admissible and subject

to the jurisdiction of an investment tribunal. It is for Claimant to prove with sufficient

certainty (and not for Bolivia to prove the contrary) that each and every one of the conditions

for admissibility and jurisdiction have been met, including the consent of the Parties. Indeed:

The burden of proof for the issue of consent falls squarely on a given claimant who

invokes it against a given respondent. Where a claimant fails to prove consent with

sufficient certainty, jurisdiction will be declined.360

257. Claimant has not come close to meeting this burden. Claimant made no investment in Bolivia

(Section 4.1). Moreover, Claimant committed an abuse of process in bringing this arbitration

(Section 4.2) and brings this arbitration on the basis of illegally privatized Assets

(Section 4.3). The Tribunal also lacks jurisdiction to hear this case under the UK – Bolivia

Treaty since Claimant’s true nationality is Swiss—not British (Section 4.4). Also, Claimant

presents its claims contrary to mandatory ICC arbitration clauses (Section 4.5), and it submits

the Tin Stock claims without properly notifying Bolivia (Section 4.6). Claimant’s claims

355 Z. Douglas, The International Law of Investment Claims, 2009, RLA-4, ¶ 101 et seq.

356 Vestey Group Ltd v. Bolivarian Republic of Venezuela, ICSID Case No. ARB/06/4, Award of 15 April 2016, RLA-5, ¶

194.

357 Emmis International Holding and others v. Hungary, ICSID Case No. ARB/12/2, Award of 16 April 2014, RLA-6, ¶

162.

358 Statement of Claim, section IV.

359 Statement of Claim, section IV.

360 ICS Inspection and Control Services Limited (United Kingdom) v. The Argentine Republic, PCA Case No. 2010-9,

Award on Jurisdiction of 10 February 2012, RLA-7, ¶ 280.

Page 90: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

85

must therefore be summarily rejected in a separate preliminary objections phase for each and

every one of these reasons.

4.1 The Tribunal Lacks Jurisdiction Because Glencore Bermuda Made No Investment In

Bolivia

258. Claimant argues that “Glencore Bermuda has made qualifying investments in Bolivia” and so

it is entitled to protection under the Treaty.361 This is straightforwardly false. Glencore

Bermuda did not make any investment at all in Bolivia. It merely held legal title to assets for

which it made no payment and to which it made no further contribution. This is insufficient

to warrant Treaty protection; Glencore Bermuda lacks the necessary link with its purported

investments. Thus, there can be no jurisdiction over its claims.

259. It is a general principle of investment law that a so-called investor is entitled to investment

treaty protection only if it actively invests in the territory of a contracting party. As the

Standard Chartered Bank tribunal put it, “Claimant’s status as treaty investor, […] implicates

Claimant doing something as part of the investing process, either directly or through an agent

or entity under the investor’s direction.”362

260. Recent investment jurisprudence has confirmed the jurisdictional requirement. Notably, the

Vestey Group tribunal concluded that, “[i]n line with a series of more recent decisions, the

Tribunal is of the opinion that the BIT notion of investment implies that the asset falling within

the list be the result of an allocation of resources made by the investor.”363 Other tribunals to

hold similarly include Orascom TMT v. Algeria,364 KT Asia v. Kazakhstan,365 Isolux v.

Spain,366 Alps Finance v. Slovak Republic,367 and Romak v. Uzbekistan.368

361 Statement of Claim, ¶ 131.

362 Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award of 2 November

2012, RLA-8, ¶ 198.

363 Vestey Group Ltd v. Bolivarian Republic of Venezuela, ICSID Case No. ARB/06/4, Award of 15 April 2016, RLA-5,

¶ 192.

364 Orascom TMT Investments S.à r.l. v. People’s Democratic Republic of Algeria, ICSID Case No. ARB/12/35, Award of

31 May 2017, RLA-9, ¶¶ 371-372.

365 KT Asia Investment Group BV v Republic of Kazakhstan (ICSID Case No ARB/09/8) Award of 17 October 2013, CLA-

118, ¶¶ 164-168 (“Without such a commitment of resources, the asset belonging to the claimant cannot constitute an

investment within the meaning of the ICSID Convention and the BIT.”).

366 Isolux Infrastructure Netherlands, BV v. Kingdom of Spain, SCC Case No. V2013/153, Award of 12 July 2016, RLA-

10, ¶ 686.

367 Alps Finance and Trade AG v. Slovak Republic, UNCITRAL, Award [Redacted] of 5 March 2011, RLA-11, ¶¶ 231-

236.

368 Romak S.A. (Switzerland) v. The Republic of Uzbekistan, UNCITRAL, PCA Case No. AA280, Award of 26 November

2009, RLA-12, ¶¶ 180, 207.

Page 91: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

86

261. The active investment requirement is a manifestation of the concept of investment underlying

investment treaties. As the Romak tribunal explained, “the term ‘investments’ under the BIT

has an inherent meaning (irrespective of whether the investor resorts to ICSID or UNCITRAL

arbitral proceedings) entailing a contribution that extends over a certain period of time and

that involves some risk.” 369 The basic concept of investment requires a connection to an

investor in the form of an economic contribution. It is this concept that is embodied in

investment treaties.

262. In fact, the requirement is not in serious dispute between the Parties. Claimant’s own primary

authority on this requirement,370 the Bayindir tribunal, confirms that the investor must itself

make a substantial contribution of funds to warrant investment Treaty protection.371 As that

tribunal held, “[c]onsidering Bayindir’s contribution both in terms of know how, equipment

and personnel and in terms of injection of funds, the Tribunal considers that Bayindir did

contribute ‘assets’ within the meaning of the general definition of investment set forth in

Article I(2) of the BIT.”372

263. Nor is it in serious dispute that Glencore Bermuda utterly failed to make any active

contribution of assets. Claimant tacitly admits as much.373 It admits that Glencore Bermuda

simply received transfer of the assets without payment: “once the investments were acquired

by Glencore International, they were immediately transferred to Glencore Bermuda.”374 It

also admits that Glencore Bermuda itself did not invest funds in Bolivia: “Glencore Bermuda,

through its affiliates, has invested hundreds of millions of dollars in Bolivia and its economy

[…].”375

264. However, the Treaty establishes a requirement that a protected investor must make an active

investment (Section 4.1.1), and Glencore Bermuda made absolutely no active investment in

the territory of Bolivia or anywhere else (Section 4.1.2).

369 Romak S.A. (Switzerland) v. The Republic of Uzbekistan, UNCITRAL, PCA Case No. AA280, Award of 26 November

2009, RLA-12, ¶ 207.

370 Statement of Claim, ¶ 130.

371 Bayindir Insaat Turizm Ticaret Ve Sanayi AŞ v Islamic Republic of Pakistan (ICSID Case No ARB/03/29) Decision on

Jurisdiction of 14 November 2005, CLA-60, ¶¶ 118-121.

372 Bayindir Insaat Turizm Ticaret Ve Sanayi AŞ v Islamic Republic of Pakistan (ICSID Case No ARB/03/29) Decision on

Jurisdiction of 14 November 2005, CLA-60, ¶ 121.

373 Statement of Claim, ¶ 314.

374 Statement of Claim, ¶ 314.

375 Statement of Claim, ¶ 314.

Page 92: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

87

4.1.1 The Treaty Extends Arbitral Jurisdiction Only To Companies Or Individuals That

Actively Invest

265. The Treaty establishes a jurisdictional requirement that the investor must actively invest, in

that the investor must direct the making and implementation of the investment. As is well

known, Article 31(1) of the Vienna Convention instructs that the Treaty be interpreted “in

accordance with the ordinary meaning to be given to the terms of the treaty in their context

and in the light of its object and purpose.”376 The active investment requirement follows

straightforwardly from such an interpretation.

266. The terms of the Treaty presume that an investor must actively invest in order to be subject to

jurisdiction under the Treaty. Article 8(1) of the Treaty establishes that Bolivia’s consent to

arbitrate was limited to disputes concerning an investment of a company of the other Party:

Disputes between a national or company of one Contracting Party and the other

Contracting Party concerning an obligation of the latter under this Agreement in

relation to an investment of the former which have not been legally and amicably

settled shall after a period of six months from written notification of a claim be

submitted to international arbitration if either party to the dispute so wishes.377

267. Because Bolivia denounced the Treaty as of May 2014, the Treaty’s Article 13 sunset

provision adds a further jurisdictional requirement: any protected investment must have been

made when the Treaty was in force. Claimants acknowledge this requirement.378 The Treaty

text is clear:

Provided that in respect of investments made whilst the Agreement is in force, its

provisions shall continue in effect with respect to such investments for a period of

twenty years after the date of termination and without prejudice to the application

thereafter of the rules of general international law.379

268. These and other provisions of the Treaty make clear that an investor must actively invest in

order to receive Treaty protection. Throughout its text, the Treaty speaks of an active

relationship between an investor and the investment, using slightly different phrases

interchangeably to describe this relationship.380 It repeatedly uses verbs that imply “some

376 Vienna Convention on the Law of Treaties, 1155 UNTS 331 of 23 May 1969, CLA-6, Article 31(1).

377 Treaty, C-1, Article 8(1).

378 Statement of Claim, ¶ 125.

379 Treaty, C-1, Article 13.

380 See, for instance, Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award

of 2 November 2012, RLA-8, ¶ 219 (“Neither provision suggests a relationship different from that otherwise regulated

by the BIT. On its face, each uses ‘investments by investors’ or ‘investment by nationals and companies’

interchangeably with the phrase ‘investments of a national or company’ employed elsewhere in the BIT”).

Page 93: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

88

action in bringing about the investment, rather than purely passive ownership.”381 This is

particularly notable in four instances.

269. First, the Treaty leaves no doubt that the investments must be “made,” whether before or after

the Treaty entered into force. Article 1 of the Treaty states that “[i]nvestments made before

the date of entry into force as well as those made after entry into force shall benefit from the

provisions of this Agreement.”382 Regardless of the timing, the Treaty is unequivocal that the

investments must be “made” by the investor.

270. Second, the Treaty specifies that each State party to the Treaty must enable nationals or

companies of the other State party to “invest capital in its territory […].” Article 2(1) of the

Treaty provides that “[e]ach Contracting Party shall encourage and create favourable

conditions for nationals or companies of the other Contracting Party to invest capital in its

territory, and, subject to its right to exercise powers conferred by its laws, shall admit such

capital.”383

271. Third, the Treaty provides that returns from the investment must be allowed in the currency

in which the capital was invested. Article 6 establishes that “[t]ransfers of currency shall be

effected without delay in the convertible currency in which the capital was originally invested

or in any other convertible currency agreed by the investor and the Contracting Party

concerned.”384 This provision assumes that the investor made an investment of capital from

which it is entitled to receive returns in the original currency.

272. Fourth, the Treaty’s sunset provision is clear that the investment must have been “made” prior

to termination. Article 13 states that, “[p]rovided that in respect of investments made whilst

the Agreement is in force, its provisions shall continue in effect with respect to such

investments for a period of twenty years after the date of termination […].”385 This sunset

provision, envisioning an active relationship between investor and investment, is especially

relevant because the Treaty has been terminated and so Claimant relies on it for jurisdiction.386

381 Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award of 2 November

2012, RLA-8, ¶ 222.

382 Treaty, C-1, Article 1.

383 Treaty, C-1, Article 2(1).

384 Treaty, C-1, Article 6(2).

385 Treaty, C-1, Article 13.

386 Statement of Claim, ¶ 125.

Page 94: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

89

273. Thus, across multiple provisions, the Treaty’s terms, interpreted in context, presume that an

active relationship must exist between a protected investor and its investment. In fact, on the

basis of very similar language in the UK-Tanzania BIT, the Standard Chartered Bank tribunal

concluded that “the text of the BIT reveals that the treaty protects investments ‘made’ by an

investor in some active way, rather than simple passive ownership.”387 Thus, absent such an

active relationship, there can be no jurisdiction under the Treaty.

274. And it is not just the text of the Treaty that requires an active relationship for jurisdiction; the

Treaty’s object and purpose provides ample confirmation of the requirement. This is clear for

three principal reasons.

275. First, the preamble of the Treaty makes clear that its object and purpose are to create

favourable conditions for active investment made by nationals and companies of the UK and

Bolivia. The preamble states that the parties desire “to create favourable conditions for

greater investment by nationals and companies of one State in the territory of the other State

[…].”388 The use of the preposition “by” specifies that the national or company of one State

is the actor that invests in the territory of the other State. It implies an active relationship

between investor and investment.

276. Second, the preamble also makes clear that the Treaty’s protection is designed to promote

active investment by nationals and companies of the UK or Bolivia in the territory of the other

State. As the preamble explains, the parties recognize “that the encouragement and reciprocal

protection under international agreement of such investments will be conducive to the

stimulation of individual business initiative and will increase prosperity in both States

[…].”389 But, as the Standard Chartered Bank tribunal observed, that protection could not

promote investment “if the national of the Contracting State had no role in deciding to make

the investment, funding the investment, or controlling or managing the investment after it was

made.”390

277. Third, the Treaty’s purpose of promoting active investment is also reflected in the general

obligation to encourage and create favourable conditions for individuals to invest. Article

2(1) states that “[e]ach Contracting Party shall encourage and create favourable conditions

387 Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award of 2 November

2012, RLA-8, ¶ 225.

388 Treaty, C-1, Preamble.

389 Treaty, C-1, Preamble.

390 Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award of 2 November

2012, RLA-8, ¶ 228.

Page 95: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

90

for nationals or companies of the other Contracting Party to invest capital in its territory,

and, subject to its right to exercise powers conferred by its laws, shall admit such capital.”391

This provision establishes the Treaty’s most general obligation and so reflects its object and

purpose. It is specifically concerned with enabling nationals or companies to invest.

278. In short, the Treaty’s terms, object, and purpose all confirm that the Treaty extends its

protection only to those foreign nationals and companies that have made an active investment

in Bolivia.

4.1.2 Glencore Bermuda Made No Investment In Bolivia, Much Less The Active Investment

Required By The Treaty

279. It is plain that Glencore Bermuda did not make any active investment in Bolivia, whether

directly or indirectly. Claimant has not provided any evidence to the contrary. This is

unsurprising. Glencore Bermuda in fact lacked the capacity to make an active investment, as

it was no more than an empty shell company that apparently did not even have executives.

280. First, Glencore Bermuda did not participate in Glencore International’s acquisition of the

holding companies for the Tin Smelter, Antinomy Smelter, or Colquiri Mine Lease, much less

of those Assets themselves. In this regard, it is striking that Claimant does not even attempt

to allege that Glencore Bermuda made any payment for the Assets.

281. It was Glencore International, not Glencore Bermuda, that was invited to bid on the Tin

Smelter, Antinomy Smelter, and Colquiri Mine Lease. As Claimant admits, “Glencore

International was invited by Argent Partners […] to participate in an auction” that included

the Assets.392 Claimant further admits it was “Glencore International’s bid for the […] assets

[that] was selected in November 2004” and “Glencore International [that] initiated its

[alleged] due diligence process […].”393 Providing ample confirmation that Glencore

Bermuda was not involved, the single exhibit of correspondence put forth to support

Claimant’s supposed due diligence (and which, as shown below, does nothing of the sort) is

not addressed to Glencore Bermuda.394

391 Treaty, C-1, Article 2(1).

392 Statement of Claim, ¶ 34 (citing Process Letter from Argent Partners (Mr Simkin) to Glencore International (Mr

Eskdale) of 30 April 2004, C-62, p. 1).

393 Statement of Claim, ¶ 35.

394 Letter from the Vice Minister of Mining to Glencore of 17 January 2005, C-63.

Page 96: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

91

282. However, what conclusively establishes that Glencore Bermuda never invested in Bolivia is

that Glencore Bermuda never made a payment of any sort for the Assets (or their holding

companies). Claimant concedes that “Glencore International concluded the purchase of the

holding companies of the Assets,”395 although it deliberately omits to submit the actual

purchase agreements (with the purchase price). Instead, it submits only the agreement through

which it assigned the shares from Glencore International to Glencore Bermuda.396 This

agreement displays no payment or consideration of any sort from Glencore Bermuda in

exchange for the assignment of the shares in the holding companies.397 Thus, it is unrebutted

that Glencore Bermuda did not pay a single cent for its so-called investment in Bolivia.

283. Nor did Glencore Bermuda subsequently make any payments to develop the Tin Smelter, the

Antimony Smelter, or the Colquiri Mine, or to Bolivia more generally. This fact is amply

confirmed by the contortions Claimant goes through in an attempt to prove the contrary.

Claimant alleges that Glencore Bermuda “directly employed over 3,500 people”398 when in

fact only Sinchi Wayra and Colquiri directly employed individuals in Bolivia.399 Nor did

Glencore Bermuda allegedly invest “in a diverse range of social initiatives,”400 if anything,

these too were actions taken only by Sinchi Wayra and not Glencore Bermuda, as Claimant

admits and its evidence confirms.401

284. And Claimant’s allegation that Glencore Bermuda spent, through 2012, US$ 550 million in

Bolivia, if anything, confirms that Glencore Bermuda made no investment. The allegation is

based only on bald assertions in letters from Glencore International (not Glencore Bermuda),

confirming that it was Glencore International, if anyone, who made the supposed

expenditures.402 These letters (even if true) do not assert that Glencore Bermuda made a cent

of those expenditures.403

395 Statement of Claim, ¶ 36.

396 Assignment and Assumption Agreements between Glencore International and Glencore Bermuda of 7 March 2005, C-

64.

397 Assignment and Assumption Agreements between Glencore International and Glencore Bermuda of 7 March 2005, C-

64.

398 Statement of Claim, ¶ 61; Sinchi Wayra, “Social Responsibility and Environment”, C-160.

399 Sinchi Wayra, “Social Responsibility and Environment”, C-160; Lazcano, ¶ 43.

400 Statement of Claim, ¶ 61.

401 Lazcano, ¶¶ 41-43; Sinchi Wayra, “Social Responsibility and Environment”, C-160.

402 Statement of Claim, ¶ 62 (citing Letters from Glencore (Mr Maté) to the President of Bolivia (Mr Morales Ayma) of 27

June 2012, C-40).

403 Letters from Glencore (Mr Maté) to the President of Bolivia (Mr Morales Ayma) of 27 June 2012, C-40.

Page 97: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

92

285. A similar failure to commit any resources led the KT Asia tribunal to reject jurisdiction for

failure to make an active investment. The tribunal insisted that, “[w]ithout such a commitment

of resources, the asset belonging to the claimant cannot constitute an investment within the

meaning of the ICSID Convention and the BIT.” 404 After observing that the “the Claimant

acquired the shares” from affiliated companies,405 it found that “the price that the Claimant

paid […] was significantly less than the market value”406 and it “never actually paid even this

price for the BTA shares.”407 In fact, unlike in KT Asia, Glencore Bermuda did not even make

a pretense of payment for the shares; it was simply assigned the rights it passively holds.

286. Second, even in the management and operation of the Tin Smelter, Antimony Smelter, and

Colquiri Mine, Glencore Bermuda was absent from the scene.

287. Critically, we know who was supposedly managing the Assets in Bolivia on behalf of the

Glencore Group. It was Mr Eskdale, Claimant’s witness in this arbitration.408 But Mr Eskdale

worked for Glencore International,409 not for Glencore Bermuda, as Asset Manager for Latin

America, Director of Global Zinc Operations, and as Board Member for Sinchi Wayra,

Colquiri, and Vinto.410 There is not a shred of evidence on record that Mr Eskdale has ever

held a position at Glencore Bermuda, either as employee or as a director. And there is not a

shred of evidence that anyone from Glencore Bermuda had any role in overseeing Sinchi

Wayra, Colquiri, and Vinto in Bolivia.

288. It was Glencore International, not Glencore Bermuda, that issued financial reporting for the

operating subsidiaries Sinchi Wayra, Colquiri, and Vinto. The front page of the December

2005 and December 2006 financial reports for Vinto—submitted by Claimant—prominently

bears the name Glencore International; the documents make no reference whatsoever to

404 KT Asia Investment Group BV v Republic of Kazakhstan (ICSID Case No ARB/09/8) Award of 17 October 2013, CLA-

118, ¶ 166.

405 KT Asia Investment Group BV v Republic of Kazakhstan (ICSID Case No ARB/09/8) Award of 17 October 2013, CLA-

118, ¶ 181-183.

406 KT Asia Investment Group BV v Republic of Kazakhstan (ICSID Case No ARB/09/8) Award of 17 October 2013, CLA-

118, ¶ 181-183.

407 KT Asia Investment Group BV v Republic of Kazakhstan (ICSID Case No ARB/09/8) Award of 17 October 2013, CLA-

118, ¶ 181-183.

408 Eskdale, ¶¶ 6-7.

409 Letter from Sinchi Wayra (Mr Capriles) to the Ministry of the Presidency (Mr Arce) of 11 May 2007, C-76, p. 2 (“El

Sr. Eskdale es ejecutivo de Glencore International AG. con base en Zug, Suiza”).

410 See Eskdale, ¶ 23; Letters from Glencore International (Mr Eskdale) to the Attorney General (Mr Arce), the President

of Bolivia (Mr Morales), the Vice President of Bolivia (Mr García), the Ministry of the Presidency (Mr Quintana), the

Minister of Mining (Mr Navarro), and the President of Comibol (Mr Quispe) of 20 May 2015, C-148.

Page 98: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

93

Glencore Bermuda.411 Nor is Glencore Bermuda mentioned in Colquiri’s financial reports.

Indeed, Glencore International issued the reports for both Colquiri412 and Sinchi Wayra413 in

its own name.

289. In fact, Sinchi Wayra, Colquiri, and Vinto themselves understood that they were subsidiaries

of Glencore International, not of Glencore Bermuda. When each of those companies had an

opportunity to describe their owners during negotiations, they did not even think to mention

Glencore Bermuda, but instead singled out Glencore International as the relevant parent

company.414 It was only in view of launching the present arbitration415 that these companies

were more careful to mention Glencore Bermuda, even though it has previously been a non-

entity.

290. Claimant’s response to the reversions provides ample confirmation that Glencore Bermuda

was uninvolved in Bolivia. As Mr Eskdale testified, “[j]ust days after the nationalization, Mr

Willy R Strothotte, Chairman of Glencore International [not Glencore Bermuda], reached out

to Bolivia […].”416 The Negotiations (and likely this arbitration) were then led by Christopher

411 Vinto S.A. - December 2005, CLEX-11-1; Vinto S.A. - Monthly Report December - 2005, CLEX-11-2; Vinto S.A. -

December 2006, CLEX-11-3

412 Colquiri S.A. - December 2006, CLEX-11-4; Colquiri S.A. - December 2008, CLEX-11-5; Colquiri S.A. - December

2009, CLEX-11-6; Colquiri S.A. - December 2010, CLEX-11-7; Colquiri S.A. - December 2011, CLEX-11-8; Colquiri

S.A. - December 2012, CLEX-11-9.

413 SW Consolidated - Management Report December 2006, CLEX-11-10; Colquiri Profit and Production 2008 2010,

CLEX-11-11; SW Monthly Report - December 2011, CLEX-11-12; SW Monthly Report - December 2012, CLEX-

11-13.

414 Letter from Sinchi Wayra (Mr Capriles) to the Minister of Mining (Mr Echazú) of 20 June 2007, C-83 (“Mediante la

presente hacemos referencia a la reunion sostenida en Palacio de Gobierno en fecha 12 del mes en curso en la cual nos

solicitó que presentemos el monto de la compensación que pide Glencore International AG (‘Glencore’) por la

nacionalización de la Fundición de Estaño de Vinto […]”) (Unofficial translation: “By this letter we refer to the meeting

held in the Government Palace on the 12th of this month during which we were asked to present an amount for the

compensation requested by Glencore International AG (‘Glencore’) for the nationalization of the Vinto Tin Smelter

[…]”); Letter from Colquiri (Mr Capriles) to EMV (Mr Infantes) of 16 April 2007, C-74 (“En consecuencia, la

celebración del Contrato de Suministro de Minerales y Concentrados de Estaño entre nuestras empresas, no implica la

renuncia total o parcial a los derechos señalados por parte de la COMPAÑIA MINERA COLQUIRI S.A ni de sus

accionistas, ni de GLENCORE INTERNATIONAL AG o sus subsidiarias, como inversores últimos de la COMPAÑIA

MINERA COLQUIRI S.A. y de la sociedad COMPLEJO METALURGICO VINTO S.A.”) (Unofficial translation: “As a

result, the execution of the Contract for Supply of Ore and Tin Concentrates between our companies, does not imply a

total or partial waiver of the rights indicated by COMPAÑIA MINERA COLQUIRI S.A or by its shareholders, or by

GLENCORE INTERNATIONAL AG or its affiliates, as ultimate investors of COMPAÑIA MINERA COLQUIRI S.A. and

COMPLEJO METALURGICO VINTO S.A.”); Letter from Complejo Vinto (Mr Capriles Tejada) to Minister of Mining

and Metallurgy (Mr Luis Alberto Echazú A) of 7 December 2007, C-48 (Vinto) (“El compromiso que esta carta

contiene, no implica renuncia de nuestra sociedad, de sus accionistas o de Glencore International A.G. a percibir una

justa indemnización por la nacionalización del Complejo Metalúrgico de Vinto y a ninguno de los derechos que nos

asisten conforme a las leyes […]”) (Unofficial translation: “The commitment contained in this letter does not imply a

waiver by our company, by its shareholders or Glencore International A.G of the award of fair compensation for the

nationalization of Complejo Metalúrgico de Vinto or of any of the rights to which we are entitled in accordance with

the law […]”).

415 Power of Attorney from Glencore Bermuda of 11 December 2007, C-90.

416 Eskdale, ¶ 48.

Page 99: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

94

Eskdale along with Daniel Maté, Glencore International’s Zinc Director.417 And when

Glencore International took the initial steps to bring the present arbitration through the

dormant Glencore Bermuda, it had to designate formal representatives, none of whom appear

to have held any prior position in that shell company. It was at this point that it legally named

as its representatives Christopher Eskdale, Eduardo Enrique Capriles Tejada, and Luis Felipe

Hartmann Luzio.418

291. Glencore Bermuda’s complete lack of control of its so-called investment is comparable to the

facts of Standard Chartered Bank. As that tribunal observed, “[a]bsent any such control, it

is difficult to perceive in this record any evidence that could serve to show that the investment

process was actually made at the direction of Claimant as investor.”419 In its view, the lack

of control made it impossible to demonstrate the active investment required for jurisdiction

under an investment treaty. Because of the “[f]ailure to demonstrate such control,” it held

that “Claimant has been unable to demonstrate its active participation in the investing process

with respect to the Loans.”420 For precisely the same reason, Glencore Bermuda is unable to

show any active investment in Bolivia, with fatal consequences for jurisdiction under the

Treaty.

292. Simply put, Glencore Bermuda was entirely passive throughout its so-called investment in

Bolivia. It never made the activity investment that the Treaty requires for jurisdiction.

4.2 The Tribunal Lacks Jurisdiction Because Glencore Bermuda Committed An Abuse Of

Process By Receiving The Investment When The Dispute Was Foreseeable

293. It is Claimant’s position that the transfer of Glencore International’s holdings to Glencore

Bermuda in 2005 was entirely innocent and so could not have amounted to an abuse of

process. It further adds that, even if it were not innocent, it had purposes other than obtaining

Treaty protection for a foreseeable dispute. It thus insists that there was no abuse.

294. Claimant is simply wrong. A change of ownership structure when there is a reasonable

prospect of a dispute constitutes an abuse of process, requiring that claims be dismissed,

whenever the change had a purpose of obtaining investment treaty protection (Section 4.2.1).

And obtaining investment treaty protection was the only plausible purpose for transferring the

Assets to Glencore Bermuda at a time when changing political conditions in Bolivia foretold

417 Eskdale, ¶ 51.

418 Power of Attorney from Glencore Bermuda of 11 December 2007, C-90.

419 Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award of 2 November

2012, RLA-8, ¶¶ 261.

420 Standard Chartered Bank v. The United Republic of Tanzania, ICSID Case No. ARB/10/12, Award of 2 November

2012, RLA-8, ¶¶ 264.

Page 100: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

95

precisely the dispute at the heart of this arbitration (Section 4.2.2). Thus, the Tribunal must

dismiss Claimant’s claims in this arbitration for abuse of process.

4.2.1 Structuring An Investment To Obtain Treaty Protection When A Dispute Is Foreseeable

Constitutes An Abuse Of Process

295. Claimant argues that there was no abuse of process because “restructuring an investment in

order to obtain treaty protection per se does not amount to an abuse.”421 This is simply an

incorrect statement of the law. International investment law denies both treaty protection and

arbitral jurisdiction to an investment when its ownership structure was changed to gain

investment treaty protection. Such behaviour is per se abusive.

296. The definitive statement of the law comes from the Philip Morris tribunal. After careful

consideration, it held that changing ownership structure when a dispute is foreseeable in order

to gain treaty protection constitutes an abuse of process and eliminates jurisdiction. As the

Philip Morris tribunal put it, “the initiation of a treaty-based investor-State arbitration

constitutes an abuse of right (or abuse of process […]) when an investor has changed its

corporate structure to gain the protection of an investment treaty at a point in time where a

dispute was foreseeable.”422 There is no need to prove additional bad faith; the restructuring

itself constitutes bad faith under the circumstances.423

297. The Philip Morris tribunal reached this conclusion on a thorough review of the prior arbitral

jurisprudence.424 It analyzed in detail the decisions in Tidewater v. Venezuela, Mobil v.

Venezuela, Pac Rim v. El Salvador, Gremcitel v. Peru, Lao Holdings v. Laos, and Chevron v.

Ecuador.425

421 Statement of Claim, ¶ 318.

422 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Award on Jurisdiction and Admissibility of 17

December 2015, CLA-129, ¶ 554.

423 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Award on Jurisdiction and Admissibility of 17

December 2015, CLA-129, ¶ 539.

424 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Award on Jurisdiction and Admissibility of 17

December 2015, CLA-129, ¶¶ 545-553.

425 Tidewater Inc and others v Bolivarian Republic of Venezuela (ICSID Case No ARB/10/5) Decision on Jurisdiction of 8

February 2013, CLA-116; Mobil Corporation, Venezuela Holdings BV, and others v Bolivarian Republic of Venezuela

(ICSID Case No ARB/07/27) Decision on Jurisdiction of 10 June 2010, CLA-97; Pac Rim Cayman LLC v Republic of

El Salvador (ICSID Case No ARB/09/12) Decision on the Respondent’s Jurisdictional Objections of 1 June 2012, CLA-

110; Renée Rose Levy and Gremcitel SA v Republic of Peru (ICSID Case No ARB/11/17) Award of 9 January 2015,

CLA-124; Lao Holdings N.V. v. Lao People’s Democratic Republic, ICSID Case No. ARB/AF/12/6, Decision on

Jurisdiction of 21 February 2014, RLA-13; Chevron Corporation (USA) and Texaco Petroleum Company (USA) v. The

Republic of Ecuador, PCA Case No. 34877, Interim Award of 1 December 2008, RLA-14.

Page 101: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

96

298. The Phoenix Action tribunal clarified why abuse of process excludes claims from investment

arbitration. As it explained in an oft-cited passage, “[t]he abuse here could be called a

“détournement de procédure”, consisting in the Claimant’s creation of a legal fiction in order

to gain access to an international arbitration procedure to which it was not entitled. As stated

in Inceysa, ‘(i)n the contractual field, good faith means absence of deceit and artifice during

the negotiation and execution of instruments that gave rise to the investment.’ It is the

conclusion of the Tribunal that the whole ‘investment’ was an artificial transaction to gain

access to ICSID.”426

299. The prohibition on abuse of process in investment law reflects a broad principle of

international law. In this regard, the World Trade Organization Appellate Body confirmed

that abusive exercises of international rights are prohibited:

[The principle of good faith], at once a general principle of law and a general principle

of international law, controls the exercise of rights by states. One application of this

general principle, the application widely known as the doctrine of abus de droit,

prohibits the abusive exercise of a state’s rights and enjoins that whenever the assertion

of a right ‘impinges on the field covered by [a] treaty obligation, it must be exercised

bona fide, that is to say, reasonably’.427

300. In the field of investment law, changing the ownership structure of an investment to obtain

treaty protection when a dispute is foreseeable is sufficient for abuse of process, for three

reasons. Claimant’s attempts to narrow this well-established principle are unavailing.

301. First, contrary to what Claimant alleges,428 there is no need for the dispute to be highly

foreseeable; reasonable foreseeability—the reasonable prospect of a dispute—is sufficient.

As the Philip Morris tribunal concluded, building on an identical holding from Tidewater,

“[a] dispute is foreseeable when there is a reasonable prospect that a measure that may give

rise to a treaty claim will materialise.”429 It is worth emphasizing that Claimant too invokes

Philip Morris and Tidewater on this point.430 This is for good reason: Philip Morris and

426 Phoenix Action, Ltd. v. The Czech Republic, ICSID Case No. ARB/06/5, Award of 15 April 2009, RLA-15, ¶ 143.

427 United States - Import Prohibition of Certain Shrimp and Shrimp Products, AB-1998-4, World Trade Organization,

Report of the Appellate Body of 8 October 1998, RLA-16, ¶ 158.

428 Statement of Claim, ¶ 320.

429 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Award on Jurisdiction and Admissibility of 17

December 2015, CLA-129, ¶ 585; Tidewater Inc and others v Bolivarian Republic of Venezuela (ICSID Case No

ARB/10/5) Decision on Jurisdiction of 8 February 2013, CLA-116, ¶ 194.

430 Statement of Claim, ¶ 319.

Page 102: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

97

Tidewater consolidated the current understanding of reasonable foreseeability. The earlier

Pac Rim and Alapi tribunals, which Claimant also cites, have been superseded.431

302. Second, despite what Claimant argues,432 a change of ownership structure can be abusive even

when obtaining treaty protection is only one of its purposes. For the opposite proposition,

Claimant places crucial reliance on Gremcitel v. Peru. 433 However, Gremcitel in no way held

that a change of ownership structure is abusive only if there is no other motive for the

change.434 It did find that, on the facts of the case, there was no other motive. The reason

why it is sufficient that obtaining treaty protection is only one of several purposes is that there

must be, in the words of the Phoenix Action tribunal, an “absence of deceit and artifice during

the negotiation and execution of instruments that gave rise to the investment.”435

303. Third, Claimant falsely argues that “tribunals have found evidence of abuse only ‘in very

exceptional circumstances,’ after taking into account ‘all the circumstances of the case.’”436

The Philip Morris award itself is sufficient to show that this is untrue. The Philip Morris

tribunal found an abuse of process, and rejected the claims, specifically because restructuring

to obtain treaty protection for a foreseeable dispute is abusive. It needed nothing more. Even

if some tribunals may have noted additional factors that are also abusive, none has rejected

the basic rule that it is, by itself, an abuse of process to restructure the investment to obtain

treaty protection in view of a foreseeable dispute.437

304. Thus, changing the investment structure with a purpose of obtaining investment treaty

protection when there is a reasonable prospect of a dispute constitutes an abuse of process and

mandates that the claims be dismissed.

431 Statement of Claim, ¶ 319.

432 Statement of Claim, ¶ 318.

433 Statement of Claim, ¶ 318.

434 Renée Rose Levy and Gremcitel SA v Republic of Peru (ICSID Case No ARB/11/17) Award of 9 January 2015, CLA-

124, ¶ 192 (“The fact that the only motivation to add Ms. Levy into the Gremcitel ownership structure was her French

nationality is confirmed by the language contained in the corporate resolution of Hart Industries dated 7 March 2005.”).

435 Phoenix Action, Ltd. v. The Czech Republic, ICSID Case No. ARB/06/5, Award of 15 April 2009, RLA-15, ¶ 143.

436 Statement of Claim, ¶ 318.

437 See, in this regard, Statement of Claim, fn. 628, citing: Renée Rose Levy and Gremcitel SA v Republic of Peru (ICSID

Case No ARB/11/17) Award of 9 January 2015, CLA-124, ¶ 186; Mobil Corporation, Venezuela Holdings BV, and

others v Bolivarian Republic of Venezuela (ICSID Case No ARB/07/27) Decision on Jurisdiction of 10 June 2010,

CLA-97, ¶ 177.

Page 103: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

98

4.2.2 Glencore International Rerouted Its Investment Through Bermuda When A Dispute

With Bolivia Was Foreseeable

305. Claimant argues that its actions were not abusive because it did not restructure to obtain Treaty

protection and the disputes were not foreseeable at the time of its investment.438 It is wrong

on both counts.

306. First, the disputes concerning each of the Assets were clearly foreseeable, and in fact foreseen,

at the moment in March 2005 when Glencore International transferred the Assets to Glencore

Bermuda. As the Minnotte tribunal observed, “an international business operator” like

Glencore International must be “deemed to be a competent professional […].”439

307. There can be little doubt Glencore International actually foresaw that there was a reasonable

prospect of a dispute concerning expropriation of its Assets. As explained before, we

understand that Glencore International took out political risk insurance for the Tin Smelter

from a syndicate led by Lloyd’s, and we suspect it did so for the Antimony Smelter and

Colquiri Mine Lease, to guard against exactly the sort of expropriation that it now claims to

have suffered. Claimant cannot seriously allege that there was no reasonable prospect of the

current dispute when Claimant itself elected to guard against this specific eventuality.

308. As previously explained, by early 2005, Bolivia was emerging from a period of political crisis.

Evo Morales was posed to assume the presidency of the Republic at the head of the MAS

party whose political platform promised a different attitude toward the economy in general

and the mining sector in particular.440 It was clearly foreseeable that Bolivia would be less

indulgent of private mining interests and would ensure complete respect for the law and the

diverse social interests affected by the mining industry.

309. It was against this background that the U.S. Geological Survey specifically warned of the

increasingly unsympathetic attitude in Bolivia toward the mining sector. As it observed,

“[r]oyalties on the production of mineral fuels and mine production and other tax revenue

from private industry were not perceived by Bolivians to have contributed to much perceptible

economic development in the country.”441 It further emphasized that, “[i]f the latest policies

to improve the mineral industry’s contribution to economic development in the country are

438 Statement of Claim, ¶¶ 317, 319.

439 David Minnotte and Robert Lewis v. Republic of Poland, ICSID Case No. ARB(AF)/10/1, Award of 16 May 2014,

RLA-17, ¶ 194.

440 See section 2.5.2 above.

441 Steven T. Anderson, The Mineral Industry of Bolivia, U.S. Geological Survey Minerals Yearbook, 2004, RLA-18, p.

3.13.

Page 104: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

99

not more successful than in the past, then they are not likely to placate the growing public

sentiment for renationalization of the mineral industry of Bolivia.” 442

310. Claimant tries to distract from the political context into which it invested by arguing that

“Glencore as a group had decided to make this acquisition by late 2004, after having met with

government officials who indicated that they welcomed Glencore’s investment.”443 But an

abuse of process arises not when a group acquires an asset, but when the group transfers the

asset to a particular subsidiary that is protected by an investment Treaty. Thus, it is entirely

irrelevant what the group could foresee when it first acquired the Assets.

311. What is more, at the time when Glencore Bermuda was assigned the Assets, disputes

concerning the Tin Smelter, Antinomy Smelter, and Colquiri Mine Lease were very likely to

arise.

312. One, Glencore International was, in all probability, aware that key Bolivian officials

considered that the Tin Smelter privatization had been illegal, as reflected in the risible

purchase prices that Allied Deals obtained. By 2002, important voices, including government

officials and leaders of mining unions from Oruro, were loudly questioning the legality of the

Tin Smelter privatization and called for its reversion in response.444 The MAS members of

parliament and even Evo Morales himself added to the calls for a response to the illegalities,

including by demanding the resignation of Foreign Trade Minister Chancellor Carlos

Saavedra Bruno.445

313. Thus, it was evident that a dispute regarding the rights over the Tin Smelter was likely to arise

given the public and widespread suspicions that it had been irregularly privatized. And it was

precisely on the grounds of the irregular privatization that Bolivia reverted the rights to the

the Tin Smelter from Glencore International’s subsidiary Vinto. This was plain from the

reversion decree. It clearly stated that the Government reverted the Tin Smelter because its

privatization was illegal:

[E]l Gobierno Nacional, en ejercicio del mandato popular expresado en las elecciones

generales del 18 diciembre de 2005 referido a la recuperación de los recursos

442 Steven T. Anderson, The Mineral Industry of Bolivia, U.S. Geological Survey Minerals Yearbook, 2004, RLA-18, p.

3.14.

443 Statement of Claim, ¶ 319.

444 DDHH pide que el Estado intervenga, Brigada Parlamentaria pide preservar fuentes de trabajo, press article, R-137;

Letter from the Federación Regional de Cooperativas Mineras de Huanuni to President Quiroga Ramírez of 20 May

2002, R-142.

445 La Razón Digital, El MAS pide la renuncia del Canciller Saavedra, press article of 8 November 2002, R-134; El Diario,

MAS pide la renuncia del Canciller de la Republica, press release of 4 December 2002, R-135; El Mundo, MAS presentó

las pruebas de corrupción contra Canciller, press release of 4 December 2002, R-136.

Page 105: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

100

naturales y su industrialización y ante las evidentes y gravísimas ilegalidades antes

referidas, se encuentra en la obligación de revertir al dominio del Estado la Fundición

de Estaño Vinto con el objeto de alcanzar el desarrollo económico, digno y

soberano.446

314. Two, Glencore International was, in all probability, aware that continued failure to put the

Antimony Smelter into operation would give rise to a conflict. The legal regulation for the

privatization process established the objective of increasing “la producción, las

exportaciones, el empleo y la productividad.”447 Reflecting this, the Terms of Reference for

the Antimony Smelter tender—incorporated as contractual terms448—specifically provide that

the object and purpose of the privatization was to put the smelter into production. As they

explain, the objective was to make possible “a la Fundición continuar la producción,

constituyéndose en una fuente de generación de empleo y tributos, en apoyo a la actividad

minera de explotación y concentración de antimonio en el país.”449

315. The likelihood of conflict was simply reinforced by Bolivia’s constitutional commitment to

ensuring that property has a social function. In Bolivian constitutional law, the social function

of property establishes that private property is only a right when the property performs a social

function.450 This principle, part of the 1967 Constitution in force at the time Glencore

Bermuda received the Assets, was also incorporated into the 2009 Constitution.451

316. Thus, it was entirely evident that the failure to put the Antimony Smelter into production

would generate a conflict over the rights to the smelter, should it remain dormant. And the

reversion of the rights was implemented specifically because of the Antimony Smelter’s

446 Supreme Decree No 29.026 of 7 February 2007, C-20, p. 6 (Unofficial translation: “[t]he National Government, in the

exercise of its popular mandate resulting from the general elections of 18 December 2005 regarding the recovery of

natural resources and their industrialization and in view of the evident and grave aforementioned illegalities, is

obligated to revert the Vinto Tin Smelter to the State’s ownership, with the purpose of guaranteeing economic, dignified

and sovereign development”).

447 Supreme Decree No. 23.991 of 10 April 1995, R-100, Art. 2(c) (Unofficial translation: “production, exports,

employment and productivity”).

448 Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External Trade

and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9, 23(1),

p. 18.

449 Terms of Reference for the Second Public Tender for the Antimony Smelter of 31 July 2000, R-109, p. 9 (Unofficial

translation: “permitting the Smelter to continue production, becoming a source for the generation of employment and

tax, in support of the mining activity of exploitation and concentration of antimony in the country”) (emphasis added).

450 Constitution of Bolivia of 7 February 2009, C-95, Article 56: “I. Toda persona tiene derecho a la propiedad privada

individual o colectiva, siempre que ésta cumpla una función social; II. Se garantiza la propiedad privada siempre que

el uso que se haga de ella no sea perjudicial al interés colectivo.” (Unofficial translation: “I. All persons have the right

to individual or collective private property, provided that it fulfils a social function; II. Private property is guaranteed

as long as its use is not detrimental to the collective interest”). The previous Constitution (promulgated in 2004) also

established the same condition in its Article 7(i), see Bolivian Constitution, Law of 13 April 2004, R-235.

451 The Constitution also mentions social function in articles 186, 393 and 397. Constitution of Bolivia of 7 February 2009,

C-95

Page 106: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

101

inactivity. The reversion decree makes plain that the Antimony Smelter was reverted

specifically because of this inactivity, in breach of the contractual “obligaciones de invertir y

fortalecer la Empresa Metalúrgica Vinto Antimonio con capacidad económica, financiera y

técnica, […] posibilitando a la Fundición continuar la producción […].”452 In fact, Claimant

does not deny that the Antimony Smelter had remained dormant since its privatization,

including during the five years that Claimant counted it among its Assets.

317. Three, Glencore International was, in all probability, aware that there was a reasonable

prospect Bolivia would have to intervene in the growing dispute with cooperativistas at the

Colquiri mine. As previously explained, following the privatization of the mine in 2000,453

Comsur significantly reduced the number of employees. Because the people living in Colquiri

are entirely dependent on the mine, the former COMIBOL workers were forced to become

independent mine workers, and ultimately to form the cooperativas.454 These cooperativas

soon became an essential source of labour for the mine.455

318. However, given the influx of cooperativistas and a lack of proper control over the mine,

tensions rapidly rose between the cooperativistas and the formal mine workers.456 While the

cooperativistas demanded ever increasing rights to work the mine and frequently stole

minerals and equipment from the mine, the company mine workers reacted with outrage to

these threats to their own position at the mine.457 Comsur was unable to control the

situation.458 These tensions led to direct confrontations between the cooperativistas and

formal mine workers, even necessitating the intervention of the State at times.459 And with

the political empowerment of cooperativistas during the ascendency of MAS,460 these

tensions and confrontations over control of the mine continued to grow in intensity.

452 Supreme Decree No 499 of 1 May 2010, C-26, Preamble, p. 17 (Unofficial translation: “the terms of reference provided

for the obligation to invest in and reinforce the Metallurgical Company Vinto Antimonio with economic, financial and

technical capacity, […] permitting the Smelter to continue production”).

453 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11.

454 Cachi, ¶¶ 12-14.

455 Mamani, ¶¶ 13-15.

456 See section 2.5.2 above.

457 See section 2.5.1 above; Mamani, ¶¶ 14-17; Cachi, ¶¶ 17-22.

458 See section 2.5.1 above; Cachi, ¶¶ 20-22; 51.

459 See section 2.5.1 above. See, for instance, Internal Memorandum from COMIBOL to the Ministry of Mines of 23

January 2004, R-152.

460 Mamani, ¶19; M. Cajías de la Vega, “Crisis, Diáspora y Reconstitución de la Memoria Histórica de los Mineros

Bolivianos” in Revista de Estudios Transfronterizos, Vol. X, No. 2 (2010), R-159, 87 (Unofficial translation: “The

presence in El Alto and La Paz of 800 miners of Huanuni and more than 3,000 mining cooperativistas was very

significant in decisive moments of the popular uprising triggered in October 2003 against the government of Gonzalo

Page 107: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

102

319. Thus, it was plainly foreseeably by early 2005 that the conflict over the mine would continue

to provoke State intervention in the mining, predictably generating disputes with the mine

owner regarding the justification, nature, and extent of that intervention. And Claimant in this

arbitration complains precisely of Bolivia’s intervention in the mine following violent

conflicts between the cooperativistas and the company mine workers.461

320. In view of these facts, Glencore International transferred its Assets in Bolivia to Glencore

Bermuda on 7 March 2005. There was no reason for this transfer except to obtain protection

of the Treaty.

321. Second, in light of Glencore International’s clear awareness of the reasonable prospect that

the current dispute would arise, it is obvious that the primary purpose for transferring the

Assets to Glencore Bermuda was to obtain Treaty protection. Notably, Claimant has not

offered any justification for the transfer to Glencore Bermuda, other than to obtain Treaty

protection.

322. To the contrary, its main defense seems to be that “the purpose of the transaction was not only

to acquire Bolivian assets but also assets located in Argentina.”462 But this assertion does not

provide an alternative explanation to the abuse of process, only an irrelevant factual

distraction. Because the Assets would have been held by the same corporate structure

(although Claimant provides no evidence the so-called Argentine assets exist), to obtain

protection for the Bolivian Assets, all of the assets would have to be transferred to Glencore

Bermuda.

323. Claimant also attempts to defend the legitimacy of the transfer of its assets to Glencore

Bermuda on the grounds that “Glencore International also benefits from the protection of an

investment treaty, the Switzerland-Bolivia Treaty.”463 But this is untrue. The Swiss-Bolivia

BIT defines “companies” as, “[i]n the case of the Swiss Confederation, legal entities or

associations without legal status but able to possess property, in which, directly or indirectly,

there is a substantial Swiss interest […].”464 However, there is no substantial Swiss interest

Sánchez de Lozada and the centre of which was that city of the department of La Paz. Not only was the presence of

residents of neighbourhoods of relocated miners noted during theentire week of the popular uprising, in particular from

Santiago II, one of the places where major confrontations with the army took place – but also the presence of mining

employees and cooperativistas from Huanuni and other mines. Thus, October was undoubtedly a moment of revelation

of ‘previous social accumulations’, not only in the mining sector but also in all popular sectors in Bolivia”).

461 Statement of Claim, ¶¶ 8-14.

462 Statement of Claim, ¶ 317.

463 Statement of Claim, ¶ 314.

464 Agreement between the Swiss Confederation and the Republic of Bolivia on the reciprocal promotion and protection of

investments, English translation, RLA-19, Article 1(b)(aa).

Page 108: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

103

in the Glencore grou; it has widely dispersed holding by a range of global funds.465 These

largest shareholders are US-based funds including Oakmark, Capitol Group American Funds,

Oppenheimer, and Vanguard.466

324. Simply put, Claimant restructured its so-called investment when there was a reasonable

prospect of this very dispute in order to obtain investment treaty protection. Its claims cannot

be heard for abuse of process.

4.3 The Tribunal Lacks Jurisdiction Because The Assets Subject To Dispute Were Illegally

Privatized

325. It is a generally accepted principle of investment arbitration that a tribunal cannot hear claims

regarding an investment tainted by illegality. This is dispositive of Claimant’s claims; none

can be heard in the present arbitration. The Assets underlying the claims advanced in this

arbitration were all illegitimately and illegally privatized (Section 4.3.1). Pursuant to the

international law principle of unclean hands, these illegalities preclude the Tribunal from

hearing the claims (Section 4.3.2).

4.3.1 The Privatization Of The Assets Was Illegal Under Bolivian Law And Contrary To

International Public Policy

326. The privatization process for the Assets was riddled with illegalities, each of which is

individually sufficient to prevent the arbitration from proceeding. The legal framework for

the privatizations of the Colquiri Mine Lease and the Antimony Smelter was established by

former Bolivian President Sánchez De Lozada to benefit his own economic interests, in

violation of the constitutional requirement of impartiality. The Tin Smelter, the Colquiri

Mine Lease, and the Antimony Smelter privatizations, carried out under this framework,

suffered from an illegal lack of transparency and good faith and violated the requirement that

state officials protect the public patrimony, as the prices received in the privatizations were

inexplicably low.

327. First, Bolivia’s 1967 Constitution, in force during Sánchez de Lozada’s presidency and during

the privatizations, established the basic obligation to act in the public interest, free from

partiality and bias. Article 43 of the Constitution provided that, “[u]na ley especial

establecerá el Estatuto del funcionario Público sobre la base del principio fundamental de

que los funcionarios y empleados públicos son servidores exclusivos de los intereses de la

465 Morningstar, Glencore PLC Major Shareholders, R-236.

466 Morningstar, Glencore PLC Major Shareholders, R-236.

Page 109: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

104

colectividad y no de parcialidad o partido político alguno.”467 In this regard, Bolivia’s

Constitution adopted widely accepted constitutional principles,468 also implemented in Bolivia

through regulations.469

328. During his presidency, Sánchez de Lozada took advantage of his position in order to

implement the policies that would later on allow him to expand his mining operations, in

complete disregard of the public interest. In particular, it was during Sánchez de Lozada’s

first term in office that he put in place the regulations for implementing the Privatization Law

via Supreme Decree 23.991.470 These regulations established the official objective of the

transferring to the private sector “actividades productivas que puedan ser realizadas por este

de manera más eficiente […].”471 Then, Sánchez de Lozada enacted the 1997 Mining Code,

prohibiting COMIBOL from directly carrying out mining activities.472

329. There can thus be little doubt that Sánchez de Lozada’s conduct while in office was biased

and self-serving, with relation to his own best interests as a businessman. He was, thereafter,

in a privileged position to reap the benefits of the normative framework he had designed and

to acquire the Assets upon which he had set his sights. His acquisition of the Colquiri Mine

Lease and Antimony Smelter were thus contrary to Bolivian constitutional requirements.

330. Second, in spite of the clear requirements of Bolivian law, the Tin Smelter, Colquiri Mine

Lease, and Antimony Smelter were privatized contrary to the basic requirements of

transparency and good faith and in blatant disregard of the legal principle that the public

patrimony must be protected.

331. The Bolivian legal framework for privatization establishes that public tender processes are

governed by the principles of transparency and good faith.473 The Bolivian Constitutional

467 Constitution of Bolivia of 1967, R-3, Article 43 (emphasis added) (Unofficial translation: “[a] special law shall

establish the Statute of Public servants based on the fundamental principle that public servants and employees serve

exclusively the collective interest and not those of any faction or any political party”).

468 Spanish Constitution, RLA-20, Article 103; Political Constitution of Colombia, RLA-21, Article 209, Constitution of

the Republic of South Africa of 1996, RLA-22, Chapter 10; L. Machi and E. Machi, “Aplicación de los principios de

“ética de la función pública" y de “imparcialidad en el ejercicio de la función” en situaciones en que la administración

ejerce potestades discrecionales”, Revista de Derecho Público No. 51, 2017, RLA-23, p. 53.

469 Supreme Decree No. 2.3318-A of 3 November 1992, R-237, Articles 3, 4.

470 See Supreme Decree No. 23.991 of 10 April 1995, R-100, Article 1. See also Section 2.2 above.

471 Supreme Decree No. 23.991 of 10 April 1995, R-100, Art. 2(a) (Unofficial translation: “production activities that may

be carried out in a more efficient way by the latter”).

472 Bolivian Mining Code, Law 1.777 of 17 March 1997, R-4, Article 91. See also Section 2.2 above.

473 Law No 1,330, 24 April 1992, published in the Gaceta Oficial No 1,735, C-58, Article 4; See Supreme Decree No. 23.991

of 10 April 1995, R-100, Article 16; Supreme Resolution No. 215.475 of 20 March 1995, R-238, Article 2; Supreme

Decree No. 25.964 of 21 October 2000, R-239.

Page 110: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

105

Court further reaffirmed the applicability of these principles to public tender processes,

emphasizing that this system seeks to assure an objective selection of private contractors.474

332. Bolivian law also imposes serious restrictions on public contracting to ensure that it is to the

economic benefit of the state. In fact, one of the core principles of Bolivian constitutional law

is the protection of the public patrimony of the State, enshrined in Article 137 of 1967

Constitution.475 Additionally, the public function is governed by the principle of efficiency –

expressly recognized in Law No. 1178,476 Supreme Decree No. 23318-A477 and the Estatuto

del Servidor Público.478

333. One, Allied Deals acquired the Tin Smelter at an inexplicably low price, causing a significant

prejudice to the public patrimony of the State. As explained before, Allied Deals paid roughly

US$ 14 million even though the actual value of the Tin Smelter was far greater. The Smelter

was handed over to Allied Deals together with certain items not included in the inventory, the

value of which was some US$ 16 million.479 As a result, the Smelter was essentially awarded

to Allied Deals for free (or, still worse, Allied Deals was effectively paid to take the Smelter).

334. Two, the minimum price established for the Antimony Smelter was US$ 100,000 and it sold

for roughly US$ 1,100,000, but both figures ignore the significant investments that Bolivia

had made in the Antimony Smelter. Although the Government was put on notice of the very

low price well before the tender was awarded to Sánchez de Lozada’s Colquiri, the

privatization was allowed to proceed causing a significant loss to the public patrimony of the

State.480

474 Bolivian Constitutional Tribunal, Decision 0024/2005 of 11 April 2005, R-240, p. 6.

475 Constitution of Bolivia of 1967, R-3, Article 137 (“[l]os bienes del patrimonio de la Nación constituyen propiedad

pública, inviolable, siendo deber de todo habitante del territorio nacional respetarla y protegerla.”) (Unofficial

translation: “[t]he assets belonging to the Nation represent public and inviolable property and it is the duty of every

inhabitant of the national territory to respect and protect it”) This principle is of particularly strict application in the

mining sector. Article 133 of the 1967 Constitution, for example, stated that the State “propenderá al fortalecimiento

de la independencia nacional y al desarrollo del país mediante la defensa y el aprovechamiento de los recursos

naturales y humanos en resguardo de la seguridad del Estado y en procura del bienestar del pueblo boliviano.”

(Unofficial translation: “[the State] shall tend to reinforce the national independence and the country’s development by

defending and guaranteeing an effective use of natural and human resources, safeguarding the State’s security and

guaranteeing the Bolivian population’s well-being”).

476 Law No. 1.178 of 20 July 1990, R-241, Article 1(a).

477 Supreme Decree No. 2.3318-A of 3 November 1992, R-237, Article 3

478 Law No. 2.027 of 27 October 1999, R-242, Article 8(g).

479 Report from Ms Wilma Morales Espinoza (EMV) to Eng. Rafael Delgadillo (COMIBOL) of 7 July 2000, R-121, p. 2.

480 See Letter from the Oruro Parliamentary Group to President Bánzer Suárez of 27 November 2000, R-110; Letter from

Leopoldo Fernández Ferreira to President Hugo Bánzer Suárez of 5 December 2000, R-113; Letter from Humberto

Bohrt Artieda to Walter Guiteras Denis of 8 December 2000, R-114. See, also, section 2.3.2 above.

Page 111: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

106

335. Three, the Colquiri Mine Lease was surprisingly awarded to the Sánchez de Lozada’s Colquiri

S.A. for free, and only in exchange for a small investment commitment during the first two

years of operations. Nonetheless, the Qualifying Commission did not undertake any material

analysis of the conditions proposed by Colquiri, not did it consider the implications that

accepting such proposal might in fact have had for the interests of the State.

336. In fact, in these proceedings, Claimant alleges that the Mine Lease was worth some US$ 443.1

million as at 29 May 2012.481 Though, as explained by Econ One, this valuation is grossly

overstated, and the real value of the Mine was in fact US$ 39.7 million as at 19 June 2012, it

is evident that the conditions in which the Lease was adjudicated caused harm to the State’s

patrimony. If the Lease was worth US$ 39.7 (or, still worse, Claimant’s alleged US$ 443.1.7

million) as at 19 June 2012 when it had only 20 years remaining on its term, it is entirely

impossible that the Lease could have been worth nothing more than ten years earlier when the

Lease had the full 30 years remaining.482

337. These facts clearly show that the circumstances surrounding the privatization of the Assets

were contrary to basic requirements of transparency and good faith which rendered the

privatization illegal. More importantly, the privatization of the Assets impaired the integrity

of the public patrimony, given the unduly low purchase prices proposed to and accepted by

the Qualifying Commission.

4.3.2 Claimant Brings Its Claims With Unclean Hands Because The Privatizations Were

Illegal

338. The Tribunal is barred from exercising jurisdiction over the claims submitted to it in the

present case. Pursuant to the clean hands principle, Claimant cannot present for adjudication

before this Tribunal claims tainted by an illegality which Claimant was aware of when it

received the Assets.

339. The clean hands principle is the manifestation of a fundamental principle of law: good faith.

As such, it is widely recognized both in civil and common law systems and as a “general

principle of law that should be applicable in all cases.”483 It is encompassed in the legal

maxims he who comes to equity must come with clean hands and the ex injuria jus nor oritur,

481 Statement of Claim, ¶ 276.

482 Econ One, Table 1.

483 R. Moloo, A. Khachaturian, “The Compliance with the Law Requirement in International Law”, 34 Fordham

International Law Journal 1473, issue 6, 2011, RLA-24, p. 1485.

Page 112: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

107

nemo auditur propiam turpitudinem allegans, ex turpi causa non oritur actio and ex dolo malo

non oritur actio principles.484

340. The principle of clean hands had definitively and authoritatively been established in the case

law of international investment tribunals. The recent Churchill Mining tribunal has

definitively established that illegal or fraudulent conduct connected to the basis of a claim

renders that claim inadmissible.

341. In reaching that conclusion, the Churchill Mining tribunal undertook a systematic and

comprehensive review of existing investment jurisprudence.485 It specifically held that

“claims arising from rights based on fraud or forgery which a claimant deliberately or

unreasonably ignored are inadmissible as a matter of international public policy.”486 It

further explained that “the general principle of good faith and the prohibition of abuse of

process entail that the claims before this Tribunal cannot benefit from investment protection

under the Treaties and are, consequently, deemed inadmissible.”487

342. In this regard, the Churchill Mining tribunal built on a consistent line of investment decisions.

The Inceysa v. El Salvador case upheld the principle that access to international investment

was barred to investments secured through illegal conduct:

Applying the first principle indicated above to the case at hand, we can affirm that

the foreign investor cannot seek to benefit from an investment effectuated by means

of one or several illegal acts and, consequently, enjoy the protection granted by the

host State, such as access to international arbitration to resolve disputes, because

it is evident that its act had a fraudulent origin and, as provided by the legal maxim,

‘nobody can benefit from his own fraud’488

343. Similarly, in the Plama v. Bulgaria case, the tribunal upheld the ex turpi causa defence and

dismissed the claims before it, in light of its conclusion that an investment treaty’s substantive

protections cannot cover an investment made contrary to the law.489

484 R. Moloo, A. Khachaturian, “The Compliance with the Law Requirement in International Law”, 34 Fordham

International Law Journal 1473, issue 6, 2011, RLA-24, p. 1479-1480.

485 Churchill Mining PLC and Planet Mining Pty Ltd v. Republic of Indonesia, ICSID Case No. ARB/12/14 and 12/40,

Award of 6 December 2016, RLA-25, ¶¶ 488-506.

486 Churchill Mining PLC and Planet Mining Pty Ltd v. Republic of Indonesia, ICSID Case No. ARB/12/14 and 12/40,

Award of 6 December 2016, RLA-25, ¶ 508.

487 Churchill Mining PLC and Planet Mining Pty Ltd v. Republic of Indonesia, ICSID Case No. ARB/12/14 and 12/40,

Award of 6 December 2016, RLA-25, ¶ 528.

