partnering 4 april 2011
TRANSCRIPT
-
7/27/2019 Partnering 4 April 2011
1/21
1
CIVL6021 - PARTNERING
1. IntroductionThe construction industry has an unenviable reputation for cost overruns, delay,
disputation and occasionally incurred in expensive litigation. Stakeholders in the
industry have been looking for alternative ways of structuring projects to avoid these
outcomes. In the early nineties a concept imported from the United States called
"partnering". Before exploring the effectiveness and impacts of partnering on the
construction industry, it is necessary to consider more on the common forms of
contract being used and the associated risks allocation to determine why they are
perceived to have failed the industry.
1.1 The Forms of Contract Commonly used in the Construction Industry
There are three basic forms of contracts commonly adopted by stakeholders:
(a) Traditional
(b) Design and construct
(c) Project management
In Traditional form, the project owner will engage an independent designer
(either a professional engineer or architect) to perform designing the scope ofwork. This is usually done prior to the contract for construction being awarded.
A contractor is appointed for the construction work in accordance with the
design, in usually practice, on a lump sum basis. However, it should be noted
that the final amount payable unlikely to equal the lump sum agreed.
InDesign and Construct engagement the contractor is responsible for both
design and construction tasks as a package. The contractor in this contract
arrangement is often paid on a lump sum basis. And again, it is unlikely that the
amount paid to the contractor will equal this lump sum. However, the advocates
for this style of contracting argue that subject to good management, there is less
potential for cost overruns.
In Project Management form of contract, the project manager/contractor is
engaged as an agent of the owner. The project manager's obligations included
appointing a design professional (engineer/architect) to prepare the design and
manage that professional as agent of the owner, and progressively engage trade
contractors to perform work as and when the design is completed. These
-
7/27/2019 Partnering 4 April 2011
2/21
2
contractors will usually be engaged on a lump sum basis. Again, when engaging
such trade contractors, the project manager is acting as agent for the owner.
1.2 Typical risk profiles associated with these forms of contract
The generic risks in construction projects are poor design, poor construction,
cost overruns, and time overruns. Although the exact risk profile under each
form of contract can be adjusted by appropriate drafting, the respective risks
associated with each of the traditional forms.
1.2.1 The Traditional form of contractIn this form of contract, the risk of poor design lies with the consultant. The
capacity of the consultant to take such risk will be dependant upon the
adequacy of its insurance policy (professional indemnity).The risk of quality of construction obviously lies with the contractor. Under
most standard form contracts, the contractor is obliged to construct in
accordance with the plans and specifications prepared by the project owner's
consultant. A failure to do so will constitute a breach of contract often entitling
the project owner to instigate a contractual regime requiring the contractor to
rectify the works or to pay the costs of the owner so doing; or pay damages
associated with the breach.
The risk of Cost Overrun in traditional forms of contract, which in majoritycases are "lump sum price" contracts, the lump sum price is subject to
adjustment will depend upon a number of factors. These factors included the
drafting of the contract, the process and the effectiveness of the design
consultant as well as the accuracy of information provided by the consultant
(e.g. the contractor is given geotechnical information which is incorrect).
Failure of such can give rise to breaches of contract entitling the contractor to
damages. Change in the scope of work constitutes a variation in which the
contractor entitles to further remuneration.
Notwithstanding that there are a number of reasons which might give rise to a
change in contract price, it is important to understand that margins earned by
contractors in are extremely low and the risk profile of those contractors is
relatively high. The low profit and significant potential for high risk is one of
the main drivers for the adversarial and contentious nature of the relationship
between contractors and project owners.
The risk of Time Overrun is split into neutral delays, project owner caused
delays and contractor caused delays. In neutral delays such as excessive
inclement weather and social disruptions (turmoil and strike) unrelated to the
-
7/27/2019 Partnering 4 April 2011
3/21
3
site, the project owner has taken the risk, the contractor will be entitled to an
extension of time and thereby be relieved of the obligation to pay liquidated
damages. The contractor will have to bear his own loss in overheads. In
project owner caused delays, the contractor will be entitled to an extension of
time to relief from liquidated damages and additional remuneration to
compensate for the additional overheads. In contractor caused delays,
contractor must bear its own overheads costs and will not be entitled to an
extension of time and therefore is liable to the owner by way of liquidated or
general damages.
