particular specification for - tak sun secondary school renovation...

45

Upload: lamthuy

Post on 20-Aug-2019

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of
Page 2: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of
Page 3: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Our ref.: 479-TEN PS1 (Rev.1)

Particular Specification for

Furniture

(Total of 11 pages, not including this page)

Page 4: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

PS1

Page 5: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Copyright © 2014 KOKUYO Furniture Co., Ltd. All rights reserved.

S TA F F W O R K S TAT I O N

L-SHAPE WORKSTATION

Legend

Full Height Fabric Partition (Pin-able, H1100 mm)Side Cabinet with MFC Top

Cable Basket under Table Table Top With Cutout

PS1

Page 6: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Copyright © 2014 KOKUYO Furniture Co., Ltd. All rights reserved.

Table Top - MFC Color Available

Panel Fabric Color Available

W O R K I N G B E N C H

Optional - Hanging Accessory

Hanging Frame

White BoardA4 Box

A4 Tray Name Plate

Tack-able Panel

Partition for Cable Management

L-SHAPE WORKSTATION

Skirting on partition

All the cables can be hidden in the partition

PS1

Page 7: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Copyright © 2014 KOKUYO Furniture Co., Ltd. All rights reserved.

J O B R E F E R E N C E

L-SHAPE WORKSTATION

PS1

Page 8: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Copyright © 2014 KOKUYO Furniture Co., Ltd. All rights reserved.

J O B R E F E R E N C E

L-SHAPE WORKSTATION

PS1

Page 9: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Copyright © 2014 KOKUYO Furniture Co., Ltd. All rights reserved.

S TA F F C H A I R

EN T R Y

Awarded certificate:

3 level adjustable lumbar support Synchronized Mechanism

Legend

PS1

Page 10: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

Copyright © 2014 KOKUYO Furniture Co., Ltd. All rights reserved.

J O B R E F E R E N C E

EN T R Y

PS1

Page 11: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

PS1

Page 12: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

PS1

Page 13: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

PS1

Page 14: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

PS1

Page 15: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

ARCHITECTURAL WORKS

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

1.2.7 Supply and install 100mm (H) ceramic skirting.

a Library: Store Room 2 m

b PE Room m

c VA Room m

d Corridor 2 m

1.2.8 Supply and install 100mm (H) H.W skirting.

a Classroom 401, 402, 403, 404, 405, 501, 502, 503,

504, 505

m

1.2.9 Supply and lay 1800mm height liquid waterproof

membrane including cement and screeding to wall and

including water test and relevant report.

a Library: Store Room 2 m²

b VA Room m²

1.2.10 Supply and lay proprietary brand waterproof

membrane complete with waterproofing cement and

sand plastering from floor level (up to 300mm high) to

receive wall finishes and including water test &

relevant report.

a Library: Store Room 2 m²

b VA Room m²

Carried Forward

Our ref.: 479 - SoR SR - 3 - 2 of 3 (Rev. 1)

Page 16: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

CARPENTRY & JOINERY

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

r (Furniture mark C17a) - Full Height Cabinet

Approx. Size:

380 x 840 x 3000mm (H)

- Library: Office cum Reception

nr.

s (Furniture mark C17b) - Full Height Cabinet

Approx. Size:

840 x 380 x 3000mm (H)

- Library: Office cum Reception

nr.

t (Furniture mark C18) - Low Height Cabinet

Approx. Size:

4590 x 1425 x 1050mm (H)

With LED Strip Light

- Library: Office cum Reception

nr.

u (Furniture mark C19) - Low Height Cabinet

Approx. Size:

1200 x 600 x 700mm (H)

- Library: Office cum Reception

nr.

v (Furniture mark C20) - Low Height Cabinet

Approx. Size:

2130 x 380 x 1200mm (H)

With plastic laminated finishes for internal finishes

- Library: Office cum Reception

nr.

Carried Forward

Our ref.: 479 - SoR SR - 4 - 7 of 12 (Rev.1)

Page 17: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

CARPENTRY & JOINERY

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

w (Furniture mark C21) - Low Height Cabinet

Approx. Size:

4590 x 500 x 2400mm (H)

- Library: Office cum Reception

nr.

x (Furniture mark C22) - Full Height Cabinet

Approx. Size:

3775 x 350 x 2550mm (H)

With plastic laminated finishes for internal finishes

- Library: Reading Area

nr.

y (Furniture mark C23) - Low Height Cabinet

Approx. Size:

3000 x 300 x 1200mm (H)

With plastic laminated finishes for internal finishes

- Library: Reading Area

nr.

z (Furniture mark C24) - Low Height Cabinet

Approx. Size:

1000 x 750 x 1100mm (H)

- Library: Reading Area

nr.

aa (Furniture mark C25) - Full Height Cabinet

Approx. Size:

2000 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Reading Area

nr.

ab (Furniture mark C26) - Low Height Cabinet

Approx. Size:

2075 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Reading Area

nr.

Carried Forward

Our ref.: 479 - SoR SR - 4 - 8 of 12 (Rev.1)

Page 18: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

CARPENTRY & JOINERY

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

ac (Furniture mark C27) - Low Height Cabinet

Approx. Size:

3000 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Reading Area, Teacher Resources Centre

nr.

ad (Furniture mark C28) - Low Height Cabinet

Approx. Size:

1800 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Teacher Resources Centre

nr.

ae (Furniture mark C29) - Low Height Cabinet

Approx. Size:

2250 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Teacher Resources Centre

nr.

af (Furniture mark C30) - Full Height Cabinet

Approx. Size:

1212 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Teacher Resources Centre

nr.

ag (Furniture mark C31) - Full Height Cabinet

Approx. Size:

2275 x 300 x 2550mm (H)

With plastic laminated finishes for internal finishes

- Library: Teacher Resources Centre

nr.

ah (Furniture mark C32) - Full Height Cabinet

Approx. Size:

1550 x 300 x 2550mm (H)

With plastic laminated finishes for internal finishes

- Library: Teacher Resources Centre

nr.

