pavement type selection – updated guidance on use of alternate bidding
DESCRIPTION
Virginia Concrete Conference Richmond, VA March 6, 2014. Pavement Type Selection – Updated Guidance on Use of Alternate Bidding . Session Outline. Background on FHWA Policy & Guidance Information. Federal Register Oct 8, 1981 PTS Policy - PowerPoint PPT PresentationTRANSCRIPT
Pavement Type Selection – Updated Guidance on Use of Alternate Bidding
Virginia Concrete ConferenceRichmond, VAMarch 6, 2014
Session Outline
1• Background on FHWA Policy & Guidance on
Alternate Bidding for Pavement Type Selection
2• State Usage
3• FHWA Technical Advisory
2
Background on FHWA Policy & Guidance Information
Federal Register Oct 8, 1981 PTS PolicyIf designs equivalent then alternate bidding permitted
Federal Register Nov 9, 1981 ClarificationDiscourages use of price adjustment clauses w/ AB
23 CFR, Part 626 Non-Regulatory Supplement April 8, 1999
FHWA does not encourage use of AB for PTS due to issue of equivalent pavement designs
3
Background on FHWA Policy & Guidance Information
FHWA Memo Nov 13, 2008 Clarifies & consolidates FHWA policy AB is not encouragedUse of commodity price adjustments should not be usedSEP 14 approval needed if using price adjustments
NCHRP Report 703 – Guide for Pavement Type Selection March 2011
4
PTS Method #1Identify feasible alternatives
Perform LCCA
Cost within specified % of
lowest estimate
Eliminate alternative
NO
YESConsider subjective factors:
constructability, adjoining pavement, competition, traffic control,budget, etc.
Make Decision
Cost within specified % of
lowest estimate
8 states
PTS Method #2 (MI)Identify feasible alternatives 1 rigid, 1 flexible
Perform LCCA
Alternate with lowest LCC
Eliminate alternative
NO
YES
Make selection decision
PTS Method #3Identify feasible alternatives
Perform LCCA
Submit to selection committee. Committee evaluates engineering and economic factors
Committee recommends a
decision
PTS Method #4
Identify feasible alternatives
Perform LCCA
Both rigid and flexible
alternatives are feasible
Eliminate alternative
NO
YES
Prepare LCC Adjustment factor
Alternate Bids to determine pavement type
10-25 states
Components of Agency Processes– Selection of alternatives– Structural design– Economic Analysis– Primary/Secondary Factors
Contractor-based processes– Alternate Bidding– Design Build– Long Term Warranty– Other ( PPP, Value Engineering, BV Contracting, Contract
Maintenance)
Overview of Pavement Type Selection
State Usage
10
State has advertised at least 1 alternate bid jobState has not utilized alternate biddingState did not reply to survey
Technical Advisory
Use of Alternate Bidding for Pavement Type Selection, T 5040.39 December 20, 2012Elimination of SEP 14 approval for price adjustments, November 8, 2012
11
Question 1 Purpose of TA
Guidance on use of AB for PTS on Federal-aid projects on NHS
12
Question 2 Does TA Supersede other Guidance
TA Supersedes:– Federal Register FHWA PTS Policy Statement
11/9/81– 23 CFR 626 NR Supplement issued 4/8/99– HIPT Memorandum issued 11/13/08
13
Question 3 Background on AB for PTS
Risk associated w/ material costs and performance23 CFR 626 NR Guidance did not encourage use of ABLimited use due to:– lack of national guidance, – consistent approach to AB and – open competitive bidding environment
14
Question 4 Scope/Applicability of TA
Recommended practice for use on FA projects on NHS
15
Question 5 FHWA Position
Suitable approach when,– Engineering/economic analysis shows no clear
choice between different pavement designs
16
Question 6 When is AB Appropriate
Equivalent Designs– Similar level of service over same performance
period (use of ME Design software)– Similar life-cycle costs
• Performance period should include min one major rehab
• NPV < 10% of alternative
17
Question 6 When is AB Appropriate
Discount Rate– Guidance available in LCCA in Pavement Design –
Interim Tech Bulletin Sept 1981– Recommend use of NPV for future costs– Recommend use of Real Discount Rate consistent
w/ OMB Circular A-94
18
Question 6 When is AB Appropriate
Consideration of Uncertainty– Determine total LCC for each alternative– Consider use of RealCost software
19
Question 6 When is AB Appropriate
Maintenance and Rehab Strategy– Should reflect realistic pavement management practices– Should utilize realistic timing and extent of M&R
activities– Provide similar level of service over performance period– NCHRP Report 703 Section 3.5 has reasonable approach http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_703.pdf
20
Question 6 When is AB Appropriate
Non-Economic Factors– Agency may consider,
• Constructability• Continuity of adjacent pavements• Availability of local materials• Experience
21
Question 6 When is AB Appropriate
Appropriate Application– Only use when AB will likely influence
determination of lowest bid– Projects w/ substantial quantities of different
pavement items not suited for AB
22
Question 6 When is AB Appropriate
Work Zone User Delay Costs– Not suited when user delay costs for initial
construction and M&R exceed 20%
23
Question 7 Administration of AB
LCCA Bid Adjustment– Should be used for all AB projects– Compute NPV of all unique costs over performance
period– Establish process w/ industry input– Include LCCA bid adjustment in project specs– Should not include non-agency costs
• User delay costs • Vehicle operating costs• Environmental costs. Etc
24
Question 7 Administration of AB
Commodity Price Adjustment– Not desirable
• Difficult to administer equal treatment• May result in in different levels of material cost risk
25
Question 7 Administration of AB
Quality Price Adjustments– If used,
• Provide similar incentives/disincentives for all alternate pavement types
26
Question 7 Administration of AB
Material Quantities– Pay items based on weight/mass may result in cost
overruns– Recommend agency establish process to monitor
costs to prevent any systematic bias
27
Question 7 Administration of AB
Approvals– Title 23 U.S.C. 112 FA construction contracts
awarded based on lowest responsive bid– SEP 14 Innovative Contracting
• Evaluated use of alternate pavement type bidding using LCCA bid adjustments
– Approval of LCCA bid adjustments no longer required per Nov 8, 2012 memo
28
Question 7 Administration of AB
Change Orders– Should not allow post-award change order for
pavement type
29
Question 8 Program Effectiveness
Monitor number of bidders and unit cost of projectsSolicit input from respective pavement industry groups
30
Question 9 Reference Materials
NCHRP Report 703 dated November 2011, Guide for Pavement Type Selection http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_703.pdf
31
Questions
Gary CrawfordPavement Design and Analysis TeamTele: (202) 366-1286E-mail: [email protected]
32