488 Inceysa Vallisoletana S.L. v. El Salvador, ICSID Case No. ARB/03/26, Award of 2 August 2006, RLA-26, ¶ 242.

489 Plama Consortium Limited v. Republic of Bulgaria, ICSID Case No. ARB/03/24, Award of 27 August 2008, RLA-27,

¶ 139, 146.

Page 113: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

108

344. The holdings in the above-cited cases are consistent with that of the tribunal in Phoenix v.

Czech Republic. Indeed, this case stands for the proposition that extending the substantive

protection of investment treaties to investments secured through improper means or which are

illegal would be inconsistent with the very purpose of international investment arbitration:

The purpose of the international mechanism of protection of investment through

ICSID arbitration cannot be to protect investments made in violation of the laws of

the host State or investments not made in good faith, obtained for example through

misrepresentations, concealments or corruption, or amounting to an abuse of the

international ICSID arbitration system. In other words, the purpose of international

protection is to protect legal and bona fide investments.490

345. Following its review of the jurisprudence, the Churchill Mining tribunal concluded quite

clearly that the illegal conduct need not be that of the investor itself for the claims to be

inadmissible. It is sufficient that the claimant did not exercise a reasonable level of due

diligence in making the purported investment.491 In other words, when risks present

themselves, the requirements of due diligence are demanding: “one would expect an investor

aware of the risks of investing in a certain environment to be particularly diligent in

investigating the circumstances of its investment.”492

346. Glencore International knew—or, at the very least, should have known—at the time it

acquired the Assets that they had previously been State-owned and had passed into private

property through highly irregular and publicly contested privatization processes. It would

have been sufficient for Glencore International to carry out a minimum of due diligence in

order for it to confirm that:

The Assets had inappropriately passed into the hands of Sánchez de Lozada, who

had taken advantage of the favourable policies he had implemented while in office;

The circumstances in which the Antimony Smelter and Colquiri mine lease had

passed to Sánchez de Lozada had been highly irregular, as the price paid for the

former had been inferior to its value, whilst the only consideration paid for the lease

of the latter had been practically insignificant; and

490 Phoenix Action, Ltd. v. The Czech Republic, ICSID Case No. ARB/06/5, Award of 15 April 2009, RLA-15, ¶¶ 100.

491 Churchill Mining PLC and Planet Mining Pty Ltd v. Republic of Indonesia, ICSID Case No. ARB/12/14 and 12/40,

Award of 6 December 2016, RLA-25, ¶ 506.

492 Churchill Mining PLC and Planet Mining Pty Ltd v. Republic of Indonesia, ICSID Case No. ARB/12/14 and 12/40,

Award of 6 December 2016, RLA-25, ¶ 518.

Page 114: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

109

The circumstances in which the Tin Smelter was acquired by Allied Deals and

subsequently by Comsur had also been highly irregular, as the purchase price of the

Smelter had been a fraction of its value.

347. Given that Glencore International’s founder, Marc Rich, had been a Bolivian citizen since

1983, the company and its affiliates could not have ignored these facts at the time the Assets

were acquired. Whether Glencore International did not carry out the required due diligence

or whether, having been aware of these facts, it chose to ignore them is of little significance.

The claims that Claimant submits to this Tribunal are tainted by its unclean hands and thus

inadmissible.

4.4 The Tribunal Lacks Jurisdiction Because The Claimant Is, In Reality, A Swiss Company

Not Subject To Treaty Protection Or, Alternatively, Because It Cannot Bring Claims

Based On Indirectly Held Rights

348. Claimant argues that the Tribunal has jurisdiction because Glencore Bermuda “is a company

incorporated under the laws of Bermuda” and nothing more than formal incorporation in

Bermuda is necessary to establish jurisdiction under the Treaty.493

349. However, Claimant simply ignores the fact that formal ownership structures are insufficient

to establish jurisdiction when the investors are purely Swiss in substantive reality. There can

be no jurisdiction because the nominal claimant is simply a vehicle through which a Swiss

company, Glencore International, attempts to invoke international protection for a Treaty that

does not protect Swiss companies. As Claimant admits, the investment in the Smelters and

the Mine Lease was Swiss in its origins and remains Swiss in its ultimate ownership.

350. The corporate veil of Glencore Bermuda can and should be pierced in this case to reveal the

Swiss nationality of the true claimant. International law recognizes that the corporate veil can

be pierced when the corporate form is misused (Section 4.4.1). Glencore Bermuda is an

empty shell company that Glencore International expressly uses to conceal misdeeds around

the globe (Section 4.4.2). Its tainted corporate veil cannot be the basis of this Tribunal’s

jurisdiction.

351. And, even if Glencore Bermuda’s tainted corporate veil cannot be pierced, Claimant cannot

simultaneously assert claims based on indirectly held rights, effectively piercing the corporate

veils of its subsidiaries. It is a general rule of international law that a company cannot assert

the rights of an indirectly-held subsidiary before an international tribunal. Given that

493 Statement of Claim, ¶¶ 311-312.

Page 115: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

110

Claimant had no rights of its own to the Assets at issue in this arbitration, there is no

jurisdiction over its claims (Section 4.4.3).

4.4.1 The Treaty Excludes Jurisdiction Asserted On The Basis Of Corporate Formalities

When The Real Party In Interest Is Not Protected

352. Article 8(1) of the Treaty offers the protection of international investment arbitration only to

a person from one Contracting Party who invests in a different Contracting Party. It does not

extend protection to a person from a non-Contracting Party who invests in a Contracting Party:

Disputes between a national or company of one Contracting Party and the other

Contracting Party concerning an obligation of the latter under this Agreement in

relation to an investment of the former which have not been legally and amicably

settled shall after a period of six months from written notification of a claim be

submitted to international arbitration if either party to the dispute so wishes.494

353. On the basis of a similar provision, the Loewen v. United States tribunal famously held that it

had no jurisdiction over a Canadian corporation because that corporation was a mere formality

and the real party in interest was from the United States. Formalities could not allow a US

investor to sue its own State:

[T]he Tribunal unanimously decides . . . [t]hat it lacks jurisdiction to determine

TLGI’s claims under NAFTA concerning the decisions of United States courts in

consequence of TLGI’s assignment of those claims to a Canadian corporation

owned and controlled by a United States corporation.495

354. The Loewen holding that economic realities must override corporate formalities reflects a

general principle of international law that retains its vitality in international investment law.

International law does not permit the use of the corporate veil to evade legal requirements or

to harm third parties. Piercing the corporate veil allows international legal decisions to be

made on the basis of substantive realities and not corporate formalities.

355. The judgment of the International Court of Justice (the “ICJ”) in the Barcelona Traction case

famously recognized that international law permits piercing the corporate veil. It emphasized

that the doctrine is especially applicable to defend the interests of those adversely affected by

the corporation:

Hence the lifting of the veil is more frequently employed from without, in the interest

of those dealing with the corporate entity. However, it has also been operated from

494 Treaty, C-1, Article 8(1).

495 Loewen Group, Inc. and Raymond L. Loewen v. United States of America, ICSID Case No. ARB/AF/98/3, Award of 26

June 2003, RLA-28, Orders, ¶ 1.

Page 116: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

111

within, in the interest of—among others—the shareholders, but only in exceptional

circumstances.

[…]

In accordance with the principle expounded above, the process of lifting the veil,

being an exceptional one admitted by municipal law in respect of an institution of

its own making, is equally admissible to play a similar role in international law. It

follows that on the international plane also there may in principle be special

circumstances which justify the lifting of the veil in the interest of shareholders.496

356. The Barcelona Traction judgment made clear that the veil may be pierced and corporate

formalities cast aside specifically to protect the interests of third parties or to prevent evasion

of legal requirements. As the ICJ explained:

[T]he law, confronted with economic realities, has had to provide protective

measures and remedies in the interests of those within the corporate entity as well

as of those outside who have dealings with it: the law has recognized that the

independent existence of the legal entity cannot be treated as an absolute. It is in

this context that the process of “lifting the corporate veil” or “disregarding the

legal entity” has been found justified and equitable in certain circumstances or for

certain purposes. The wealth of practice already accumulated on the subject in

municipal law indicates that the veil is lifted, for instance, to prevent the misuse of

the privileges of legal personality, as in certain cases of fraud or malfeasance, to

protect third persons such as a creditor or purchaser, or to prevent the evasion of

legal requirements or of obligations.497

357. The principles of Barcelona Traction have recently been adopted and applied by, inter alia,

the international investment tribunal in TSA Spectrum. That tribunal emphasized veil piercing

is available when the corporate form is used to evade otherwise applicable legal requirements:

In the Barcelona Traction case, the International Court of Justice stated that, in

international law, it is allowed to pierce the corporate veil, for instance to prevent

the misuse of the privileges of legal personality or to prevent the evasion of legal

requirements or obligations.498

358. The veil must be pierced when the nominal investor is the alter ego of the beneficial investor,

as shown by misuse of the corporate form. There is no real debate that such a misuse of

corporate form justifies piercing the corporate veil. In fact, even Claimant’s own cited cases

on this point recognize it.499 The Saluka tribunal recognized that it is “permissible for a

tribunal to look behind the corporate structures of companies involved in proceedings before

496 Barcelona Traction, Light and Power Company, Limited (Belgium/Spain) [1970] ICJ Reports 3, CLA-7, ¶¶ 57-58

(emphasis added).

497 Barcelona Traction, Light and Power Company, Limited (Belgium/Spain) [1970] ICJ Reports 3, CLA-7, ¶ 56.

498 TSA Spectrum de Argentina S.A. v. Argentine Republic, ICSID Case No. ARB/05/5, Award of 19 December 2008, RLA-

29, ¶ 117 (emphasis added).

499 Statement of Claim, ¶ 313.

Page 117: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

112

it” in some circumstances.500 One of those circumstances is when, as ADC recognized, “the

real beneficiary of the business misused corporate formalities […].”501 Claimant’s other cited

cases do not address veil piercing.502

359. In short, the corporate veil must be pierced in the present case to prevent Claimant from

evading the clear jurisdictional requirement of the Treaty: the investor must be from a State

that is party to the Treaty. Failure to pierce the veil would seriously prejudice Bolivia, a third

party that is now in risk of being subject to lengthy and expensive litigation through

Claimant’s abuse of corporate formalities.

4.4.2 The Corporate Veil Must Be Pierced Because Glencore Bermuda Is An Empty Shell

Hiding The True Party In Interest

360. It is Claimant’s position that “Glencore Bermuda is not a shell company” because “Glencore

Bermuda is the company that has historically been the holding company for the vast majority

of Glencore’s international investments, including those in Latin America.”503 From this it

concludes that its corporate veil cannot be pierced to reveal Claimant’s true nationality.

361. However, the basic fact is that the Bolivian Assets were bought and paid for by Glencore

International. This is not seriously contested. As Claimant admits, Glencore International

purchased the rights and then “subsequently assigned all of the rights, titles and interests

acquired from the purchase to its wholly-owned subsidiary Glencore Bermuda.”504 Nor is it

contested that Glencore International continued to control and benefit from its Bolivian

holdings.

362. Instead, Claimant argues that Glencore Bermuda’s corporate veil should block the Tribunal

from recognizing Claimant’s true Swiss nationality. But what is Glencore Bermuda?

500 Saluka Investments BV v Czech Republic (UNCITRAL) Partial Award of 17 March 2006, CLA-62, ¶ 230.

501 ADC Affiliate Limited and ADC & ADMC Management Limited v Republic of Hungary (ICSID Case No ARB/03/16)

Award of the Tribunal of 2 October 2006, CLA-64, ¶ 358.

502 See The Rompetrol Group NV v Romania (ICSID Case No ARB/06/3) Decision on Respondent’s Preliminary Objections

on Jurisdiction and Admissibility of 18 April 2008, CLA-76, ¶¶ 83, 110 (addressing only whether general international

law principles of nationality apply in investment treaty disputes); Fedax NV v Republic of Venezuela (ICSID Case No

ARB/96/3) Decision of the Tribunal on Objections to Jurisdiction of 11 July 1997, CLA-21, ¶ 17 (noting that nationality

was not in dispute).

503 Statement of Claim, ¶ 314.

504 Statement of Claim, ¶ 37.

Page 118: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

113

363. In effect, Glencore Bermuda is nothing more than a shell company in Bermuda where

Glencore International or Glencore International Plc parked subsidiaries engaged in

questionable activities or whose activities they would prefer to conceal.

364. The length and breadth of what Claimant has to say about Glencore Bermuda is that it “is a

company incorporated and constituted under the laws in force in Bermuda.”505 Claimant does

not attempt to put forth a shred of evidence of any activity in Bermuda. It does not identify

any of employees. It does not reference shareholder or board meetings. It does not even

describe physical facilities.

365. However, thanks to the recently released Paradise Papers, we now know why Claimant is so

shy to describe Glencore Bermuda. Glencore Bermuda exists only in a nearly empty room

that “held a filing cabinet, a computer, a telephone, a fax machine and a checkbook” and

apparently nothing more.506 This room was in the offices not of Glencore Bermuda or

Glencore International but of Appleby, the Glencore Group’s Bermudan law firm.507 This is

the full extent of Glencore Bermuda’s physical existence.

366. Nor does Glencore Bermuda have a staff that is any more substantial. According to the

Paradise Papers, in contrast to the Glencore Group’s home office in Switzerland with 800

employees, “the company had only an Appleby employee [in Bermuda] who moonlighted as

an official stand-in Glencore director for a ‘very limited number of hours.’”508 This employee

barely performed any work on behalf of Glencore Bermuda: “[t]he employment contract was

designed to keep the stand-in director below thresholds that would invoke payroll taxes and

social security insurance coverage, according to a file note prepared by Appleby in May

2014.”509

367. Claimant effectively admits that Glencore Bermuda was nothing more than a shell company.

As Mr Eskdale explains, Glencore Bermuda was a “holding company for Glencore’s

investments worldwide and as such held at that time the vast majority of Glencore’s

505 Statement of Claim, ¶ 128.

506 International Consortium of Investigative Journalists, Room of Secrets Reveals Glencore’s Mysteries, press article of 5

November 2017, R-243, p. 1.

507 International Consortium of Investigative Journalists, Room of Secrets Reveals Glencore’s Mysteries, press article of 5

November 2017, R-243, pp. 6-7.

508 International Consortium of Investigative Journalists, Room of Secrets Reveals Glencore’s Mysteries, press article of 5

November 2017, R-243, p. 7.

509 International Consortium of Investigative Journalists, Room of Secrets Reveals Glencore’s Mysteries, press article of 5

November 2017, R-243, p. 7.

Page 119: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

114

investments in the Americas.”510 What this means, according to the Paradise Papers, is that

the Glencore Group hid its vast network of offshore companies as subsidiaries of Glencore

Bermuda. As the Paradise Papers state, “[a] Glencore employee told Appleby that the

company did not have a complete chart showing all its offshore entities ‘mainly because it

would take up one wall.’”511

368. And the Glencore Group did not use its Bermudan shell company for noble purposes. By way

of example, it used Glencore Bermuda as a repository for its off-the-books holding in shipping

company SwissMarine to which it then lent funds at non-commercial interest rates.512 It used

Glencore Bermuda to hold its interest in a zinc operation in Burkina Faso that forcibly

suppressed protest from the local community.513 And it used Glencore Bermuda to hold its

stake in a mining company in the Democratic Republic of Congo to which it funnelled loans

allegedly destined for corrupt payments.514

369. Simply put, Glencore Bermuda is a shell company used to conceal the Glencore Group’s

misdeeds around the globe. Its marred corporate veil cannot be the basis for this Tribunal’s

jurisdiction. It must be pierced to reveal that the Claimant is truly Swiss.

4.4.3 Even If (Quod Non) The Corporate Veil Protects Glencore Bermuda, International Law

Does Not Allow It To Bring Claims For Its Indirect Investment

370. It is undisputed and undisputable that Glencore Bermuda had no direct holding in the Assets

at issue in the present arbitration. To the contrary, it held nothing more than shares in three

Panamanian companies, which in turn held the Assets through several more layers of

corporate intermediaries. International law prohibits Glencore Bermuda from bringing claims

based on alleged violations of the rights of a subsidiary when its own rights were untouched.

Glencore Bermuda’s claims are thus barred.

510 Eskdale, ¶ 20.

511 International Consortium of Investigative Journalists, Room of Secrets Reveals Glencore’s Mysteries, press article of 5

November 2017, R-243, p. 7.

512 International Consortium of Investigative Journalists, The Ships Glencore Wanted to Keep ‘Hush Hush’, press article of

9 November 2017, R-244, p. 2 (“Glencore’s significant shareholding of SwissMarine and its control over operational

matters such as opening a bank account suggest that SwissMarine should have been specified by name in Glencore’s

recent financial statements, said Prem Sikka, Emeritus Professor of Accounting at the University of Essex.”; “‘It would

be difficult to justify the 18% rate in any context, including the November 2008 financial crisis,’ said Nikos Nomikos,

professor of shipping risk management at Cass Business School.”).

513 International Consortium of Investigative Journalists, Development Dreams Stand Still While Mining Money Moves

Offshore, press article of 8 November 2017, R-245, pp. 1-2

514 International Consortium of Investigative Journalists, Room of Secrets Reveals Glencore’s Mysteries, press article of 5

November 2017, R-243; International Consortium of Investigative Journalists, Glencore responds to ICIJ’s questions,

press article of 5 November 2017, R-246.

Page 120: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

115

371. As an initial matter, it would be the height of unfairness to find jurisdiction despite this rule.

This is because the Tribunal would simultaneously have to pierce the corporate veil in favour

of Claimant, allowing it to assert the rights of its subsidiaries, while refusing to pierce the

corporate veil in favor of Bolivia. Such an inconsistent position cannot be the basis of the

Tribunal’s jurisdiction.

372. Even apart from the dictates of consistency and fairness, the basic rule of customary

international law against protection by substitution precludes jurisdiction over this dispute.

This rule establishes that a foreigner may only bring claims for violations of its own rights,

not for rights of companies in which it holds an interest. A shareholder may not substitute

itself for that of the company in which it holds shares.

373. This rule is given authoritative voice in the International Law Commission’s Articles on

Diplomatic Protection. Article 11 states:

A State of nationality of shareholders in a corporation shall not be entitled to exercise

diplomatic protection in respect of such shareholders in the case of an injury to the

corporation unless:

(a) the corporation has ceased to exist according to the law of the State of

incorporation for a reason unrelated to the injury; or

(b) the corporation had, at the date of injury, the nationality of the State alleged to be

responsible for causing the injury, and incorporation in that State was required by it

as a precondition for doing business there.515

374. Widely recognized, the ICJ recently had occasion to affirm and apply the rule in the Diallo

Case between Guinea and the Democratic Republic of Congo. It held as follows:

The Court, having carefully examined State practice and decisions of international

courts and tribunals in respect of diplomatic protection of associés and shareholders,

is of the opinion that these do not reveal — at least at the present time — an exception

in customary international law allowing for protection by substitution, such as is relied

on by Guinea.516

375. The ICJ’s holding in Diallo built off its earlier dicta in Barcelona Traction, where it sharply

distinguished between a shareholder’s own right, which is actionable, and its interest, which

is not. There the ICJ concluded that, “[n]ot a mere interest affected, but solely a right

infringed involves responsibility, so that an act directed against and infringing only the

515 International Law Commission, Draft Articles on Diplomatic Protection, 2006, RLA-30.

516 Case concerning Ahmadou Sadio Diallo (Republic of Guinea v. Democratic Republic of the Congo), ICJ, Judgment, ICJ

Reports 2007 of 24 May 2007, RLA-31, ¶ 89.

Page 121: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

116

company's rights does not involve responsibility towards the shareholders, even if their

interests are affected.”517

376. Although the customary international law rule against bringing claims based on the rights of

subsidiary companies is clear, the ICJ has recognized that a treaty, such as an investment

treaty or a friendship, commerce, and navigation treaty, can vary the basic rule. This is the

moral of its ELSI judgment.518

377. However, the Treaty applicable in the present dispute in no way alters the rule of customary

international law that arbitral jurisdiction is limited to claims regarding the investors own

rights and not those of its subsidiaries. In this regard, Article 8(1) of the Treaty provides:

Disputes between a national or company of one Contracting Party and the other

Contracting Party concerning an obligation of the latter under this Agreement in

relation to an investment of the former which have not been legally and amicably

settled shall after a period of six months from written notification of a claim be

submitted to international arbitration if either party to the dispute so wishes.519

378. This provision defines the scope of the claims over which the Tribunal has jurisdiction. It

does not extend jurisdiction to indirect investments of a company, as it would need to do in

order to alter the background rule of customary international law. An indirect investment is

exactly one where the company is not the legal holder of the right to the relevant asset.

Nothing in the Treaty’s arbitration provision suggests that jurisdiction extends to claims

regarding such rights.

379. In this regard, it is worth emphasizing that Bolivia and the United Kingdom, the States Parties

to the Treaty, could have extended jurisdiction to indirect investment, thus varying the rule of

customary international law. Bolivia has explicitly extended jurisdiction to the direct or

indirect investments of foreign companies in other investment treaties, including those

concluded contemporaneously with the Treaty. Notably, one such example, from the year

before the Treaty, is the BIT concluded between Switzerland and Bolivia.520 By contrast,

Bolivia and the United Kingdom did not agree to alter the customary international law rule of

substitution.

517 Barcelona Traction, Light and Power Company, Limited (Belgium/Spain) [1970] ICJ Reports 3, CLA-7, ¶ 46.

518 Case concerning Ahmadou Sadio Diallo (Republic of Guinea v. Democratic Republic of the Congo), ICJ, Judgment, ICJ

Reports 2007 of 24 May 2007, RLA-31, ¶¶ 87-88.

519 Treaty, C-1, Article 8(1).

520 The BIT concluded between Switzerland and Bolivia protects investments owned directly or indirectly by Swiss

companies. Article 1(b) establishes “‘Companies’ means: (aa) In the case of the Swiss Confederation, legal entities or

associations without legal status but able to possess property, in which, directly or indirectly, there is a substantial

Swiss interest […].” Agreement between the Swiss Confederation and the Republic of Bolivia on the reciprocal

promotion and protection of investments, English translation, RLA-19.

Page 122: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

117

380. This is further confirmed by the definition of investment given in the Treaty. Pursuant to the

Treaty, investments are rights that a company might possess, including rights to property,

shares, monetary claims, or contractual performance. The Treaty does not include in the

category of investments rights that are indirectly held, such as the property rights of a

subsidiary.

381. As the Treaty provides in Article 1(a), the forms a qualifying investment may take are:

(i) movable and immovable property and any other property rights such mortgages,

liens or pledges;

(ii) shares in and stock and debentures of a company and any other form participation

in a company;

(iii) claims to money or to any performance under contract having a financial value;

(iv) intellectual property rights and goodwill;

(v) any business concessions granted by the Contracting Parties in accordance with

their respective laws, including concessions to search for, cultivate, extract or exploit

natural resources.521

382. In short, the Treaty does not vary the basic rule of customary international law precluding

jurisdiction over claims regarding rights of subsidiaries as opposed to the claimant company.

383. And in the present case there is no dispute that all of Claimant’s claims regard such rights of

other companies. Claimant freely admits that Glencore Bermuda held nothing more than

shares in Kempsey, Iris, and Shattuck, three Panamanian companies, which in turn own

Colquiri through Sinchi Wayra.522 It similarly admits that Colquiri directly owns the Assets

(or Vinto, owned by Colquiri, in the case of the Tin Smelter).523

384. In light of these plain facts and the prohibition on claims based on the rights of subsidiaries,

the Tribunal has no jurisdiction over Claimant’s claims.

4.5 The Tribunal Lacks Jurisdiction Because The Dispute Concerns Contracts With

Mandatory ICC Arbitration Clauses And Diplomatic Claims Exclusions

385. Claimant attempts to submit to this Tribunal claims that ultimately arise out of and concern

the validity, compliance with, and fulfilment of the Tin Smelter, Antinomy Smelter, and

Colquiri Lease contracts (the “Contracts”). In doing so, it simply ignores the mandatory ICC

521 Treaty, C-1, Article 1(a).

522 Statement of Claim, ¶ 131.

523 Statement of Claim, ¶ 131.

Page 123: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

118

arbitration clauses in each of the Contracts requiring ICC arbitration of the claims. As a result

of these clauses, there is no jurisdiction over any of Claimant’s claims.

386. Each of the three Contracts contains a very broad ICC arbitration clause designed to ensure

that any dispute touching the Contracts directly or indirectly will be submitted to the ICC.

The clause reads:

Todos los desacuerdos, conflictos, disputas, controversias y/o diferencias que se

susciten entre las partes del CONTRATO, que tengan relación directa o indirecta con

la validez, interpretación, alcance y/o cumplimiento del CONTRATO, serán

solucionadas por las partes de la siguiente manera: […] 15.3 Si las partes tampoco

llegaran a un acuerdo total a través del procedimiento de conciliación antes pactado,

todos los desacuerdos, conflictos, disputas, controversias y/o diferencias pendientes de

solución se someterán y serán solucionados a través de un proceso de arbitraje, el cual

se llevará a cabo de acuerdo a las Reglas de la Cámara Internacional de Comercio

(International Chamber of Commerce) y a lo estipulado más adelante en la presente

cláusula.524

387. Moreover, each of the three Contracts contains a further clause designed to preclude any

recourse to dispute resolution under international law:

La ARRENDADORA, el ARRENDATARIO y la OPERADORA, en virtud del

CONTRATO, hacen expresa renuncia a todo reclamo por la via diplomática en cuanto

se refiere a la interpretación y ejecución del CONTRATO.525

388. These contractual provisions, and especially the exclusive ICC arbitration clause, preclude

jurisdiction over Claimant’s claims before this UNCITRAL tribunal. When the rights asserted

in an international investment arbitration arise from a contract, the claimant is bound by any

dispute resolution provision (Section 4.5.1). Although Claimant is not a direct party to the

Contracts, it is bound by the exclusive ICC arbitration clause because it is ultimately asserting

524 Notarizations of the sale and purchase agreement of the Tin Smelter between the Ministry of External Trade and

Investment, Corporación Minera de Bolivia, Empresa Metalúrgica Vinto and Allied Deals Estaño Vinto SA, C-7, Article

15; Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External

Trade and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9,

Article 15; Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol,

Colquiri SA and Comsur of 27 April 2000, C-11, Article 17.3 (Unofficial translation: “All disagreements, conflicts,

disputes, controversies and/or differences arising between the parties to the CONTRACT, directly or indirectly related

to the validity, interpretation, scope and/or compliance with the CONTRACT, shall be resolved by the parties as follows:

[…] 15.3 If the parties do not reach a global agreement following the aforementioned conciliation procedure, all

disagreements, conflicts, disputes, controversies and/or differences pending to be resolved shall be submitted and shall

be resolved by arbitration under the Arbitration Rules of the International Chamber of Commerce and in accordance

with what is further provided in this article”).

525 Notarizations of the sale and purchase agreement of the Tin Smelter between the Ministry of External Trade and

Investment, Corporación Minera de Bolivia, Empresa Metalúrgica Vinto and Allied Deals Estaño Vinto SA, C-7, Article

18; Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External

Trade and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9,

Article 18 (Unofficial translation: “The LESSOR, the LESSEE and the OPERATOR, by virtue of the CONTRACT,

expressly waive any claim through diplomatic channels relating to the interpretation and performance of the

CONTRACT”).

Page 124: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

119

rights to the Tin Smelter, Antinomy Smelter, and Colquiri Mine Lease arising from the

Contracts (Section 4.5.2).

4.5.1 An Investment Arbitral Tribunal Has No Jurisdiction Over Contract Claims Recast As

Treaty Breaches When The Contracts Provide For An Alternative Forum

389. The SGS v. Philippines tribunal is recognized for holding that an investment tribunal cannot

hear a contract claim when the parties to the contract have stipulated mandatory jurisdiction

in a different forum. As it explained:

[T]he Tribunal should not exercise its jurisdiction over a contractual claim when

the parties have already agreed on how such a claim is to be resolved, and have

done so exclusively. SGS should not be able to approbate and reprobate in respect

of the same contract: if it claims under the contract, it should comply with the

contract in respect of the very matter which is the foundation of its claim.526

390. The basic rationale is that Claimant cannot be allowed to pick and choose the parts of the

Contracts on which it wishes to rely (its so-called rights to the assets) and disregard the rest

(the exclusive arbitration clauses). This was the logic of the BIVAC v. Paraguay tribunal

(albeit directly addressing the umbrella clause). As it held, “the parties to a contract are not

free to pick and choose those parts of the Contract that they may wish to incorporate into an

‘umbrella clause’ provision such as Article 3(4) and to ignore others.”527 Any contrary

conclusion “would seriously and negatively undermine contractual autonomy” because “the

parties to a contract […] must respect [their freely assumed] commitments, and they are

entitled to expect that others, including international courts and tribunals, also respect them

[…].”528

391. This is sensible. Arbitral jurisdiction is based on consent. When the parties to a contract have

agreed to the exclusive jurisdiction of a forum, there can be no mutual consent to alternative

fora. The exclusive consent to ICC arbitration from the Tin Smelter, Antinomy Smelter, and

Colquiri Mine Lease Contracts must exclude jurisdiction in any other forum.

526 SGS Société Générale de Surveillance S.A. v. The Republic of the Philippines, ICSID Case No. ARB/02/6, Decision on

Objections to Jurisdiction of 29 January 2004, RLA-32, ¶ 155. See, also, Toto Costruzioni Generali S.p.A. v. The

Republic of Lebanon, ICSID Case No. ARB/07/12, Decision on Jurisdiction of 11 September 2009, RLA-33¶ 202;

General Claims Commission, North American Dredging Company of Texas (U.S.A.) v. United Mexican States,

UNRIAA, volume IV of 31 March 1926, RLA-34, ¶ 23; Woodruff Case, UNRIAA, volume IX of 1903-1905, RLA-35,

p. 222.

527 Bureau Veritas, Inspection, Valuation, Assessment and Control, BIVAC B.V. v. The Republic of Paraguay, ICSID Case

No. ARB/07/9, Decision on Objections to Jurisdiction of 29 May 2009, RLA-36, ¶ 148. See, also, Bosh International

Inc. and B&P Ltd Foreign Investments Enterprise v. Ukraine, ICSID Case No. ARB/08/11, Award of 25 October 2012,

RLA-37, ¶¶ 251-258.

528 Bureau Veritas, Inspection, Valuation, Assessment and Control, BIVAC B.V. v. The Republic of Paraguay, ICSID Case

No. ARB/07/9, Decision on Objections to Jurisdiction of 29 May 2009, RLA-36, ¶ 148.

Page 125: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

120

392. This exclusive consent must even displace the dispute resolution provisions of the Treaty.

The contractual arbitration clauses are more specific to the subject matter of the dispute than

the Treaty dispute resolution provisions, and so predominantly based on the principle of lex

specialis. They were concluded later than the dispute resolution provisions of the Treaty, and

so predominatnly based on the principle of lex posteriori.529 And the parties to the Contracts

specifically elected to exclude any recourse under international law for disputes regarding the

Contracts.530

4.5.2 Claimant’s Claims Concern Obligations Under The Smelter Privatization Contracts

And The Colquiri Lease

393. Claimant’s claims in this dispute have a direct relationship with the validity, interpretation

and fulfillment of the three Contracts underlying the Tin Smelter, the Antinomy Smelter, and

Colquiri Mine Lease. In fact, Claimant itself alleges that “any contractual obligations Bolivia

has entered into with respect to Glencore Bermuda’s or its local affiliates’ investments also

amount to obligations under the Treaty.”531 Thus, they are precluded by the mandatory ICC

arbitration clauses in the Contracts.

394. As an initial matter, there can be no doubt that Claimant alleges in this arbitration that its

affected rights arise directly from the contracts. Claimant asserts as much in its pleadings. It

concedes that Vinto obtained the Tin Smelter via the Tin Smelter Contract,532 that Colquiri

obtained the Antimony Smelter via the Antimony Smelter Contract,533 and that Colquiri

obtained the Colquiri Mine Lease via the Lease Contract.534 Thus, the rights asserted in this

arbitration are ultimately based in these contracts.

529 The Treaty was ratified 16 February 1990 while the contracts were concluded between 2000 and 2002.

530 Notarizations of the sale and purchase agreement of the Tin Smelter between the Ministry of External Trade and

Investment, Corporación Minera de Bolivia, Empresa Metalúrgica Vinto and Allied Deals Estaño Vinto SA, C-7, Article

18; Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External

Trade and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9,

Article 18;Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol,

Colquiri SA and Comsur of 27 April 2000, C-11, Article 19.

531 Statement of Claim, ¶ 181.

532 Statement of Claim, ¶ 29 (citing Notarizations of the sale and purchase agreement of the Tin Smelter between the

Ministry of External Trade and Investment, Corporación Minera de Bolivia, Empresa Metalúrgica Vinto and Allied

Deals Estaño Vinto SA, C-7).

533 Statement of Claim, ¶ 31 (citing Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between

the Ministry of External Trade and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA

of 11 January 2002, C-9).

534 Statement of Claim, ¶ 30 (citing Lease agreement for the Colquiri Mine between the Ministry of External Trade and

Investment, Comibol, Colquiri SA and Comsur of 27 April 2000, C-11

Page 126: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

121

395. Not only do these rights arise from the Contracts, but Claimant’s allegations make it clear that

the dispute is about the validity, interpretation, and fulfillment of the Contracts.

Consequently, the claims are within the scope of the mandatory ICC arbitration clause.

396. First, Claimant alleges, as the foundation of its Tin Smelter claims, that the Tin Smelter

reversion was not justified “on the basis of purported illegalities in the privatization of the

asset.”535 But this allegation is ultimately a question of the legal status of the Tin Smelter

contract and the effects it has on the party’s obligations under that contract. Bolivia reverted

the Tin Smelter exactly because it considered that contract to have been affected by illegalities

that eliminated its obligation to perform under the contract by transferring the Tin Smelter.536

Claimant in fact recognizes that this was Bolivia’s stated reason for the reversion.537 Thus,

the Tin Smelter claims are ultimately covered by the mandatory arbitration clause.

397. Second, Claimant similarly alleges, as the grounds for its Antimony Smelter claims, that the

Antimony Smelter reversion was not justified based “on the Antimony Smelter’s non-

production […].”538 But this too is a contractual question. Claimant recognizes that Bolivia

asserted the productive inactivity as the reason for the reversion. Bolivia’s reversion decree

specifically stated that the productive inactivity justified the reversion because the terms and

conditions for the tender established “las obligaciones de invertir y fortalecer la Empresa

Metalúrgica Vinto Antimonio con capacidad económica, financiera y técnica, […]

posibilitando a la Fundición continuar la producción […].”539 These terms and conditions

were ultimately incorporated into the privatization contract for the Antimony Smelter.540

Thus, Claimant’s Antinomy Smelter claims are ultimately about the fulfilment of the contract.

398. Third, Claimant finally alleges that Bolivia could not terminate the Colquiri Mine Lease in

response to the violent conflict that erupted at the Mine.541 But this is straightforwardly a

question as to whether Bolivia fulfilled its obligations under the Lease Contract. Claimant

specifically alleges that Bolivia breached Article 9.2.1 of the Contract—which states that “[l]a

535 Statement of Claim, ¶ 5.

536 Supreme Decree No 29.026 of 7 February 2007, C-20, Preamble.

537 Statement of Claim, ¶ 67.

538 Statement of Claim, ¶ 6.

539 Supreme Decree No 499 of 1 May 2010, C-26, Preamble, p. 17 (Unofficial translation: “obligations to invest and

reinforce the Empresa Metalúrgica Vinto Antimonio with economic, financial and technical capacity […] allowing the

Smelter to continue production”).

540 Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External Trade

and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9, Article

23(1).

541 Statement of Claim, ¶¶ 8-12.

Page 127: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

122

ARRENDADORA se obliga a no interferir ni limitar las operaciones del

ARRENDATARIO”542—through its actions to ensure public safety and security at the Mine.543

It is indisputably that Claimant’s allegations concern Bolivia’s alleged interference and

limitations of operations at the Colquiri Mine. Thus, Claimant’s Colquiri Mine claims are

about Bolivia’s fulfillment of the Contract under the circumstances.

399. In conclusion, each set of Claimant’s claims are ultimately based on contractual disagreements

regarding the privatization and lease contracts. Such disagreements are within the scope of

the mandatory ICC arbitration clause. This Tribunal has no jurisdiction over the dispute.

4.6 The Tribunal Lacks Jurisdiction Over The Tin Stock Claims Because They Were Never

Notified To Bolivia

400. Claimant alleges that it “formally notified Bolivia of the existence of the dispute, pursuant to

Article 8 of the Treaty.”544 This is incorrect as to its Tin Stock claims. Claimant never notified

Bolivia that it had potential claims regarding the Tin Stock under any international investment

treaty, let alone the Treaty applicable in this dispute. This failure to notify eliminates

jurisdiction over the Tin Stock claims.

401. The Treaty specifies certain preconditions for arbitration in Article 8(1), among them the

requirement to provide written notification of a claim six months before filing for arbitration:

Disputes between a national or company of one Contracting Party and the other

Contracting Party concerning an obligation of the latter under this Agreement in

relation to an investment of the former which have not been legally and amicably

settled shall after a period of six months from written notification of a claim be

submitted to international arbitration if either party to the dispute so wishes.545

402. The purpose of such a “cooling off period” is to allow for non-contentious resolution of the

dispute, in part or in whole. As the Burlington tribunal observed, “[t]he six-month waiting

period requirement of Article VI is designed precisely to provide the State with an opportunity

to redress the dispute before the investor decides to submit the dispute to arbitration.”546

542 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11, Clause 9.2.1 (Unofficial translation: “The LESSOR commits not to interfere with

or limit the LESSEE’s operations”).

543 Statement of Claim, ¶ 186.

544 Statement of Claim, ¶ 134(b). Confirmed in Letter from Glencore (Mr Eskdale) to the Solicitor General (Mr Arce

Zaconeta) and the Minister of Mining and Metallurgy (Mr Navarro Miranda) of 5 January 2016, C-41.

545 Treaty, C-1, Article 8(1).

546 Burlington Resources Inc. v. Republic of Ecuador, ICSID Case No. ARB/08/5, Decision on Jurisdiction of 2 June 2010,

RLA-38, ¶ 312.

Page 128: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

123

However, absent proper notification of a given claim or claims, it is impossible for the state

to seek amicable resolution or to provide redress.

403. It is for this reason that investment tribunals insist on strict compliance with the notification

requirement.547 Notably, the Rurelec tribunal, interpreting the very Treaty from this dispute,

concluded that the notification requirement limits consent to arbitration: “[t]he explicit

wording requiring a written notification and the expiry of a period of six months from that

notification leads the Tribunal to consider that the ‘cooling off period’ narrows the consent

given by the Contracting Parties to international arbitration.”548

404. Despite ample opportunities, Claimant never provided Bolivia with written notification of its

Tin Stock claims, depriving Bolivia of the opportunity to reach an amicable resolution of those

claims.

405. Claimant makes clear in its pleadings that it makes distinct claims concerning the Tin Stock.

In its summary of claims, Claimant alleges that “Bolivia seized the Smelters, the Tin Stock

and the Colquiri Lease” and that “the way the Smelters, the Tin Stock and the Colquiri Lease

were seized also amounts to breaches […].”549 Claimant similarly distinguishes the Tin Stock

claims from those concerning the other assets repeatedly throughout its Statement of

Defense.550

406. The reason is clear. It is Claimant’s case that the Tin Stock “was the property of Colquiri and

did not form part of the Antimony Smelter’s inventory, nor was it included in the Antimony

Smelter Nationalization Decree.”551 For this reason, it contends that Bolivia committed

distinct breaches from those concerning the Antinomy Smelter because “the Minister of

Mining failed to secure its return to Glencore Bermuda or any of its affiliates.”552 So,

Claimant makes a separate set of claims regarding the Tin Stock on the face of its own

pleadings.

547 Burlington Resources Inc. v. Republic of Ecuador, ICSID Case No. ARB/08/5, Decision on Jurisdiction of 2 June 2010,

RLA-38, ¶ 312; Tulip Real Estate and Development Netherlands B.V. v. Republic of Turkey, ICSID Case No.

ARB/11/28, Decision on Bifurcated Jurisdictional Issue of 5 March 2013, RLA-39, ¶ 83.

548 Guaracachi America, Inc and Rurelec Plc v Plurinational State of Bolivia (UNCITRAL) Award of 31 January 2014,

CLA-120, ¶ 388.

549 Statement of Claim, ¶ 139.

550 See, e.g., Statement of Claim, ¶¶ 16, 82, 131, 139, 148, 164-165, 225, 286, 295.

551 Statement of Claim, ¶ 6. See also Statement of Claim, ¶¶ 6, 79, 81, 165, 174, 218.

552 Statement of Claim, ¶ 6. See also Statement of Claim, ¶ 79, 81, 165, 174, 218.

Page 129: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

124

407. Given the nature of the Tin Stock claims, Bolivia should have been given the opportunity to

resolve them amicably. It is Claimant’s own position that the Tin Stock claims arise from a

mistake on the part of Bolivia that potentially could have been resolved more easily than the

remaining claims.

408. But Claimant never gave Bolivia that opportunity by notifying the Tin Stock claims to Bolivia.

Claimant asserts that “in its written notices dated 11 December 2007, 14 May 2010 and 27

June 2012 Glencore Bermuda formally notified Bolivia of the existence of the dispute,

pursuant to Article 8 of the Treaty.”553 However, none of its formal notices of dispute make

even a single reference to the Tin Stock, much less to Claimant’s intention to bring claims

regarding the reversion of the Tin Stock.554

409. Nor did any of Claimant’s additional communications regarding this dispute mention the Tin

Stock or the potential Tin Stock claims. To the contrary, they simply mentioned the reversions

of the Tin Smelter, the Antimony Smelter, and the Colquiri Mine Lease.555 In this regard, the

final communication from Claimant prior to its Request for Arbitration stated only that, “en

febrero de 2007 y mayo de 2010, el Gobierno dispuso, respectivamente, la nacionalización

de las fundiciones de estaño y antimonio pertenecientes al Complejo Metalúrgico Vinto S.A

(Vinto), con todos sus activos.”556 The possibility of the Tin Stock claims was never even

raised.

410. In fact, not a single letter mentions the Tin Stock in connection with Glencore International

or Glencore Bermuda, and still less as the basis of a possible investment treaty claim. The

only letters that refer to the Tin Stock come from Colquiri and they only seek the return of the

553 Statement of Claim, ¶ 134(b). See also, Letter from Glencore (Mr Eskdale) to the Solicitor General (Mr Arce Zaconeta)

and the Minister of Mining and Metallurgy (Mr Navarro Miranda) of 5 January 2016, C-41.

554 Letter from Glencore Bermuda (Mr Kalmin and Mr Hubmann) to Ministry of the Presidency (Mr Quintana), 11

December 2007, C-25; Letters from Glencore International PLC (Mr Maté and Mr Glasenberg) to the President of

Bolivia (Mr Morales) and the Ministry of Mining (Mr Pimentel), 14 May 2010, C-27; and Letters from Glencore

International PLC (Mr Maté) to the President of Bolivia (Mr Morales), 27 June 2012, C-40.

555 See, e.g., Letters from Glencore International (Mr Eskdale) to the Attorney General (Mr Arce), the President of Bolivia

(Mr Morales), the Vice President of Bolivia (Mr García), the Ministry of the Presidency (Mr Quintana), the Minister of

Mining (Mr Navarro), and the President of Comibol (Mr Quispe) of 20 May 2015, C-148; Letter from Sinchi Wayra

(Mr Capriles) to the Minister of Legal Defense (Ms Arismendi) of 22 June 2010, C-103.

556 Letter from Glencore (Mr Eskdale) to the Solicitor General (Mr Arce Zaconeta) and the Minister of Mining and

Metallurgy (Mr Navarro Miranda) of 5 January 2016, C-41 (Unofficial translation: “in February 2007 and May 2010,

the Government decided respectively to nationalize the tin and antimony smelters belonging to the Complejo

Metalúrgico Vinto S.A (Vinto), together with all its assets”).

Page 130: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

125

Tin Stock following its reversion.557 None of them mention a possible international claim by

Glencore International or Glencore Bermuda.

411. In short, Claimant did not notify its Tin Stock claims prior to arbitration as the Treaty requires.

Those claims must be rejected for lack of jurisdiction.

5. BOLIVIA’S REQUEST FOR BIFURCATION SHOULD BE GRANTED

412. As Bolivia has repeatedly emphasized,558 efficiency and justice demand bifurcation of this

dispute. Any of Bolivia’s preliminary objections would conclusively dispose of this dispute

without further proceedings (with a single exception). Resolution of the dispute following a

bifurcation would avoid the substantial time and expense associated with a full merits phase

and, more fundamentally, would ensure that Bolivia does not have to defend itself in a forum

to which it has not granted its consent.

413. Claimant implicitly recognizes that bifurcation is appropriate in this case. It is for this reason

that Claimant has deliberately attempted to block bifurcation through procedural tactics that

caused further delay and costs. It refused to submit its arguments on bifurcation when the

Tribunal invited it to do so in March, instead commenting only on how to reach a decision on

bifurcation.559 It then insisted on submitting a Statement of Claim prior to any decision on

bifurcation.560 It now attempts to claim that bifurcation would be inefficient, invoking the

conditions that Claimant itself created.561

414. Despite have intentionally caused delay in the decision on bifurcation, Claimant now has the

audacity to allege that Bolivia seeks to delay the case.562 This allegation is manifestly false.

Bolivia has set forth serious jurisdictional objections that could put an immediate end to the

dispute (the opposite of delay). But the complaints about delay also lie ill in Claimant’s

mouth. Claimant was willing to wait almost ten years following the Tin Smelter reversion to

557 Letter from Colquiri SA (Mr Capriles Tejada) to Ministry of Mining (Mr Pimentel Castillo) of 3 May 2010, C-28; Letter

from Colquiri (Mr Capriles) to the Minister of Mining (Mr Pimentel) of 7 June 2010, C-101; Letter from EMV (Mr

Villavicencio) to Colquiri (Mr Capriles) of 8 June 2010, C-102.

558 Respuesta a la Notificacion de Arbitraje of 18 August 2016, ¶ 53; Escrito de Bolivia sobre Cuestiones Procesales, ¶ 20;

Bolivia's Response on Bifurcation, ¶ 10.

559 Claimant's Letter to the PCA, dated 3 April 2017, pp. 6-8.

560 Claimant's Letter to the PCA, dated 3 April 2017, pp. 7-8.

561 Statement of Claim, ¶¶ 299, 325.

562 Statement of Claim, ¶ 328.

Page 131: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

126

commence this arbitration. It is simply not credible for Claimant now to assert that a

jurisdictional phase would be “unreasonably burdensome.”563

415. Neither Claimant’s arguments nor strategic delays can defeat Bolivia’s right to have its serious

and substantial preliminary objections heard in a bifurcated phase. Bifurcation is to be

presumed, absent good cause, for reasons of justice and efficiency (Section 5.1). There can

be no good cause to deny bifurcation to Bolivia’s preliminary objections (Section 5.2).

5.1 Granting Bifurcation Prevents States From Having To Defend Themselves When There

Is No Jurisdiction And Ensures Efficient Resolution Of Disputes

416. Despite the clear demands of efficiency and justice, Claimant continues to argue that the

Tribunal should in effect adopt a presumption against bifurcation.564 But this is wrong. To

the contrary, the Tribunal should presume that the proceedings are to be bifurcated for two

reasons that cut to the core of the international arbitral system: procedural justice and

procedural efficiency.

417. First, it is fundamentally unjust, and even contrary to fundamental legal principles, to demand

that a state defend itself against the merits of a claim before a tribunal without jurisdiction or

where that jurisdiction is in dispute. Jurisdiction for international adjudication is premised

on state consent and only with that consent may a tribunal or court proceed to review state

behaviour.

418. No less an authority on international adjudication than Prof. Rosenne has confirmed this rule.

As Prof. Rosenne affirms, “[a] basic rule of international law and a principle of international

relations [provides] that a State is not obliged [to] give an account of itself on issues of merits

before an international tribunal which lacks jurisdiction or whose jurisdiction has not been

established.”565 Prof. Thirlway echoes this view. He avows that “a jurisdictional issue must

be dealt with as a preliminary point since a State is entitled to decline to permit its conduct to

be scrutinized by a tribunal unless it has conferred jurisdiction on that tribunal.”566

419. In fact, Claimant’s own authority, Prof. Lalive, took the same position. Quoting Sir Hersh

Lauterpacht with favor, Prof. Lalive affirmed that “‘[a] defendant Government which pleads

to the jurisdiction of the Court ought not, without good reasons, and without its consent, to be

563 Statement of Claim, ¶ 328.

564 Statement of Claim, section VII(A)(1).

565 S. Rosenne, The world court: what it is and how it works, 5th ed., 1995, RLA-40, p. 99.

566 H. Thirlway, “Preliminary Objections” in Max Planck Encyclopedia of Public International Law, August 2006, RLA-

41, ¶ 4.

Page 132: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

127

expected to submit to the effort, expense and uncertainty of engaging in proceedings on the

merits.’”567 And Prof. Lalive’s statement, which Claimant cites out of context, that tribunals

sometimes find good reasons to join jurisdiction to the merits, does not change his

confirmation of the basic legal position.568

420. Bifurcation, in short, is favoured by the basic principles of international adjudication and even

of fundamental justice. A state cannot be judged until the tribunal’s capacity to do so is

confirmed. In this regard, Claimant is simply wrong to argue that the only relevant

consideration is efficiency.569

421. Second, efficiency is, however, an additional consideration that militates in favor of

bifurcation. By considering preliminary objections separately, the time and costs associated

with consideration of the merits are potentially avoided.

422. The Philip Morris v. Australia tribunal, when deciding in favor of bifurcation,570 emphasized

the substantial savings in time and costs that bifurcation could (and in fact did) bring. It

recognized that the merits phase would “be extremely large and complex in the submissions,

documents, witness and expert testimonies, and issues to be evaluated” and so concluded that,

“should preliminary objections prevail with the result that no procedure on the merits

becomes necessary, this would result in a major saving of work and costs.”571 Notably, it

reached this conclusion even though “the Respondent ha[d] already submitted its full

Statement of Defence” and “the work involved and the period up to a final hearing would be

shorter than in the usual scenario […].”572

423. By contrast, the Caratube tribunal came to regret that the respondent state had not sought

bifurcation, given the great loss of efficiency incurred from hearing the entire dispute in a

single phase. As that tribunal observed, “[w]ith the wisdom of hindsight, the majority of the

costs and expenses of each party and of the dispute, both in duration and expense, would have

been avoided had Respondent opted for bifurcation and the preliminary determination of its

567 P Lalive, “Some objections to Jurisdiction in Investor-State Arbitration,” Transcript of Presentation to the 16th ICCA

Congress, London, CLA-35, p. 8.

568 Statement of Claim, ¶ 302 (citing P Lalive, “Some objections to Jurisdiction in Investor-State Arbitration,” Transcript

of Presentation to the 16th ICCA Congress, London, CLA-35, p. 8).

569 Statement of Claim, ¶ 299.

570 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Procedural Order No 8 of 14 April 2014, CLA-

121, ¶¶ 116, 123.

571 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Procedural Order No 8 of 14 April 2014, CLA-

121, ¶ 106.

572 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Procedural Order No 8 of 14 April 2014, CLA-

121, ¶ 105.

Page 133: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

128

equivalent of Rule 41(1) objections under the Rules.”573 In that case, as in this one, the

potential savings in duration and expense included reducing legal time and fees, eliminating

experts and their reports, and reduction of hearing length.574

424. Claimant tries to discount the costs from an unnecessary merits phase and suggests that

bifurcation would also result in inefficiency, as either party may be motivated to challenge the

resulting decision on preliminary objections before the domestic courts at the seat of the

arbitration.575 This rebuttal goes nowhere. Just as with the arbitration itself, any set aside

proceedings would be vastly simplified and reduced in cost if they only have to address

preliminary objections and not the remainder of the dispute. The same is true if there is no

bifurcation, because either party may seek to set aside the decision on preliminary objections

even when rendered along with a merits award. Thus, Claimant’s argument here is simply

irrelevant.

425. By resisting bifurcation until after the Statement of Claim (and Statement of Defense),

Claimant has already introduced substantial inefficiencies into this proceeding. A failure to

bifurcate at this stage would further add to the wasted time and resources by forcing the parties

to litigate the merits and quantum, even though the Tribunal lacks the capacity to decide the

claims.

426. Given that both justice and efficiency weigh heavily in favor of bifurcation, Claimant instead

attempts to distract attention from these facts. It argues that “[t]he 2010 UNCITRAL Rules,

which apply to this case, eliminated any presumption that might have existed under the 1976

UNCITRAL Rules in favor of hearing jurisdictional objections as a preliminary question.”576

But this argument is a red herring. Bolivia does not argue that there is a presumption in favor

of bifurcation simply because of the language of the UNCITRAL Rules. Instead, it is

Bolivia’s position that fundamental considerations of justice and efficiency compel

bifurcation.

427. Claimant also attempts to distract attention from the demands of justice and efficiency by

citing to academic commentary on bifurcation in commercial arbitration.577 But commercial

arbitration, involving commercial parties, is subject to a very different legal framework and

573 Caratube International Oil Company LLP v. The Republic of Kazakhstan, ICSID Case No. ARB/08/12, Award of 5

June 2012, RLA-42, ¶ 487.

574 Caratube International Oil Company LLP v. The Republic of Kazakhstan, ICSID Case No. ARB/08/12, Award of 5

June 2012, RLA-42, ¶¶ 488-490.

575 Statement of Claim, ¶ 327.

576 Statement of Claim, ¶ 300.

577 Statement of Claim, ¶ 303.

Page 134: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

129

legal considerations than investment arbitrations against sovereign states. Commercial

companies, even involved in domestic arbitration, do not have the same rights and

prerogatives as sovereign states. Notably, sovereign states are never subject to compulsory

jurisdiction.

428. In short, the demands of justice and efficiency establish a weighty presumption in favor of

bifurcation of international proceedings.

5.2 Bolivia’s Objections Comply With All The Requirements For An Order On Bifurcation

429. Taking into account the presumption in favor of bifurcation, the Tribunal’s analysis should

apply the three criteria from Philip Morris Asia v. Australia: “1) Is the objection prima facie

serious and substantial? 2) Can the objection be examined without prejudging or entering the

merits? 3) Could the objection, if successful, dispose of all or an essential part of the claims

raised?”578 If these criteria are plausibly met, the proceedings must be bifurcated.

430. Although Claimant too acknowledges that Philip Morris provides the applicable standard, it

attempts to distort that standard.579 It proposes that the standard asks whether the objection

has a great “likelihood of success” rather than whether the objection is “serious and

substantial.”580 But neither Philip Morris nor Glamis Gold,581 Claimant’s other authority, in

fact propose such a criterion, and for good reason: the evaluation of a request for bifurcation

cannot require that the tribunal enter into the merits of the preliminary objections. The criteria

are as Philip Morris sets them forth.

431. Bolivia’s objections clearly satisfy the Philip Morris criteria. As already mentioned, if any of

Bolivia’s preliminary objections were granted (except the failure to notify the dispute about

the Tin Stock582), it would bring an immediate end to the entirety of this arbitration. The

objections are serious and substantial, as they are backed by extensive legal authorities and

factual exhibits. And the preliminary objections are entirely separate from the merits: the

core facts for the objections extend only through when Glencore Bermuda received the Assets

in 2005, while the core merits facts are from events in 2007, 2010, 2012, and beyond.

578 Philip Morris Asia Limited v Commonwealth of Australia (UNCITRAL) Procedural Order No 8 of 14 April 2014, CLA-

121, ¶ 109.

579 Statement of Claim, ¶ 307.

580 Statement of Claim, ¶¶ 304, 307.

581 Glamis Gold Ltd v United States of America (UNCITRAL) Procedural Order No 2 of 31 May 2005, CLA-58, ¶ 12(c).

582 Glencore never notified Bolivia that it had potential claims regarding the Tin Stock under any international investment

treaty, let alone the Treaty applicable in this dispute. This failure to notify eliminates jurisdiction over the Tin Stock

claims. See section 2.6.2 above.

Page 135: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

130

432. First, the objection that Glencore Bermuda did not invest relies on the basic principle of

investment arbitration that the so-called investor must make an investment to be protected. It

further is based on the undisputed fact that Glencore Bermuda was simply assigned the legal

rights to shares in the Panamanian companies in 2005, but made no payment or contribution

in exchange for its so-called investment. This objection rests on accepted legal principles,

uncontested facts, and has no relation to the merits.

433. Second, the objection that Claimant committed an abuse of process is based on a widely

accepted principle of international adjudication. Its factual foundations regarding the

foreseeability of the alleged expropriations are supported by extensive evidence of the

controversies surrounding the assets in 2005 when the assets were transferred to Glencore

Bermuda. They do not concern whether the later reversions were in fact expropriations or

otherwise illegal. The objection thus rests on solid legal and factual bases that are unrelated

to the merits.

434. Third, the objection that the Assets were illegal privatized concerns a privatization process

that occurred from 1999-2002, and was long since over at the time of the alleged

expropriations at the core of this dispute. It is a well-established principle of investment law

that claims cannot be heard when the underlying asset is tainted by illegality. Thus, the

objection is founded on solid legal principles and facts with no relationship to the merits of

the dispute.

435. Fourth, the objection that Claimant is, in reality, Swiss is based on the legal authority of the

ICJ and undisputable facts about Glencore Bermuda. These facts are centered on Bermuda

and have nothing at all to do with what is alleged to have happened in Bolivia. The legal and

factual bases for the claim are substantial and unrelated to the merits of the dispute.

436. Fifth, the objection that this dispute is subject to the mandatory ICC arbitration clauses in the

privatization contracts is based on plain contractual provisions. It is widely accepted in

international law that mandatory arbitration clauses preclude litigation in other fora. As the

objection is based on 2000-2002 mandatory arbitration agreements, it is serious and

substantial and unrelated to the merits.

437. Although Bolivia’s objections clearly satisfy the Philip Morris criteria, Claimant nevertheless

argues against bifurcation. It primarily argues that that the preliminary objections “are clearly

closely intertwined with the merits.”583 But this response amounts to nothing more than a bald

assertion. Claimant does not, and cannot, provide any reasonable explanation as to why

583 Statement of Claim, ¶ 321.

Page 136: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

131

preliminary objections concerning the making of the so-called investment would intertwine

with merits facts that occurred after the so-called investment was complete.

438. Instead, Claimant’s explanation is that Mr. Eskdale would have to testify twice in the event

of bifurcation. But this argument is both legally irrelevant and factually incorrect.584 The

facts for preliminary objections remain legally separate from the merits even if one witness

addresses both sets of facts; otherwise any claimant could strategically defeat bifurcation by

simply having a witness talk about both sets of facts. It is also incorrect that Mr. Eskdale

would necessarily have to testify twice: if any of Bolivia’s preliminary objections are

accepted, Mr. Eskdale would only have to testify a single time.

439. It does not help Claimant to add that the merits of the dispute concern “the facts,

circumstances and the legal framework on which Glencore Bermuda relied when investing in

Bolivia.”585 Apart from these considerations having almost nothing to do with the merits

(legitimate expectations are nothing more than tack-on claims586), Bolivia’s preliminary

objections do not concern what Claimant did or did not rely on when investing.

440. In short, Bolivia’s preliminary objections should all be heard in a bifurcated phase in order to

ensure Bolivia is treated with justice and to promote efficiency. The objections are serious

and substantial and have nothing to do with the merits of the dispute. Basic principles of

international adjudication demand bifurcation.

6. BOLIVIA’S CONDUCT WAS CONSISTENT WITH THE TREATY AND

INTERNATIONAL LAW

441. Claimant advances three sets of claims based on the reversion of the Assets. Repeating the

same arguments in various permutations and combinations, Claimant essentially alleges that

these reversions breached the expropriation clause, full protection and security clause

(“FPS”), and the fair and equitable treatment (“FET”) and impairment clauses of the Treaty.

442. Each and every one of these allegations is false. The reversions did not breach the

expropriation clause of the Treaty because they were valid exercises of Bolivia’s police

powers and otherwise lawful (Section 6.1). They did not breach the FPS clause of the Treaty

because there was never any risk of permanent impairment to the Assets and Bolivia took all

reasonable and legal measures of protection available under the circumstances (Section 6.2).

584 Statement of Claim, ¶ 315.

585 Statement of Claim, ¶ 325.

586 See section 6.3.1 below.

Page 137: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

132

And they certainly did not breach the FET or impairment clauses; Claimant’s allegations to

the contrary are mere repetitions of its other claims (Section 6.3).

6.1 Bolivia Did Not Expropriate The Assets But Instead Exercised Its Rights Under Bolivian

Law And Under The Police Powers Doctrine

443. Claimant’s principal allegations in this arbitration are that Bolivia carried out unlawful

expropriations of the Tin Smelter, the Antimony Smelter, the Tin Stock, and the Colquiri Mine

Lease. It argues that “Bolivia does not contest that it has nationalized, through an outright

taking, the assets of Colquiri and Vinto (ie, the Tin Smelter, the Antimony Smelter, the Colquiri

Lease and the Tin Stock)”587 and that, “[i]n order for Bolivia to carry out a lawful

expropriation, it must comply with the requirements set out in Article 5 of the Treaty.”588

444. These allegations are riddled with errors. Claimant fails even to consider, much less to

disprove, that Bolivia’s reversions were valid exercises of its police powers, taken to enforce

law, public order, and safety within its territory. The Tin Smelter was reverted because it was

illegally privatized and the Antimony Smelter was reverted because of a breach of the basic

contractual commitment to put the Smelter into production. And, as is obvious even from

Claimant’s own pleadings, Bolivia reverted the Colquiri Mine Lease in order to restore public

order and safety following a massive conflict that Glencore International allowed to develop

with the artisanal miners who shared rights to the Colquiri Mine. (Section 6.1.1)

445. Claimant also incurs the basic legal error of assuming that expropriations (which the

reversions were not) breach investment treaties and are unlawful whenever compensation is

not paid or prior due process is not accorded. This assumption is incorrect. The failure to

pay compensation pending the outcome of arbitration or court proceedings neither breaches

the Treaty nor makes an expropriation unlawful. And the only due process that the Treaty

requires is posterior, to be satisfied either by court proceedings before the domestic courts

(which Claimant never pursued) or by this very arbitration. There was no breach of the

Treaty’s requirements for expropriation, even assuming (quod non) that one occurred.