1.2.2 The design and ConstructThe risk profile in design and construct contract in relation to cost, time and
construction is usually the same as that taken by a contractor under a"construct only" contract. The contractor is responsible for both design and
construction. Therefore any defect in the work the contractor must be
responsible. As the contractor is given the task of completing the design to a
design brief, the project owners risk is lost of the control over the final design
and functional expectation. Most of these projects narrowly defined the
aesthetic of the finished product and the performance criteria of novel
mechanical or process engineering in a project brief. This form of contract is
unsuitable for circumstances where the project owner wants aesthetics effectsand special functional requirements.
1.2.3 The Project Management ContractThe essential features of project management contract are the project owner
appoints a "project manager" to act as his agent to manage both the design
process and construction. The project manager undertakes to exercise
reasonable care in his management services. However, the project owner still
facing the risk on design, construction, cost overrun and time overrun.
Because diligence of the project manager it does not definitely warrant that the
project will be built to a particular standard and be completed by a particular
time at a particular price.
The risk of poor design is shared between the project manager and an
independent design consultant employed by the project manager (in its
capacity as agent for the owner). Primary responsibility for the quality of
design rests with the design consultant, except in unusual circumstances, it
will not be liable by the project manager.
The capacity for the risk to be borne by the designer under professional
-
7/27/2019 Partnering 4 April 2011
4/21
4
indemnity insurance in which insurers are notorious for contesting liability.
In the project management model, therisk in construction is likely rest with
the project owner. The project manager engage a number of trade contractors
who are only responsible for their own works and generally enter into a
contract where it undertakes to complete works in accordance with the
specified standard. Problems do arise where more than one trade contractor is
responsible for the end result. It is not uncommon that trade contractors blame
one another for any defect that might appear in the final work. Similarly,
problems arise where the work of one trade contractor is damaged by the work
of another.
Any risk in cost overrun is rest with the project owner. The project manager is
not responsible for costs, except increases of cost which are a consequence of
the project manager's negligence. Generally, the costs will be the aggregateamount paid the design consultants, the trade contractors plus the fees of the
project manager.
The risk in time overrun is often represented by delays and disruption in
co-ordination difficulties between trade contractors. Logically, the primary
responsibility of coordinating the trade contractors rests with the project
manager. However, even with the best project management, co-ordination
difficulties can arise because of non performance of one or more of the trade
contractors which interferes with the operations of subsequent tradecontractors. Again it is generally the case that the project manager does not
take any risk in relation to time, apart from its general obligation to exercise
reasonable care in the management function.
2. Why Partnering
All stakeholders share the common goal to complete the project successfully with
respect to the prescribed time, budget, quality, and its final functional requirement.
Partnering reduces dispute and litigation; it would save countless non-productive
hours of works by all parties involved in the project. It results
1.Owners money becomes more cost effective2.Contractor and Designer are more profitable.
Stakeholders of the have vested interest in the successful completion of a project
in the following perspectives:
Project owner success of final product and turn over to user Contractor meet specification, profit and timely payment Subcontractor & Supplier meet specification, profit and timely payment Designer properly implement the design that meets the owners expectations
-
7/27/2019 Partnering 4 April 2011
5/21
5
Partnering can essentially be differentiated into two types:
(1) Project Partnering(Project-specific or Project-by-Project Partnering), and
(2) Strategic Partnering(Multi-project or Long-term Partnering)
Project Partneringis the name given to partnering arrangement for one project only,
while Strategic partnering takes place when two or more firms use partnering
approach on a long-term basis for more than one project or continuing activities.