Carried Forward

Our ref.: 479 - SoR SR - 4 - 9 of 12 (Rev.1)

Page 19: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

CARPENTRY & JOINERY

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

ai (Furniture mark C33) - Full Height Cabinet

Approx. Size:

1550 x 400 x 2400mm (H)

- Library: Store Room 2

nr.

aj (Furniture mark C34) - Open Shelf

Approx. Size:

1200 x 450 x 2400mm (H)

- Library: Teacher Resources Centre

nr.

ak (Furniture mark C35) - Open Shelf

Approx. Size:

1550 x 600 x 2400mm (H)

- Library: Store Room 2

nr.

al (Furniture mark C36) - Low Height Cabinet + Hanging

Cabinet

Approx. Size:

1100 x 400 x 800mm (H) +

1100 x 600 x 850mm (H)

With LED Strip Light

- Library: Store Room 2

nr.

am (Furniture mark C37) - Low Height Cabinet

Approx. Size:

1850 x 350 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Tutorial Room 2

nr.

Carried Forward

Our ref.: 479 - SoR SR - 4 - 10 of 12 (Rev.1)

Page 20: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

CARPENTRY & JOINERY

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

an (Furniture mark C38) - Open Shelf

Approx. Size:

2900 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Tutorial Room 1

nr.

ao (Furniture mark C39) - Open Shelf

Approx. Size:

2600 x 300 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Common Area

nr.

ap (Furniture mark C40) - Low Height Cabinet

Approx. Size:

2760 x 500 x 1100mm (H)

With plastic laminated finishes for internal finishes

- Library: Common Area

nr.

aq (Furniture mark C41) - Low Height Cabinet

Approx. Size:

1765 x 500 x 1100mm (H)

- Library: Common Area

nr.

ar (Furniture mark C42) - Low Height Cabinet

Approx. Size:

7000 x 500 x 1100mm (H)

- Library: Study Area

nr.

as (Furniture mark C43) - Full Height Cabinet

Approx. Size:

930 x 250 x 2550mm (H)

With plastic laminated finishes for internal finishes

- Library: Study Area

nr.

at (Furniture mark C44) - Full Height Cabinet

Approx. Size:

2850 x 300 x 2550mm (H)

With plastic laminated finishes for internal finishes

- Library: Study Area

nr.

Carried Forward

Our ref.: 479 - SoR SR - 4 - 11 of 12 (Rev.1)

Page 21: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

METAL WORKS

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

1.4.8 Supply and install HILTI HAS-M6 anchor bolt nr.

1.4.9 Provide sampling strength test on M6 and M8 HAS

HILTI anchor bolt by recognized independent

laboratory for tensile load by Pull-out test.

Sum

1.4.10 Provide reports of non-destructive for welded joints to

verify the integrity and adequacy of the welds by

radiography or ultrasonic examination for butt welding

and magnetic inspection or dyr penetrant testing for

fillet welding.

Sum

1.4.11 Provide Registered Structural Engineer (RSE) safety

certificate of steel framing structural works after

completion of work.

Sum

To Summary of Tender - Item 1.4

Our ref.: 479 - SoR SR - 5 - 3 of 3 (Rev.1)

Page 22: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

ELECTRICAL WORKS

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

ELV

1.8.4 Supply and install cable containment provisions

including G.I. conduits, metal trunking; adaptable

boxes and fittings and/or flexible conduits and

fittings or any cable installing facilities; earth

continuity conductors.

a Single Data point to be connected to the Server

Room c/w CAT.6 cable wiring w/ modular jacks

& plug

nr.

b Twin Data point outlet to be connected to the

Server Room c/w CAT.6 cable wiring w/ modular

jacks & plug

nr.

c 120" 4:3 electric type projector screen fuse spur

unit.

(Brand: DA-LITE)

nr.

d 100" 4:3 manual type projector screen fuse spur

unit.

(Brand: DA-LITE)

nr.

e Relocated existing projector at 3/F PE Room nr.

f Projector (Brand: Panasonic PT-LB332) at VA

Room

nr.

g Projector (Brand: Panasonic PT-EX510) at VA

Library

nr.

h Connection outlet w/ AV signal VGA, HDMI &

S.S. cover panel

nr.

i Door release button nr.

j Break glass type door release button nr.

k False ceiling conseal type electric projector lift w/

plenum & closure.

nr.

l Twin Computer data outlet to be connceted to the

projector c/w CAT.6 cable wiring w/ modular jack

& plug.

nr.

Carried Forward

Our ref.: 452 - SoR SR - 9 - 2 of 5 (Rev.1)

Page 23: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

ELECTRICAL WORKS

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

1.8.5 Supply and install wall MK trunking

a PE Room m

b VA Room m

1.8.6 Supply and install metal trunking for low voltage

work and all necessary fixing accessories and

ironmongeries.

sum

PUBLIC ADDRESS AND AUDIO SYSTEM

1.8.7 Supply and install public address and audio

system, including all necessary equipment and all

fittings, approved wiring and G.I. conduits,

trunkings c/w painting match w/ wall/ceiling,

fixings and fittings

a PA Speaker

(Brand: TOA PC-2369 (TBC) (White))

18 nr.

b TOA F-2852C (White) 8 nr.

c Crown Audio 402 3 nr.

d TOA F-1300W (White) 2 nr.

e Behringer X32 Rack 1 nr.

f SoundCraft Ui12 1 nr.

g Shure PGX SM58 HH Set 2 nr.

h Metal equipment rack

(Approx. Size 600mm x 600mm x 600mm)

1 nr.

i Radial JPC Stereo DI Box 1 nr.

