1. Doosan Skoda Power introduction
2. NPPs experience
3. Solution for the new 1200 MW NPP
4. Possible suplliers model
Agenda
3
Heritage of Doosan Škoda Power - top class Steam Turbines
Emil Škoda found the engineering workshop
23 MW Reheating Steam Turbine
220 MW Turboset (Nuclear)
2009 20131869 1966 20061932 19921976
R&D Center of excellence for steam
turbine Doosan Group
1000 MW Turboset (Nuclear)
Doosan acquired Škoda Power
First turbine manufactured as per Škoda design
1914
200 MW Turboset
USC unit 660 MW
1100 MW (LP ST Nuclear)
2014
First turbine as per Škoda licence in Korea
4
Steam turbine& Generator
Completemachine hall
(Turbine Island)
R&D
Design,Engineering,Production
Service,LTSA
1
2
3
Fossil fuel
Cogeneration
Combined cycle
Nuclear
Waste incineration
Biomass
Solar
Doosan Škoda Power provides total solutions for various power generation application,
ranging from design of turbogenerator equipment to supply, erection and post-project
services.
Doosan Škoda Power – 1 100 professionals
Doosan Škoda Power: 50+ worldwide projects
New ST NPPServiceR&M
Felton
0
Red DragonAtacama IIAtacama I
Kelar
EC NovaStalowa Wola
ZabrzeTychyUrsus
SwieciePKN ORLEN
Salalah II
VäroVartanLund
Punta del Tigre
BerlinStendal
Jemalong Vast Solar
Dublin
MatixPioneer
OPG
Termotasajero II
Paco Panama
DunbarMargam
TempleboroughTeesrep
Gardanne
Mochovce
Loviisa
Empalme IEmpalme II
Bandel
HoforLisbjerg
Karabatan
GratiGrati Ad on
Muara Tawar
Ledvice
Meghnaghat
Martinik
SamraZarqa
Fadhili
Tula
Okpai
CengizIstanbul
Huelva
Gardabani
8
Steam Turbines 220 MW for NPPs
Jaslovské Bohunice V1 (1978; 1980) 4 x 220 MW
Jaslovské Bohunice V2 (1984; 1985) 4 x 220 MW
Dukovany (1985; 1986; 1986; 1987) 8 x 220 MW
Mochovce 1,2 (1998; 1999) 4 x 220 MW
Mochovce 3,4 (commissioning) 4 x 220 MW
10
Modernization of NPP Dukovany
Modernization of condensers (1999 – 2001)
Modernization of LP parts (2005 – 2008)
Modernization of HP parts (2009 – 2012)
14
The new NPP 1200 MW - CZ supply from STG to Turbine Island
Steam Turbine 1200MW
High Pressure Heaters
Feed water Heaters
Condensers
Turbine Island design
Turbine Island engineering
Erection / Commissiong
Life time service
NPP 1200MW in Czech Republic = Czech supliers model
Nuclear Island
supplier
TurbineIsland DSPW
BoP - CZ
Mechanical part
Engineering
Supply CZ
Erection CZ
Electric part
Engineering
Supply CZ
Erection CZ
I&C part
Engineering
Supply CZ
Installation CZ
Civil partEngineering Local civil contractor Local civil contractor
Construction Local civil contractor Local civil contractor Local civil contractor
Licencing
Project management + Concept design
Thank you for your attention
and
please, support CZ champions
while every day is a new chalange
Doosan Škoda Power