2.1Principles of PartneringTo achieve the merit of partnering and accomplish the common goal, all parties
vested interest in the project should put away all negative cultural characteristics
and engage in a more productive and open relationship of honesty, trust andsynergy for the project.
There are numerous of definitions of partnering have been derived form past
studies, definitions that emerged in the early nineties applicable to all industries
state that Partnering is one such technique, which attempts to create an effective
project management process between two or more organizations. It aims at
generating an organizational environment of trust, open communication and
employee involvement (Sander and Moore 1992). The definition of partnering
developed for the construction industry in CII, 1991 in the USA states A
long-term commitment between two or more organizations for the purposes of
achieving specific business objectives by maximizing the effectiveness of each
participant resources. This requires changing traditional relationships to a shared
culture without regard to organizational boundaries. The relationship is based on
trust, dedication to common goals, and an understanding of each others
individual expectations and values (CII, 1991). In England, the CIB (UK)
defined partnering to be: A structured management approach to facilitate team
working across contractual boundariesit should not be confused with other
good project management practice, or with long-standing relationships,
negotiated contracts, or preferred supplier arrangements, all of which lack the
structure and objective measures that must support a partnering relationship
(CIB, 1997).
Partnering is the simple process of establishing good working relationships
between contracting parties. When everybody brings his/her real heart towards the
common goal; creation of a high-trust culture will develop among the counterparts
within the project team gradually. This culture requires that team member accept
the mistakes and errors of others and assist them in finding solutions that aremutually agreeable to all of the team members. This is not to say that one or
-
7/27/2019 Partnering 4 April 2011
6/21
6
more parties can abrogate their contractual responsibility through the partnering
process. On the contrary, each party is faithful to their respective role and takes
responsibility for all actions related to the contract. The study of Chan et al (2002)
grouped the common benefits of partnering in thirteen headings, namely, reduced
litigation, better cost control, better time control, better quality product, efficient
problem solving, closer relationship, enhanced communication, continuous
improvement, potential for innovation, lower administrative cost, better safety
performance, increased satisfaction, and improve culture. Table 1 shows the
matrix of the identified benefits and the frequency of their citation.
Table 1. Source of reference for partnering benefits
Source: Chan et al (2002)
-
7/27/2019 Partnering 4 April 2011
7/21
7
2.2 Partnering and Total Quality Management (TQM)
The theories of TQM and the principles of partnering are mutually compatible
to each other.
TQM advocates and focuses on customer services.
TQM emphasizes continuous improvement in quality of product and service.
TQM recommends supplier and customer relationship.
Partnering recognizes that construction project is nothing more than
compilation of many processes and the effort of many customer and suppliers.
TQM theories apply through partnering process enhance customer services
thus building up relationships between all involved parties. The project owner,
the main contractor, subcontractors and suppliers will find greater success and
profitability in their respective roles.
2.3 Benefits of Partnering
Partnering benefits all parties including the project owner, the main contractor,
subcontractors, supplier and on-site employees. The fundamental principles of
partnering in commitment, trust, respect, communication and equality are
designed to include proper consideration of the interests of all parties at every
level (CII, 1991; Cowan et al, 1992; Badger and Mulligan, 1995). Partnering
process empowers all the project personnel to accept responsibility and to dotheir jobs by delegating decision-making and problem-solving to the lowest
possible of authority. The range of common benefits illustrated in Table 1
identified the weighting among the merits.
In partnering arrangement, the problems of disputes, claims or litigations are
greatly reduced through open communication and improved working
relationship. Closer working relationship between the project owner,
contractor, and the design consultants provide a better working environment to
all parties. Traditional adversarial relationship between parties transforms to a
trust based relationship (Lazar, 1997; Drexler and Larson, 2000). Partnering
recognizes an implied covenant of good-faith dealing by all parties, within this
atmosphere of cooperation and mutual trust, the parties can jointly determine
and evaluate the design, engineer and construction approaches. The tools for
sharing of gains and risks thus established among parties. Better cost control
is another merit of partnering. It is achieved by alleviating rework, lowering
change order rate and improving problem-solving. Reduce unnecessary delays
by the fair and equitable attitude that resolve many disputes, discrepancies and
changed conditions which arose during construction process, thus achieve
-
7/27/2019 Partnering 4 April 2011
8/21
8
better time control through the project duration. Partnering facilitates
communication on quality issues, enables earlier recognition of potential
problem and helps develop a quality consciousness. Problem solving is swiftly
responded and handled at all levels within the project team via delegation
mechanism down to the lowest possible level in dealing with problems.