Carried Forward

Our ref.: 452 - SoR SR - 9 - 3 of 5 (Rev.1)

Page 24: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

RENOVATION 2016

IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOL

FOR TAK SUN SECONDARY SCHOOL

AT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

SCHEDULE OF RATES

HVAC WORKS

Item Description Qty Unit Unit Rate Amount

(HK$) (HK$)

Brought Forward

1.9.3 INDOOR UNIT

a (C1) - Ceiling Mounted Cassette type:

Cooling Capacity 2.80kW

Heating Capacity 3.20kW

nr.

b (C1.5) - Ceiling Mounted Cassette type:

Cooling Capacity 4.50kW

Heating Capacity 5.00kW

nr.

c (C2) - Ceiling Mounted Cassette type:

Cooling Capacity 5.60kW

Heating Capacity 6.30kW

nr.

d (C2.5) - Ceiling Mounted Cassette type:

Cooling Capacity 7.10kW

Heating Capacity 8.00kW

nr.

1.9.4 VRV OUTDOOR UNIT

a 14HP + 22HP (36HP) (outdoor unit)

101.5kW + 114.0kW

nr.

AC SYSTEM (FOR 3/F ROOM 311)

1.9.5 Supply and install ceiling mount cassette type A/C unit

which comprising 1 nr. indoor unit and 1 nr. outdoor

unit c/w insulated refrigerant pipes, full-size S.S. drain

pan, insulated drain pipe lead to nearest drain point,

GMS support frame, emergency stop switch , weather

proof isolator, anti-vibration isolator, isolating switch

and associate electrical work for the condenser

including G.I. conduit wiring and ancillary control

equipment. (Refrigerant used should be R410A).

a (C2) - Ceiling Mounted Cassette type:

Cooling Capacity 5.60kW

Heating Capacity 6.30kW

-With wired remote control fixed on wall side

nr.

Carried Forward

Our ref.: 452 - SoR SR - 10 - 2 of 3 (Rev.1)

Page 25: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

DRAWING SCHEDULE

SHEET NO: DRAWING TITLE:PAPER SIZE: PAGE SHEET NO: DRAWING TITLE:PAPER SIZE: PAGEREV. REV.

TSSS-AA01 DRAWING SCHEDULE 01A-3 A1

10

TSSS-AA02 DRAWING SCHEDULE 02 B

11

TSSS-GN01 GENERAL NOTES

C

TSSS-EX01 LOCATION PLAN AND EXISTING 1/F LAYOUT PLAN

02

13

14

15

16

17

18

19

20

03

04

05

06

21

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

1

1

0

0

0

1

0

0

0

0

3

0

0

0

4

0

0

1

1

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

A-3

TSSS-DWF01

07

A-3 0

08

A-3 1

TSSS-LP01 PROPOSED WORKS OF 1/F LAYOUT PLAN

09

A-3 0 22

0A-3

23

24

250A-3

1 04-07-2016

Karen

Karen

K L

K L

17-06-2016

A

N.T.S. (A3)

TSSS-AA01

DRAWING SCHEDULE 01

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-Cover & AA

德信中學

TAK SUN SECONDARY SCHOOL

TSSS-EX02 EXISTING 2/F LAYOUT PLAN

TSSS-EX03 EXISTING 3/F LAYOUT PLAN

TSSS-EX04 EXISTING 4/F LAYOUT PLAN

TSSS-EX05 EXISTING 5/F LAYOUT PLAN

TSSS-EX06 EXISTING 7/F LAYOUT PLAN

TSSS-LP02 PROPOSED WORKS OF 2/F LAYOUT PLAN

TSSS-LP03 PROPOSED WORKS OF 3/F LAYOUT PLAN

TSSS-LP04

PROPOSED WORKS OF ROOM 311 LAYOUT PLAN (3/F PART PLAN)

TSSS-LP05

PROPOSED WORKS OF 5/F LAYOUT PLANTSSS-LP06

PROPOSED WORKS OF 7/F LAYOUT PLANTSSS-LP07

TSSS-LP08

PROPOSED WORKS OF LIBRARY LAYOUT PLAN (7/F PART PLAN)

TSSS-DWF02

ROOM 311 DOOR WINDOW & FURNITURE MARK PLAN (3/F PART PLAN)

LIBRARY DOOR WINDOW & FURNITURE MARK PLAN (7/F PART PLAN)

TSSS-AA03 DRAWING SCHEDULE 03

12

01

TSSS-LP10 PROPOSED WORKS - ELEVATION 1

TSSS-LP11 PROPOSED WORKS - ELEVATION 2

PROPOSED WORKS OF 4/F LAYOUT PLAN

TSSS-LP12

TSSS-FP01

PROPOSED WORKS - ELEVATION 3

TSSS-FP02

PROPOSED LIBRARY FLOOR PATTERN PLAN (7/F PART PLAN)

PROPOSED ROOM 311 FLOOR PATTERN PLAN (3/F PART PLAN)

TSSS-LP13 PROPOSED WORKS - ELEVATION 4

TSSS-LP09

PROPOSED WORKS OF MAIN ROOF PART PLAN PROPOSED WORKS

OF ROOF AND UPPER ROOF PART PLAN

TSSS-EX07 EXISTING ROOF PLAN

FOR TENDER

1

1

1

Page 26: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

2

2

0

A-3

A-3

A-3

DRAWING SCHEDULE

SHEET NO: DRAWING TITLE:PAPER SIZE: PAGE SHEET NO: DRAWING TITLE:PAPER SIZE: PAGEREV. REV.

