partners in pisd future january 15, 2012
DESCRIPTION
Partners in PISD Future January 15, 2012. Building Eagle Excellence. Culture of our Work. Appreciation (see listing) of participation Self accommodation (take care of your needs) Presentation/large and small group discussion Focus groups Packet contents - PowerPoint PPT PresentationTRANSCRIPT
Building Eagle Excellence
Partners in PISD FutureJanuary 15, 2012
Culture of our Work
• Appreciation (see listing) of participation• Self accommodation (take care of your needs)• Presentation/large and small group discussion• Focus groups• Packet contents– Copies of powerpoint/data overviews– Additional data as requested
AGENDA
First Meeting• Overview
• Financial Status• Data Sources
• Areas of Focus - DRAFT
Second Meeting (tonight)• Bond Considerations/Impact• Tour Plan• Next Steps
Data Sources*
• Internal facility/technology needs assessment• Safety audit (M. Fletcher/team)• Financial audit • Internal resource review• External technology audit (Renaissance)• Demographer study (due – end of January)• Traffic flow engineering (TBD)
* copies available as needed
Areas of Focus
• Immediate Needs Assessment – Safety– Facility/learning environments
• Completion of QSCB• Training Facility (2 year Project) • Technology (TBD) – Campus Needs Assessments• Bond Considerations/Impact on Citizens
Facilities Review
New Elementary
Primary • Keyless entry• Canopy• Traffic Flow• K-1 PlaygroundNEW ElementaryIntermediate• Safe entry/admin move• Parking• Science/New Wing• Playground• Cosmetics/Rest RoomsJH• Science Rooms• Gym/Lockers• Cosmetics• Relocate bus pick-upFencing for all campuses Prek-8
Future HS EditionCareer Tech Center
High School
Training Center
Parking lot
Band Pad
Green space/ TBD
Pause and Reflect – Qs
What Next?* Review financial impact
2012 ISD Tax Rate ComparisonSimilar Size & Locale to Pleasanton ISD – Data from Texas ISD 2012 Tax Rate Survey
School District M & O Rate I & S Rate Total
Beeville ISD 1.04000 0.22553 1.26553*
Charlotte ISD 1.01000 0.17000 1.18000*
Cuero ISD 1.29000 0.03000 1.32000
Devine ISD 1.17000 0.21200 1.38200
Dilley ISD 1.11578 0.08475 1.20053*
Floresville ISD 1.04000 0.47580 1.51580
Jourdanton ISD 1.1221 0.00000 1.12210 **
La Vernia ISD 1.04000 0.35500 1.39500
Lytle ISD 1.17000 0.25000 1.42000
Medina Valley ISD 1.04000 0.38000 1.42000
Pearsall ISD 1.04000 0.17050 1.21050*
Pleasanton ISD 1.04000 0.09000 1.13000
Poteet ISD 1.04000 0.37900 1.41900
Somerset ISD 1.17000 0.10800 1.27800
Southside ISD 1.17000 0.19890 1.36890
Three Rivers ISD 1.00000 0.11720 1.11720
2012-2013 ISD Tax Rate ComparisonSimilar Size & Locale to Pleasanton ISD – Graph Format
BeevilleCharlotte
CueroDevine
DilleyFloresville
JourdantonLa Vernia
LytleMedina Valley
PearsallPleasanton
PoteetSomerset
SouthsideThree Rivers
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6
M & O RateI & S Rate
PLAN A
New Comprehensive High School• 1600 students/248,000 sq. ft (155 per student)• No Auditorium/includes practice fields/gyms, etc.
$54,500,000 (includes all FFE/Fees/Survey, Geo)• Does not include cost of land and road access
Renovated facilities• Primary• Pick up/Drop Off area; road construction• Playground/parking/Safety doors• Growth (6-8 classrooms)
$ 1,500,000 -$4,000,000 (classrooms)
• PIC/JH (serve elementary and PIC students)• Safety entrance/admin wing• 13,100 sq ft. addition (wing)/additional classrooms• Parking/Playground/Sports Court• Gym remodel/windows/roof• Cosmetics/Parent Drop off
$ 7,000,000.• HS (serve JH and potential PIC students)• Remodel/cosmetics (walls, locker, repurpose rooms)• Remove metal buildings/landscape/parking
$ 4,000,000
• Technology $ 2,500,000• Support Areas $ 4,500,000
• Maintenance relocation, buses, offset of stadium)Total: $ 74,000,000-
$76,500,000
PLAN B
New Elementary School• 1000 students/115,000 sq ft• Playground/sport court• Road development
$ 29,000,000(includes FFE/fees/survey/geo)
Renovated facilities• Primary• Pick up/Drop Off area; road construction• Playground/parking/Safety doors• Growth (6-8 classrooms)
$ 1,500,000 -$4,000,000 (classrooms)
• PIC • Safety entrance/admin wing• 13,100 sq ft. addition (wing)/additional classrooms• Parking/Playground/Sports Court• Cosmetics/Parent Drop off
$ 4,000,000.• JH• Safety entrance/admin wing/Science classrooms/windows• Cosmetics/Parent Drop Off $ 5,000,000.
• HS • Remodel/cosmetics (walls, locker, repurpose rooms)• Relocated Admin/Counseling; Covered pick-up• Career and Tech Center/Parking/Road
$ 23,000,000• Technology $ 2,500,000• Support Areas $ 4,500,000
• Maintenance relocation, buses, offset of stadium)
TOTAL: $ 69,500,000- $72,000,000
15% growth
8% growth
Taxpayer ImpactBond 2013
Property Categories
Property Values
Exemptions Net Value Current Tax Rate
Tax 30₵ Tax Rate Increase (Proposed)
New Tax Additional Tax Per Year
Additional Tax Per Month
1 Homestead 100,000150,000200,000300,000
15,000 15,000 15,000 15,000
85,000135,000185,000285,000
1.13 per 100 Value
960.50 1525.50 2090.50 3220.50
1.43 per 100Value
1215.501930.502645.504075.50
255.00 405.00 555.00 855.00
21.25 33.75 46.25 71.25
2 Homestead Over 65 Exemption
100,000150,000200,000300,000
15,000 15,000 15,000 15,000
85,000135,000185,000285,000
1.13 per 100 Value
960.501525.502090.503220.50
1.43 per 100 Value
960.501525.502090.503220.50
0 0 0 0
0 0 0 0
Business/ Commercial
250,000350,000450,000
0 0 0
250,000350,000450,000
1.13 per 100 Value
2825.003955.005085.00
1.43 per 100 Value
3575.005005.006435.00
750.001050.001350.00
62.50 87.50 112.50
Ag exemption consideration
1– Based on Current Values Remaining the Same From 12-13 to 13-142– Tax Bills are Frozen at the Time of Approval of Over 65 Exemption
2012-2013 ISD Tax Rate ComparisonSimilar Size & Locale to Pleasanton ISD – Graph Format
BeevilleCharlotte
CueroDevine
DilleyFloresville
JourdantonLa Vernia
LytleMedina Valley
PearsallPleasanton
PoteetSomerset
SouthsideThree Rivers
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6
M & O RateI & S Rate
Table Talk
• Plan A and Plan B review– Missing elements– Priority items (what could wait)– Perceived challenges
SummaryPartners Meeting (2)
• Questions for clarification
• Packet Review– Additional Partners?– Additional Data needs?
Next Steps:- Partners share
information and gather feedback
- Partners meet next week at ELEM (or send representative*)
- 3rd meeting focus on recommendations for Board of Trustees
THANK YOU……
this PARTNERship is essential to ensure future Pleasanton Eagles Soar!