(Section 6.1.2)

587 Statement of Claim, ¶ 148.

588 Statement of Claim, ¶ 149.

Page 138: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

133

6.1.1 Bolivia Carried Out A Legitimate Exercise Of Its Police Powers To Enforce The Law

And To Maintain Public Safety

446. In its attempt to show that the reversions were expropriations, Claimant does nothing more

than assert that possession of the Tin Smelter, the Antimony Smelter, the Tin Stock, and the

Colquiri Mine Lease were taken from it. But this is entirely insufficient.

447. Under international law, to prove an expropriation, it is also necessary to show that the

impugned measures were not valid exercises of police powers (Section 6.1.1.1). There can

be no doubt that the reversions of the Tin Smelter, Antinomy Smelter, and Tin Stock were

such valid exercises. The Tin Smelter was reverted because the privatization was illegal and

the Antinomy Smelter was reverted because Colquiri never satisfied the fundamental

condition of the privatization, that the Smelter be put back in operation. And the reversion of

the Colquiri Mine Lease was a similarly valid exercise of police powers, taken to restore

public order and public safety in the face of a violent conflict at the mine (Section 6.1.1.2).

6.1.1.1 Legitimate Exercises Of Police Powers To Enforce The Law Or To Maintain Public Safety

Are Not Expropriatory

448. It is Claimant’s position that allegations of expropriation can be decided on a summary basis.

It argues that “[a] physical occupation, dispossession or assumption of substantial control

that is not merely ephemeral and that deprives an investor of the use or enjoyment of its

investment, including the deprivation of all or a significant part of the economic benefit of its

property, is expropriatory.”589 From this, Claimant infers that, “[i]f the measures at stake

have these effects, there is no need to inquire into the motives, intentions or form of the

measures in order to conclude that an expropriation has occurred.”590

449. This simplistic view of expropriation is contrary to well-established international law.

According to the international doctrine of police powers, an exercise of a state’s police powers

in the public interest is not an expropriation. This principle holds that “the State’s reasonable

bona fide exercise of police powers in such matters as the maintenance of public order, health

or morality, excludes compensation even when it causes economic damage to an investor and

that the measures taken for that purpose should not be considered as expropriatory […].”591

589 Statement of Claim, ¶ 147.

590 Statement of Claim, ¶ 147.

591 Philip Morris Brand Sàrl, Philip Morris Products S.A. and Abal Hermanos S.A. v. Oriental Republic of Uruguay, ICSID

Case No. ARB/10/7, Award, RLA-43, ¶ 295.

Page 139: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

134

450. Thus, Claimant cannot merely make conclusory allegations based on alleged losses of

economic benefit; it must demonstrate that an expropriation has actually occurred.

451. It is beyond serious doubt that the police powers doctrine in international law limits the Treaty

obligations concerning expropriation, including the requirement to pay compensation. Article

31(3)(c) of the Vienna Convention on the Law of Treaties mandates the interpretation of the

Treaty’s expropriation provision in light of “any relevant rules of international law applicable

in the relations between the parties.”592 One of these rules is the police powers doctrine.

452. This was the conclusion of the Philip Morris v. Uruguay tribunal. The Claimant in that case

argued that the exercise of police powers is not an exception or a defense to expropriation. 593

The tribunal flatly rejected the argument. As it explained:

The Tribunal disagrees. As pointed out by the Respondent, Article 5(1) of the BIT must

be interpreted in accordance with Article 31(3)(c) of the VCLT requiring that treaty

provisions be interpreted in the light of “[a]ny relevant rules of international law

applicable to the relations between the parties,” a reference “which includes …

customary international law.” This directs the Tribunal to refer to the rules of

customary international law as they have evolved.594

453. The Philip Morris v. Uruguay tribunal is a recent entry in a long line of authorities to recognize

the police powers doctrine. Most notably, the 1961 Harvard Draft Convention on the

International Responsibility of States for Injury to Aliens recognized the police powers

doctrine as a defense to expropriation claims in a broad range of circumstances:

An uncompensated taking of an alien property or a deprivation of the use or enjoyment

of property of an alien which results from the execution of tax laws; from a general

change in the value of currency; from the action of the competent authorities of the

State in the maintenance of public order, health or morality; or from the valid exercise

of belligerent rights or otherwise incidental to the normal operation of the laws of the

State shall not be considered wrongful, provided (a) it is not a clear and discriminatory

violation of the law of the State concerned; (b) it is not the result of a violation of any

provision of Article 6 to 8 of this Convention [denial of justice]; (c) it is not an

unreasonable departure from the principles of justice recognized by the principal legal

systems of the world; and (d) it is not an abuse of the powers specified in this paragraph

for the purpose of depriving an alien of his property.595

592 Vienna Convention on the Law of Treaties, 1155 UNTS 331 of 23 May 1969, CLA-6, Article 31(3)(c).

593 Philip Morris Brand Sàrl, Philip Morris Products S.A. and Abal Hermanos S.A. v. Oriental Republic of Uruguay, ICSID

Case No. ARB/10/7, Award, RLA-43, ¶¶ 289-290.

594 Philip Morris Brand Sàrl, Philip Morris Products S.A. and Abal Hermanos S.A. v. Oriental Republic of Uruguay, ICSID

Case No. ARB/10/7, Award, RLA-43, ¶¶ 289-290.

595 The American Journal of International Law, Harvard Draft Convention on the International Responsibility of States for

Injuries to Aliens, 1961, RLA-44, Article 10(5).

Page 140: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

135

454. In the years since that Convention, repeated investment tribunals have applied the police

powers doctrine as a limitation on expropriation. These tribunals include Saluka v. Czech

Republic,596 Methanex Corp v. USA,597 Chemtura v. Canada,598 Suez v. Argentina,599 and Les

Laboratoires Servier, S.A.S. v. Poland.600 The doctrine has been applied in substance, if not

in name, by many other tribunals.601

455. Crucially, the police powers doctrine assigns claimant the burden of proof to establish that

actions allegedly constituting expropriation were not an exercise of police powers. Once a

respondent proposes a prima facie justification for the impugned actions, it falls to the

claimant to prove that the actions were disproportionate, discriminatory, or in bad faith. As

the tribunal in Les Laboratoires held:

Poland has come forward with prima facie justification for rejecting the Claimant’s

applications for marketing authorizations. […]

In light of such explanations, it would be unreasonable to demand that Poland “prove

the negative” in the sense of demonstrating an absence of bad faith and discrimination,

or the lack of disproportionateness in the measures taken.

Thus, the burden then falls onto the Claimants to show that Poland’s regulatory actions

were inconsistent with a legitimate exercise of Poland’s police powers. If the Claimants

produce sufficient evidence for such a showing, the burden shifts to Poland to rebut

it.602

456. In short, once Bolivia puts forth evidence that the reversions were taken for public purposes—

protecting public health and safety and confiscating goods unlawfully obtained—as it does

below, it becomes Claimant’s burden to demonstrate that Bolivia’s actions were

disproportionate, discriminatory, or in bad faith.

596 Saluka Investments BV v Czech Republic (UNCITRAL) Partial Award of 17 March 2006, CLA-62, ¶¶ 255; 262.

597 Methanex Corporation v. USA, NAFTA/UNCITRAL, Final Award on Jurisdiction and Merits of 3 August 2005, RLA-

45, Part IV, Chapter D, ¶ 7.

598 Chemtura Corporation v. Canada, NAFTA/UNCITRAL, Award of 2 August 2010, RLA-46, ¶ 266.

599 Suez, Sociedad General de Aguas de Barcelona S.A., and Vivendi Universal S.A. v. The Argentine Republic, ICSID Case

No. ARB/03/19, Decision on Liability of 30 July 2010, RLA-47, ¶¶ 139-140.

600 Les Laboratoires Servier, S.A.S., Biofarma, S.A.S., Arts et Techniques du Progres S.A.S. v. Republic of Poland, PCA,

Final Award of 14 February 2012, RLA-48, ¶¶ 569-584.

601 Marvin Roy Feldman Karpa v. United Mexican States, ICSID Case No. ARB(AF)/99/1, Award of 16 December 2002,

RLA-49, ¶ 103; Total SA v Argentine Republic (ICSID Case No ARB/04/1) Decision on Liability of 27 December 2010,

CLA-103, ¶ 123; Glamis Gold, Ltd. v. The United States of America, UNCITRAL, Award of 8 June 2009, RLA-50, ¶

804.

602 Les Laboratoires Servier, S.A.S., Biofarma, S.A.S., Arts et Techniques du Progres S.A.S. v. Republic of Poland, PCA,

Final Award of 14 February 2012, RLA-48, ¶¶ 582 – 584.

Page 141: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

136

6.1.1.2 The Reversions Were Exercises Of Police Powers Implemented For Public Purposes

457. There can be little doubt that each of the reversions was made for a public purpose within the

scope of the police powers doctrine. The Tin Smelter was reverted due to illegality, the

Antimony Smelter due to productive inactivity, and the Colquiri Mine Lease due to violent

conflict at the Mine. It is Claimant’s burden to disprove that these actions fall within Bolivia’s

police powers.

458. First, Bolivia reverted the Tin Smelter because of illegalities in the privatization process, as a

measure to return wrongfully privatized assets to their rightful owner. Thus, this was an

exercise of police powers, not an expropriation.

459. The Tin Smelter reversion decree explicitly stated that the reversion was undertaken to combat

the illegalities that had tainted the privatization. As it explained, “del análisis del proceso de

privatización se evidencia que la Fundición de Estaño Vinto, fue transferida violando

diferentes normas y disposiciones legales.” 603

460. Among these violations, the most important was the improper price for which the Smelter was

sold. The Tin Smelter was effectively privatized for a negative price; Bolivia received

US$ 14,751,349 but included US$ 16,521,556 in tin concentrate and spare parts. As the

reversion decree correctly observed, the Smelter was sold “por el monto de $us14.751.349”

to Vinto SA even though “se ha beneficiado además con la entrega ilegal de estaño metálico

en circuito, concentrados, materiales y repuestos por más de $us16.000.000.”604 A report

from EMV to COMIBOL in July 2000 confirmed that the Tin Smelter had been transferred

along with US$ 16,521,556 in spare parts and tin concentrate.605

461. In addition to the inexplicable low price, the tender process suffered from additional serious

irregularities: the Tin Smelter tender was awarded even though the purchaser was not qualified

pursuant to the Terms of Reference. Allied Deals did not meet the minimum financial

requirements to participate in the tender process and acquire the Tin Smelter for Vinto SA.606

Bidders were required to demonstrate that they had the financial capacity to operate the Tin

603 Supreme Decree No 29.026 of 7 February 2007, C-20, p. 5 (Unofficial translation: “it appears from the analysis of the

privatization process that the Tin Smelter Vinto was transferred in breach of various rules and legal provisions”).

604 Supreme Decree No 29.026 of 7 February 2007, C-20, p. 5; COMIBOL, Report on the reversion of the Complejo

Metalúrgico Vinto to the Bolivian State of 29 January 2007, R-247, p. 2 (Unofficial translation: “[despite the]

adjudication amount of $us14,751,349 […] Allied Deals PLC has furthermore benefited from the illegal delivery of

metallic tin in circuit, concentrate, materials and spare parts for more than $us16.000.000.- (SIXTEEN MILLION

00/100 AMERICAN DOLLARS)’”); see also Supreme Decree No. 29.026 of 7 February 2007, R-248.

605 Report from Ms Wilma Morales Espinoza (EMV) to Eng. Rafael Delgadillo (COMIBOL) of 7 July 2000, R-121, p. 2.

606 See section 2.4.1 above.

Page 142: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

137

Smelter, something that Allied Deals could not do. And Allied Deals also did not meet the

minimum environmental and security requirements for the tender.607 It did not provide any of

the required evidence that it had a satisfactory environmental record.

462. There can be no doubt that the confiscation of illegally acquired assets is a public purpose

falling within the scope of the police powers doctrine. It is common across most states to

confiscate property tainted by illegality without providing compensation. For example, in

many parts of the United States, property may be seized under civil forfeiture laws whenever

there is probable cause to believe that the property is connected to certain criminal activity.608

In other legal systems, a similar effect is accomplished through the legal figure of extinction

of domain.609 Such confiscations are not considered to be expropriations, for the simple

reason that an obligation to compensate for the confiscation of illegal goods would effectively

defeat the entire purpose.

463. Thus, Bolivia’s reversion of the Tin Smelter due to the illegalities tainting its privatization

was for a public purpose within the scope of the police powers doctrine. It was not an

expropriation.

464. Second, the reversion of the Antimony Smelter was similarly for the public purpose of limiting

the private ownership of productive assets to those who will use them productively. There

was no expropriation of the Antimony Smelter.

465. The reversion decree for the Antimony Smelter makes clear that it was reverted for failure to

ensuring the productive activity of the smelter. The reversion decree observes that “en los

últimos años se evidenció la inactividad productiva de la Planta Metalúrgica Vinto

Antimonio, asi como su desmantelamiento […].”610 It concludes that the inactivity prevents

the Smelter from becoming “una fuente de generación de empleo, tributos y externalidades

en apoyo a la actividad minera de explotación y concentración de antimonio en el país.”611

607 See section 2.4.1 above.

608 See, e.g., Delaware Code, Title 16 (Health and Safety), Chapter 47 (Controlled Substances Act), RLA-51, § 4784(c)–

(j)); Massachussets General Laws, Title XV (Regulation of Trade), Chapter 94C (Controlled Substances Act), RLA-52,

§ 47(d).

609 Colombian Law No. 1708 of 20 January 2014, RLA-53, Article 15; Federal Law of Extinction of Domain, implementing

Article 22 of the Constitution of the United Mexican States of 29 May 2009, RLA-54, Article 3.

610 Supreme Decree No 499 of 1 May 2010, C-26, p. 2 (Unofficial translation: “In recent years, the inactivity of the

Metallurgical Company Vinto Antimonio became obvious, as well as its dismantling”).

611 Supreme Decree No 499 of 1 May 2010, C-26, p. 2 (Unofficial translation: “a source for the generation of employment

and tax, in support of the mining activity of exploitation and concentration of antimony in the country”).

Page 143: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

138

Accordingly, the purpose of the reversion was for failure to ensure the productive activity of

the Smelter, to the detriment of the public interest.

466. It is commonly accepted across Latin America that the social function of property limits the

rights of property holders. Private property exists specifically to ensure that the productive

use of assets contributes to society. Non-productive property performs no social function and

should not receive protection from the state apparatus, with the result that there is no right to

property.612 States who recognize that private property must have a social function include,

in Latin America, Colombia, Chile, and Brazil,613 and, in Europe, Germany, Italy, and

Spain.614 The Bolivian Constitution similarly adopts the social function doctrine: private

property is only a right when the property performs a social function.615

467. Reflecting this concern, the legal regulation for privatization established the objective of

increasing “la producción, las exportaciones, el empleo y la productividad,”616 which the

Antimony Smelter contract directly incorporated in its provisions. According to the tender

Terms of Reference —which became part of the final contractual terms617— for the Antimony

Smelter, the privatization was to guarantee that the Smelter would be put into production.

They stated that the privatization would make possible “a la Fundición continuar la

producción, constituyéndose en una fuente de generación de empleo y tributos, en apoyo a la

actividad minera de explotación y concentración de antimonio en el país.”618

468. In this regard, COMIBOL issued a report during the privatization process confirming that the

public purpose behind the privatization process was to increase the productive efficiency of

612 D. Bonilla, “Liberalism and Property in Colombia: Property as a Right and Property as a Social Function”, 80 Fordham

Law Review, 2011, RLA-55, pp. 1163-1164.

613 Political Constitution of Colombia, RLA-21, Article 58; Political Constitution of the Republic of Chile, RLA-56, Article

24; Constitution of the Federative Republic of Brazil, RLA-57, Article 5(XXIII).

614 Basic Law for the Federal Republic of Germany, RLA-58, Article 14(2); Constitution of the Italian Republic, RLA-

59, Article 42; Spanish Constitution, RLA-20, Article 33.

615 Constitution of Bolivia of 7 February 2009, C-95, Article 56: “I. Toda persona tiene derecho a la propiedad privada

individual o colectiva, siempre que ésta cumpla una función social; II. Se garantiza la propiedad privada siempre que el

uso que se haga de ella no sea perjudicial al interés colectivo.” The previous Constitution (promulgated in 2004) also

established the same condition in its Article 7(i), Bolivian Constitution, Law of 13 April 2004, R-235 (Unofficial

translation: “I. All persons have the right to individual or collective private property, provided that it fulfils a social

function; II. Private property is guaranteed as long as its use is not detrimental to the collective interest”).

616 Supreme Decree No. 23.991 of 10 April 1995, R-100, Art. 2(c) (Unofficial translation: “production, exports,

employment and productivity”).

617 Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External Trade

and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9, 23(1),

p. 21.

618 Terms of Reference for the Second Public Tender for the Antimony Smelter of 31 July 2000, R-109, p. 9 (Unofficial

translation: “permitting the Smelter to continue production, becoming a source for the generation of employment and

tax, in support of the mining activity of exploitation and concentration of antimony in the country”).

Page 144: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

139

the assets and the Bolivian economy as a whole. As it explains, “[e]l reordenamiento de las

empresas y demás entidades públicas tiene como objetivo incrementar la competitividad y

eficiencia de la economía nacional mediante: a) La transferencia al sector privado, a título

oneroso y en forma transparente, de actividades productivas que puedan ser realizadas por

éste de manera más eficiente […].”619

469. Claimant does not deny that it left the Antimony Smelter idle, and did not increase the

efficiency of its production. Instead, Claimant simply quibbles that it was never instructed to

put the Smelter into production,620 even though the privatization contract itself makes clear

that it had an obligation to do so.

470. Thus, the reversion of the Smelter was straightforwardly for the public purpose of ensuring

private property is put to productive use, in accordance with the Tin Smelter contract terms as

well as with the widely-accepted doctrine of property’s social function. Its reversion was an

exercise of police powers, not an expropriation.

471. Third, Bolivia implemented the Colquiri Mine reversion to protect public safety and order in

the midst of a dangerous dispute between the Colquiri Mine workers and the cooperativistas.

Thus, it was a clear exercise of Bolivia’s police powers and not an expropriation.

472. The reversion was a response to a public safety crisis that became critical when, on 30 May

2012, approximately one thousand cooperativistas violently occupied the Colquiri Mine,

seeking permanent control of the entire facility.621 As a result of this invasion of the mine, 15

people were wounded.622 This provoked a direct response from the company workers, who

issued an immediate ultimatum to the Government and the Ministry of Mines to solve the

619 COMIBOL, Legal Report GAD-627/2003 of 27 June 2003, R-249, pp. 2-3 (emphasis added) (Unofficial translation:

“[t]he reorganization of companies and other public entities aims to increase the competitiveness and efficiency of the

national economy by: a) The transfer to the private sector, for a price and in a transparent manner, of production

activities that may be carried out in a more efficient way by the latter”).

620 Statement of Claim, ¶ 6.

621 Cachi, ¶ 33. See, also, Mamani, ¶ 25 (“En la mañana del 30 de mayo de 2012, cuando nos encontrábamos trabajando

en el interior de la Mina, fuimos alertados de que un gran número de cooperativistas (aproximadamente unos 1200)

estaba ingresando por el sector El Triunfo (una antigua bocamina) y que otros se estaban dirigiendo al nivel de

extracción de la Mina (que es la bocamina que queda en el nivel 165, conocido como Sanjuanillo). Los cooperativistas

fueron muy violentos y nos atacaron con palos, piedras y dinamita, hiriendo a algunos de los compañeros que estaban

trabajando en ese turno al interior de la mina”) (Unofficial translation: “On the morning of 30 May 2012, while we

were working in the interior of the Mine, we were alerted that a large number of cooperativistas (approximately 1.200)

were entering through the El Triunfo sector (a former mine mouth) and that there were others who were going towards

the extraction level of the Mine (which is the mouth at level 165, known as Sanjuanillo). The cooperativistas were very

violent and attacked us with sticks, stones and dynamite, injuring some of our colleagues who were working during that

shift inside the Mine”).

622 La Patria, Cooperativistas toman mina en Colquiri y hieren a siete mineros, press article of 31 May 2012, R-21.

Page 145: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

140

problem lest they retake the mine by force.623 As an immediate counter-measure, the union

for the company workers imposed a blockade of the cooperativistas on the sole road between

Colquiri and the rest of Bolivia.624

473. The Government and COMIBOL took immediate action to resolve the crisis, to no avail.

Police squads were dispatched to Colquiri the very day that that the Mine was invaded625 and

the cooperativistas were blocked from selling any of their mineral production.626 The

Government, represented by the Minister of Mines and the Minister of Labour, in

collaboration with COMIBOL then sought to mediate a permanent solution to the conflict

between the company workers and the cooperativistas.627 They held repeated meetings with

the leaders of the mine workers union628 and the leaders of the cooperativistas in which many

623 Mamani, ¶¶ 26-27; Letters from the Sindicato Mixto de Trabajadores Mineros Colquiri to the President of Bolivia (Mr

Morales), the Ministry of Mining (Mr Virreira), and Comibol (Mr Córdova) of 30 May 2012, C-111.

624 Mamani, ¶ 29 (“Recuerdo que, aunque ninguno de los presentes creíamos conveniente un enfrentamiento violento con

los cooperativistas, sí acordamos la necesidad de ejercer presión (incluso por la fuerza) para asegurar nuestras fuentes

de trabajo. Por este motivo, y a partir de esta fecha, la FSTMB bloqueó las rutas que de Caracollo conducen a La Paz

y Colquiri (la única vía de acceso a la Mina) y exigió la presencia de representantes del Gobierno Nacional”)

(Unofficial translation: “I recall that, although no one present thought that a violent confrontation with the

cooperativistas was desirable, we did agree that it was necessary to put pressure (including by force) to ensure our

work sources. For this reason, and from this date, FSTMB blocked the routes that lead from Caracollo to La Paz and

Colquiri (the only way to access the Mine) and demanded the presence of representatives of the National Government”).

625 La Razón, El Gobierno envía más policías a Colquiri para evitar conflicto, press article of 1 June 2012, R-213.

626 Página Siete, Gobierno impide salida de mineral de Colquiri, press article of 1 June 2012, R-214 (“el Gobierno impide

la salidad de mineral de Colquiri para ser comercializado debido a la toma de la mina por el conflicto que existe entre

mineros y cooperativistas […]. También la energía eléctrica fue cortada en la zona para evitar que la maquinaria

funcione”) (Unofficial translation: “the Government is preventing Colquiri ore from being transferred to be sold due to

the mine being taken over as a result of the existing conflict between miners and cooperativistas, stated the executive

president of [COMIBOL] yesterday during an interview with radio ERBOL. The decision was made on Wednesday

night after cooperativistas took control over the mine compound. Electricity was also cut in the area to prevent the

machinery from functioning”).

627 Mamani, ¶ 28 (“La toma de un yacimiento tan grande como Colquiri tuvo una repercusión en todo el sector minero

nacional. Muy rápidamente, varios sindicatos y organizaciones productivas rechazaron la toma de la Mina Colquiri.

Por esta misma razón, el 31 de mayo de 2012, la FSTMB, entidad que agrupa a los distintos sindicatos mineros del

país, convocó a un ampliado nacional de emergencia en la localidad de Caracollo, a unos 39 kilómetros de la Mina,

para discutir las acciones violentas de los cooperativistas”) (Unofficial translation: “The takeover of a site as large as

Colquiri had repercussions over the entire national mining sector. Rapidly, several unions and productive organizations

rejected the takeover of the Colquiri Mine. For this same reason, on 31 May 2012, the [FSTMB], an entity formed by

the different mining unions of the country, convened an emergency national meeting in the town of Caracollo, some 39

kilometers from the Mine, to discuss the violent actions of the cooperativistas”).

628 Minutes of understanding with the Sindicato de Trabajadores Mineros de Colquiri and the Federación Sindical de

Trabajadores Mineros de Bolivia of 3 June 2012, C-115.

Page 146: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

141

different proposals were considered to end the dispute.629 Despite the extensive efforts to find

a solution, the cooperativistas refused to accept any of the proposed terms.630

474. It was at this moment, when all other solutions to the crisis had failed, that the Government

began to consider reversion as a way to prevent any further bloodshed. The cooperativistas

were unwilling to accept any solution in which Colquiri would remain at the mine and the

company workers wanted a solution that would allow them to return to work and keep their

jobs.631 Following discussions in La Paz regarding reversion as a possible solution,632 on 7

June 2012, the Government, the cooperativistas, and company workers participated in an open

629 La Patria, En suspenso acuerdo entre Gobierno y mineros sindicalizados y cooperativistas, press article of 4 June 2012,

C-117; La Razón, Minería hace 5 ofertas, pero aun no convence a los cooperativistas, press article of 5 June 2012, R-

215; Mamani, ¶¶ 32-33 (“Según lo que entendimos, el Gobierno estaba buscando el apoyo de la empresa Sinchi Wayra

para entregar a los cooperativistas nuevas áreas en la Mina. Sin embargo, la prensa publicó que las conversaciones

no habían avanzado porque los representantes de la cooperativa debían consultar la propuesta con sus bases. A pesar

de lo anterior, y con el fin lograr una salida negociada al conflicto, los miembros del STMC aceptamos que Sinchi

Wayra hiciera un nuevo ofrecimiento a los cooperativistas. El 5 de junio de 2012, la compañía minera Colquiri confirmó

al Estado su intención crear 200 nuevos puestos de trabajo en la compañía y ceder la veta San Antonio a la Cooperativa

26 de Febrero. Esta veta tiene un acceso a través de una rampa puesta en funcionamiento en 2007 por Sinchi Wayra y

puede ser explotada comercialmente en los niveles 240 y 325”) (Unofficial translation: “From what we understood, the

Government was seeking Sinchi Wayra’s support to allocate new areas of the Mine to the cooperativistas. However,

the press reported that discussions had not progressed because the representatives of the cooperative had to consult the

proposal with their bases. This notwithstanding, and with the objective of achieving a negotiated end to the conflict, we

the members of STMC agreed that Sinchi Wayra make a new offer to the cooperativistas. On 5 June 2012, Compañía

Minera Colquiri confirmed to the State its intention to create 200 new work positions in the company and to assign the

San Antonio vein to the Cooperativa 26 de Febrero. This vein includes an access through a ramp commissioned in 2007

by Sinchi Wayra and can be commercially exploited at levels 240 and 325”); Letter from Colquiri (Mr Capriles) to the

Minister of Mining (Mr Virreira) and Comibol (Mr Córdova) of 5 June 2012, C-120; Letter from the Ministry of Mines

to the Cooperativa 26 de Febrero of 6 June 2012, R-216.

630 La Patria, Colquiri: Mineros suspenden labores y cooperativistas no aceptan veta, press article of 5 June 2012, C-118

(“Entretanto, los trabajadores cooperativistas, que se reunieron en el distrito minero de Colquiri, determinaron no

aceptar la oferta de acceder a la veta ‘San Antonio’ en su totalidad y continúan con su exigencia de ‘sacar’ a la empresa

de aquella localidad minera”) (Unofficial translation: “Meanwhile, the cooperativistas who held meetings in the mining

district of Colquiri, decided not to accept the offer of the ‘San Antonio’ vein in its entirety and continue to require the

company’s ‘exit’ from the mining town”); Cachi, ¶¶ 35-36; Mamani, ¶¶ 33-34.

631 Mamani, ¶ 36; La Patria, Colquiri: Mineros suspenden labores y cooperativistas no aceptan veta, press article of 5 June

2012, C-118.

632 La Patria, Gobierno plantea nacionalizar Colquiri para poner fin a conflicto minero, press article of 6 June 2012, R-

221 (“El Gobierno planteó ayer la nacionalización de la mina Colquiri, operada por la empresa privada Sinchi Wayra,

para poner fin al conflicto minero que se suscitó desde el pasado miércoles 30 de mayo cuando los trabajadores de la

cooperativa minera ‘26 de Febrero’ tomaron el yacimiento”) (Unofficial translation: “The Government proposed

yesterday the nationalization of the Colquiri mine, operated by the private company Sinchi Wayra, in order to put an

end to the mining conflict commenced last Wednesday 30 May when the workers of the cooperativa minera ‘26 de

Febrero’ took control over the deposit”); La Razón, Virreira y cooperativa discuten ampliación de áreas de trabajo,

press article of 8 June 2012, R-26 (“El miércoles [i.e., 6 June 2012], Virreira reiteró la propuesta a la cooperativa de

‘rescindir el contrato de arrendamiento’ con la compañía privada para que la administración de la mina Colquiri pase

a manos de la Corporación Minera de Bolivia (Comibol), previo “acuerdo común” entre los cooperativistas y los

trabajadores asalariados. Álvaro ratificó que los cooperativistas ‘repudian’ la medida porque ‘en nuestro sector

trabajamos sin restricción de edad y sólo algunos serían incorporados a los asalariados’”) (Unofficial translation: “On

Wednesday [i.e., 6 June 2012], Virreira reiterated the proposal to the cooperative to ‘terminate the lease agreement’

with the private company so that the administration of the Colquiri mine be reverted to the Bolivian Mining Corporation

(Comibol), following a ‘common agreement’ between cooperativistas and employees. Álvaro backed the idea that the

cooperativistas ‘repudiate’ the measure because ‘in our sector we work without age restrictions and only some would

be incorporated as employees’”).

Page 147: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

142

council in the village of Colquiri to resolve the violent conflict.633 Against the Government’s

promise that COMIBOL would hire the cooperativistas,634 the entire community agreed that

reversion of the mine lease would be an acceptable solution.635

475. However, Glencore International then intervened to disrupt the agreement by granting one

sector of the cooperativistas control of the Rosario vein of the mine.636 It did so despite

opposition from its own workers, and thus managed to reignite the violence surrounding the

Mine.637 One thousand mine workers imposed blockades on major roads638 and protests broke

633 Mamani, ¶ 39 (“Entretanto, los miembros del STMC y la FSMB nos desplazamos nuevamente hasta la población de

Colquiri, donde iniciamos una reunión en Cabildo con una masiva participación de los pobladores. Nuestra reunión se

instaló en la Plaza 6 de Agosto, a unos 2km de la bocamina Sanjuanillo, donde las bases de la Cooperativa 26 de

Febrero se encontraban reunidas”) (Unofficial translation: “Meanwhile, we the members of STMC and FSTMB travelled

again to the village of Colquiri, where we initiated a Council meeting attended by a great number of the village

population and central institutions of the village (neighbourhood council, authorities of indigineous communities,

guilds, transporters, etc.) Our meeting was set up in the Plaza 6 de Agosto, some 2 km from the Sanjuanillo mine mouth,

where the bases of the Cooperativa 26 de Febrero were assembled, together with some leaders who wanted to subvert

the nationalisation proposal”); Cachi, ¶ 38. See, also, Video Bolivia, Enfrentamiento en Mina Colquiri. Hay Heridos,

June 2012 (Video), R-222 (“Al momento no sindican que los cooperativistas estarían divididos, ya que algunos de ellos

habrían decidido ser parte de lo que es los mineros asalariados”) (Unofficial translation: “Presently they indicate that

the cooperativistas would be divided, since some of them would have decided to join the mining employees”).

634 Proposal from the Government to the Cabildo of Colquiri, R-27 (“Esta reversión supone varios compromisos del Estado

(COMIBOL) para cumplir con los trabajadores actuales y nuevos en Colquiri. Estos compromisos son los siguientes:

mantener los puestos de trabajo de todos y cada uno de los trabajadores, mantener sus niveles salariales, mantener y

respetar sus conquistas sociales y laborales, incorporar a los ex cooperativistas a la planilla de la COMIBOL, dar a

COMIBOL el capital operativo y dar a COMIBOL el capital de inversión para el desarrollo de la mina”) (Unofficial

translation: “This reversion implies several commitments by the State (COMIBOL) towards current and new employees

in Colquiri. These commitments are the following: maintain the work positions of each and every one of the employees,

maintain their salaries, maintain and respect their social and employment achievements, incorporate the former

cooperativistas into the workforce of COMIBOL, provide COMIBOL with operational capital and provide COMIBOL

with investment capital to develop the mine”).

635 La Patria, Mineros asalariados y cooperativistas aceptan rescisión de contrato en Colquiri, press article of 8 June 2012,

R-223 (“mineros asalariados y cooperativistas determinaron […] aceptar la rescisión del contrato de arrendamiento

de Colquiri […] para evitar enfrentamientos por la explotación de minerales y demanda de fuentes de empleo […].Ese

pronunciamiento surgió un día después que el Gobierno pidió a ambos sectores un ‘acuerdo social’ para terminar con

el conflicto que desataron los cooperativistas, el 30 de mayo reciente, cuando tomaron esa mina en demanda de nuevas

áreas de explotación”) (Unofficial translation: “mining employees and cooperativistas determined […] to accept the

termination of the Colquiri lease agreement […] to prevent confrontations due to ore exploitation and the demand for

work sources […]. This statement intervened one day after the Government requested from both sectors a ‘social

agreement’ to end the conflict triggered by the cooperativistas on 30 May when they took control over that mine,

requesting additional exploitation areas”).

636 Agreement between Colquiri SA, Fedecomin, Fencomin, Central Local de Cooperativas Mineras de Colquiri,

Cooperativa Minera Collpa Cota, Cooperativa Minera Socavón Inca, and Cooperativa 26 de Febrero, C-35.

637 Mamani, ¶¶ 41-42. See, also, Cachi, ¶¶ 43-44 (“En vista de lo anterior, luego de que se conoció la firma del acuerdo

para ceder la veta Rosario, los trabajadores de la empresa anunciaron que se tomarían la Mina por la fuerza. Los

cooperativistas que estábamos en Colquiri reiteramos nuestro respaldo. Esto desató un conflicto violento entre, por un

lado, los trabajadores de la Mina y la facción de los cooperativistas que exigíamos la nacionalización y, por el otro, la

otra facción de cooperativistas que querían el control de la veta Rosario”) (Unofficial translation: “In light of the

foregoing, after the conclusion of the agreement to assign the Rosario vein became known, the company’s workers

announced that they would take control over the Mine by force. The cooperativistas who were in Colquiri reiterated

our support. This triggered a violent conflict between, on the one hand, the Mine workers and the cooperativistas

faction requesting the nationalization, and on the other hand, the cooperativistas faction wanting to take control over

the Rosario vein”).

638 Mineros de Colquiri bloquean conani exigiendo la emisión del D.S. de Nacionalización, Video (2012), R-224.

Page 148: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

143

out that quickly resulted in violent confrontations.639 Thus, it became clear that any solution

other than reversion would not resolve the crisis.

476. Following this renewed violence, the Government implemented the reversion of the Colquiri

Mine Lease as the only viable solution to the conflict. It called a meeting of the

cooperativistas and mine workers in La Paz. At this meeting on 19 June 2012, the parties

reached a formal agreement to resolve the conflict wherein that the state would revert the

Colquiri mine but leave the cooperativistas with mining rights.640 The agreement emphasized

that “[l]a viabilización de estos acuerdos exige a ambas partes la deposición de actitudes de

confrontación y la inmediata pacificación del Distrito Minero de Colquiri.”641 The very next

day, the Government implemented the agreement through the Mine Lease Reversion Decree.

477. Thus, the reversion was a “reasonable bona fide exercise of police powers in such matters as

the maintenance of public order, health or morality.” 642 Bolivia had no reasonable alternative

to the reversion if it was to restore public order and safety in the face of the violent

confrontation between the workers and the cooperativistas. The reversion was not

expropriatory.

6.1.2 If The Reversions Were Expropriations (Quod Non), They Were Lawful

478. Claimant asserts that, “[i]n order for Bolivia to carry out a lawful expropriation, it must

comply with the requirements set out in Article 5 of the Treaty.”643 Claimant then goes on to

639 La Prensa, Colquiri se convierte en un campo de batalla, press article of 15 June 2012, C-142 (“Mineros asalariados y

afiliados a la cooperativa 26 de Febrero se enfrentaron ayer con dinamita y palos por el control de la mina Colquiri,

mientras el Gobierno volvió a convocarlos para dialogar en procura de encontrar una solución al conflicto que ya lleva

dos semanas. La llegada de la noche y la explosión de cachorros de dinamita generaron zozobra entre los pobladores

de Colquiri, quienes pedían entre sollozos la llegada de efectivos policiales y la pacificación de la zona, que está

ubicada en la provincia Inquisivi, del departamento de La Paz”) (Unofficial translation: “Mining employees and

affiliates to the cooperativa 26 de Febrero clashed yesterday, [using] dynamite and sticks, over control of the Colquiri

mine, while the Government again summoned them to discuss with a viewt to find a solution to the conflict that has

already lasted two weeks. Nightfall and the explosion of dynamite sticks generated anxiety amongst Colquiri’s

population, who requested, sobbing, the arrival of police forces and the appeasement of the area, located in the province

of Inquisivi, in the department of La Paz”).

640 Agreement between the Government of Bolivia, COB, Fencomin, FEDECOMIN-LP, FSTMB, Central de Cooperativas

de Colquiri, and Sindicato Mixto de Trabajadores Mineros de Colquiri of 19 June 2012, R-18.

641 Agreement between the Government of Bolivia, COB, Fencomin, FEDECOMIN-LP, FSTMB, Central de Cooperativas

de Colquiri, and Sindicato Mixto de Trabajadores Mineros de Colquiri of 19 June 2012, R-18 (Unofficial translation:

“[t]he viability of these agreements requires that both parties abandon all conflictual attitude and the immediate

appeasement of the Mining District of Colquiri”).

642 Philip Morris Brand Sàrl, Philip Morris Products S.A. and Abal Hermanos S.A. v. Oriental Republic of Uruguay, ICSID

Case No. ARB/10/7, Award, RLA-43, ¶ 295.

643 Statement of Claim, ¶ 149.

Page 149: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

144

argue that the supposed expropriations were unlawful because they violated the compensation

provision of the Treaty and were undertaken without affording prior due process.644

479. Both arguments ignore the meaning of Article 5 of the Treaty as well as applicable

international law. An expropriation does not breach Article 5 of the Treaty, and still less is

unlawful, simply because no compensation is paid while negotiations or arbitrations are

pending (Section 6.1.2.1). And Article 5 is clear that no particular procedure is necessary

prior to an expropriation; it explicitly establishes that only a mechanism for posterior review

is required (Section 6.1.2.2). Thus, even if the reversions were (quod non) expropriations,

they were lawful expropriations in compliance with the terms of the Treaty.

6.1.2.1 Bolivia Would Have Satisfied Any Applicable Compensation Requirement By Participating In

Lengthy Negotiations And In This Arbitration

480. It is Claimant’s position that the reversions were unlawful because “Bolivia did not pay just

and effective compensation, defined as the fair market value of the investments, promptly and

without delay” in accordance with Article 5 of the Treaty.645

481. This position is erroneous. Far from constituting a breach, the Treaty’s compensation

provision in Article 5 assumes that a dispute regarding an alleged expropriation or

compensation due might have to be submitted to the courts or to arbitration. Thus, the

provision is breached only for failure to pay upon conclusion of negotiations and this

arbitration. Moreover, the mere failure to pay compensation, whether or not in breach of the

Treaty, does not make an expropriation unlawful within the terms of international law.

International law defines an unlawful expropriation as one that cannot be rectified (except

through restitution of the property), and specifically excludes expropriations that lack only the

payment of compensation.

482. First, because Claimant sought to obtain compensation through arbitration, Bolivia fully

satisfied any compensation obligation it might have had (quod non) by participating in this

process.

483. In their attempt at rebuttal, Claimant places primary reliance on two century-old arbitral

awards: Goldenberg and Norwegian Shipowners.646 Neither of these dated awards address

the interpretation of a treaty expropriation provision, let alone one contained in an investment

644 Statement of Claim, ¶ § V(A)(3)(a)(b).

645 Statement of Claim, ¶ 150.

646 Statement of Claim, ¶¶ 156-157.

Page 150: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

145

treaty. Nor is Claimant able to muster any evidence that any modern investment tribunal

follow these awards as authorities.

484. To the contrary, modern investment law finds no treaty breach when a state withholds

compensation while the amount of compensation, or even the duty to compensate, remains in

controversy.

485. In this regard, the Treaty provides for arbitration to determine compensation precisely when

there is controversy as to the legal character of a state action or the amount of compensation

due, both of which are present in this case. Article 5 states that “[t]he national or company

affected shall have the right to establish promptly by due process of law in the territory of the

Contracting Party making the expropriation the legality of the expropriation and the amount

of the compensation in accordance with the principle set out in this paragraph.”647

486. This Treaty provision makes clear that adjudication may be necessary in order to fix the

amount of compensation due following an expropriation. One acceptable form of adjudication

to determine the compensation – and the one Claimant itself chose – is international

arbitration. The World Bank Guidelines on the Treatment of Foreign Direct Investment

confirm as much: “Determination of the ‘fair market value’ will be acceptable if conducted

according to a method agreed by the State and the foreign investor (hereinafter referred to as

the parties) or by a tribunal or another body designated by the parties.”648 Bolivia cannot be

expected to pay compensation before the international arbitration process – the acceptable

method selected by Claimant – has finished.

487. The Tidewater tribunal reached precisely such a conclusion. As it held, because arbitration is

how the appropriate compensation is fixed, the mere failure to pay compensation prior to

arbitration cannot breach the compensation provision of an investment treaty:

It follows that such a tribunal must have an opportunity to make its determination as

to compensation. Where such a tribunal has done so (and assuming that the other

conditions are met) the expropriation will not be illegal. […] An expropriation only

wanting fair compensation has to be considered as a provisionally lawful

expropriation, precisely because the tribunal dealing with the case will determine and

award such compensation.649

647 Treaty, C-1, Art. 5.

648 World Bank. 1992. Guidelines on the Treatment of Foreign Direct Investment. Foreign Investment Law Journal, Chapter

IV Expropriation and unilateral alterations or termination of contracts, CLEX-18, IV(4).

649 Tidewater Inc., Tidewater Investment SRL, Tidewater Caribe, C.A., et el. v. The Bolivarian Republic of Venezuela,

ICSID Case No. ARB/10/5, Award of 13 March 2015, RLA-60, ¶ 140-141.

Page 151: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

146

488. This same holding was recently reconfirmed by the Ampal-American tribunal. It again

reasoned that it is the role of an investment tribunal to calculate the compensation, so the

failure to pay compensation prior to arbitration cannot be unlawful. As it explained:

By these terms, Article III(1) creates an international obligation on the part of the State

to pay compensation for the expropriation of an investor’s property. This Tribunal is

empowered to enforce that obligation, calculating the amount of compensation due

according to the standard prescribed in the Treaty, in the event that the State fails to

pay such compensation. This does not require the Tribunal to find that the

expropriation in question was unlawful, as may be the case in the event that the taking

was not done for a public purpose or was discriminatory.650

489. Although Claimant cites to Siag v. Egypt to support the opposite conclusion,651 that tribunal

mentioned compensation as nothing more than an afterthought without legal consequence, as

it found the expropriation problematic on more serious grounds.652 The Siag tribunal’s

analysis of the issue was limited to a single paragraph. 653 And, importantly, the tribunal did

not hold that its obiter dictum about the lack of compensation had any legal effect whatsoever.

It is on this thin reed that Claimant elected to build its compensation argument.

490. Thus, it cannot be a breach of Article 5 of the Treaty for a state to withhold compensation on

the grounds that the amount or very duty to pay compensation is contested. This is almost

always the case when an expropriation claim is brought before an investment tribunal. A state

cannot have a treaty obligation to pay contested compensation when it is unable to bring an

arbitration against the investor to recover overpayment. And it cannot be right that every

tribunal to find expropriation must automatically find a breach of the compensation provision

as well.

491. In the present case, Claimant elected to bypass the Bolivian courts and proceed directly to

international recourse. The Bolivian courts never had the opportunity to decide whether the

reversions were expropriations, whether they were internationally lawful, and what amount

of compensation might be due. Claimant cannot allege that Bolivia acted in breach of the

Treaty by failure to pay compensation prior to arbitration when basic questions underlying

that compensation were in dispute.

650 Ampal-American Israel Corporation and others v. Arab Republic of Egypt, ICSID Case No. ARB/12/11, Decision on

Liability and Heads of Loss of 21 February 2017, RLA-61, ¶ 186.

651 Statement of Claim, ¶ 156.

652 Waguih Elie George Siag and Clorinda Vecchi v Arab Republic of Egypt (ICSID Case No ARB/05/15) Award of 1 June

2009, CLA-89, ¶¶ 434-435.

653 Waguih Elie George Siag and Clorinda Vecchi v Arab Republic of Egypt (ICSID Case No ARB/05/15) Award of 1 June

2009, CLA-89, ¶ 434.

Page 152: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

147

492. In fact, Claimant appears to agree but argues that, “[w]hen the State has not offered acceptable

compensation prior to or at the time of the taking, the State is obligated to at least ‘engage in

good faith negotiations to fix the compensation in terms of the standard’ established by the

governing treaty.”654 Although this is not necessary to satisfy a treaty compensation

provision, Bolivia did negotiate in good faith over the course of ten years. It is not credible

in the least that Claimant thought Bolivia was negotiating in bad faith or that these

negotiations were futile, as it continued to negotiate for almost ten years following the Tin

Smelter reversion, almost seven years following the Antinomy Smelter Reversion, and almost

five years following the Colquiri Mine Lease reversion.

493. It is still less reasonable for Claimant to now complain about a purported lack of compensation

when it likely received payment from insurance. It is our understanding, confirmed by

Claimant’s 2011 prospectus,655 that Claimant received payment from political risk insurance

covering the Tin Smelter. This payment would have been made by a syndicate led by Lloyd’s.

We suspect that Claimant likely received similar payments from political risk insurance

covering the Antimony Smelter and Colquiri Mine Lease.

494. In sum, international arbitration itself satisfies the treaty compensation provision by fixing the

amount, if any, of compensation due. Payment will be timely so long as it is made promptly

upon the termination of these proceedings and any recourse that may be taken against the

outcome of these proceedings.

495. Second, in any event, Bolivia did not have to make any payment at all in order for the

reversions to be lawful, even assuming (quod non) that they were expropriations. Claimant

simply ignores the meaning of unlawful expropriation in international law, and instead jumps

right to labeling the reversions as unlawful. But it is plain that the reversions could not have

been unlawful for lack of compensation.

496. Claimant’s authority, Chorzow Factory,656 sets out the classic (albeit outdated) distinction

between a lawful and unlawful expropriation, which Claimant here invokes. That judgment

contrasted a provisionally lawful expropriation, lacking only compensation, with an

inherently unlawful expropriation, entirely prohibited by international law. The failure to pay

654 Statement of Claim, ¶ 158.

655 Prospectus of Glencore International plc of 3 May 2011, R-193, p. 13 (“For example, in 2007, the Bolivian government

nationalised a smelter owned by a subsidiary of Glencore. However, in that instance, no material losses were sustained

and Glencore continues to do business in Bolivia.”).

656 Statement of Claim, ¶ 231.

Page 153: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

148

compensation did not make an expropriation inherently unlawful. As the Permanent Court of

International Justice (“PCIJ”) stated in that judgment:

The action of Poland which the Court has judged to be contrary to the Geneva

Convention is not an expropriation to render which lawful only the payment of fair

compensation would have been wanting; it is a seizure of property, rights and interests

which could not be expropriated even against compensation, save under the

exceptional conditions fixed by Article 7 of the said Convention.657

497. In the PCIJ’s distinction, the non-payment of compensation does not render the expropriation

inherently unlawful because legality relates to whether it is legally permissible for a state to

expropriate in the first place; providing compensation is a secondary obligation. As Mohebi

explains, “the non-payment of compensation does not, as such, make a taking ipso facto

wrongful, rather it is a violation by the expropriating state of an independent duty which

applies evenly to both unlawful and lawful taking […].”658 Commentators including

Crawford, Brownlie, and Sheppard are in agreement with Mohebi that the failure to pay

compensation cannot by itself make an expropriation inherently unlawful.659

498. In fact, no investment tribunal has ever drawn any legal consequence from an expropriation

found unlawful only for the lack of compensation. This is specifically true for the lone two

cases that Claimant has cited,660 which simply ordered compensation in accordance with the

treaty terms.661 Instead, the overwhelming majority of tribunals confronting failures to pay

compensation nevertheless declined to hold the expropriation to be unlawful. These tribunals

include Venezuela Holdings v. Venezuela, Santa Elena v. Costa Rica, Tidewater v.

657 Case Concerning the Factory at Chorzów (Germany/Poland) (Merits) [1928] PCIJ Series A, No 17, CLA-2, p.46.

658 M. Mohebi,The International Law Character of the Iran-United States Claims Tribunal, 1999, RLA-62, p. 289.

659 J. Crawford, Brownlie'’s Principles of Public International Law, 8th ed., 2012, RLA-63, p. 624; A. Sheppard, “The

distinction between lawful and unlawful expropriation” in Investment Arbitration and the Energy Charter Treaty,

JurisNet LLC, 2006, RLA-64, p. 171.

660 Statement of Claim, ¶¶ 154-155.

661 Guaracachi America, Inc and Rurelec Plc v Plurinational State of Bolivia (UNCITRAL) Award of 31 January 2014,

CLA-120, ¶ 441, 444 (ordering payment in accordance with the terms of the treaty compensation provision); Rumeli

Telekom AS and Telsim Mobil Telekomikasyon Hizmetleri AS v Republic of Kazakhstan (ICSID Case No ARB/05/16)

Award of 29 July 2008, CLA-79, ¶ 706, 794.

Page 154: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

149

Venezuela,662 Metalclad v. Mexico, Tecmed v. Mexico, Abengoa v. Mexico, Sistem v. Kyrgyz

Republic, Wena v. Egypt, and Middle East Cement v. Egypt.663

499. In short, a failure to pay compensation does not make an expropriation unlawful within the

terms of international law. Nor does the failure to pay compensation breach the compensation

provision of the Treaty. Thus, even if the reversions were expropriations (quod non), they

were not unlawful for lack of compensation.

6.1.2.2 Although Due Process Is Not A Requirement For Expropriation, Bolivia Observed Due

Process Of Law By Making Available Posterior Remedies

500. Claimant argues that “Bolivia’s conduct was also devoid of any respect for due process, in

breach of another key requirement for lawfulness under international law.”664 This is doubly

incorrect. Due process is not a requirement for lawful expropriation under the Treaty. Nor

did Bolivia fail to accord due process to Claimant.

501. First, it is simply untrue that due process in prior proceedings is a condition for expropriation

under the Treaty. Instead, the Treaty specifically provides, as a separate requirement, that

individuals must be able to bring a posterior challenge to the legality of expropriations with

due process.

502. The plain text of the Treaty shows that due process is irrelevant to the legality of expropriation.

Article 5 of the Treaty, the expropriation provision, makes no mention of due process as a

condition for permissible expropriation. Instead, the conditions for expropriation are (i) that

it is for “a public purpose and for a social benefit related to the internal needs of that Party,”

662 Venezuela Holdings, B.V., Mobil Cerro Negro Holding, Ltd., Mobil Venezolana de Petróleos Holdings, Inc., Mobil

Cerro Negro, Ltd., and Mobil Venezolana de Petróleos, Inc. v. Bolivarian Republic of Venezuela, ICSID Case No.

ARB/07/27, Award of 9 October 2014, RLA-65, ¶¶ 306-307; Compañía del Desarrollo de Santa Elena SA v Republic

of Costa Rica (ICSID Case No ARB/96/1) Final Award of 17 February 2000, CLA-25, ¶ 101; Southern Pacific

Properties (Middle East) Limited v Arab Republic of Egypt (ICSID Case No ARB/84/3) Award on the Merits of 20 May

1992, CLA-18, ¶ 158 and 183; Tidewater Inc., Tidewater Investment SRL, Tidewater Caribe, C.A., et el. v. The

Bolivarian Republic of Venezuela, ICSID Case No. ARB/10/5, Award of 13 March 2015, RLA-60, ¶ 146.

663 In these last cases, the Tribunals did not deal with the issue directly, but still did not declare the expropriation unlawful

and applied the treaty standard of compensation (i.e., the standard for lawful expropriations): Metalclad Corporation v

United Mexican States (ICSID Case No ARB(AF)/97/1) Award of 30 August 2000, CLA-27, ¶ 118; Técnicas

Medioambientales Tecmed SA v United Mexican States (ICSID Case No ARB(AF)/00/2) Award of 29 May 2003, CLA-

43, ¶ 187; Abengoa, S.A. and COFIDES, S.A. v. United Mexican States, ICSID Case No. ARB(AF)/09/2, Award of 18

April 2013, RLA-66, ¶ 681; Sistem Mühendislik Inşaat Sanayi ve Ticaret A. v. Kyrgyz Republic, ICSID Case No.

ARB(AF)/06/1, Award of 9 September 2009, RLA-67, ¶¶ 119 and 156; Wena Hotels Ltd. v. Arab Republic of Egypt,

ICSID Case No. ARB/98/4, Award of 8 December 2000, RLA-68, ¶¶ 101, 118 and 125;Middle East Cement Shipping

and Handling Co SA v Arab Republic of Egypt (ICSID Case No ARB/99/6) Award of 12 April 2002, CLA-34, ¶¶ 143-

151.

664 Statement of Claim, ¶ 169.

Page 155: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

150

and (ii) that it is “against just and effective compensation.”665 Due process is unconnected to

the permissibility of expropriation.

503. Although the Treaty does not make due process a condition for expropriation, many other

investment treaties explicitly do so. In fact, almost every award that Claimant invokes on this

issue considers investment treaties that do make due process a condition for expropriation.666

(The lone exception is a case that Claimant cites even though it did not find an expropriation

unlawful on the grounds of a due process violation.667) Despite the clear option of making

due process a condition for expropriation, Bolivia and the United Kingdom did not elect do

so. This Tribunal should not read into the Treaty a condition for expropriation that the States

Parties did not adopt.

504. Instead, the Treaty establishes a different role for due process. Following an expropriation,

the affected individual must have a domestic avenue to challenge the legality of the

expropriation and the appropriate amount of compensation. However, this obligation is

unrelated to the legality of the expropriation itself, as it contemplates a process to, inter alia,

determine the legality of the expropriation. As the Treaty provides in Article 5, “[t]he

national or company affected shall have the right to establish promptly by due process of law

in the territory of the Contracting Party making the expropriation the legality of the

expropriation and the amount of the compensation in accordance with the principle set out in

this paragraph.”668

505. Simply put, the Treaty establishes that individuals must have a right to due process following

an expropriation, in order to challenge the legality of the expropriation. It does not make due

process a condition of that legality.

506. Second, Bolivia accorded full due process because Claimant had ample avenues to bring a

posterior challenge to the reversion before the Bolivian courts and in this arbitration. As

665 Treaty, C-1, Article 5(1).

666 AIG Capital Partners, Inc and CJSC Tema Real Estate Company v Republic of Kazakhstan (ICSID Case No ARB/01/6)

Award of 7 October 2003, CLA-45, p. 8 (quoting Article III(1) of the Kazakhstan-U.S. BIT); Mohammad Ammar Al-

Bahloul v Republic of Tajikistan (SCC Case No V (064/2008)) Partial Award on Jurisdiction and Liability of 2

September 2009, CLA-91, p. 33 (quoting Article 13 of the ECT); ADC Affiliate Limited and ADC & ADMC

Management Limited v Republic of Hungary (ICSID Case No ARB/03/16) Award of the Tribunal of 2 October 2006,

CLA-64, ¶ 368 (quoting Article 4 of the Cyprus-Hungary BIT); Crystallex International Corporation v Bolivarian

Republic of Venezuela (ICSID Case No ARB(AF)/11/2) Award of 4 April 2016, CLA-130, ¶ 711 (quoting Article VII(1)

of the Canada-Venezuela BIT); Ioannis Kardassopoulos and Ron Fuchs v Republic of Georgia (ICSID Case Nos

ARB/05/18 and ARB/07/15) Award of 3 March 2010, CLA-96, ¶ 386 (quoting Article 13 of the ECT).

667 Quiborax SA and Non Metallic Minerals SA v Plurinational State of Bolivia (ICSID Case No ARB/06/2) Award of 16

September 2015, CLA-127, ¶¶ 240-254 and ¶ 171-194 (showing that neither claimant nor respondent debated the issue

of illegality on the grounds of due process).

668 Treaty, C-1, Article 5(1) (emphasis added).

Page 156: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

151

explained, the Treaty envisions only that there must be a posterior remedy for expropriations

(which the reversions were not) to challenge the legality and the amount of expropriations.

Claimant chose for its own reasons not to pursue the recourse made available to it.

507. As an initial matter, any breach of due process would require “a manifest disrespect of due

process that [offends] a sense of judicial propriety.”669 It is not enough that a marginal breach

of due process occurs; it must be manifest and it must offend judicial propriety. Any number

of tribunals have confirmed this high standard for breach of due process, including Arif v.

Moldova, AES v. Hungary, and Tokios Tokelés v. Ukraine.670 The standard for a breach of

administrative due process, as Claimant also seems to allege, is even more difficult to satisfy.

The “processes of administrative decision-making cannot be judged by the standards expected

of judicial proceedings” and do not even require “a formal adversarial procedure […].”671

508. Claimant could have pursued the avenues provided for by Administrative Procedure Law and

the 1967 and 2009 Constitutions in order to challenge the legality of the reversion decrees.

509. One, the Administrative Procedure Law provides that any interested party may file a “recurso

de revocatoria” before the authority that enacted the respective administrative act.672 If the

authorities confirm the administrative act, the interested party then may challenge its legality

before the Supreme Court of Justice through an administrative contentious proceeding.673

Even the expropriation law, on which Claimant relies, establishes the possibility of

challenging an alleged expropriation before the judicial branch.674

510. Two, the 1967 Constitution, in force at the time of the Tin Smelter reversion decree,

established the possibility of filing a “recurso de amparo” against illegal acts or omissions of

public officials or private persons that “restrinjan, supriman o amenacen restringir o suprimir

los derechos y garantías de las personas reconocidos por esta Constitución y las leyes.”675

669 Mr Franck Charles Arif v. Republic of Moldova, ICSID Case No. ARB/11/23, Award of 8 April 2013, RLA-69, ¶ 447.

670 Mr Franck Charles Arif v. Republic of Moldova, ICSID Case No. ARB/11/23, Award of 8 April 2013, RLA-69, ¶ 447;

AES Summit Generation Limited and AES-Tisza Erömü Kft v Republic of Hungary (ICSID Case No ARB/07/22) Award

of 23 September 2010, CLA-100, ¶ 9.3.40; Tokios Tokelés v. Ukraine, ICSID Case No. ARB/02/18, Award of 26 July

2007, RLA-70, ¶ 133; Jan de Nul NV and Dredging International NV v Arab Republic of Egypt (ICSID Case No

ARB/04/13) Award of 6 November 2008, CLA-83, ¶ 187.

671 C. McLachlan, L. Shore, M. Weiniger, International Investment Arbitration: Substantive Principles, 2nd ed., 2017,

RLA-71, ¶ 7.193.

672 Law No. 2.341 of 23 April 2002, R-250, Art. 64.

673 Law No. 2.341 of 23 April 2002, R-250, Art. 70.

674 Law of Expropriation due to Public Utility of 30 December 1884, C-49, Arts. 38, 39.

675 Constitution of Bolivia of 1967, R-3, Art. 19 (Unofficial translation: “limit, eliminate or threat to limit or eliminate the

rights and guaranties of individuals that are recognized by this Constitution and the law”).

Page 157: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

152

511. Three, the 2009 Constitution further expanded the constitutional actions that Claimant could

have pursued against the reversion decrees of the Colquiri Mine Lease and the Antimony

Smelter (indeed, even against the Tin Smelter decree). It contemplates the possibility of filing

not only an “acción de amparo”676 (similar to the “recurso de amparo” provided for in the

1967 Constitution), but also an “acción de inconstitucionalidad”677 and an “acción de

cumplimiento” before the courts.678

512. Despite the availability of these avenues to challenge the reversion decrees, Claimant itself

decided not pursue any of them. Instead, it elects to complain about the lack of due process

when it failed to pursue the available process.

513. Third, Claimant tacks on a grab bag of supposed grievances about the manner of the

reversions, repeated from elsewhere in its pleadings, as if this would strengthen its due process

argument. Bolivia does not here repeat its prior explanations of why each of the reversions

was justified and why it subsequently negotiated in good faith.679 Instead, it only addresses

Claimant’s remaining assertions.

514. One, Claimant alleges that it did not receive any advanced notice whatsoever of the Tin

Smelter and Antimony Smelter reversions.680 This allegation is flatly contradicted by

Claimant’s own factual assertions. Claimant itself admits that President Morales announced

the Tin Smelter reversion on 22 January 2007,681 and the reversion itself did not occur until 7

February 2007. It also admits that President Morales announced the Antimony Smelter

676 Constitution of Bolivia of 7 February 2009, C-95, Art. 128 (“La Acción de Amparo Constitucional tendrá lugar contra

actos u omisiones ilegales o indebidos de los servidores públicos, o de persona individual o colectiva, que restrinjan,

supriman o amenacen restringir o suprimir los derechos reconocidos por la Constitución y la ley”) (Unofficial

translation: “The ‘Acción de Amparo Constitucional’ may be brought against illegal or undue acts or omissions of public

servants, or of any individual or collective person, which limit, eliminate, threat to limit or eliminate rights recognized

by this Constitution and the law”).

677 Constitution of Bolivia of 7 February 2009, C-95, Art. 132 (“Toda persona individual o colectiva afectada por una

norma jurídica contraria a la Constitución tendrá derecho a presentar la Acción de Inconstitucionalidad, de acuerdo

con los procedimientos establecidos por la ley”) (Unofficial translation: “Every individual or collective person who is

affected by a legal provision which is contrary to the Constitution is entitled to bring an ‘Acción de

Inconstitucionalidad’, pursuant the procedures established by the law”).

678 Constitution of Bolivia of 7 February 2009, C-95, Art. 134 (“La Acción de Cumplimiento procederá en caso de

incumplimiento de disposiciones constitucionales o de la ley por parte de servidores públicos, con el objeto de

garantizar la ejecución de la norma omitida”) (Unofficial translation: “The ‘Acción de Cumplimiento’ may be brought

in case of violation of constitutional or legal provisions by public servants, with the objective of guaranteeing the

enforcement of the omitted rule”).