1 04-07-2016

Karen

Karen

K L

K L

17-06-2016

B

N.T.S. (A3)

TSSS-AA02

DRAWING SCHEDULE 02

30

31

32

27

28

29

TSSS-DS01 DOOR SCHEDULE 01

TSSS-DS02 DOOR SCHEDULE 02

TSSS-WS01 WINDOW SCHEDULE 01

33

A-3

A-3

A-3

A-3

A-3

A-3

A-3

0

1

1

0

0

0

0

34

A-3

0

35

42

A-3

A-3

0

0

37

38

40

A-3

0

39

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-Cover & AA

德信中學

TAK SUN SECONDARY SCHOOL

TSSS-CS01

CLASSROOM 106,206,306,406,506 - CABINET (TYPE C1) DETAIL

36A-3

0

A-3

0

0

A-3

44

45

46

43

47

A-3

A-3

A-3

A-3

A-3

A-3

0

0

0

48

49A-3

A-3 51

52

A-3

0

53

50A-3

TSSS-CS06

TSSS-CS07

TSSS-CS08

TSSS-CS09

TSSS-CS10

TSSS-CS11

TSSS-CS13

TSSS-CS14

TSSS-CS15

TSSS-CS16

TSSS-CS17

TSSS-CS02

CLASSROOM 106,206,306,406,506 - CABINET (TYPE C2) DETAIL

TSSS-CS03

CLASSROOM 401-405,501-505 - CABINET (TYPE C3) DETAIL

TSSS-CS04

CLASSROOM 401-405,501-505 - CABINET (TYPE C4) DETAIL

TSSS-CS05

PE ROOM & VA ROOM - CABINET (TYPE C5, C6) DETAIL

TSSS-CS18

VA ROOM - CABINET (TYPE C8, C9) DETAIL

VA ROOM - CABINET (TYPE C10, C11) DETAIL

VA ROOM - CABINET (TYPE C12) DETAIL

VA ROOM - CABINET (TYPE C13) DETAIL

& STORE ROOM 1 - CABINET (TYPE C14) DETAIL

CORRIDOR 1 - CABINET (TYPE C15) DETAIL

& ENTRANCE - CABINET (TYPE C16) DETAIL

OFFICE CUM RECEPTION - CABINET (TYPE C18) DETAIL

OFFICE CUM RECEPTION - CABINET (TYPE C19, C20) DETAIL

OFFICE CUM RECEPTION - CABINET (TYPE C21) DETAIL

READING AREA - CABINET (TYPE C22, C23) DETAIL

READING AREA - CABINET (TYPE C24, C25) DETAIL

READING AREA - CABINET (TYPE C26) DETAIL & READING AREA &

TEACHER RESOURCES CENTRE - CABINET (TYPE C27) DETAIL

TEACHER RESOURCES CENTRE - CABINET (TYPE C28 ,C29) DETAIL

TEACHER RESOURCES CENTRE - CABINET (TYPE C30 ,C31) DETAILPE ROOM - CABINET (TYPE C7a, C7b) DETAIL

26

41

TSSS-CS19

TEACHER RESOURCES CENTRE - CABINET (TYPE C32) DETAIL

& STORE ROOM 2 - CABINET (TYPE C33) DETAIL

TSSS-CS20

TSSS-CS21

TSSS-CS12

OFFICE CUM RECEPTION - CABINET (TYPE C17a & 17b) DETAIL

TSSS-CP02

TSSS-CP01

PROPOSED ROOM 311 REFLECTED CEILING LAYOUT PLAN

(3/F PART PLAN)

PROPOSED LIBRARY REFLECTED CEILING LAYOUT PLAN

(7/F PART PLAN)

A-3TSSS-SE01

PROPOSED FALSE CEILING SUPPORTED STRUCTURAL FRAMING PLAN

(7/F PART PLAN) 1 OF 2

TSSS-SE02

PROPOSED FALSE CEILING SUPPORTED STRUCTURAL FRAMING PLAN

(7/F PART PLAN) 2 OF 2

FOR TENDER

1

1

1

1

1

1

1

Page 27: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

0

1A-3

A-3

A-3

DRAWING SCHEDULE

SHEET NO: DRAWING TITLE:PAPER SIZE: PAGE SHEET NO: DRAWING TITLE:PAPER SIZE: PAGEREV. REV.

1 04-07-2016

Karen

Karen

K L

K L

17-06-2016

C

N.T.S. (A3)

TSSS-AA03

DRAWING SCHEDULE 03

58

59

60

55

56

57

61

A-3

A-3

A-3

A-3

A-3

A-3

A-3

1

0

0

0

1

TSSS-DL01

62

A-3

2

63

70

A-3

A-3

0

0 65

66

69

A-3

67

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-Cover & AA

德信中學

TAK SUN SECONDARY SCHOOL

64A-3 0

A-3

1

A-3

72

73

71

A-3

A-3

1

0

A-3

0

TSSS-DL02

TSSS-FS01

PROPOSED LIBRARY REFLECTED ELV LAYOUT PLAN

TSSS-FS02

TSSS-PL01

PROPOSED LIBRARY REFLECTED LIGHTING LAYOUT PLAN

TSSS-PL02

PROPOSED ROOM 311 MVAC LAYOUT PLAN

(3/F PART PLAN) & (4/F PART PLAN)

A-3

A-3

A-3

A-3

TSSS-EE01

A-3

A-3

A-3

A-3

STUDY AREA - CABINET (TYPE C43, C44) DETAIL

TSSS-EL02

INTERIOR FINISHES SCHEDULE 01

TSSS-MVAC01

TSSS-MVAC02

PROPOSED LIBRARY REFLECTED POWER LAYOUT PLAN

PROPOSED ROOM 311 REFLECTED ELV LAYOUT PLAN

PROPOSED LIBRARY MVAC LAYOUT PLAN (7/F PART PLAN)