Partnering provides a way to all parties to develop continuous improvement,
encourages introduction of advanced technology and innovation through open
communication in design and construction process. Administration cost is
lowered by eliminating defensive case building, simplified administrative
procedures and reduced unnecessary paperwork. Taking joint responsibility to
ensure a safe working environment for all parties reduces the risk of hazardous
working conditions and avoids workplace accidents (Matthews and Rowlinson
1999). Partnering enhances customer satisfaction as the customer is closer tothe construction process and better informed. Contractors obtain a reasonable
and are assured for continued work at predetermined profit margins (Moore et
al, 1992; Back and Sanders, 1996). When people work in a conflict-free
environment will show distinct improvement in the culture. They concentrate
on the job rather than on potential claims, and the morale and effectiveness of
the whole work team is improved (Bloom, 1997).
2.4 Barriers of PartneringMisunderstanding of partnering concept is one of the major barriers in
partnering implementation. Some project participants failed to understand how
the partnering relationship could provide a competitive advantage. Larson and
Drexler (1997) advocated that limited experience in partnering approach
affected the understanding and knowledge of project participants could cause a
failure in partnering. The objective of partnering encourages project
participants to change from their traditional adversarial attitude to a more
cooperative, team-based approach to prevent disputed attitude. The unchanged
traditional adversarial relationship and other inappropriate attitudes hamper
the development of good relationship between contracting parties. Many
parties do not trust other party due to past experiences; therefore it is difficult
to build trust among them. Risk sharing is another barrier to the success of a
partnering project. Trying to take full advantage of the partnering approach
resulted in parties may be unwilling to share the risk. In some cases,
partnering created strong dependency of the partner, Gardiner and Simmon
(1998) explained that partnering did not remove or reduce inter-dependencies,
it could be used to strengthen the relationship and increase the trust between
-
7/27/2019 Partnering 4 April 2011
9/21
9
parties. Furthermore, partnering is culturally opposed to the traditional
implementation of construction projects. Established a new culture is difficult
or may take time to implement, many organizations are reluctant to change
into integrating culture. Particularly the reluctance appears in bureaucratic
organizations which impeded the effectiveness of partnering. Partnering
requires the commitment of all participants. Participants must have total
commitment to the partnering process. However, uneven level of commitment
is common in practice due to different goals and objectives among parties.
Failure in communication is a common ground which affected the
effectiveness of partnering. Communication should be two-way, clear, and
open, timely response in the same way is expected. Parties do not normally
trust each other completely and are not willing to communicate and exchange
information. Issues and problems are allowed to slide and escalate in thepartnering process. Conflicts among participants are existed when the
partnering team is reluctant to identify, confront and resolve problems.
Partnering needs nourishment throughout the life of a project, joint effort in
maintaining continuous improvement is important to keep partnering going.
After the initial partnering workshop, it is easy to get back to daily activities
and ignore the partnering concept. Training is the essential activity to make
participants to fully understand the concept of partnering. Insufficient training
provided to participants is an obstacle to successful partnering. Topmanagement commitment is essential to the success of the partnering process
in any organization. Top management commitment goes beyond signing the
partnering charter or writing policy letters. It requires an executive to invest
his/her time in early partnering workshops, train staff, and work with industry
counterparts.
In order to improve the productivity and performance of the project, critical
success factors (CSF) in partnering should be identified. They are resources,
management commitment and support, mutual trust, continuous commitment
and willingness, coordination, creativity, effective communication, conflict
resolution, perceived satisfaction of partners expectations and compatible
goals.