679 Sections 2.6 and 2.7 above.

680 Statement of Claim, ¶¶ 173-174.

681 Statement of Claim, ¶ 65,

Page 158: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

153

reversion on 1 May 2007 but the reversion did not occur until 2 May 2007.682 Thus, it is

simply untrue that Claimant received no advanced notice at all of the reversions.

515. Two, Claimant further characterizes the presence of the police and the army during the

reversions as a violation of due process.683 Claimant’s argument lies ill in mouth. It is

precisely Claimant that has elsewhere complained about Bolivia’s supposed failure to provide

sufficient police protection.684 The police and military were present at the reversions precisely

to guarantee the peaceful transfer of the Asset. Sinchi Wayra resisted the implementation of

the reversion decree: the plant’s workers were standing outside the buildings when the

Bolivian authorities entered the site and conflict could have erupted at any moment.685 The

situation remained under control precisely because of the police.

516. Three, Claimant argues that “Bolivia failed to comply with the basic formalities required by

Bolivian law for an expropriation to be considered lawful […].”686 Even if Claimant’s

allegations about the relevant formalities were true (which they are not), Bolivia did not

expropriate the Assets; it reverted them pursuant to the inherent powers of the executive under

the Bolivian constitution, including to enforce the laws and to ensure security and order.687

As previously explained, the Tin Smelter was reverted due to illegalities in the privatization

process,688 the Antimony Smelter was reverted due to prolonged inactivity contrary to the

privatization contract and the law,689 and the Colquiri Mine Lease was reverted to quell the

violent conflict caused by Claimant’s unstable relationship with the cooperativistas.690

517. In conclusion, Claimant has not presented a single reason to think that Bolivia denied it due

process in reverting the Assets. The long and short of the matter is that Bolivia provided many

posterior opportunities to challenge the reversions, none of which Claimant pursued.

682 Statemnet of Claim, ¶¶ 77, 78

683 Statement of Claim, ¶ 173.

684 Statement of Claim, ¶ 97

685 Eskdale, ¶¶ 44-45.

686 Statement of Claim, ¶ 176 (emphasis added).

687 Constitution of Bolivia of 1967, R-3, Art. 96(1), (18); Constitution of Bolivia of 7 February 2009, C-95, Art. 172(1),

(16).

688 Section 2.6.1 above.

689 Section 2.6.2 above.

690 Section 2.6.3 above.

Page 159: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

154

6.2 Bolivia Provided Full Protection And Security To The Assets At All Times

518. It is Claimant’s position that “Bolivia has failed to provide full protection and security and to

observe its obligations under the Colquiri lease, in breach of the Treaty[.]”691 To support this

allegation, Claimant effectively asserts that Bolivia has an obligation under the Treaty’s FPS

provision to guarantee that no private individual would ever adversely affect the Colquiri

Mine in any way. On this basis, Claimant then attempts to conclude from the supposition that

the cooperativistas did adversely affect the mine that it must have been Bolivia’s fault.

519. But this reasoning is foreign to the applicable international law and to the facts of this dispute.

To provide FPS, a state needs no more than take legal and reasonable measures under the

circumstances to prevent the permanent physical impairment of an asset (Section 6.2.1)— a

standard that is not modificed by the Colquiri Mine Lease (Section 6.2.3). This Bolivia did.

Bolivia could not reasonably intervene with force in a dispute involving thousands of people,

but it implemented those coercive measures available and aggressively attempted to negotiate

a solution with the cooperativistas and mine workers (Section 6.2.2).

6.2.1 Full Protection And Security Requires Only Lawful And Reasonable Measures In

Response To A Threat Of Permanent Physical Impairment

520. Claimant attempts to suggest that the Treaty’s FPS provision in effect establishes a guarantee

that no third party will in any way affect an investment.692 This position is obviously false.

The FPS provision requires nothing more than that the state exercise due diligence —that is

make reasonable efforts— appropriate to the circumstances.

521. The meaning of the provision was made plain in the ICJ’s Elettronica Sicula (ELSI)

judgement. According to the Court, such provisions do not create an obligation of strict

liability or a guarantee that property will never be affected. To the contrary, a state satisfies

such a provision by exercising appropriate due diligence under the circumstances. As the

Court explicitly held, the provision “cannot be construed as the giving of a warranty that

property shall never in any circumstances be occupied or disturbed.”693

522. The ICJ is not alone in this view. Investment tribunals have widely confirmed the Court’s

holding that protection provisions are not warranties and do not establish obligations of result,

but instead require nothing more than due diligence or reasonable action. Recent investment

691 Statement of Claim, § V(B).

692 See Statement of Claim, ¶¶ 178-179.

693 Case concerning Elettronica Sicula S.p.A. (ELSI) (United States of America v. Italy), ICJ, Judgment of 20 July 1989,

RLA-72, ¶ 108.

Page 160: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

155

tribunals to reaffirm the meaning of these clauses include Allard v. Barbados,694 Mamidoil v.

Albania,695 Tulip v. Turkey,696 and Toto v. Lebanon.697 In fact, even Claimant’s own authority

on this issue, the Frontier Petroleum v. Czech Republic tribunal, confirms the holding.698

523. As developed in investment law, states need only exercise due diligence. This obligation

requires the state to take a potential measure of protection only when (i) there is a threat of

permanent impairment to physical integrity of the investment; (ii) the potential measure to

prevent permanent impairment is lawful; and (iii) the potential measure is reasonable under

the circumstances.

524. First, there must be a threat of permanent impairment to physical integrity of the investment.

Mere occupation by unwelcome third parties does not itself qualify. This was one of the

lessons from the ICJ’s judgment in ELSI.699 Just as here, ELSI concerned the occupation of

industrial property by former workers and other individuals who did no significant damage to

the property.700 In such circumstances, the failure of the state to take measures to resolve the

occupation cannot breach the FPS provision.

694 Peter A. Allard v. The Government of Barbados, PCA Case No. 2012-06, Award of 27 June 2016, RLA-73, ¶ 244: “The

obligation is limited to reasonable action, and a host State is not required to take any specific steps that an investor asks

of it.”

695 Mamidoil Jetoil Greek Petroleum Products Societe Anonyme S.A. v. Republic of Albania, ICSID Case No. ARB/11/24,

Award of 30 March 2015, RLA-74, ¶ 821: “The Tribunal refers to a jurisprudence constante according to which the

standard of constant protection and security does not imply strict liability but rather obliges States to use due diligence

to prevent harassment and injuries to investors […]. The Tribunal further concurs with Electrabel v. Hungary that due

diligence does not oblige the State to “prevent each and every injury”.

696 Tulip Real Estate Investment and Development Netherlands B.V. v. Republic of Turkey, ICSID Case No. ARB/11/28,

Award of 10 March 2014, RLA-75, ¶ 430: “The Tribunal agrees with the observations in Wena Hotels that the FPS

standard does not impose on the State a “strict liability” obligation. That is, the State cannot insure or guarantee the

full protection and security of an investment.”

697 Toto Costruzioni Generali S.p.A. v. Republic of Lebanon, ICSID Case No. ARB/07/12, Award of 7 June 2012, RLA-

76, ¶ 228: “However, the International Court of Justice in Elettronica Sicula S.p.A.(ELSI) (United States of America v.

Italy) found that the provision in a treaty for ‘constant protection and security’ cannot be construed as the giving of a

warranty that property shall never in any circumstances be occupied or disturbed”.

698 Frontier Petroleum Services Ltd v Czech Republic (UNCITRAL) Final Award of 12 November 2010, CLA-102, ¶ 269.

699 Case concerning Elettronica Sicula S.p.A. (ELSI) (United States of America v. Italy), ICJ, Judgment of 20 July 1989,

RLA-72, ¶ 108:“In any event, considering that it is not established that any deterioration in the plant and machinery

was due to the presence of the workers, and that the authorities were able not merely to protect the plant but even in

some measure to continue production, the protection provided by the authorities could not be regarded as falling below

"the full protection and security required by international law"; or indeed as less than the national or third-State

standards.”

700 Case concerning Elettronica Sicula S.p.A. (ELSI) (United States of America v. Italy), ICJ, Judgment of 20 July 1989,

RLA-72, ¶¶ 107-108

Page 161: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

156

525. This was also the view of the investment tribunals in Noble Ventures v. Romania701 as well as

Toto v. Lebanon.702 In particular, the Toto tribunal considered whether Lebanon took

sufficient action to protect against the occupation of property destined for the construction of

a workshop. In rejecting the FPS claim, the tribunal emphasized that there was no breach, in

part, because “the temporary obstructions […] did not amount to an impairment which

affected the physical integrity of the investment.” 703

526. Second, the omitted measures must be permissible under the applicable international and

municipal law. This is a common sense requirement. As the Tecmed tribunal explained, any

alleged failure to act must be assessed “in accordance with the parameters inherent in a

democratic state.”704 It rejected the notion that FPS can require the state to take actions that

are contrary to basic democratic principles. For this reason, it rejected the allegation that

Mexico had taken insufficient actions to stop direct action by opponents of a landfill.705

527. Third, and relatedly, the omitted measures must be reasonable under the circumstances.

Investment tribunals, including Toto v. Lebanon, 706 Mamidoil v. Albania,707 and Tulip v.

Turkey,708 consistently acknowledge this requirement for a breach of FPS. In this regard, the

Mamidoil tribunal put the point bluntly: “The measure of due diligence is conditioned by the

circumstances.”709 And the Tulip tribunal echoed that “[t]he question of whether the State

701 Noble Ventures Inc v Romania (ICSID Case No ARB/01/11) Award of 12 October 2005, CLA-59, ¶ 165.

702 Toto Costruzioni Generali S.p.A. v. Republic of Lebanon, ICSID Case No. ARB/07/12, Award of 7 June 2012, RLA-

76, ¶ 229.

703 Toto Costruzioni Generali S.p.A. v. Republic of Lebanon, ICSID Case No. ARB/07/12, Award of 7 June 2012, RLA-

76, ¶ 229.

704 Técnicas Medioambientales Tecmed SA v United Mexican States (ICSID Case No ARB(AF)/00/2) Award of 29 May

2003, CLA-43, ¶ 177.

705 Técnicas Medioambientales Tecmed SA v United Mexican States (ICSID Case No ARB(AF)/00/2) Award of 29 May

2003, CLA-43, ¶ 177: At any rate, the Arbitral Tribunal holds that there is not sufficient evidence supporting the

allegation that the Mexican authorities, whether municipal, state, or federal, have not reacted reasonably, in accordance

with the parameters inherent in a democratic state, to the direct action movements conducted by those who were against

the Landfill.

706 Toto Costruzioni Generali S.p.A. v. Republic of Lebanon, ICSID Case No. ARB/07/12, Award of 7 June 2012, RLA-

76, ¶ 229.

707 Mamidoil Jetoil Greek Petroleum Products Societe Anonyme S.A. v. Republic of Albania, ICSID Case No. ARB/11/24,

Award of 30 March 2015, RLA-74, ¶ 821.

708 Tulip Real Estate Investment and Development Netherlands B.V. v. Republic of Turkey, ICSID Case No. ARB/11/28,

Award of 10 March 2014, RLA-75, ¶ 430.

709 Mamidoil Jetoil Greek Petroleum Products Societe Anonyme S.A. v. Republic of Albania, ICSID Case No. ARB/11/24,

Award of 30 March 2015, RLA-74, ¶ 821.

Page 162: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

157

has failed to ensure FPS is one of fact and degree, responsive to the circumstances of the

particular case.”710

528. The Pantechniki sole arbitrator, Jan Paulsson, in fact devoted careful analysis to determining

what measures are reasonable in given circumstances. He concluded that the appropriate

standard is that proposed by Newcombe and Paradell.711 That standard, adopted in full by

Paulsson, establishes that the measure of due diligence is conditioned by the resources and

circumstances of the state. It is a modified objective standard:

Although the host state is required to exercise an objective minimum standard of due

diligence, the standard of due diligence is that of a host state in the circumstances and

with the resources of the state in question. This suggests that due diligence is a modified

objective standard - the host state must exercise the level of due diligence of a host

state in its particular circumstances.”712

529. As Pantechniki further explains, the Newcombe and Paradell standard of due diligence

reflects the state’s level of development and stability. When a state has less capacity to act or

greater instability, the due diligence standard is less demanding:

In practice, tribunals will likely consider the state’s level of development and stability

as relevant circumstance in determining whether there has been due diligence. An

investor investing in an area with endemic civil strife and poor governance cannot have

the same expectation of physical security as one investing in London, New York or

Tokyo.713

530. Applying this standard, the Pantechniki sole arbitrator rejected the investor’s FPS claim

because Albania could not reasonably intervene to stop looting; the scale of the social unrest

precluded any action, rendering the authorities powerless.714

531. Now it is Claimant’s position that, at least, the last of these factors is irrelevant and that the

State should have to intervene regardless of available State resources, regardless of reasonable

expectations of security, and regardless of the scale of the unrest. To suggest that international

law accepts this view, Claimant relies principally on AAPL v. Sri Lanka and AMT v. Zaire,

710 Tulip Real Estate Investment and Development Netherlands B.V. v. Republic of Turkey, ICSID Case No. ARB/11/28,

Award of 10 March 2014, RLA-75, ¶ 430.

711 Pantechniki S.A. Contractors & Engineers v. Republic of Albania, ICSID Case No. ARB/07/21, Award of 30 July 2009,

RLA-77, ¶ 81.

712 Pantechniki S.A. Contractors & Engineers v. Republic of Albania, ICSID Case No. ARB/07/21, Award of 30 July 2009,

RLA-77, ¶ 81.

713 Pantechniki S.A. Contractors & Engineers v. Republic of Albania, ICSID Case No. ARB/07/21, Award of 30 July 2009,

RLA-77, ¶ 81.

714 Pantechniki S.A. Contractors & Engineers v. Republic of Albania, ICSID Case No. ARB/07/21, Award of 30 July 2009,

RLA-77, ¶ 82.

Page 163: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

158

the most recent of which was decided twenty years ago.715 It simply ignores that investment

law has evolved in the intervening years.

532. It also ignores that not even these two awards support its legal position. In the present case,

it is undisputed that cooperativistas are not state actors and that Bolivia was not involved in

their alleged actions against Claimant. However, AAPL concerned a State-initiated counter-

insurgency raid on the area surrounding the shrimp-farm investment,716 and AMT concerned

looting by members of the Zairian armed forces.717 In both cases, State actors directly

instigated the damage that the investor suffered.718

533. Further revealing the vacuity of its position on FPS, Claimant also places reliance on Frontier

v. Czech Republic, Saluka v. Czech Republic, and Azurix v. Argentina,719 none of which

concern the provision of physical protection against third party actions. Instead, these awards

all consider the restrictions that the FPS clause imposes on the State’s legal system.720

534. Simply put, to demonstrate a breach of the FPS provision, Claimant must prove that (i) there

was a threat of permanent impairment to the physical integrity of its investment, (ii) Bolivia

had legal measures available to it to counter that threat, and (iii) it was unreasonable under the

circumstances for Bolivia to omit those measures.

6.2.2 Bolivia Took All Actions That Were Reasonably Available In Light Of The Severe Social

Conflict And Limitations From Human Rights Law

535. Claimant alleges that “Bolivia failed to physically protect Glencore Bermuda’s investment,

Colquiri, against violence interference from the local cooperatives”721 and so breached the

FPS clause. This allegation is false, as it does not meet any of the three necessary elements

of an FPS claim. Claimant’s failure to prove even one is sufficient to defeat its FPS claim.

715 Statement of Claim, ¶¶ 178-179.

716 Asian Agricultural Products Ltd (AAPL) v Republic of Sri Lanka (ICSID Case No ARB/87/3) Final Award of 27 June

1990, CLA-14, ¶ 85(b).

717 See American Manufacturing & Trading Inc v Republic of Zaire (ICSID Case No ARB/93/1) Award of 21 February

1997, CLA-20, ¶ 3.04.

718 The reliance on Siag v. Egypt suffers from a similar flaw, since in that case the Egyptian courts had ruled that the full

protection clause had been breached and the State failed to take the necessary measures to return the investment to the

claimants. Waguih Elie George Siag and Clorinda Vecchi v Arab Republic of Egypt (ICSID Case No ARB/05/15) Award

of 1 June 2009, CLA-89, ¶ 447-448.

719 Statement of Claim, ¶¶ 179-180.

720 See Saluka Investments BV v Czech Republic (UNCITRAL) Partial Award of 17 March 2006, CLA-62, ¶ 490, 493, 495-

496; Azurix Corp v Argentine Republic (ICSID Case No ARB/01/12) Award of 14 July 2006, CLA-63, ¶ 408; Frontier

Petroleum Services Ltd v Czech Republic (UNCITRAL) Final Award of 12 November 2010, CLA-102, ¶¶ 256, 273.

721 Statement of Claim, ¶ 184.

Page 164: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

159

536. First, the Colquiri Mine was in no danger of suffering any permanent physical impairment

during the dispute with the workers and cooperativistas. To the contrary, both the workers

and the cooperativistas had a basic interest in preserving the Mine as a productive asset that

could support their livelihoods. Competition over who would benefit from this asset was at

the heart of the dispute.

537. Although Claimant states that the situation “posed an ongoing serious risk to the physical

security of Glencore Bermuda’s workers as well as the integrity of the Colquiri Mine,”722 this

response goes nowhere. Glencore International’s workers were principal protagonists in the

violent conflict that broke out and substantially responsible for impeding its resolution, as

they blockaded main roads and engaged in violent protests in an attempt to influence events.723

Any risk was due to their own actions. And Claimant has not put forth any evidence at all

that the integrity of the Mine was in any danger of permanent physical impairment.

538. Second, Bolivia took all legal actions available to it under the circumstances. Although

Claimant does not even make explicit what action it thinks Bolivia failed to take, it implies

that Bolivia should have repressed the conflict at the Mine at gunpoint.724

539. This suggestion is unreasonable in the extreme. Claimant’s implication ignores the fact that

over one thousand cooperativistas violently took control of the Mine.725 In response, the mine

workers, backed by a powerful union, blockaded the road to Colquiri and threatened to retake

the Mine by force.726 The number of union members involved in the counter-actions

722 Statement of Claim, ¶ 185.

723 Mamani, ¶¶ 41-42; La Patria, Marcha de cooperativistas provoca destrozos en propiedad privada, press article of 12

June 2012, C-130.

724 Statement of Claim, ¶ 184.

725 Cachi, ¶ 33. See, also, Mamani, ¶ 25 (“En la mañana del 30 de mayo de 2012, cuando nos encontrábamos trabajando

en el interior de la Mina, fuimos alertados de que un gran número de cooperativistas (aproximadamente unos 1200)

estaba ingresando por el sector El Triunfo (una antigua bocamina) y que otros se estaban dirigiendo al nivel de

extracción de la Mina (que es la bocamina que queda en el nivel 165, conocido como Sanjuanillo). Los cooperativistas

fueron muy violentos y nos atacaron con palos, piedras y dinamita, hiriendo a algunos de los compañeros que estaban

trabajando en ese turno al interior de la mina”) (Unofficial translation: “On the morning of 30 May 2012, while we

were working in the interior of the Mine, we were alerted that a large number of cooperativistas (approximately 1.200)

were entering through the El Triunfo sector (a former mine mouth) and that there were others who were going towards

the extraction level of the Mine (which is the mouth at level 165, known as Sanjuanillo). The cooperativistas were very

violent and attacked us with sticks, stones and dynamite, injuring some of our colleagues who were working during that

shift inside the Mine”).

726 Mamani, ¶ 29 (“Recuerdo que, aunque ninguno de los presentes creíamos conveniente un enfrentamiento violento con

los cooperativistas, sí acordamos la necesidad de ejercer presión (incluso por la fuerza) para asegurar nuestras fuentes

de trabajo. Por este motivo, y a partir de esta fecha, la FSTMB bloqueó las rutas que de Caracollo conducen a La Paz

y Colquiri (la única vía de acceso a la Mina) y exigió la presencia de representantes del Gobierno Nacional”)

(Unofficial translation: “I recall that, although no one present thought that a violent confrontation with the

cooperativistas was desirable, we did agree that it was necessary to put pressure (including by force) to ensure our

work sources. For this reason, and from this date, FSTMB blocked the routes that lead from Caracollo to La Paz and

Colquiri (the only way to access the Mine) and demanded the presence of representatives of the National Government”).

Page 165: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

160

eventually reached into the thousands727 and involved actions not just at the mine but in other

parts of the country as well.728

540. What Claimant is proposing is not simply sending a few police officers to arrest a lone

miscreant but, in effect, to send a military force into the middle of a violent conflict between

thousands of individuals taking place across the country and within the tunnels of the

underground Colquiri Mine. In addition to being futile, such an action would, in all likelihood,

resulted in mass casualties and deaths among the mine workers, the cooperativistas, and the

police or military sent in to suppress the former. A military intervention in a social mining

context may have catastrophic consequences. Claimant cannot seriously propose that Bolivia

failed to exercise due diligence for its failure to take such an action.

541. In fact, Bolivia had in the past made the serious mistake of attempting to use force to intervene

in a mining dispute. During an uprising of mining workers and local communities against the

Canadian company Da Capo Resources, the military intervened at the company’s

Amayapampa project. The result was a violent confrontation with the civilian protesters led

to the deaths of seven people and injuries to about a hundred more. And the violation of

human rights did not even serve the intended purpose of protecting the mining project: the

project was ultimately suspended.729

542. Thus, any forcible police action at Colquiri would have risked violating Bolivia’s human

rights obligations under the ICCPR and the American Convention.730 As the Inter-American

Court of Human Rights has held, the use of force must always obey the principles of absolute

necessity and proportionality.731 The use of force is prohibited unless it is absolutely

727 Mineros de Colquiri bloquean conani exigiendo la emisión del D.S. de Nacionalización, Video (2012), R-224.

728 La Prensa, Colquiri se convierte en un campo de batalla, press article of 15 June 2012, C-142 (“Mineros asalariados y

afiliados a la cooperativa 26 de Febrero se enfrentaron ayer con dinamita y palos por el control de la mina Colquiri,

mientras el Gobierno volvió a convocarlos para dialogar en procura de encontrar una solución al conflicto que ya lleva

dos semanas. La llegada de la noche y la explosión de cachorros de dinamita generaron zozobra entre los pobladores

de Colquiri, quienes pedían entre sollozos la llegada de efectivos policiales y la pacificación de la zona, que está

ubicada en la provincia Inquisivi, del departamento de La Paz”) (Unofficial translation: “Mining employees and

affiliates to the cooperativa 26 de Febrero clashed yesterday, [using] dynamite and sticks, over control of the Colquiri

mine, while the Government again summoned them to discuss with a viewt to find a solution to the conflict that has

already lasted two weeks. Nightfall and the explosion of dynamite sticks generated anxiety amongst Colquiri’s

population, who requested, sobbing, the arrival of police forces and the appeasement of the area, located in the province

of Inquisivi, in the department of La Paz”).

729 See, for instance, La Razón, Amayapampa, un proyecto ‘fantasma’ , press article of 4 April 2016, R-218; La Patria, La

masacre de “Navidad”, Amayapampa y Capasirca, press article of 19 March 2014, R-219.

730 American Convention, Art. 4, 5; ICCPR, Art. 6, 7

731 Nadege Dorzema et al. v. Dominican Republic, Inter-American Court of Human Rights, Judgment of 24 October 2012,

RLA-78, ¶ 85

Page 166: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

161

necessary in light of “a threat or a real or imminent danger to the agents or third parties.”732

It is also prohibited unless proportionate, meaning that it can only be applied progressively

after employing negotiation tactics or control733 and only when “there was proportionality

between the use of force and the harm it sought to prevent.”734

543. Claimant’s implied proposal that Bolivia should have repressed the cooperativistas and

workers with force is in stark violation of these principles. Claimant would have had Bolivia

use force to protect its property rights, which is grossly disproportionate to the risk to human

life that the use of force would entail. Claimant also would have had Bolivia forego the

progressive response to a situation that human rights law requires, by immediately using force

to protect its property rights instead of resolving the situation through negotiation. Private

property rights do not take precedence over the human person in international law. Claimant

was not entitled to the violent repression of the cooperativistas or the workers.

544. Third, the measures of protection that Bolivia took were entirely reasonable under and

consistent with “the level of due diligence of a host state in [Bolivia’s] particular

circumstances.”735 Bolivia had limited capacity to control violent outbursts by cooperativistas

or mine workers, outbursts which could rapidly expand to include thousands of individuals.736

In fact, the participation en masse of the cooperativistas in demonstrations against Sánchez

de Lozada in 2003 were key in forcing his resignation. 737 Glencore International knew, or

should have known this, when it invested.

732 Nadege Dorzema et al. v. Dominican Republic, Inter-American Court of Human Rights, Judgment of 24 October 2012,

RLA-78, ¶ 85

733 Nadege Dorzema et al. v. Dominican Republic, Inter-American Court of Human Rights, Judgment of 24 October 2012,

RLA-78, ¶ 85

734 Nadege Dorzema et al. v. Dominican Republic, Inter-American Court of Human Rights, Judgment of 24 October 2012,

RLA-78, ¶ 87

735 Pantechniki S.A. Contractors & Engineers v. Republic of Albania, ICSID Case No. ARB/07/21, Award of 30 July 2009,

RLA-77, ¶ 81.

736 La Patria, La masacre de “Navidad”, Amayapampa y Capasirca, press article of 19 March 2014, R-219; El Día, Se

reactiva el conflicto minero en Mallku Khota, press release of 3 October 2012, R-251; M. Cajías de la Vega, “Crisis,

Diáspora y Reconstitución de la Memoria Histórica de los Mineros Bolivianos” in Revista de Estudios Transfronterizos,

Vol. X, No. 2 (2010), R-159, p. 87.

737 M. Cajías de la Vega, “Crisis, Diáspora y Reconstitución de la Memoria Histórica de los Mineros Bolivianos” in Revista

de Estudios Transfronterizos, Vol. X, No. 2 (2010), R-159, p. 87 (“La presencia en El Alto de La Paz de los 800 mineros

de Huanuni y de más de 3.000 cooperativistas mineros, fue altamente significativa en momentos decisivos de la

insurrección popular que se desató en octubre de 2003 contra el gobierno de Gonzalo Sánchez de Lozada y que tuvo su

epicentro en esa ciudad del departamento de La Paz. No sólo se notó la presencia, en toda la semana que duró el

levantamiento popular, de los pobladores de los barrios mineros de relocalizados, principalmente de Santiago II, uno

de los lugares donde se produjeron mayores enfrentamientos con el ejército, sino de trabajadores mineros asalariados

y cooperativistas llegados desde Huanuni y otras minas. Así, octubre fue sin duda un momento de revelación de

“acumulaciones sociales previas”, aunque no sólo para el sector minero, sino para el conjunto de los sectores

populares en Bolivia […]”) (Unofficial translation: “The presence in El Alto and La Paz of 800 miners of Huanuni and

more than 3,000 mining cooperativistas was very significant in decisive moments of the popular uprising triggered in

October 2003 against the government of Gonzalo Sánchez de Lozada and the epicentre of which was in that city of the

Page 167: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

162

545. Despite the intrinsic limitations it faced, Bolivia took extensive actions in response to the

conflict at the Colquiri mine. The events of early April were over so quickly that no response

was reasonably feasible.738 However, immediately following the invasion of the Mine on 30

May 2012, police squads were dispatched to Colquiri739 and legal restrictions were imposed

to prevent the cooperativistas from selling minerals from the Mine.740 Thus, Bolivia took the

coercive actions available to it to resolve the situation. Claimant’s allegation that Bolivia

failed to intervene is entirely false.741

546. Recognizing that it could not coercively resolve the situation, Bolivia sought a negotiated

solution. It sent top Government officials —the Minister of Mines and the Minister of

Labor— as well as COMIBOL representatives to mediate a solution between the workers and

the cooperativistas.742 This became an extended effort of exchanging proposals, with multiple

department of La Paz. Not only was the presence of residents of neighbourhoods of relocated miners noted during the

entire week of the popular uprising, in particular from Santiago II, one of the places where major confrontations with

the army took place – but also the presence of mining employees and cooperativistas from Huanuni and other mines.

Thus, October was undoubtedly a moment of revelation of ‘previous social accumulations’, not only in the mining sector

but also in all popular sectors in Bolivia”).

738 See section 2.6.3.1 above.

739 La Razón, El Gobierno envía más policías a Colquiri para evitar conflicto, press article of 1 June 2012, R-213.

740 Página Siete, Gobierno impide salida de mineral de Colquiri, press article of 1 June 2012, R-214 (“el Gobierno impide

la salidad de mineral de Colquiri para ser comercializado debido a la toma de la mina por el conflicto que existe entre

mineros y cooperativistas […]. También la energía eléctrica fue cortada en la zona para evitar que la maquinaria

funcione”) (Unofficial translation: “the Government is preventing Colquiri ore from being transferred to be sold due to

the mine being taken over as a result of the existing conflict between miners and cooperativistas, stated the executive

president of [COMIBOL] yesterday during an interview with radio ERBOL. The decision was made on Wednesday

night after cooperativistas took control over the mine compound. Electricity was also cut in the area to prevent the

machinery from functioning”).

741 Statement of Claim, ¶ 184(f).

742 Mamani, ¶ 28 (“La toma de un yacimiento tan grande como Colquiri tuvo una repercusión en todo el sector minero

nacional. Muy rápidamente, varios sindicatos y organizaciones productivas rechazaron la toma de la Mina Colquiri.

Por esta misma razón, el 31 de mayo de 2012, la FSTMB, entidad que agrupa a los distintos sindicatos mineros del

país, convocó a un ampliado nacional de emergencia en la localidad de Caracollo, a unos 39 kilómetros de la Mina,

para discutir las acciones violentas de los cooperativistas”) (Unofficial translation: “The takeover of a site as large as

Colquiri had repercussions over the entire national mining sector. Rapidly, several unions and productive organizations

rejected the takeover of the Colquiri Mine. For this same reason, on 31 May 2012, the [FSTMB], an entity formed by

the different mining unions of the country, convened an emergency national meeting in the town of Caracollo, some 39

kilometers from the Mine, to discuss the violent actions of the cooperativistas”).

Page 168: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

163

different terms considered in extensive and repeated meetings with the relevant leaders.743

Claimant again falsely states that Bolivia failed to intervene.744

547. Only when these initial efforts proved fruitless due to the intransigence of the

cooperativistas745 did Bolivia begin to consider reversion as a way to prevent further

bloodshed.746

548. In addition to falsely alleging that Bolivia failed to act, Claimant also alleges that Bolivia

undermined Glencore International’s own solution of granting the Rosario vein of the mine to

the cooperativistas.747 This too is flatly false. Far from solving anything, proposing the grant

of the Rosario vein had the effect of enflaming again a conflict that was just beginning to calm

743 Minutes of understanding with the Sindicato de Trabajadores Mineros de Colquiri and the Federación Sindical de

Trabajadores Mineros de Bolivia of 3 June 2012, C-115; La Patria, En suspenso acuerdo entre Gobierno y mineros

sindicalizados y cooperativistas, press article of 4 June 2012, C-117; La Razón, Minería hace 5 ofertas, pero aun no

convence a los cooperativistas, press article of 5 June 2012, R-215; Mamani, ¶¶ 32-33 (“Según lo que entendimos, el

Gobierno estaba buscando el apoyo de la empresa Sinchi Wayra para entregar a los cooperativistas nuevas áreas en

la Mina. Sin embargo, la prensa publicó que las conversaciones no habían avanzado porque los representantes de la

cooperativa debían consultar la propuesta con sus bases. A pesar de lo anterior, y con el fin lograr una salida negociada

al conflicto, los miembros del STMC aceptamos que Sinchi Wayra hiciera un nuevo ofrecimiento a los cooperativistas.

El 5 de junio de 2012, la compañía minera Colquiri confirmó al Estado su intención crear 200 nuevos puestos de trabajo

en la compañía y ceder la veta San Antonio a la Cooperativa 26 de Febrero. Esta veta tiene un acceso a través de una

rampa puesta en funcionamiento en 2007 por Sinchi Wayra y puede ser explotada comercialmente en los niveles 240 y

325”) (Unofficial translation: “From what we understood, the Government was seeking Sinchi Wayra’s support to

allocate new areas of the Mine to the cooperativistas. However, the press reported that discussions had not progressed

because the representatives of the cooperative had to consult the proposal with their bases. This notwithstanding, and

with the objective of achieving a negotiated end to the conflict, we the members of STMC agreed that Sinchi Wayra

make a new offer to the cooperativistas. On 5 June 2012, Compañía Minera Colquiri confirmed to the State its intention

to create 200 new work positions in the company and to assign the San Antonio vein to the Cooperativa 26 de Febrero.

This vein includes an access through a ramp commissioned in 2007 by Sinchi Wayra and can be commercially exploited

at levels 240 and 325”); Letter from Colquiri (Mr Capriles) to the Minister of Mining (Mr Virreira) and Comibol (Mr

Córdova) of 5 June 2012, C-120; Letter from the Ministry of Mines to the Cooperativa 26 de Febrero of 6 June 2012,

R-216.

744 Statement of Claim, ¶ 184(f).

745 La Patria, Colquiri: Mineros suspenden labores y cooperativistas no aceptan veta, press article of 5 June 2012, C-118

(“Entretanto, los trabajadores cooperativistas, que se reunieron en el distrito minero de Colquiri, determinaron no

aceptar la oferta de acceder a la veta ‘San Antonio’ en su totalidad y continúan con su exigencia de ‘sacar’ a la empresa

de aquella localidad minera”) (Unofficial translation: “Meanwhile, the cooperativistas who held meetings in the mining

district of Colquiri, decided not to accept the offer of the ‘San Antonio’ vein in its entirety and continue to require the

company’s ‘exit’ from the mining town”); Cachi, ¶¶ 35-36; Mamani, ¶ 33-34.

746 La Patria, Gobierno plantea nacionalizar Colquiri para poner fin a conflicto minero, press article of 6 June 2012, R-

221; La Razón, Virreira y cooperativa discuten ampliación de áreas de trabajo, press article of 8 June 2012, R-26;

Mamani, ¶ 39 (“Entretanto, los miembros del STMC y la FSMB nos desplazamos nuevamente hasta la población de

Colquiri, donde iniciamos una reunión en Cabildo con una masiva participación de los pobladores. Nuestra reunión se

instaló en la Plaza 6 de Agosto, a unos 2km de la bocamina Sanjuanillo, donde las bases de la Cooperativa 26 de

Febrero se encontraban reunidas”) (Unofficial translation: “Meanwhile, we the members of STMC and FSTMB travelled

again to the village of Colquiri, where we initiated a Council meeting attended by a great number of the village

population and central institutions of the village (neighbourhood council, authorities of indigineous communities,

guilds, transporters, etc.) Our meeting was set up in the Plaza 6 de Agosto, some 2 km from the Sanjuanillo mine mouth,

where the bases of the Cooperativa 26 de Febrero were assembled”); Cachi, ¶ 38. See, also, Video Bolivia,

Enfrentamiento en Mina Colquiri. Hay Heridos, June 2012 (Video), R-222; Proposal from the Government to the

Cabildo of Colquiri, R-27; La Patria, Mineros asalariados y cooperativistas aceptan rescisión de contrato en Colquiri,

press article of 8 June 2012, R-223.

747 Statement of Claim, ¶ 184(j).

Page 169: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

164

down because of Bolivia’s efforts. Because the proposed grant exploited divisions among the

cooperativistas and its own workers, over a thousand union members blockaded roads in

response748 and protests began, quickly escalating to violence.749

549. In conclusion, Claimant has failed to demonstrate that there was threat to the permanent

physical integrity of the Mine, that Bolivia did not take legal measures available to it, and that

the measures it did take were unreasonable under the circumstances. The FPS claim thus fails

many times over.

6.2.3 The Colquiri Mine Lease Contract Adds Nothing To The Full Protection And Security

Standard

550. Attempting to shore up its position, Claimant proposes that Articles 9.2.1 and 12.2.1 of the

Colquiri Mine Lease, for some unexplained reason, establish a more demanding protection

requirement than does the Treaty’s FPS clause.750 This is simply incorrect. Those Articles

establish exactly the same standard of protection as the FPS clause.

551. Article 9.2.1 does not establish any requirement of protection at all; it provides only for an

obligation of non-interference. It states that “[l]a ARRENDADORA se obliga a no interferir

ni limitar las operaciones del ARRENDATARIO.”751 Thus, this provision is entirely irrelevant

to the applicable standard of protection.

552. Article 12.2.1 also adds nothing to the relevant standard of protection, as it explicitly

incorporates the background legal standard and does not establish any elevated standard. The

Article states:

La ARRENDADORA garantizará: La pacifica posesión uso y goce del CENTRO

MINERO, debiendo defender, proteger garantizar y reivindicar derechos contra

748 Mineros de Colquiri bloquean conani exigiendo la emisión del D.S. de Nacionalización, Video (2012), R-224.

749 La Prensa, Colquiri se convierte en un campo de batalla, press article of 15 June 2012, C-142 (“Mineros asalariados y

afiliados a la cooperativa 26 de Febrero se enfrentaron ayer con dinamita y palos por el control de la mina Colquiri,

mientras el Gobierno volvió a convocarlos para dialogar en procura de encontrar una solución al conflicto que ya lleva

dos semanas. La llegada de la noche y la explosión de cachorros de dinamita generaron zozobra entre los pobladores

de Colquiri, quienes pedían entre sollozos la llegada de efectivos policiales y la pacificación de la zona, que está

ubicada en la provincia Inquisivi, del departamento de La Paz”) (Unofficial translation: “Mining employees and

affiliates to the cooperativa 26 de Febrero clashed yesterday, [using] dynamite and sticks, over control of the Colquiri

mine, while the Government again summoned them to discuss with a viewt to find a solution to the conflict that has

already lasted two weeks. Nightfall and the explosion of dynamite sticks generated anxiety amongst Colquiri’s

population, who requested, sobbing, the arrival of police forces and the appeasement of the area, located in the province

of Inquisivi, in the department of La Paz”).

750 Statement of Claim, ¶ 186.

751 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11, Clause 9.2.1 (Unofficial translation: “[t]he LESSOR commits not to interfere with

or limit the LESSEE’S operations”).

Page 170: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

165

incursiones, usurpaciones y otras perturbaciones de terceros durante la vigencia del

CONTRATO, de acuerdo a las disposiciones legales vigentes, sin excepción alguna

asumiendo además su responsabilidad por la evicción de acuerdo a la LEY

APLICABLE.752

553. On the one hand, any obligation of protection arising from Article 12.2.1 is identical to the

background standard of protection from the Treaty. The Article explicitly states that the

obligations are those from the applicable legal provisions in force, in this case either the Treaty

or Bolivian law. If the applicable legal provisions are from the Treaty, then the Article

straightforwardly adds nothing to the Treaty standard of protection. If they are from Bolivian

law, then Claimant has failed to argue, much less establish, that they are different from the

Treaty standard.

554. On the other hand, even if it were true that Article 12.2.1 establishes an independent standard

of protection, the only reasonable interpretation of that standard is that it is no more

demanding than the Treaty standard. The leasor of the mine cannot reasonably be expected

to be an absolute guarantor that nothing and no one will ever interfere with mine operations.

Instead, it can only be expected to take reasonable (and legal) actions under the circumstances

to protect the Mine.

555. Moreover, Claimant has not even attempted to specify what actions it considers that

COMIBOL should have taken to end the dispute with the cooperativistas.

556. In short, Claimant’s appeal to the Colquiri Mine Lease is futile; that contract does not establish

a heightened standard of protection.

6.3 Although Claimant’s Fair And Equitable Treatment Allegations Are Redundant,

Bolivia Provided Fair And Equitable Treatment To The Assets At All Times

557. After setting out its principal claims, Claimant tacks on FET and impairment claims that

simply repackages its previous allegations.

558. At the outset, Claimant argues that “[t]he Treaty does not define what constitutes ‘fair and

equitable treatment’, and it is generally accepted that this standard of conduct cannot be

summarized in a precise statement of legal obligation.”753 Thus, it is the position of Claimant

752 Lease agreement for the Colquiri Mine between the Ministry of External Trade and Investment, Comibol, Colquiri SA

and Comsur of 27 April 2000, C-11, Clause 12.2.1 (Unofficial translation: “The LESSOR will guarantee: The peaceful

possession, use and enjoyment of the MINING CENTRE, by defending, protecting, guaranteeing and assert all rights

against intrusions, usurpation and other disruptions by third-parties during the CONTRACT term, in conformity with

legal provisions in force, with no exception, being furthermore liable for eviction pursuant to the APPLICABLE LAW”).

753 Statement of Claim, ¶ 194.

Page 171: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

166

that Bolivia breached this standard, which not even Claimant can precisely identify, by

breaching other provisions of the Treaty.

559. This position is incorrect. It should come as no surprise that it is incorrect, given that not even

Claimant considers itself capable of articulating the precise legal obligation that Bolivia

supposedly breached. In fact, the lack of any articulable legal standard that supports the claim

is so pronounced that Claimant is ultimately compelled to include a claim for breach of good

faith as the basis for claiming almost seven hundred million dollars in supposed damages.754

560. Because the FET and impairment claims are nothing more than repetition, Bolivia only

addresses these separately out of an abundance of caution. However, Bolivia satisfied

Claimant’s legitimate expectations, such as they were (Section 6.3.1), acted with full

transparency, predictability, and due process in the Smelter reversions (Section 6.3.2),

conducted itself in good faith regarding the Colquiri Mine (Section 6.3.3), and was not

administratively negligent during the negotiations (Section 6.3.4). As Claimant has failed to

make any distinct allegations concerning impairment of its investment, Bolivia’s response to

the impairment clause claim is incorporated into its response to the FET claim.755

6.3.1 Bolivia Satisfied Glencore Bermuda’s Legitimate Expectations At All Times

561. Claimant claims that Bolivia breached its legitimate expectations by (i) allegedly

expropriating its investment contrary to the applicable requirements, including for

compensation,756 (ii) allegedly committing actions contrary to the Bolivian investment law,757

and (iii) allegedly failing to protect the Colquiri Mine from the cooperativistas contrary to the

Colquiri Mine Lease.758

562. Not a single one of these supposed breaches of legitimate expectations in fact occurred.

Claimant has not put forward a scrap of evidence that it held any expectations of the sort it

claims to have been violated. It has no testimony or documentation to this effect from any

employee or director of Glencore Bermuda. (Mr. Eskdale was not affiliated with Glencore

Bermuda; only with Glencore International).

754 Statement of Claim, ¶ 194 et seq.

755 Statement of Claim, ¶ 193.

756 Statement of Claim, ¶ 214.

757 Statement of Claim, ¶ 215.

758 Statement of Claim, ¶ 216.

Page 172: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

167

563. To the contrary, Claimant in fact expected that Bolivia would act precisely as Claimant has

alleged in this arbitration. The Minnotte tribunal observed that “an international business

operator” such as Glencore International must be “deemed to be a competent professional

[…].”759

564. Glencore International was very familiar with Bolivia and the political context in which it

acquired Assets. It had extensive experience with the country from the 1990s when it

presented its credentials and was preselected to participate in former President Sánchez de

Lozada’s capitalization process.760 This was only natural given that Glencore International

founder Marc Rich became a Bolivian citizen in 1983761 and thereafter carried out business in

Bolivia in the country, including with his close friend Sánchez de Lozada.762

565. We understand that Glencore International took out political risk insurance against the risks

it expected could affect the Tin Smelter from a syndicate led by Lloyd’s.763 We suspect that

it similarly took out political risk insurance for the Antimony Smelter and Colquiri Mine

Lease. These are not the actions of a company that had, much less relied on, the expectations

that Claimant now claims.

566. It is black letter law that there can be no FET breach on the basis of expectations unless the

investor relied on those expectations when it made its investment. As the Crystallex tribunal

recently held, “[a] legitimate expectation may arise in cases where the Administration has

made a promise or representation to an investor as to a substantive benefit, on which the

investor has relied in making its investment, and which later was frustrated by the conduct of

the Administration.”764 This holding is in no way controversial. It reiterates a principle long

established in cases such as OKO Pankki Oyj v. Estonia,765 Cargill v. Poland,766 and Micula

759 David Minnotte and Robert Lewis v. Republic of Poland, ICSID Case No. ARB(AF)/10/1, Award of 16 May 2014,

RLA-17, ¶ 194.

760 N.M. Rotschild & Sons Limited, Capitalization of E.M. Vinto and transfer of operating control over COMIBOL

properties to private sector initiative, R-102, p. 1779.

761 Supreme Resolution No. 198045 of 27 May 1983, R-173.

762 House Report No. 454, “Justice Undone - Clemency Decisions in Clinton White House”, US Congressional Serial Set

(Serial No. 14778), 107th Congress, 2nd session, R-174, p. 124.

763 Section 2.5.4 above.

764 Crystallex International Corporation v Bolivarian Republic of Venezuela (ICSID Case No ARB(AF)/11/2) Award of 4

April 2016, CLA-130, ¶ 547 (emphasis added).

765 OKO Pankki Oyj and others v. Republic of Estonia, ICSID Case No. ARB/04/6, Award of 19 November 2007, RLA-

79, ¶ 247

766 Cargill, Incorporated v. Republic of Poland, ICSID Case No. ARB(AF)/04/2, Award of 29 February 2008, RLA-80, ¶

459.

Page 173: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

168

v. Romania.767 Absent such reliance when making an investment, any expectations of the

investor would have had no effect and any actions contrary to them would have caused no

harm.

567. The complete failure to provide any evidence of actual expectations or reliance is fatal to each

of Claimant’s legitimate expectations claims. The analysis can and should stop here.

However, each of Claimant’s three legitimate expectations claims suffer from individually

decisive flaws as well.

568. First, Claimant alleges that “Glencore Bermuda had a legitimate expectation that, should

Bolivia wish to take over its investments, it would provide Glencore Bermuda with just

compensation” and “would comply with all other requirements under domestic law and basic

principles of due process.”768

569. Claimant’s allegation goes nowhere. It is nothing more than an overt repackaging of its

allegation that Bolivia expropriated its investment in breach of the Treaty. Bolivia has already

explained at length why it did not expropriate Claimant’s so-called investment, much less in

breach of any applicable requirements.769 These arguments dispose of Claimant’s allegation

here as well.

570. Second, Claimant alleges that “Glencore Bermuda’s legitimate expectations were derived

from the Colquiri Lease” and that “Bolivia violated those expectations when it failed to

protect the Colquiri Mine from the invasion of the cooperativistas […].”770

571. As with the prior allegation, this one is equally a plain repackaging of Claimant’s umbrella

clause claim that Bolivia provided insufficient protection to the Colquiri Mine. Bolivia has

already explained why the Colquiri Mine Lease is not covered by the umbrella clause (or,

mutatis mutandis, the FET clause) and why it complied with all protection obligations in that

Lease. These explanations provide more than sufficient grounds to reject this allegation as

well.

572. However, Claimant’s allegation here also rests on a fundamental misunderstanding of

investment law. A contract, such as the Colquiri Mine Lease, cannot give rise to any

legitimate expectations. Thus, even if Bolivia had acted contrary to the Mine Lease,

767 Ioan Micula and others v Romania (ICSID Case No ARB/05/20) Award of 11 December 2013, CLA-119, ¶ 672.

768 Statement of Claim, ¶ 214.

769 Section 6.1 above.

770 Statement of Claim, ¶ 216.

Page 174: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

169

nevertheless there would be no breach of Claimant’s legitimate expectations or the FET

provision of the Treaty.

573. The reason is simple. As Prof. Christoph Schreuer explained, if contracts could give rise to

legitimate expectations, “the FET standard would be nothing less than a broadly interpreted

umbrella clause. […] It cannot be assumed that the umbrella clause adds nothing to the FET

standard.”771 The umbrella clause must have some effect, so the FET provision cannot protect

contractual expectations.

574. Consistent with Prof. Schreuer’s view, the SAUR tribunal held that mere breaches of

contractual expectations do not violate the FET provision. As it explained, “[q]ue un Estado

esté incurriendo en incumplimiento de sus propias leyes o contratos no constituye ni

condición necesaria ni suficiente para que se entienda violado el estándar iusinternacional

de TJE o de PPS.”772 SAUR is part of a long line of similar decisions, including those of the

Parkerings,773 Hamester,774 Bayindir,775 and Impregilo776 tribunals.

575. In fact, Claimant’s own lead authority on legitimate expectations, the Bayindir tribunal,777

reached the same conclusion. It held that, “because a treaty breach is different from a contract

violation, the Tribunal considers that the Claimant must establish a breach different in nature

from a simple contract violation, in other words one which the State commits in the exercise

of its sovereign power.”778

576. Thus, as a mere repetition of prior arguments that also relies on inadmissible contractual

expectations, the allegations based on the Colquiri Mine Lease should be rejected.

771 C. Schreuer, “Fair and Equitable Treatment (FET): Interactions with Other Standards”, in C. Ribeiro (ed.), Investment

Protection and the Energy Charter Treaty, 2008, RLA-81, pp. 89-90.

772 SAUR International SA v. The Republic of Argentina, ICSID Case No. ARB/04/4, Decision on Jurisdiction and Liability

of 6 June 2012, RLA-82, ¶ 483 (Unofficial translation: “[t]he fact that a State is failing to comply with its own laws or

contracts is not a necessary or sufficient requirement to consider that the international standard of FET or FPS has

been violated”).

773 Parkerings-Compagniet AS v. Republic of Lithuania, ICSID Case No. ARB/05/8, Award of 11 September 2007, RLA-

83, ¶ 344.

774 Gustav F W Hamester GmbH & Co KG v. The Republic of Ghana, ICSID Case No. ARB/07/24, Award of 18 June 2010,

RLA-84, ¶¶ 334-337.

775 Bayindir Insaat Turizm Ticaret Ve Sayani AŞ v Islamic Republic of Pakistan (ICSID Case No ARB/03/29) Award of 27

August 2009, CLA-90, ¶ 180.

776 Impregilo SpA v Argentine Republic (ICSID Case No ARB/07/17) Award of 21 June 2011, CLA-105, ¶ 294.

777 Statement of Claim, ¶ 200.

778 Bayindir Insaat Turizm Ticaret Ve Sayani AŞ v Islamic Republic of Pakistan (ICSID Case No ARB/03/29) Award of 27

August 2009, CLA-90, ¶ 180.

Page 175: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

170

577. Third, Claimant alleges that “Glencore Bermuda’s investment was further based on a legal

framework which provided for basic guarantees to foreign investors, consisting of, inter alia,

the Investment Law […].”779

578. Despite the allegation, Claimant fails to explain in what way it believes that its expectations

stemming from the Investment Law have been breached. It leaves this as a bare allegation

without providing any factual allegations at all in support. This empty allegation should be

given short shrift.

579. But even if it were substantiated by facts, the allegation is fundamentally flawed. Legitimate

expectations cannot arise from general legislation such as the Investment Law. Instead, they

arise only when the state makes specific undertakings or representations to the foreign

investor. This was the conclusion of the recent Philip Morris v. Uruguay tribunal:

It clearly emerges from the analysis of the FET standard by investment tribunals that

legitimate expectations depend on specific undertakings and representations made by

the host State to induce investors to make an investment. Provisions of general

legislation applicable to a plurality of persons or of category of persons, do not create

legitimate expectations that there will be no change in the law.780

580. This conclusion confirms that of a number of earlier tribunals, including ECE v. Czech

Republic and PSEG v. Turkey, that legitimate expectations arise only from specific assurances.

ECE held that, “[f]οr a claimant’s expectations to qualify in this sense, however, they must

normally be based οn specific assurances given by the competent authorities to the investor

prior to or at the time of the making of the investment.”781 PSEG, in turn, held that

“[l]egitimate expectations by definition require a promise of the administration on which the

Claimants rely to assert a right that needs to be observed.”782

581. Agreeing with these conclusions, Crystallex explained why general legislation cannot give

rise to legitimate expectations. In its view, “[t]o be able to give rise to such legitimate

779 Statement of Claim, ¶ 215.

780 Philip Morris Brand Sàrl, Philip Morris Products S.A. and Abal Hermanos S.A. v. Oriental Republic of Uruguay, ICSID

Case No. ARB/10/7, Award, RLA-43, ¶ 426.

781 ECE Projektmanagement International GmbH and Kommanditgesellschaft PANTA Achtundsechzigste

Grundstücksgesellschaft mbH & Co v. The Czech Republic, PCA Case No. 2010-5, Award of 19 September 2013, RLA-

85, ¶ 4.762.

782 PSEG Global Inc and Konya Ilgin Elektrik Üretim ve Ticaret Limited Şirketi v Republic of Turkey (ICSID Case No

ARB/02/5) Award of 19 January 2007, CLA-66, ¶ 241.

Page 176: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

171

expectations, such promise or representation – addressed to the individual investor – must be

sufficiently specific, i.e. it must be precise as to its content and clear as to its form.”783

582. However, general legislation is not precise as to its content and clear as to its form because it

leaves discretion to the state and is rarely unconditional. As the Crystellex tribunal explained,

“[l]aws are general and impersonal in nature; they will usually leave some degree of

discretion to the state agencies for the making of their case specific decisions and, in fact, are

rarely unconditional in their provisions so that the investor would have difficulty founding an

actual expectation akin to a vested right.” 784

583. The Investment Law itself displays the exact lack of precision and clarity that impedes the

formation of legitimate expectations. The provisions of the Investment Law are abstract, not

suggesting with any precision or clarity what they require or how they could be breached.

This is likely why Claimant cannot make any specific allegation of how its supposed

expectations from the Investment Law were violated. All it can do is assert that “the

Investment Law provided certain guarantees […] in relation to property rights, imports and

exports, production and marketing and investment insurance.”785 It gives no explanation of

how the Law affected its expectations or how Bolivia might have acted contrary to those

supposed expectations.

584. Thus, Claimant’s empty allegation based on non-existent expectations from the Investment

Law should be summarily dismissed.

6.3.2 Bolivia Acted Transparently, Predictably, And With Respect For Due Process

585. Claimant alleges that “Bolivia also failed to provide a transparent and predictable framework

to Glencore Bermuda and its investments, violating Glencore Bermuda’s due process

rights.”786 It asserts that these supposed requirements were breached because (i) “the Tin

Smelter and Antimony Smelter nationalizations were carried out under the pretext of alleged

illegalities related to the assets’ privatization,”787 (ii) “the Antimony Smelter Nationalization

Decree provided that the expropriation was carried out because of the “productive inactivity”

783 Crystallex International Corporation v Bolivarian Republic of Venezuela (ICSID Case No ARB(AF)/11/2) Award of 4

April 2016, CLA-130, ¶ 547.

784 Crystallex International Corporation v Bolivarian Republic of Venezuela (ICSID Case No ARB(AF)/11/2) Award of 4

April 2016, CLA-130, ¶ 552.

785 Statement of Claim, ¶ 215.

786 Statement of Claim, ¶ 217.

787 Statement of Claim, ¶ 217.

Page 177: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

172

of the asset,”788 and (iii) “[t]he government also exceeded the scope of the Antimony Smelter

Nationalization Decree when it seized the Tin Stock.”789

586. Claimant’s allegations that Bolivia breached due process and transparency and predictability

are wrong.

587. First, Claimant’s due process claim is entirely misguided as a matter of law. As Claimant

admits, due process requires only “the need to give an investor a reasonable chance (within

a reasonable timeframe) to claim its legitimate rights and have its claims heard.”790 Bolivia

satisfied this requirement by making available its courts to challenge the smelter reversions

as well as by making available international investment arbitration.791 It was Claimant’s own

choice not to pursue its available avenues of recourse for almost ten years.

588. In any event, the errors in the due process claim were addressed more fully above; restating

the same complaint twice does not make Claimant’s case any more convincing.792

589. Second, the transparency and predictability allegation is equally fallacious.793 Bolivia acted

transparently and predictably in the reversion of the smelters. Bolivia reverted the smelters

for precisely the reasons that it stated in the reversion decrees: The Tin Smelter was reverted

because of the illegalities in its privatization while the Antimony Smelter was reverted

because it was sitting idle, contrary to the contractual terms of its privatization.

590. As Claimant is “deemed to be a competent professional,”794 these grounds for the reversions

should have been obvious to Claimant from the time it received its so-called investments in

Bolivia for two reasons.

591. One, it was well-known that government officials, and especially representatives of the MAS

party, had observed serious irregularities in the privatization of the Tin Smelter. The MAS

members of the parliament had formally demanded the resignation of Chancellor Carlos

788 Statement of Claim, ¶ 218.

789 Statement of Claim, ¶ 218.

790 Statement of Claim, ¶ 209.

791 Section 2.1.2.2 above.

792 Section 6.1.2.2 above, see Statement of Claim, ¶ 169 et seq. and again ¶ 206 et seq.

793 Statement of Claim, ¶¶ 218-219.

794 David Minnotte and Robert Lewis v. Republic of Poland, ICSID Case No. ARB(AF)/10/1, Award of 16 May 2014,

RLA-17, ¶ 194.

Page 178: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

173

Saavedra Bruno due to illegalities in sale of Vinto while serving as Foreign Trade Minister.795

And Evo Morales himself, future president of Bolivia, was one of the principal voices from

the MAS party calling for the resignation.796

592. Two, it was also well known that the regulations for privatization as well as the Antimony

Smelter contract required the private owner to invest in and strengthen the smelter. The legal

regulation for the privatization process established the objective of increasing “la producción,

las exportaciones, el empleo y la productividad.”797 As the Terms of Reference for the

Antimony Smelter tender —incorporated into the final contractual terms798— explain, the

Smelter was privatized specifically to guarantee production, with the concomitant economic

benefits. Its text states:

La Licitación tiene por objeto la transferencia a título oneroso de los Activos y

Derechos de la fundición de antimonio de la Empresa Metalúrgica Vinto, en favor de

una empresa especializada con capacidad económica, financiera y técnica, que

permita el ingreso de capital, tecnología, prácticas comerciales y de gestión privada,

posibilitando a la Fundición continuar la producción, constituyéndose en una fuente

de generación de empleo y tributos, en apoyo a la actividad minera de explotación y

concentración de antimonio en el país.799

593. The reversion of the smelter was grounded in the failure to fulfill this fundamental object and

purpose of the privatization process: ensuring the productive activity of the smelter. As the

reversion decree clearly states:

en los últimos años se evidenció la inactividad productiva de la Planta Metalúrgica

Vinto Antimonio, asi como su desmantelamiento, no obstante haberse estipulado en el

pliego de condiciones las obligaciones de invertir y fortalecer la Empresa Metalúrgica

Vinto Antimonio con capacidad económica, financiera y técnica, que permita el

ingreso de capital, tecnología, prácticas comerciales y gestión privada, posibilitando

a la Fundición continuar la producción, constituyéndose en una fuente de generación

795 La Razón Digital, El MAS pide la renuncia del Canciller Saavedra, press article of 8 November 2002, R-134; El Diario,

MAS pide la renuncia del Canciller de la Republica, press release of 4 December 2002, R-135.

796 El Mundo, MAS presentó las pruebas de corrupción contra Canciller, press release of 4 December 2002, R-136;

797 Supreme Decree No. 23.991 of 10 April 1995, R-100, Art. 2(c) (Unofficial translation: “production, exports,

employment and productivity”).

798 Notarization of the sale and purchase agreement of the Vinto Antimony Smelter between the Ministry of External Trade

and Investment, Comibol, Empresa Minera Colquiri and Compañía Minera Del Sur SA of 11 January 2002, C-9, 23(1),

p. 21.

799 Terms of Reference for the Second Public Tender for the Antimony Smelter of 31 July 2000, R-109, p. 9 (Unofficial

translation: “[t]he Bid’s object is to transfer in exchange for consideration the Assets and Rights of the Antimony Smelter

of the Vinto Metallurgical Company to a specialized company with economic, financial and technical capacity, that will

allow the inflow of capital, technology, commercial practices and private management, permitting the Smelter to

continue production, becoming a source for the generation of employment and tax, in support of the mining activity of

exploitation and concentration of antimony in the country”).

Page 179: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

174

de empleo, tributos y externalidades en apoyo a la actividad minera de explotación y

concentración de antimonio en el país.800

594. Claimant freely admits that the Antimony Smelter was in fact inactive and that Claimant had

not brought it back into production.801 Nor does it deny that the object and purpose of the

Antimony Smelter privatization contract was to ensure the productive activity of the smelter.

Instead, it simply complains that Bolivia failed to ask it to fulfill the contractual purpose

associated with the Smelter.802 But this does not change the fact that the Reversion Decree

was transparent about its reasons, and that these reasons were predictable from the terms of

the privatization contract.

595. Thus, both the Tin Smelter and Antimony Smelter reversions were transparent and

predictable. They were taken for exactly the reasons described in the corresponding decrees,

reasons that were long known to Claimant.

596. However, even if a potential regulatory action is not transparent or predictable to an investor

at the outset, a state is nevertheless permitted to take regulatory actions in the public interest.

This was the conclusion of the recent Urbaser tribunal: “The fair and equitable treatment does

not provide for a standard according to which the investor would remain completely isolated

and immune from the host State’s endeavors to deal with such situations in complying with

public interests.”803 As the Urbaser tribunal reasoned, the investor has to expect the state to

address any problems that arise during the course of the investment. It explained that “[t]he

investor is and must be aware of the State’s commitment to deal with situations and problems

that may emerge over the time and were impossible to anticipate.”804

597. The expectation that novel problems might arise during the course of the investment is

particularly strong when circumstances indicate that legal change is likely. The Parkerings

tribunal observed that, because, “legislative changes, far from being unpredictable, were in

fact to be regarded as likely,” it was the case that, “as any businessman would, the Claimant

800 Supreme Decree No 499 of 1 May 2010, C-26, p. 2 (Unofficial translation: “In recent years, the inactivity of the

Metallurgical Company Vinto Antimonio became obvious, as well as its dismantling, notwithstanding that the terms of

reference provided for the obligation to invest in and reinforce the Metallurgical Company Vinto Antimonio with

economic, financial and technical capacity, that would allow the inflow of capital, technology, commercial practices

and private management, permitting the Smelter to continue production, becoming a source for the generation of

employment and tax, in support of the mining activity of exploitation and concentration of antimony in the country”).