PROPOSED LIBRARY MVAC LAYOUT PLAN (ROOF PART PLAN)

PROPOSED ROOM 311 REFLECTED FIRE SERVICES LAYOUT PLAN

PROPOSED LIBRARY REFLECTED FIRE SERVICES LAYOUT PLAN

PROPOSED ROOM 311 REFLECTED PLUMBING LAYOUT PLAN &

SCHEMATIC LINE DIAGRAM FOR PLUMBING

PROPOSED LIBRARY REFLECTED PLUMBING LAYOUT PLAN &

SCHEMATIC LINE DIAGRAM FOR PLUMBING

54 68

TSSS-CS27

TSSS-IF01

EXISTING MAIN SCHEMATIC WIRING DIAGRAM

PROPOSED ROOM 311 REFLECTED POWER LAYOUT PLAN

PROPOSED BUILDING SERVICE NOTES

STUDY AREA - CABINET (TYPE C42) DETAIL

TSSS-CS26

TUTORIAL ROOM 1 - CABINET (TYPE C38) DETAIL

& COMMON AREA - CABINET (TYPE C39) DETAIL

COMMON AREA - CABINET (TYPE C40, C41) DETAIL

TSSS-CS24

TSSS-CS25

TSSS-EE02

TSSS-EE03

TSSS-EE04

TSSS-MVAC03

A-3

STORE ROOM 2 - CABINET (TYPE C36) DETAIL

& TUTORIAL ROOM 2 - CABINET (TYPE C37) DETAIL

TSSS-CS23

TSSS-EE05

TSSS-EE06

740

A-3

PROPOSED ROOM 311 REFLECTED DRAINAGE LAYOUT PLAN &

SCHEMATIC LINE DIAGRAM FOR DRAINAGE

750

A-3

PROPOSED LIBRARY REFLECTED DRAINAGE LAYOUT PLAN &

SCHEMATIC LINE DIAGRAM FOR DRAINAGE

760

A-3 770

STORE ROOM 2 - CABINET (TYPE C34 ,C35) DETAIL

TSSS-CS22

A-3 780

2PROPOSED 3/F LIGHTING LAYOUT PLANTSSS-EL01

TSSS-EE07

0EXISTING MCB BOARD PHOTO

FOR TENDER

1

1

0

Page 28: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

22550

3000

FALSE

CEILING

F.F.L

ACOUSTIC CEILING TILE

READING AREA STORE ROOM 2TEACHERS

RESOURCES CENTRE

OFFICE CUMRECEPTION STUDY AREACOMMON AREA

400 400

2550

1100

1000

8600 86004550

LIBRARY

LED STRIP FITTING

EXISTING BEAM

EXISTING BEAM

ACOUSTIC CEILING TILE

2400

NEW 3000mm(H) TIMBER WALL DADO

C/W PLASTIC LAMINATED FIN.

12mm THICK GYPSUM BOARD

WALL FINISHES

12mm THICK GYPSUM

BOARD WALL FINISHES

EXISTING WINDOW

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-LP02

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

1 04-07-2016

Alan

Alan

K L

K L

17-06-2016

20

1:75(A3)

TSSS-LP010

PROPOSED WORKS - ELEVATION 1

PROPOSED WORKS - ELEVATION 1

Page 29: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

3775

168414338600

3000

FALSE

CEILING

F.F.L

ACOUSTIC CEILING TILE

TUTORIAL ROOM 1 ENTRANCETUTORIAL ROOM 2 COMMON AREA READING AREA

400 40014338600

3775

22550

LIBRARY

EXISTING BEAM

EXISTING BEAM

ACOUSTIC CEILING TILENEW 3000mm(H) TIMBER WALL

DADO C/W PLASTIC

LAMINATED FIN.

NEW 3000mm(H) TIMBER WALL DADO

C/W PLASTIC LAMINATED FIN.

12mm THICK GYPSUM

BOARD WALL FINISHES

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-LP02

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

1 04-07-2016

Alan

Alan

K L

K L

17-06-2016

21

1:75(A3)

TSSS-LP11

PROPOSED WORKS - ELEVATION 2

PROPOSED WORKS - ELEVATION 2

Page 30: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

272545255007250

3000

FALSE

CEILING

F.F.L

TUTORIAL ROOM 1STUDY AREA COMMON AREA

2550

750

EXISTING WINDOW

100

15100

LIBRARY

EXISTING BEAM

APPLY 2 COATS OF ANTİ-MOULD ACRYLİC EMULSİON

PAİNT OVER A COAT OF PRİMER FOR WALL.

NEW 3000mm(H) TIMBER WALL DADO

C/W PLASTIC LAMINATED FIN.

NEW 1100mm (H) TIMBER WALL DADO C/W PLASTIC

LAMINATED FIN. AND 25mm (H) TIMBER MOULDING ON TOP;

UPPER: 1100mm (H) x 10mm (THK.) CLEAR TEMPERED GLASS

W/ BACK PAINTED FINISHES

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-LP02

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

1 04-07-2016

Alan

Alan

K L

K L

17-06-2016

22

1:50(A3)

TSSS-LP12

PROPOSED WORKS - ELEVATION 3

PROPOSED WORKS - ELEVATION 3

Page 31: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

69505007000

15100

3000

FALSE

CEILING

F.F.L

300

TEACHERS

RESOURCES CENTRE

READING AREA

350

LIBRARY

EXISTING WINDOW

EXISTING BEAM

APPLY 2 COATS OF ANTİ-MOULD ACRYLİC EMULSİON

PAİNT OVER A COAT OF PRİMER FOR WALL.