3. The Process of Partnering
The partnering process shall be implemented at the very beginning of the project. The
process included the expression of interest, partnering workshop, follow up workshop
and final workshop. Figure 1 shows the process of partnering.
-
7/27/2019 Partnering 4 April 2011
10/21
10
The most important element in the establishing a partnering relationship is
commitment from the senior management (Mohr and Spekman, 1994). It must be
visible, supportive, ongoing and sensitive to organizational change.
3.1 Partnering Workshop
A well-planned initial partnering workshop is a unique opportunity for all
participating parties to form a cohesive project team leading to the success of the
project. The initial partnering workshop is most important to the partnering
process, because it
Shows commitments of the parties, Helps building up a cohesive project team from all involved parties, Develops problem resolution scheme, Establishes empowerment in all levels of project members, Expedites problem solving path and time via escalation ladder so as to allow
a timely resolution of problem,
Supports profit sharing arrangement (when applicable) Ensures the agreed partnering results, all participants sign the partnering
charter (an example of partnering charter is shown in Figure 2).
Figure 1: The Partnering Process
Source: Abudayyeh (1994)
-
7/27/2019 Partnering 4 April 2011
11/21
11
Participation of CEO/Executive level is an essential element for a successful
partnering. The presence of CEO/Executive levels is a clear indication of the
commitment of the company in partnering. CEO/Executive levels involvement
is related to the establishment of the corporate partnering philosophy.
CEO/Executives attendance with their counterparts in the workshop strongly
supported the building of relationship and understanding among parties. The spirit
that developed will ultimately assist in resolving issues in an equitable manner
throughout the course of the project.
Figure 2: Partnering Charter
-
7/27/2019 Partnering 4 April 2011
12/21
12
3.2 Location and Facilities
The venue where the workshop takes place should be close to the job site. It
should be chosen in the neutral place that does not belong to any participating
parties. The reason is that a neutral facility provides an environment where team
members can come together in non-threatening surroundings and develop into the
project team. It also removes the members from their normal works thus
eliminates distraction and interruption.
An experienced facilitator is important to assist the key managers from each
organization in developing the agenda for the workshop. The facilitator is also
responsible to produce the written record of the workshop and furnish it to the
team participants. This permanent record can then serve as the basis for future
reference should issues arise during the course of the project.
3.3 Team Building
Build up a partnering team with all involved parties of a project is built up among
different levels of the participants. Parties from various firms do have different
cultures and ways of communication. The workshop facilitates identifying the
effective communication methods and reporting paths most applicable for the
project. Through open discussion in the workshop, participants share experiences
and map anticipated problems of the project. Everyone attending the workshop
expresses views and ideas to the anticipated problems and suggests solutions viabrainstorming. All team members have issues to bring up at the workshop. Ideas
are discussed and shared. All emerged resolutions are recorded as reference of
implementation. Unresolved problems are also recorded for further action. A
Plan of Action is established by setting up ownership and expected time of
resolution.
The process of experience sharing and brainstorming enhances understanding and
communication, forming an atmosphere for everyone to know each other and
work together before the commencement of the project. Through an effective
initial partnering workshop, a sense of work together as a team will be built up
among all.
3.4 Resolutions of Partnering Workshop
a) EmpowermentEmpowerment is the delegation of suitable authority and responsibility to the
team members at all levels of the project. Empowerment shall be given to the
lowest possible level in the construction site. In this arrangement, members
whom are closest to the problem could make timely decision within their
-
7/27/2019 Partnering 4 April 2011
13/21
13
scope of their given power.
b) Escalation Ladder (Issue Resolution Matrix, Communication Matrix)Establish highest extent of decision-making power to all levels of the project
among all partners within the partnering team for problem resolving. Time
limit will be set up for all levels to evaluate and resolve their problems. If a
problem cannot be resolved within the time frame or the problem is beyond
their authority to make decision, it will be reported to their immediate
supervisor for further action within the allowable time limit. The problem will
therefore be escalated to the suitable decision makers to resolve within a
limited time frame.