801 Statement of Claim, ¶ 218.

802 Statement of Claim, ¶ 218.

803 Urbaser S.A. and Consorcio de Aguas Bilbao Biskaia, Bilbao Biskaia Ur Partzuergoa v. The Argentine Republic, ICSID

Case No. ARB/07/26, Award of 8 December 2016, RLA-86, ¶ 628.

804 Urbaser S.A. and Consorcio de Aguas Bilbao Biskaia, Bilbao Biskaia Ur Partzuergoa v. The Argentine Republic, ICSID

Case No. ARB/07/26, Award of 8 December 2016, RLA-86, ¶ 628.

Page 180: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

175

was aware of the risk that changes of laws would probably occur […].” 805 On this basis, it

held that, “in such a situation, no expectation that the laws would remain unchanged was

legitimate.”806 This position was affirmed by Mamidoil v. Albania807 and Toto v. Lebanon.808

598. Just as in those cases, Claimant made its so-called investment precisely at a moment where

the political regime and economy in Bolivia were in the midst of a period of transition. The

Sánchez de Lozada government had fallen. The MAS party, with its very different political

and economic policies, was on the ascendency and was likely to take the presidency in the

next election. Claimant should have predicted that Bolivia would address regulatory issues

differently in the immediate future than it had in the past.

599. To avoid the inconvenient fact that it invested at a moment of political change when it already

had notice of the grounds for the reversions, Claimant cites to Gold Reserve. But Gold

Reserve is straightforwardly inapposite. Gold Reserve concerns a situation where the state

had ulterior motives for its actions. To see this, we need not look further than Claimant’s own

characterization of the Gold Reserve award: “the reasons for the cancellation were not limited

to those officially stated by the Ministry, but, rather, were to be found in ‘the change of

political priorities of the Administration […] taken regarding mining of mineral reserves

starting in late 2007 by the highest levels of authority.’”809 Claimant has not proven, much

less provided any evidence, that Bolivia had reasons for the reversions other than those stated

in the official decrees.

600. Thus, Claimant has failed to make out, much less prove, its allegations that Bolivia breached

due process and transparency and predictability.

6.3.3 Bolivia Acted In Good Faith When Intervening At The Colquiri Mine And When Issuing

The Reversion

601. Claimant alleges that Bolivia breached the FET provision because “the nationalization of

Colquiri was the result of Bolivia’s inaction and bad faith.”810 In support of this conclusory

805 Parkerings-Compagniet AS v. Republic of Lithuania, ICSID Case No. ARB/05/8, Award of 11 September 2007, RLA-

83, ¶ 335, also ¶¶ 327-338.

806 Parkerings-Compagniet AS v. Republic of Lithuania, ICSID Case No. ARB/05/8, Award of 11 September 2007, RLA-

83, ¶ 335, also ¶¶ 327-338.

807 Mamidoil Jetoil Greek Petroleum Products Societe Anonyme S.A. v. Republic of Albania, ICSID Case No. ARB/11/24,

Award of 30 March 2015, RLA-74, ¶ 623.

808 Toto Costruzioni Generali S.p.A. v. Republic of Lebanon, ICSID Case No. ARB/07/12, Award of 7 June 2012, RLA-

76, ¶ 245.

809 Statement of Claim, ¶ 207.

810 Statement of Claim, ¶ 219.

Page 181: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

176

allegation, it advances two arguments, both of which are redundant, and neither of which

explains why Bolivia’s conduct would have amounted to bad faith.811

602. As an initial matter, Claimant does not attempt to explain how its allegations, even if true,

would evidence behaviour contrary to good faith. It does not even propose a legal standard

of good faith. This is because, as the ICJ has repeatedly held, good faith “is not in itself a

source of obligation where none would otherwise exist.”812 Thus, Claimant’s claim for breach

of good faith must be summarily rejected.

603. However, even if it were not, Claimant is unable to show that Bolivia acted in bad faith

through either of the two repetitive arguments it advances.

604. First, Claimant asserts that “Bolivia first failed to respond to Glencore Bermuda’s requests

for assistance, thus failing to protect the Colquiri Mine from the unlawful and violent

interference of the cooperativistas […].”813 This is nothing more than yet another repackaging

of Claimant’s allegation about an FPS breach, which Bolivia has already rebutted at length.814

In short, Bolivia took all the measures that were legal and reasonable under the difficult

circumstances of the Colquiri Mine dispute.

605. Second, Claimant asserts that “once the conflict with the cooperatives was resolved, Bolivia

still decided to nationalize the Colquiri Mine.”815 This repackages Claimant’s allegations

about the need for the expropriation, allegations that Bolivia has also already debunked in

detail.816 Simply put, it is not true that the conflict was resolved at the time of the reversion;

it was the reversion that put an end to the dispute.

606. No matter how much Claimant wishes it were so, adding together two erroneous arguments

does not equal a sound argument for bad faith. Claimant’s bad faith allegations should be

rejected.

811 Statement of Claim, ¶¶ 219-220.

812 Case concerning border and transborder armed actions (Nicaragua v. Honduras), ICJ, Jurisdiction of the Court and

Admissibility of the Application, Judgment of 20 December 1988, RLA-87, ¶ 94. See also Case concerning the land

and maritime boundary between Cameroon and Nigeria (Cameroon v. Nigeria), ICJ, Preliminary Objections, Judgment

of 11 June 1998, RLA-88, ¶ 59.

813 Statement of Claim, ¶ 219.

814 Section 6.2 above.

815 Statement of Claim, ¶ 219.

816 Section 6.1 above.

Page 182: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

177

6.3.4 Claimant’s Allegation Of Administrative Negligence And Inconsistency Is Legally And

Factually Vacuous

607. Claimant argues that “Bolivia’s handling of the negotiations with Glencore Bermuda since

2007 evidences ‘serious administrative negligence and inconsistency,’ since it subjected

Glencore Bermuda to a ‘roller-coaster’ ride.”817 Of course, Glencore Bermuda never

negotiated with Bolivia, only Glencore International did. And Claimant proposes that the

applicable legal standard for those negotiations is a “roller-coaster ride.” The Tribunal

should not find a breach of international law on account of a so-called “roller-coaster ride.”

This is not a serious claim and should be dismissed out of hand.

608. Nor do the facts support the existence of any Treaty breach. Following the reversions, Bolivia

carried out the difficult negotiations appropriately and consistently. Claimant’s own decision

to wait almost ten years after the Tin Smelter reversion and almost five years after the Colquiri

Mine Lease reversion to file this arbitration attest to that fact. In fact, Claimant’s primary

complaint about the negotiations is that Bolivia did not give it what it wanted, nothing more.818

But this is an unremarkable feature of any unsuccessful negotiation. So, although Claimant

may have been unsatisfied with the outcome of the negotiations, that dissatisfaction is not a

fair and equitable treatment breach.

609. And these facts bear no resemblance to those underlying the PSEG v. Turkey decision, on

which Claimant places primary reliance for this claim.819 As the PSEG tribunal concluded,

the breach consisted of “continuing legislative claims [such as] the requirements relating, in

law or practice, to the continuous change in the conditions governing the corporate status of

the Project, and the constant alternation between private law status and administrative

concessions that went back and forth.”820 The negotiations between Claimant and Bolivia did

not take place against a background of constant legal change, rendering the conclusions of the

PSEG tribunal entirely irrelevant.

610. Nor would this change had Claimant invoked Saluka in connection to the negotiations

(although it only mentions it as relevant to transparency).821 The Saluka tribunal held that

“[t]he Czech Government failed to deal with IPB and its shareholder Saluka/Nomura, on the

817 Statement of Claim, ¶ 221.

818 Statement of Claim, ¶ 221.

819 Statement of Claim, ¶ 221.

820 PSEG Global Inc and Konya Ilgin Elektrik Üretim ve Ticaret Limited Şirketi v Republic of Turkey (ICSID Case No

ARB/02/5) Award of 19 January 2007, CLA-66, ¶ 250.

821 Statement of Claim, ¶ 202.

Page 183: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

178

one hand, and CSOB, on the other hand, in an unbiased and even-handed way […].”822

Building on this holding, the tribunal concluded that the bias against the investor manifested

itself in a lack of transparency and a refusal of adequate communication.823 By contrast,

Claimant has not alleged bias or a lack of even-handedness, and it cannot: in whose favor

would Bolivia have been biased? Thus, Saluka too is irrelevant to this dispute.

611. In short, Claimant’s allegation of an FET breach connected to the negotiations goes nowhere.

It is based on a farcical legal standard, lacks factual support, and is contrary to the authorities

that Claimant invokes to support it.

7. IF THE TRIBUNAL WERE TO CONSIDER THAT IT HAS JURISDICTION OVER

THIS DISPUTE AND THAT BOLIVIA BREACHED THE TREATY (QUOD NON), IT

SHOULD, NONETHELESS, FIND THAT CLAIMANT’S CLAIMED DAMAGES

ARE HIGHLY SPECULATIVE AND UNCERTAIN AND THAT, IN ANY EVENT,

ITS VALUATIONS ARE HYPOTHETICAL AND FLAWED

612. Claimant’s case on quantum appears to rest on the hope that, by inflating its damages claim

to an outrageous US$ 675.7 million (including interest), it will somehow lay the groundwork

for the Tribunal to compromise on a slightly lesser, yet still grossly inflated damages award.

This approach makes a mockery of the relevant standards of compensation and damages under

the Treaty and international law.

613. Claimant’s mockery of the relevant standards of compensation leads to a grossly inflated

damages claim. Claimant is aware of this, as shown by the fact that, in March 2005, it

implicitly valued all of the Assets (i.e., the Mine, the Tin Smelter and the Antimony Smelter)

at US$ 9,900,990.824 Indeed, in March 2005, Glencore International purchased from CDC

Group Plc. 24.34% of Colquiri’s shares825 (Colquiri was the owner of all the Assets at the

time) for US$ 2,410,581.70.826 Simple mathematics show that, to Glencore International, the

implicit value of 100% of Colquiri’s shares was US$ 9,900,990. This is 40 times less than

what Claimant is claiming for the same Assets in this arbitration (excluding the Tin Stock and

interests).827

614. In calculating the lost value of the operating Assets, Claimant has not calculated their fair

market value (“FMV”) and has misrepresented the impact of the relevant variables. Claimant

822 Saluka Investments BV v Czech Republic (UNCITRAL) Partial Award of 17 March 2006, CLA-62, ¶ 407.

823 Saluka Investments BV v Czech Republic (UNCITRAL) Partial Award of 17 March 2006, CLA-62, ¶¶ 420-432.

824 Econ One, ¶ 16.

825 Share register of Colquiri SA, C-17, p. 4.

826 Put and Call Agreement between CDC and Glencore International of 15 March 2005, C-65.

827 Statement of Claim, ¶ 295; Econ One, Footnote 10.

Page 184: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

179

adopts exaggerated and implausible scenarios for each of the variables of its discounted cash

flow (“DCF”) method valuations. It suffices to consider the historical operating performance

of the operating Assets to see how arbitrary and speculative Claimant’s valuations are. In the

case of the Mine, while during the seven years leading up to the valuation date its Earnings

Before Interest Taxes Depreciation and Amortization (“EBITDA”) ranged between US$ 10

million to US$ 42 million, Claimant’s damages claim assumes that such EBIDTA would have

been approximately 5 times higher during the next 18 years (2012 – 2030):828

615. Similarly, in the case of the Tin Smelter, while its EBIDTA ranged between US$ 0.4 million

to US$ 14.7 million for the 7 years leading up to the valuation date, Claimant’s damages claim

assumes that such EBIDTA would have been approximately 3 times higher during the next

20 years (2007 – 2026):829

828 Econ One, Figure 1.

829 Econ One, Figure 7.

Page 185: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

180

616. Claimant’s valuations are entirely speculative and fail to establish any damage sufficiently

certain to warrant compensation under international law (Section 7.1). Even if the damages

sought by Claimant for the Mine and the Tin Smelter were certain (quod non), those damages

were not caused by Bolivia but rather by Claimant’s own acts (Section 7.2). Claimant’s

valuations are flawed and grossly inflated (Section 7.3), and so its interest claim (Section

7.4). Were the Tribunal to award damages to Claimant for the Mine and the Tin Smelter

(quod non), it must take into account Claimant’s contribution to its loss to substantially reduce

any recovery (Section 7.5).

7.1 Claimant’s Valuations Are So Speculative That Claimant Has Failed To Establish Any

Damage Sufficiently Certain To Warrant Compensation Under International Law

617. It is a settled principle of international law that Claimant bears the burden of proving the

certainty of its alleged damages (Section 7.1.1). But because Claimant’s alleged damages are

premised on mere (and abusive) speculation, they are not certain enough to be compensated

under international law (Section 7.1.2).

7.1.1 Under International Law, It Is Claimant’s Burden To Prove Its Damages With Certainty

618. Although Claimant purports to lay out the “applicable standards for the assessment of

compensation,”830 it simply ignores the most basic standards of all. It does not explain that it

is Claimant’s burden to prove that its claimed damages are compensable and it does not

explain that only damages that are certain merit compensation. And it certainly does not

830 Statement of Claim, ¶ 227.

Page 186: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

181

explain that this standard of proof rules out compensation for future projects that have no

record of profits.

619. It is a well-established principle that a claimant bears the burden of proving the damages it

claims, regarding both the fact and the amount of the loss.831 The Crystallex tribunal recently

confirmed the consensus view that, “as a general matter, it is clear that it is the Claimant that

bears the burden of proof in relation to the fact and the amount of loss.”832 Similarly, the

Gold Reserve tribunal concluded that “Claimant bears the burden of proving its claimed

damages.”833

620. Restating customary international law, the International Law Commission’s Articles on State

Responsibility establish that compensation for losses must be proven with “sufficient certainty

to be compensable.”834 The Articles on State Responsibility further recognize, for any

damages claim, that “[t]ribunals have been reluctant to provide compensation for claims with

inherently speculative elements.”835

621. Unsurprisingly, almost all tribunals to pronounce on the issue have followed the Articles on

State Responsibility in demanding that losses be demonstrated with reasonable or sufficient

certainty.836 Amoco speaks for these tribunals when it reports that “[o]ne of the best settled

831 S. Ripinsky and K. Williams, Damages in International Investment Law, British Institute of International and

Comparative Law, 2008 (extract), RLA-89, p. 162 (“In the damages context, it is always the claimant who alleges that

it has suffered a loss as a result of the respondent’s conduct; therefore, the claimant bears the burden of proof in relation

to the fact and the amount of loss”) (emphasis added).

832 Crystallex International Corporation v Bolivarian Republic of Venezuela (ICSID Case No ARB(AF)/11/2) Award of 4

April 2016, CLA-130, ¶ 864;

833 Gold Reserve Inc v Bolivarian Republic of Venezuela (ICSID Case No ARB(AF)/09/1) Award of 22 September 2014,

CLA-123, ¶ 685.

834 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, Art. 36, comment 27 (“In cases

where lost future profits have been awarded, it has been where an anticipated income stream has attained sufficient

attributes to be considered a legally protected interest of sufficient certainty to be compensable.”); M. Whiteman,

Damages in International Law, vol. III (1943), RLA-90, p. 1837; UNIDROIT Principles of International Commercial

Contracts (2010), RLA-91, Art. 7.4.3(1), CA-513; United Nations Compensation Commission, Governing Council

Decision 9 of 6 March 1992, RLA-92 ¶¶ 8, 19.

835 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, Art. 36, comment 27.

836 Amoco International Finance Corporation v Government of the Islamic Republic of Iran and others, Partial Award

(1987-Volume 15) Iran-US Claims Tribunal Report, CLA-10, ¶ 238; Ioan Micula and others v Romania (ICSID Case

No ARB/05/20) Award of 11 December 2013, CLA-119, ¶ 1008; Compañía de Aguas del Aconquija SA and Vivendi

Universal SA v Argentine Republic (ICSID Case No ARB/97/3) Award of 20 August 2007, CLA-70, ¶ 8.3.4; Mobil

Investments Canada Inc. and Murphy Oil Corporation v. Canada, ICSID Case No. ARB(AF)/07/4, Decision on

Liability and Principles of Quantum of 22 May 2012, RLA-93, ¶ 438; Archer Daniels Midland Company and Tate &

Lyle Ingredients Americas, Inc. v. United Mexican States, ICSID Case No. ARB(AF)/04/5, Award of 11 November

2002, RLA-94, ¶¶ 285-286; Gemplus SA and others v United Mexican States, and Talsud SA v United Mexican States

(ICSID Case Nos ARB(AF)/04/3 and ARB(AF)/04/4) Award of 16 June 2010, CLA-98, ¶¶ 12-56, 13-91; PSEG Global

Inc and Konya Ilgin Elektrik Üretim ve Ticaret Limited Şirketi v Republic of Turkey (ICSID Case No ARB/02/5) Award

of 19 January 2007, CLA-66, ¶ 310; Hassan Awdi, Enterprise Business Consultants, Inc. and Alfa El Corporation v.

Romania, ICSID Case No. ARB/10/13, Award of 2 March 2015, RLA-95, ¶ 514; AIG Capital Partners, Inc and CJSC

Page 187: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

182

rules on international responsibility of States is that no reparation for speculative or uncertain

damages can be awarded. This holds true for the existence of the damage and of its effect as

well.”837

622. For the avoidance of doubt, Bolivia is not suggesting that Claimant’s burden includes

establishing with a 100% certainty the exact amount of damages claimed. However, Claimant

must establish the existence of damages with reasonable certainty.838 The well-known

Chorzow decision established that “reparation must (…) reestablish the situation which

would, in all probability, have existed if that act had not been committed”839.

623. In this context, as the Mohammad Ammar Al-Bahloul tribunal rightly held, for an award of

future profits the claimant must prove that each condition on which its claim is premised

would more likely than not be fulfilled840; damages cannot be based on conjectures (“(…) the

assessment of damages cannot be based on conjecture or speculation. A persuasive factual

basis for the assessment must be shown”).841

624. In this respect, Claimant’s case grossly fails. Its entire damages case rests on a series of

assumptions about future operations that are highly speculative and unrealistic, thus resulting

in damages that are arbitrary and uncertain. A good example of this is Claimant’s valuation

of the Old Tailings Reprocessing Project, which represents over 30% of the damages claimed

by Claimant for Colquiri (i.e., more than US$ 100 million). Although no one has ever

operated this Project, Claimant’s experts’ value it based on the DCF method and assuming it

is a going concern with a proven record of profitability. Needless to say, this results in an

arbitrary and highly speculative valuation (all of the inputs used in the DCF valuation are

unsupported and were arbitrarily-chosen). As explained by the Caratube tribunal, “the DCF

method is widely accepted as an appropriate method to assess the lost profits of going

Tema Real Estate Company v Republic of Kazakhstan (ICSID Case No ARB/01/6) Award of 7 October 2003, CLA-45,

¶ 12.1.10. Cf., Anatolie Stati, Gabriel Stati, Ascom Group S.A. and Terra Raf Trans Traiding Ltd v. The Republic of

Kazakhstan, SCC Case No. V116/2010, Award of 19 December 2013, RLA-96, ¶ 1688 (requiring a “high standard of

proof”); Autopista Concesionada de Venezuela, CA v Bolivarian Republic of Venezuela (ICSID Case No ARB/00/5)

Award of 23 September 2003, CLA-44, ¶ 351.

837 Amoco International Finance Corporation v Government of the Islamic Republic of Iran and others, Partial Award

(1987-Volume 15) Iran-US Claims Tribunal Report, CLA-10, ¶ 238.

838 This is conceded by Glencore. In footnote 492 of its Statement of Claim, Glencore defines “going concern” as “an

enterprise consisting of income-producing assets which has been in operation for a sufficient period of time to generate

the data required for the calculation of future income and which could have been expected with reasonable certainty

(…)” (emphasis added).

839 Case Concerning the Factory at Chorzów (Germany/Poland) (Merits) [1928] PCIJ Series A, No 17, CLA-2 (emphasis

added).

840 Mohammad Ammar Al-Bahloul vs. Republic of Tajikistan, SCC Arbitration No. V(064/2008), Final Award, 8 June 2010,

RLA-97, ¶ 78. 841 Mohammad Ammar Al-Bahloul vs. Republic of Tajikistan, SCC Arbitration No. V(064/2008), Final Award, 8 June 2010,

RLA-97, ¶ 39.

Page 188: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

183

concerns with a proven record of profitability […].”842 Econ One further explains that “[t]he

purpose of requiring historical data for the implementation of a DCF analysis is to provide a

more reliable source of information for projecting future cash flows, than speculative plans

for operations that had never existed […].”843

625. There was not even certainty that Claimant would ever invest in the Old Tailings Reprocessing

Project (in fact, as discussed below, evidence suggests the opposite), which confirms why the

Tribunal should dismiss Claimant’s damages claim for this Project. A similar situation arose

in the Micula case, where claimants sought compensation for the lost profits they would have

derived from certain investments that were not made, allegedly, as a result of Romania’s

breach. The tribunal rejected the claim given that the facilities needed to generate the revenues

did not exist in their “complete, revenue-generating form” at the time of Romania’s breach

(and even though, in that case, claimants had submitted proof of their intention to complete

those facilities). The Micula tribunal concluded that “Claimants have failed to prove with

sufficient certainty that they would have indeed implemented the Incremental Investments that

serve as the basis for this lost profits claim.”844 In the present case, no facilities were built by

Claimant for the development of the Old Tailings Reprocessing Project, and there is no

evidence that Claimant would have implemented this Project.

626. The Tribunal cannot compensate Claimant for lost future profits which are based on

unsubstantiated assumptions (and thus speculative). As the Murphy tribunal explained, “[to

award uncertain profits] would not place Claimant in the position that it would have been in

but-for the wrongful act. Such a ruling would replace what was an uncertain future with a

particular outcome too far removed from the ‘but-for’ hypothetical.”845

627. Thus, it is Claimant’s burden to prove with certainty all elements of the alleged losses

underpinning its damages claims.

842 Caratube International Oil Company LLP and Mr. Devincci Salah Hourani v. Republic of Kazakhstan, ICSID Case No.

ARB/13/3, Award of 27 September 2017, RLA-98, ¶ 1094 (emphasis added).

843 Econ One, ¶ 47.

844 Ioan Micula and others v Romania (ICSID Case No ARB/05/20) Award of 11 December 2013, CLA-119, ¶ 1065.

845 Murphy Exploration and Production Company International v. Republic of Ecuador [II], PCA Case No. 2012-16, Partial

Final Award of 6 May 2016, RLA-99, ¶ 485-487. The Murphy tribunal further recalled that “the general requirement

for awarding damages for violations of international obligations [is] that any compensable damage must not be too

speculative, remote, or uncertain.”

Page 189: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

184

7.1.2 Through Its Highly Speculative And Unrealistic Valuation, Claimant Has Not Proven

Its Damages Claims With Certainty

628. Claimant’s valuations of the Mine (Section 7.1.2.1), the Tin Smelter (Section 7.1.2.2) and the

Antimony Smelter (Section 7.1.2.3) are all premised on mere speculation and defy common

sense.

7.1.2.1 Compass Lexecon’s Valuation Of the Mine Is Premised On Mere Speculation

629. It is not uncommon for parties to international arbitration to disagree on how best to estimate

the exact FMV of an investment and, almost inevitably, the parties’ experts will submit

different views to tribunals. However, this case is not common in how far the Claimant’s

experts have gone into making assumptions (most likely on instruction from Claimant) that

are so far removed from reality that they appear to be valuing a “magical mine.”

630. Compass Lexecon’s valuation of the Mine relies on RPA’s analysis for the key value drivers,

namely production (key premise to calculate revenues) and costs.846 Yet, these parameters are

based on pure speculation and mere aspirations found on a single document dated July 2011,

i.e., almost a year before the Mine reverted to the State (the “Triennial Plan”),847 without any

other documentary support. Moreover, as the facts between July 2011 and mid-2012

demonstrate, said Triennial Plan was never even implemented.

631. A careful review of RPA’s analysis and Compass Lexecon’s valuation shows, at least, that:

632. First, their models are solely based on the Triennial Plan, without an independent assessment

of whether it was realistic, even less so whether a willing buyer would have taken it at face

value, which RPA and Compass Lexecon do.

633. Said Triennial Plan was nothing more than an unsupported conjecture and aspiration, as

demonstrated by the lack of any internal assessment of its economic viability (much less

investment approval), and was not even approved by Colquiri’s management. In fact, Eng

Moreira (the Mine’s Superintendent as of July 2011, when the Plan was allegedly prepared)

had not even seen the Triennial Plan relied upon by Claimant before this arbitration.848

Claimant’s submission is notably missing any internal approvals, any investment

authorizations, any authorization for expenditures, etc., in the more than 10 months that

846 Compass Lexecon Expert Report, ¶ 52.

847 2012-2014 Colquiri Mine Three-year Plan, C-108.

848 Moreira, ¶ 19.

Page 190: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

185

followed before the Mine Lease was reverted. What happened with this Plan after July 2011

is a mystery.

634. Second, Claimant’s experts’ valuations result in a “magical mine” where:

- Mineral resources are delineated and mineral reserves replenish without any need for the

operator to invest in exploration; they just “magically” appear. Per the last

reserves/resources estimate (as of 31 December 2011),849 allegedly performed prior to

the reversion of the Mine Lease (in mid-2012), all reserves and resources would have

been produced in 13.6 years with the then production levels.850 Yet RPA has no qualms

in projecting that, without any need to invest in exploration, the Mine would have

continued operating for another 20 years;851

- The processing plant’s production doubles in three years (from 289,888 tons in 2011 to

550,579 tons in 2014),852 and remains at that level until 2030853 (despite there not being

enough water or electricity to sustain such enormous production); and

- The Mine’s total production (i.e., production from Colquiri’s current processing plant and

from the new old tailings plant) moves from 1,000 tons per day (in 2012) to 5,000 tons

per day (in 2014), i.e., the Mine’s production grows by a multiple of 5 in three years854

(even though this is technically unfeasible and inconsistent with the chronic lack of

investment at Colquiri).

635. The combination of such an extraordinary and unrealistic increase in production with no

exploration investment grossly inflates Claimant’s claim.

636. In addition, in Claimant’s “magical mine”:

- Projects that take years to complete at a significant cost (such as a 2,500 m underground

ramp or a new plant) are approved, built and in operation in half a year during 2012 (to

justify the phenomenal production increases in the early years of the Compass Lexecon

model, so as to front-load the model) at very low or no cost;

849 Glencore Annual Report 2011, R-252, p. 72.

850 Econ One, ¶ 36.

851 RPA FBD Glencore v Bolivia Expert Report, ¶ 86.

852 RPA FBD Glencore v Bolivia Expert Report, ¶ 113, Table 3; Compass Lexecon Colquiri Valuation, CLEX-4,

“Revenues”.

853 RPA FBD Glencore v Bolivia Expert Report, ¶ 113. Compass Lexecon Colquiri Valuation, CLEX-4, “Revenues”.

854 Moreira, ¶ 18.

Page 191: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

186

- The additional tailings (resulting from increased production) “disappear” so that there is

no need to build a very costly and large new dam;

- The January-June 2012 production is achieved both before and after the reversion of the

Mine Lease855 (since RPA and Compass Lexecon make no allocation for production

already achieved by Colquiri in such months);

- Per Claimant’s experts, the Mine becomes a much more profitable venture from the very

moment the Mine Lease was reverted by the State (i.e., mid-2012) and for the next 17 ½

years. For instance:

Despite having to mine deeper and deeper,856 production costs become lower in

the future (because Colquiri would allegedly benefit from economies of scale).857

Yet, Colquiri has not benefited from economies of scale in its entire history,

including during Sinchi Wayra’s operation;858 and

Despite the fact that, in 2011 and the first half of 2012, metallurgical recoveries

at Colquiri were around 60% or less for both zinc and tin,859 Claimant’s experts

assume that metallurgical recoveries will average “72% for tin and 76% for zinc”

per year from 2012 until 2030.860 This is inconsistent with Colquiri’s operating

history and, more importantly, ignores the reality of the Mine (an underground

mine whose metallurgical recoveries will progressively decrease as mining

moves deeper into more sulfurous areas of the Mine and head grades decrease).861

637. Third, Claimant’s experts also assume that an Old Tailings Reprocessing Project (which

contributes over US$ 100 million to Colquiri’s value in their model) would have been

implemented shortly after the reversion of the Mine Lease (after having been abandoned for

8 years, i.e., since 2004). Yet, the economic viability of this Project is uncertain at best,862

and thus any value attributed to it is entirely speculative.

855 SRK, ¶ 54; Econ One, ¶ 19.

856 SRK, ¶¶ 14, 44.

857 RPA FBD Glencore v Bolivia Expert Report, ¶ 179.

858 Econ One, ¶ 75.

859 SRK, ¶ 48, Table 2.

860 RPA FBD Glencore v Bolivia Expert Report, ¶ 48.

861 Villavicencio, ¶ 69.

862 SRK, Section 8.2, ¶ 85; Moreira, ¶ 24.

Page 192: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

187

638. Such degree of speculation in RPA’s analysis and Compass Lexecon’s valuation are so far

from meeting the standard of proof for Claimant’s damages to be sufficiently certain that the

Tribunal should not hesitate in denying any compensation on this basis alone.

639. One, Claimant’s experts’ analysis is entirely premised on the Triennial Plan, without any

critical analysis or independent review (contrary to what a willing buyer would have done).863

This Plan, dated July 2011, forecasts a significant production increase both at the Mine and

the plant resulting from several future projects (such as the expansion of Colquiri’s processing

plant or a new main ramp). Aside from the fact that, as discussed in section 7.3.4.2 below,

this Plan’s assumptions and resulting forecasts are flawed, the Triennial Plan appears to be

nothing more than unsupported conjecture and aspiration. Indeed:

There are no internal approvals of the Triennial Plan, no investment authorizations,

no authorization for expenditures, etc., in the more than 10 months between the date

in which the Plan was allegedly prepared (July 2011) and the date in which the Mine

Lease was reverted (June 2012). There is no engineering for the projects forecasted

in the Plan either. What happened with this Plan after July 2011 is a mystery, yet

Claimant’s experts’ analysis is entirely premised on it;

As explained by Eng Moreira (the Mine’s Superintendent as of July 2011, when the

Triennial Plan was allegedly prepared), in August / September 2011 he met in La Paz

with Ms Maria Eugenia Aramayo to discuss and prepare Sinchi Wayra’s budget for

2012.864 At no point during these meetings they discussed about the Triennial Plan,

much less about the investments / projects forecasted in that Plan.865 Had the

Triennial Plan been approved or, as Claimant contends, had Colquiri been in the

process of implementing it, it would have been discussed at these meetings and

considered in Sinchi Wayra’s 2012 budget;866

As explained by Eng Moreira, until his involvement in this arbitration, he had never

seen or heard about the Triennial Plan submitted by Claimant.867 Had the Triennial

Plan been something serious, more than a mere aspiration, Eng Moreira would have

definitely been aware of its existence;

863 RPA FBD Glencore v Bolivia Expert Report, ¶ 13; Compass Lexecon Expert Report, ¶ 51.

864 Moreira, ¶ 24.

865 Moreira, ¶ 24.

866 Compañía Minera Colquiri Annual Budget for 2012, R-33.

867 Moreira, ¶ 19.

Page 193: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

188

The investments, purchases, etc., that, per the Triennial Plan, were supposed to have

been made between July 2011 (the Triennial Plan’s date) and 20 June 2012 (when the

Mine Lease was reverted) were never carried out.868 Neither Claimant nor its

witnesses have submitted any evidence to the contrary; and

The Triennial Plan contains no economic, social or environmental analyses.869 Had

this Plan been seriously considered at Colquiri or, as Claimant contends, had Colquiri

been in the process of implementing it, these analyses would have been undertaken.

It is simply not possible to conceive that a Plan of these characteristics, which

forecasts that Colquiri’s production will grow by a multiple of 5 (from 1,000 tons per

day, in 2012, to 5,000 tons per day, in 2014 (including production from both

Colquiri’s current processing plant and the new plant for old tailings) as a result of

various investments), would not have an internal assessment of its economic viability,

nor any social or environmental analyses supporting its implementation.

640. A valuation solely based on the Triennial Plan (such as Compass Lexecon’s, which takes the

Triennial Plan at face value) is speculative at best. The hypothetical and unrealistic nature of

Claimant’s damages claim is obvious when comparing Colquiri’s historical financial

performance with Compass Lexecon’s forecasts. For instance, while Colquiri’s historical

Earnings before EBITDA ranged from approximately US$ 10 million to US$ 42 million

during the seven years leading up to June 2012, the earnings projected by Compass Lexecon

for the next 20 years are about five times higher.870

641. The speculative nature of Compass Lexecon’s valuation is all the more apparent when the

Triennial Plan of July 2011 is compared to Claimant’s March 2012 investment plan (the

“March 2012 Investment Plan”)871 (which is neither mentioned nor submitted by Claimant).

The March 2012 Investment Plan, submitted by Sinchi Wayra to COMIBOL on April 2012,

contains significantly different (more conservative) projections and investments from those

reflected in the Triennial Plan. For instance, while the Triennial Plan anticipated a 2-year

ramp up period to attain the annual production of 550,579 MT, the March 2012 Investment

Plan contemplated a 4-year ramp up period to reach the lower annual production of 470,000

MT. Likewise, the March 2012 Investment Plan projected the need for US$ 12.3 million more

868 Moreira, ¶ 21.

869 Moreira, ¶ 29.

870 Econ One, ¶¶ 33-34.

871

March 2012 Investment Plan, EO-7.

Page 194: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

189

in CAPEX as compared to the Triennial Plan. Thus, the March 2012 Investment Plan

confirms that Claimant’s experts’ valuation is untethered from reality and speculative, and

that Claimant’s sole objective in relying on the Triennial Plan is to inflate its damages claim.872

642. Two, Claimant’s experts assume that a number of infrastructure projects and equipment

purchases (required to increase production) were in progress as of 20 June 2012, when the

Mine Lease was reverted. However, aside from the witness statement of Mr Eduardo

Lazcano, Claimant has not submitted any evidence in support of these assumptions.

Furthermore, to justify its exaggerated and unrealistic production increases, Compass

Lexecon assumes that most of these projects would have been built between June and

December 2012, which is unrealistic and unfeasible.873 Claimant’s experts are valuing a

magical mine.

643. Mr Lazcano’s witness statement refers to four projects, namely:874

The Expansion of Colquiri’s Processing Plant. At paragraph 23, Mr. Lazcano says

there were ongoing works for the expansion of the processing plant, and that new

equipment had been purchased for this purpose. However, Mr Lazcano has not

provided any evidence supporting this.

The Old Tailings Plant. At paragraph 33, Mr Lazcano says that several studies and

detailed engineering had been carried out for the construction of the Old Tailings

Plant. However, Mr Lazcano has not provided any evidence supporting this.

The New Tailings Dam. At paragraph 34, Mr Lazcano says that, by 2012, Sinchi

Wayra had already identified the land on which the new tailings dam would be built

and agreed on the purchase terms with the local community. However, neither

Claimant, its experts nor Mr Lazcano have provided any evidence of this.

Furthermore, after reviewing Colquiri’s internal files, Eng Moreira has not found

“rastro de acuerdo alguno para la compra de terrenos para la construcción de un

nuevo dique […].”875

872 Econ One, ¶ 52.

873 Moreira, ¶ 64.

874 Lazcano, ¶ 21.

875 Moreira, ¶ 62 (Unofficial translation: “any trace of any agreement for the purchase of land for the construction of a new

dam”).

Page 195: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

190

Infrastructure works. At paragraph 30, Mr Lazcano also indicates that the

construction of the main ramp was ongoing. Yet, Mr Lazcano glosses over the fact

that, as of 20 June 2012, only 30 meters of the main ramp (out of 2,500) had been

built, that such limited works could have no impact whatsoever on production

levels876 and that building the entire ramp would take, at least, 3 additional years877

(yet Compass Lexecon assumes that, by 2014, the processing plant’s production

would have doubled by benefiting from a fully operational 2,500 m ramp)878.

644. Had these projects been carried out in reality (or, at least, begun in 2012), some documents

should exist. Neither Claimant nor its witnesses have submitted any of these documents

(despite the fact that, as explained by Eng Moreira, Sinchi Wayra took the computers and files

when the Mine Lease was reverted).879

645. Three, Claimant’s experts assume that “the history of replacement [of mineral resources and

ore reserves] will continue and that a valuation of the Mine should include mineralization

that is not yet included in Mineral Resources […].”880 Put differently, RPA (and thus

Compass Lexecon’s valuation) assume that mineral resources will be magically delineated

and reserves will magically replenish during the next 17 ½ years (i.e., from mid-2012 until

2030). This is entirely speculative. There is no exploration work supporting these

assumptions nor any investment in exploration factored in by Compass Lexecon.881 As of 31

December 2011, pursuant to the Australasian Code for Reporting of Exploration Results,

Mineral Resources and Ore Reserves (the “JORC Code”),882 resources at Colquiri were

estimated at 4,181 MT and reserves at 1.55 MT,883 which – at the Mine’s production level at

the time – would have been produced in 13.6 years.884 By assuming the existence of 7.9 MT

additional tons of magical resources and reserves, and without any need to invest capital in

exploration, RPA arbitrarily concludes that Colquiri would have had resources and reserves

to continue operating until 2030 (i.e., 6 years more – at a higher production rate – than based

876 Moreira, ¶¶ 47-48.

877 Moreira, ¶ 48.

878 Compass Lexecon Colquiri Valuation, CLEX-4, “Revenues”.

879 Moreira, ¶ 13.

880 RPA FBD Glencore v Bolivia Expert Report, ¶ 18.

881 SRK, ¶¶ 43-45.

882 Reserves & Resources, Glencore <http://www.glencore.com/investors/reports-and-results/reserves-and-resources/ >

last visited 2 December 2017, R-254.

883 RPA FBD Glencore v Bolivia Expert Report, ¶ Table 1.

884 Econ One, ¶ 36.

Page 196: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

191

on the reported resources and reserves). The JORC Code precisely prohibits reporting

resources that are not supported by geological exploration:

The term ‘Mineral Resource’ covers mineralisation, including dumps and tailings,

which has been identified and estimated through exploration and sampling and

within which Ore Reserves may be defined by the consideration and application of

the Modifying Factors.885

Geological evidence and knowledge required for the estimation of Mineral

Resources must include sampling data of a type, and at spacings, appropriate to the

geological, chemical, physical, and mineralogical complexity of the mineral

occurrence, for all classifications of Inferred, Indicated and Measured Mineral

Resources. A Mineral Resource cannot be estimated in the absence of sampling

information.886

646. RPA’s assumption of resources and reserves is necessary for it to justify how Colquiri’s

processing plant production could have increased from 289,888 tons in 2011 to 550,579 in

2014 (i.e., by a factor of 190%!) and then would remain at that phenomenal level until 2030.887

Needless to say, RPA’s assumptions grossly inflate Claimant’s claim.

647. Four, Claimant’s experts assume that production at Colquiri would double as of 2014, but

overlook that vast amounts of additional water and electricity would be needed to sustain such

production levels, and that they do not exist in the Colquiri area. As explained by Eng

Moreira:

En estos momentos, con una capacidad de tratamiento en planta de 1.300 tpd, ya

tenemos muchos problemas de agua – es, simplemente, imposible encontrar

suficiente agua en la zona para tratar el tonelaje que prevé ese Plan Trienal.888

648. In spite of this, Claimant’s experts assume that the water and electricity needed would

magically appear. Claimant’s experts unrealistic production estimates also overlook the

impact that population growth (throughout time and, in particular, resulting from the Mine

and plant employment demands) would have on water supply.

885 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 12; JORC Code, 2004, Australasian Code for Reporting of Exploration Results, Mineral Resources

and Ore Reserves, RPA-32, p.7.

886 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 11. JORC Code, 2004, Australasian Code for Reporting of Exploration Results, Mineral Resources

and Ore Reserves, RPA-32, p.7.

887 RPA FBD Glencore v Bolivia Expert Report, ¶ 113; Compass Lexecon Colquiri Valuation, CLEX-4, “Revenues”.

888 Moreira, ¶ 36 (Unofficial translation: “For the time being, with the plant’s treatment capacity of 1,300 tons per day we

already have water issues – it is simply impossible to find sufficient water in the area to treat the tonnage provided in

that Triennial Plan”).

Page 197: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

192

649. Five, although they assume increased production (coming both from the expansion of

Colquiri’s processing plant and the Old Tailings Reprocessing Project),889 Claimant’s experts

underestimate (not to say almost ignore) the need to build a very costly new dam. Indeed, the

Triennial Plan – on which Claimant’s experts rely – only considers an investment of

US$ 5 million for the construction of a new tailings dam.890 This is clearly insufficient, as

evidenced by the fact that the Huanuni mine recently built a new tailings dam at a cost of

US$ 9.5 million for the first phase (in addition to the cost of the land).891 By underestimating

this cost, Claimant’s experts assume that the tailings resulting from the increased production

will magically disappear.

650. Six, Claimant’s experts assume that (i) unrealistically high mineral grades (ii) will remain

constant throughout the life of the mine.892 On the one hand, as explained by Eng Moreira,

Claimant’s experts ignore the degeneration in grades that results from the passage of time.893

Furthermore, because future mining at the Mine will require going deeper, mineral grades are

expected to be negatively impacted (which will result in grades lower than those estimated by

RPA).894 On the other hand, given that deep exploration had not been undertaken as of June

2012, it is not possible to predict grade continuity through the mineral deposit.895 Claimant’s

experts ignore this, grossly inflating Claimant’s claim.

651. Seven, Claimant’s experts assume that, as of June 2012, (i) unrealistically high metallurgical

recovery rates will (ii) remain constant throughout the life of the mine.896 As explained by

Eng Moreira, this is inconsistent with Colquiri’s historical operating performance, which

reflects a decreasing trend in metallurgical recoveries throughout time.897 Recovery rates are

expected to continue decreasing in time because they are correlated to grades (which, as

explained above, are expected to decrease due to the passage of time and because mining will

progressively move deeper into the Mine). Claimant’s experts’ assumption that metallurgical

recoveries at Colquiri will magically reach its historical peak as of June 2012 (and remain

constant during the next 17 ½ years) is thus entirely unsupported. As explained by Prof.

889 RPA FBD Glencore v Bolivia Expert Report, ¶¶ 113, 135; Compass Lexecon Colquiri Valuation, CLEX-4.

890 2012-2014 Colquiri Mine Three-year Plan, C-108, p. 202.

891 Moreira, ¶ 63.

892 RPA FBD Glencore v Bolivia Expert Report, ¶¶ 18, 48.

893 Moreira, ¶ 70 et seq.

894 SRK, 4, 63.

895 SRK, ¶¶ 15, 64.

896 RPA FBD Glencore v Bolivia Expert Report, ¶ 48.

897 Moreira, ¶¶ 71-73.

Page 198: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

193

Rigby, Claimant’s experts have not carried out analytical testwork or pilot plant studies that

support their assumptions.898

652. Eight, Claimant’s experts have failed to deduct Colquiri’s production between January and

May 2012 from their damages DCF valuation (made as of 29 May 2012), thus assuming that,

magically, Colquiri would have achieved such production both before and after the reversion

of the Mine Lease. As explained by Econ One, “Compass Lexecon, relying on the production

forecast from Colquiri’s Plan Trienal 2012-2014 (the “Triennial Plan”), includes the full

amount of 360,113 MT of ore hoped to be produced in 2012 [in its valuation]. […] I have

apportioned the 2012 cash flow to take into account only the period starting 19 June 2012.”899

In fact, “Correcting Compass Lexecon’s model only to include the six and a half months of

operation from late May 2012 through the end of the year decreases its valuation by US$ 9.2

million.”900

653. Nine, Claimant’s experts assume that the Old Tailings Reprocessing Project (which they value

at more than US$ 100 million) would have been implemented shortly after the reversion of

the Mine Lease (i.e., mid-2012). This is speculative. Indeed, this Project has been evaluated

several times over the last four decades (e.g., by Minproc in 1988 and PAH in 2004901) and,

still, no one has invested on it. Sinchi Wayra itself had more than 7 ½ years to implement this

Project (from March 2005, when Claimant alleges having acquired control of Colquiri, until

June 2012, when the Mine Lease was reverted) and did not do so. It is undisputed, therefore,

that there is no going concern involving the old tailings. It is thus extremely speculative to

assume that this Project would have been implemented shortly after the reversion of the Mine

Lease (Compass Lexecon’s model assumes investments on this Project as of 2013)902 and,

even more so, to attribute more than US$ 100 million in value to this Project on the basis of a

DCF model (which cannot be used to value non-going concerns). If Claimant has not invested

in this Project is because its economic viability is uncertain.903 As explained by Eng Moreira,

“el reprocesamiento de las colas requiere inyectar una cantidad importante de capital para

permitir el tratamiento de las colas y su viabilidad no es segura […].”904

898 SRK, 66.

899 Econ One, footnote 18.

900 Econ One, ¶ 19.

901 RPA FBD Glencore v Bolivia Expert Report, ¶ 128.

902 Compass Lexecon Colquiri Valuation, CLEX-4, Tab “CAPEX”.

903 SRK, Section 8.2, ¶ 85.

904 Moreira, ¶ 83 (Unofficial translation: “reprocessing the tailings requires to inject a significant amount of capital to

permit the treatment of tailings and its viability is not certain”).

Page 199: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

194

654. For all these reasons, Compass Lexecon’s valuation of Colquiri is based on mere speculation

and should be rejected.

7.1.2.2 Compass Lexecon’s Valuation Of The Tin Smelter Is Premised On Mere Speculation

655. Claimant claims an astounding US$ 65.9 million in damages for the Tin Smelter as of 8

February 2007.905 This claim is premised on mere speculation for, at least, five reasons.

656. First, Claimant’s experts assume that the Tin Smelter would magically produce 14,000 annual

tons of tin ingots starting on 2008 and for the next 18 years (i.e., until 2026, when Claimant’s

experts estimate the production life of the Tin Smelter will end).906 These projections

disregard the state of the Tin Smelter’s furnaces and machinery as February 2007, and

unreasonably assume those same furnaces (which dated from the 70s and were obsolete907)

would operate for the next 18 years (which is technically unfeasible).

657. The state of disrepair of the Tin Smelter’s machinery as of 8 February 2007 was described in

Decree No. 29658 as follows:

[S]e ha evidenciado la deplorable situación del horno eléctrico, hornos reverberos

No. 3 y 4 y demás equipos y maquinarias, que no fueron objeto de un mantenimiento

adecuado y renovación permanente por parte de la empresa privada, por lo que es

de suma importancia que la Empresa Metalúrgica Vinto efectúe la modernización

y mejora de la planta de fundición de estaño, lo que representa una inversión

económica

[…]

[L]a tecnología actual […] data desde hace treinta y cinco (35) años atrás y los

hornos, equipos y maquinarias, presentan un desgaste natural. Por cuanto es

necesario e indispensable la actualización de su tecnología que implique la

modernización de la Empresa Metalúrgica Vinto.908

658. Yet neither RPA nor Compass Lexecon include in their models the costs of new furnaces.

659. Moreover, Claimant’s experts ignore that the Tin Smelter has not reached a production level

of 14,000 annual tons of ingots even after investing US$ 39 million to acquire and install the

905 Statement of Claim, ¶ 295.

906 Compass Lexecon Vinto Valuation, CLEX-2, Tab “Production”.

907 Villavicencio, ¶¶ 45-46.

908 Supreme Decree No. 29.658 of 30 July 2008, R-256 (emphasis added) (Unofficial translation: “[T]he deplorable

situation of the electric furnace, the reverberatory furnaces No. 3 and 4 and other equipment and machinery has become

obvious. They were not correctly maintained or regularly updated by the private company, therefore, it is of the utmost

importance for Empresa Metalúrgica Vinto to modernize and improve the Tin Smelter plant, which represents an

economic investment. [T]he current technology […] dates from thirty-five (35) years ago and the furnaces, equipment

and machinery have naturally deteriorated. This is why, it is necessary and crucial to update its technology and thus

to modernize Empresa Metalúrgica Vinto”).

Page 200: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

195

Ausmelt Furnace from 2009 to 2015.909 As explained by Eng Villavicencio (EMV’s current

General Manager and Director of its Engineering and Projects Department as of 2006):

la producción desde el año 1998 (periodo de rehabilitación), tiene un

promedio de 10.500 TMF anuales y, durante la privatización, un promedio de

11.500 TMF. En la etapa después de la reversión y antes del Horno Ausmelt

mantuvimos un promedio de 11.500 TMF de estaño producido. En la

actualidad, con la inversión en el Ausmelt, tenemos una capacidad de

producción instalada de 18.000 TMF y hemos llegado a alrededor de las

13.000 TMF (no obstante, Compass Lexecon proyecta hasta 13.974 TMF

anuales de producción cuando, si no se hubiera realizado la inversión en el

Ausmelt, en ningún momento hubiésemos excedido la producción de 12.000

TMF anuales).910

660. Second, Claimant’s experts assume that the Tin Smelter would process 30,000 annual tons of

concentrates to produce 14,000 annual tons of ingots as of 2008, but overlook that there are

not sufficient concentrates in Bolivia to justify such tremendous production (much less during

an 18-year period). As explained by Mr Villavicencio:

[Compass Lexecon ignores] que, desde 1998, no se registran volúmenes de

tratamiento de concentrados cercanos o superiores a las 30.000 TMS

(inclusive hoy teniendo el Horno Ausmelt) ya que las minas en Bolivia no

producen suficientes concentrados (los proyectos de Huanuni y Colquiri

recién van a funcionar en 2019)911

661. However, Claimant’s experts assume that mines in Bolivia will magically start producing

more concentrates so as to sustain the tremendous production they have estimated for the Tin

Smelter.

662. Third, Claimant’s experts assume that unduly high concentrates grades (48.75% Sn) – the

main input for the production of tin ingots – would remain constant over an 18-year period.912

This, again, is unrealistic and speculative. On the one hand, the Tin Smelter’s historical

operational performance shows that, from 1987 to date, concentrates grades have been in

909 Villavicencio, ¶¶ 65-66.

910 Villavicencio, ¶ 66 (emphasis added) (Unofficial translation: “since 1998 (the rehabilitation period), production has

been at an average of 10,500 fine metric tons annual and during the privatization at an average of 11,500 fine metric

tons. After the reversion and before the Ausmelt Furnace we maintained an average production of 11, 500 fine metric

tons of tin. Since the Ausmelt investment, our current installed capacity of production amounts to 18,000 fine metric

tons and we have attained around 13,000 fine metric tons (however, Compass Lexecon estimates an annual production

of 13,974 fine metric tons, if the Ausmelt investment had not been made, the annual production would have never

exceeded 12,000 fine metric tons)”).

911 Villavicencio, ¶ 64 (emphasis added) (Unofficial translation: “[Compass Lexecon ignores] that since 1998 there are no

records showing concentrate being treated in volumes near or exceeding 30,000 fine metric tons (not even today with

the Ausmelt Furnace) given that Bolivian mines do not produce enough concentrate (the Huanuni and Colquiri projects

will just begin to operate in 2019)”).

912 RPA FBD Glencore v Bolivia Expert Report, ¶ 194; Compass Lexecon Vinto Valuation, CLEX-2, Tab “Production”.

Page 201: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

196

steady decline (e.g., 50.25% in 1990, 48.74% around 2009, 46.77% in 2015 and so forth).913

On the other hand, given that, as explained by Eng Moreira,914 a mine’s mineral grades are

expected to decrease in time as the mine grows older (and, in this case, also as mining moves

deeper into the Mine), the grades of the concentrates acquired by the Tin Smelter (from the

Huanuni mine, the Mine and cooperativistas) are also expected to decrease.915

663. Fourth, Claimant’s experts likewise assume that metallurgical recovery rates at the Tin

Smelter will remain constant and unduly high (at 95.6% Sn).916 This is, again, speculative.

Given that concentrates grades are expected to be lower, so are metallurgical recoveries. As

explained by Eng Villavicencio, Claimant’s experts’ assumptions are “contrari[as] a una

regla de oro de la metalurgia: a mayor ley, mayor recuperación y viceversa […].”917

664. Fifth, Claimant’s experts have failed to deduct the Tin Smelter’s production between 1

January and 8 February 2012, thus assuming that the Tin Smelter would have achieved such

production both before and after the reversion.918 Claimant’s experts’ error has an impact of

US$ 0.6 million.

7.1.2.3 Claimant’s Valuation Ignores That The Antimony Smelter Was A Liability, Not An Asset

665. Based on the valuation performed by Ms Russo, Claimant claims an astounding

US$ 1.9 million in damages for the Antimony Smelter, an asset it recognizes has been

inoperative since the 1990s and which was only “occasionally used as a storage facility for

the Colquiri Mine […].”919

666. The valuation of Ms Russo is far removed from reality and speculative (at best) because it

ignores the reality of the Antimony Smelter (an obsolete asset) as well as its environmental

liability (significant closure and remediation costs would be needed to restore the site before

the land can be given a residential use, as suggested by Ms Russo).

667. First, as of 1 May 2010, when the Antimony Smelter reverted to the State, its infrastructure

was obsolete. As explained by Eng Villavicencio, “la Fundidora de Antimonio estaba en

913 Villavicencio, ¶ 70.

914 Moreira, ¶¶ 70-75.

915 Villavicencio, ¶¶ 68-70.

916 RPA FBD Glencore v Bolivia Expert Report, ¶ 196.

917 Villavicencio, ¶ 72 (Unofficial translation: “contrary to a golden rule in metallurgy: the higher the grade, the higher

recovery, and vice versa”).

918 Econ One, ¶ 20.

919 Statement of Claim, ¶ 59.

Page 202: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

197

condiciones muy precarias a la fecha de la reversión en 2010, por lo que, al contrario de lo

que indica la Arq. Russo, no valía nada. Las edificaciones estaban en avanzado estado de

deterioro […].”920

668. Second, the Antimony Smelter is a non-operative asset with a significant environmental

burden. This burden results from (i) past operations of the Antimony Smelter,921 and (ii) the

ongoing operations of the Tin Smelter (active since 1971 and located within meters of the

Antimony Smelter), which produce harmful gasses. As explained by Eng Villavicencio, “la

Fundidora de Antimonio está en el área de influencia directa del complejo metalúrgico de

Vinto, por lo que recibe constantemente la pluma de arsénico y azufre generada por los

procesos de tostación de la Fundidora de Vinto (que seguirá en operaciones, por más que la

Fundidora de Antimonio cierre y llegue a transformarse en un área urbanizable) […].”922

669. Third, as a result of the above, the environmental burden existing at the Antimony Smelter

will need to be remediated by any potential buyer at a significant cost before any residential

use can even be envisaged.923

670. Fourth, the 40-plus-year-old infrastructure and buildings existent at the Antimony Smelter

will need to be dismantled, which will also represent a significant cost that would outweigh

any revenue from scrap material.924

671. Bolivia has retained Architect Diego Mirones to perform a proper valuation of the Antimony

Smelter. Mr Mirones holds a Degree in Architecture from the Facultad de Arquitectura,

Universidad de San Andrés, in Bolivia, and has over 30 years of experience as a real estate

appraiser. Mr Mirones has vast experience performing independent valuations of real estate,

having worked for the private sector and for well-known Bolivian banks throughout his

career.925

920 Villavicencio, ¶ 111 (Unofficial translation: “at the time of the Antimony Smelter’s reversion, the latter was very poor

condition, therefore, contrary to what Arc. Russo states, it was worth nothing. The buildings were in an advanced state

of deterioration […]”).

921 Villavicencio, ¶ 92.

922 Villavicencio, ¶ 109 (emphasis in original) (Unofficial translation: “the Antimony Smelter is located in the area which

is directly influenced by the metallurgic plant of Vinto. As a result, it constantly receives an arsenic and sulfur plume

generated by the roasting processes of the Vinto Smelter (which will continue to operate, even if the Antimony Smelter

closes and becomes a developable area)”).

923 Mirones, ¶ 117.

924 Mirones, ¶ 112; Econ One, ¶ 128.

925 Mirones, ¶¶ 1-3.

Page 203: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

198

672. Mr Mirones has performed a valuation of the Antimony Smelter. He visited the land and

inspected the Antimony Smelter’s infrastructure.926 After considering, among others, the state

of the Antimony Smelter’s infrastructure, its environmental burden and the closure,

remediation and dismantling costs that would need to be incurred by any potential buyer of

the Antimony Smelter (all ignored by Ms Russo), Mr Mirones has concluded that the

Antimony Smelter has no positive value.927

673. Indeed, as explained in section 7.3.6 below, the abovementioned costs are higher than the

limited value of the obsolete Antimony Smelter (estimated by Mr Mirones at

US$ 664,393.59),928 thus making this asset a liability. Consequently, the damages claimed by

Claimant for the Antimony Smelter are speculative (at best) and should be denied.

674. For the above reasons, the Tribunal should conclude that the damages claimed by Claimant in

this arbitration are speculative and, as a result, cannot be compensated under international

law.

7.2 Even If The Damages Claimed For The Mine Lease Reversion Were Certain (Quod

Non), They Were Not Caused By Bolivia But Rather By Claimant’s Own Acts

675. Causation is one of the cornerstones of liability under international law. A State can only be

held liable for damages it has caused.

676. Pursuant to Article 31 of the Articles on State Responsibility, the responsible State is “under

an obligation to make full reparation for the injury caused by the internationally wrongful

act. Injury includes any damage, whether material or moral, caused by the internationally

wrongful act of a State.”929

677. In addition, the commentary to Article 31 specifies that only the injury caused by the

internationally wrongful act of a State can be the object of full reparation:

It is only ‘[i]njury [ …] caused by the internationally wrongful act of a State’

for which full reparation must be made. This phrase is used to make clear that

the subject matter of reparation is, globally, the injury resulting from and

926 Mirones, Section 3.

927 Mirones, ¶ 117.

928 Mirones, ¶ 105.

929 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, Article 31, p. 91 (emphasis added).

Page 204: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

199

ascribable to the wrongful act, rather than any and all consequences flowing

from an internationally wrongful act.930

678. Accordingly, a causal relationship must be established between the internationally wrongful

act and the harm allegedly suffered. As the tribunal in the BG Group case held, “[t]he

damage, nonetheless, must be the consequence or proximate cause of the wrongful act.” 931

The same view was espoused by the S.D. Myers tribunal “the economic losses claimed by [the

claimant] must be proved to be those that have arisen from a breach of the [treaty], and not

from other causes.”932 Thus, when the claimant fails to establish the causal link, compensation

must be denied.

679. The analysis of causation also involves identifying the dominant cause of the damages sought.

When such dominant cause is attributable to the conduct of the party seeking damages, the

causal link is severed and no compensation is therefore due. As the ICJ put it in the ELSI

case:

Furthermore, one feature of ELSI’s position stands out: the uncertain and

speculative character of the causal connection, on which the Applicant’s case

relies, between the requisition and the results attributed to it by the Applicant.

There were several causes acting together that led to the disaster to ELSI. No

doubt the effects of the requisition might have been one of the factors involved.

But the underlying cause was ELSI’s headlong course towards insolvency;

which state of affairs it seems to have attained even prior to the requisition.933

680. Commenting on the ELSI decision, the Biwater tribunal stated that:

In that case, the ICJ held that the primary cause of the claimant’s difficulties lay in

its own mismanagement over a period of years, and not the act of requisition

imposed by the governmental authorities.934

681. It is thus a settled principle of international law that the claimant bears the burden of proving

the existence of a sufficient – and dominant – causal link between the State’s allegedly

930 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, Article 31, p. 92, comment 9

(emphasis added).

931 BG Group Plc. v. The Republic of Argentina, UNCITRAL, Final Award of 24 April 2007, RLA-100, ¶ 428.

932 S.D. Myers, Inc. v. Government of Canada, NAFTA-UNCITRAL, Partial Award of 13 November 2000, RLA-101,

¶ 316. See also S. Ripinsky and K. Williams, Damages in International Investment Law, British Institute of International

and Comparative Law, 2008 (extract), RLA-89, p. 114, quoting C. Egleton, Measure of Damages in International Law,

Yale Law Journal, 1929-1930.

933 Case concerning Elettronica Sicula S.p.A. (ELSI) (United States of America v. Italy), ICJ, Judgment of 20 July 1989,

RLA-72, ¶ 101 (emphasis added).

934 Biwater Gauff (Tanzania) Ltd v United Republic of Tanzania (ICSID Case No ARB/05/22) Award of 24 July 2008,

CLA-78, ¶ 786 (emphasis added).

Page 205: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

200

unlawful conduct and the harm suffered.935 More recently, in the Blusun case, the tribunal

denied compensation precisely because the claimant had failed to discharge its burden of

proving such causation:

The Claimants ha[d] not discharged the onus of proof of establishing that the

Italian state’s measures were the operative cause of the Puglia Project’s

failure.936

682. In the present case, Claimant has failed to prove that the damages claimed in connection with

the reversion of the Mine Lease were dominantly caused by Bolivia’s alleged unlawful acts.

Quite the opposite, as explained in section 2.6.3 above, Claimant’s mismanagement and

aggravation of the social conflicts at the Mine forced the State to intervene and revert the Mine

Lease in June 2012.

683. First, Claimant inherited the social tensions created by Comsur’s poor management of the

relations between the Mine’s workers and the cooperativistas operating at the Mine. These

tensions were boosted by the political transformations in Bolivia following Sánchez de

Lozada’s resignation in 2003, in which the cooperativas, as new and fundamental social

actors, played a crucial role.937

684. After acquiring control over the Mine, Claimant never sought to properly redress this

situation. Instead, as explained by Mr Cachi (a former cooperativista), “[c]on Sinchi Wayra

[i.e., Glencore International’s subsidiary], la seguridad de la Mina decreció aún más y la

aprobación del trabajo de los cooperativistas por parte de la empresa fue mayor. Esto causó

que el descontento de los trabajadores se tornara, en algunos casos, violento, sobre todo al

interior de la Mina, cuando los trabajadores y los cooperativistas se encontraban en la misma

área. Los enfrentamientos entre trabajadores y cooperativistas se hicieron más y más

frecuentes.”938 The record shows that, under Sinchi Wayra’s control, the cooperativistas (and,

935 Biwater Gauff (Tanzania) Ltd v United Republic of Tanzania (ICSID Case No ARB/05/22) Award of 24 July 2008,

CLA-78, ¶ 787 (“The Arbitral Tribunal considers that in order to succeed in its claim for compensation, BGT has to

prove that the value of its investment was diminished or eliminated, and that the actions BGT complains of were the

actual and proximate cause of such diminution in, or elimination of, value”); S. Ripinsky and K. Williams, Damages in

International Investment Law, British Institute of International and Comparative Law, 2008 (extract), RLA-89, p. 162

(“In the damages context, it is always the claimant who alleges that it has suffered a loss as a result of the respondent‘s

conduct; therefore, the claimant bears the burden of proof in relation to the fact and the amount of loss, as well as to

the causal link between the respondent‘s conduct and the loss”).