NEW 3000mm(H) TIMBER WALL DADO

C/W PLASTIC LAMINATED FIN.

NEW 1100mm (H) TIMBER WALL DADO C/W

PLASTIC LAMINATED FIN. AND 25mm (H)

TIMBER MOULDING ON TOP

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-LP02

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

1 04-07-2016

Alan

Alan

K L

K L

17-06-2016

23

1:50(A3)

TSSS-LP013

PROPOSED WORKS - ELEVATION 4

PROPOSED WORKS - ELEVATION 4

Page 32: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

60

0

1200

C19

1

PLAN

C19

2

ELEVATION 01

C19

3

SECTION A-A

DETAIL 01

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

70

0

600

520

70

0

CABINET LOCK W/ KEY ALIKE FEATURE

ALUMINUM CONCEAL HANDLE

20mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD SLIDING DOOR W/

PLASTIC LAMINATED FINISHES

A

A

REFERENCE IMAGE 02

F.F.L F.F.L

1200

1160

LOCKABLE HEAVY DUTY

BEARING WHEEL

(金屬承重滾輪 )

LOCKABLE HEAVY DUTY BEARING WHEEL

(金屬承重滾輪 )

38

0

1000

2130

01

-

PLAN

1

C20

ELEVATION 01

2

C20

F.F.L

A

A

10

03

50

30

50

32

03

20

30

12

00

SECTION A-A

3

C20

F.F.L

10

03

50

30

35

0

12

00

1000 3050 50

2130

1000

10003050 50

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

50

32

0

6mm THK. CLEAR ACRYLIC BOX

6mm THK. CLEAR ACRYLIC BOX

1

3

5

°

300

BOOK

50mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

46

1:40 (A3)

TSSS-CS14

OFFICE CUM RECEPTION - CABINET (TYPE C19, C20) DETAIL

C19

OFFICE CUM RECEPTION

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C20

OFFICE CUM RECEPTION

Page 33: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

35

0

89650 5030

10

03

50

30

50

31

23

0

25

50

SECTION A-A

3

C22

31

23

03

12

30

31

23

03

12

30

31

2

F.F.L

350

10

00

03

50

30

31

23

03

12

30

31

23

03

12

30

31

25

0

25

50

30

31

2

3775

A

A

01

-

PLAN

1

C22

ELEVATION 01

2

C22

F.F.L

896 30 896 30 896

89650 5030

3775

896 30 896 30 896

BOOK

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

10

03

50

30

50

32

03

20

30

12

00

10

03

50

30

50

32

03

20

30

12

00

30

0

01

-

PLAN

1

C23

ELEVATION 01

2

C23

F.F.L

A

A

SECTION A-A

3

C23

F.F.L

947 94794730 3050 50

3000

947 94794730 3050 50

3000

300

REFERENCE IMAGE

ADJUSTABLE BOOK HOLDER

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

ADJUSTABLE BOOK HOLDER

( REFER TO REFERENCE IMAGE )

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

48

1:40 (A3)

TSSS-CS16

READING AREA - CABINET (TYPE C22, C23) DETAIL

C22

READING AREA

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C23

READING AREA

Page 34: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

A

A

11

00

10

03

30

70

1000

28

07

04

00

75

0

1000

01

-

PLAN

1

C24

ELEVATION 01

2

C24

F.F.L

SECTION A-A

3

C24

F.F.L

10

04

00

10

0

11

00

10

03

30

70

10

04

00

10

0

100 350 300

750

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

CUSHION MOUNTED WITH

ARTIFICIAL LEATHER FINISHED

STORAGE

STORAGE

STORAGE

CUSHION MOUNTED WITH

ARTIFICIAL LEATHER FINISHED

10

03

50

30

50

27

02

70

30

11

00

SECTION A-A

3

C25

F.F.L

30

0

935 3050

2000

50

10

03

50

30

27

02

70

30

11

00

01

-

PLAN

1

C25

ELEVATION 01

2

C25

F.F.L

A

A

50

2000

935

50935 93530300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

49

1:40 (A3)

TSSS-CS17

READING AREA - CABINET (TYPE C24, C25) DETAIL

C24

READING AREA

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C25

READING AREA

Page 35: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

10

03

50

30

50

27

02

70

30

11

00

SECTION A-A

3

C26

F.F.L

30

0

972 3050

2075

50

10

03

50

30

27

02

70

30

11

00

01

-

PLAN

1

C26

ELEVATION 01

2

C26

F.F.L

A

A

50

2075

972

50972 97230300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

10

03

50

30

50

27

02

70

30

11

00

10

03

50

30

50

27

02

70

30

11

00

30

0

01

-

PLAN

1

C27

ELEVATION 01

2

C27

F.F.L

A

A

SECTION A-A

3

C27

F.F.L

703 3050 50

3000

703 3050 50

3000

703 30 703 30 703

30 30703 703 703 300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

6mm THK.CLEAR TEMPERED

GLASS SLIDING DOOR

CABINET LOCK W/

KEY ALIKE FEATURE

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

6mm THK.CLEAR TEMPERED

GLASS SLIDING DOOR

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

50

1:40 (A3)