The following table (Table 2) is an example of Escalation Ladder which isfictitiously prepared to illustrate the arrangement and significance.
Table 2: Delegation of Power by means of Escalation Ladder
3.5Expanding the Partnering TeamOwnerContractorDesigner, are not the only key players in the project.
Subcontractors and Suppliers play an important role. There are a number of key
subcontractors and suppliers have been appointed before the commencement of
the project, they are also invited to the workshop and join the cohesive project
team as members. Their participation in partnering workshop, joining the project
team and signing in the charter signifies their importance in the project. The
views and concerns of subcontractors and suppliers are heard and addressed
because other members in the project team value their participation as parties of
the partnering process and their performance is vital to the success of the project.
Of course subcontractors and suppliers are given greater respect to the employer
and the contractor as their respond to their participation as team member, they also
incur greater expectations and assume responsibilities towards the success of the
project. More subcontractors and suppliers will be added as the project goes along,
and key subcontractors and suppliers are selected to become members of the
project team and invited to join the mid-partnering workshop.
Client
Side
Contractor
Side
Time limit for
Decision Making
Name Position Name Position
Mr. Chan Executive Director Mr. Lee CEO One week
Nancy Project Director Robert Director Four days
Henry Project Manager Tony Project Manager Two days
Mary Engineer Jim Coordinator One day
John Works Supervisor Michael Foreman Half day
-
7/27/2019 Partnering 4 April 2011
14/21
14
4. Value Engineering in PartneringThe gain-sharing scheme is an opportunity for contractor to propose alternative means
or materials to achieve a product of equal or greater quality and value for a project.
Value engineering is not favorable in the construction industry due to reasons as
follow:
Designers were often offended by the idea that someone would come up withbetter ideas than that they had spent considerable time designing.
Owners have not encouraged the submission of proposals because they donot want to hassle with them.
Contractors are reluctant to submit proposals because they may noteventually be benefited contractually, deduction of contract sum often result
when the proposals are adopted.
The partnering workshop provides an excellent opportunity to allow this synergism totake a hold and produce innovative results. The skills and innovation that
contractors, designers and owners bring together and set the stage for exciting value
engineering opportunities to the project. In partnering workshop, VE idea is
modified to make it consistent with the one-team approach. So that VE proposals are
no longer considered solely the contractors idea. A term value engineering joint
proposal (VEJP) is given.
Contracts performed under partnering mechanism often include arrangement to share
some of the savings with the contractor. Usually if a contractor submits an idea and itis implemented, the owner will split the savings based on a predetermined formula
such as 50-50 or 40-60 etc. This is VE paradigm.
The concept of continuous improvement of TQM is very important to partnering
process. To ensure whether the performance of the partnering team is continuous
improving mechanism - theJoint Evaluation, must be established for the assessment
and evaluation. Performance standard should be established in accordance with the
goals and objectives of the partnering charter. Since measurable objectives are
established as discussed in previous item (partnering charter portion), an open and
candid evaluation should be executed jointly by all the team members in formats and
patterns setup to fit those goals and objectives are essential.
5. Mid-project Workshop
Any project duration exceeds 12 months should organize mid-project workshop for
every key project participants to attend. The main purpose of mid-project workshop
is to introduce new comers (new employees of the parties, new subcontractors, and
new suppliers) review the performance of the project under partnering with the
established joint evaluation mechanism. Bring up the Pros and Cons, and formulate
-
7/27/2019 Partnering 4 April 2011
15/21
15
resolution to problems encountered. A facilitator is needed either from outside
source or elected within the project. Review and appraise the performance with a
true heart is most important; it would help to enhance past successes and rectify
shortcomings of the project.
6. Close-out Workshop
A close-out partnering workshop to bring the full team together to review and
celebrate the success or to learn the lesson of less success objectives. This can be
done under the guidance of a facilitator or assigned a team leader from the team.