936 Blusun S.A., Jean-Pierre Lecorcier and Michael Stein v. Italian Republic, ICSID Case No.

ARB/14/3, Award of 27 December 2016, RLA-102, ¶ 394 (emphasis added).

937 See section 2.5.2 above.

938 Cachi, ¶ 24 (Unofficial translation: “[u]nder Sinchi Wayra, security in the Mine diminished even more and the approval

of the cooperativistas’ work by the company was more significant. This led, in some cases, to the workers’ discontent

becoming violent, in particular within the Mine, when workers and cooperativistas met in the same area. Confrontations

between workers and cooperativistas became more and more frequent”).

Page 206: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

201

in particular, the Cooperativa 26 de Febrero) gradually came to control larger and deeper

areas of the Mine,939 to the point that, “[p]ara finales de 2011, los cooperativistas teníamos

prácticamente el control de la Mina.”940

685. Second, Sinchi Wayra requested the intervention of the State at the eleventh hour, making it

impossible for COMIBOL to resolve a social conflict which had been brewing for over a year

(as a result of yielding to the cooperativas’ interests in occupying the Mine). In fact, it was

Colquiri’s own admission that “[d]ichas perturbaciones al desenvolvimiento de la operación

minera señalada, han sido atendidas en gran medida y hasta el momento por nuestra

empresa”941 – that is to say, intentionally without involving the State’s institutions before

April 2012. As explained above, it was impossible for COMIBOL to resolve a structural

problem this deep in a matter of days.

686. Third, Sinchi Wayra’s own employees deeply distrusted the company’s ability to solve the

tensions it had caused and encouraged with the cooperativistas over the years. Such distrust

explains their decision to support the reversion of the Mine Lease. In Mr Mamani’s words,

the workers advised the directors of Sinchi Wayra “nuestras preocupaciones (sobre todo, por

la forma como la empresa había venido cediendo y entregando áreas de la Mina desde hacía

mucho tiempo a los cooperativistas) y que en esos momentos críticos no solamente se estaba

jugando la estabilidad laboral de nuestros trabajadores, sino el futuro mismo de la Mina.

Para nosotros, ya era claro que Sinchi Wayra había perdido el control de la Mina y la

confianza de sus propios trabajadores.”942

687. Fourth, being fully aware of the Government’s efforts to resolve the conflict provoked by the

occupation of the Mine by the cooperativistas on 30 May 2012, Sinchi Wayra promoted

939 See, for instance, Public Deed No. 0215/2009, amendment to the lease agreement between COMIBOL and the

Cooperativa 26 de Febrero of 21 October 2009, R-210; Colquiri internal report concerning ore bought and/or

transported for the Cooperativa 26 de Febrero of 15 December 2007, R-198; Colquiri internal report concerning ore

bought and/or transported for the Cooperativa 26 de Febrero of 21 April 2008, R-199; Colquiri internal report

concerning ore bought and/or transported for the Cooperativa 26 de Febrero of 17 April 2007, R-200; Proof of payment

for the transport of ore for the Cooperativa 26 de Febrero of 21 October 2007, R-201; Proof of payment for the transport

of ore for the Cooperativa 26 de Febrero of 20 November 2007, R-202; Proof of payment for the transport of ore for

the Cooperativa 26 de Febrero of 7 January 2008, R-203; Colquiri internal report concerning ore transported for the

Cooperativa 26 de Febrero of 25 May 2008, R-204; Colquiri internal report concerning ore transported for the

Cooperativa 26 de Febrero of 29 June 2008, R-205.

940 Cachi, ¶ 31 (Unofficial translation: “[b]y the end of 2011, we the cooperativistas practically controlled the Mine”).

941 Letter from Colquiri SA (Mr Capriles Tejada) to Comibol (Mr Córdova Eguivar) of 3 April 2012, C-30, p. 1. (Unofficial

translation: “[t]hose disturbances to the performance of this mining operation have been so far, to a large extent, taken

care of by our company”).

942 Mamani, ¶ 37 (Unofficial translation: “our concerns (in particular, regarding the manner in which the company had

been assigning and relinquishing areas of the Mine gradually and for a long time) and that during those critical

moments, the employment stability of our workers as well as the future of the Mine itself were at stake. In our opinion,

there was no doubt that Sinchi Wayra had lost control over the Mine and the trust of its own workers”).

Page 207: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

202

inconsistent agreements with national leaders of the cooperativas and a fraction of the

Cooperativa 26 de Febrero opposing a potential reversion of the Mine Lease. Concretely, on

7 June 2012, at the same time the Gran Cabildo approved the reversion of the Mine Lease at

Colquiri,943 Sinchi Wayra executed the Rosario Agreement.944

688. Sinchi Wayra’s actions escalated the conflict to unprecedented levels of violence, and left the

State with no other option but to terminate the Mine Lease. As explained by Minister Romero,

the Rosario Agreement was an almost unsurmountable obstacle to the resolution of the social

conflict at Colquiri (caused by Sinchi Wayra itself), and even sparked waves of violence in

Colquiri in September 2012, after the State had issued the Mine Lease Reversion Decree. This

made a new intervention by the State necessary.945

689. Consequently, even assuming the damages claimed by Claimant for Colquiri were certain

(which Bolivia denies), Claimant would be the sole responsible for such damages.

Accordingly, Claimant’s claim for compensation must be dismissed.

7.3 Even If The Damages Claimed Were Certain (Quod Non), Claimant’s Valuations Are

Flawed And Grossly Inflated

690. The Treaty establishes the applicable principles of compensation (Section 7.3.1). Claimant’s

proposed valuation dates for Colquiri and the Antimony Smelter are inconsistent with Art. V

of the Treaty (Section 7.3.2). In addition, given that Compass Lexecon’s valuations ignore

key premises for the valuation of mining assets (Section 7.3.3), its FMV estimates of Colquiri

(Section 7.3.4) and the Tin Smelter (Section 7.3.5) are flawed. Compass Lexecon’s valuation

of the Antimony Smelter is also flawed as it is based on the valuation prepared by Ms Russo,

943 Operative vote of the Gran Cabildo de Colquiri of 7 June 2012, R-17.

944 Agreement between Colquiri SA, Fedecomin, Fencomin, Central Local de Cooperativas Mineras de Colquiri,

Cooperativa Minera Collpa Cota, Cooperativa Minera Socavón Inca, and Cooperativa 26 de Febrero, C-35.

945 Romero, ¶¶ 19-21 (“Poco tiempo después de suscribir el Acta de Acuerdo en junio de 2012, y de la promulgación del

Decreto Supremo de Reversión, se dieron nuevos enfrentamientos entre cooperativistas y trabajadores de la Empresa

Minera Colquiri (ahora controlada por COMIBOL). Según estos reportes, y a pesar de lo negociado en junio de 2012,

los trabajadores seguían disconformes en que la veta Rosario -la más atractiva de la Mina- estuviese casi en su totalidad

en manos de los cooperativistas. Los cooperativistas, por su parte, continuaban expresando que tenían derecho a la

referida veta, por el acuerdo obtenido con Sinchi Wayra y que además existía un acuerdo firmado con los trabajadores

con visto bueno del Estado […]. Las tensiones volvieron a degenerar rápidamente en actos violentos en septiembre de

2012, lo que hizo necesaria nuevamente la intervención del Ministerio a mi cargo”) (Unofficial translation: “Shortly

after we concluded the minutes of agreement in June 2012 and that the Reversion Supreme Decree was enacted, new

confrontations between cooperativistas and employees of Empresa Minera Colquiri (now controlled by COMIBOL)

took place. Following these reports, and despite the June 2012 negotiations, workers were still not satisfied with the

fact that almost the totality of the Rosario vein, the most attractive in the Mine, was under the cooperativistas’ control.

As for the cooperativistas, they continued to contend that they were entitled to that vein pursuant to the agreement

signed with Sinchi Wayra and that furthermore, there was an agreement signed with the workers that had the State’s

green light […]. Tensions rapidly degenerated again in violent acts in September 2012, and this required again the

intervention of the Ministry under my responsibility”).

Page 208: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

203

which incurs in several methodological errors (Section 7.3.6). Compass Lexecon’s valuation

of the Tin Stock (Section 7.3.7).

7.3.1 The Plain Terms Of The Treaty Establish The Applicable Principles Of Compensation

691. Claimant maintains that the Treaty does not specify “the relevant standard of the

compensation owed to Glencore Bermuda”, and so that compensation “must be assessed by

the Tribunal with reference to applicable principles of customary international law.”946

Claimant is wrong. The Treaty explicitly establishes that the compensation to be paid is

equivalent to the FMV of the investment immediately prior to the date when the expropriation

occurred or became public knowledge.

692. As Claimant admits,947 the Treaty provides the measure of compensation for a lawful

expropriation (and is equally applicable to unlawful expropriations). That measure of

compensation is the market value of the expropriated asset on the valuation date. The Treaty

sets the valuation date as the date immediately before (i) the expropriation occurred or (ii)

became public knowledge, whichever is earlier. Article V of the Treaty provides:

Investments of nationals or companies of either Contracting Party shall not

be nationalised, expropriated or subjected to measures having effect

equivalent to nationalisation or expropriation (hereinafter referred to as

"expropriation") in the territory of the other Contracting Party except for a

public purpose and for a social benefit related to the internal needs of that

Party and against just and effective compensation. Such compensation shall

amount to the market value of the investment expropriated immediately before

the expropriation or before the impending expropriation became public

knowledge, whichever is the earlier, shall include interest at a normal

commercial or legal rate, whichever is applicable in the territory of the

expropriating Contracting Party, until the date of payment, shall be made

without delay, be effectively realizable and be freely transferable.948

693. Under international law, the market value of an asset is assessed by reference to the concept

of fair market value or FMV. The FMV of an asset is determined based on an objective

standard, understood as the price a hypothetical willing and able buyer would pay to a willing

seller for the asset at a given time.

694. Arbitral tribunals consistently look at “the price that a willing buyer would pay to a willing

seller in circumstances in which each had good information, each desired to maximize his

946 Statement of Claim, ¶ 230.

947 Statement of Claim, ¶ 229.

948 Treaty, C-1, Article V (emphasis added).

Page 209: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

204

financial gain, and neither was under duress or threat.”949 As the SPP v. Egypt tribunal

recognized, “the purchase and sale of an asset between a willing buyer and a willing seller

should, in principle, be the best indication of the value of the asset.”950

695. In the context of going concerns, the tribunal will look to the investment’s “earning capacity

during the remainder of its life […] for assessing its ‘market value.”951 In other words, the

Tribunal should consider the revenue stream that a willing buyer would have factored to value

the Assets.

696. In doing so, the Tribunal should consider all risks affecting the future revenue stream that a

willing buyer would have factored into its valuation. Indeed, “[w]here tribunals have

measured compensation by reference to the fair market value of an investment, i.e. the amount

a hypothetical willing buyer would pay for the investment, they have tended to take account

for the impact of business risks on fair market value.”952

697. Thus, the very essence of FMV (on which Claimant purportedly based its claims) is the

objective approach of a hypothetical transaction between a willing buyer and a willing seller,

not Claimant’s subjective valuation. As noted by commentators, “the reference to a

‘hypothetical buyer’ makes it clear that the value of the property is not to be determined from

949 Siemens AG v Argentine Republic (ICSID Case No ARB/02/8) Award of 6 February 2007, CLA-67, ¶ 325, citing Starrett

Housing Corporation and others v Government of the Islamic Republic of Iran, Final Award (1987-Volume 16) Iran-

US Claims Tribunal Report, CLA-11, ¶ 277. See also, Enron Corporation and Ponderosa Assets LP v Argentine

Republic (ICSID Case No ARB/01/3) Award of 22 May 2007, CLA-68, ¶ 361; Compañía del Desarrollo de Santa Elena

SA v Republic of Costa Rica (ICSID Case No ARB/96/1) Final Award of 17 February 2000, CLA-25, ¶ 73 (“there is no

dispute between the parties as to the applicability of the principle of full compensation for the fair market value of the

Property, i.e., what a willing buyer would pay to a willing seller.”); Southern Pacific Properties (Middle East) Limited

v Arab Republic of Egypt (ICSID Case No ARB/84/3) Award on the Merits of 20 May 1992, CLA-18, ¶ 197 (“[i]n the

Tribunal’s view, the purchase and sale of an asset between a willing buyer and a willing seller should, in principle, be

the best indication of the value of the asset”); Sempra Energy International v Argentine Republic (ICSID Case No

ARB/02/16) Award of 28 September 2007, CLA-71, ¶ 405; Azurix Corp v Argentine Republic (ICSID Case No

ARB/01/12) Award of 14 July 2006, CLA-63, ¶ 424; CME Czech Republic BV v Czech Republic (UNCITRAL) Final

Award of 14 March 2003, CLA-42, ¶ 140 (“[o]ne of the best possible indicators of an enterprise’s fair market value is

what an actual buyer thinks it is worth.”).

950 Southern Pacific Properties (Middle East) Limited v Arab Republic of Egypt (ICSID Case No ARB/84/3) Award on the

Merits of 20 May 1992, CLA-18, ¶ 197.

951 Middle East Cement Shipping and Handling Co SA v Arab Republic of Egypt (ICSID Case No ARB/99/6) Award of 12

April 2002, CLA-34, ¶ 127; G. Arangio-Ruiz, Second Report on State Responsibility, Yearbook of the International Law

Commission, 1 (1989), RLA-103 II(1), ¶ 23 (“[c]ompensation by equivalent is thus intended to substitute, for the injured

State, for the property, the use, the enjoyment, the fruits and the profits of any object, material or non-material, of which

the injured party was totally or partly deprived as a consequence of the internationally wrongful act.”).

952 S. Ripinsky and K. Williams, Damages in International Investment Law, British Institute of International and

Comparative Law, 2008 (extract), RLA-89, p. 334. See also, id., p. 336 (“[w]hen determining the fair market value of

the investment lost, tribunals have often approximated the impact a particular risk would play on the amount a

hypothetical willing buyer would be prepared to pay for the investment.”).

Page 210: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

205

a subjective perspective, be it that of the former owner or that of the expropriating State, but

from the perspective of a third person who is not directly involved in the transaction.”953

698. The hypothetical willing buyers and sellers used to determine the objective fair market value

of an asset are assumed to be knowledgeable and prudent. As the Vestey Group tribunal

explained, the determination of FMV “is primarily an economic exercise, which involves

identifying the price at which the asset would change hands between a willing buyer and a

willing seller in an arm’s length transaction where the parties each act knowledgeably,

prudently, and without coercion.”954

699. Consistent with the above, the Iran-U.S. Claims Tribunal stressed the need to ensure that all

of the inputs in the valuation of an income–producing asset are accurate, reliable, and realistic

in deciding the price a reasonable buyer would pay for the asset.955 For example, the Starrett

Housing decision specified that the methods employed and approach to each stage of the fair

market valuation should be “logical and appropriate,”956 as well as based on assumptions and

premises that are “reasonable,”957 “reasonably and fairly determined,”958 “reliable,”959 and

“realistic.”960

700. As explained in sections 7.3.4.1 and 7.3.5.1 below, Compass Lexecon’s valuations are not

premised on a reasonable, well-informed, knowledgeable and prudent willing buyer. Rather,

they assume, for example, a negligent buyer who accepts at face value the Triennial Plan

(which does not even amount to a business plan, was never approved or implemented, and is

based on flawed assumptions) and premises its entire valuation of the Assets on it. This is

contrary to the Treaty and warrants the full dismissal of Compass Lexecon’s valuations.

953 I. Marboe, Compensation and Damages in International Law: the Limits of “Fair Market Value”, TDM, Vol. 4, Issue

6, November 2007, RLA-104, p. 735.

954 Vestey Group Ltd v. Bolivarian Republic of Venezuela, ICSID Case No. ARB/06/4, Award of 15 April 2016, RLA-5 ¶

402 (emphasis added).

955 Phillips Petroleum Company Iran v Islamic Republic of Iran and the National Iranian Oil Company, Award (1989-

Volume 21) Iran-US Claims Tribunal Report, CLA-12, ¶¶ 111-116, 154-58.

956 Starrett Housing Corporation and others v Government of the Islamic Republic of Iran, Final Award (1987-Volume 16)

Iran-US Claims Tribunal Report, CLA-11, ¶ 280.

957 Starrett Housing Corporation and others v Government of the Islamic Republic of Iran, Final Award (1987-Volume 16)

Iran-US Claims Tribunal Report, CLA-11, ¶¶ 278, 285, 287, 308, 319, 334.

958 Starrett Housing Corporation and others v Government of the Islamic Republic of Iran, Final Award (1987-Volume 16)

Iran-US Claims Tribunal Report, CLA-11, ¶ 287.

959 Starrett Housing Corporation and others v Government of the Islamic Republic of Iran, Final Award (1987-Volume 16)

Iran-US Claims Tribunal Report, CLA-11, ¶ 326.

960 Starrett Housing Corporation and others v Government of the Islamic Republic of Iran, Final Award (1987-Volume 16)

Iran-US Claims Tribunal Report, CLA-11, ¶¶ 311, 326.

Page 211: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

206

7.3.2 Claimant Adopts Incorrect Valuation Dates For The Mine Lease And The Antimony

Smelter

701. Article V of the Treaty provides that, in case of expropriation, compensation must be based

on the “market value of the investment expropriated immediately before the expropriation or

before the impending expropriation became public knowledge, whichever is the earlier

[…].”961 Accordingly, the Tribunal should value Colquiri as of 19 June 2012 (the day before

the Mine Lease Reversion Decree) (Section 7.3.2.1), and should value the Antimony Smelter

as of 30 April 2010 (the day before it reverted to the State) (Section 7.3.2.2).

7.3.2.1 The Fair Market Value Of The Mine Lease Must Be Assessed As Of 19 June 2012

702. Claimant argues that the “appropriate date for determining the FMV” of the Mine Lease is 29

May 2012, that is, “the day prior to the moment in which Glencore Bermuda finally and

irrevocably lost control of its investment […].”962 It denies that the FMV should be assessed

on the day prior to the Mine Lease Reversion Decree, 19 June 2012.

703. Claimant’s attempt to use the earlier 29 May 2012 valuation date is not innocent. Claimant

instructs its experts to use such date so as to include in their damages assessment potential

revenues from the Rosario vein (which, RPA acknowledges, is a “principal” vein of the

Mine)963 and thereby avoid the consequences of the 7 June 2012 Rosario Agreement, in which

Claimant willingly assigned the Rosario vein to the Cooperativa 26 de Febrero. When the

proper valuation date for Colquiri is applied (19 June 2012), any potential revenues from the

Rosario vein are excluded. Indeed, no willing buyer would have agreed to pay value for a

vein surrendered to the cooperativas.

704. Despite this attempt to escape from the consequences of its own actions, Claimant admits that

the date for valuation of an expropriation is no earlier than the date at which the investor

“finally and irrevocably lost control” of its investment.964 Thus, it is Claimant’s burden to

prove that it finally and irrevocably lost control of the Mine as of 30 May 2012. Claimant is

entirely unable to meet this burden.

705. First, Claimant retained control of the Mine until 20 June 2012 when the Mine Lease was

reverted. Bolivia understands that production of minerals from the Mine continued until 20

961 Treaty, C-1, Article V (emphasis added).

962 Statement of Claim, ¶ 255(iii).

963 RPA FBD Glencore v Bolivia Expert Report, ¶ 82.

964 Statement of Claim, ¶ 255(iii).

Page 212: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

207

June 2012,965 revealing that Claimant had not “finally and irrevocably lost control of its

investment […].” Moreover, as Claimant itself alleges, it entered into the Rosario Agreement

on 7 June 2012 with cooperativistas in which it agreed to turn over the Rosario vein of the

Mine.966 Although this action had the disastrous effects (of which Claimant now complains),

967 it conclusively demonstrates that Claimant remained in control of the Mine. In Claimant’s

words, the Rosario Agreement resulted in a “truce” that resulted in “the cooperatives [lifting]

their blockade”968 after 7 June 2009. One cannot offer something irrevocably lost.

706. Second, Glencore International’s own statements also confirm it had not “finally and

irrevocably lost control of its investment” as of 30 May 2012. In particular, Mr Eskdale (one

of Claimant’s witnesses), referring to the status of the negotiations as of 8 June 2012 (i.e., 9

days after allegedly losing control), states “[w]e were relieved that the conflict was over. We

had done our best to engage with the various stakeholders in order to reach a compromise

that would have allowed us to resume production, protect the safety of our workers, and still

be able to market the minerals extracted from the mine. For the first time in days we breathed

and slept […].”969 So, as of 30 May 2012, nothing was final or irrevocable.

707. The 2012 Annual Report for Glencore International admits that “[t]he Colquiri mine was

nationalised on 22 June 2012 and is no longer reported in Sinchi Wayra’s reserves and

resources.”970 Had Claimant really “finally and irrevocably lost control of its investment” in

May 2012, the Glencore group would have been required – pursuant to its reporting

obligations as a listed company – to inform the public. However, it was not until 22 June

2012 that, for the very first time, Glencore International reported that it had been deprived of

its investment in Colquiri:

Glencore International plc (“Glencore”) today received a signed Supreme

Decree from the Government of Bolivia, nationalising the Colquiri mine in the

Bolivian province of La Paz, with immediate effect. […].971

708. Third, the occupation of the Mine on 30 May 2012 by the cooperativistas could not have been

an expropriation by Bolivia. It is undisputed that the actions of the cooperativas are not

965 Statement of Claim, ¶ 220; Eskdale, ¶ 94.

966 Statement of Claim, ¶ 184(j).

967 Mineros de Colquiri bloquean conani exigiendo la emisión del D.S. de Nacionalización, Video (2012), R-224; La

Prensa, Colquiri se convierte en un campo de batalla, press article of 15 June 2012, C-142.

968 Statement of Claim, ¶ 220.

969 Eskdale, ¶ 94 (emphasis added).

970 Glencore Annual Report 2012, R-257, p. 71, note 2.

971 Glencore International’s response to the nationalization of the Colquiri mine in Bolivia, press release of 22 June 2012,

R-258.

Page 213: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

208

attributable to Bolivia. The cooperativistas are, obviously, not part of the Bolivian sState nor

affiliated with it in any way. Cooperativistas are workers in the informal mining sector who

have organized themselves into independent labor organizations. In fact, Claimant has not

even alleged that they are part of the State. Thus, even if Claimant lost control of the Mine

due to actions of the cooperativistas, it could not legally amount to an expropriation by

Bolivia.

709. By contrast, Bolivia never had control of the Mine prior to 20 June 2012. This point is not in

dispute between the Parties. To the contrary, Claimant repeated complains about Bolivia’s

lack of control of the Mine before that date (and falsely alleges that this lack of control

amounted to an FPS breach). As Claimant states, “policemen posted at the site failed to defuse

the situation and were unable to enter the mine” from “30 May 2012 until the formal

nationalization of the Colquiri Mine on 20 June 2012 […].”972 It is impossible that Bolivia

could have deprived Claimant of control of the Mine when Bolivia allegedly lacked control

over the situation.

710. Implicitly recognizing that the actions of the cooperativistas cannot constitute an

expropriation by Bolivia, Claimant adds the argument that Bolivia should have expelled the

cooperativistas from the Mine and the failure to do so breached the Treaty.973 However, as

extensively argued above,974 Bolivia took all available actions to defuse the situation at the

Mine that were legal and reasonable under the circumstances.

711. One, shortly after the occupation of the Mine by the Cooperativa 26 de Febrero, the State

engaged in negotiations with the workers and cooperativistas in an attempt to ensure Sinchi

Wayra’s operation of the Mine. As explained in section 2.6.3.2 above, it is undisputed that,

over the days that followed the occupation of the Mine, the Government sought Sinchi

Wayra’s and the unions’ support to work on a proposal to assign the San Antonio Vein to the

Cooperativa 26 de Febrero, and prepared up to 5 different offers which were then submitted

to the cooperativistas.975 Had Bolivia expropriated the Mine on 30 May 2012 (as Claimant

alleges), it would have not engaged in negotiations thereafter.

712. Two, Sinchi Wayra prompted the escalation of the violence in Colquiri with the execution of

the Rosario Agreement on 7 June 2012. Bolivia continued seeking a solution to the conflict

972 Statement of Claim, ¶ 184(g).

973 Statement of Claim, ¶ 255(iii).

974 See Section 2.6.3 above.

975 La Razón, Minería hace 5 ofertas, pero aun no convence a los cooperativistas, press article of 5 June 2012, R-215.

Page 214: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

209

created by Sinchi Wayra in the forthcoming days. This effort to resolve the conflict, however,

is not tantamount to a taking of the Mine by the State.

713. Three, while the Government’s proposal to revert the Mine Lease was on the table since early

June 2012, it is undisputed that the Reversion was only—and could have only been—

implemented on 20 June 2012.976 Indeed, Minister Romero confirms that the Mine Lease

Reversion Decree is the result of the agreements the Government had reached with

cooperativistas and the Mine workers the day before it was issued977 (that is, on 19 June

2012978).

714. For the foregoing reasons, Colquiri must be valued as of 19 June 2012 (i.e., the day before the

reversion of the Mine Lease).

7.3.2.2 The Antimony Smelter Should Be Valued As Of 30 April 2010 (Ex Ante)

715. Claimant claims that the Tribunal should value the Antimony Smelter as of the date of the

award.979 According to Claimant, “where the value of an investment has increased following

expropriation, full reparation may require […] the valuation date to be fixed at the date of

the award.”980 In effect, Claimant denies that the Treaty determines that the valuation date

for expropriation is the date prior to when the expropriation occurred or became public,

whichever is earlier.

716. However, Claimant’s sole argument to avoid the clear authority of the Treaty is to assert that

the Treaty’s plain terms for compensation do not apply to the alleged expropriations of the

Tin Smelter, Antimony Smelter, and Mine Lease because they were unlawful.981

717. Claimant’s sole argument rests on flawed foundations. Even if the Antimony Smelter

reversion was an expropriation (quod non), it was lawful. As fully explained in section 6.1.2,

Bolivia satisfied all Treaty obligations that would have applied to the reversion even if (quod

non) it was an expropriation. The Treaty obligation to provide compensation was not

breached because this arbitration will determine what compensation, if any, Bolivia owes to

Claimant. And a breach of the compensation provision of the Treaty would not, in any event,

976 Supreme Decree No 1.264 of 20 June 2012, C-39.

977 Romero, ¶¶ 13-18.

978 Agreement between the Government of Bolivia, COB, Fencomin, FEDECOMIN-LP, FSTMB, Central de Cooperativas

de Colquiri, and Sindicato Mixto de Trabajadores Mineros de Colquiri of 19 June 2012, R-18.

979 Statement of Claim, ¶ 255 (iv).

980 Statement of Claim, ¶ 254.

981 Statement of Claim, ¶ 229.

Page 215: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

210

render an expropriation unlawful within the meaning of that term in international law. Nor

was the Treaty obligation to provide due process breached, as the Treaty is explicit that this

requires nothing more than the opportunity to bring a posterior challenge to an expropriation,

which Claimant never even attempted.

718. Ex abundante cautela, even supposing that the Antimony Smelter’s reversion was unlawful

(quod non), Claimant errs when it asserts that the Treaty specifies no standard of

compensation in the Article V provision.982 It plainly does.

719. First, the State parties to the Treaty clearly and explicitly accepted a compensation provision

that is general in scope and that admits of no limitation to cases of lawful expropriation. As

the British Caribbean Bank tribunal insightfully noted, “at no point does the [Belize-United

Kingdom BIT], being a lex specialis, distinguish between lawful and unlawful expropriation,”

and concluded that the legality distinction is irrelevant.983 The Belize-United Kingdom BIT,

effectively identical to the Treaty in that neither distinguishes between lawful and unlawful

expropriation, states that:

Investments of nationals or companies of either Contracting Party shall not be

nationalized, expropriated or subjected to measures having effect equivalent to

nationalization or expropriation (hereinafter referred to as ‘expropriation’) in the

territory of the other Contracting Party except for a public purpose related to the

internal needs of that Party and against just and equitable compensation.984

720. The weight of authority from investment tribunals shows that, even absent such decisive text,

the treaty’s lex specialis on compensation applies to an expropriation contrary to the treaty’s

requirements.985 As Audley Sheppard observed, “the standard of compensation contained in

the investment protection treaty would appear to be a lex specialis that supersedes the lex

982 Statement of Claim, ¶ 229.

983 British Caribbean Bank Ltd. v. Belize, PCA Case No. 2010-18, Award of 19 December 2014, RLA-105, ¶ 260.

984 Agreement Between the Government of the Kingdom of Great Britain and Northern Ireland and the Government of

Belize for the Promotion and Protection of Investments of 30 April 1982, RLA-106, Article 5.

985 The Flughafen tribunal, for example, found that the expropriation had illegally violated due process but nonetheless

applied the treaty provision on compensation. Flughafen Zürich A.G. and Gestión e Ingenería IDC S.A. v. Bolivarian

Republic of Venezuela, ICSID Case No. ARB/10/19, Award of 18 November 2014, RLA-107, ¶¶ 739-747. Many other

cases consider expropriations that apparently are inherently unlawful but nevertheless apply the BIT provisions as lex

specialis and value the loss at the time of expropriation. See, Wena Hotels Ltd. v. Arab Republic of Egypt, ICSID Case

No. ARB/98/4, Award of 8 December 2000, RLA-68, ¶¶ 101, 118, 125; CME Czech Republic BV v Czech Republic

(UNCITRAL) Partial Award of 13 September 2001, CLA-32, ¶¶ 603, 611, 615-618; Técnicas Medioambientales

Tecmed SA v United Mexican States (ICSID Case No ARB(AF)/00/2) Award of 29 May 2003, CLA-43, ¶¶ 149, 187-

192; Abengoa, S.A. and COFIDES, S.A. v. United Mexican States, ICSID Case No. ARB(AF)/09/2, Award of 18 April

2013, RLA-66, ¶¶ 623, 681, 694.

Page 216: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

211

generalis of customary international law, and should apply in all cases of expropriation,

whether the conduct requirements have been complied with or not.”986

721. In short, the Treaty establishes that, if the Antimony Smelter reversion were an expropriation

(quod non), compensation must be assessed on the date the Antimony Smelter reversion

occurred or became public knowledge, whichever is earlier.

722. Second, the valuation date from the Treaty’s compensation provision applies to the Antimony

Smelter valuation for at least two additional reasons:

723. One, the Treaty’s compensation provision specifies the standard of full compensation

applicable for an expropriation. The parties to the Treaty agreed that valuation of the loss

immediately prior to the expropriation (or when it became public) would be sufficient to

provide full compensation. This is what constitutes full reparation for the purpose of a dispute

under the Treaty. There can be no reason to deviate from the will of the Treaty parties, as

expressed in Article V(1) of the Treaty when determining compensation.987

724. Two, unlike the valuation date established in the Treaty, the date of the award has no

connection to the breach and loss suffered; it is arbitrary.988 The compensation should not

vary just because a tribunal takes more or less time to arrive at an award. Moreover, using

the date of the award would allow investors to time litigation strategically and abusively in

order to maximize compensation. The only natural valuation date is immediately prior to the

expropriation.

725. Finally, Claimant argues that the loss should be valued as of the award date because there is

a lack of available information from the time of the expropriation (i.e., as of 30 April 2010,

the day before the reversion) to assign a value to the Antimony Smelter.989 This argument is

flawed.

726. There was official and reliable contemporaneous information (as of 2010) about the Antimony

Smelter’s land and buildings, which Ms Russo could have referred to (as Mr Mirones did990).

986 A. Sheppard, “The distinction between lawful and unlawful expropriation” in Investment Arbitration and the Energy

Charter Treaty, JurisNet LLC, 2006, RLA-64, pp. 196-197.

987 Treaty, C-1, Article V(1). According to Article V(1), compensation shall “amount to the market value of the investment

expropriated immediately before the expropriation or before the impending expropriation became public knowledge,

whichever is earlier […]”.

988 Markham Ball, Assessing Damages in Claims by Investors against States, 16 ICSID Review Foreign Investment Law

Journal 408, 2001, RLA-108, p. 417.

989 Statement of Claim, ¶ 255(iv); Informe de Avalúo - Gina Russo of 15 August 2017, ¶ 1.5.

990 Mirones, ¶¶ 11-13.

Page 217: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

212

Ms Russo could have accessed the public cadastre to obtain the cadastre value of the land, and

topographic maps, obtain tax related information on the Antimony Smelter as of 2010, among

others. As Mr Mirones explains:

[l]a información catastral en Bolivia tiene carácter público.

[…] el catastro de Oruro cuenta con información (oficial y muy relevante) sobre el

Terreno (entre otros, su valor catastral). La Arq. Russo ignoró esta información, a

pesar de estar disponible al 1 de mayo de 2010. También estaba disponible – a esta

misma fecha – información proveniente del Registro Público, de las autoridades

tributarias, etc.991

727. Yet, Ms Russo ignored these reliable sources as part of its valuation exercise and chose to

privilege the highly speculative information provided by real estate agents as well as a local

newspaper992 (far from specialized on real estate).993

728. For the above reasons, the Antimony Smelter should be valued as of 30 April 2010 (i.e., the

day immediately before it reverted to the State).

7.3.3 Compass Lexecon’s Valuations Ignore Key Premises For The Valuation Of Mining

Assets

729. Compass Lexecon relies on the DCF method994 to calculate the FMV of Colquiri, including

the Old Tailings Reprocessing Project995 (which is not a going concern) (as of 29 May 2012)

and of the Tin Smelter (as of 8 February 2007).

730. The DCF method projects future cash flows (expected until the end of the life of a project)

and then discounts them to the valuation date to obtain their net present value. The yearly

operating cash flows are calculated by subtracting the expenses (mainly capital expenses, or

“CAPEX”, and operating expenses, or “OPEX”) from the revenues (the product of

production volumes and price) that the enterprise valued is expected to generate during the

valuation period.996 Although the DCF valuation method is commonly used to value going

991 Mirones, ¶¶ 25-26 (Unofficial translation: “[c]adastral information is public in Bolivia. […] the Oruro cadastre

contains (official and very important) information on the Plot (amongst others, its cadastral value). Arc. Russo ignored

this information even though it was available on 1 May 2010. By the same date, information from the Public Registry,

from the tax authorities, etc. was also available”).

992 Econ One, ¶ 134.

993 Mirones, ¶ 45.

994 Compass Lexecon Expert Report, p. 7, Table 1.

995 Compass Lexecon Expert Report, Section V.1.1.b; Compass Lexecon Colquiri Valuation, CLEX-4, “Production”.

996 Econ One, ¶ 11.

Page 218: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

213

concerns, the accuracy of its results is highly dependent on the inputs used in the valuation

model.997

731. A key value driver in any DCF analysis of a mineral-producing asset are the reserves and

resources estimated to be produced in the future. Because of their impact on valuations and

to protect investors, mining companies are bound to report exploration results, mineral

resources and ore reserves by international standards and guidelines. Glencore International

reports its resources and reserves in accordance with (i) the JORC Code, (ii) the South African

Code for Reporting of Mineral Resources and Mineral Reserves (the “SAMREC Code”), and

(iii) the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Standards on

Mineral Resources and Reserves.998

732. In addition, there are well-known industry standards for the valuation and assessment of

mining assets, such as the Australasian Code for the Public Reporting of Technical

Assessments and Valuations of Mineral Assets (“VALMIN Code”), which, as stated by

Claimant, “provides a set of fundamental principles, minimum requirements and supporting

recommendations to assist in the assessment and valuation of mineral properties […].”999

733. According to the VALMIN Code, the valuation and technical assessment of mining assets

must be guided by the reasonableness principle.1000 Pursuant to this principle, a valuation

must be based on assumptions that are “impartial, rational, realistic and logical in its

treatment of the inputs […] to the extent that another Practitioner with the same information

would make a similar Technical Assessment or Valuation […].”1001

734. The inputs considered in a DCF valuation of a mining asset generally include: technical or

physical factors (e.g., resource and reserves tonnages, metal grades and recovery rates),

economic factors (e.g., price of minerals, production costs), and political and regulatory

997 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 1.

998 Reserves & Resources, Glencore <http://www.glencore.com/investors/reports-and-results/reserves-and-resources/ >

last visited 2 December 2017, R-254.

999 Statement of Claim, ¶ 245.

1000 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, Section 4.1; VALMIN Code 2005 - Australasian Code For Public Reporting of Technical Assessments

and Valuations of Mineral Assets, R-261, p. 22.

1001 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, Section 4.1. (emphasis added); VALMIN Code 2005 - Australasian Code For Public Reporting of

Technical Assessments and Valuations of Mineral Assets, R-261, p. 22.

Page 219: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

214

factors (e.g., taxes, environmental regulations).1002 The realistic and rational treatment of

these inputs determine the economic viability of a mining project.

735. These factors are never constant during the life of a mine.1003

736. Bolivia agrees with Claimant in that the DCF method is appropriate to value the Mine (except

for the Old Tailings Reprocessing Project, which is not a going concern) and the Tin Smelter.

However, Bolivia disagrees with Claimant’s experts’ grossly inflated valuation of these assets,

which results from their speculative and overly optimistic analysis.

737. Before setting out the specific criticisms to RPA’s analysis and Compass Lexecon’s

valuations, it is important to understand how each of the key factors mentioned above impacts

the valuation. We briefly address each of them below, beginning with mineral resources and

reserves (Section 7.3.3.1), grades or mineral concentration (Section 7.3.3.2), metallurgical

recovery rates (Section 7.3.3.3), production forecasts (Section 7.3.3.4), prices (Section

7.3.3.5), and operating and capital expenses (Section 7.3.3.6).

7.3.3.1 Mineral Reserves and Resources

738. A mineral resource is “a concentration or occurrence of solid material of economic interest

in or on the Earth’s crust in such form, grade (or quality), and quantity that there are

reasonable prospects for eventual economic extraction”,1004 i.e., its economic viability is yet

to be established (which calls into question whether any value should be attributed to them

for damages calculations). Also, “[t]he location, quantity, grade (or quality), continuity and

other geological characteristics of a Mineral Resource are known, estimated or interpreted

from specific geological evidence and knowledge, including sampling.”1005

1002 M. Samis, “Using Dynamic DCF and Real Option Methods for Economic Analysis in NI43-101 Technical Reports”, R-

262, p. 7.

1003 M. Samis, “Using Dynamic DCF and Real Option Methods for Economic Analysis in NI43-101 Technical Reports”, R-

262, p. 7.

1004 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 11, ¶ 20; JORC Code, 2004, Australasian Code for Reporting of Exploration Results, Mineral

Resources and Ore Reserves, RPA-32, p. 7; CIM Definition Standards For Mineral Resources and Mineral Reserves of

10 May 2014, R-263, p. 3; CIM Definition Standards For Mineral Resources and Mineral Reserves of 27 November

2010, R-264, p. 4.

1005 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 11, ¶ 20; JORC Code, 2004, Australasian Code for Reporting of Exploration Results, Mineral

Resources and Ore Reserves, RPA-32, p. 7; CIM Definition Standards For Mineral Resources and Mineral Reserves of

10 May 2014, R-263, p. 3; CIM Definition Standards For Mineral Resources and Mineral Reserves of 27 November

2010, R-264, p. 4.

Page 220: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

215

739. Pursuant to recognized industry standards,1006 mineral resources are classified, in order of

decreasing geological confidence, as either “measured”, “indicated” or “inferred.”

740. A “measured” mineral resource has the highest level of geological confidence:

[Its] grade (or quality), densities, shape, and physical characteristics are estimated

with confidence sufficient to allow the application of Modifying Factors to support

detailed mine planning and final evaluation of the economic viability of the deposit.

Geological evidence is derived from detailed and reliable exploration, sampling and

testing and is sufficient to confirm geological and grade or quality continuity

between points of observation […]. A Measured Mineral Resource has a higher

level of confidence than that applying to either an Indicated Mineral Resource or

an Inferred Mineral Resource. It may be converted to a Proven [Mineral] Reserve

or under certain circumstances to a Probable Ore Reserve.1007

741. An “indicated” mineral resource presents a lower level of geological confidence than a

“measured” mineral resource, but a higher level of confidence than an “inferred” mineral

resource:1008

An Indicated Mineral Resource is that part of a Mineral Resource for which

quantity, grade (or quality), densities, shape and physical characteristics are

estimated with sufficient confidence to allow the application of Modifying Factors

in sufficient detail to support mine planning and evaluation of the economic viability

of the deposit. Geological evidence is derived from adequately detailed and reliable

exploration, sampling and testing and is sufficient to assume geological and grade

(or quality) continuity between points of observation. An Indicated Mineral

Resource has a lower level of confidence than that applying to a Measured Mineral

Resource and may only be converted to a Probable Ore Reserve.1009

An Inferred Mineral Resource is that part of a Mineral Resource for which quantity

and grade (or quality) are estimated on the basis of limited geological evidence and

sampling. Geological evidence is sufficient to imply but not to verify geological and

grade (or quality) continuity. It is based on exploration, sampling and testing

information gathered through appropriate techniques from locations such as

outcrops, trenches, pits, workings and drill holes. An Inferred Mineral Resource has

1006 These standards include, among others: Australasian Code for Reporting of Mineral Resources and Ore Reserves

(prepared by the Joint Ore Reserve Committee (JORC)); Canadian National Instrument 43-101 (“NI 43-101”); U.S.

Securities & Exchange Commission Industry Guide 7; and, the SME Guide for Reporting Exploration Results, Mineral

Resources and Mineral Reserves.

1007 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 13, ¶ 23 (emphasis added); JORC Code, 2004, Australasian Code for Reporting of Exploration

Results, Mineral Resources and Ore Reserves, RPA-32, p. 7; See also, CIM Definition Standards For Mineral Resources

and Mineral Reserves of 10 May 2014, R-263, pp. 4-5; CIM Definition Standards For Mineral Resources and Mineral

Reserves of 27 November 2010, R-264, p. 5.

1008 CIM Definition Standards For Mineral Resources and Mineral Reserves of 10 May 2014, R-263, p. 4; CIM Definition

Standards For Mineral Resources and Mineral Reserves of 27 November 2010, R-264, p. 5.

1009 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 13, ¶ 22 (emphasis added); JORC Code, 2004, Australasian Code for Reporting of Exploration

Results, Mineral Resources and Ore Reserves, RPA-32, p. 7. See also, CIM Definition Standards For Mineral Resources

and Mineral Reserves of 10 May 2014, R-263, p. 4; CIM Definition Standards For Mineral Resources and Mineral

Reserves of 27 November 2010, R-264, p. 5.

Page 221: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

216

a lower level of confidence than that applying to an Indicated Mineral Resource and

must not be converted to an Ore Reserve.1010

742. Only “measured” and “indicated” resources are relevant for the determination of mineral

reserves. Indeed, due to their uncertainty, mining codes require the exclusion of “inferred”

resources from mining project feasibility and economic studies.1011 Similarly, well-known

industry regulations “prohibit[] the disclosure of the results of an economic analysis that

includes or is based on inferred mineral resources […].”1012 As explained below, Claimant

and its experts have deviated from this.

743. In particular, it bears emphasizing that, per the industry standards cited above, mineral

resources may only be delineated based on geological data gathered through “exploration,

sampling and testing” activities (depending on how detailed exploration is, resources, if any,

may then be classified as “measured”, “indicated” or “inferred”).

744. A mineral reserve is “the economically mineable part of a Measured and/or Indicated Mineral

Resource […].”1013 Mineral reserves can only be determined by pre-feasibility and/or

feasibility studies, which consider all of the relevant “modifying factors” (i.e., mining,

metallurgical, economics, marketing, legal, environmental, social and governmental

factors)1014 before determining whether mining extraction is technically and economically

feasible or not. Modifying factors play a key role in assessing mining viability and, hence, in

valuations. As explained in the VALMIN Code, a life-of-mine plan is a study of a mining

operation where:

All modifying factors have been considered in sufficient detail to demonstrate

at the time of reporting that extraction is reasonably justified. Such a study

1010 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 12, ¶ 21 (emphasis added); JORC Code, 2004, Australasian Code for Reporting of Exploration

Results, Mineral Resources and Ore Reserves, RPA-32, p. 7; See also, CIM Definition Standards For Mineral Resources

and Mineral Reserves of 10 May 2014, R-263, p. 4. CIM Definition Standards For Mineral Resources and Mineral

Reserves of 27 November 2010, R-264, p. 5.

1011 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, pp. 12-13 (emphasis added); JORC Code, 2004, Australasian Code for Reporting of Exploration Results,

Mineral Resources and Ore Reserves, RPA-32, p. 7; See also, CIM Definition Standards For Mineral Resources and

Mineral Reserves of 10 May 2014, R-263, p. 4; CIM Definition Standards For Mineral Resources and Mineral Reserves

of 27 November 2010, R-264, p. 5.

1012 NI 43-101 Standards of Disclosure for Mining, R-265, Section 2.3(1) (emphasis added).

1013 CIM Definition Standards For Mineral Resources and Mineral Reserves of 10 May 2014, R-263, p. 5 (emphasis added);

CIM Definition Standards For Mineral Resources and Mineral Reserves of 27 November 2010, R-264, p. 5.

1014 SRK, footnote 37.

Page 222: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

217

should be inclusive of all development and mining activities proposed through

to the effective closure of the existing or proposed mining operation.1015

745. Reserves are classified into “proven” and “probable.” A proven mineral reserve is “the

economically mineable part of a Measured Mineral Resource”1016 (which, consequently, has

the highest degree of geological and economic certainty), and a probable mineral reserve is

“the economically mineable part of an Indicated, and in some circumstances, a Measured

Mineral Resource.”1017

746. The increasing level of geological confidence between the different types of mineral resources

and reserves, and the relevance of the modifying factors to assess the technical and economic

viability of a mining project, are illustrated in the following diagram:1018

747. Claimant’s experts, however, disregard these fundamental industry standards and practices

and value a “magical mine.” In Claimant’s “magical mine,” resources are delineated and

reserves replenish “magically” without the need for exploration,1019 and 100% of such reserves

and resources are mined (including inferred resources,1020 which international standards

1015 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, p. 41, Glossary – Life-of-Mine Plan (emphasis added). See also VALMIN Code 2005 - Australasian

Code For Public Reporting of Technical Assessments and Valuations of Mineral Assets, R-261.

1016 CIM Definition Standards For Mineral Resources and Mineral Reserves of 10 May 2014, R-263, p. 6; CIM Definition

Standards For Mineral Resources and Mineral Reserves of 27 November 2010, R-264, p. 5.

1017 CIM Definition Standards For Mineral Resources and Mineral Reserves of 10 May 2014, R-263, p. 6; CIM Definition

Standards For Mineral Resources and Mineral Reserves of 27 November 2010, R-264, p. 5.

1018 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, p. 9; JORC Code, 2004, Australasian Code for Reporting of Exploration Results, Mineral Resources

and Ore Reserves, RPA-32, p. 6.

1019 RPA FBD Glencore v Bolivia Expert Report, ¶¶ 46-54.

1020 SRK, Table 1.

Page 223: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

218

consider to be geologically uncertain). As a result, Claimant’s experts’ valuation is grossly

inflated and should be dismissed by the Tribunal.

7.3.3.2 Grade Or Mineral Concentration

748. The grade is the concentration of metal in a ton of mineralized material. The grade (calculated

in grams/ton) is the basis for determining how much revenue can be obtained from the

mineralized material and, hence – once all costs are considered – for determining whether it

would be economical to mine such material. Thus, in the valuation of mineral deposits, the

estimation of average grade is more significant than the estimation of tonnage.1021

749. There is a certain grade below which it is not economically viable to mine and process, even

though metal is present in the ore.1022 This is known as the cut-off grade. The cut-off grade

reflects the minimum concentration of metal that is required to exist in a ton of mineralized

material so that revenue equals the costs necessary to produce said metal (i.e., to breakeven).

In addition, for the purposes of valuing Colquiri and the Tin Smelter, two additional notions

are also relevant: (i) the head grade or concentration of metal in the ore extracted from the

mine as delivered to the metallurgical plant for the production of concentrates, and (ii) the

grade of the resulting concentrates that will then go through the smelting process.

750. Much like in the estimation of reserves, the average grade is estimated through sampling.

However, average grade estimates carry a larger margin of error than the estimation of

reserves mainly for two reasons.1023 First, the grade may exhibit considerable variation

throughout a deposit (e.g., in underground mines, such as Colquiri, ceteris paribus, grade is

expected to decrease as extraction moves deeper into the Mine). Second, waste material is

expected to be mined with the ore (dilution). Due to dilution, the grade of ore, as mined, will

necessarily be lower than the grade of ore present in the mine.1024 This, in turn, increases costs

and reduces revenue (for every ton of mineral mined, less grade of metal will be processed).

It is, therefore, fundamental that any DCF valuation appropriately reflect the level of

dilution.1025 As explained by Prof. Rigby, with respect to Colquiri, “Due to dilution, the grade

of the ore, as mined, will necessarily be lower than the in situ grade of the ore present in the

mine. This is clearly demonstrated by comparing the proven and probable reserve grades with

1021 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 4.

1022 SRK, ¶ 45, Section 7.3.6.

1023 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 4.

1024 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 4.

1025 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 5.

Page 224: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

219

the actual mined grades over the years (Figure 2 and Figure 3), which are generally

materially lower for both tin and zinc.”1026

751. Yet, despite the fact that no real deep exploration drilling had been undertaken and little (if

any knowledge) existed, in 2012, as to grade continuity for tin and zinc in Colquiri, Claimant’s

experts assume unreasonably high and constant head grades as part of their valuation. Indeed,

the head grades for both tin (1.29%) and zinc (7.52%) projected by RPA (which would

allegedly remain constant from 2014 until 2030) fail to account for dilution and are, thus, too

elevated. Likewise, for the Tin Smelter, Claimant’s experts adopt optimistic, constant

concentrate grades, disregarding the fact that, as mining moves deeper into the mines where

the concentrates are sourced from (underground mines, such as Colquiri and Huanuni), grades

are expected to decrease.

7.3.3.3 Metallurgical Recovery Rates

752. The metallurgical recovery rate refers to the valuable metal recovered from a ton of mineral

through metallurgical treatment. When estimating this rate, there are two important aspects

to consider:

753. First, because the characteristics of minerals (including its grade) will usually vary throughout

the mine, the metallurgical recovery rate is not expected to remain constant throughout the

life of the mine. As explained by Prof. Rigby, “[t]here is often a relationship between the

head or feed grade to a process plant and the resulting metallurgical recovery. The higher

the head grade, the higher the metallurgical recovery and vice versa […].”1027 Therefore,

among others, metallurgical recoveries will be affected by the variance of grade present

throughout the ore.

754. Second, metallurgical recovery is generally said to be a function of the fragmentation size of

ore. The smaller the size of fragmentation, better recovery, and vice versa. Because these

two variables have a direct impact on processing costs and plant productivity, a higher

recovery rate will bring along higher costs and slower production rates (a basic rule that

Claimant’s experts disregard).

755. Consequently, metallurgical recovery has a major impact in the economics of a mining

project. Accordingly, the application of reasonable recovery rates (which Claimant’s experts

1026 SRK, ¶ 60.

1027 SRK, ¶ 92.

Page 225: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

220

have failed to do for Colquiri and the Tin Smelter) in a DCF valuation is as important as the

application of proper grades.

7.3.3.4 Production Forecasts

756. The ore production forecast is based on the scale of the mineral reserve (tonnages) and the

market’s ability to absorb the final product.1028 Historical operating experience can be

generally used to forecast reliably production rates.1029 However, because there is only a

limited amount of valuable mineral in a mine, historical operating rates will not necessarily

be the driving proxy for the entire life of the mine.

757. Once the annual rate of ore production has been established, the rate of production for the

saleable mineral may be determined. The production schedule should be determined

considering, among others, the ore production forecast, the grade of the mined ore (i.e., the

cut-off grade and dilution factor), and metallurgical recovery. Essentially, these factors will

reduce the quantity of the saleable mineral which will be produced from the ore, making the

rate of production of saleable mineral lower than the rate of ore production.1030

758. In addition to those mentioned above, when estimating the production rate of the saleable

mineral, a DCF valuation should also consider (i) the cost of producing a ton of saleable

mineral (i.e., cost of mining, cost of processing a ton of material and overhead costs), and (ii)

market prices.

759. In the case of Colquiri, there is a significant number of operating factors limiting the

production,1031 including the plant’s treatment capacity, the availability of water and

electricity in the Colquiri area, and the dam’s capacity. As explained by Eng. Moreira:

Es fundamental tener presente que la operación de la mina Colquiri es un proceso

continuo, es decir, para que la producción pueda aumentar no basta con encontrar

más recursos o reservas minerales; hay que tener equipos con suficiente capacidad

de extracción, recursos humanos e insumos (como aire, agua, energía eléctrica)

para luego poder procesarlos en la planta concentradora y tener espacio donde

depositar la colas que se generan.1032

1028 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 5.

1029 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 5.

1030 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 7.

1031 SRK, ¶ 26.

1032 Moreira, ¶ 31 (Unofficial translation: “It is crucial to bear in mind that the operation of the Colquiri mine is an ongoing

process, that is, in order to increase production, it is not sufficient to find more resources or mineral reserves; it is

necessary to have equipment with sufficient capacity for extraction, human resources and consumables (like air, water,

electric energy) in order to process them in the concentrating plant and space to deposit the tailings that are generated”).

Page 226: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

221

760. Claimant’s experts gloss over these limitations.

761. In the case of the Tin Smelter, Claimant’s experts’ production estimates disregard the poor

state of the Smelter’s infrastructure and production units (those that were operative) at the

time of the reversion, projecting unjustifiably high production rates that are (even)

inconsistent with the Tin Smelter’s historical operating performance.

7.3.3.5 Prices

762. The forecasted annual revenues of a mining asset are the product of the annual production of

saleable mineral and market prices.

763. Prices are one of the main determinants of value.1033 The VALMIN Code establishes that any

report that includes a forecast of revenue “must set out a reasonable basis for price-related

assumptions applying to any product(s) derived from the Mineral Asset […].”1034 Price related

assumptions include, among others: current and forecasted market conditions, forecast

product prices, sales volumes, and smelter treatment and refinery charges.

764. As stated in the VALMIN Code, future economic conditions may greatly influence the

economic viability and value (if any) of a mineral asset.1035 Therefore, a valuation should

include accurate and reliable forecasts with supporting evidence.1036

7.3.3.6 Operating And Capital Expenses

765. In any DFC valuation, once revenues are estimated, they are subtracted by the estimated

expenses in order to obtain the projected annual operating free cash flows of the valued asset.

In the case of Colquiri1037 and the Tin Smelter, this requires reasonably projecting mining and

processing costs, smelting costs, other operating costs, capital costs and closure costs – which

Claimant’s experts have failed to do.

1033 M. Samis, “Using Dynamic DCF and Real Option Methods for Economic Analysis in NI43-101 Technical Reports”, R-

262, p. 7.

1034 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, Section 7.6(a) (emphasis added); VALMIN Code 2005 - Australasian Code For Public Reporting of

Technical Assessments and Valuations of Mineral Assets, R-261, p.16.

1035 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, Section 9.4; VALMIN Code 2005 - Australasian Code For Public Reporting of Technical Assessments

and Valuations of Mineral Assets, R-261, p. 17.

1036 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, Section 9.4; VALMIN Code 2005 - Australasian Code For Public Reporting of Technical Assessments

and Valuations of Mineral Assets, R-261, p.16.

1037 SRK, ¶¶ 40-41.

Page 227: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

222

766. The VALMIN Code establishes that the valuator “should review and describe the actual and

forecast capital and operating costs for the estimated productive life of the Mineral Assets

[…].” Furthermore, it provides that “capital and operating costs should take into account any

likely changes with time in factors such as work practices and productivity, and […] assess

whether they are realistic and achievable […].”1038

767. A fundamental principle of mine economics is that costs are determined by the amount of

mined and processed minerals, while revenues are determined by the amount of metal

produced.1039 As explained above, as the dilution in a tonnage of mine material increases, the

grade of mineral in the tonnage decreases.1040 This increases costs, and decreases revenue.

Therefore, the costs of a project depend largely on the grade of the ore. A company with a

lower grade of ore will have to process more rock at a greater cost, in order to obtain the same

amount of economically valuable material than a company with a higher grade of ore.1041 It

is, therefore, paramount to the valuation of a mining asset to account for the variance of grade

during the life of the mine as an element of cost.

768. Changes in capital and operating costs should also be considered. Equipment used in the mine

and process plant will have to undergo maintenance, overhauls, be rebuilt and, ultimately, be

replaced during the mine life, a new dam may be required, etc.

769. Additionally, costs specific to the mining operation at hand should be factored into the

valuation. For underground mining, it is key to consider that, as the mining operations move

deeper into the mine, the thickness and, consequently, weight of the over-lying rock increases,

inevitably increasing costs. Likewise, production expansions will usually be preceded by

important investments in studies and equipment.

770. Finally, any valuation should include appropriate mine closure and reclamation costs.

771. This phase may last several years. Closure costs include remediation and rehabilitation, which

shall be considered in accordance with the environmental regulations in force at the mine

location and may take several years. These costs largely depend on the particular

circumstances of the mine and ore characteristics, existence of tailings and waste materials,

and post closure water quality. Closure and remediation are typically defined by a mine

1038 The VALMIN Code - Australasian Code For Public Reporting of Technical Assessments and Valuations of Mineral

Assets, R-260, Section 7.5 (emphasis added); VALMIN Code 2005 - Australasian Code For Public Reporting of

Technical Assessments and Valuations of Mineral Assets, R-261, p. 16.

1039 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 5.

1040 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 5.

1041 C. Lattanzi, “Discounted Cash Flow Analysis. Inputs Parameters and Sensitivity”, R-259, p. 5.

Page 228: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

223

closure plan with costs allocated to remediation and refined throughout the life cycle of the

mine. Reclamation costs are the costs incurred for all the physical facilities to be

decommissioned, dismantled and removed from the site.

772. Claimant’s experts ignore or underestimate the Assets’ operating and capital expenses. For

instance, in the case of Colquiri, they ignore the increased costs that come with moving deeper

into the mine, and also those that result from dilution. In the case of the Tin Smelter,

Claimant’s experts ignore the need to make significant capital investments to increase

production (they assume that very-old furnaces, dating back to the 70s, will continue to

operate during the next 20 years). Glencore’s experts also ignore or underestimate the closure,

remediation and reclamation costs for all of the Assets, thus inflating their values.

7.3.4 Compass Lexecon’s Valuation Of Colquiri Is Flawed As It Is Based On Unrealistic And

Incorrect Assumptions Concerning Key Value Drivers

773. Claimant claims US$ 443.1 million as the FMV of Colquiri as of 29 May 2012,1042 in which

the Old Tailings Reprocessing Project represents 26% of the amount claimed, that is, over

US$ 100 million.1043

774. Compass Lexecon’s valuation is premised on a negligent, unreasonable and misinformed

willing buyer (Section 7.3.4.1). In addition, Compass Lexecon’s DCF model is based on

unrealistic and incorrect inputs, including an unduly low discount rate (Section 7.3.4.4),

which result in inflated values for the Mine Lease (Section 7.3.4.2) and the Old Tailings

Reprocessing Project (Section 7.3.4.3).

7.3.4.1 Compass Lexecon’s Valuation Is Premised On A Negligent And Misinformed Willing Buyer

775. The FMV standard requires that any valuation be premised on a reasonable, well-informed,

knowledgeable and prudent willing buyer and seller. This is not the case of Compass

Lexecon’s willing buyer.

776. Indeed, while Compass Lexecon acknowledges that the cornerstone of its valuation is the

Triennial Plan,1044 it ignores that a willing buyer would have realized or done, at least, three

things:

1042 Statement of Claim, ¶ 276.

1043 Econ One, ¶ 46, footnote 73.

1044 Compass Lexecon Expert Report, ¶52.

Page 229: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

224

777. First, it would have realized (i) that the Triennial Plan is simply aspirational (i.e., it is an

internal document that was never seriously assessed (much less approved) by Colquiri’s

management), (ii) that the Triennial Plan does not include any economic, social or

environmental analyses (all of which are fundamental to assess the viability of a plan of this

nature), and (iii) that the investments, purchases, etc., that, per the Triennial Plan, were

supposed to be undertaken between July 2011 (the Triennial Plan’s date) and 20 June 2012

(the day in which the Mine Lease was reverted) were not carried out,1045 and thus dismiss this

Plan.

778. Second, it would have audited the Triennial Plan, realized its assumptions are overly

optimistic and dismissed it. Indeed, as explained by Bolivia’s experts, among others, the

Triennial Plan assumes (i) the existence of magical resources and reserves whose existence is

not supported by any exploration (and, in fact, where the operator will never need to invest in

exploration), (ii) that the processing plant’s production will almost double in a two-year

period,1046 which “tests all credibility”,1047 and (iii) that the Mine’s operation costs will

decrease over time as a result of economies of scale, which is inconsistent with Colquiri’s

historical performance (Colquiri has never benefited from economies of scale and, in fact, has

a track record for underestimating costs).1048

779. Claimant’s experts aggravate this situation. Aside from assuming – without any independent

critical analysis – that all of the Triennial Plan’s aspirations would materialize, they further

assume that the Plan’s 2014 aspirations would remain constant throughout the life of the mine

(i.e., for 17 ½ years, until 2030). Notably, this is what RPA does in relation to head grades

(i.e., 7.52% zinc and 1.29% tin) and metallurgical recoveries (i.e., 76% zinc and 72% tin).

Needless to say, as this is contrary to basic industry knowledge, any willing buyer would have

dismissed these assumptions.

780. Third, it would have realized that the Triennial Plan makes no reference to the Old Tailings

Reprocessing Project and, given its economic uncertainty and the fact that it had been

neglected since 2004 by the operator, not assign any value to it.

