Pathfinder update webcall

15th May 2009

Welcome to the

BT's 21CN programme is subject to consultation and further development. Dates and other details should be treated as indicative only, and subject to change

Page 2: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Agenda

• Recap of Pathfinder objectives and progress

• Completion of Pathfinder 1 & information

• Learning from Pathfinder so far

• The next stages of Pathfinder?

• Reminder of opportunities to engage

• Question and answer session

Page 3: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Voice migration first phase of voice pilot activity – Pathfinder • The voice migration and pilot activity in preparation for voice network

migration is known as Pathfinder

• This pilot activity involves voice line migrations only at present

• The pilot is taking place in a small area of South Wales

• Pathfinder is providing learning and helping to build confidence for large scale migrations

• All planning and operational activities are carried out in close collaboration with a working group of service providers

• We are contacting service providers with customers in the area ahead of migration activities

Page 4: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Pathfinder

• The first phase of Pathfinder has now successfully completed

• 15 exchanges migrated to 21CN in the South Wales area

• The final 3 exchanges (Llandaff, Whitchurch and Llanishen) were successfully migrated on 7th May 09

• There were no issues with the migration of 3 sites in a night

• CPE payment machines that caused issues at previous sites were successfully groomed

• A total of 64K working customer lines have been migrated to 21CN

• XXX number of calls have been carried over 21CN

Page 5: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Completed exchange migrations

Exchange name

Date of migration Exchange name Date of migration

Wick 23rd October 2008 Caerphilly 26th March 2009

Bedlinog 30th October 2008 Roath E 23rd April 2009

Nelson 6th November 2008 Roath D 23rd April 2009

Penarth 22nd January 2009 Llanishen 7th May 2009

Ynysybwl 5th February 2009 Whitchurch 7th May 2009

Treharris 19th February 2009 Llandaff 7th May 2009

Cardiff S 5th March 2009

Ferndale 12th March 2009

Tonyrefail 12th March 2009

Page 6: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Learning from Pathfinder so far

• Key findings

- Proved the slow start approach taken is the correct one

- Tested the technology, processes and supporting tools with CPs

- Fault numbers continue to run at a low level, at or below numbers for 20C

• Niche CPE problems now understood and fixes planned

• No significant issues with Caller Display, burglar alarms or ATMs

• No recent significant platform issues, good call quality & good network performance

• CP confidence built

Page 7: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Pathfinder – the next phase

• Moving into “Pathfinder Volume POTS”

• Voice migrations only, not ISDN2/30

• January 2010 through to July 2010 • Increasing the South Wales footprint

• 7 DLEs to be migrated – Cardiff G, L, E, F, Bridgend, Cardiff B & Pontypridd

• Will complete the migration of up to 260K lines

• No change to architecture for Pathfinder Volume POTS - Ericsson based call server

• Gradual migration of groomed or regressed lines will take place

• July 2009 – September 2009 - Call Server and MSAN upgrades in Pathfinder area – providing further functionality and increased industrialisation

• Will provide key learning following migration of a complete DLE in a night

Page 8: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Opportunities to engage• Regular calls will continue through the summer (refer to the Consult21 planner

for details)

• Ability to influence the programme by attending the Consult21 Implementation and Migration working group

• Receive the monthly summary of 21CN activities via Consult21

• View the Pathfinder update report via the Consult21 website – www.btwholesale.com/consult21, under the IMWG working group section

• The Pathfinder Dashboard and Learning Log can be found in the Secure Area of the Consult21 website

• Do visit the Consult21 migration one stop shop area of the website – to view the supporting tools available

Email [email protected] for information on how to become engaged

Your customers are affected – it’s important for you to be aware and engaged

Page 9: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Useful information & how to get engaged

Or visit these sites

The Consult21 website: www.btwholesale.com/consult21

The independent public information website covering the process of migration: http://www.switchedonuk.org

For general information about BT’s 21CN programme go to: http://www.btplc.com/21CN/

Page 10: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Answers

Questions

Page 11: Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details

Thank you for coming on the call