TSSS-CS18

READING AREA - CABINET (TYPE C26) DETAIL& READING AREA & TEACHER RESOURCES CENTRE

- CABINET (TYPE C27) DETAIL

C26

READING AREA

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C27

READING AREA &

TEACHER RESOURCES CENTRE

Page 36: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

10

03

50

30

50

27

02

70

30

11

00

SECTION A-A

3

C28

F.F.L

30

0

835 3050

1800

50

10

03

50

30

27

02

70

30

11

00

01

-

PLAN

1

C28

ELEVATION 01

2

C28

F.F.L

A

A

50

1800

835

50835 83530300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30

0

697 30

50

2250

10

03

50

30

27

02

70

30

11

00

01

-

PLAN

1

C29

ELEVATION 01

2

C29

F.F.L

A

A

10

03

50

30

50

27

02

70

30

11

00

SECTION A-A

3

C29

F.F.L

50697 30 697

697 30

2250

50697 30 697 300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

51

1:40 (A3)

TSSS-CS19

TEACHER RESOURCES CENTRE- CABINET (TYPE C28 ,C29) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C29

TEACHER RESOURCES CENTRE

C28

TEACHER RESOURCES CENTRE

Page 37: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

10

03

50

30

50

27

02

70

30

11

00

SECTION A-A

3

C30

F.F.L

30

0

111250

1212

50

10

03

50

30

27

02

70

30

11

00

01

-

PLAN

1

C30

ELEVATION 01

2

C30

F.F.L

A

A

50

1212

501112 300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

BOOK

30

0

70550 5030

SECTION A-A

3

C31

10

00

03

50

30

31

23

03

12

30

31

23

03

12

30

31

25

0

25

50

30

31

2

2275

70550 5030

2275

A

A

01

-

PLAN

1

C32

ELEVATION 01

2

C32

F.F.L

705 30 705

705 30 705

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

10

03

50

30

50

31

23

0

25

50

31

23

03

12

30

31

23

03

12

30

31

2

F.F.L

300

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

52

1:40 (A3)

TSSS-CS20

TEACHER RESOURCES CENTRE- CABINET (TYPE C30 ,C31) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C31

TEACHER RESOURCES CENTRE

C30

TEACHER RESOURCES CENTRE

Page 38: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

30

0

71050 5030

SECTION A-A

3

C32

10

00

03

50

30

31

23

03

12

30

31

23

03

12

30

31

25

0

25

50

30

31

2

1550

71050 5030

1550

A

A

01

-

PLAN

1

C32

ELEVATION 01

2

C32

F.F.L

710

710

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

10

03

50

30

50

31

23

0

25

50

31

23

03

12

30

31

23

03

12

30

31

2

F.F.L

300

BOOK

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

50mm THK. GMS FRAMING OPEN SHELVES

C/W 20 THK. PLYWOOD SHELVING IN PLASTIC LAMINATE

FIN.

50mm THK. GMS FRAMING OPEN SHELVES ADJUSTABLE

C/W 20 THK. PLYWOOD SHELVING IN PLASTIC LAMINATE FIN.

40

0

50 1450

501550

01

-

PLAN

1

C33

ELEVATION 01

2

C33

F.F.L

41

47

04

14

70

41

47

04

14

70

41

45

0

24

00

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

53

1:40 (A3)

TSSS-CS21

TEACHER RESOURCES CENTRE - CABINET (TYPE C32) DETAIL& STORE ROOM 2 - CABINET (TYPE C33) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C33

STORE ROOM 2

C32

TEACHER RESOURCES CENTRE

Page 39: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

50

70

01

00

85

0

HEAVY DUTY HINGES

(2 NOS PER DOOR)

MAGNETIC CATCH OPEN

600

FINGER GROOVE

(REFER TO DETAIL 01)

CONCRETE PLINTH

F.F.L

DETAIL 01

FINGER GROOVE

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

FINGER GROOVE (REFER TO DETAIL 01)

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

20mm THK. PLYWOOD ADJUSTABLE SHELVES

W/ PLASTIC LAMINATE FINISHES

SOLID SURFACING MATERIAL COUNTERTOP

CABINET LOCK W/ KEY ALIKE FEATURE

A

A

60

0

1100

01

-

PLAN

1

C36

ELEVATION 01

2

C36

F.F.L

SECTION A-A

3

C36

1100

80

0

34

53

45

50

75

0

24

00

50

70

01

00

85

08

00

34

53

45

50

75

0

24

00

FINGER GROOVE AND INDIRECT LIGHT W/

LED STRIP FITTING (REFER TO DETAIL 01)

20mm THK. PLYWOOD ADJUSTABLE SHELVES

W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

FINGER GROOVE AND INDIRECT LIGHT W/

LED STRIP FITTING (REFER TO DETAIL 01)

20mm THK. PLYWOOD ADJUSTABLE SHELVES

W/ PLASTIC LAMINATE FINISHES

40

0

400

10

03

50

30

50

27

02

70

30

11

00

10

03

50

30

50

27

02

70

30

11

00

35

0

01

-

PLAN

1

C37

ELEVATION 01

2

C37

F.F.L

A

A

SECTION A-A

3

C37

F.F.L

860 3050 50

1850

860 3050 50

1850

860

860 350

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

55

1:40 (A3)

TSSS-CS23

STORE ROOM 2 - CABINET (TYPE C36) DETAIL& TUTORIAL ROOM 2 - CABINET (TYPE C37) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C37

TUTORIAL ROOM 2

C36

STORE ROOM 2

Page 40: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

10

03

50

30

50

27

02

70

30

11

00

10

03

50

30

50

27

02

70

30

11

00

30

0

01

-

PLAN

1

C38

ELEVATION 01

2

C38

F.F.L

A

A

SECTION A-A

3

C38

F.F.L

913 3050 50

2900

50 50

2900

913 30 913

913 30 913 30 913 300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

10

03

50

30

50

27

02

70

30

11

00

10

03

50

30

50

27

02

70

30

11

00

30

0

01

-

PLAN

1

C39

ELEVATION 01

2

C39

F.F.L

A

A

SECTION A-A

3

C39

F.F.L

813 3050 50

2600

50

2600

813 30 813

813 30 813 30 813 50 300

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

56

1:40 (A3)