781. Compass Lexecon’s willing buyer ignores all of these considerations.

1045 Claimant has not submitted any authorizations for expenditures (AFEs), which are typically required before making

these types of investments or incurring in these types of expenditures.

1046 2012-2014 Colquiri Mine Three-year Plan, C-108, p. 88.

1047 SRK, ¶ 57.

1048 Econ One, ¶¶ 74-75.

Page 230: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

225

782. Even assuming, arguendo, that a willing buyer could have given some credit to the Triennial

Plan, such buyer would have considered, at the very least, that (i) the Triennial Plan’s

projections would need to be revised in light of the social conflicts that arose at the Mine after

July 2011 (the Triennial Plan’s date), and, (ii) in any case, that the Triennial Plan’s

implementation would take much longer than estimated in that Plan. Again, Compass

Lexecon’s willing buyer does none of this.

783. Beyond the Triennial Plan, Compass Lexecon ignores that, when assessing the FMV of

Colquiri, any willing buyer would have considered, at least, three things:

784. First, the shared-risk agreement that Claimant was negotiating with the State (pursuant to the

requirements of the 2009 Constitution) when the Mine Lease was reverted. The Rosario

Agreement, signed on 7 June 2012, already acknowledged that “COLQUIRI S.A. se encuentra

en proceso de migración del contrato de arrendamiento a un contrato de asociación con

COMIBOL […].”1049 Similarly, Glencore International’s press release of 22 June 2012 states

that “[t]he nationalisation of the Colquiri mine was announced just as Glencore was finalising

the renegotiation of its mining contracts with the Government of Bolivia. The new agreement

would have provided for a State participation of up to 55% of the profits (increasing the total

Government take to 77-79%) […].”1050 Such negotiation, per Glencore International’s own

admission, would have resulted in the State receiving a larger share of the value of Colquiri’s

operations that under the Mine Lease. Accordingly, no reasonable buyer would have paid

value for the Mine Lease without discounting the renegotiation, which is what Compass

Lexecon does.

785. Second, the Rosario Agreement, signed on 7 June 2012, whereby Glencore International

(through Sinchi Wayra and Colquiri) willingly assigned the Rosario vein to the Cooperativa

26 de Febrero.

786. Third, the social conflicts and violence existing in the Colquiri area (described in section 2.6.3

above), and the resulting risk of State intervention.

1049 Agreement between Colquiri SA, Fedecomin, Fencomin, Central Local de Cooperativas Mineras de Colquiri,

Cooperativa Minera Collpa Cota, Cooperativa Minera Socavón Inca, and Cooperativa 26 de Febrero, C-35, Clause

Eight, p. 2 (Unofficial translation: “COLQUIRI S.A. is currently in process of migration from the lease contract to an

association contract with COMIBOL”).

1050 Glencore International’s response to the nationalization of the Colquiri mine in Bolivia, press release of 22 June 2012,

R-258.

Page 231: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

226

787. Although each one of these situations has a direct impact in Colquiri’s FMV, none were

considered by Compass Lexecon. This suffices to dismiss its valuation as highly speculative

and exagerated.

7.3.4.2 Compass Lexecon’s Valuation Of The Mine Lease Is Inflated

788. Compass Lexecon’s valuation of the Mine Lease rests entirely on the Triennial Plan (adopted

by RPA at face value). This plan, among other flaws, assumes that, by 2014, (i) production at

Colquiri would have almost doubled, and (ii) there would be “reserves of 2,353,000 tonnes

and resources of 5,529,000 tonnes […].”1051 Then, based on RPA’s analysis, which forecasts

another 17 ½ years of production at Colquiri on the unsupported basis that it “fully expect[s]

that the history of [mineral resource and ore reserve] replacement will continue”,1052

Compass Lexecon estimates the NPV of the Mine Lease as of 29 May 2012 at US$ 443.1.

789. Section V.1 of Compass Lexecon’s report describes the different variables considered in its

valuation. These include (i) reserves and resources, (ii) production and processing schedule,

(iii) grades and metallurgical recovery rates, (v) zinc and tin prices, (vi) operating and capital

expenses (to process ore into tin concentrate), and (vi) discount rate.1053 Because Compass

Lexecon relies on unsupported, speculative or simply exaggerated variables, its valuation

cannot be relied upon. Indeed, “[a] model is only as good as the assumptions it uses. Faulty

assumptions or bad data result in faulty output”1054 (garbage in, garbage out). Bolivia

addresses these variables below.

a) Compass Lexecon assumes, with no support, the magic delineation of

resources and replenishment of reserves at the Mine

790. Compass Lexecon’s valuation is premised “on RPA’s opinion that the life of the mine could

be extended beyond the resources and reserves registered [i.e., reported to the public] given

the mine operator’s long history of replenishing the reserves and resources […].”1055 Based

on this, Compass Lexecon projects “production until the end of the Colquiri Lease in 2030

[…].”1056

1051 Compass Lexecon Expert Report, ¶ 51.

1052 RPA FBD Glencore v Bolivia Expert Report, ¶ 86.

1053 Statement of Claim, ¶ 267.

1054 M. Maher, C. Stickney, R. Weil, Managerial Accounting. An Introduction to Concepts, Methods and Uses, 10th ed.,

2008, R-266, p. 184.

1055 Compass Lexecon Expert Report, ¶ 52 b).

1056 Compass Lexecon Expert Report, ¶ 52 b).

Page 232: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

227

791. Needless to say, the magic delineation of resources and replenishment of reserves (which

results in an estimate of 10.7MT of mineable material until 20301057) has a key impact on

Compass Lexecon’s valuation.

792. Bolivia has appointed Prof. Neal Rigby as its mining expert in this arbitration. Prof. Rigby

holds a PhD from the University of Wales, where he was the Industrial Research Director in

Mining and Minerals Engineering (Department of Mining) for seven years. Prof. Rigby is

also a founding partner of SRK (UK), a leading international consulting firm that provides

advice in the mining and metals industry. SRK has more than 1,400 professionals

internationally in over 45 offices in 6 continents, and Prof. Rigby has served as its Global

Group Chairman for 15 years. In his more than 40 years of experience in the mining industry,

Prof. Rigby has performed independent assessments of resources and mineral reserves, project

evaluations and audits, feasibility studies, among many other matters of great relevance in this

arbitration.

793. As explained by Prof. Rigby, “there is no basis in fact for the 10.7Mt of mineable material

assumed by RPA […].”1058 As of Claimant’s valuation date (29 May 2012), these resources

and reserves “had not yet been found by exploration […].”1059 This is confirmed by Glencore

International’s 2011 Annual Report, which shows that, as of 31 December 2011, there were

only 4.1811060 MT of resources (excluding inferred resources, which are too speculative

geologically to be considered1061) and 1.55 MT of reserves at Colquiri.1062

794. Furthermore, Compass Lexecon’s valuation assumes that 100% of these resources and

reserves would be mined.1063 Had Claimant’s experts visited the Mine and met with Colquiri’s

management (including Eng Moreira), they would have known that, historically, only 60% of

resources and 90% of reserves have been mined.1064 Indeed:

1057 RPA FBD Glencore v Bolivia Expert Report, ¶ 175.

1058 SRK, ¶ 55.

1059 SRK, ¶ 77.

1060 RPA FBD Glencore v Bolivia Expert Report, p. 20, Table 1.

1061 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) 2012

Edition, R-255, pg. 12; JORC Code, 2004, Australasian Code for Reporting of Exploration Results, Mineral Resources

and Ore Reserves, RPA-32, p. 7; See also, CIM Definition Standards For Mineral Resources and Mineral Reserves of

10 May 2014, R-263, pg. 4; CIM Definition Standards For Mineral Resources and Mineral Reserves of 27 November

2010, R-264, p. 5.

1062 Glencore Annual Report 2011, R-252, p. 72.

1063 SRK, ¶ 55.

1064 Moreira, ¶¶ 12, 66-67.

Page 233: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

228

En la mina Colquiri, el promedio de reservas que llegan a producción es solamente

de 90%. El 10% restante se deja en el interior de la mina por factores de seguridad

como pilares (cuando hacemos voladuras) y puentes de 5 metros para mantener el

nivel superior de la galería. Si voláramos toda la parte superior, nos quedaríamos

sin piso por donde caminar.

Por otro lado, no todo recurso necesariamente se convierte en reserva. En la mina

Colquiri existe una probabilidad de, más o menos, 60% de que los recursos se

conviertan en reservas […].1065

795. After making the necessary adjustments, as of June 2012, Prof. Rigby concludes that a willing

buyer would have only given value to 2.5 MT of resources (4.181 x 0.6) and 1.4 MT of

reserves (1.555 x 0.9) as reported by Colquiri.

b) Compass Lexecon’s production and plant processing forecasts are unduly

high

796. It is exclusively on the basis of the Triennial Plan that RPA and Compass Lexecon’s valuation

assumes a “[p]roduction rate of 360 ktpa in 2012 increasing to 551 ktpa in 2014 […].”1066

Then, based on RPA’s analysis, Compass Lexecon goes on to assume that the production

forecasted for 2014 (i.e., 550,579 MT) would remain constant until 2030.1067 This production

forecast is wrong for, at least, five reasons.

797. First, as explained above, the Triennial Plan is merely an aspirational document that was never

seriously assessed (much less approved) by Colquiri’s management. Eng Moreira, Colquiri’s

Mine Superintendent at the time the Triennial Plan was prepared (July 2011), was not aware

of its existence until this arbitration. The investments, purchases, etc., that, per the Triennial

Plan, were supposed to be made from July 2011 (the Plan’s date) to 20 June 2012 (when the

Mine Lease was reverted) were never carried out. What happened with this Plan is a mystery.

Consequently, it is not reasonable to assume – as Compass Lexecon’s valuation does – that

the 2014 Triennial Plan’s production forecasts would be achieved.

798. Second, RPA’s production estimates (throughout the life of the Mine) are based on resources

and reserves which “had not yet been found by exploration”1068 neither as of Claimant’s

1065 Moreira, ¶ 66, (Unofficial translation: “In the Colquiri mine, the average reserves that reach production is only 90%.

The remaining 10% is left in the mine interior for safety reasons as pillars (when we carry out blasting) and 5-metre

long bridges to maintain the raised floor level of the gallery. If we blast the entire raised section, there wouldn’t be a

floor on which to walk”).

1066 RPA FBD Glencore v Bolivia Expert Report, ¶ 47.

1067 Compass Lexecon Expert Report, ¶ 52(b); RPA FBD Glencore v Bolivia Expert Report, ¶¶ 90-95.

1068 SRK, ¶¶ 66, 77.

Page 234: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

229

valuation date (29 May 2012) nor as of Bolivia’s valuation date (19 June 2012). Thus, those

resources and reserves cannot be considered for forecasting production, as RPA does.

799. Third, even if, arguendo, the abovementioned reserves and resources existed, it would not be

feasible for a mine like Colquiri to reach RPA’s production forecasts. As explained by Prof.

Rigby, “[f]or a mine with the operational constraints that Colquiri has, I do not believe that

it would be technically and practically feasible to double the production rate. Even more, to

suggest that this would happen over a period of two years as projected by RPA tests all

credibility”.1069 Also, as explained by Eng Moreira, even after investing US$ 77 million in

Colquiri’s processing plant, production will still come below 320,000 MT (far less than

projected by RPA) because of the existence of several constraints. Indeed, Eng Moreira

explains that “[e]n la actualidad, seguimos operando con el mismo equipo en el Cuadro

Victoria con las mismas limitantes en cuanto a la capacidad de extracción”1070 and “tenemos

muchos problemas de agua […]. En cuanto a la energía, hemos tenido que incluir, como parte

de la contratación de la nueva planta que vamos a construir, […] un nuevo transformador

[…]. [E]l transformador [existente] estaba trabajando [ya] a su capacidad máxima […].”1071

800. Fourth, RPA’s production forecasts include production from the Rosario vein, which was

assigned to the cooperativas before the alleged expropriation.1072 Claimant cannot pretend to

be compensated for production that belongs, per its own agreement, to someone else. And, in

any event, no willing buyer would accept to pay value for reserves/resources from a vein

transferred by the mine operator to a third party.

801. Fifth, RPA’s production estimates are inconsistent with Colquiri’s own internal estimates. As

explained by Econ One, “in 2012 alone, Compass Lexecon’s expected production is 21.2%

higher than the production amount forecasted in the Colquiri management reports for 2012,

[and] 19.5% higher than the amount that could have been expected based on the actual levels

of ore processed in first part of 2012, prior to the Claimant’s valuation date”.1073 This same

1069 SRK, ¶ 57.

1070 Moreira, ¶ 43, (Unofficial translation: “[c]urrently, we continue to operate with the same equipment in the Victoria

Block with the same limitations on extraction capacity).

1071 Moreira, ¶¶ 36-37 (Unofficial translation: “we have many problems with water […]. Concerning energy, we had to

include, as part of the new plant that we are going to construct, […] a new transformer. […] [T]he [existing]

transformer was [already] working at its maximum capacity”).

1072 Agreement between Colquiri SA, Fedecomin, Fencomin, Central Local de Cooperativas Mineras de Colquiri,

Cooperativa Minera Collpa Cota, Cooperativa Minera Socavón Inca, and Cooperativa 26 de Febrero, C-35.

1073 Econ One, footnote 54.

Page 235: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

230

exaggeration is reflected in Compass Lexecon’s estimates until the end of its estimated life of

the mine.

c) Compass Lexecon assumes that unduly high head grades will remain

constant throughout the life of the mine, contrary to the reality of the Mine

and industry practice

802. Compass Lexecon’s valuation further assumes that the Mine has a “[t]otal mineable resource

of 10.7 Mt grading 1.29% Sn and 7.52% Zn based on a mine life of 20 years”.1074 These

grades estimates are unduly high (and the assumption that they will remain constant over time

is wrong) for, at least, three reasons.

803. First, the head grades estimated by RPA do not account for the substantial waste dilution that

is incurred during the mining process. As explained by Prof. Rigby, “[a] higher waste dilution

increases costs and reduces revenues because, for every ton of mineral mined, less grade of

metal may be processed. RPA’s analysis does not take this into consideration, thus projecting

too elevated head grades for tin and zinc”.1075

804. Second, Claimant’s experts have not undertaken any deep exploration that would allow them

to predict grade continuity through the mineral deposit.1076 Furthermore, this assumption is

inconsistent with the reality of Colquiri. As explained by Prof. Rigby, future mining will

require going deeper into the Mine, which will negatively impact grades.1077

805. Third, RPA’s estimated head grades (of 1.29% Sn and 7.52% Zn) are inconsistent with

Colquiri’s reality. For instance, Colquiri’s head grades for zinc were at 6,83% as of June

20121078, and yet Compass Lexecon assumes – with no justification whatsoever – that such

head grades will increase by almost 1% only 6 months later (by the end of 2012), and remain

constant during the next 20 years of mine life.1079

d) Compass Lexecon assumes that unduly high metallurgical recoveries will

remain constant throughout the life of the mine, contrary to the reality of the

Mine and industry practice

1074 Compass Lexecon Colquiri Valuation, CLEX-4; RPA FBD Glencore v Bolivia Expert Report, ¶ 46 (emphasis added).

1075 SRK, ¶ 61 (emphasis added).

1076 SRK, ¶ 62.

1077 SRK, ¶ 63.

1078 Compass Lexecon Colquiri Valuation, CLEX-4, “Historical Data”, “Revenues”.

1079 Compass Lexecon Colquiri Valuation, CLEX-4, “Revenues”.

Page 236: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

231

806. Compass Lexecon assumes “[m]etallurgical recoveries of 72% for tin and 76% for zinc” from

2012 until the end of the Mine life.1080 These recovery estimates are unduly high (and the

assumption that they will remain constant in time is simply wrong) for, at least, three reasons.

807. First, RPA’s recovery rates are inconsistent with Colquiri’s historical performance. RPA

projects recoveries “of 72% for tin and 76% for zinc” from 2012 until 2030 (i.e., for a 17 ½

year period) even though, in 2011 and the first half of 2012, metallurgical recoveries at

Colquiri were around 60% or less for both tin and zinc.1081 More generally, as explained by

Econ One, “the historical average rate of recovery for zinc was 69.6%, which RPA and

Compass Lexecon assume will increase to 76.0%. Historically tin was recovered at a rate of

65.5%, compared with RPA and Compass Lexecon’s assumption 72.0%”1082. Colquiri’s

actual recovery rates (after 2012) confirm the exaggeration of RPA’s estimates (after 2012,

“metallurgical recoveries for both zinc and tin continued to remain substantially below those

projected by RPA […]”).1083

808. Second, there is no analysis or testwork that supports the metallurgical recoveries assumed by

RPA. As explained by Prof. Rigby, “There is simply no rigorous analytical or testwork

support for these improvements [i.e., of 72% for tin and 76% for zinc] and certainly not in the

long term for ore which has not yet been found by exploration. Typical testwork would have

included, for example, bench scale, locked cycle tests, pilot plant and metallurgical simulation

analysis.”1084

809. Third, it is wrong to assume that metallurgical recoveries will remain constant in time. Given

that, as explained above, head grades are expected to decrease over time because mining will

move deeper into more sulfurous areas of the Mine, metallurgical recoveries would also be

expected to decrease. As explained by Prof. Rigby, “there is often a relationship between the

head or feed grade to a process plant and the resulting metallurgical recovery. The higher

the head grade, the higher the metallurgical recovery and vice versa”.1085 Indeed, as Eng

1080 Compass Lexecon Colquiri Valuation, CLEX-4, “Revenues”.

1081 SRK, ¶ 66. Average recoveries between 2007 and 2012 were 63.62% for tin and 68.21% for zinc, thus remaining

substantially below RPA’s estimates. SRK, ¶ 66.

1082 Econ One, ¶ 41.

1083 SRK, Table 2, ¶ 49.

1084 SRK, ¶ 66.

1085 SRK, ¶ 92.

Page 237: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

232

Villaviencio eloquently explains, there is “una regla de oro de la metalurgia: a mayor ley,

mayor recuperación y viceversa.”1086

810. The unduly high (and unrealistic) processing forecasts, head grades and metallurgical

recoveries estimated by Claimant’s experts (discussed in the previous subsections) result in

exaggerated production estimates.1087

e) Compass Lexecon’s valuation relies on non-verified sales prices

811. As discussed above, metal prices are one of the key inputs to estimate future revenues, thus

having a direct impact on the NPV of the Mine Lease. In order to forecast its concentrates’

sales prices, Compass Lexecon (i) first, forecasts tin and zinc ingot prices (based on publicly

available forecasts) and then, (ii) adjusts those prices based on the terms of contracts signed

by Colquiri and Glencore International.1088 Econ One has expressed a number of reservations

with Compass Lexecon’s sales prices estimates.

812. In relation to tin and zinc ingot prices, Compass Lexecon has not relied on any internal price

forecasts from Colquiri, Sinchi Wayra S.A. or Glencore International even though such

forecasts most likely exist (mining companies such as Glencore International will usually use

such forecasts to inform its revenue expectations).1089

813. In relation to concentrate prices, Compass Lexecon relies on contracts signed by Colquiri and

Glencore International, which, per Claimant’s account, were related companies at the time.1090

Consequently, these contracts may not reflect arm length terms, yet Compass Lexecon has not

made any comparisons or analyses to validate the reasonability of such terms. Moreover,

although some of these contracts date back to 2007, Compass Lexecon has not made “any

revisions to reflect changing market dynamics from 2007 to its valuation date in 2012”.1091

f) Compass Lexecon underestimates capital and operating expenses

814. The capital expenditures and operating costs considered by Compass Lexecon are unduly low

for, at least, seven reasons.

1086 Villavicencio, ¶ 72 (Unofficial translation: “a golden rule of metallurgy: the higher the grade, the greater the recovery

and vice versa”).

1087 Econ One, ¶ 43.

1088 Econ One, ¶ 53.

1089 Econ One, ¶ 55.

1090 Statement of Claim, ¶ 36.

1091 Econ One, ¶ 62.

Page 238: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

233

CAPEX

815. Although Compass Lexecon’s valuation assumes that production would increase to 551,000

MT by 20141092 (which is technically unfeasible), it underestimates the investments that would

be (theoretically) needed to support such production increase.

816. First, Compass Lexecon considers an investment of US$ 27.3 million to build a new

processing plant at Colquiri (the existing processing plant had been working at full capacity

for several years by the valuation date).1093 This amount is clearly insufficient, as

demonstrated by the fact that, currently, Colquiri is building a new processing plant at a cost

of US$ 77 million.1094

817. Second, Compass Lexecon considers an investment of US$ 5 million (Phase I) to build a new

tailings dam at Colquiri1095 (given that the existing dam was soon to reach its maximum

capacity as of the valuation date, a new dam would be needed to dispose of the additional

tailings resulting from the increased production). The amount considered by Compass

Lexecon is, however, unduly low, as further expansions of the dam would be expected. As

explained by Prof. Rigby, “[w]hile the Triennial Expansion Plan makes reference to US$

5 million for increased tailings capacity, this is totally inadequate for the fivefold increase in

tailings production [coming from the processing plant’s expansion and the Old Tailings

Project] as proposed by RPA.”1096 Furthermore, the Tribunal should note that the Huanuni

mine recently built a new tailings dam at a cost of US$ 9.5 million for the first phase (plus the

cost of the land and contingent expenses).1097

818. Third, Compass Lexecon estimated reclamation and closure costs for Colquiri at

US$ 3.3 million.1098 This unduly low estimate ignores Colquiri’s long operating history

(which results in higher environmental damages that will need to be remediated) and its very-

old infrastructure (which will need to be dismantled). As explained by Prof. Rigby, “[i]n my

opinion and, having visited the site, [Compass Lexecon’s reclamation and closure costs

estimate] is inadequate for a site with such a long operating history (as indicated in Section

1092 Compass Lexecon Colquiri Valuation, CLEX-4; RPA FBD Glencore v Bolivia Expert Report, ¶ 176.

1093 Colquiri, Triennial Plan 2012-2014, July 2011, CLEX-7, p. 119; RPA FBD Glencore v Bolivia Expert Report, ¶ 181.

1094 Moreira, ¶ 35.

1095 Colquiri, Triennial Plan 2012-2014, July 2011, CLEX-7, p. 202.

1096 SRK, ¶ 85.

1097 Moreira, ¶ 63.

1098 Compass Lexecon Colquiri Valuation, CLEX-4; RPA FBD Glencore v Bolivia Expert Report, ¶ 53.

Page 239: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

234

5 above, the Colquiri mine was in operation since Colonial times) and such extensive and

largely ageing facilities and infrastructure”.1099

OPEX

819. Compass Lexecon’s valuation also underestimates the OPEX required by its assumed

increased production.

820. First, Compass Lexecon’s valuation ignores that, as a result of its increased production

forecasts, more energy will be needed to sustain operations. As indicated by Eng Moreira, “el

costo de energía eléctrica no tiene lógica en su proyección, ya que si se tiene previsto el

incremento de la producción también debería incrementar el gasto por energía en similar

magnitud a partir de una nueva planta.”1100 To date, producing far less than forecasted by

Compass Lexecon, Colquiri had to acquire a new energy transformer, given that “[…] el

transformador [existente] estaba trabajando [ya] a su capacidad máxima”.1101

821. Second, in order to justify its low OPEX figures, RPA and Compass Lexecon assumes that,

as a result of its increased production, Colquiri will benefit from economies of scale and thus

reduced costs. As explained by Econ One, “[e]conomies of scale are present whenever

operating costs increase less than proportionately with production, in this case ore

processed”.1102 Compass Lexecon’s assumption is contradicted by Colquiri’s own operating

history, which any willing buyer would review as part of its due diligence. Indeed, even

though its production increased over time, Colquiri was never able to benefit from economies

of scale. For instance, from 2006 to 2007, Colquiri processed 8% more ore but its operating

costs increased by 22%.1103

822. Third, mining at Colquiri (in the future) will be in deeper levels of the Mine. As a result,

mining operations will become more remote from the central infrastructure, which will result

in higher operating costs. Compass Lexecon’s valuation ignores these higher costs, and how

they will be (even) higher as a resulted of its increased production estimates.

1099 SRK, ¶ 72.

1100 Moreira, ¶ 79 (Unofficial translation: “the estimated cost of electric power is illogical since, if an increase in production

is foreseen, energy expenditures should be increased proportionally for a new plant”).

1101 Moreira, ¶¶ 36-37 (Unofficial translation: “the [existing] transformer was [already] working at its maximum capacity”).

1102 Econ One, ¶ 68.

1103 Econ One, ¶ 68.

Page 240: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

235

823. Fourth, Compass Lexecon includes general and administrative costs of US$ 2 million per year

based on Colquiri’s historical costs.1104 Compass Lexecon underestimates overall costs by

cherry-picking between the management reports and the audited financial statements for its

estimates.1105 Indeed, had However, the management reports relied upon by Compass

Lexecon show that, historically, Colquiri’s general and administrative costs were much

higher. As explained by Econ One,

824. For the above reasons, the Tribunal should conclude that Compass Lexecon’s valuation of the

Mine Lease is inflated, and dismiss it outright.

7.3.4.3 The Old Tailings Reprocessing Project Was Not A Going Concern, Or, In Any Event,

Economically Viable As Of Claimant’s Or Bolivia’s Valuation Date, And It Is Not So Today

Either

825. Claimant maintains it would have invested on the Old Tailings Reprocessing Project on the

basis of a Feasibility Study prepared in 2004 (i.e., 8 ½ years before the Mine Lease was

reverted), and that this Project would have allowed it “to recover approximately 10 million

tonnes of old tin and zinc tailings located next to the Colquiri Mine Operations”.1106 Based

on this, and RPA’s analysis, Compass Lexecon estimates the NPV of the Old Tailings

Reprocessing Project at more than US$ 100 million.1107

826. Claimant’s claim is baseless and speculative.

827. In limine, Claimant’s valuation of the Old Tailings Reprocessing Project (which represents

more than US$ 100 million of the damages claimed by Claimant for Colquiri) is inherently

speculative. Although no one has ever operated this Project, Claimant’s experts’ value it

based on the DCF method and assuming it is a going concern with a proven record of

profitability. Needless to say, this results in an arbitrary and highly speculative valuation (all

of the inputs used in the DCF valuation are unsupported and were arbitrarily-chosen).

828. Moreover, there are, at least, ten reasons why this Project would not have been implemented

and, in any case, why this Project would not have resulted in any positive NPV to Claimant.

1104 Compass Lexecon Expert Report, ¶ 55.

1105 Econ One, ¶¶ 55-56, 76-77.

1106 Statement of Claim, ¶ 271.

1107 Econ One, ¶¶ 45-47.

Page 241: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

236

829. First, any willing buyer would have placed significant weight in the fact that Sinchi Wayra

never developed this project. Under Claimant’s account, it purportedly acquired control of

the Colquiri Mine in March 2005, thus having 7 ½ years (i.e., between March 2005 and June

2012, when the Mine Lease was reverted) to develop this project.1108 It did not do so and

neither RPA nor Compass Lexecon explain why. The only reasonable assumption a willing

buyer would have made in 2012 is that the Project’s economic viability was not enough to

meet Claimant’s hurdle rate. Indeed, this Project was the subject of several feasibility studies

in the 1980s and early 2000s (studies prepared by Minproc in 1988 and by PAH in 2004) and,

still, to date, no mine operator has invested on it. As explained by Eng Moreira:

lo que el Ing. Lazcano no se pregunta es por qué si este proyecto era tan

atractivo, no fue puesto en marcha durante la administración privada (ni en

la actualidad). Muy sencillo, además de las limitaciones físicas que ya

expliqué, el reprocesamiento de las colas requiere inyectar una cantidad

importante de capital para permitir el tratamiento de las colas y su viabilidad

no es segura.1109

830. Second, RPA’s estimated head grades for the tailings are unduly high, and its assumption that

they will remain constant throughout the life of the mine is mistaken. For instance, RPA

estimates head grades for zinc at 4.21% even though the feasibility study on which RPA relies

(to conclude that Colquiri would have implemented the Old Tailings Reprocessing Project)

estimates zinc head grades at only 3.74%.1110 Furthermore, RPA’s assumption regarding

constant grades ignores that the more recent tailings in the shallow part of the dam – which

would be reprocessed first – have a lower grade than the older tailings – which are deposited

deeper in the dam – because they result from the use of newer processing technologies (which

can extract more metal than older technologies).1111

831. Third, RPA’s estimated metallurgical recovery rates are unduly high (65% for zinc and 50%

for tin), and the assumption that they will remain constant throughout the life of the mine is

likewise mistaken. As explained by Prof. Rigby, “[t]here is often a relationship between the

head or feed grade to a process plant and the resulting metallurgical recovery. The higher

the head grade, the higher the metallurgical recovery and vice versa”.1112 Given that, as

1108 Statement of Claim, ¶ 36.

1109 Moreira, ¶ 83 (emphasis added) (Unofficial translation: “what Eng. Lazcano does not question is why if the project was

so attractive, it was never commissioned during the private administration (or today). Very simply, in addition to the

physical limitations that I already mentioned, reprocessing tailings requires spending an important amount of capital

to allow the treatment of tailings and its viability is not certain”).

1110 Colquiri Tailings Feasibility Study, 2004, CLEX-13, p. 13; RPA FBD Glencore v Bolivia Expert Report, ¶ 55.

1111 Moreira, ¶ 87.

1112 SRK, ¶ 93.

Page 242: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

237

explained above, old tailings’ head grades will be variable and lower than estimated by RPA,

so will be metallurgical recoveries.

832. Fourth, because it adopted the Triennial Plan at face value, Compass Lexecon has only

considered an investment of US$ 5 million for the construction of a new tailings dam. This

is clearly insufficient, given that (i) the existing dam has almost reached full capacity, and (ii)

the increased production estimated by RPA (i.e., 550,579 MT from the Mine’s processing

plant every year (since 2014) combined with the new tailings from the Old Tailings Project)

will result in a vast amount of additional tailings that will need to be disposed of (as explained

by Eng Moreira “implica multiplicar por 500% nuestra producción.”1113). The Huanuni mine

recently built a new tailings dam (Phase I) at a cost of US$ 9.5 million (plus the cost of

purchasing the land).1114 Consequently, Compass Lexecon should have estimated a much

larger investment for the construction of the tailings dam.

833. Fifth, RPA considers an investment of US$ 30.5 million for the construction of a new tailings

reprocessing plant,1115 which is clearly insufficient.

834. Sixth, the operating costs estimated by RPA for the Old Tailings Reprocessing Project are

unduly low. As explained by Prof. Rigby, there is only a small difference between the regular

ore treatment process and the old tailings reprocessing (“[g]iven the fact that the old tailings

have already been processed once, the proposed new process flowsheet (for the old tailing)

essentially only eliminated the frontend crushing stage from the existing flowsheet (used in

the regular operations of the Colquiri plant))”1116. Consequently, operating costs for the old

tailings reprocessing (estimated at US$ 13.16 / ton by RPA) are expected to be substantially

higher and, in any case, closer to the regular ore treatment costs (US$ 20.201117).

835. Seventh, while Compass Lexecon estimated capital and operating costs based on the 2004

feasibility study,1118 it has not adjusted those costs for inflation or to reflect other changes

resulting from the passage of time.

1113 Moreira, ¶ 18.

1114 Moreira, ¶ 63.

1115 RPA estimates capital costs “at $46.5 million over the project life, including $30.5 million for initial plant construction

and $15 million for sustaining capital.” See RPA FBD Glencore v Bolivia Expert Report, ¶ 61.

1116 SRK, ¶ 88.

1117 RPA FBD Glencore v Bolivia Expert Report, ¶ 23

1118 Compass Lexecon Expert Report, ¶ 56.

Page 243: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

238

836. Eight, RPA and Compass Lexecon assume that there would be sufficient water in the Colquiri

area to sustain their increased levels of production, and that operating costs would not be

affected. However, this is not the case. As explained by Eng Moreira, “habría que hacer

maravillas para poder operar estas dos plantas [expanded processing plant and Old Tailings

Project], en particular por la falta de agua y energía. En estos momentos, con una capacidad

de tratamiento en planta de 1.300 tpd, ya tenemos muchos problemas de agua – es,

simplemente, imposible encontrar suficiente agua en la zona”.1119

837. Ninth, RPA and Compass Lexecon ignore that the cooperativistas were already exploiting the

old tailings.1120 Therefore, given the social implications, the implementation of the Old

Tailings Reprocessing Project would not be as straightforward and short-term as Eng Lazcano

now pretends.1121 As Eng Moreira explains:

Difícilmente íbamos a poder iniciar la explotación de las colas cuando ya estaban

siendo explotadas por la Cooperativa 21 de Diciembre, que incluso había abierto

túneles y bocaminas en la ladera del dique.1122

838. Tenth, RPA estimates reclamation and closure costs for the Old Tailings Reprocessing Project

at US$ 1 million.1123 As explained by Prof. Rigby, this estimate is unduly low. Prof. Rigby

expects the total reclamation and closure costs of Colquiri (i.e., for the Mine and the Old

Tailings Reprocessing Project) to be around US$ 8 million.1124

839. For the above reasons, the Tribunal should conclude that the Old Tailings Reprocessing

Project would not have been implemented and, even assuming, arguendo, it had been, that

this project would not have resulted in a positive NPV as of the valuation date. Consequently,

the Tribunal should dismiss Claimant’s damages claim.

1119 Moreira, ¶ 36 (Unofficial translation: “[…] miracles would be needed to operate these two plants, especially due to the

lack of water and energy. At the time, with the plant’s treatment capacity of 1,300 tons per day we already have water

issues – it is simply impossible to find sufficient water in the area”).

1120 Public deed of sublease of tailings, subscribed by Compañía Minera Colquiri S.A. and the Cooperativa “21 de Diciembre

Colquiri LTDA” of 10 March 2006, R-39.

1121 Lazcano, ¶ 33.

1122 Moreira, ¶ 58 (Unofficial translation: “It would have been difficult to start exploiting the tailings when they were being

exploited by the Cooperativa 21 de Diciembre, which had even opened tunnels and mine entrances in the dam’s side”).

1123 RPA FBD Glencore v Bolivia Expert Report, ¶ 62.

1124 SRK, ¶ 71.

Page 244: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

239

7.3.4.4 The Discount Rate Used By Compass Lexecon To Estimate The NPV Of Colquiri’s Future

Cash Flows Is Unrealistically Low

840. Compass Lexecon discounts the projected cash flows of Colquiri (i.e., resulting from the Mine

Lease and the Old Tailings Reprocessing Project) at a rate equivalent to Colquiri’s WACC as

of 29 May 2012, which Compass Lexecon estimates at 12.3%.1125

841. Compass Lexecon’s discount rate is unduly low. Bolivia will not repeat here the criticisms

developed by Econ One in its report; rather, Bolivia will only make two general comments

that reflect the arbitrariness of Compass Lexecon’s discount rate calculation:

Compass Lexecon has estimated a country risk premium that only reflects Bolivia’s

sovereign default risk. However, as explained by Econ One, “the calculation of the

country default spread is only the first step in the calculation of the country risk

premium, since it only measures the risk of default on sovereign debt. The second step

is to apply an adjustment to take into account the additional risks inherent in the

equity market of a particular country that are not captured in the yield spread [i.e.,

equity risk premium]”.1126 Had Compass Lexecon considered Bolivia’s equity risk

premium, it would have obtained a much higher country risk premium; and

Compass Lexecon has not considered an illiquidity/size premium in its calculations.

When calculating the WACC (based on the Capital Asset Pricing Model – CAPM) of

smaller firms, as in the present case (Colquiri is a small firm), an illiquidity/size

premium must be applied to better reflect their cost of capital. This is the case

because, as explained by Econ One, most of the inputs used to calculate CAPM refer

to large companies (much larger than Colquiri). Since an investment in a smaller firm

is more volatile than an investment in a larger firm, calculating the CAPM without

considering the size of the company would underestimate its true cost of capital.

Furthermore, the CAPM measures the cost of capital for large publicly-traded

companies which are considered to be very liquid assets, and this is not the case of

Colquiri (an illiquid physical asset).

842. After correcting for these (and other) flaws, Econ One estimates Colquiri’s discount rate as of

19 June 2012 at 22.13%.1127

1125 Compass Lexecon Expert Report, ¶ 74.

1126 Econ One, ¶ 167 (emphasis added).

1127 Econ One, ¶ 92.

Page 245: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

240

843. For the above reasons, the Tribunal should conclude that Compass Lexecon’s valuation of

Colquiri is inflated, and dismiss it outright. Were the Tribunal to consider that Claimant has

suffered damages that are certain and should be compensated (quod non), such compensation

should be limited to US$ 39.7 million.1128 However, this compensation must be adjusted to

reflect (i) Claimant’s contribution to its own loss (section 7.5) and (ii) the compensation

already received by Claimant from its insurer (sections 2.5.4 and 2.6.1).

7.3.5 Compass Lexecon’s Valuation Of The Tin Smelter Is Flawed As It Is Based On

Unrealistic And Incorrect Assumptions

844. According to Compass Lexecon, the FMV of the Tin Smelter as of 8 February 2007 would be

US$ 65.9 million.1129 As in the case of Colquiri, Compass Lexecon projects the Tin Smelter’s

future cash flows (until 2026, when RPA estimates the Tin Smelter’s production life will end),

and then discounts them to obtain its NPV as of the valuation date.

845. In limine, Compass Lexecon’s (inflated and unrealistic) valuation is inconsistent with the

statements made by Claimant after the reversion of the Tin Smelter, where it expressed that it

had suffered no material losses as a result of the reversion. Claimant’s 2011 IPO prospectus

states that:

[I]n 2007, the Bolivian government nationalised a smelter owned by a

subsidiary of Glencore. However, in that instance, no material losses were

sustained and Glencore continues to do business in Bolivia.1130

846. Similarly, as explained above, Compass Lexecon’s valuation is inconsistent with Colquiri’s

operating history. As explained by Econ One, while the Tin Smelter’s EBIDTA ranged

between US$ 0.4 million to US$ 14.7 million for the 7 years leading up to the valuation date,

Compass Lexecon’s valuation assumes that such EBIDTA would have been approximately 3

times higher during the next 20 years.1131

847. Compass Lexecon’s valuation of the Tin Smelter is premised on a negligent, unreasonable

and misinformed willing buyer (Section 7.3.5.1). Furthermore, it relies on unduly high

production forecasts (Section 7.3.5.2), unduly high revenue forecasts (Section 7.3.5.3),

underestimates operating and capital expenses (Section 7.3.5.4), and applies an unduly low

discount rate (Section 7.3.5.5). These flaws are discussed below.

1128 Econ One, Table 1.

1129 Statement of Claim, ¶¶ 258-265.

1130 Prospectus of Glencore International plc of 3 May 2011, R-193, p. 13 (emphasis added).

1131 Econ One, ¶¶ 100-101.

Page 246: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

241

7.3.5.1 Compass Lexecon’s Valuation Of The Tin Smelter Is Premised On A Negligent, Unreasonable

And Misinformed Willing Buyer

848. Compass Lexecon appears to ignore that the FMV standard requires that the Tin Smelter’s

valuation be premised on a reasonable, well-informed, knowledgeable and prudent willing

buyer.

849. As explained in section 2.5.4 above, as of 2005, it was already publicly known that the State

was considering regaining ownership of the Tin Smelter. Indeed, “[t]he press reported that

members of the Bolivian Parliament, including MAS members, had requested ‘una reversión

de la empresa metalúrgica Vinto, a favor del Estado’ (a request backed by cooperativistas

from Huanuni, also controlled at the time by RGB).”1132

850. Any willing buyer in 2007 would have, therefore, factored in this risk when estimating the

FMV of the Tin Smelter. As explained by the Venezuela Holdings tribunal:

Article 6(c) of the BIT requires that the compensation due in case of expropriation

represent “the market value of the investments affected before the measures

are taken or the impending measures became public knowledge, whichever is

earlier”. This means that the compensation must correspond to the amount

that a willing buyer would have been ready to pay to a willing seller in

order to acquire his interests but for the expropriation, that is, at a time

before the expropriation had occurred or before it had become public that it

would occur. The Tribunal finds that, it is precisely at the time before an

expropriation (or the public knowledge of an impending expropriation) that the

risk of a potential expropriation would exist, and this hypothetical buyer would

take it into account when determining the amount he would be willing to pay in

that moment.1133

851. Compass Lexecon’s willing buyer, however, ignores this risk, which results in an inflated

valuation of the Tin Smelter.

852. A reasonable, well-informed, knowledgeable and prudent willing buyer would consider all

available information about the asset before making its decision and take an active approach.

In conducting a due diligence of the Tin Smelter, a willing buyer would find that the

production units were old (i.e., had been in operations for more than 30 years) and obsolete,

and that some units were out of service. Any willing buyer would have thus concluded that

1132 See section 2.5.4.

1133 Venezuela Holdings, B.V., Mobil Cerro Negro Holding, Ltd., Mobil Venezolana de Petróleos Holdings, Inc., Mobil

Cerro Negro, Ltd., and Mobil Venezolana de Petróleos, Inc. v. Bolivarian Republic of Venezuela, ICSID Case No.

ARB/07/27, Award of 9 October 2014, RLA-65, ¶ 365 (emphasis added).

Page 247: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

242

significant refurbishment and modernization. Indeed, as Eng Villavicencio explains when

describing the state of the production units:

era indispensable modernizar la operación (para reducir costos y mantener la

producción). De lo contrario, en 5 años habríamos comenzado a operar a

pérdida.1134

No reparar y renovar los equipos y maquinaria productiva, que tenían más de 30

años de operaciones, habría significado que nos quedásemos a la zaga de la

economía mundial en cuanto a la producción de estaño metálico, soportando costos

de producción más altos que otras fundidoras. Invertir en nuevos equipos y

tecnología resultaba imperativo para mantener la producción. De hecho, en 2008

tuvimos una fuerte pérdida en la empresa debido a la falta de disponibilidad de

reverberos.1135

7.3.5.1 Claimant’s Valuation Of The Tin Smelter Is Inflated

853. Section V.2 of Compas Lexecon’s report describes the different variables considered in its

DCF valuation of the Tin Smelter. These are (i) production schedule, (ii) grades recoveries

and prices, (iii) operating and capital expenses, and (iv) the Tin Smelter’s discount rate

(calculated based on the WAAC).1136 Given that the inputs used in Compass Lexecon’s model

are mistaken, so is its valuation.

a) Compass Lexecon relies on unduly high production forecasts

854. Claimant maintains that “[b]ased on the smelter’s capacity, its historical performance and

RPA’s analysis, Compass Lexecon projects that, but-for the expropriation, Vinto’s Tin

Smelter would have processed 30,000 tonnes of tin concentrate annually from 2008, with a

tin recovered yield of 46.6 percent.”1137 This is wrong for, at least, three reasons.

855. First, RPA’s production estimates are inconsistent with the Tin Smelter’s historical

performance. As explained by Econ One, the processing capacity of the Tin Smelter remained

below 20,000 MT up through 1999, and then remained at or below 25,000 MT between 2003

and 2006.1138 Thus, it is not reasonable to assume, as RPA does, that (i) the Tin Smelter will

1134 Villavicencio, ¶ 47 (Unofficial translation: “it was crucial to modernize the operation (in order to reduce costs and

maintain production). Otherwise, in 5 years we would have started to operate at a loss”).

1135 Villavicencio, ¶ 49 (Unofficial translation: “If we didn’t repair and update the equipment and production machinery,

which had been operating for more than 30 years, we would have remained behind the world economy regarding the

production of metallic tin and thus we would have borne higher production costs than other smelters. Investing in new

equipment and technology was crucial to maintain production. For instance, in 2008 we faced an important loss in the

company due to the lack of availability of reverberatory furnaces”).

1136 Compass Lexecon Expert Report, ¶ 77.

1137 Statement of Claim, ¶ 259.

1138 Econ One, ¶¶ 103-108

Page 248: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

243

process 30,000 MT per year, and (ii) that such production rate will remain constant throughout

the life of the Smelter.

856. Second, RPA’s projections ignore the reality of the Tin Smelter. As explained by Eng

Villavicencio, when it reverted to the State in February 2007, “[l]os hornos y demás unidades

de producción [de la Fundidora de Estaño] se encontraban en estado obsoleto.”1139 In these

circumstances, it is not reasonable to assume that the Tin Smelter would reach its highest

historical production as of the year following the reversion (i.e., as of 2008). Quite the

opposite. Eng Villavicencio explains that “[d]e hecho, en 2008 tuvimos una fuerte pérdida

en la empresa debido a la falta de disponibilidad de reverberos.”1140 The production levels

projected by RPA have not even been attained even after the US$ 39 million investment made

by the Tin Smelter in the Ausmelt Furnace (i.e., the latest smelting technology), which neither

RPA nor Compass Lexecon consider.1141

857. RPA’s sole justification for its increased production estimates is the so-called “investments”

made in the Tin Smelter between 2002 and 2006, which would, allegedly, contribute to

increased production. But this is highly misleading. As explained by Eng Villavicencio,

EMV’s General Manager, all of the so-called “investments” listed by RPA are nothing more

than operating expenses aimed at sustaining the continuity of operations.1142 Among these

operating expenses are “construcción de duchas y vestuarios adecuados para los

trabajadores”, “[c]ambios en el material de los filtros empleados en el sistema de filtración

de emisiones gaseosas”, and “[i]nstalación de un sistema neumático para el golpeado

mecánico del horno.”1143 They have no bearing on production.

858. Third, Claimant’s experts’ production forecasts are also untethered from the reality of the tin

market in Bolivia. Indeed, Claimant’s experts assume that the Tin Smelter would process

30.000 annual tons of concentrates to produce 14.000 annual tons of ingots as of 2008 for 18

years, but ignores the fact that there is a lack of sufficient tin concentrates in the Bolivian

market. As Eng Villavicencio explains:

1139 Villavicencio, ¶ 46 (Unofficial translation: “[t]he furnaces and other production equipment [in the Tin Smelter] were

obsolete”).

1140 Villavicencio, ¶ 49 (Unofficial translation: “[f]or instance, in 2008 we faced an important loss in the company due to

the lack of availability of reverberatory furnaces”).

1141 Villavicencio, ¶ 64.

1142 Villavicencio, ¶ 39.

1143 Villavicencio, ¶¶ 77, 83-84 (Unofficial translation: “construction of appropriate showers and changing rooms for

workers”, “[c]hanges in the filter material used in the gas emission filtration system” “[i]nstallation of a pneumatic

system for the mechanic tapping of the furnace’”).

Page 249: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

244

proyecta la producción de la Fundidora de Vinto (por un período de 20 años)

“asumiendo” que procesaría 30.000 TMS y que habría un porcentaje de estaño

recuperado constante de 46.6%, sin considerar, especialmente, la falta de

disponibilidad de concentrados en Bolivia.1144

859. Claimant’s experts’ production forecasts are, therefore, unrealistic.

b) Compass Lexecon estimates unduly high grades, recoveries and prices

860. Compass Lexecon considers tin ingot sales prices and applies it to the estimated production

of ingots (which, in turn, depend on the grades in the concentrates processed by the Smelter

and the metallurgical recovery achieved during the smelting process) to calculate the Tin

Smelter’s revenues.

861. Compass Lexecon’s estimates are wrong for, at least, four reasons.

862. First, RPA assumes that unduly high concentrates grades (48.75% Sn) would remain constant

throughout the Tin Smelter’s production life. This is wrong. On the one hand, the Tin

Smelter’s historical operating performance shows that, from 1987 to date, concentrate grades

have been in steady decline (e.g., 50.25% in 1990, 48.74% around 2009, 46.77% in 2015 and

so on).1145

863. There is no reason to expect this trend will change. On the other hand, as acknowledged by

Compass Lexecon, “[t]he Tin Smelter processes various concentrates from not only the

1144 Villavicencio, ¶ 63 (emphasis in original) (Unofficial translation: “estimates the production of the Vinto Smelter (for a

20-year period) ‘assuming’ that it would process 30,000 metric tons and that there would be a consistent percentage of

recovered tin of 46.6%, without considering in particular, the lack of availability of concentrates in Bolivia”).

1145 Villavicencio, ¶ 70.

86.00%

88.00%

90.00%

92.00%

94.00%

96.00%

98.00%

40.0%

42.0%

44.0%

46.0%

48.0%

50.0%

52.0%

54.0%

56.0%

1985 1990 1995 2000 2005 2010 2015 2020

Re

cup

era

ción

, %

Le

y d

e S

n e

n e

l C

on

cen

tra

do

, %

Año

Ley Sn en el Concentrado, % Recuperación, %

Lineal (Ley Sn en el Concentrado, %) Lineal (Recuperación, %)

Page 250: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

245

Colquiri Mine, but also from other mines and cooperatives; each of these mines typically

produces concentrate at different grade”.1146 Because the Tin Smelter acquires concentrates

from different sources and with different grades, it is wrong to assume that grades will remain

constant in time.

864. Second, RPA assumes “[m]etallurgical recoveries of 95.6% for Sn resulting in a 99.95% pure

Sn bullion product”,1147 which would remain constant in time until 2026. This is mistaken.

Given that, as explained above, concentrate grades are expected to be lower than estimated by

RPA (and also variable), so will be metallurgical recovery.

865. Third, Compass Lexecon has not corroborated its tin ingot price forecasts “with any internal

business plans or price forecasts from Colquiri, Sinchi Wayra S.A., Glencore International or

any other related party”,1148 even though there is reason to believe that such internal price

forecasts exist.1149 This is not to say that the willing seller’s subjective views about future

prices are controlling. However, in estimating a reasonable future price scenario, a willing

buyer would have sought to collect as many data points about pricing as possible, including

the price projections generated in the ordinary course of business by the relevant players in

the tin market in Bolivia and worldwide (such as Colquiri – a tin producer; Sinchi Wayra –

former shareholder of the Tin Smelter; and Glencore International – one of the largest

worldwide traders of tin).

866. Fourth, Compass Lexecon’s premium estimate (which results in adding between US$ 203 to

US$ 289 per tonne to tin ingot sales prices) is based on a single contract signed by the Tin

Smelter and Soft Metals in 2006 for the supply of 14 tonnes with a 3% over LME price

premium.1150 This is not representative. One, a single contract entered into in February 2006,

i.e., almost a year before the valuation date does not provide a sufficiently reliable basis to

project premia for contracts to be entered in the following 20 years. Two, even Glencore

International’s own short-term purchase contracts with the Tin Smelter shortly after the

valuation date confirm that Compass Lexecon price projections are way off the mark.1151 For

example, as Eng Villavicencio explains, “los contratos entre Glencore y Vinto de 19 de julio

de 2007 (que fija un premio de USD 120), de 17 de septiembre de 2007 (con premio de USD

1146 Compass Lexecon Expert Report, ¶ 79 (emphasis added).

1147 RPA FBD Glencore v Bolivia Expert Report, ¶ 66.

1148 Econ One, ¶ 116.

1149 Econ One, ¶¶ 115-116.

1150 Vinto SA-Soft Metals Ltda - Purchase Contract 03 - 20.02.06, CLEX-32.

1151 Econ One, ¶ 117.

Page 251: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

246

75), de 18 de octubre de 2007 (que establece un premio de USD 35) y el de 12 de noviembre

de 2008 (que establece un premio de USD 146). Desde 2009, los premios han oscilado entre

USD 50 y 300 sobre el precio del mercado.”1152 Three, recently Glencore made an offer to

purchase tin ingots without a premium, as confirmed by Eng Villavicencio.1153 Four, Compass

Lexecon includes a 3% constant premium over tin prices while, as explained by Eng

Villavicencio, no direct correlation can be established between premia and tin market prices:

indexar el premio a largo plazo como un porcentaje del precio de estaño, como hace

Compass Lexecon, no es habitual. El precio del estaño fluctúa según la demanda

del mercado, por lo que basar el premio a largo plazo en esa cotización no tendría

sentido por su imprevisibilidad. No existe relación directa entre el premio y el

precio, más bien, el premio depende de la calidad del producto (como en nuestro

caso, que producimos lingotes con un muy bajo contenido de plomo – 17g/TM de

plomo frente a los 50kg/TM habituales en el mercado).1154

867. Considering a broader sample of contracts, as Econ One does, demonstrates that the average

premium is substantially lower than that applied by Compass Lexecon.1155

c) Compass Lexecon ignores or underestimates necessary operating and

capital expenses

868. In order to further exaggerate the FMV of the Tin Smelter, Compass Lexecon omits to include

significant costs in its model, despite projecting a significant increase in production. To arrive

at this result, RPA and Compass Lexecon assume that “economies of scale [would] come with

the increase in concentrate feed” and, on that basis, proceed to estimate the “smelting, quality

control, maintenance, and other indirect expenses” at US$ 9.3 million.1156 Compass Lexecon

further considers US$ 300,000 for general and administrative costs, and US$ 800,000 for

sustaining capital expenditures annually.1157

1152 Villavicencio, ¶ 87 (Unofficial translation: “the contracts between Glencore and Vinto of 19 July 2007 (that fixes a price

premium of USD 120), of 17 September 2007 (with a price premium of USD 75), of 18 October 2007 (that establishes

a price premium of USD 35) and of 12 November 2008 (that establishes a price premium of USD 146). Since 2009,

price premiums have oscillated between USD 50 and 300 over the market price.”).

1153 Villavicencio, ¶ 87; Econ One, ¶ 118. See also, Purchase offer for 200 TMN of Metallic Tin from Glencore of 19

September 2017, R-83.

1154 Villavicencio, ¶ 88 (Unofficial translation: “indexing the price premium in the long term as a percentage of the price of

tin, as done by Compass Lexecon, is un usual. The price of tin fluctuates following the market demand, therefore, basing

the price premium in the long term on that price makes no sense due to its unpredictability. There is no direct relation

between the price premium and the price, rather, the price premium depends on the product’s quality (as in our case

where we produce ingots with a very low lead content - 17g/metric ton of lead versus the usual 50kg/metric ton in the

market)”).

1155 Econ One, ¶¶ 117-120.

1156 Compass Lexecon Expert Report, ¶ 85.

1157 Compass Lexecon Expert Report, ¶ 85.

Page 252: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

247

869. Compass Lexecon’s model ignores or underestimates necessary capital investments and

operating costs for, at least, five reasons.

CAPEX

870. First, while Compass Lexecon assumes that the Tin Smelter’s production would reach its

historical maximum as of 2008 (i.e., only a year after reversion), it conveniently forgets to

consider the significant CAPEX investment that would be needed to achieve the stated

production level.1158 Indeed, as of February 2007, the main furnaces and production units

were working at maximum capacity with a limited life-span of 3 to 5 months (after which

overhauls would be necessary), while other units had been put out of service.

Eng Villavicencio explains that:

Las 5 unidades principales de producción (hornos reverberos 3 y 4, horno eléctrico,

y hornos volatilizadores 2 y 4) tenían, a partir del 31 de enero de 2007, una vida

útil de 3 a 5 meses, mientras las otras unidades de producción estaban fuera de

servicio y paralizadas.1159

871. This is far from unexpected given that most of the production units were commissioned in the

1970s (when the Tin Smelter began operations) and had not been refurbished. In fact,

Eng Villavicencio confirms that “[l]a privada había operado hasta el límite la maquinaria,

agotando su vida útil sin hacer los mantenimientos mayores (overhauls) necesarios. Los

hornos y demás unidades de producción se encontraban en estado obsoleto dado que la

empresa privada no había realizado inversiones importantes.”1160

872. It is, hence, not reasonable to assume that the Tin Smelter would reach “maximum historical

production levels” (using the old furnaces existing as February 2007) when it has not even

been able to do so with the Ausmelt Furnace (which required a US$ 39 million investment).1161

873. Second, Compass Lexecon estimates that only US$ 800,000 per year will be spent, as

sustaining capital,1162 in the Tin Smelter. This amount is clearly insufficient. As explained

by Eng Villavicencio:

1158 Compass Lexecon Expert Report, ¶ 79-85 and Table 6; RPA FBD Glencore v Bolivia Expert Report, ¶¶ 195, 202.

1159 Villavicencio, ¶ 47(a) (Unofficial translation: “the 5 main units of production (reverbaratory furnaces 3 and 4, electric

furnace, volatilization furnaces 2 and 4) had, from 31 January 2007, a useful life of between 3 and 5 months, while the

other production units were out of service and paralyzed”).

1160 Villavicencio, ¶ 46 (Unofficial translation: “[t]he private company had operated the machinery until its limit, consuming

its useful life without carrying out the necessary maintenance (overhauls). The furnaces and other units of production

were obsolete given that the private company did not make important investments”).

1161 Villavicencio, ¶ 66.

1162 Compass Lexecon Expert Report, ¶ 85.

Page 253: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

248

Esto es insuficiente. Para mantener un nivel de procesamiento de 30.000 TMS, como

proyectan RPA y Compass Lexecon – asumiendo que se tuviese la maquinaria

necesaria – se deben hacer inversiones importantes para mantener los equipos en

condiciones óptimas de producción (acortando los lapsos de los mantenimientos y

overhauls preventivos, por ejemplo).1163

OPEX

874. First, Compass Lexecon assumes that, as a result of the Tin Smelter’s increased production,

it would automatically benefit from economies of scale and thus would have lower operating

costs per tonne in 2007-2013 (i.e., the first years of the model) than in 2006. Compass

Lexecon’s assumption is unsupported. As explained by Econ One, “Compass Lexecon relies

on the RPA Report to support these supposed economies of scale, but the reference Compass

Lexecon makes is a quote regarding operations at Colquiri”.1164

875. Second, Compass Lexecon’s tin concentrate purchase price estimate is also based on a single

contract signed by the Tin Smelter and Colquiri in 2007. As for the ingot sales, it is

unreasonable to project purchase prices for the next 20 years on the basis of a single contract.

It is even more unreasonable to do so when, as in the present case, the Tin Smelter acquired

most of its concentrates (60%) from the Huanuni mine (and not Colquiri).1165

876. Third, Compass Lexecon estimates that the Tin Smelter’s general and administrative costs

will only amount to US$ 300,000 per year (during the next 20 years). This is wrong on many

counts. Compass Lexecon’s estimate is arbitrarily based on the amount of G&A incurred in

2006 (US$ 264,395) and ignores that, in the previous year (i.e., 2005), G&A costs amounted

to US$ 751,243 (i.e., almost three times G&A costs for 2006). As explained by Econ One,

“it is more appropriate to assume that G&A in the future would be equal to the average

incurred in 2005 and 2006, or US$ 507,819, instead of Compass Lexecon’s assumption that

the lowest of two very different values is the most appropriate”.1166

d) The discount rate used by Compass Lexecon is unduly low

1163 Villavicencio, ¶ 86 (Unofficial translation: “This is insufficient. To maintain a processing level of 30.000 metric tons,

as RPA and Compass Lexecon project – assuming that one has the necessary machinery – one has to make important

investments in order to maintain the equipment in optimal condition for production (limiting the intervals between

maintenance and preventative overhauls, for example)”).

1164 Econ One, ¶ 110.

1165 This is acknowledged by Compass Lexecon (see Compass Lexecon Expert Report, ¶ 79) and confirmed by Eng

Villavicencio (see Villavicencio, ¶ 16).

1166 Econ One, ¶ 111.

Page 254: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

249

877. Compass Lexecon discounts the projected cash flows of the Tin Smelter at a rate equivalent

to the Tin Smelter’s WAAC as of 8 February 2007, which Compass Lexecon estimates at

15.7%.1167

878. Compass Lexecon’s discount rate is unduly low. Bolivia will not repeat here the criticisms

developed by Econ One in its report; rather, Bolivia will only make three general comments

that reflect the arbitrariness of Compass Lexecon’s discount rate calculation.

879. First, following the adjudication of the sales contract to Allied Deals, local organizations and

unions in Oruro1168, as well as members of the Bolivian Parliament,1169 called for

investigations to be carried out prior to the conclusion of the sale purchase agreement. Indeed,

by early 2005, “[t]he overthrow of the main champion of neo-liberal economics in 2003, the

rise of Evo Morales, the palpable shift of politics to the left throughout the country and the

decline of the traditional party structure ha[d] left the business environment clouded with

uncertainty.”1170 Fully aware of the risk that this Asset might be reverted to the State in the

near future, Glencore International still acquired the Tin Smelter.

880. Second, the significant risks of investing in the mining sector in Bolivia were being reported

as of February 2007. Such that any willing buyer would have taken into consideration the

1167 Compass Lexecon Expert Report, Section V.2.6, ¶¶ 89-90.

1168 Statement of the Oruro Civic Committee, R-122 (“TERCERO.- Solicitar al Gobierno la inmediata realización de

gestiones para que el daño económico infringido al Departamento de Oruro sea revertido, recuperándose el valor total

de los materiales y concentrados obsequiados al Consorcio ALLIED DEALS.”) (Unofficial translation: “THIRD.-

Request the Government to immediately take the necessary measures so that the economic damage caused to the

Department of Oruro can be reverted, thus recovering the total value of materials and concentrate gifted to the

Consortium ALLIED DEALS”).. See, also, Letter from the Oruro Central Obrera to President Banzer Suárez of 23 May

2001, R-126 (“la clase trabajadora y lodos los sectores del pueblo de Oruro, nos encontramos agobiados por el hambre

y la miseria que reina en nuestro sociedad debido a que nuestro patrimonio y que constituía FUENTE DE TRABAJO,

ha sido enajenado ilegalmente y en un monto absolutamente exiguo constituyendo un engaño en la venta del Complejo

Metalúrgico de Vinto a la Empresa [Allied Deals]”) (Unofficial translation: “the working class and all sectors of the

people of Oruro are overwhelmed by the hunger and misery that reigns in our society given that our asset, which

constituted a SOURCE OF WORK, has been transferred illegally and for a completely inadequate amount, which

amounts to fraud in the sale of Complejo Metalúrgico de Vinto to the company [Allied Deals]”).