Award should be given to honor the success of the team and also the selected
partnering champion. Awards or plaques present to one or several individuals who
truly exemplified the principles of partnering on the project.
It is advisable that the team members be asked to make one final rating of the teamand its performance against the charter. The evaluation or assessment of the teams
progress should be a part of the close-out workshop. The ultimate result is that the
partnering team moves forward to the next project with a greater resolve for more
significant successes.
6.1 Lessons Learned
Subsequent to a number of studies on partnering, the followings are points
consolidated the experiences of participants who have involved in partneringprojects:
1. Use outside facilitation at your partnering workshops until the owner andindustry are mature in the process.
2. The partnering workshop is the beginning of the process and should not be seenas the whole of partnering.
3. No project over 12 months in duration should go without having a mid-projectworkshop.
4. Take time to develop and apply the issue escalation process.5. Develop and use the team evaluation process with consistency and commitment.6. Use all partnering tools in every project.7. Decide early on whether record keeping will be done and then measure only
those necessary areas.
8. Top management commitment ultimately determines if an organization issuccessful and profitable in the partnering process.
-
7/27/2019 Partnering 4 April 2011
16/21
16
7. Partnering Experiences in Hong Kong
The first two design and construct projects in Hong Kong used partnering approach
were the North District Hospitaland the Tseung Kwan O Hospital (Chan et al,
2002). Initial partnering workshop for the former was conducted after tender butbefore contract award. The workshop for the latter was launched by the contractor
according to the provisions of the construction contract. Application of partnering
was also implemented in the Kowloon-Canton Railway Corporation (KCR) and
Mass Transit Railway Corporation (MTRC) in the West Rail and Tseung Kwan O
Extensions respectively (Bayliss, 2000). Apart from the infrastructure developments,
The Hong Kong Housing Authority (HKHA) and the Hong Kong Housing Society
were also actively nurturing a partner culture in the public and semi-public sector
residential developments (Chan et al, 2001). Since then another hospital projects the
Haven of Hope Hospital usedpartnering. Both projects are reported successful.
Chan et al (2002) tabulated 48 partnering projects of various natures undertaken by
public and private sectors at that time in Hong Kong (Table 3).
-
7/27/2019 Partnering 4 April 2011
17/21
17
The outstanding achievement in the Tseung Kwan O Extension (TKOE) was
recorded. The project used partnering approach and resulted in very significant
saving in cost. Partnering have contributed to the last $ 4 billion of savings that
brought the out-turn cost down to $ 17 billion from the originally budgeted $
Table 3: Partnering Projects in Hong Kong
Source: Chan et al 2002
-
7/27/2019 Partnering 4 April 2011
18/21
18
30.5 billion. The project was completed 16 weeks ahead ofschedule.
In TKOE, MTRC established a Partnering Steering Group interacted with the
contractors consistently. The group arranged a list of partnering activities to handle
the project, these activities included:
Monthly partnering meetings Performance monitoring according to standardizedformats Multi-contract workshops Other opportunities to interact, including shared offices, social events etc.
Developments on the above partnering model, including clearer gain-share
pain-share agreements were later incorporated in the Tsim Sha Tsui station
extension project and the Tung Chung Cable Carproject.
Partnering is mandatory on Housing Authority projects, and it is worth studying
its influence on project outcomes. Some other Government Works Departments
have reportedly had different types of experiences on their initial partnered
projects. Some said that partnering was good, until there was a major problem,
after which relationships were spoiled and parties reverted to adversarial
contractual approaches. Observations on the applicability and potential benefits
from partnering and the possible obstacles in the Hong Kong project revealed
inadequate partnering culture developed among participants. It can be reflected by
the attitudes of inadequate trust and communication which have been rooted
deeply under the experiences of adversarial traditional contracting system.
8. Differences between Partnership, Joint Venture and Partnering
Partnership
Partnership is a relationship in which two or more people, organizations, or countries
work together as partners; they carry on a business in common with a view of profit.
Under partnerships losses will have to be shared as well as profits. Partnership is a
legal binding agreement between parties. It is often long term and dissolution is
complex.