TSSS-CS24

TUTORIAL ROOM 1 - CABINET (TYPE C38) DETAIL& COMMON AREA - CABINET (TYPE C39) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C39

COMMON AREA

C38

TUTORIAL ROOM 1

Page 41: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

2760

50

0

11

00

PLAN

1

C40

C40

SECTION A-A

32

ELEVATION 01

C40

20mm THK. PLYWOOD W/ PLASTIC LAMINATE FINISHES

50 867 5030

2760

50

29

03

02

90

30

31

01

00

F.F.L

A

A

50 867 30 50

01

-

F.F.L

10

03

10

30

05

0

11

00

30

0

30mm THK. PLYWOOD W/ PLASTIC LAMINATE FINISHES

500

DRAWER

DRAWER

DRAWER

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

867 30 867

MAGAZINE TRAY W/ DRAWER

DRAWERDRAWER DRAWER

867 30 867

20mm THK. PLYWOOD W/

PLASTIC LAMINATE FINISHES

01

-

PLAN

1

C41

ELEVATION 01

2

C41

50

0

F.F.L

75

0

1765

853

35

0

11

00

853

1765

853 853

SECTION A-A

3

C41

F.F.L

75

03

50

11

00

A

A

20mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

57

1:40 (A3)

TSSS-CS25

COMMON AREA - CABINET (TYPE C40, C41) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C41

COMMON AREA

C40

COMMON AREA

Page 42: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

A

A

01

-

PLAN

1

C43

ELEVATION 01

2

C43

10

00

03

50

30

31

23

03

12

30

31

23

03

12

30

31

25

0

25

50

50 50830

930

25

0

50 50830

930

10

03

50

30

50

31

23

0

25

50

F.F.L

30

31

2

SECTION A-A

3

C43

31

23

03

12

30

31

23

03

12

30

31

2

F.F.L

250

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

BOOK

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30

0

89650 5030

10

03

50

30

50

31

23

0

25

50

SECTION A-A

3

C44

31

23

03

12

30

31

23

03

12

30

31

2

F.F.L

300

10

00

03

50

30

31

23

03

12

30

31

23

03

12

30

31

25

0

25

50

30

31

2

89630896

2850

89650 5030 89630896

2850

A

A

01

-

PLAN

1

C44

ELEVATION 01

2

C44

F.F.L

BOOK

20mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

20mm THK. PLYWOOD DOOR W/

PLASTIC LAMINATED FINISHES

30mm THK. PLYWOOD ADJUSTABLE

SHELVES W/ PLASTIC LAMINATE FINISHES

50mm THK. PLYWOOD W/

PLASTIC LAMINATED FINISHES

1 04-07-2016

Sana

Sana

K L

K L

22-06-2016

59

1:40 (A3)

TSSS-CS27

STUDY AREA - CABINET (TYPE C43, C44) DETAIL

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Builder\TSSS-CS01_colour

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

C44

STUDY AREA

C43

STUDY AREA

Page 43: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Building Service\TSSS-EE

FOR TENDER

德信中學TAK SUN SECONDARY SCHOOL

PROPOSED LIBRARY REFLECTED ELV LAYOUT PLAN

1 2016-07-04

Fergus

Fergus

T Tong

T Tong

25-05-2016

67

1:100 (A3)

TSSS-EE07

PROPOSED LIBRARY REFLECTED ELV LAYOUT PLAN

APPROX. AREA = 307.3m²

(7/F PART PLAN)

Page 44: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Building Service\TSSS-MVAC-R2

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

1 2016-07-04

Fergus

Fergus

T Tong

T Tong

25-05-2016

70

1:100(A3)

TSSS-MVAC01

PROPOSED ROOM 311 MVAC LAYOUT PLAN(3/F PART PLAN) & (4/F PART PLAN)

PROPOSED ROOM 311 MVAC LAYOUT PLAN

(3/F PART PLAN)

PROPOSED ROOM 311 MVAC LAYOUT PLAN

(4/F PART PLAN)

Page 45: Particular Specification for - Tak Sun Secondary School Renovation 2/Ren2016-Tender-Addendum-1.pdf · Our ref.: 479-TEN PS1 (Rev.1) Particular Specification for Furniture (Total of

CLIENT : ARCHITECT : NOTES : PROJECT TITLE : DRAWING TITLE : REV. DATE: DESCRIPTIONS: DESIGNED : JOB NO. : 4791. The drawing & design are copyright and no portion may be reproduced without the written permission of the Architect.2. Use written dimensions or grid lines. Measurements to existing work to be checked on site.3. This drawing is to be read in conjunction with the Architects specification & condition of contract.4. Drawing not showing the last revisions below are to be cancelled.

RENOVATION 2016IMPROVEMENT WORKS TO LIBRARY, MULTIFUNCTION ROOM AND CLASSROOMS AT SCHOOLFOR TAK SUN SECONDARY SCHOOLAT 27 NING TAI ROAD, MA ON SHAN, SHATIN, HONG KONG

DRAWN : PAGE :

CHECKED : SCALE :

APPROVED : DWG. NO.:

DATE :Z:\PROJECT DATA\Acad1. Dwg\Educational Establishments\479 - Tak Shun Secondary School\Final Tender Drawing\Building Service\TSSS-MVAC-R2

FOR TENDER

德信中學

TAK SUN SECONDARY SCHOOL

PROPOSED LIBRARY MVAC LAYOUT PLAN

(7/F PART PLAN)

1 2016-07-04

Fergus

Fergus

T Tong

T Tong

25-05-2016

71

1:100(A3)

TSSS-MVAC02