1169 Letter from Representative Pedro Rubín de Celis to the Contralor General de la República of 10 May 2001, R-124, p.

2 (“En el numeral 5 del documento denominado ‘acta de Entendimiento’ en fecha de 2 de marzo de 2000 por los

Presidentes de Vinto y COMIBOL, por una parte, y por el representante de ALLIED DEALS PLC dice textualmente:

‘la vendedora depositará, a la brevedad posible en sus almacenes – estaño e incluir estaño metálico dentro de los ítems

ofertados en la venta de la Fundidora’. De esta manera, los compradores obtuvieron en forma fraudulenta el dinero

para comprar la propia fundición en forma de estaño en circuito, en concentrados y en metálico por un valor de [US$

11,477,539]. A ello habrá que añadir las 500 toneladas de estaño metálico entregadas a favor de la compradora como

respaldo al valor ajustado del material en circuito y al valor ajustado de los activos fijos”) (Unofficial translation: “Item

5 of the document named ‘minutes of Understanding’ of 2 March 2000 [executed] by the Presidents of Vinto and

COMIBOL, on the one hand, and by the representative of ALLIED DEALS PLC, literally says: ‘the seller will deposit

shortly in its warehouses – tin and include metallic tin within the items offered in the sale of the Smelter. This way, the

buyers obtained fraudulently the money to buy the smelter itself in the form of pipeline tin, in concentrates and metal

for the amount of [US$ 11,477,539]. To this must be added 500 tons of metallic tin delivered in favor of the buyer as a

guarantee of the adjusted value of the pipeline material and the adjusted value of fixed assets”). See, also, Formal

complaint by Representative Pedro Rubín de Celis against Minister Carlos Saavedra Bruno, R-125.

1170 Business Monitor International, Risk Summary - Bolivia, 14 January 2005, R-171.

Page 255: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

250

“little potential for significant improvement in the investment climate in Bolivia […]

government remains keen to nationalise the mining industry”.1171 In spite of this, Compass

Lexecon has estimated a country risk premium that only reflects Bolivia’s sovereign default

risk. However, as explained by Econ One, “the calculation of the country default spread is

only the first step in the calculation of the country risk premium, since it only measures the

risk of default on sovereign debt. The second step is to apply an adjustment to take into

account the additional risks inherent in the equity market of a particular country that are not

captured in the yield spread [i.e., equity risk premium]”.1172 Had Compass Lexecon

considered Bolivia’s equity risk premium, it would have obtained a much higher country risk

premium.

881. Third, Compass Lexecon has not considered an illiquidity/size premium in its calculations.

When calculating the WACC (based on the CAPM) of smaller firms, as in the present case

(the Tin Smelter is a small firm), an illiquidity/size premium must be applied to better reflect

their cost of capital. This is the case because, as explained by Econ One, most of the inputs

used to calculate CAPM refer to large companies (much larger than the Tin Smelter). Since

an investment in a smaller firm is more volatile than an investment in a larger firm, calculating

the CAPM without considering the size of the company would underestimate its true cost of

capital. Furthermore, the CAPM measures the cost of capital for large publicly-traded

companies which are considered to be very liquid assets, and this is not the case of the Tin

Smelter (considered an illiquid physical asset).

882. After correcting for these (and other) flaws, Econ One estimates the Tin Smelter’s discount

rate as of 8 February 2007 at 28.48%.

883. For the above reasons, the Tribunal should conclude that Compass Lexecon’s valuation of the

Tin Smelter is inflated, and dismiss it outright. Were the Tribunal to consider that Claimant

has suffered damages that are certain and should be compensated (quod non), such

compensation should be limited to US$ 12.1 million.1173 However, this compensation must

be adjusted to reflect (i) Claimant’s contribution to its own loss (section 7.5) and (ii) the

compensation already received by Claimant from its insurer (sections 2.5.4 and 2.6.1).

7.3.6 Compass Lexecon’s Estimate Of The FMV Of The Antimony Smelter Is Incorrect

Because It Is Based On A Valuation (Performed By Ms Russo) Which Is

1171 BMI Report - Bolivia Risk Ratings Report of 8 February 2007, R-267.

1172 Econ One, ¶ 167 (emphasis added).

1173 Econ One, ¶ Table 4.

Page 256: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

251

Methodologically Flawed And Disregards Key Variables That Make This Asset

Valueless

884. It is undisputed that the Antimony Smelter was only “occasionally” used as a mere storage

facility.1174 Furthermore, as explained by Eng Villavicencio, at the time it reverted to the State

(i.e., in 1 May 2010), the Antimony Smelter was a dismantled facility (with copper having

been even stripped from the electrical wiring).1175

885. Despite this, Claimant claims an astounding US$ 2.2 million as “the FMV of the Antimony

Smelter”, which, it asserts, “is equivalent to the sum of the value of its individual components

[i.e., land, buildings and improvements].”1176 Claimant claims this amount based on the

valuation performed by Ms Russo, which follows the asset-based approach and values the

asset as of 15 August 2017 (i.e., ex post).1177

886. In limine, as explained in section 7.3.2, the Treaty specifies the standard of compensation

applicable to an expropriation. The parties to the Treaty agreed that “[…] compensation shall

amount to the market value of the investment expropriated immediately before the

expropriation or before the impending expropriation became public knowledge, whichever is

the earlier […].”1178 This constitutes, per the will of the parties to the Treaty, full reparation

for the purpose of a dispute under the Treaty. Accordingly, the Antimony Smelter should be

valued as of 30 April 2010 (i.e., the day immediately before it reverted to the State).

887. Aside from ignoring the reality of the Antimony Smelter, which is an obsolete asset, Ms

Russo’s valuation incurs in, at least, five methodological flaws that invalidate her valuation.

888. First, Ms Russo values the Land assuming it could have a residential use in the future. A

minimum knowledge of the Antimony Smelter and its history and the context in Oruro belie

this assumption. Indeed, Ms Russo’s analysis overlooks (i) that the Land is located right next

to the Tin Smelter, which has been operative since 19711179 and produces harmful gas

emissions,1180 and (ii) while operative, the Antimony Smelter also generated contaminated

waste that remained in the soil and the environment (to date, the Antimony Smelter has not

1174 Statement of Claim, ¶ 59.

1175 Villavicencio, ¶¶ 95, 98.

1176 Statement of Claim, ¶ 251.

1177 Informe de Avalúo - Gina Russo of 15 August 2017, Section 3.

1178 Treaty, C-1, Article 5(1).

1179 Villavicencio, ¶¶ 14, 103.

1180 Villavicencio, ¶ 109.

Page 257: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

252

been remediated).1181 In this context, it is evident that the Land cannot serve a residential

purpose (now or in the future). Had Ms Russo visited the Antimony Smelter this much would

have been apparent to her.

889. Moreover, as Eng Villavicencio:

tenemos dos ejemplos de terrenos de las fundidoras Metabol y Operaciones

Metalúrgicas S.A. (OMSA) de plomo y estaño, respectivamente, en Oruro que

cerraron en los años 90 y que hoy, lejos de haber sido urbanizados, han quedado

vacantes. Y esto pese a que están dentro del radio urbano, en la zona sur de Oruro

(mientras que la Fundidora de Antimonio está a las afueras). Aunque los

alrededores de dichas fundidoras sí han visto un gran crecimiento urbanístico, sus

terrenos no han sido edificados.1182

890. Second, contrary to Article V of the Treaty, Ms Russo’s valuation is premised on a negligent

and misinformed willing buyer. Although she (i) acknowledges that the Land’s use is “mostly

industrial” and (ii) assumes that the Land could be used for residential purposes, her valuation

ignores several fundamental costs that would be considered by any willing buyer (e.g., the

closure, remediation and dismantling costs that would need to be incurred to remediate the

environment and dismantle the 40-plus-year-old infrastructure).1183

891. Third, Ms Russo’s valuation incurs in a number of contradictions aimed at inflating the value

of the Antimony Smelter. Although her valuation assumes that the Land would serve a

residential purpose, she goes on to emphasize the “mostly industrial” use of the Land to avoid

applying factors that would otherwise reduce its value. For instance:

Size factor: Because of the Land’s “predominantemente industrial” use, Ms Russo

concludes that “los conceptos de recreación y equipamiento [como factores] no son

asimilables” and thus should not be applied to reduce the area that could be valued.1184

Shape factor: “[S]i bien la forma del terreno de la Fundición de Antimonio podría

considerarse irregular [y por ende dan lugar a la aplicación del coeficiente de

1181 Villavicencio, ¶¶ 107-108.

1182 Villavicencio, ¶ 104 (Unofficial translation: “we have two examples of the land from the Metabol and Operaciones

Metalúrgicas S.A. (OMSA) lead and tin smelters, respectively, in Oruro, which closed during the 90s and today, far

from being developable areas, have remained vacant. This, despite the fact that they are located inside the urban area,

in the south of Oruro (while the Antimony Smelter is located in the outskirts). Although the areas surrounding those

smelters have been experience important urban growth, the land has not been developed”).

1183 Mirones, Section 9.

1184 Informe de Avalúo - Gina Russo of 15 August 2017, ¶ 5.14.3 (Unofficial translation: “predominantly industrial”; “the

concepts of recreation and public facilities [as factors] are inapplicable”).

Page 258: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

253

forma], su extenso tamaño y su uso industrial hacen irrelevante la aplicación de este

factor […].”1185 Yet, Ms Russo insists on applying residential use values to the Land.

892. Fourth, although Ms Russo assumes that the Land could serve a residential purpose, it grants

value to the industrial structures currently existing at the Antimony Smelter (e.g. sheds,

offices, storage rooms, guardhouse, etc.). Rather than giving value to outdated structures and

buildings, Ms Russo should have considered demolition costs consistent with its intended

residential use.

893. Fifth, Ms Russo did not visit the Antimony Smelter, go to the cadaster or perform any formal

studies to determine, among others, the exact area of the Land and state of structures. This is

contrary to the minimum diligence required from a real estate valuator.

894. Indeed, Ms Russo’s valuation of the infrastructure does not reflect the poor state of the

buildings, which, as can be clearly seen in the photos taken during the 3 May 2010 inspection

following the asset’s reversion to the State,1186 were far from being in the generous

“regular”1187 state qualified by Ms Russo:

1185 Informe de Avalúo - Gina Russo of 15 August 2017, ¶ 5.14.4 (emphasis added) (Unofficial translation: “[E]ven though

the shape of the Antimony Smelter’s land might be considered irregular [and thus give rise to the application of the size

factor], its large size and industrial use render the application of this factor irrelevant”).

1186 Notarized Inventory of the Antimony Smelter as of 1 May 2010, R-84.

1187 Informe de Avalúo - Gina Russo of 15 August 2017, Table 17.

Page 259: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

254

895. Moreover, Ms Russo’s desktop exercise is also apparent in her valuation of all the buildings

as if they were all concrete structures with a concrete base.1188 Save for “la nave principal,

los almacenes y la estructura del transformador” (as explained by Eng Villavicencio),1189 the

buildings are precarious wooden or brick structures (as can be seen in the May 2010 photos

below).1190

896. As explained by Eng Villavicencio, neither did Ms Russo inspect the Antimony Smelter’s

infrastructure before valuing it.1191 Ms Russo could have requested access to the Antimony

1188 Informe de Avalúo - Gina Russo of 15 August 2017, Table 12.

1189 Villavicencio, ¶ 112 (Unofficial translation: “the main industrial unit, the warehouses and the transformer building”).

1190 Notarized Inventory of the Antimony Smelter as of 1 May 2010, R-84.

1191 Villavicencio, ¶ 12.

Page 260: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

255

Smelter to inspect its infrastructure, but chose not to do so. It is not reasonable to base the

valuation of 40-plus-year-old infrastructure on satellite images.1192

897. These methodological flaws render Ms Russo’s valuation grossly unreliable as a basis for an

award of damages. In fact, the Antimony Smelter is a liability and not an asset.

898. On the one hand, the building structures of the Antimony Smelter will need to be demolished

given their dire state. Eng Villavicencio has attested as to the state of the buildings (many of

which were built out of precarious, recycled materials) as of the May 2010 reversion. Indeed,

“las edificaciones (salvo por aquellas que nosotros hemos rehabilitado desde 2010 para

auxiliar las actividades de fundición de estaño de Vinto) no tienen ninguna utilidad, y deben

ser desmanteladas y demolidas, lo cual representa un coste superior al de las estructuras

mismas.”1193

899. On the other hand, the Antimony Smelter is also an environmental liability. The Antimony

Smelter was in production until the late 90s and then again for a few months in 2002. During

this time, it generated contaminated industrial waste (“desechos resultantes de las

operaciones metalúrgicas, como escoria con óxidos de hierro y de calcio (un material

particularmente duro y difícil de retirar) y […] desechos de arsénico en una piscina ubicada

al este del terreno” 1194) that has not been remediated to date. Moreover, the Antimony

Smelter is within the direct area of influence of the operating Tin Smelter.1195 As explained

by Eng Villavicencio, the Tin Smelter produces “constantemente la pluma de arsénico y

azufre generada por los procesos de tostación de la Fundidora.”1196 These environmental

liabilities derive in significant remediation costs that any willing buyer would take into

consideration.

1192 Informe de Avalúo - Gina Russo of 15 August 2017, ¶ 4.6.

1193 Villavicencio, ¶ 117 (Unofficial translation: “the buildings (except for those that we rehabilitated since 2010 to assist

Vinto’s tin smelting) do not have any use and must be dismantled and demolished, which represents a higher cost than

that of the structure itself”).

1194 Villavicencio, ¶ 107 (Unofficial translation: “waste resulting from metallurgic operations, such as slag with iron and

calcium oxide (a particular tough material and difficult to remove) and […] arsenic waste in a pool located to the east

of the land”).

1195 Villavicencio, ¶ 103.

1196 Villavicencio, ¶ 109 (emphasis in original) (Unofficial translation: “a constant plume of arsenic and sulfur generated

by the smelting processes of the Smelter”).

Page 261: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

256

900. Alternatively, even if the Tribunal were to disregard the environmental liabilities and costs of

demolition, and accept that the Land could be residential, it should still conclude that Ms

Russo’s valuation lacks rigor:1197

Como he explicado, la metodología aplicada por la Arq. Russo para realizar su

avalúo de la Fundidora de Antimonio no es la correcta. Por ejemplo, no es correcto

partir de la premisa de que podría darse un uso residencial a los Terrenos en el

futuro. Además, los datos en que se basa su valuación no son certeros, demostrables

ni provienen de fuentes oficiales o confiables. Por ello, los valores obtenidos son

meramente especulativos.1198

901. Bolivia has instructed Mr Mirones to perform a valuation of the Antimony Smelter under

those assumptions. Mr Mirones’ valuation is based on visits to the subject property and his

knowledge of the Oruro area, where he practices.1199

902. As explained by Mr Mirones, although the comparables method is commonly used in the real

estate industry,1200 it cannot be used in this case to value the land:

A pesar de que existe información sobre compraventas en el área de Oruro, no he

considerado dichas transacciones en mi valuación por cuanto no involucran

inmuebles comparables al Terreno. Como ya he mencionado, las características del

Terreno son muy particulares, al punto de hacerlo prácticamente único.1201

903. Indeed, the Antimony Smelter’s characteristics (e.g., size of the land, location, irregular shape,

lack of direct access to access roads, absence of direct access to utilities – which derive from

the Tin Smelter, and the environmental liabilities of the land – including an open arsenic mud

pit, etc.) render it “almost unique” in the area. As put by Mr Mirones “Si bien es cierto que

para aplicar el “método de comparables” no es necesario encontrar un bien idéntico, en este

caso, no he encontrado ningún inmueble de características siquiera similares.”1202

904. In light of the above, to calculate the FMV of the Land, Mr Mirones has considered its cadaster

value as a first step. To do so, Mr Mirones located and inspected the land, corroborating the

1197 Mirones, Sections 4, 9.

1198 Mirones, ¶ 106 (Unofficial translation: “As I explained, the methodology applied by Arc. Russo to carry out the valuation

of the Antimony Smelter, is not the correct one. For instance, it is not correct to start from the premise that the land

could be put to residential use in the future. Furthermore, the data on which he bases his valuation are not accurate,

demonstrable and do not come from official or reliable sources. Because of this, the resulting values are merely

speculative”).

1199 Mirones, Sections 2 and 3.

1200 Mirones, ¶ 40.

1201 Mirones, ¶ 41 (Unofficial translation: “Although there is information on sales in the area of Oruro, I have not considered

those transactions in my valuation since they do not involve real estate comparable to the Land. As I already mentioned,

the Land’s characteristics are very peculiar, to the point of rendering it almost unique”).

1202 Mirones, ¶ 42 (Unofficial translation: “Although it is true that in order to apply the ‘comparable method’ it is not

necessary to find an identical asset, in this case, I have not even found any property even with similar characteristics”).

Page 262: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

257

information provided by the Oruro cadaster.1203 Then, based on the maps and information

provided by the Civil Works Unit of the Tin Smelter,1204 Mr Mirones applied the cadastre

value per square meter to the area of the land as of 2010.1205

905. At a second stage, in accordance with the National Cadastre Regulation,1206 Mr Mirones

applied a number of corrective factors based on the characteristics of the land, in order to

obtain the FMV of the land:1207

906. Mr Mirones then estimated the residual value of the buildings in the Antimony Smelter

employing the replacement cost method.1208 First, Mr Mirones classified the structures in 5

categories (which coincide with Ms Russo’s classification),1209 to then calculate their area

based on topographical maps1210 and his in situ inspections in November and December 2017.

Mr Mirones then estimated the square meter cost of the structures:

Para determinar el valor inicial, realicé una comparación con los costos de

construcción por m2 vigentes en el mercado local de construcciones basado en la

calidad de los materiales y estado de conservación de las Edificaciones. El valor

inicial es el resultado del producto del área por el precio en dólares por m2

determinado.1211

1203 Urban Cadastre Report of 15 November 2017, DM-4.

1204 Technical Planimetry Report of the Antimony Smelter of 29 November 2017, DM-2.

1205 Mirones, ¶¶ 49-51.

1206 Reglamento Nacional de Catastro Urbano, Decreto Supremo No. 22902 of 19 September 1991, GR-9.

1207 Mirones, ¶¶ 51-70.

1208 Theoretical Framework, DM-15.

1209 Mirones, ¶ 72.

1210 Technical Planimetry Report of the Antimony Smelter of 29 November 2017, DM-2.

1211 Mirones, ¶ 90 (Unofficial translation: “In order to determine the initial value, I carried out a comparison with the

construction costs per square meter in effect in the local market for construction based on the quality of materials and

the state of conservation of the Buildings. The initial value results from the area multiplied by the price in dollars per

square meter”).

Page 263: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

258

907. The initial value of the each building category was then adjusted based on their specific

characteristics and state – such as obsolescence, state of conservation, and use1212 – on the

basis of his inspections to the Antimony Smelter.1213 On the basis of this, Mr Mirones

estimated the residual value of the buildings in the Antimony Smelter at:1214

908. Mr Mirones then explains that a willing buyer would consider the closure and remediation

costs that would need to be incurred (irrespective of the use given to the land); and the costs

of dismantling the Antimony Smelter’s 40-plus-year-old infrastructure (which would

outweigh any revenue from scrap material). As a result, any willing buyer would conclude

that the Antimony Smelter is a liability more than anything.

909. Based on the above, Mr Mirones has concluded that the Antimony Smelter has no positive

value.1215

7.3.7 Compass Lexecon’s Valuation Of The Tin Stock

910. Claimant maintains that, on 1 May 2010, Bolivia seized 161 tons of Tin Stock stored in the

Antimony Smelter. Relying on a simple letter sent by Colquiri to the Ministry of Mining in

May 2010,1216 Compass Lexecon values this Tin Stock at US$ 707,821 as of 30 April

2010.1217

911. Compass Lexecon’s valuation is exaggerated. An inspection was carried out shortly after the

reversion of the Antimony Smelter (by a notary and a chemical expert) to inspect the Tin

1212 Reglamento Nacional de Catastro Urbano, Decreto Supremo No. 22902 of 19 September 1991, GR-9, p. 23, 2.1.3.1.

1213 Mirones, ¶¶ 94-103.

1214 Mirones, ¶ 104.

1215 Mirones, ¶ 117.

1216 Letter from Colquiri SA (Mr Capriles Tejada) to Ministry of Mining (Mr Pimentel Castillo) of 3 May 2010, C-28.

1217 Compass Lexecon Expert Report, ¶ 101.

Page 264: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

259

Stock and certify its quantity. The audit report issued on 23 September 2010 (as a result of

this inspection) determined that there were 157.6 metric tons of Tin Stock stored at the

Antimony Smelter. Based on this report, Econ One has estimated the value of the Tin Stock

at US$ 606,264.1218

* * * * *

912. For all the foregoing reasons, after making the necessary corrections and adjustments, Econ

One has estimated the value of (i) Colquiri at US$ 39.7 million (as of 19 June 2012), (ii) the

Tin Smelter at US$ 12.1 million (as of 8 February 2007), (iii) the Antimony Smelter at US$

0 (as of 30 April 2010), and (iv) the Tin Stock at US$ 606,264 (as of 30 April 2010).

7.4 Claimant’s Claim For Interest Is Grossly Inflated

913. While Claimant alleges that it “should receive pre and post award interest at a rate that

ensures ‘full reparation,’”1219 in reality it is seeking much more than that. In effect,

Claimant’s claim for interest would result – were it to be accepted (quod non) – in its unjust

enrichment and in punitive damages being awarded against the State, as evidenced by the fact

that interest accounts for US$ 227.7 million, i.e. almost 34% of the total damages claimed.

914. Claimant also alleges that it is seeking payment of “interest rate at a normal commercial rate

applicable in Bolivia as provided in Article 5 of the Treaty.”1220 Upon its instruction, Compass

Lexecon has calculated these interest rates at (i) 8.6% as of 8 February 2007 (for the Tin

Smelter), (ii) at 6.1% as of 30 April 2010 (for the Tin Stock), and (iii) at 6.4% as of 29 May

2012 (for Colquiri).1221 Claimant also requests the Tribunal to calculate interest compounded

(annually), which further inflates its already exorbitant interest claim.1222

915. For the reasons further developed below, were the Tribunal inclined to award interest to

Claimant, it should apply a risk-free interest rate (Section 7.4.1) and award simple interest

(Section 7.4.2).

1218 Econ One, ¶ 140.

1219 Statement of Claim, Section VI.C.1.

1220 Statement of Claim, ¶ 290.

1221 Compass Lexecon Expert Report, ¶ 101.

1222 Statement of Claim, ¶ 291.

Page 265: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

260

7.4.1 Were The Tribunal To Award Interest To Claimant (Quod Non), It Should Apply A

Risk-Free Interest Rate To Avoid Overcompensation

916. Should the Tribunal award interest to Claimant (quod non), only interest at the risk-free rate

would prevent Claimant’s unjust enrichment since it did not bear any operating risk in relation

to the Assets following their transfer to the State (Section 7.4.2.1). If the Tribunal were,

however, to conclude that interest should also compensate Claimant for some undefined risk,

the Tribunal should use at most the US LIBOR + 1% spread (Section 7.4.2.2). As will have

become apparent to the Tribunal from its analysis of Claimant’s valuation, in relation to

interest Compass Lexecon’s inputs are also exaggerated and ignore, inter alia, Claimant and

Glencore International’s credit ratings and leverage to obtain cheap financing (Section

7.4.2.3).

7.4.1.1 Interest In This Case Should Be At The Risk-Free Rate To Avoid Claimant’s Unjust

Enrichment

917. By definition, ongoing investments are expected to yield more than risk-free rates. Indeed,

investors require return for bearing the risk of their investment.

918. In the present case, Claimant was relieved of its investment risk in the Assets from the very

moment they were reverted to the State. Any interest covering the period of time thereafter,

accordingly, should be at the risk-free rate. Otherwise, Claimant would be rewarded for an

operating risk it did not bear and, hence, it would be overcompensated. This is explained in

the often-cited piece by Fisher and Romaine excerpted below:

The violation took place at a single point of time, time 0. It involved the

destruction of an asset whose value at that time is clearly known as Y. Hence,

had damages been assessed at time 0, an award of Y would have made the

plaintiff whole. Unfortunately, however, the processes of justice take time,

and the award is to be made at time t > 0. How (if at all) should the plaintiff

be compensated for this fact?

At first glance, it may seem that the plaintiff is entitled to interest at its

opportunity cost of capital, r. After all, had the plaintiff received Y at time 0

[the time of the event], it would have invested the funds, receiving presumably

its average rate of return (…)

The fallacy here (in either version) has to do with risk. The plaintiff’s

opportunity cost of capital includes a return that compensates the plaintiff for

the average risk it bears. But, in depriving the plaintiff of an asset worth Y at

time 0, the defendant also relieved it of the risks associated with investment in

that asset. The plaintiff is thus entitled to interest compensating it for the time

value of money, but it is not also entitled to compensation for the risks it did

Page 266: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

261

not bear. Hence prejudgment interest should be awarded at the risk-free

interest rate (…).1223

919. Several international arbitral tribunals have, following the rationale above, awarded interest

at risk-free rates where the investor no longer operated the allegedly expropriated asset.

920. The Murphy tribunal found, in this connection, that “there [had been] an industrial risk that

applied to Murphy’s investment up until it sold its investment in March 2009.”1224 Thereafter,

there was no justification for the application of an interest rate which remunerated any sort of

operating risk, which the claimant had ceased to bear. Accordingly, the tribunal applied a

risk-free rate.1225

921. Likewise, the Burlington tribunal rejected the actualization rate proposed by the claimant

(which was equivalent to Burlington’s weighted average cost of capital or “WACC”). The

tribunal applied instead “a reasonable risk-free commercial rate,”1226 seeing as though

WACC “contain[ed] an element of reward for risk that [was] inappropriate [there] because

Burlington no longer [bore] the risk of operation.”1227

922. The Burlington tribunal held that a risk-free interest rate applied on the basis of the following

language in the bilateral investment treaty between Ecuador and the United States:

Compensation shall be equivalent to the fair market value of the expropriated

investment immediately before the expropriatory action was taken or became

known, whichever is earlier; be calculated in a freely usable currency on the basis

of the prevailing market rate of exchange at that time; be paid without delay; include

interest at a comercially reasonable rate from the date of expropriation; be fully

realizable and be freely transferable.1228

923. This provision is essentially identical to the Treaty provision regarding compensation, which

reads as follows:

Such compensation shall amount to the market value of the investment expropriated

immediately before the expropriation or before the impending expropriation became

1223 Econ One, ¶ 193.

1224 Murphy Exploration and Production Company International v. Republic of Ecuador [II], PCA Case No. 2012-16, Partial

Final Award of 6 May 2016, RLA-99, ¶ 450.

1225 Murphy Exploration and Production Company International v. Republic of Ecuador [II], PCA Case No. 2012-16, Partial

Final Award of 6 May 2016, RLA-99, ¶ 516.

1226 Burlington Resources, Inc v Republic of Ecuador (ICSID Case No ARB/08/5) Decision on Reconsideration and Award

of 7 February 2017, CLA-134, ¶¶ 533-535.

1227 Burlington Resources, Inc v Republic of Ecuador (ICSID Case No ARB/08/5) Decision on Reconsideration and Award

of 7 February 2017, CLA-134, ¶ 533.

1228 Treaty between the United States and Ecuador concerning the Encouragement and Reciprocal Protection of Investments,

signed in Washington, D.C on August 27, 1993, entered in force May 11, 1997 (Treaty), R-268, Article III.1 (emphasis

added).

Page 267: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

262

lublic knowledge, whichever is the earlier, shall include interest at a normal

commercial or legal rate, whichever is applicable in the territory of the

expropriating Contracting Party, until the date of payment, shall be made without

delay, be effectively realizable and be freely transferable.1229

924. For similar considerations, the tribunal in Vestey Group Limited adopted the the six-month

US Treasury bond rate as a reasonable risk-free rate applicable in circumstances where the

claimant had ceased to bear the operating risk:

In conclusion, the Tribunal will resort to a risk free rate applicable to US currency

debt, i.e. the six-month US Treasury bond rate. The practice of international

tribunals confirms this conclusion.1230

925. The Yukos tribunal adopted the same approach and awarded interest at a rate based on ten-

year U.S. Treasury bond rates:

The Tribunal observes that many investor-state tribunals have adopted this

“investment alternatives approach,” using rates of U.S. debt instruments even when

the claimant was not a U.S. investor. The Tribunal, in the exercise of its discretion,

has concluded that it would be appropriate to award to Claimants interest on a rate

based on ten-year U.S. Treasury bond rates.1231

926. Doctrine has confirmed this view. For example, in Prof Kantor’s words:

Historic earnings must be “brought forward” to the valuation date by means

of an interest rate, while future earnings are discounted back to the valuation

date by means of a discount rate. The interest rate used for bringing historical

amounts forward will clearly not contain the same risk factors as the discount

rate used to present value future amounts. As a practical matter, the interest

rate used for the historical amount is often a “risk-free” rate (such as the rate

for US Treasuries) or a statutory rate for pre-judgment interest.1232

927. The interest rates that Claimant advocates for in respect of each of the Assets should be

discarded for, at least, two reasons.

928. First, as noted above, the Treaty mandates the application of interest at a commercially

reasonable rate. Such a rate is the six-month or the one-year U.S. Treasury bill rate. From an

economic perspective, the term commercial interest rate includes the rates that are regularly

available to investors.1233 As Econ One explains, each specific rate “will depend on the risk

1229 Treaty, C-1, Article 5(1) (emphasis added).

1230 Vestey Group Ltd v. Bolivarian Republic of Venezuela, ICSID Case No. ARB/06/4, Award of 15 April 2016, RLA-5, ¶

446.

1231 Yukos Universal Limited (Isle of Man) v Russian Federation (PCA Case No AA 227) Final Award of 18 July 2014,

CLA-122, ¶ 1684-1685.

1232 Econ One, ¶ 195 (emphasis added).

1233 Econ One, ¶ 196.

Page 268: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

263

profile of the financial product generating the interest payments.”1234 Given that the amount

to be granted by an arbitral award is not exposed to risk, the applicable interest rate should

compensate Claimant exclusively for the time value of money.1235 This is achieved through a

risk-free interest rate.

929. Second, Compass Lexecon calculated the commercial interest rate based on “rates for loans

granted from commercial banks to businesses in Bolivia, as published by the Central Bank of

Bolivia as a proxy.”1236 As explained by Econ One, lenders to businesses in Bolivia require a

spread over the risk free rate to compensate for the ex-ante risk of default of the debtor. Since,

“[c]laimant’s award of compensation is not exposed to the ex-ante risks involved in lending

to Bolivian companies”, using Compass Lexecon’s proposed rates would lead to Claimant’s

unjust enrichment.

930. For the foregoing reasons, interest in the present case should be calculated based on the six-

month or the one-year U.S. Treasury bill rates.1237

7.4.1.2 If The Tribunal Were To Decide That Interest Should Compensate Also For Non-Existent Risk

(Quod Non), It Should At Most Award Interest At The US LIBOR + 1% Rate

931. International banks and, more generally, international markets most often set lending rates by

reference to the LIBOR rate for the given currency plus a small margin (spread) to account

for risk. It is not in dispute that Claimant is a multinational corporation with access to

international financing. As Glencore International’s Annual Reports show, in the last few

years, it has secured billions of dollars in financing at an average rate of US LIBOR + 1%

rates or less. For instance:1238

Glencore International’s 2016 Annual Report shows that, in 2016, it obtained over

US$ 14 billion in revolving credit facilities at LIBOR plus 0.50 to 0.60; and

Glencore International’s 2011 Annual Report shows that, in 2011, it obtained over

US$ 8 billion in revolving credit facilities at LIBOR plus 1.10 to 1.75.

1234 Econ One, ¶ 196.

1235 Econ One, ¶ 193.

1236 Compass Lexecon Expert Report, ¶ 101.

1237 Econ One, ¶ 196.

1238 Econ One, ¶ 198.

Page 269: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

264

932. The average of the above four rates is LIBOR + 0.9875% (i.e., 0.50% + 0.60% + 1.10% +

1.75% ÷ 4 = 0.9875%). Thus, there is no justification for awarding Claimant interest at a rate

higher than LIBOR + 1%.

933. Investment tribunals regularly use LIBOR plus a small margin as “commercial interest” rates.

For example, the SGS tribunal concluded “that it would be appropriate to apply the LIBOR

rate plus one percentage point.”1239 Likewise, the Deutsche Bank tribunal awarded interest at

the LIBOR +1.12%:

The interest rate to be applied shall be based on a nine-month Libor rate as of 9

December 2008, the Early Termination Date, plus a market-based funding spread

based on credit risks associated with Deutsche Bank, based on Deutsche Bank’s one

year credit default swap rate, of 1.12%. Interest will run until full payment.1240

934. The widespread use of LIBOR plus a small margin has been acknowledged by several arbitral

tribunals, including in the Burlington v. Ecuador, Lemire v. Ukraine, PSEG Global v. Turkey,

Sempra v. Argentina, Enron v. Argentina, Continental Casualty v. Argentina, El Paso v.

Argentina, National Grid v. Argentina, RDC v. Guatemala and Rumeli v. Kazakhstan

cases,1241 as well as by commentators.1242

935. For the foregoing reasons, if the Tribunal were to decide that interest should also compensate

for risk (quod non), in line with Claimant’s and Glencore International’s average borrowing

rates and investment case law, the Tribunal should use US LIBOR + 1% as interest rate in this

case.

1239 SGS Societe Generale De Suveillance S.A. and the Republic of Paraguay, ICSID Case No. ARB/07/29, Award of 10

February 2012, RLA-109, ¶ 188.

1240 Deutsche Bank AG v Democratic Socialist Republic of Sri Lanka, ICSID Case No. ARB/09/02, Award of 31 October

2012, RLA-110, ¶ 575.

1241 Burlington Resources, Inc v Republic of Ecuador (ICSID Case No ARB/08/5) Decision on Reconsideration and Award

of 7 February 2017, CLA-134, ¶ 535; Joseph Charles Lemire v Ukraine (ICSID Case No ARB/06/18) Award of 28

March 2011, CLA-104, ¶ 352, 356; PSEG Global Inc and Konya Ilgin Elektrik Üretim ve Ticaret Limited Şirketi v

Republic of Turkey (ICSID Case No ARB/02/5) Award of 19 January 2007, CLA-66, ¶¶ 345-348; Sempra Energy

International v Argentine Republic (ICSID Case No ARB/02/16) Award of 28 September 2007, CLA-71, ¶ 486; Enron

Corporation and Ponderosa Assets LP v Argentine Republic (ICSID Case No ARB/01/3) Award of 22 May 2007, CLA-

68, ¶ 452; Continental Casualty Company v Argentine Republic (ICSID Case No ARB/03/9) Award of 5 September

2008, CLA-81, ¶ 314; El Paso Energy International Company v Argentine Republic (ICSID Case No ARB/03/15)

Award of 31 October 2011, CLA-106, ¶ 745; National Grid plc v Argentine Republic (UNCITRAL) Award of 3

November 2008, CLA-82, ¶ 294; Railroad Development Corporation v. Republic of Guatemala, ICSID Case No.

ARB/07/23, Award of 29 June 2012, RLA-111, ¶¶ 278-279; Rumeli Telekom A.S. and Telsim Mobil Telekomikasyon

Hizmetleri A.S. v. Republic of Kazakhstan, ICSID Case No. ARB/05/16, Award of 29 July 2008, RLA-112, ¶ 769.

1242 S. Ripinsky and K. Williams, Damages in International Investment Law (British Institute of International and

Comparative Law, 2008), RLA-113, p. 370.

Page 270: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

265

7.4.1.3 The Interest Rates Calculated By Compass Lexecon Are Exaggerated And Ignore Claimant’s

and Glencore International’s High Credit Ratings And Leverage To Obtain Cheap Financing

936. Compass Lexecon maintains that, in this case, “normal commercial interest” rates would be

(i) 8.6% as of 8 February 2007 (for the Tin Smelter), (ii) 6.1% as of 30 April 2010 (for the

Tin Stock) and (iii) 6.4% as of 29 May 2012 (for Colquiri).1243

937. However, Compass Lexecon’s proposed rates are unduly high because they reflect the interest

rates applicable to average loans to average businesses in Bolivia. Neither of these self-

serving premises apply in the case of Claimant. Indeed, (i) Claimant does not request average

loans but rather multi-billion dollar loans, and (ii) Claimant is not an average business in

Bolivia but rather a multinational corporation with very high credit ratings, leverage and

access to international financing. For these reasons, Claimant is able to obtain financing at

very low cost. As explained by Econ One:

Even if interest in this Arbitration were to include ex ante risks (as explained

above, it should not), the rates chosen by Compass Lexecon still would be

incorrect, since they reflect the rates applicable to average loans to average

businesses in Bolivia. Although Compass Lexecon does not provide

information in that regard, it is reasonable to conclude that (i) the average

commercial loan in Bolivia is for a relatively small amount and (ii) the

average commercial borrower in Bolivia does not have very high credit

ratings. These two factors explain why the average interest rates used by

Compass Lexecon are so high. Businesses with higher credit ratings

borrowing larger amounts are able to do so at lower rates. Glencore itself is

able to borrow billions of dollars at rates around LIBOR + 1%.1244

938. For these reasons, the interest rates proposed by Compass Lexecon should be dismissed for

being too high.

7.4.2 Claimant Can, At Most, Claim Simple Interest

939. Claimant asserts that “[t]he only way to fully compensate Glencore Bermuda for Bolivia’s

unlawful conduct is to compound the pre-award interest rate on an annual basis.”1245 In

addition, Clamant also purports to be entitled to “compound interest accruing from the date

of the award until payment is made in full.”1246 This is incorrect.

1243 Compass Lexecon Expert Report, ¶ 101.

1244 Econ One, ¶ 198 (emphasis added).

1245 Statement of Claim, ¶ 291.

1246 Statement of Claim, ¶ 292.

Page 271: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

266

940. First, as indicated by the CME tribunal, “[i]n respect of international law, arbitral tribunals

in the past awarded compound interest infrequently.”1247 The Commentary to the

International Law Commission’s Articles on State Responsibility in fact notes that simple

interest should be awarded under to international law:

The general view of courts and tribunals has been against the award of compound

interest, and this is true even of those tribunals which hold claimants to be normally

entitled to compensatory interest.1248

941. Even though, more recently, some arbitral tribunals have awarded compound interest in some

cases, other tribunals have refused to award compound interest, favouring simple interest

instead. This has, for instance, been the view espoused by the tribunals in the Arif v.

Moldova1249 or the Yukos1250 cases.

942. In fact, as explained by Prof. Gotanda, whose work Claimant itself relies on,1251 arbitral

tribunals have only moved away in some cases from the standard practice of awarding simple

interests.1252 This is corroborated by an ICSID study which found that, out of 24 ICSID

awards rendered between 2008 and 2014, in which interest was awarded, the tribunal in

roughly one third awarded simple interest.1253 In the words of the Rosinvest tribunal, the

practice of awarding compound interest to claimants “is by no means unanimous. If, as above,

the Tribunal finds it should award interest at a normal commercial rate, this does not mean

the Tribunal is bound to award compound interest.”1254

1247 CME Czech Republic BV v Czech Republic (UNCITRAL) Final Award of 14 March 2003, CLA-42, ¶ 644. See also

Archer Daniels Midland Company and Tate & Lyle Ingredients Americas, Inc. v. The United Mexican States, ICSID

Case No. ARB(AF)/04/05, Award of 21 November 2007, RLA-114, ¶ 296 (“no uniform rule of law ha[s] emerged in

international arbitral practice as to the applicability of simple or compound interest in any given case.”).

1248 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, p. 108, point (8) (“An aspect of

the question of interest is the possible award of compound interest. The general view of courts and tribunals has been

against the award of compound interest, and this is true even of those tribunals which hold claimants to be normally

entitled to compensatory interest. For example, the Iran-United States Claims Tribunal has consistently denied claims

for compound interest, including in cases where the claimant suffered losses through compound interest charges on

indebtedness associated with the claim.”).

1249 Mr Franck Charles Arif v. Republic of Moldova, ICSID Case No. ARB/11/23, Award of 8 April 2013, RLA-69, ¶ 619

(“Claimant has not justified compound interest, and given the nature of the damages in this case, the Tribunal considers

simple interest is more appropriate”).

1250 Yukos Universal Limited (Isle of Man) v Russian Federation (PCA Case No AA 227) Final Award of 18 July 2014,

CLA-122, ¶ 1689.

1251 Statement of Claim, ¶¶ 291-292.

1252 J. Y. Gotanda, “Compound Interest in International Disputes”, Law & Policy in International Business, Vol. 34, Issue

2, 2003, RLA-115, p. 2.

1253 T. Hart, “Study of Damages in International Center for the Settlement of Investment Disputes Cases” in Transnational

Dispute Management, Vol. 11, Issue 3, June 2014, RLA-116, pp. 18-19.

1254 Rosinvestco UK Ltd. v. The Russian Federation, SCC Arbitration V (079/2005), Final Award of 12 September 2010,

RLA-117, ¶ 689.

Page 272: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

267

943. In this connection, arbitral tribunals have held that compound interest should only be awarded

in appropriate circumstances, which is not the case here.1255 As explained by the Santa Elena

tribunal:

No uniform rule of law has emerged from the practice in international arbitration

as regards the determination of whether compound or simple interest is appropriate

in any given case. Rather, the determination of interest is a product of the exercise

of judgment, taking into account all of the circumstances of the case at hand and

especially considerations of fairness which must form part of the law to be applied

by this Tribunal.1256

944. Claimant has not made any specific allegations regarding any circumstances of this particular

case that would support its claim for compound interest. To the contrary, Claimant

commenced this arbitration in July 2016, i.e., some ten years following the reversion of the

Tin Smelter, six years following the reversion of the Antimony Smelter and five years

following the reversion of the Mine Lease. In such circumstances, if interest were to be

awarded (quod non), it should be simple.

945. Second, Bolivian law prohibits compound interest in Articles 412 and 413 of the Civil

Code.1257

946. Reference to local laws for purposes of awarding interest is common. For example, in Desert

Line v. Yemen, the State submitted that simple interest had to apply, consistent with

international law and the prohibition of compound interest under Yemenite law. The tribunal

in that case applied a simple interest rate.1258 Likewise, the tribunal in Aucoven v. Venezuela

reached the same conclusion on the basis that Venezuelan law did not allow compound

interest.1259 Finally, the tribunal in Duke Energy v. Ecuador held that the prohibition of

1255 CME Czech Republic BV v Czech Republic (UNCITRAL) Final Award of 14 March 2003, CLA-42, ¶ 647 (“The

Tribunal does not find particular circumstances in this case justifying the award of compound interest”). See also Mr

Franck Charles Arif v. Republic of Moldova, ICSID Case No. ARB/11/23, Award of 8 April 2013, RLA-69, ¶¶ 616-

620; Compañía del Desarrollo de Santa Elena SA v Republic of Costa Rica (ICSID Case No ARB/96/1) Final Award

of 17 February 2000, CLA-25, ¶¶ 103-104.

1256 Compañía del Desarrollo de Santa Elena SA v Republic of Costa Rica (ICSID Case No ARB/96/1) Final Award of 17

February 2000, CLA-25, ¶¶ 103 (emphasis added).

1257 Civil Code of the Plurinational State of Bolivia, RLA-118, Articles 412 and 413 (“Artículo 412 - Están prohibidos el

anatocismo y toda otra forma de capitalización de los intereses. Las convenciones en contrario son nulas. Artigo 413 -

El cobro de intereses convencionales en tasa superior a la máxima legalmente permitida, así como de intereses

capitalizados, constituye usura y se halla sujeto a restitución, sin perjuicio de las sanciones penales”) (Unofficial

translation: “Article 412 - Anatocism and all other forms of capitalization of interests are prohibited. Agreements to the

contrary are void. Article 413 - Charging conventional interests at a higher rate than the maximum legally permitted,

as well as of capitalized interests, constitutes usury and is subject to restitution, regardless of criminal sanctions”).

1258 Desert Line Projects LLC v. The Republic of Yemen, ICSID Case No. ARB/05/17, Award of 6 February 2008, RLA-

119, ¶¶ 294-295.

1259 Autopista Concesionada de Venezuela, CA v Bolivarian Republic of Venezuela (ICSID Case No ARB/00/5) Award of

23 September 2003, CLA-44, ¶ 396.

Page 273: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

268

compound interest in Ecuadorian law had to be enforced.1260 As a result, the tribunal awarded

simple interest.

7.5 Any Damages Awarded To Claimant For Colquiri And The Tin Smelter (Quod Non)

Must Be Significantly Reduced To Reflect Claimant’s Contribution To Its Own Losses

947. As developed in sections 7.1 and 7.2 above, Claimant has failed to prove the certainty of the

damages claimed and, in any case, that they were caused by Bolivia. If, notwithstanding the

foregoing, the Tribunal were to award compensation to Claimant for Colquiri and the Tin

Smelter (quod non), it should reduce such compensation to account for Claimant’s

contribution to its own losses.

948. As a matter of law, compensation shall be significantly reduced where the victim contributes

to its losses (Section 7.5.1). As explained above, there can be no doubt that Claimant, at the

very least, materially contributed to its alleged losses in relation to Colquiri and the Tin

Smelter (Section 7.5.2).

7.5.1 As A Matter Of Law, Compensation Shall Be Significantly Reduced Where The Alleged

Victim Contributed To Its Own Losses

949. It is a settled principle of international law that any compensation for an internationally

wrongful act must be reduced or eliminated on account of any intentional, reckless or

negligent conduct of the injured party that contributed to the losses in question.

950. In this connection, Article 39 of the Articles on State Responsibility provides that:

In the determination of reparation, account shall be taken of the contribution to the

injury by willful or negligent action or omission of the injured State or any person

or entity in relation to whom reparation is sought.1261

951. The Commentary to Article 39 explains that when “the injured State, or the individual victim

of the breach, has materially contributed to the damage by some wilful or negligent act or

omission [that] should be taken into account in assessing the form and extent of

reparation”.1262

1260 Duke Energy Electroquil Partners & Electroquil S.A. v. Republic of Ecuador, ICSID Case No. ARB/04/19, Award of

18 August 2008, RLA-120, ¶ 457.

1261 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, Article 39, p. 109.

1262 International Law Commission, “Draft articles on Responsibility of States for Internationally Wrongful Acts with

commentary” [2001-II(2)] Yearbook of the International Law Commission, CLA-30, Article 39, pp. 109-110, point (1).

Page 274: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

269

952. This principle is also recognized by the vast majority of legal systems, including Bolivian

law.1263 Contributory negligence has also been upheld in the jurisprudence of international

investment tribunals,1264 and many scholars have acknowledged and endorsed this line of

authority.1265

953. The principle of contributory negligence has been recognized not only in cases where the

claimant had carried out an unlawful or prohibited act, but also in cases where the claimant’s

behavior was merely “negligent or imprudent.”1266

954. Contributory negligence reduces any compensation due specifically when a state commits an

internationally wrongful act. Indeed, logic dictates that contributory negligence presupposes

1263 Civil Code of the Plurinational State of Bolivia, RLA-118, Articles 995 to 998.

1264 See, for instance, MTD Equity Sdn Bhd and MTD Chile SA v Republic of Chile (ICSID Case No ARB/01/7) Award of

25 May 2004, CLA-49; Azurix Corp v Argentine Republic (ICSID Case No ARB/01/12) Award of 14 July 2006, CLA-

63; RosInvestCo UK Ltd. v. The Russian Federation, SCC Case No. V079/2005, Award of 12 September 2010, RLA-

121; Antoine Goetz & others and S.A. Affinage des Metaux v. Republic of Burundi, ICSID Case No. ARB/95/3, Award

of 19 February 1999, RLA-122; Occidental Exploration and Production Company v Republic of Ecuador (LCIA Case

No UN 3467) Final Award of 1 July 2004, CLA-50; Ioan Micula and others v Romania (ICSID Case No ARB/05/20)

Award of 11 December 2013, CLA-119; Gemplus SA and others v United Mexican States, and Talsud SA v United

Mexican States (ICSID Case Nos ARB(AF)/04/3 and ARB(AF)/04/4) Award of 16 June 2010, CLA-98; CME Czech

Republic BV v Czech Republic (UNCITRAL) Partial Award of 13 September 2001, CLA-32; Enron Corporation and

Ponderosa Assets LP v Argentine Republic (ICSID Case No ARB/01/3) Award of 22 May 2007, CLA-68; Anatolie

Stati, Gabriel Stati, Ascom Group S.A. and Terra Raf Trans Traiding Ltd v. The Republic of Kazakhstan, SCC Case No.

V116/2010, Award of 19 December 2013, RLA-96.

1265 A. Moutier-Lopet, “Contribution to the Injury”, in J. Crawford, A. Pellet, S. Olleson, The Law of International

Responsibility, 2010 (extract), RLA-123, pp. 642-643; I. Marboe, Calculation of Compensation and Damages in

International Investment Law, 2017 (extract), RLA-124, pp. 121-122; S. Ripinsky and K. Williams, Damages in

International Investment Law, British Institute of International and Comparative Law, 2008 (extract), RLA-89, pp. 314-

319; S. Ripinsky, “Assessing Damages in Investment Disputes: Practice in Search of Perfect”, Journal of World

Investment & Trade, Vol. 10, No. 1, 2009, RLA-125, pp. 19-21; Th. Wälde and B. Sabahi, “Compensation, Damages

and Valuation”, in International Investment Law, Vol. 4, Issue 6, 2007, RLA-126, p. 38; B. Bollecker-Stern, “Le

Préjudice dans la Théorie de la Responsabilité Internationale”, Publications de la Revue Générale de Droit International

Public, No. 22, 1973 (extract), RLA-127, p. 310 (“[…] taking into account in the evaluation of the amount of the

compensation the gravity of the fault [of the injured party] irrespective of its link to the damage, or eventually taking

into account the causal role of the faulty conduct to determine the amount of the indemnity granted: this is the idea of

‘contributory negligence’”) (Unofficial translation: “[…] tenir compte dans l’évaluation du montant de la reparation

de la gravité de la faute quelle que soit sa relation avec le dommage, soit enfin tenir compte du role causal de la conduite

fautive pour determiner le montant de l’indemnité allouée: c’est l’idée de la ‘contributory negligence’”); M. Reitzer, La

réparation comme conséquence de l’acte illicite en droit international, Thesis, Paris, Sirey, 1938 (“unanimous case law

diminishes or excludes compensation in cases where the aggrieved party contributed, by his action or by his omission,

to provoke or to increase the damage suffered, or that he hasn’t been sufficiently diligent to prevent the extension of the

damage.”) (Unofficial translation of: “[u]ne jurisprudence unanime diminue ou exclut la réparation dans le cas où le

lésé a contribué, par son acte ou par son omission, à provoquer ou à augmenter le dommage subi, ou bien qu’il n’a pas

deployé toute diligence nécessaire en vue de prevenir l’extension dudit dommage.”), as quoted in B. Bollecker-Stern,

“Le Préjudice dans la Théorie de la Responsabilité Internationale”, Publications de la Revue Générale de Droit

International Public, No. 22, 1973 (extract), RLA-127, p. 311, footnote 855; G. Salvioli, “La responsabilité des Etats

et la fixation des dommages et intérêts par les tribunaux internationaux”, Recueil des Cours de l’Académie de Droit

International de La Haye, 1929/III (extract), RLA-128, p. 266; B. Graefrath, “Responsibility and Damages Caused”,

Recueil des Cours de l’Académie de Droit International de La Haye, 1984/II (extract), RLA-129, p. 95 (“Concurrent

causation by third parties or the injured party himself may entail diminution of the duty to compensation”); J. Crawford,

State Responsibility: The General Part, 2013 (extract), RLA-130, pp. 500-503.

1266 S. Ripinsky, “Assessing Damages in Investment Disputes: Practice in Search of Perfect”, Journal of World Investment

& Trade, Vol. 10, No. 1, 2009, RLA-125, p. 20; MTD Equity Sdn Bhd and MTD Chile SA v Republic of Chile (ICSID

Case No ARB/01/7) Award of 25 May 2004, CLA-49, ¶¶ 242-243; Copper Mesa Mining Corporation v. Republic of

Ecuador, PCA No. 2012-2, Award of 15 March 2016, RLA-8, ¶¶ 6.91-6.102.

Page 275: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

270

the existence of an obligation to compensate and that the latter should be premised on a finding

of responsibility for the commission of an international wrongful act.1267 Therefore, even if

Bolivia had breached its obligations pursuant to the Treaty (quod non), Claimant’s

compensation must be reduced or eliminated on account of its own negligence behavior.1268

955. As explained below, Claimant materially contributed to its alleged losses with respect to the

Mine and the Tin Smelter.

7.5.2 As A Matter Of Fact, Claimant’s Behavior Materially Contributed To Its Alleged Losses

In Relation To Colquiri And The Tin Smelter

956. Should the Tribunal consider that Claimant is not the only party responsible for the reversion

of the Mine Lease (quod non), it must, find, in any event, that Claimant significantly

contributed to the reversion of the Mine Lease. As explained in sections 2.6.3.1 through

2.6.3.3 above, Claimant mismanaged and aggravated the social conflicts at the Mine, forcing

the State to intervene and terminate the Mine Lease in June 2012:

Claimant inherited the social tensions created by Comsur’s poor management of the

relations between the workers of Colquiri and the cooperativistas operating at the

Mine. Instead of properly redressing this situation, under Claimant’s control, the

cooperativistas (and, in particular, the Cooperativa 26 de Febrero) gradually

controlled larger and deeper areas of the Mine,1269 to the point that, “[p]ara finales de

2011, los cooperativistas teníamos prácticamente el control de la Mina.”1270

Claimant requested the intervention of the State at the eleventh hour, making

impossible for COMIBOL to resolve a social conflict that had evolved over years. As

explained above, in the circumstances, it was impossible for COMIBOL to resolve a

1267 See, e.g., A. Moutier-Lopet, “Contribution to the Injury”, in J. Crawford, A. Pellet, S. Olleson, The Law of International

Responsibility, 2010 (extract), RLA-123, p. 639.

1268 RosInvestCo UK Ltd. v. The Russian Federation, SCC Case No. V079/2005, Award of 12 September 2010, RLA-121,

¶ 635 (“[w]hile these contributions of Yukos to its own demise do not change the conclusion that Respondent breached

the IPPA with regard to Claimant’s shares, they may be relevant in the consideration later in this Award of the quantum

of any damage due to Claimant which will be examined hereafter in this award”).

1269 See, for instance, Public Deed No. 0215/2009, amendment to the lease agreement between COMIBOL and the

Cooperativa 26 de Febrero of 21 October 2009, R-210; Colquiri internal report concerning ore bought and/or

transported for the Cooperativa 26 de Febrero of 15 December 2007, R-198; Colquiri internal report concerning ore

bought and/or transported for the Cooperativa 26 de Febrero of 21 April 2008, R-199; Colquiri internal report

concerning ore bought and/or transported for the Cooperativa 26 de Febrero of 17 April 2007, R-200; Proof of payment

for the transport of ore for the Cooperativa 26 de Febrero of 21 October 2007, R-201; Proof of payment for the transport

of ore for the Cooperativa 26 de Febrero of 20 November 2007, R-202; Proof of payment for the transport of ore for

the Cooperativa 26 de Febrero of 7 January 2008, R-203; Colquiri internal report concerning ore transported for the

Cooperativa 26 de Febrero of 25 May 2008, R-204; Colquiri internal report concerning ore transported for the

Cooperativa 26 de Febrero of 29 June 2008, R-205.

1270 Cachi, ¶ 31.

Page 276: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

271

structural problem and ensure the rights of Sinchi Wayra over the Mine Lease in a

matter of days.

Sinchi Wayra’s own employees deeply distrusted its ability to solve the tensions with

the cooperativistas that it had caused and encouraged over the years. Such distrust

explains their decision to Support the reversion of the Mine Lease.

Being fully aware of the Government’s efforts to resolve the conflict provoked by the

taking of the Mine by the cooperativistas on 30 May 2012, Sinchi Wayra entered into

the Rosario Agreement with national leaders of the cooperativas and a fraction of the

Cooperativa 26 de Febrero opposing a potential reversion of the Mine Lease. By

executing the Rosario Agreement, Sinchi Wayra engaged in inconsistent escalated the

conflict to unprecedented levels of violence, and left the State with no other option

but to revert the Mine Lease.

957. Similarly, as explained in section 2.5.4 above, Claimant also contributed to its own losses in

relation to the Tin Smelter.

958. By early 2005, “[t]he overthrow of the main champion of neo-liberal economics in 2003, the

rise of Evo Morales, the palpable shift of politics to the left throughout the country and the

decline of the traditional party structure ha[d] left the business environment clouded with

uncertainty.”1271 This was particularly the case for the Tin Smelter, given the ample publicity

surrounding its irregular privatization since 2001. As discussed in section 2.4 above, following

the adjudication of the sales contract to Allied Deals, local organizations and unions in

Oruro1272 as well as members of the Bolivian Parliament1273 called for investigations to be

1271 Business Monitor International, Risk Summary - Bolivia, 14 January 2005, R-171.

1272 Statement of the Oruro Civic Committee, R-122 (“TERCERO.- Solicitar al Gobierno la inmediata realización de

gestiones para que el daño económico infringido al Departamento de Oruro sea revertido, recuperándose el valor total

de los materiales y concentrados obsequiados al Consorcio ALLIED DEALS.”) (Unofficial translation: “THIRD.-

Request the Government to immediately take the necessary measures so that the economic damage caused to the

Department of Oruro can be reverted, thus recovering the total value of materials and concentrate gifted to the

Consortium ALLIED DEALS”). See, also, Letter from the Oruro Central Obrera to President Banzer Suárez of 23 May

2001, R-126 (“la clase trabajadora y lodos los sectores del pueblo de Oruro, nos encontramos agobiados por el hambre

y la miseria que reina en nuestro sociedad debido a que nuestro patrimonio y que constituía FUENTE DE TRABAJO,

ha sido enajenado ilegalmente y en un monto absolutamente exiguo constituyendo un engaño en la venta del Complejo

Metalúrgico de Vinto a la Empresa Allied Deals”) (Unofficial translation: “the working class and all sectors of the

people of Oruro are overwhelmed by the hunger and misery that reigns in our society given that our asset, which

constituted a SOURCE OF WORK, has been transferred illegally and for a completely inadequate amount, which

amounts to fraud in the sale of Complejo Metalúrgico de Vinto to the company [Allied Deals]”).

1273 Letter from Representative Pedro Rubín de Celis to the Contralor General de la República of 10 May 2001, R-124, p.

2 (“En el numeral 5 del documento denominado ‘acta de Entendimiento’ en fecha de 2 de marzo de 2000 por los

Presidentes de Vinto y COMIBOL, por una parte, y por el representante de ALLIED DEALS PLC dice textualmente:

‘la vendedora depositará, a la brevedad posible en sus almacenes – estaño e incluir estaño metálico dentro de los ítems

ofertados en la venta de la Fundidora’. De esta manera, los compradores obtuvieron en forma fraudulenta el dinero

para comprar la propia fundición en forma de estaño en circuito, en concentrados y en metálico por un valor de

Page 277: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

272

carried out prior to the conclusion of the sale purchase agreement. But the Banzer Suárez

administration paid no mind to such calls for investigation and proceeded to validate the tender

process and conclude the sale.

959. Glencore International decided to acquire the Tin Smelter from fleeing president Sánchez de

Lozada nonetheless, being fully aware of the risk that this Asset might be reverted to the State

in the near future. In fact, it is our understanding that it cashed out a political risk insurance

policy held by several international financial institutions, receiving at least US$ 110-120

million in the process.

960. For these reasons, if the Tribunal were to award compensation to Claimant for Colquiri and

the Tin Smelter, it should reduce that compensation by 75% and, at least, 50% to reflect

Claimant’s contribution to its own damages. Also, as explained in sections 2.5.4 and 2.6.1

above, any such compensation should also be reduced given that Claimant has already

received compensation from its insurer (for the same underlying facts). This amount should

be offset from any compensation awarded to Claimant.

8. PRAYER FOR RELIEF

961. In light of all the above, and reserving its rights to complement, develop or modify its position

at a further, appropriate stage of these proceedings, Bolivia respectfully requests the Tribunal:

8.1 On The Forthcoming Procedural Steps

962. To convene a hearing on Bolivia’s request for bifurcation;1274 and

963. Following such hearing, to order the bifurcation of the proceedings, in order to decide upon

Bolivia’s objections to jurisdiction and admissibility as a preliminary matter.

8.2 On Jurisdiction And Admissibility

964. To declare:

a. That it lacks jurisdiction over Claimant’s claims; and

[US$ 11,477,539]. A ello habrá que añadir las 500 toneladas de estaño metálico entregadas a favor de la compradora

como respaldo al valor ajustado del material en circuito y al valor ajustado de los activos fijos”) (Unofficial translation:

“Item 5 of the document named ‘minutes of Understanding’ of 2 March 2000 [executed] by the Presidents of Vinto and

COMIBOL, on the one hand, and by the representative of ALLIED DEALS PLC, literally says: ‘the seller will deposit

shortly in its warehouses – tin and include metallic tin within the items offered in the sale of the Smelter. This way, the

buyers obtained fraudulently the money to buy the smelter itself in the form of pipeline tin, in concentrates and metal

for the amount of [US$ 11,477,539]. To this must be added 500 tons of metallic tin delivered in favor of the buyer as a

guarantee of the adjusted value of the pipeline material and the adjusted value of fixed assets”). See, also, Formal

complaint by Representative Pedro Rubín de Celis against Minister Carlos Saavedra Bruno, R-125.

1274 See Bolivia’s letter to the Tribunal of 18 December 2017.

Page 278: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

273

b. That Claimant’s claims are, in any event, inadmissible; and

965. To order:

a. Claimant to reimburse Bolivia for all the costs and expenses incurred in this arbitration,

including with interest due and payable from the date Bolivia incurred such costs until

the date of full payment; and

b. Such other relief as the Tribunal may consider appropriate.

8.3 On The Merits

966. If, par impossible, the Tribunal were to find that it has jurisdiction over Claimant’s claims

and/or that such claims are admissible, to declare:

a. That Bolivia complied with its international obligations under the Treaty and

international law;

b. That all of Claimant’s claims are thus dismissed; and

c. That, in any event, Claimant materially contributed to their alleged losses, and that any

amounts the Tribunal may award to Claimant are to be reduced accordingly; and

967. To order:

a. Claimants to reimburse Bolivia for all the costs and expenses incurred in this

arbitration, including with interest due and payable from the date Bolivia incurred such

costs until the date of full payment; and

b. Such other relief as the Tribunal may consider appropriate.

Page 279: PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) …PCA Case No. 2016-39/AA641 Glencore Finance (Bermuda) Ltd. (Claimant) – VS – The Plurinational State of Bolivia (Respondent)

274

Respectfully submitted this 18th day of December 2017