Joint venture
Individuals or companies may enter into a joint venture agreement to workcooperatively on a project or contract. A joint venture shares common elements of a
-
7/27/2019 Partnering 4 April 2011
19/21
19
partnership agreement. With joint ventures there must be joint management and
control, although not necessarily equal. There must be contribution to the enterprise,
some property, money, effort, skill and knowledge. As distinguished from a
partnership, a joint venture commonly has a single purpose.
Partnering
Partnering attempts to create an environment where trust, team work and prevention
of disputes, foster a cooperative bond to everyones benefit to facilitate the
completion of a successful project. The major difference between partnering and
partnership or joint venture is, partnership and joint venture are legal binding
relationship while partnering is non-legal binding and voluntary relationship.
-
7/27/2019 Partnering 4 April 2011
20/21
20
Reference
Abudayyeh, O. (1994), Partnering: a team building approach to quality construction
management, Journal of Management in Engineering, ASCE, 10(6), 1994, pp.26-29
Badger, W.W. and Mulligan, D.E. (1995), Rationale and benefit associated with
international alliances, Journal of Construction Engineering and Management, ASCE,
12(1), pp.100-111
Bayliss, R.F. (2000), Project partnering a case study on MTR Corporation Ltds
Tseung Kwan O Extension, Proceedings of the Millennium Conference on
Construction Project Management Recent Developments and the Way Forward
2000, Hong Kong
Back W.E. and Sanders, S.R. (1996), Partnering in a unit price environment, Project
Management Journal, 27(2), pp. 18-25
Bloom, M.J. (1997), Partnering A better way for doing business, 1997, The MITRE
Corporation, Badford, Massachusetts.
Cowan, C., Gray, C., and Larson, E. (1992), Project partnering, Project ManagementJournal, 22(4), pp. 5-12
Chan, A.P.C., Cheng, E.W.L. and Li, H., (2001), Full Report on Construction
Partnering in Hong Kong, The Hong Kong Housing Society
Chan, A.P.C., Chan, D.W.M., Ho, K.S.K., (2002), Research Monograph: An Analysis
of Project Partnering in Hong Kong, Department of Building and Real Estate, The
Hong Kong Polytechnic University, 2002, ISBN 962-367-363-9
Construction Industry Board (CIB) (1997), Partnering in the team: a report by
Working Group 12 of the Construction Industry Board, Thomas Telford Pub, London,
1997
Construction Industry Institute (CII) (1991), In search of partnering excellence,
Publication no. 17-1, Report CII, Austin, Texas, USA
Drexler, J.A. and Larson, E.W. (2000), Partnering: why project owner-contractor
-
7/27/2019 Partnering 4 April 2011
21/21
21
relationships change. Journal of Construction Engineering and Management, ASCR,
126(4), pp. 239-297
Gardiner, P.D. and Simmons, J.E.L. (1998), Conflict in small and medium sized
project: case of partnering to the rescue, Journal of Management in Engineering,
ASCE, 14(1), pp. 35-40
Larson, E. and Drexler, J.A. (1997), Barriers to project partnering: report from the
firing line, Project Management Journal 28(2), pp.46-52.
Lazar, F.D. (1997), Partnering new benefits from peering inside the black box,
Journal of Management in Engineering, ASCE 13(6), pp. 75-83
Mathews, J. and Rowlinson, S. (1999), Partnering: incorporating safety management,
Engineering, Construction and Architectural management, 6(4), pp. 347-357
Mohn, J. and Spekman, R. (1994), Characteristics of partnering success: partnering
attributes, communication behaviour and conflict resolution techniques, Strategic
Management Journal, 15, 1994, pp. 135-152
Moore, C., Mosley, D. and Slagle, M. (1992), Partnering guidelines for win-winproject management, Project Management Journal 22, pp.18-21
Sander, S.R. and Moore, M.M. (1992), Perceptions on partnering in the public sector,
Project Management Journal, 22(4), 13-19, 1992